RECEIVE A PRESENTATION FROM
REPRESENTATIVES OF POSEIDON RESOURCES
AND THE SAN DIEGO COUNTY WATER
AUTHORITY REGARDING THE
CONSTRUCTION PROGRESS ON THE
CARLSBAD DESALINATION PROJECT
DEPT. DIRECTOR
CITY ATTY.
CITY MGR.
RECOMMENDED ACTION:
To receive a presentation from representatives of Poseidon Resources and the San Diego County Water
Authority regarding the Carlsbad Desalination project.
ITEM EXPLANATION:
Representatives from Poseidon Resources and the San Diego County Water Authority will give an update
on current and future activities relatingto the construction ofthe Carlsbad Desalination project.
FISCAL IMPACT:
None.
ENVIRONMENTAL IMPACT:
Pursuant to Public Resources Code Section 21065, this action does not constitute a "project" within the
meaning of CEQA in that it has no potential to cause either a direct physical change in the environment,
or a reasonably foreseeable indirect physical change in the environment, and therefore does not require
environmental review.
PUBLIC NOTIFICATION:
Listed on City of Carlsbad website.
EXHIBITS:
None.
DEPARTMENT CONTACT: Casey Arndt 760-602-2780, ext. 7320 casey.arndt@carlsbadca.gov
FOR CLERK USE
COUNCIL ACTION: APPROVED • CONTINUED TO DATE SPECIFIC •
DENIED • CONTINUED TO DATE UNKNOWN •
CONTINUED • RETURNED TO STAFF •
WITHDRAWN • OTHER - SEE MINUTES
AMENDED • REPORT RECEIVED
Carlsbad Desalination Project
Construction Update
March 10, 2015
Plant Construction
2
Plant Construction –Intake Pump Station
3
Plant Construction
4
Administration Building
Control Room
Plant Construction –Pretreatment Wet Testing
5
Loading Anthracite Filter Backwash Seawater Discharge
Plant Construction
6
RO Building
Energy Recovery
Plant Construction –Screen Wall
7
Plant Construction –On-Site Delivery Pipeline
8
Project Status –83.7% Complete as of March 1
9
10
Pipeline Construction
Pipeline Schedule in Carlsbad
11
Tunnel boring at Macario is
about 50% complete.
A double shift, including
night work, began March 3
and will continue thru the
end of March. Residents in
this area have been notified.
Macario Tunnel will be
complete mid-late April.
12
Pipeline Construction –Macario Tunnel
Pipeline Construction –Lower Faraday
Pipe installation is nearly complete in this area. When the Macario
Tunnel is complete the remaining pieces of pipe will be installed to
tie-in. Restorations and median landscaping on lower Faraday will
be completed at that time.
13
Small crews continue to work on manways and other appurtenances
throughout the City of Carlsbad. Individual traffic control is set up in
these areas.
14
Pipeline Construction –Appurtenances in Carlsbad