HomeMy WebLinkAbout2013-04-30; City Council; 21194; NOC North Batiquitos Lift Repair Project 1007-1CITY OF CARLSBAD - AGENDA BILL
21.194 NOTICE OF COMPLETION OF CONTRACT FOR
CONSTRUCTION OF THE NORTH BATIQUITOS
LIFT STATION FORCE MAIN EMERGENCY
REPAIR, PROJECT NO. 1007-1
DEPT. DlRECJO^^f^^ jJf^
MTG. 4/30/2013
NOTICE OF COMPLETION OF CONTRACT FOR
CONSTRUCTION OF THE NORTH BATIQUITOS
LIFT STATION FORCE MAIN EMERGENCY
REPAIR, PROJECT NO. 1007-1
CITY ATTORNEY '
DEPT. TRAN
NOTICE OF COMPLETION OF CONTRACT FOR
CONSTRUCTION OF THE NORTH BATIQUITOS
LIFT STATION FORCE MAIN EMERGENCY
REPAIR, PROJECT NO. 1007-1 CITY MANAGER
RECOMMENDED ACTION:
Adopt Resolution No. 2013-084 accepting the contract for construction of the North
Batiquitos Lift Station Force Main Emergency Repair, Project No. 1007-1 as complete, and directing
the City Clerk to record a Notice of Completion and release bonds in accordance with State Law and
City Ordinances.
ITEM EXPLANATION:
On October 7, 2012, a sewer line was discovered leaking at the North Batiquitos Sewer Lift Station.
Upon discovering the leak, the sewage pumps at the lift station were shut off and the sewage flow
entering the lift station was captured with the use of tanker trucks that hauled the wastewater to the
Encina Water Pollution Control Facility. By the evening of October 8^ a temporary above-ground
bypass pipeline had been installed and was placed into operation; ending the tanker truck operation.
Approximately 1.1-million gallons of sewage was trucked offsite during this operation.
On November 7, 2012, the city entered into a Public Works Contract with Piperin Corporation to
provide permanent repairs to the sewer force main and locate the failed pipe section. The repairs
included the installation of an above-grade force main manifold system which provides operational
advantages for both emergency and maintenance applications. The new system allows for the
diversion of flow into either of the two existing downstream force main alignments and provides
connection ports for bypass pump connections. The existing on-site buried ductile iron pipe (DIP) was
abandoned and replaced with the new above grade force main manifold. Piperin Corporation
completed the contract work on November 21, 2012. City staff has inspected the work and found it to
be satisfactory. Staff recommends acceptance of the improvements by the City Council.
The City Manager declared a local emergency on October 9, 2012 and the declaration was ratified by
Council on October 23, 2012 by Resolution No. 2012-236. The declaration of local emergency to
repair the North Batiquitos Sewer Force Main was terminated on November 27, 2012 with the
adoption of Resolution No. 2012-258.
On October 12, 2012, the City Planner issued an emergency Coastal Development Permit (CDP 12-
22) to allow repairs to the sewer line at the North Batiquitos lift station. On January 30, 2013 the City
Planning Commission approved a Post Emergency Coastal Development Permit (CDP 12-25) forthe
repairs done on the force main along with a Habitat Management Plan Permit (HMP 13-01) to allow
temporary and permanent impacts to sensitive habitat for the force main repair.
DEPARTMENT CONTACT: Patrick Vaughan 760-602-2780 x7321 patrick.vaughan@carisbadca.gov
FOR CITY CLERKS USE ONLY
COUNCIL ACTION: APPROVED K CONTINUED TO DATE SPECIFIC •
DENIED CONTINUED TO DATE UNKNOWN •
CONTINUED • RETURNED TO STAFF •
WITHDRAWN • OTHER - SEE MINUTES •
AMENDED •
Page 2
ENVIRONMENTAL IMPACT:
Emergency projects for the repair of essential service facilities are statutorily exempt from the
California Environmental Quality Act (CEQA) pursuant to Public Resources Code Section
21080(b)(2) and CEQA Guidelines 15269.
The issuance of the Post Emergency CDP 12-25 for the sewer repair work, as required by the
emergency CDP, is exempt from CEQA per CEQA Guidelines Section 15302(c) - replacement or
reconstruction of an existing utility system on the same site involving negligible or no expansion of
capacity. The City Planner filed a Notice of Exemption for the project.
FISCAL IMPACT:
The following table provides a summary of the total project cost.
