HomeMy WebLinkAbout2014-02-25; City Council; 21509; Additional Funds and Increase Contingency Palomar and College Improvemnts Project 6028 6029CITY OF CARLSBAD - AGENDA BILL AB# 21.509 APPROPRIATION OF ADDITIONAL FUNDS AND APPROVE AN INCREASE IN THE CONTINGENCY FOR THE CONSTRUCTION OF THE PALOMAR AIRPORT ROAD AND COLLEGE BOULEVARD IMPROVEMENTS, PROJECT NOS. 6028 AND 6029 DEPT.DIRECTOR 0^, MTG. 02/25/2014 APPROPRIATION OF ADDITIONAL FUNDS AND APPROVE AN INCREASE IN THE CONTINGENCY FOR THE CONSTRUCTION OF THE PALOMAR AIRPORT ROAD AND COLLEGE BOULEVARD IMPROVEMENTS, PROJECT NOS. 6028 AND 6029 CITY ATTY. jdXl DEPT. PW/TRAN APPROPRIATION OF ADDITIONAL FUNDS AND APPROVE AN INCREASE IN THE CONTINGENCY FOR THE CONSTRUCTION OF THE PALOMAR AIRPORT ROAD AND COLLEGE BOULEVARD IMPROVEMENTS, PROJECT NOS. 6028 AND 6029 CITY MGR. authorizing the appropriation of additional funds and RECOMMENDED ACTION: Adopt Resolution No. 2014-028 approving an increase in the contingency for the construction of Palomar Airport Road and College Boulevard Improvements, Project Nos. 6028 and 6029. ITEM EXPLANATION; On November 6, 2012, the city council adopted Resolution No. 2012-240 awarding a contract to PAL General Engineering, Inc. for the construction of the Palomar Airport Road and College Boulevard Intersection Improvements, Project Nos. 6028 and 6029. On February 19, 2013, PAL General Engineering, Inc. was issued a notice to proceed and construction of the project commenced. In an effort to reduce impacts to the motoring public and to implement safe traffic control procedures, staff determined portions of the contract work along Palomar Airport Road should be completed at night or on weekends. The revised work hour requirement results in additional cost to the project. During the course of construction, it was discovered that San Diego Gas and Electric (SDGSiE) facilities, not previously identified, conflicted with the proposed storm drain alignment. The quoted cost from SDG&E to identify and relocate their facilities is $200,000. In lieu of relocating the SDG&E facilities, staff redesigned the storm drain system, altering the alignment and using alternative pipe materials. The construction cost for the revised alignment is estimated at $100,000. In order to complete the storm drain system contract work, staff is requesting Council increase the contract contingency by $165,000 and appropriate an additional $155,000 to the project budget. FISCAL IMPACT: The improvements for the intersection of Palomar Airport Road and College Boulevard have two funding sources. Project No. 6028 is funded by the Traffic Impact Fee (TIF) program and is appropriated for roadway improvements. Project No. 6029 is funded by the General Capital Construction (GCC) program and is appropriated for the storm drain improvements. An increase of $165,000 in the contract contingency and an additional appropriation of $155,000 to the General Capital Construction Fund is being requested for Project No. 6029. DEPARTMENT CONTACT: Patrick Vaughan 760-602-2780x7321 patrick.vaughan(5)carlsbadca.gov FOR CLERK USE. COUNCIL ACTION: APPROVED CONTINUED TO DATE SPECIFIC • DENIED CONTINUED TO DATE UNKNOWN • CONTINUED • RETURNED TO STAFF • WITHDRAWN • OTHER - SEE MINUTES • AMENDED • REPORT RECEIVED • TABLE 1 - REVISED PROJECT COST ESTIMATE (PROJECT NO. 6028) ROADWAY IMPROVEMENTS - PROJEa NO. 6028 ESTIMATED COSTS Construction Contract (PAL General Engineering, Inc.) $94,834 Construction Contingency (15%) $14,225 Construction Management & Inspection (10%) $9,483 Total Estimated Construction Cost $118,542 Remaining Balance (6028) -TIF $202,352 ADDITIONAL APPROPRIATION REQUESTED $0 TABLE 2 - REVISED PROJECT COST ESTIMATE (PROJECT NO. 6029) STORM DRAIN IMPROVEMENTS - PROJECT NO. 6029 ESTIMATED COSTS Construction (PAL General