HomeMy WebLinkAbout2014-05-20; City Council; 21603; Carlsbad Desalination Project UpdateCITY OF CARLSBAD - AGENDA BILL 12 21,603 AB# MTG. 05/20/14 DEPT. PW-TRAN CARLSBAD DESALINATION PROJECT UPDATE DEPT.DIRECTDR CITY ATTY. CITY MGR. RECOMMENDED ACTION: To receive a presentation from representatives of Poseidon Resources and the San Diego County Water Authority regarding the Carlsbad Desalination project. ITEM EXPLANATION: Representatives from Poseidon Resources and the San Diego County Water Authority will give an update on current and future activities relating to the construction ofthe Carlsbad Desalination project. FISCAL IMPACT: None. ENVIRONMENTAL IMPACT; Pursuant to Public Resources Code Section 21065, this action does not constitute a "project" within the meaning of CEQA in that it has no potential to cause either a direct physical change in the environment, or a reasonably foreseeable indirect physical change in the environment, and therefore does not require environmental review. EXHIBITS: None. DEPARTMENT CONTACT: Casey Arndt 760-602-2780, ext. 7320 casey.arndt@carlsbadca.gov FOR CLERK USE. COUNCIL ACTiON: APPROVED • CONTINUED TO DATE SPECIFIC DENIED • CONTiNUED TO DATE UNKNOWN CONTINUED • RETURNED TO STAFF WITHDRAWN • OTHER - SEE MINUTES AMENDED • REPORT RECEIVED • _ • • • Carlsbad Desalination Project Construction Update May 20, 2014 Plant Construction –Intake Pump Station2 3Plant Construction –Pretreatment Plant Construction –Administration & RO Buildings4 Plant Construction –Racks in RO Building5 Project Status –52.9 % Complete as of May 16 Pipeline Schedule in Carlsbad7 Pipeline Schedule in Carlsbad8 Pipeline Schedule in Carlsbad9 Pipeline Construction –Cannon RoadCannon Road to be returned to full service May 23I-5 tunnel pipe has been installed and backfill has begun. Paving continues.Curbs and medians are being restored.10 Pipeline Construction –Lower FaradayNight work on lower Faraday is complete.Work now continues during the day and crews are using sound blankets for the nesting birds.11 Pipeline Construction –Faraday Avenue / CRCTunnels at Van Allen Way and College Ave Complete.Trenching crews are working from Van Allen heading east towards College.Outreach continues in the CRC, positive feedback from CRCOA regarding work to date.12 Pipeline Construction –Lionshead / MelroseLionshead base paving installed and crews have turned onto Melrose.Working closely with the Cities of Carlsbad and Vista on the traffic control on Melrose.Melrose will be complete by September.13 Macario TunnelTunnel subcontractor mobilizing later this month.14