NORTH BATIQUITOS LIFT STATION FORCEMAIN
EMERGENCY REPAIR PROJECT NO. 1007-1
(PIPERIN CORPORATION)
Spill Response Expenditures (bypass pumping & tanker trucks, cleanup,
misc. equipment rental and services) $162,329
Construction Expenditures
Force Main Repair (Piperin Corporation Original Contract) $ 90,000
Change Order #1 $143,031
Total Construction Expenditures $233,031
Total Project Cost $395,360
Funding for the emergency response and repair services were provided from the sewer replacement
fund. No additional appropriation is required.
EXHIBITS:
1. Resolution No. 2013-084 accepting the contract for construction of the North Batiquitos
Lift Station Force Main Emergency Repair, Project No. 1007-1 as complete, and directing the City
Clerk to record a Notice of Completion and release bonds in accordance with State Law and City
Ordinances.
2. Location map.
3. Notice of Completion
n
1
RESOLUTION NO. 2013-084
2
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
3 CARLSBAD, CALIFORNIA, ACCEPTING THE CONTRACT FOR
CONSTRUCTION OF THE NORTH BATIQUITOS LIFT STATION
4 FORCE MAIN EMERGENCY REPAIR, PROJECT NO. 1007-1 AS
COMPLETE, AND DIRECTING THE CITY CLERK TO RECORD
5 A NOTICE OF COMPLETION AND RELEASE BONDS IN
ACCORDANCE WITH STATE LAW AND CITY ORDINANCES.
6 "
7 WHEREAS, the construction of the North Batiquitos Lift Station Force Main Emergency
8 Repair, Project No. 1007-1, has been substantially completed to the City's satisfaction by Piperin
9 Corporation, on November 21, 2012; and
10 WHEREAS, final contract requirements were met and the final change order executed
11 on December 13, 2012; and
''2 WHEREAS, the formal project Notice of Completion has been prepared; and
''3 WHEREAS, all project costs have been established to date.
14 NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carisbad,
California, as follows:
1. That the above recitations are true and correct.
2. That the construction of the North Batiquitos Lift Station Force Main Emergency Repair
^® is deemed complete and is hereby accepted by the City Council of the City of Carisbad.
3. The City Clerk of the City of Carisbad is hereby authorized and directed to execute and
record the Notice of Completion for the North Batiquitos Lift Station Force Main Emergency
Repair, Project No. 1007-1.
///
///
///
///
///
///
19
20
21
22
23
24
25
26
27
28
9.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
PASSED, APPROVED AND ADOPTED at a regular meeting of the City Council of the
City of Carisbad on the 30*^ day of April, 2013, by the following vote to wit:
AYES:
NOES:
Council Members Hall, Packard, Wood, Blackburn and Douglas.
None.
ABSENT: None.
MATT HALL, Mayor
ATTEST:
LOCATION MAP
PACIFIC
OCEAN
NOT TO SCALE
PROJECT NAME
BATIQUITOS LAGOON LIFT STATION REPAIR
PROJECT
NUMBER
1007-1
EXHIBIT
1
PLOTTED BY: SCOTT EVMiS PLOT DATE:4/17/13 PATH:C:\UWVES DEPARTUENr\DESIGN 0/MS/£W\SM/7H\A/SLS fW FAILURE\10071.DWG
RECORDED REQUESTED BY
CITY OF CARLSBAD
AND WHEN RECORDED PLEASE
MAIL TO:
City Clerk
City of Carisbad
1200 Carisbad Village Drive
Carlsbad, California 92008
Space above this line for Recorder's use.
PARCEL NO:
Notice is hereby given that:
NOTICE OF COMPLETION
The undersigned is owner of the interest or estate stated below in the property hereinafter described.
The full name of the undersigned is City of Carisbad, a municipal corporation.
The full address of the undersigned is 1200 Carisbad Village Drive, Carisbad, California 92008.
The nature of the title of the undersigned is: In fee.
A work or improvement on the property hereinafter described was completed on November 21, 2012.
The name of the contractor for such work or improvement is Piperin Corporation.
The property on which said work or improvement was completed is in the City of Carisbad, County of
San Diego, State of California, and is described as follows: The North Batiquitos Lift Station Force
Main Emergency Repair, Project No. 1007-1.
The street address of said property is 7382 Gabbiano Lane, in the City of Carisbad (92011).
\QfO^>i Engine
VERIFICATION OF CITY CLERK
I, the undersigned, say:
I am the City Clerk of the City of Carisbad, 1200 Carisbad Village Drive^ Carisbad, California,
92008; the City Council of said City on AiarCC^ 30 20 /5. accepted the above
described work as completed and ordered th'at a Notice of Completion be filed.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on H^^UU c3. 20 / 3, at Carisbad, California.
CITY OF CARLSBAD
BARBARA ENGLES
City Clerk
Word\Masters\Forms\Notice of Completion (City) 3/9/98 r