HomeMy WebLinkAbout2016-01-19; City Council; 22194; Receive the Quarterly Municipal Projects and Council Goals Status Reports for Period Ending December 31, 2015CITY OF CARLSBAD-AGENDA BILL
..........
AB# 22,194 RECEIVE THE QUARTERLY MUNICIPAL PROJECTS AND DEPT. DIRECTORY.1.
DATE 01/19/16 COUNCIL GOALS STATUS REPORTS FOR PERIOD ENDING CITYATIY. H~ ~:>
DEC.31,2015 KY\ DEPT. PW CITY MGR.
/
RECOMMENDED ACTION:
Receive the quarterly municipal projects and Council Goals status reports for the period ending Dec. 31,
2015 from staff.
ITEM EXPLANATION:
Quarterly project status reports include:
Council Goals Status Report
On March 17, 2015 the City Council adopted a prioritized list of 13 strategic goals and directed staff to
operationalize them through a strategic plan. This report provides a status on progress towards those
strategic goals.
Capital Improvement Program (CIP)
The CIP is a 15 year planning document that outlines the expenditure plan for future capital projects and
the corresponding revenues to pay for those expenditures. The program includes streets, drainage,
traffic signals and other circulation-related projects; water, recycled water, and sewer; city facility
construction, expansion, renovation and maintenance; parks, trails and recreational facilities. The CIP for
Fiscal Year (FY) 2015-16 to FY 2028-29 outlines 240 continuing and new projects at a cost of
approximately $455 million. Project funds are appropriated each fiscal year upon adoption of the annual
Operating Budget and Capital Improvement Program by the City Council. The FY 2015-16 Capital
Improvement Program includes approximately $73.7 million in new appropriations.
Private Development
Residential and commercial projects throughout the city are monitored by the Community and Economic
Development Department.
Information Technology
Building IT capacity was identified as a City Council priority in 2015. Modernization of existing systems
and implementation of new technologies will enable the city to maintain its commitment to innovative
solutions that deliver better, faster ways to get things done and the best value for taxpayer dollar.
DEPARTMENT CONTACT: Pat Thomas 760-602-2751 Pat.Thomas@carlsbadca.gov
FOR CLERK USE.
COUNCIL ACTION: APPROVED CONTINUED TO DATE SPECIFIC D
DENIED D CONTINUED TO DATE UNKNOWN D
CONTINUED D RETURNED TO STAFF D
WITHDRAWN D OTHER-SEE MINUTES v AMENDED D REPORT RECEIVED
3
Quarterly CIP Projects Status Report
January 19, 2016
Page2 of2
These reports summarize the status of projects through Dec. 31, 2015.
FISCAL IMPACT:
None.
ENVIRONMENTAL IMPACT:
Pursuant to Public Resources Code Section 21065, this action does not constitute a "project" within the
meaning of CEQA in that it has no potential to cause either a direct physical change in the environment,
or a reasonably foreseeable indirect physical change in the environment, and therefore does not require
environmental review.
PUBLIC NOTIFICATION:
Listed on City of Carlsbad website.
EXHIBITS:
1. CIP Projects Status Quarterly Report, through Dec. 31, 2015
2. Private Development Status Update, through Dec. 31, 2015
3. IT Status Update, through Dec. 31, 2015
4. Council Goals Status Report, through Dec. 31, 2015
2
b.x~ \f-.i. CIP PROJECT STATUS UPDATE Q12016 (through Dec. 31, 2015)
ITEM
#
PROJECT
#
CONSTRUCTION PHASE
10
11
12
13
14
15
16
17
18
19
4003
4717
4019
4020
4716
6607
6024
6035
6604
6013
5040
5517
5208
5008
3957
5209
3949,3886,
3492 & 5027
6322
DIVISION
Property
Parks
Parks
Property
Property
Property
Transportation
Transportation
Transportation
Transportation
Transportation
Utilities
Utilities
Utilities
Utilities
Transportation
Utilities
Utilities
Transportation
DIVISION
CONTACT
Casey Arndt
Kyle lancaster
Kyle lancaster
Steven Didier
Michael O'Brian I
Bob Richardson
Jason Kennedy
Scott Fisher
Alison Luedtke I
Sherri Howard
John Maashoff
Alison Luedtke I
Sherri Howard
Mike Bailey
PROJECT NAME
Fire Station 3
Aviara Community Park Synthetic Turf Replacement
Village Streetscape
Cole Library Improvements and Refurbishment
Faraday Center lighting Conversion
Safety Training Center Solar
CMP Replacement • 2763 La Gran Via
La Costa Slope Repair
MUTCD Street Name Sign Replacement Project
Romeria Drainage Channel Improvements
Concrete Replacement Program
Mark B~~~~:/ Scott 1 Ellery Water Pump Station Decommission
Mark Biskup I Scott
Fisher North Batiquitos lift Station Pump Improvements
lindsey Stephenson I
k . k I 'Palomar Oaks and Calavera Hills Recycled Water Pipelines (ES 1A and Mar 81s up Scott ES 71 Fisher
Shadi Sami/Scott 1Tri-agencyWaterTrans Main Reach 2, Phase 1 Fisher
Casey Arndt
Terry Smith /Scott
Fisher
El Camino Real Widening (Tamarack to Chestnut)
Carlsbad Water Recycling Facility Expansion
Terry Smith I Casey IV/C Sewer Reaches 118-15, Aqua Hedionda lift Station and Avenida
Arndt Encinas Recycled Water line
Doug Bilse Ped Crossing Carlsbad Blvd I Carlsbad Village RRFB
PRE-CONSTRUCTION PHASE: INCLUDES PLANNING & DESIGN, Blll[AWARD PERIOD
20 6001 Transportation Jonathan Schauble 12015 Slurry Seal Project
21 5526 Utilities Mark Biskup I Foxes landing lift Station and Force Main
22 4030 Property Steven Didier I Dove Library Improvements and Refurbishment
23 4713 Property Steven Stewart I Fire Station 2 Refurbishment
24 4714 Property Steven Stewart I Fleet Maintenance Renovation
25 3338 Transportation Jason Geldert IAgua Hedionda Channel Improvements
26 6607 Transportation Sherri Howard ICMP Replacement ·Highland at Adams
PROJECT
BUDGET
9,352,000
860,000
345,000
5,300,000
90,000
450,000
160,000
209,000
2,320,000
647,000
460,000
250,000
905,000
2,481,000
6,455,000
12,833,907
10,361,000
62,950,000
200,000
2,400,000
3,275,000
6,046,529
375,000
885,000
TBD
125,000
OIUGINAL
ESTIMATID ......
COMI'LITION
DATI
Q4 2015
Q3 2015
Q12016
Q12016
Q4 2015
Q4 2015
Q12016
Q4 2015
03 2014
Q4 2015
Q2 2016
Q4 2015
02 2016
Q2 2016
Q2 2016
Q2 2015
Q4 2016
Q3 2017
012015
Q4 2015
Q4 2015
Q3 2016
Q4 2015
012016
Q3 2009
Q12015
CUIUIENT
ES11MA11DPHASE
COMftUTlON DAll
Q4 2015
Q12016
012016
Q12016
Q1 2016
Q12016
012016
012016
012016
Q1 2016
Q2 2016
Q2 2016
012016
02 2016
Q2 2016
Q3 2016
Q4 2016
Q4 2017
Q2 2016
Q4 2015
04 2015
Q12016
012016
012016
Q12016
012016
SCHEDULE
STATUS
0
0
0
0
0
~
0
Q)
Q)
Q)
0
(it
0
0
0
0
0
Q)
0
0
0
0
0
0
~
COMMENTS FUNDING SOURCE
Project Is under construction with a substantial completion of 12/31/2015. Public Facilities Fee
Estimated completion end of Jan, 2016. Subject to change if El Nino weather conditions !Infrastructure Replacement
interfere with construction. Fund
Walkthrough with contractor for the installation of concrete benches, steel
trash/recycling receptacles, and steel/wood benches occurred In late Dec. 2015.
Under Construction
In progress
In progress, estimated completion date January 21, 2016.
Under construction
Under construction
Under construction. Delay caused by sign design decisions and bracket material supply
delays. Estimated completion date February 10, 2016.
Under construction
Pre-Construction Meeting 12117115
Bidders nonresponsive; Rebid awarded. NTP January 2016.
Construction completion expected January 2016.
Construction ongoing; combined budget for 1A & 7, ES7 pipeline installed and is being
pressure tested prior to tie-in. In construction.
NTP was issued for 9/1512015; In construction.
Approx. 65 days behind schedule. Median construction begins January 2016. Project
completion estimated October 2016.
Construction to begin January 2016.