Engineering, Inc.) $164,108 Construction Contingency (15%) $24,616 Additional Construction Contingency Requested $165,000 Construction Management & Inspection (10%) $16,411 TOTAL ESTIMATED CONSTRUCTION COST $355,135 Remaining Balance (6029) -GCC $10,869 ADDITIONAL APPROPRIATION REQUESTED $155,000 ENVIRONMENTAL IMPACT: The project is exempt from the California Environmental Quality Act (CEQA) per CEQA Guidelines Section 15301(c) - minor alteration of existing facilities including streets, sidewalks, gutters, and similar facilities involving negligible or no expansion. A Notice of Exemption was filed with the San Diego County Clerk on June 18, 2012. EXHIBITS: 1. Location map. 2. Resolution No. 2014-028 authorizing the appropriation of additional funds and approving an increase in the contingency for the construction of Palomar Airport Road and College Boulevard Improvements, Project Nos. 6028 and 6029. LOCATION MAP VICINITY MAP NOT TO SCAU NOT TO SCALE PROJECT NAME„^,^.^^„ >. ,r^r^^r^-r- r^^ . . . PALOMAR AIRPORT ROAD AND COLLEGE BOULEVARD IMPROVEMENTS PROJECT NUMBER 6028 & 6029 EXHIBIT 1 PLOTTED BY: SCOTT EVANS PLOT DATE:7/26/12 PATH:D:\TRANSP0RTAT10N [)EPARTUENT\LOCAVON UAPS\6028-6029.DWG 1 RESOLUTION NO. 2014-028 10 11 12 13 23 24 25 26 27 28 WHEREAS, on November 6, 2012, the city council adopted Resolution No. 2012-240 2 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CARLSBAD, CAUFORNIA, AUTHORIZING THE APPROPRIATION OF ADDITIONAL FUNDS AND APPROVING AN INCREASE IN THE CONTINGENCY FOR 4 THE CONSTRUCTION OF PALOMAR AIRPORT ROAD AND COLLEGE BOULEVARD IMPROVEMENTS. PROJECT NOS. 6028 AND 6029. 5 6 J awarding a contract to PAL General Engineering, Inc. for the construction of the Palomar 8 Airport Road and College Boulevard Intersection Improvement Project, Project Nos. 6028 and ^ 6029; and WHEREAS, on February 19, 2013, PAL General Engineering, Inc. was issued a notice to proceed and construction of the project commenced; and WHEREAS, during the course of construction additional project costs were incurred due 14 to the requirement for night work in order to reduce traffic impacts and implement safe traffic 15 control procedures; and 16 WHEREAS, during the course of construction it was determined that SDG&E facilities, 17 not previously identified, conflicted with the project alignment; and 18 WHEREAS, implementation of a revised project alignment would eliminate the need to 19 2Q move the proposed SDG&E facilities; and 21 WHEREAS, staff is requesting an additional appropriation amount of $155,000 to the 22 General Capital Construction Fund for project no. 6029; and WHEREAS, staff is requesting an increase in the contingency for the construction of the Palomar Airport Road and College Boulevard Improvement Project, Project Nos. 6028 and 6029. Implementation of the revised alignment increases the cost to construct Project No. 6029. 1 NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad, California, as follows that: 9 10 11 12 27 28 1. The above recitations are true and correct. 2. The administrative services director is authorized to appropriate additional 5 General Capital Construction Funds in the amount of $155,000 for Project No. 6029. ^ 3. That the contingency amount for Project No. 6029 is increased by $165,000 and g the city manager is hereby authorized to approve construction change orders up to the revised contingency amount of $203,841. // 13 // 14 // 15 16 17 18 19 // // // // 20 // // // // // 21 22 23 24 25 26 // 5 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 PASSED, APPROVED AND ADOPTED at a Regular Meeting of the City Council of the City of Carlsbad on the 25th day of February 2014. by the following vote to wit: AYES: NOES: ABSENT: Council Members Hall, Packard, Wood, Blackburn. None. None. MATT JHALL, Mayor ATTEST: BARBARA ENGLESON^ty Clerk