HomeMy WebLinkAbout2013-05-14; City Council; 21228; MUTCD Street Name Sign Replacement Program 6035CITY OF CARLSBAD - AGENDA BILL AB# 21.228 MTG. 05/14/13 DEPT. PW AWARD OF CONTRACT AND APPROPRIATION OF FUNDS FOR THE MUTCD STREET NAME SIGN REPLACEMENT PROGRAM, PROJECT NO. 6035 DEPT. DIRECTOR Vdtd^ CITY ATTORNEY CITY MANAGER RECOMMENDED ACTION: Adopt Resolution No. 2013-114 accepting bids and awarding the contract to S&B Engineering Inc. and appropriation of funds for the MUTCD Street Name Sign Replacement Program, Project No. 6035. ITEM EXPLANATION: On July 24, 2012, through Resolution Number 2012-187, Agenda Bill 20,973, Council approved the plans and specifications and authorized the advertisement for bids for the MUTCD Street Name Sign Replacement Program, Project No. 6035. On February 7, 2013, six (6) sealed bids were received, opened and witnessed for the construction of the project. TABLE 1 MUTCD Street Name Sign Replacement Program, Project No. 6035 CONTRACTOR Schedule A Schedule B Total Bid - Schedules A & B 1. Sign Excellence $371,007.43 215,128.72 586,136.15 2. S&B Engineering $421,313.00 216,346.00 637,659.00 3. Weir Construction Corporation $501,983.00 249,410.00 751,393.85 4. McGuire - Pacific Constructors $429,452.00 369,856.00 799,308.00 5. PCI $673,724.00 427,180.00 1,100,904.00 6. Sterndahl Enterprises Inc $1,042,910.00 381,780.00 1,424,660.00 After city staff completed a review of the bids for compliance with the contract documents, it was determined that the bid submitted by the apparent low bidder. Sign Excellence, was non-responsive. The bid was deemed non-responsive because it did not include a valid bidder's bond as required by California law. On March 6, 2013 staff notified Sign Excellence and S&B Engineering of staffs intent to recommend rejection of the bid provided by Sign Excellence and award of the contract to S&B Engineering. The Engineer's estimate for this project was $578,000. All bid documents submitted by S&B Engineering, Inc. have been reviewed by staff and were found to be in order. Staff recommends awarding the construction contract to S&B Engineering, Inc. in the amount of $637,659.00. DEPARTMENT CONTACT: John Maashoff 760-434-2856 john.maashoff@carlsbadca.gov FOR CITY CLERKS USE ONLY COUNCIL ACTION: APPROVED CONTINUED TO DATE SPECIFIC • DENIED CONTINUED TO DATE UNKNOWN • CONTINUED • RETURNED TO STAFF • WITHDRAWN • OTHER-SEE MINUTES • AMENDED • Page 2 ENVIRONMENTAL IMPACT: The project is exempt from the California Environmental Quality Act (CEQA) per CEQA Guidelines Section 15301(c) - minor alteration of existing facilities including streets, sidewalks, gutters, and similar facilities involving negligible or no expansion. FISCAL IMPACT: Table 1 shows the current status of the MUTCD Street Name Sign Replacement Program. TABLE 1 - SUMMARY OF PROJECT EXPENSES MUTCD Street Name Sign Replacement Program PROJECT NO. 6035 TASK DESCRIPTION APPROPRIATED TO DATE EXPENDITURES/ ENCUMBRANCES TO DATE REMAINING BALANCES Design $25,000 $18,142 $6,858 Construction $425,000 $2,158 $422,842 Inspection, Materials Testing $35,000 $2,579 $32,421 TOTAL $485,000 $22,879 $462,121 The total estimated project cost is shown in Table 2. TABLE 2 - ANTICIPATED CONSTRUCTION PHASE COSTS MUTCD STREET NAME SIGN REPLACEMENT PROGRAM ESTIMATED COSTS Construction Contract - Schedules A & B $637,659 Construction Contingency (10%) $63,766 Inspection, Testing, and Construction Management $31,883 TOTAL ESTIMATED COST $733,308 Remaining Balance $462,121 ADDITIONAL APPROPRIATION ANTICIPATED FOR CONSTRUCTION $271,187 The city appropriated $485,000 for this project through the Capital Improvement Program based on an estimated construction cost for replacing all ground mounted street name signs, Schedule "A" of the subject