Construction of the sewer forcemain across NRG property has started. The first pipeline
General Capital Construction
General Capital Construction
Infrastructure Replacement
General Capital Construction
Infrastructure Replacement
Gas tax
GAS
Gas Tax, General Capital
Construction
Gas Tax
Water replacement
Sewer Replacement
Water Replacement, Water
Recycled
Water Replacement
Traffic Impact Fees, TransNet
Water Replacement
work in Avenida Encinas is expected to begin in January. Delays to several construction I Sewer Connection
activities are being analyzed to determine impact to overall schedule.
Project Complete: Phase I Carlsbad Blvd project completed in October 2015. Phase II
Carlsbad Village project completed in November 2015.
Construction Contract awarded on November 17,2015. PreCon scheduled for
December 29, 2015.
lift Station Replacement Final Design
Contract awarded, construction anticipated to begin Feb. 2016
Bids rejected by City Council12/15l15, extensive remodeling deferred. Minor
maintenance and upgrades are ongoing, this project will be removed from the list
durinli! the next cvcle.
In design. Facility assessment complete.
RWOCB denied water quality certification. Based on denial USACOE withdrew the
provisional permits. Working on settlement with Rancho Carlsbad HOA.
Out to Bid. Obtaining the Coastal Development Permit via the California Coastal
Commission required more time and effort that originally anticipated.
General Capital Construction
Gas Tax, TransNet local
Sewer Replacement
General Capital Construction
Infrastructure Replacement
Infrastructure Replacement
General Capital Construction,
Planned local Drainage
Infrastructure Replacement
Pag!: 1 ofS
CIP PROJECT STATUS UPDATE Q12016 (through Dec. 31, 201S)
ITEM • PROJECT • DIVISION DIVISION
CONTACT PROJECT NAME
-1--1 -~---1---. PRE-CONSTRUCTION PHASE: INCLUDES PLANNING & DESIGN, BID/AWARD PERIOD
27 6607 Transportation
28 6618 Transportation
29 6608 Transportation
30 6608 Transportation
31 6608 Transportation
32 6052 Transportation
33 5529 Utilities
34 4601 Parks
35 3866 Parks
36 4718 Property
37 4719 Property
38 4715 Property
39 6617 Transportation
40 3649 Parks
41 4605 Parks
42 6049 Transportation
43 6019 Transportation
44 4602 Parks
45 6057 Parks
46 4603 Parks
47 4605 Parks
48 3572 Property
Sherri Howard
Sherri Howard
Sherri Howard
Sherri Howard
Sherri Howard
Jonathan Schauble
Mark Biskup
Kasia T rojanowska
Kasia Trojanowska
Bob Richardson
Steven Stewart
Steven Stewart
Sherri Howard
Barbara Kennedy
Barbara Kennedy
Emad Eiias
Jonathan Schauble
liz Ketabian
CMP Replacement • Hoover Street at Adams
Farol Court Drainage Repairs
Northwest Quadrant Storm Drain (6)· 3095 Monroe
Northwest Quadrant Storm Drain (6)-Madison (Arbuckle to Post
Office)
Northwest Quadrant Storm Drain (6)-Roosevelt (laguna South)
Parking lot Maintenance-Faraday Building
Poinsettia l/S Emergency Bypass Pump System
Calavera Hilts Community Park Gateway Improvements
lake Calavera Trails Master Plan ·Pre-fab Restroom
City Halt Building Refurbishment
EOC Reconfiguration
Safety Center Refurbishment
Drainage Master Plan Project BCA (Park Drive I Tamarack S.D.)
Avlara Community Park Amphitheater & Picnic Areas
Poinsettia Community Park-Phase 3 (does not Include community
center)
ADA Improvement Program (Public Right of Way)
Valley and Magnolia Improvements
leo Carrillo Ranch Phase 3-Stables Restoration & Chicken
Coop/Restroom
Kyle lancaster I Northern Public Beach Access Improvements
Barbara Kennedy
Mick Calarco
Steven Stewart
Pine Avenue Park Community Bldg. and Gardens-Phase 2
Poinsettia Park Multi-Gen.,Muhi-Purpose Community Center
Feasibility Study
Maintenance and Operations Center
PROJECT
BUDGET
175,000
411,700
250,000
175,000
450,000
50,000
320,000
550,000
250,000
919,000
1,858,128
3,413,148
1,068,613
2,944,800
3,588,000
1,670,000
1,674,236
200,000
2,600,000
10,805,300
90,000
28,111,264
ORIGINAl.
EmMA ltD
PHASE
COMPUTION
DATt
Q1 2015
03 2015
Q3 2016
Q3 2016
Q1 2016
Q1 2016
Q3 2015
Q22016
012016
Q2 2016
Q4 2015
04 2015
Q2 2016
Q3 2016
Q3 2016
Q3 2016
Q3 2016
Q4 2016
Q4 2016
Q4 2016
04 2016
Q4 2016
CUitltiNT
IS11MA11DPHASI
COMPLfnON DATI
Q1 2016
012016
012016
Q1 2016
Q1 2016
Q1 2016
Q12016
Q2 2016
Q2 2016
Q2 2016
Q3 2016
03 2016
Q2 2016
Q3 2016
Q3 2016
Q3 2016
Q3 2016
04 2016
042016
Q4 2016
04 2016
04 2016
SCHEDULE
STATUS
G
a
G
G
G
G
G
~
0
G
~
a
G
G
G
G
G
0
G
0
G
G
COMMENTS
Out to Bid. Obtaining the Coastal Development Permit via the California Coastal
Commission required more time and effort that originally anticipated.
This unique project is requiring extensive coordination with technical design experts
and regulatory agencies to develop the long term solution. Many of the design and
regulatory requirements are revealing themselves as the project proceeds thru the
development process. In addition the development of the long term solution is being
impacted by the development of the near term/temporary solution.
Final plans and specification in preparation.
Final plans and specifications completed.
Final plans and specifications completed. Construction must occur outside the rainy
Contracting for sealcoat and striping of 1635 Faraday Ave
Design complete. Awarding contract January 2016.
Amount shown is for construction only. Construction is pending the potential revision
of plans and specifications, upon direction.
Information noted is for prefab restroom building only. Pre-construction budget:
$30,000.
Interior lighting replacement with LED's, roof replacement and refurbishment HVAC
units and review and repair of the covered concrete walkways as needed
Delayed 6 months due to staffing. Project scoping and stakeholder meetings 01 2016.
Delayed 6 months due to staffing. Project seeping and stakeholder meetings 01 2016.
Survey complete. Predesign in progress. CMWD and Streets Maintenance will be
partnering with this project.
80% Plan Review completed and returned to design consultants at end of Dec. 2015.
80% Plan Review completed and returned to design consultants at end of Dec. 2015
Improvements to accessible pathway in the public right-of-way. Phase I to address
Focus Study Area A per the ADA Transition Plan for Public Rights of Way. Focus Study
Area A generally includes the Village, the Barrio, the Coastal Corridor north of Agua
Hedionda lagoon and the area adjacent to the Barrio and the Village just east of 1-5.
Design underway. Utility Undergrounding District #20 formed at City Council Meeting
Nov. 17, 2015.
Contract for Professional Design Services awarded Sept. 23, 2015. Final Design
Development Plans submitted by consultant end of Dec. 2015.
long term/major improvements include concrete stair removals, landscape and
hardscape Improvements at access entries. Pre construction budget $500,000.
Community outreach meeting completed on Dec. 3, 2015. Community survey
commenced in mld·Dec. 2015.
30% Construction Plans completed at end of Dec. 2015
Feasibility study "BiB Ideas" public outreach meeting held Dec. 10, 2015 along with
Focus Group Questionnaire and interviews.
Agenda Bill to approve contract for design authorized Od 20, 2015. Planning and
design underway.
