Loading...
HomeMy WebLinkAbout2014-06-24; City Council; 21664; Carlsbad Desalination Project UpdateCITY OF CARLSBAD - AGENDA BILL 21 AB# 21,664 MTG. 06/24/14 DEPT. PW-TRAN CARLSBAD DESALINATION PROJECT UPDATE DEPT. DIRECTOR CITY ATTY. CITY MGR. RECOMMENDED ACTION; To receive a presentation from representatives of Poseidon Resources and the San Diego County Water Authority regarding the Carlsbad Desalination project. ITEM EXPLANATION; Representatives from Poseidon Resources and the San Diego County Water Authority will give an update on current and future activities relating to the construction ofthe Carlsbad Desalination project. FISCAL IMPACT; None. ENVIRONMENTAL IMPACT; Pursuant to Public Resources Code Section 21065, this action does not constitute a "project" within the meaning of CEQA in that it has no potential to cause either a direct physical change in the environment, or a reasonably foreseeable indirect physical change in the environment, and therefore does not require environmental review. EXHIBITS; None. DEPARTMENT CONTACT: Casey Arndt 760-602-2780, ext. 7320 casey.arndt@carlsbadca.gov FOR CLERK USE. COUNCIL ACTION: APPROVED • CONTINUED TO DATE SPECIFIC • DENIED • CONTINUED TO DATE UNKNOWN • CONTINUED • RETURNED TO STAFF • WITHDRAWN • OTHER - SEE MINUTES • AMENDED • REPORT RECEIVED rsem 2/ Carlsbad Desalination Project Construction Update THE CARLSBAD Desalination Project Enhancing Water Reliability for San Diego County June 24, 2014 Plant Construction — RO Building Project Status — 55.5% Complete as of June 17 months completed 35 Month Baseline Construction Schedule 31.5 Month Projected Construction Schedule ^^^^^^^H^^^^g 963.630 Labor Hours 572.795 labor hours used to date 329 employed to date 46% complete 26,231 linear feet complete I Over SOO employed at peak of construction I 100% Plant Design Completion 100% complete I 100% Pipeline Design Completion 100% complete I 100% Plant Completion I 53,000 Linear Feet of Delivery System Plant Equipmmt Contracts Executed 96% complete Pipeline Schedule in Carlsbad Pipeline Schedule in Carlsbad TENTATIVE SCHEDULE Monthly Update • june 23, 2014 Pipeline Schedule in Carlsbad Q Aqueduct CorHiecIlon Faclllttp^ tB CamplEted PipeliFi« in&lilldlioii III Paving romplele _ Desalination Conveyance Pipeline Mam hfading (City of Carlsbad) ^ [Jesjlinailon Conv<^ancp Pipeline Mam Hpadinft (Ctiy of Vi«ia] Oesalinalion Conveyance Pipeline Main Heading (Cily of SST^ Marcos] an Underground lunnel Work tstimalert (.omolelion Pipeline Construction — Lower Faraday ^ Due to pipe location, one lane of traffic flagging from 8:30-3:30 until the Fall. > Sections of Lower Faraday to be paved this Saturday. Pipeline Construction — Faraday A venue / CRC > Crews are restoring between College and Rutherford and trenching and installing pipe east of Rutherford. Rutherford tunnel will begin after restoration on the north side of Faraday is completed. > Outreach continues in the CRC, positive feedback from CRCOA regarding work to date. 10 Pipeline Construction — Lionshead / Melrose Crews continue to install pipe on Melrose until September. Intersection of Melrose and Lionshead will be closed until mid-July while crews stabilize utilities and work to install pipe underneath. Working closely with the Cities of Carlsbad and Vista on the traffic control on Melrose and Faraday. Pipeline Construction — Macario Tunnel > Tunnel pit excavation has begun on Cannon. > Tunnel pit in Veteran's Park will begin in July. 12 Pipeline Construction - AvemdaEnemas Tunnei > Carrier skids failed while pushing pipe. SDCWA approved repair plan and repairs started 6/24. > Repairs will take 2-4 weeks > Cannon Road and Avenida Encinas pits will be restored and road opened mid-August. > Delay has been communicated to West Development. 13