contract. Schedule "B" was included as a bid item in the contract to allow the city the option to replace the remaining signal mounted internally illuminated street name signs at the same time that the ground mounted street name signs are replaced. Page 3 Staff recommends appropriating an additional $271,187 to the project and awarding the contract, Schedule "A" and Schedule "B", for the construction of the MUTCD Street Name Sign Replacement Program, Project No. 6035. Sufficient funds are available in the Gas Tax Fund for this appropriation. EXHIBITS: Resolution No. 2013-114 accepting bids and awarding the contract to S&B Engineering Inc. and appropriation of additional funds for the MUTCD Street Name Sign Replacement Program, Project no. 6035. 3 RESOLUTION NO. 2013-114 1 2 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF 3 CARLSBAD, CALIFORNIA, ACCEPTING BIDS AND AWARDING THE CONTRACT TO S&B ENGINEERING INC., AND 4 APPROPRIATION OF FUNDS FOR THE MUTCD STREET NAME SIGN REPLACEMENT PROGRAM, PROJECT NO. 6035. 5 6 WHEREAS, the City Council of the City of Carlsbad, California, has determined it 7 necessary, desirable, and in the public interest to construct the MUTCD Street Name Sign 8 Replacement Program, Project No. 6035; 9 WHEREAS, on July 24, 2012, the City Council of the City of Carlsbad, through 10 Resolution No. 2012-187, approved the plans and authorized to advertise for bids to construct the 11 MUTCD Street Name Sign Replacement Program, Project No. 6035; and 12 WHEREAS, six (6) sealed bids were received on February 7, 2013, by the City of 13 Carlsbad for the construction of said project; and 14 WHEREAS, the lowest bidder. Sign Excellence, did not present a valid bid bond as 15 required by law; and 16 WHEREAS, the lowest responsive bid was submitted by S&B Engineering, Inc. in the 17 amount of $637,659; and 18 WHEREAS, additional funding for in the amount of $271,187 is needed to cover all 19 project costs; and 20 WHEREAS, sufficient funding for said project is available in the Gas Tax Fund. 21 WHEREAS, Section 3.28.040 (c)(5) of the Carlsbad Municipal Code authorizes the City 22 Manager to approve change orders in the amount equal to the contingency set at the time of 23 project award. 24 NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad, 25 California, as follows: 26 1 • That the above recitations are true and correct. 27 28 , 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 2. That the low bid by Sign Excellence is rejected as it was not accompanied by a valid Bid Bond. 3. That the low bid of $637,659 submitted by S&B Engineering, Inc. for the construction of the MUTCD Street Name Sign Replacement Program, Project No. 6035, is accepted and the Mayor is hereby authorized to execute a contract with S&B Engineering, Inc. for said project 4. That the City Manager is hereby authorized to approve construction change orders up to $63,766. 5. That the Administrative Services Director is authorized to appropriate $271,187 from the Gas Tax Fund towards the MUTCD Street Name Sign Replacement Program, Project No. 6035. 6. That the award of this contract is contingent upon the bidder submitting the lowest responsible bid executing the required contract and submitting the required bonds and insurance policies, as described in the contract, within twenty (20) days of adoption of this resolution. The City Manager may grant reasonable extensions of time. // // // // // // // // // // // 5 PASSED, APPROVED AND ADOPTED at a Regular Meeting of the City Council of the City of Carlsbad on the 14*^ day of May, 2013, by the following vote to wit: AYES: NOES: Council Members Hall, Packard, Wood, Blackburn and Douglas. None. ABSENT: None. 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 ^Q^, City Clerk As