-::)
FUNDING SOURCE
!--
Infrastructure Replacement
Infrastructure Replacement
Gas tax
Infrastructure Replacement
Sewer Connection
General Capital Construction
General Capital Construction
Infrastructure Replacement
General Capital Construction,
Infrastructure Replacement
Fund
General Capital Construction,
Infrastructure Replacement
Fund
Planned local Drainage
Park-in-lieu
Public Facility Fees
TransNet local
Traffic Impact Fees, Water
Replacement
Public Facility Fees
Infrastructure Replacement,
General Capital Construction
Park-in-lieu, Public Facility
Fees
General Capital Construction
CFD#1, Water and Sewer
Replacement Funds
Pag~2ofS
CIP PROJECT STATUS UPDATE Q12016 (through Dec. 31, 201S)
OltGWM
IT~M PROJECT I DIVISION I DIVISION I PROJECT NAME I PROJECT I s:o SCHEDULE II II CONTACT BUDGET coMPUnON STATUS
1------ -.. ,. PRE-CONSTRUCTION PHASE: INCLUDES PlANNING & DESIGN,_, B:ri=D'-'A..:;W=AR"'D::...:..PE::R.::IO=D------------+------+------t------+---
49 I 6619 I Transportation I Sherri Howard 0
50 I 6031 I Transportation I Marshall Plantz !Carlsbad Blvd Realignment IS 3,250,000 I 04 2016 I Q4 2016 I 0
51 6014,6053 I Transportation I Brandon Miles !Carlsbad Boulevard Bridge Barrier Rail at Encina Discharge I S 1,350,955 I 02 2016 I Q4 2016 I (it
52 I 6054 Transportation Jonathan Schauble Terra mar Area Coastal Improvement Project S 6,050,000 Q3 2016 04 2016 Q
53 4015 Transportation Marshall Plantz Village & Barrio Traffic Circles S 315,000 Ql 2014 04 2016 0
54 5210 Utilities Shadi Sami Recycled Water Phase Ill Tank at D Site S 1,800,000 04 2016 Q4 2016 0
55 5533 Utilities Mark Biskup Simsbury Extension S 301,000 04 2016 04 2016 0
56 6320 Transportation I Doug Bilse !Traffic Signal Program I S 5,684,974 I 04 2016 I 04 2016 I 0
57 I 4725 I Transportation Brandon Miles jetty Hall Site Refurbishment IS 2,250,000 I 02 2017 I 02 2017 I 0
58 I 6607 I Transportation Brandon Miles jCMP Replacement -Elmwood/Laguna I S 525,000 I 02 2017 I 02 2017 I 0
59 6056 Transportation
60 6042 Transportation
61 6058 Transportation
62 5038 Utilities
Brandon Miles El Camino Real and Agua Hedionda Creek Bridge Railing Repair and
Sidewalk
Brandon Miles I El Camino Real at Cannon Intersection Improvements
Doug Bilse Carlsbad Blvd. and Tamarack Ave. Pedestrian Improvements
Kirsten Plonka I Shadil Flow Control Facility 5 (Desai)
Sami
210,000 ( 012017 ( 03 2017 I ~
849,ooo I 012017 I 03 2017 I a
996,ooo 1 Q12017 Q12018 ( Q)
1,500,000 ( Q4 2016 I TBD ( ~
COMMENTS
The scope of the security to be provided by this fencing project and the impact on
adjacent portions of the creek require coordination with multiple stakeholders and as a
\.["
FUNDING SOURCE
result the development of the solution is taking longer than anticipated. It should be !General Capital Construction
noted that the project does not impact the capacity of the creek to convey flood
waters.
Coordinating with other Coastal Corridor projects.
Design underway and updating permits with Coastal Commission, Caltrans review of
railing type was longer than expected.
2nd Public Outreach Meeting completed Nov. 19, 2015. Online survey collecting input
from community until Dec. 18, 2015.
Project scope and design Is on hold pending the adoption of the Village and Barrio
MasterPlan.
RFP to be released 01 2016.
In final design, construction schedule dependent on Quarry Creek Development.
Phase I complete December 2015. Phase II includes an automated monitoring system
that will be compatible with the adaptive signal system and autonomous vehicle
technolo~~:v. and fiber optic installation December 2016.
Renovation and remodel of the parking lots, facility access and grounds.
To be coordinated with the design and implementation of the City Hall Site
General Capital Construction,
TransNet
TransNet, Federal grants, GCC
Traffic Impact Fees
General Capital Construction
Water Replacement
Sewer Replacement
Traffic Impact Fee
General Capital Construction
Refurbishment Proj.ect, _(~r~j~ct No. 4725). Some preliminary investigations have been !Infrastructure Replacement
performed and project 1n1t1at1on will be able to occur as a result of the approval of
additional staffing which is expected to be in place during 04 2015.
To be completed in collaboration with Project 6042 (ECR and Cannon Bridge
Improvements). The previous report noted an "original estimated completion date"
that was incorrect as a result of an error while converting formats. When the project !Infrastructure Replacement
work began the schedule was revised schedule to match the scope of work and as a
result the new current estimated completion date is Q3 2017.
The previous report noted an "original estimated completion date" that was incorrect
as a result of an error while converting formats. When the project work began the
schedule was revised schedule to match the scope of work and as a result the new
current estimated completion date is Q3 2017.
Pre-Construction: SANDAG ATP Grant notice to proceed Jan 1, 2016. Budget figure
does not include recently awarded TransNet funds of $1.05MM. Technical Reports to
Traffic Impact Fees
determine constraints and public outreach will be complete April 2016. CC to select I Gas TaK, Trans Net local
preferred alternative June 2016. CEQA, Design and PS&E completed May 2017. Award
of bid August, 2017. Construction completed June, 2018.
Project on hold until Desai agreement can be reached with SDCWA. Waiting on revised
state conservation regulations.
Pag~3of5
CIP PROJECT STATUS UPDATE Q12016 (through Dec. 31, 2015) ~
ORIGINAL
IT~M I PROJECT I DMSION I DIVISION I PROJECT NAME I PROJECT I ESTIMATfD CURJt£NT SCHEDULE COMMENTS
I
FUNDING SOURCE ....... ESTlMATtD....... I # CONTACT BUDGET COMPLETION -COMPLfTIONDATl STATUS =----------PROGRAMS & STUDIES
I I I lco.,t•l Cocridor Mobil;ty Re•diness Pl•n Is 100.000 I I I G Final Draft review until l/17/16. Stakeholder outreach, commission and city council
63 6055 Transportation Doug Bilse Q4 2015 012016 presentations starting in Feb. 2016. Coastal Mobility Infrastructure Action Plan I General Capital Construction
implementation projects could start June 2016.
64 I 5019 I Utilities I Shadi Sami Water Valve Replacement Program $ 550,000 012016 012016 G Staff is working on the condition assessment of the potable water valves within the I Water Replacement system.
65 I 6001 I Transportation I Jonathan Schauble Pavement Management Program Update Citywide $ 100,000 Ql2016 Q2 2016 G IMS evaluated citywide pavement condition 04 2015. Staff evaluating PCI data and I Gas Tax, TransNet Local software updates.
66 I 6059 I Transportation I Brandon Miles/Glen Village Double Tracking $ 250,000 03 2015 03 2016 0 Currently reviewing draft Project Study Report. Report was delayed due to !General Capital Construction Van Peski administrative issues at SANDAG.
G Feasibility study "Big Ideas" public outreach meeting held Dec. 10, 2015 along with
67 I 4607 I Parks I Mick Calarco Outdoor Adventure Park Feasibility Study $ 122,500 04 2016 04 2016 Focus Group Questionnaire and inten~iews. Community sun~eys to commence in !General Capital Construction
Januarv 2016.
68 I 6030 Transportation Jonathan Schauble Camino Hills & Jackspar Slope Stability $ 859,400 Ongoing Ongoing G Continuing to monitor 2 indinometers on Camino Hills Rd GCC
69 Non CIP Transportation Jonathan Schauble Carrillo Way Inclinometer $ 10,000 Ongoing Ongoing G Staff evaluating inclinometer readings and possible future monitoring contract. Non-CIP Operating Budget
70 I 6620 Transportation Sherri Howard Storm Drain Condition Assessment $ 1,000,000 Ongoing Ongoing G Televising strategy and contracting underway Infrastructure Replacement
Fund
71 I 5035 Utilities Kirsten Plonka limited Access Pipeline Relocation Program $ 1,940,000 Ongoing Ongoing G Design 90% complete on La Costa pipeline. Altisma relocation design under way. Water Replacement
72 3840 Utilities Kirsten Plonka Misc. Sewer lift Station Rehabilitation Projects $ 1,610,380 Ongoing Ongoing G Engineering support to Operations for Misc. Minor Improvements/Contracts. Sewer Replacement
73 I 5503 I Utilities Kirsten Plonka Misc. Sewer Pipeline and Manhole Replacement and Repair $ 4,057,894 Ongoing Ongoing G Engineering support to Operations for Misc. Minor Improvements/Contracts. Sewer Replacement
74 I 5520 Utilities Kirsten Plonka Odor/Corrosion Assessment $ 200,000 Ongoing Ongoing G Addressing miscellaneous wastewater odor control issues throughout the city. Sewer Replacement
LONG TERM MAINTENANCE
75 I 3821A Transportation Sherri Howard Lake Calavera Mitigation long Term Maint. $ 200,000 03 2017 03 2017 G long term maint plan. Annual report in Sept. Quarterly site visits ongoing. Drought Water Replacement delayed growth.
