Loading...
HomeMy WebLinkAbout2015-01-20; City Council; 21826; Update on Capital Improvement ProjectsUpdate on Capital Improvement Program (CIP) Projects City Council Meeting January 20, 2015 Background •Capital Improvement Program (CIP) is 15 year planning document •FY 2014-15 to FY 2028-29 •258 new and continuing projects costing approximately $496 million •Council adopts annual Operating Budget and CIP appropriating funds for upcoming fiscal year Background (cont.) •FY 2014-15 CIP •$69.7 million in new appropriations •$186.6 million in continuing appropriations •$256 million total appropriation •CIP projects driven by growth in city as well as need to replace existing facilities CIP Revenues 22% 3% 32% 25% 18% Capital Improvement Program Revenues Developer Fees Special District Fees and Taxes Water and Wastewater funds Infrastructure Replacement funds Other Sources (grants, bonds, other agencies) CIP Expenditures 25% 16% 18% 16% 17% 3%5% Capital Improvement Program Expenditures Streets/Circulation Civic Projects Wastewater Parks Water Drainage Other Vista-Carlsbad Sewer Lift Station Location Map Vista-Carlsbad Sewer Lift Station Architectural Rendering Looking SW Phase III Recycled Water Project –Master Plan Phase III Recycled Water Project –Feasibility Study Alga Norte Park Solar Panels Fire Station #3 Parks and Recreation •Parks Master Plan Updates •Aviara Community Park •Outdoor Community Gathering Space •Small Amphitheater •Pine Avenue Community Park •Community Center/Recreation Building •Botanical Garden •Poinsettia Community Park •Multi-use Sports Arena •Playground •Dog Park •Future Multigenerational Community Center Parks and Recreation •Beach Access Repair/Upgrades •Tamarack Beach Restroom Building •Park Athletic Field Lighting Retrofit •Stagecoach Park •Calavera Hills Park •Poinsettia Community Park Soccer Field Synthetic Turf Replacement Questions?