76 I 6604/6024 Transportation Sherri Howard Romeria and La Costa Slope Repair Mitigation Site $ 150,000 02 2020 02 2020 G Initial planting in 02 2015. Maintenance and monitoring required until 2020. Gas Tax. General Capital
Construction
77 38218 Transportation Sherri Howard Lake Calavera Dam Mitigation long Term Maintenance Mitigation $ Site 250,000 03 2021 0 3 2021 G Conceptual Mitigation Plan approved. Preparation of Bid Documents under way Water Replacement
78 3338 Transportation Sherri Howard Agua Hedionda Channel Maintenance between Cannon Road and El $ 100,000 Ongoing Ongoing G Routine Maintenance, Monitoring and Reporting continuing. Drainage Master Plan Camino Real Bridges
79 Non CIP Transportation Sherri Howard Buena Vista Creek Channel Maintenance $ 500,000 Ongoing Ongoing G Nature's Image performing maintenance Special District
80 3919/6032 Transportation Brandon Miles Encinas Creek Bridge Revetment Monitoring $ 15,000 Ongoing Ongoing G Received approval from CCC to change monitoring to every 5-years, next report due Planned local Drainage April2020
81 3821B Transportation Sherri Howard Lake Calavera Dam Maintenance $ 250,000 Ongoing Ongoing G MND complete. Draft Streambed Alteratin Agreement received from CA Dept of Fish Water Replacement and Wildlife.
Page4of5
ITEM
II
PROJECT •
i..,--..,.,-~1-
FUTURE PROJECTS
82 I 3801
83
84 6004
85 4013
86 6051
87 6034
88 6608
89 6043
90 6044
91 6611
92 6060
93 6061
94 5001
95 5007
96 5013
97 5034
98 5501
99 5212
100 5528
101 5531
102 5032
103 5020
104 5024
105 5534
I
DM SION
Parks
Parks
Transportation
Transportation
Transportation
Transportation
Transportation
Transportation
Transportation
Transportation
Tran~ortation
Transp9rtation
Utilities
Utilities
Utilities
Utilities
Utilities
Utilities
Utilities
Utilities
Utilities
Utilities
Utilities
Utilities
I
DIVISION
CONTACT
Liz Ketabian
Liz Ketabian
Kirsten Plonka
Kirsten Plonka
Terrv Smith
Kirsten Plonka
Mark Biskuo
Mark Biskuo
Kirsten Plonka
Kirsten Plonka
Kirsten Plonka
Kirsten Plonka
CIP PROJECT STATUS UPDATE Q12016 (through Dec. 31, 2015)
PROJECT NAME
I Roberston Ranch Park Development
Veteran's Park
Avenida Encinas widening south of Palomar Airport Road
Barrio Street lighting
El Camino Real widening la Costa Ave to Arena I Road
Melrose at PAR Improvements
Northwest Quadrant Storm Drain 6 -Sunnvhill McArthur
Palomar Airport Road left turn lane expansion to N/B Paseo Del
Norte
Palomar Airport Road right turn lane widening to S/B Paseo Del
Norte
Park Drive OraiRage and Street Improvements
Trails Roadway Crossim!s
Wavfindina Sian Replacement Program
Maerkle Transmission Main
Cathodic Protection Program Improvement
College (ECR to Cannon) Water Pipeline
El Fuerte and Corintia Street Pressure Redudn Station
ExistinR Buena Interceptor Purchase and Rehabilitation
Fire Flow Svstem lmorovements
Gateshead Sewer lift Station Removal
Northwest Quadrant CIPP Sewer linine
Palomar Business Park Recvded Water line
Pressure Redudne Station Re lacement Rehabilitation
Reservoir R~pair and Maintenance Program
Terramar Sewer Reolacement Arbei/Los Robles
s
Is Is
s
s s s
PROJECT
BUDGET
2,700,000
23,240,000
5,402,000
100,000
2,550,000
561,000
50.000
233,000
564,000
243,000
380.000
150.000
4,875,000
1.246.700
1,060,000
500.000
1,362,000
720.000
150.000
700.000
1.245.000
1.102.000
4,000,000
1.250.000
OIIIGINAL
ESTIMATID ......
COMPUTION
DAn
CUIUIINT
IEmMATID PHASI:
COWUMNDAn
SCHEDULE
STATUS COMMENTS
Currently on Unfunded Projects list; budget shows partial funding of $2.7 MM against
total cost of $7.8MM. Scheduled currently for buildout. Unknown start date
Current CIP schedule shows development at 2026-30.
Project to schedule to be determined based on the construction progress of the Vista
Carlsbad sewer project along the Avenida Encinas.
Pending performance of striping solution the project may be unnecessary. Evaluating
performance of existing configuration
Project initiation anticipated Q1 2016
Project initiation anticipated Q1 2016
ProJect initiation anticipated Q1 2016
Catarini Ranch to Design and Construct with a reimbursement agreement. In design
phase.
Prolect estimated to beRin in 2016
Schedule dependent on Catarini Ranch Development.
Project estimated to beain in 2016
Project estimated to beain in 2016
Project estimated to beain in 2016
Project estimated to beain in 2016
Project estimated to beain in 2016
Project estimated to beain in 2016
Project estimated to beRin in 2016
Project estimated to beRin in 2016
Project estimated to beRin in 2016
r
FUNDING SOURCE
Park-in-lieu
CF0#1
Traffic Impact Fee
General Capital Construction
Traffic Impact Fee
Traffic Impact Fee
Gas Tax
Gas Tax
Gas Tax
GCC
Gas Tax
Gas Tax
Water Replacement
Water Connection
Page SofS
~~V\Mcit 2... PRIVATE DEVELOPMENT STATUS UPDATE Q1 2016 (through Dec. 31, 2015) 6J
CURRENT
ITEM PROJECT PHASE PROJECT NAME PROJECT VALUE ESTIMATED SCHEDULE PROJECT DESCRIPTION/COMMENTS # # COMPLETION STATUS
DATE
COMMERCIAL
1 SOP 01-04 Construction La Costa Town Square Commercial $75 million 0 2 2016 0 264,000-square-foot neighborhood-serving commercial center located at the southeast corner of La Costa
Avenue and El Camino Real. Three pads (42,000 square feet) remaining to be built
2 SOP 09-04(A) Design The Shoppes at Carlsbad Renovation {Formerly: Westfield
Carlsbad) Unknown Unknown 0 Existing approvals still valid. Awaiting information from new owners on revised concepts
3 SOP 14-06 Construction Hoehn Motors Audi Dealership $6.4 million 0 12016 0 Construction of a new 54,688-square-foot Audi dealership, including a rooftop parking structure, at former GMC
dealership located in Car Country Carlsbad
0 Two, three-story industrial buildings at the norteast corner of El Camino Real and Gateway Road with a combined
4 SUP 13-03 Construction ViaSat Expansion $50 million 02 2016 111,042-square-feet of professional office space and 32,058-square-feet of manufacturing space for a total
buildin• area of 143 100-sauare-feet
0 156,000 square-foot tenant improvement at the former Floral Trade Center on Avenida Encinas west of Interstate
5 CD 13-18 Construction "MAKE" Tenant Improvement $5.2 million 03 2015 5 designed as a collobrative, work-sharing environment for innovative design companies. Project is complete and
will be removed from the next update
60,000 square foot building with demonstration kitchen, micro-brewery and tasting room, wine tasting,
6 CUP 12-10 Design North 40 $4.5 million 0 2 2017 0 wholesale floral market, public produce market open to the public in the former flower fields south of Cannon
Road between Car Country Drive and Legoland Drive. Construction is expected to commence Q2 2016
0 Demolition of tanks to make way for new power plant. Demolition of existing Encina Power Station anticipated
7 None Discretionary Carlsbad Energy Center Project Unknown 04 2017 by end of 2020. The site is located on the east side of Carlsbad Boulevard north of Cannon Road
Hotel (71 rooms)/time share (36 rooms) project on property located just east of the existing Marbrisa Resort and
Westin Hotel & Timeshare (Formerly: Lot 9) $31 million Q2 2018 • Sheraton Hotel projects owned and operated by Grand Pacific Resorts. The site is located at the north end of The 8 GPA 14-03 Discretionary Crossings Drive. Start of construction expected Q4 2016. Project delayed due to unforeseen site conditions.
Home2 Carlsbad Suites $18-20 million 012018 0 88,254 square foot, 3 story, 147 room hotel located at the northeast corner of Palomar Airport Road and Palomar 9 CUP 15-06 Discretionary Oaks Way
10 SOP 15-23 Discretionary North Coast Medical Unknown 012018 0 49,942 square foot, 3 story, medical office building located south of Palomar Airport Road and east of Hidden
Valley Road
11 SOP 15-25 Discretionary High Tech Corporate Headquarters $16.2 million Unknown 0 Two-story, 136,327 square foot corporate headquarters office building located on the north side of Whiptail
Loop, north of Faraday Avenue and east of Gazelle Court
12 SOP 15-26 Discretionary Legoland California Hotel II $17.5 million 03 2018 0 Three-story, 137,700 square foot, 250 room hotel located at Legoland California Resort
0 Two warehouse buildings totaling 155,000 square feet with 431oading docks and ancillary office space. The
13 SOP 15-10 Discretionary Carlsbad Oaks North Lot 13 $8.7 million 01 2017 property is located north of Faraday Avenue on Whiptail Loop East bordering Vista to the east
Marbrisa (timeshare) and the Sheraton Hotel project were approved together in 2004. The approval includes 350
hotel units and 350 timeshare units. Phases 1 & 2 of the Sheraton Hotel (250 units/pool/conference
14 SP 207(E) Construction Marbrisa Hotel and Timeshares $28 million Q2 2020 0 rooms/restaurant/spa) are constructed. Phase 1 of Marbrisa (80 units) is also complete. Phase 2 of Marbrisa
under construction and includes 162 timeshare units/sales offices/primary resort pool area and recreation room.
Phase 3 (future construction) includes 100 hotel units. The site is located south of Cannon Road and north of
Lelloland
15 GPA 05-05 Design Springhill Suites (Formerly: DKN Hotel) Unknown Unknown 0 104 room hotel east of Carlsbad Boulevard, south of Oak Avenue and west of Lincoln Street
Page 1 of 3
PRIVATE DEVELOPMENT STATUS UPDATE Q1 2016 (through Dec. 31, 201S)
~
CURRENT
ITEM PROJECT PHASE PROJECT NAME PROJECT VALUE ESTIMATED SCHEDULE PROJECT DESCRIPTION/COMMENTS II II COMPLETION STATIJS
DATE
RESIDENTIAL
0 308 single family homes and 364 multi-family homes comprised of 100 senior apartments and 264 market rate
16 GPA 11-07 Construction Robertson Ranch West Village $236 million Unknown apartments and widening of El Camino Real. The project is located at El Camino Real and Tamarack Avenue. First
I phase expected to be completed 03 2016
17 SDP 13-02 Construction Arterro (Formerly: La Costa Town Square Residential) $29.8 million 012016 0 63 one and two story single family homes located of the northeast corner of La Costa Avenue and Rancho Santa
Fe Road
18 MP 10-01 Construction Quarry Creek Master Plan $69 million 02 2018 0 636 residential units, a 1.5-acre community facilities site, a 1.3-acre park and ride site and preservation of 92
acres of natural open space on a 156-acre site in northeast Carlsbad
19 CT 12-05 Construction Montecina (Formerly: La Costa Residential) $12.8 million 012016 0 32 detached single-family homes located within the La Costa Master Plan at the northeast corner of Rancho
Santa Fe Road and Paseo lupine
20 CT 12-07 Construction Southern Preserve La Costa (Formerly: Fair Oaks Valley) $39.2 million 04 2016 0 49 single family residences located on the eastern edge of Carlsbad off Camino Junipero
21 CT 13-05 Construction Seagrove (Formerly: State Street Townhomes) $30 million 012016 0 47 two and three-story air space townhomes, including 411ive/work units and six (6) inclusionary units from 2531
to 2601 State Street • 105 detached single-family homes on minimum 1/2 acre lots located north of El Camino Real and east of the
22 CT 00-18 Design Cantarini Ranch Unknown Unknown intersection at College Boulevard and Cannon Road. Developer is currently working out financing options for
constructing ColleRe Boulevard
23 CT 00-21 Design Holly Springs Unknown Unknown ~ 43 detached single-family homes on minimum 1/2 acre lots located north of El Camino Real and east of the
intersection at College Boulevard and Cannon Road
~ 127 apartments including SO% affordable located along the future extension of College Boulevard between El
24 SDP 01-10(A) Design Encinas Creek Apartment Homes Unknown Unknown Camino Real and Cannon Road. The site is located on the northeast side of the intersection of future portions of
Carlsbad Boulevard and future "C" street.
Demolition of a 50-unit apartment complex and the construction of 3Siuxury townhomes and a subterranean
25 CT 05-12 Construction Summerhouse {Ocean St. Condos) $14.5 million Q3 2015 0 parking structure adjacent to the Buena Vista lagoon on north side of Ocean Street, between Garfield Street and
Mountain View Drive. Project is complete and will be removed from the next update
26 GPA 14-06 Discretionary Poinsettia 61 $63.4 million 04 2020 0 Construction of Reach "E" of Poinsettia lane south of Cassia and the construction of 123 detached single-family
condominiums on a 60.1-acre site. Groundbreaking anticipated Ql 2018
33,732 square foot four-story mixed-use building consisting of 14 residential units (two of which are affordable),
27 CT 14-01 Design State Mixed Use 30 $7.5 million 03 2016 0 13 timeshare units, one (1) ground floor commercial unit (4,529 square feet). a roof deck and an enclosed at-
grade parking garage located at the northeast corner of State Street and Oak Avenue
0 Mixed use project on 17 acres to include 90,267 square feet of commercial space and 125 residential units
28 GPA 14-04 Discretionary Uptown Bressi $64 million 03 2019 located at the northwest corner of El Fuerte Street and Gateway Road. Discretionary approvals expected Q3 2016
Village East is a multiple-family residential development to include 14 three-story buildings with 76 for-sale
townhome units and a 73 unit for-rent condominium building with two levels of subterranean parking.
0 Village West is a mixed use development to include 13,300 sq. ft. of commercial (3,300 sq. ft. of restaurant, 1,750
29 GPA 15-01 Discretionary Ponto Beachfront Villages East and West $200 million 03 2017 of coffee shop; and 8,250 sq. ft. of retail) located on the ground level facing Carlsbad Boulevard and Avenida
Encinas. The residential portion of this development includes 42 for-sale multi-family townhome units on the
second and third levels
Both Villages are located north of Avenida Encinas and East of Ponto Drive
305-unit continuing care retirement community including 58 detached cottages, 166 independent living units
30 GPA 09-02 Design Dos Colinas $36.2 million 03 2017 a (i.e., senior apartments) and an 81-room/95-bed congregate care facility Located east of El Camino Real and
South of Cannon Road. Developer is currently working out financing options for constructing College Blvd.
0 Demolition of SO residential units and the construction of an 120 unit affordable apartment project (6 three story
31 SDP 15-18 Design Pacific Wind $20 million 03 2019 buildings) as well as vacating Harding Street and Carol Place and converting two existing lots into a two parcel
site. The project will be completed in two phases
Page 2 of 3
PRIVATE DEVELOPMENT STATUS UPDATE Q12016 (through Dec. 31, 2015) D --
CURRENT
ITEM PROJECT PHASE PROJECT NAME PROJECT VALUE ESTIMATED SCHEDULE PROJECT DESCRIPTION/COMMENTS II II COMPLETION STATUS
DATE
RESIDENTIAL
0
35 unit multi-family condominium development on a 3.67 acre site at 2416 Altisma Way. Development consists
32 CT 15-01 Design Cascada Verde Unknown Unknown of 3-story, four-and five-plex buildings, with unit sizes ranging from 809 square feet to 2,010 square feet.
Ql-Jan/Feb/Mar 0 Actively being processed I
Q2 -Apr/May/June u Pending action by developer
Q3 -July/Aug/Sept Q On hold
Q4 -Oct/Nov/Dec
Page 3 of 3
~Vit.J it-Q
ITEM
II DIVISION CONTACT PHASE PROJECT NAME
1 Nicholas lourfan Execute Council Chamber Upgrade
2 Nicholas lourian Execute Managed Print Services
3 Sherry Remington Execute Enterprise Content Management
4 Sherry Remington Execute EnerGov
5 Nicholas l ourian Initiate Voice Over IP (VOIP) and Wide Area Network (WAN)
6 Nicholas l ourian Request Infrastructure as a Service (Cloud Hosting Services)
7 Sherry Remington Execute Enterprise Resource Planning (ERP) System Discovery
IT STATUS UPDATE Q12016 (through Dec. 31, 2015)
CURRENT
ORIGINAL ESTIMATED SCHEDULE PROJECT VALUE COMPLETION DATE COMPLETION STATUS
DATE
s 350.000 24 August (03 2015) Q4 2015 0
s 2,055,781 14 September (03 2015) Q4 2015/01 2016 0
s 1,500,000 17 August (03 2015) Q4 2015/01 2016 • s 1,238,088 23 December (0 4 2015) Q2 2016 0
s 1,000,000 02 December (04 2015) TBD a
s 120,000 28 April (02 2016) Q1 2016/Q2 2016 8
s 500,000 10 February (01 2016) Q1 2016/Q2 2016 •
01 -Jan/Feb/Mar
Q2-Apr/May/June
03 ·July/Aug/Sept
04 -Oct Nov Dec
PROJECT DESCRIPTION/COMMENTS
---,...-
All functional modifications completed and project closed out In OAPTIV: Only cosmetic remain (glass on staff
table/holes on dais top) .
Multi-Function Devices in place throughout the city with the exception of Cole Library (renovation in
progress), Safety Center and Fire Stations .
Go live for HP Records Management replacing OMS complete on 23 Nov 2015; Agenda Management has
been delayed through February 2016.
On track to go live June 2016.
VOIP on hold until completion of WAN upgrade.
Prepping for priority 1 and 2 application migration to cloud-hosting services.
We currently have 27 business processes identified through discovery phase. Due to rescheduling of working
sessions we will go beyond the draft assessement report that was originiatly due from Plante Moran in
January 2016. Expect discovery phase final analysis April 2016.
Page 1 of 1
t}(~b\t-4 COUNCIL GOALS STATUS UPDATE Q1 2016 (through Dec. 31, 2015) ~ -
ITEM# PRIORITY GOAL STATUS ACTIVITY/ PROGRESS
1 A To complete the General Plan including the Transportation 0 • On September 22, 2015, City Council approved the General Plan Update, including modifications and clarifications to the
Element Mobility Element. (A lawsuit has been filed challenging the approval.)
Complete Zoning Ordinance and Local Coastal Program 0 • On October 20, 2015, City Council approved an agreement with Michael Baker International to update the Zoning
Updates Ordinance (Q3 2016) and Local Coastal Program (Q1 2017), and to complete a sea level rise analysis (Q1 2016).
• IT Department leadership and staff resources have been realigned to address the city's critical technology needs.
• A new electronic records management system launched in Q4 2015.
• An enhanced agenda management system will launch in Q1 2016.
• New equipment for managed print services is being implemented for completion of city-wide rollout in Q1 2016.
• Three new engineers have been hired and assigned to address the current CIP project backlog.
2 B To build/sustain IT/CIP capacity 0 • 'Greenlight Report' created and presented to City Council quarterly.
• CIP Advisory Committee created and CIP to undergo Leadership Team review to ensure council goals are met .
• Conducting a pilot project using tablet-based incident command system.
• Safety preparing to meet next-gen standards for 800 MHz radio communications.
• Implementing Next-gen Incident Command System (NICS) for Emergency Operations Center communications.
• Police Department to implement TeleStaff (scheduling and time management) software upgrade in Q1 2016, and an
automated report management system in Q4 2016.
3 A To create/maintain/sustain the balance between 0 • 2015 Carlsbad Resident Survey data collection is complete. Results presented to City Council in Q4 2015.
environmental/fiscal/social well-being • Currently developing next-generation city performance metrics linked to the nine Carlsbad Community Values.
• Master Plan implementation projects for Poinsettia, Pine and Aviara Parks are currently in design phase, with construction
0 to begin Q3 2016.
Accelerate park development • Master Plan implementation project for Pine Avenue Community Center is currently in design phase, with construction to
begin Q4 2016.
• Strategically reallocated resources to staff new Parks Planner position.
Ensure trails development 0 • Trails Master Plan Update will be presented to City Council in Q2 2016.
Create an Arts Master Plan 0 • Public Art Master Plan will be presented to City Council in Q1 2016.
• Finalizing contract to develop Arts and Culture Master Plan, which will be presented to City Council in Q1 2017.
• Electric Vehicle Charging Station-Alga Norte Park.
0 • Solar Energy Generation -Alga Norte Park and Safety Training Center.
Other notable city projects and initiatives • Recycled Water System Expansion.
• Drought Response initiative ongoing.
• Partnership with Walk/Bike Carlsbad.
Page 1 of4
COUNCIL GOALS STATUS UPDATE Q12016 (through Dec. 31, 2015) ~ ,.-
~ ~ !; .., a! ITEM# PRIORITY GOAL STATUS ACTIVITY/ PROGRESS !'11.·1 ~
• Public outreach efforts underway for Terramar Area Coastal Improvement Project, Ocean Street Beach Access Project
0 (seven stairway locations), Village and Barrio Master Plan, and the Parks Master Plan Feasibility Studies.
4 B To engage the community proactively • Public outreach efforts for Tamarack Ave./Carlsbad Blvd. Intersection Improvement Project to begin Q1 2016.
• Communications now included in project budgets (i.e., Library Renovations, Coastal Corridor Improvements, Village
construction and infrastructure improvements).
Foster the next generation of leaders 0 • Currently engaging high school student focus group to help design 'Youth Civic Education in Action Program' to foster next
generation civic leaders. Draft program to be presented to Council in Q1 2016.
• High level of communication, engagement and interaction through social media: Facebook {42,000 Followers). Twitter
Include strong IT/Intranet/lnternet component 0 {8,600 Followers).
• Staff to initiate project team meetings to develop citizen complaint app in 2016.
• Implemented online survey tools.
• Recently updated the city's open space web page.
• Produced a series of vid!:O vignettes highlighting th!: city's open space prQgram.
Tell "open space" story ~ • Union-Tribune article on 'Open Space Done the Carlsbad Way' published October 6, 2015.
• Carlsbad Currents open space feature article.
• Community Services Guide.
To review/plan for city facilities consistent with growth "
• All facilities currently meeting the City's growth management standards.
5 c • Producing monthly Development Monitoring Report. management • Preparing Strategic City Facilities/Asset Management Report Q1 2016.
• Initiated monthly strategic planning meetings of the city leadership Team to develop and support an innovative
organizational culture.
• Only community in San Diego County, and one of 12 cities participating in statewide community para medicine I
' alternative destination pilot program.
• Piloting program with California Coastal Commission and SANDAG to enhance processing times for Carlsbad projects.
6 B To seek and apply innovation in city services ~ • Piloting collaborative design process, including cross-departmental city staff team and project design consultants working
to address permitting issues prior to formal application.
• Created series of Council Visioning Panels {Autonomous & Connected Vehicles-Q2 2015 I Big Data and the Future of
Open Government-Q4 2015 I Future of Energy-Q1 2016).
• Mobility Readiness Plan to be presented to City Council Q1 2016.
• License plate recognition capability.
• Utilizing SWAT command vehicle and robotics technology to improve safety.
• Newly hired Real Estate Manager to project city space needs, and to identify and evaluate highest and best use of
7 B To manage the city assets to achieve enhanced city services 'I underutilized city-owned properties.
(assets are defined as unused/underutilized properties) • Co-location of city facilities at Maintenance & Operations Center to create operational efficiencies and free up city land
assets for other uses.
Page 2 of 4
COUNCIL GOALS STATUS UPDATE Q12016 {through Dec. 31, 2015) -=r
~ ITEM# PRIORITY GOAL STATUS ACTIVITY/ PROGRESS ~
• On September 22, 2015, City Council approved the General Plan Update, including the Mobility Element.
8 A To manage growth consistent with the Community Vision and
nine Core Values including the Transportation Element G • Updates to the city's Zoning Ordinance {Q3 2016) and Local Coastal Program (Q1 2017) are underway.
• New performance metrics will be focused on Community Core Values.
• Five-year check-in on Community Vision to be conducted in 2016.
9 B To plan the Village element to maximize Village vitality 8 • On November 12, 2015, the DRAFT Village/Barrio Master Plan was released for community review.
Develop the Village/Barrio Master Plan (include identification G) • The Plan incorporates parking strategies that identify parking structure development opportunities.
of a parking structure) • The final Village/Barrio Master Plan will be presented to City Council for approval in Q2 2016.
Railroad grade separation G • SANDAG Project Study Report (design alternatives feasibility analysis) and Economic Study underway.
• Ocean Street Parking Lot Project completed Q4 2015.
• Tamarack Ave./Carlsbad Blvd. Intersection Improvement Project currently in conceptual design and public outreach;
construction to begin Q3 2017.
To enhance the coastal corridor for maximum • • Terra mar Area Coastal Improvements Project currently in conceptual design and public outreach; construction to begin in
10 B resident/tourist satisfaction Q3 2017.
• Ocean Street Beach Access Project (seven stairway locations) currently in conceptual design and public outreach;
construction to begin in Q3 2016.
• Strategic plan for CA State Beaches Maintenance and Operations to be developed with assistance from legislative
consultant in 2016.
• New parks maintenance contracts deliver best value to the community.
• Employee pay for performance process clarifies organizational priorities and performance expectations.
• Employee engagement survey will provide insights on improving job satisfaction and organizational performance.
11 A To steward/govern/manage consistent with the city's
organizational values G • New on-boarding program provides extra support during employees' first 90-days on the job.
• World Class Customer Service training programs attended by 167 employees.
• Monthly training on performance management and coaching methods offered to supervisors.
• Broad offerings in technology and applications training are presented frequently.
• 1-year project management training program provided to 50 employees through partnership with USD.
---
Page 3 of 4
COUNCIL GOALS STATUS UPDATE Q12016 (through Dec. 31, 2015} ~
-----
ITEM# PRIORITY GOAL STATUS ACTIVITY/ PROGRESS
12 B To foster economic development 0 • Existing businesses including ViaSat, Legoland, Spy Optic and Pizza Port are expanding operations in Carlsbad.
• New businesses including GoPro, Under Armour, Amazon Fresh and Surf Air are establishing a presence in Ca rlsbad.
• Continuing efforts to attract graduate level engineering program(s) to serve the city and region's talent needs.
'i) • Facilitated meetings, assisted and coordinated due diligence process with Rochester Institute of Technology.
Continue higher education project • Worked with San Diego Regional Economic Development Council to engage with UCSD about the project.
• Working with businesses to identify specific graduate-level aca demic programming t hat will grow the talent base to serve
the needs of local and regional busniesses.
• Life in Action talent attraction campaign hosts web and social media presence, hosts media tours and sponsored events, I
Emphasize talent attraction 0 and produces promotional brochures to support business relocation and employee recruitment.
•Partnered with Mira Costa College to support workforce pipeline development through Technology Career Institute.
•Presented the 'Bio, Tech and Beyond' life sciences start-up showcase.
Work on 78 Corridor and leverage partnerships with five cities 0 • Innovate 78 campaign contract administrator for contract with San Diego Economic Development Corporation.
• Monthly/Quarterly meetings of economic development managers and mayors are held to evaluate effectiveness.
• Working with private industry to remove barriers to expanding or retaining business in Carlsbad.
• New online project permitting system in development to be completed in Q2 2016.
• CED customer service training completed and customer service delivery update ongoing, including remodeled "public
Emphasize business friendly philosophy (i) service counter" to be completed Q2 2016.
• Evaluating opportunities to improve security at city facilities.
• Hosted 2015 Brokers Forum.
• Libraries offer business support services including public access to eResearch databases, free access to public computers,
business workshops, meeting spaces and networking opportunities, computer classes and drop-in computer help sessions.
13 A To provide basic city services 0 • The 2015 Carlsbad Resident Survey shows that 91% of Carlsbad residents are satisfied with city services.
• Police Department emphasis on public outreach and community engagement efforts is ongoing.
Continue and improve public safety services 0 • Crime Analysis Response (CAR) model focused on data-driven policing.
• El Niiio preparations and public outreach efforts are ongoing.
• 2015 Vehicle Report Card program implemented to help prevent theft.
0 • Fire Station #3 under construction and on schedule for Q1 2016 opening.
Continue and improve emphasis on fire protection • Fire Station #2 Project Feasibility Study to be presented to City Council.
• New fire engine from State of California Office of Emergency Services received Q4 2015.
Page 4 of4
City Council Workshop
January 19, 2016
Capital Improvement Program (CIP)
Status Report
Quarter Ending December 31, 2015
CIP Budget Summary
•CIP for FY 2015-16 to FY 2029-30 (15 year
planning document)
•240 continuing and new projects
•Total cost of $559.8 million
CIP Budget Summary (cont.)
•Project Types
–Streets/Circulation $125,841,075 28%
–Parks $ 82,496,360 18%
–Civic Projects $ 79,140,455 17%
–Wastewater $ 67,794,962 15%
–Water (inc.Recy.)$ 63,469,200 14%
–Drainage $ 15,549,012 3%
–Other (loans)$ 20,839,636 5%
CIP Budget Summary (cont.)
•Revenues
–Developer Fees 21%
–Financing Districts 4%
–Utility Replacement Transfers 30%
–Infrastructure Replacement Transfers 28%
–Other Agencies 17%
CIP Budget Summary (cont.)
•FY 2015-16 CIP budget approved by City Council
on June 30, 2015
–$67.1 million new appropriations
–$224.9 million continuing appropriations
–Total of $292 million appropriations
Mid-year Financial Status, FY 15-16
•35% of FY 15-16 budget committed
–$292 MM appropriated
–$102.6 MM encumbered and expended
Quarterly Projects Report
ITEM #PROJECT #DIVISION DIVISION
CONTACT PROJECT NAME PROJECT
BUDGET
ORIGINAL
ESTIMATED
PHASE
COMPLETION
DATE
CURRENT
ESTIMATED PHASE
COMPLETION DATE
SCHEDULE
STATUS COMMENTS FUNDING SOURCE
CONSTRUCTION PHASE
1 4003 Property Casey Arndt Fire Station 3 $ 9,352,000 Q4 2015 Q4 2015 Project is under construction with a substantial completion of 12/31/2015.Public Facilities Fee
2 4717 Parks Kyle Lancaster Aviara Community Park Synthetic Turf Replacement $ 860,000 Q3 2015 Q1 2016 Estimated completion end of Jan. 2016. Subject to change if El Nino weather
conditions interfere with construction.
Infrastructure Replacement
Fund
3 4019 Parks Kyle Lancaster Village Streetscape $ 345,000 Q1 2016 Q1 2016 Walkthrough with contractor for the installation of concrete benches, steel
trash/recycling receptacles, and steel/wood benches occurred in late Dec. 2015.General Capital Construction
4 6001 Transportation Jonathan Schauble 2015 Slurry Seal Project $ 2,400,000 Q4 2015 Q4 2015 Construction Contract awarded on November 17, 2015. PreCon scheduled for
December 29, 2015. Gas Tax, TransNet Local
5 5526 Utilities Mark Biskup Foxes Landing Lift Station and Force Main $ 3,275,000 Q4 2015 Q4 2015 Lift Station Replacement Final Design Sewer Replacement
6 4030 Property Steven Didier Dove Library Improvements and Refurbishment $ 6,046,529 Q3 2016 Q1 2016 Contract awarded, construction anticipated to begin Feb. 2016 General Capital Construction
7 6055 Transportation Doug Bilse Coastal Corridor Mobility Readiness Plan $ 100,000 Q4 2015 Q1 2016
Final Draft review until 1/17/16. Stakeholder outreach, commission and city
council presentations starting in Feb. 2016. Coastal Mobility Infrastructure Action
Plan implementation projects could start June 2016.
General Capital Construction
8 5019 Utilities Shadi Sami Water Valve Replacement Program $ 550,000 Q1 2016 Q1 2016 Staff is working on the condition assessment of the potable water valves within
the system. Water Replacement
9 6001 Transportation Jonathan Schauble Pavement Management Program Update Citywide $ 100,000 Q2 2016 Q2 2016 IMS evaluated citywide pavement condition Q4 2015. Staff evaluating PCI data
and software updates.Gas Tax, TransNet Local
10 3821A Transportation Sherri Howard Lake Calavera Mitigation Long Term Maint. $ 200,000 Q3 2017 Q3 2017 Long term maint plan. Annual report in Sept. Quarterly site visits ongoing.
Drought delayed growth. Water Replacement
11 6604/6024 Transportation Sherri Howard Romeria and La Costa Slope Repair Mitigation Site $ 150,000 Q2 2020 Q2 2020 Initial planting in Q2 2015. Maintenance and monitoring required until 2020.Gas Tax. General Capital
Construction
12 3821B Transportation Sherri Howard Lake Calavera Dam Mitigation Long Term Maintenance
Mitigation Site $ 250,000 Q3 2021 Q3 2021 Conceptual Mitigation Plan approved. Preparation of Bid Documents under way Water Replacement
13 3801 Parks Liz Ketabian Roberston Ranch Park Development $ 2,700,000
Currently on Unfunded Projects list; budget shows partial funding of $2.7 MM
against total cost of $7.8MM. Scheduled currently for buildout. Unknown start
date
Park-in-Lieu
14 Parks Liz Ketabian Veteran's Park $ 23,240,000 Current CIP schedule shows development at 2026-30. CFD #1
15 6004 Transportation Avenida Encinas widening south of Palomar Airport Road $ 5,402,000 Project to schedule to be determined based on the construction progress of the
Vista Carlsbad sewer project along the Avenida Encinas. Traffic Impact Fee
FUTURE PROJECTS
PRE-CONSTRUCTION PHASE: INCLUDES PLANNING & DESIGN, BID/AWARD PERIOD
PROGRAMS & STUDIES
LONG TERM MAINTENANCE
Fire Station No. 3
•Approximately 99% complete
•Exterior and interior of the fire station are
complete
•Hose tower is complete
•Site surface improvements are complete
•Trail Blazer Way is paved and landscaped
•Exterior art work installed
•Final landscaping and equipment commissioning
occurring January 2016
Fire Station No. 3 (cont.)
•Alarm, telecommunication, and radio systems
installed and being tested
•Sliding gate, final signing and striping to be
installed January 2016
•FFE being delivered and installed January 2016
•Final walk-throughs are being conducted and
punch list items are being corrected
•Project on schedule and within budget
•Final completion scheduled for February 2016
Fire Station No. 3 (cont.)
Cole and Dove Library Modernization
•Cole Library closure started
Sept. 1, 2015
•Project Schedule:
–Cole Library September 2015
to February 2016
–Dove Library January 2016 to
June 2016
•Overall project budget
$11,300,000
Cole and Dove Library Modernization (cont.)
Facilities Renovation Projects
•Fire Station No. 1
–Interior / exterior refurbishment (ongoing through March 2016)
•Harding Community Center
–Interior refurbishment (ongoing through April 2016)
–HVAC and roof replacement (completed)
•Faraday Center
–HVAC and roof replacement(Summer 2016)
–Interior refurbishment (ongoing through 2016)
•City Hall
–Interior renovations and roof replacement (initiate design
February 2016, construction Summer 2016)
Safety Training Center PV
•Panel Installation December 2015
MUTCD Street Sign Replacement Project
•95% complete
•Replacement of ground
mounted signs
complete
•Signal mounted sign
replacement ongoing
•Project completion:
February 2016
Traffic Signal Modernization Program
•5 –7 year program
•Fiber optic and wireless communications
•Converted to video detection
•Traffic Management Center (TMC)
•Coordination timing programs
•Traffic monitoring system
•Adaptive controls
Traffic Monitoring System
(Bluetooth Travel Time Origin and Destination)
El Camino Real Widening:
Tamarack to Chestnut
•Approximately 50% complete
•Work continues on drainage facilities and utility
installation
•Phase 2 (raised median) began January 2016
•Phase 3 (west side improvements including retaining
wall) expected to begin mid-February 2016
•Project delayed due to archaeological discoveries and
landfill debris in east side embankment
•Original schedule completion in 1st quarter 2016
•Estimated completion 3rd quarter 2016
El Camino Real Widening:
Tamarack to Chestnut (cont.)
El Camino Real Widening:
Tamarack to Chestnut (cont.)
El Camino Real Widening:
Tamarack to Chestnut (cont.)
CWRF Plant Expansion
•Design build contract awarded 06/09/15
•D/B contractor to begin work in early 2016
•Expansion of plant from 4 mgd to 7 mgd
•Estimated completion: Fall 2016
Recycled Water Pipelines
•Palomar Oaks Business Park
•Calavera Hills
•Cannon Road to NRG
•CWRF to Cannon Road
(included with V/C Sewer
Interceptor)
Recycled Water Pipelines (cont.)
Recycled Water Pipelines (cont.)
Vista Carlsbad (V/C) Sewer Interceptor and
Avenida Encinas Recycled Waterline
•Sewer force main construction on NRG property is
underway
•SoCal Gas has started 12” gas line shutdown and removal
•Storm drain pipelines being installed at lift station site
•Construction activity at north end of Avenida Encinas to
begin in late January 2016
•Public outreach process initiated
•Estimated completion date for construction: August 2017
Vista Carlsbad (V/C) Sewer Interceptor and
Avenida Encinas Recycled Waterline (cont.)
Vista Carlsbad (V/C) Sewer Interceptor and
Avenida Encinas Recycled Waterline (cont.)
Vista Carlsbad (V/C) Sewer Interceptor and
Avenida Encinas Recycled Waterline (cont.)
Village -Coastal Streetscape
•Replacement of streetscape furnishings –Phase II
–Bench / trash receptacle work began in January 2016
–New installations to be completed by early February
2016
Carlsbad Blvd/Village Pedestrian
Crossings (RRFBs)
•Completed the RRFB installation at:
–Carlsbad Blvd. & Sycamore Avenue
–Carlsbad Blvd. & Maple Avenue
–Carlsbad Blvd. & Cherry Avenue
–Carlsbad Blvd. & Hemlock Avenue
–Grand Avenue & Tyler Street Ally
–Grand Avenue & Carlsbad by the Sea
Terramar Area Coastal Improvement Project
•Nov. 19, 2015: Second
public outreach meeting
•Online survey closed
Dec. 21, 2015
•Next Steps: Revise
project alternatives;
begin environmental
and permitting
Carlsbad Blvd. / Tamarack Ave.
Improvements
•Two SANDAG ATP Grants for
$ 1.246 million
•Public outreach Spring 2016
•Construction to begin Q4 2017
•Next Step:
-Finalize project scope with
Coastal Commission staff
Ocean Street Parking Lot
•Safety and beach access improvements
completed in October 2015
–New walking path
–Sealing and re-stripe parking lot
Before
After
Northern Beach Access Improvements
•Oak Avenue
•Carlsbad Village Drive
•Grand Avenue
•Christiansen Way
•Beech Avenue
•Cypress Avenue
•Rue Des Chateaux
Northern Beach Access Improvements (cont.)
Typical Improvements:
•Add low level lighting
•New plantings and irrigation
•Enhance pavement on Ocean
Street
•Replace/refurbish stairs & handrails
•Replace fencing/improve screen
walls
•New benches/litter receptacles,
bike racks and signage
Public Beach Access –Grand Ave.
Northern Beach Access Improvements (cont.)
Public Outreach
•City website:
-Citizen Survey
-Over 300 respondents
-December 2015 / January 2016
•Public meeting:
-Dec.3, 2015
-Opportunity to review proposed improvements
-Survey distributed to those in attendance
Village Double Tracking-Project Study Report
•Currently reviewing a Project Study Report,
prepared by T.Y. Lin for SANDAG for trenching
options
•Meeting with NCTD to discuss opportunities
•Coordination of meetings with SANDAG to
discuss project
•Economic Feasibility Study currently being
developed by RSG for SANDAG
Maintenance and Operations Center
(MOC)
•October 20, 2015 City Council approved
contract with Bridging Consultant for
preliminary design and entitlement services
•1st Q 2016 -3rd Q 2016: preliminary design
•3rd Q 2016 –2nd Q 2017: D/B team completes
design, begin construction 2017
•Construction schedule approx. 18-24 months
Maintenance and Operations Center (cont.)
OLIVENHAIN RD
M
ONROE ST
T A M A RAC K AV T A MARACK AV
ARMA
DA D
RPASEO
DEL NO
R
TE
FAR
A
DAY AV
CANNON R D
EL CAMINO REAL
C
A
R
L
SBA
D B
L
ME
LROSE DR
A
VI
ARA P
Y
ALGA RD
ALICA N T E RDEL FUERT E STEL F
U
ERTE ST
LA COSTA A V LA COSTA AV
R
A
NC
HO S
A
NTA FE R
DCAMINO DE L O S COCHESCOLLEGE B LM ARRON RD
CARLSBAD BL
C ARL SBAD VILLAGE DR
BATIQUITOS LAGOON
BUENA
VI
S
T
A
L
A
G
OO
N
AGUA HEDIONDA LAGOON
PACIFIC
OCEAN
FLEET MAINTENANCE
LE
G
O
L
A
N
D
D
R
THE
C
RO
S
S
IN
G
S
DR
405 OAK AVENUE
CARLSBAD MUNICIPAL
WATER DISTRICT
PARK MAINTENACE
City of Carlsbad
Facilities
Maintenance and Operations Center (cont.)
Northwest Quadrant Storm Drain
Improvement Program Projects
•Construction
–Madison Street, Wilson Street
•Pre-Construction (Design)
–Roosevelt Street
–State Street
–Arbuckle Street
–Monroe Street
Northwest Quadrant Storm Drain
Improvement Program Projects (cont.)
Pavement Management Program
•2015/16 Slurry Seal Project
–Various streets throughout the city
–Pre-construction meeting held on 01/07/16
–Construction to begin in January 2016
–Budget: $1.8 million
•2015/16 Pavement Overlay Project
–College Blvd. (north of Cannon)
–Black Rail Road
–Grand Avenue (east of Jefferson)
–Carlsbad Village Drive (east of Tamarack)
–Budget: Approximately $2.0 million
Pavement Management Program (cont.)
Slurry Seal Locations
Concrete Replacement Program
•Various streets throughout the city
•Pre-construction meeting held on 12/17/15
•Construction to begin January 2016
•Estimated completion date: March 2016
4th Qtr. 2015 –Parks & Recreation
Milestones & Accomplishments
Oct. 22:Received 30 percent construction plans for
Aviara & Poinsettia Parks
Nov. 24:Received design plans for Pine Avenue Park
Nov. 24:Received 80 percent construction plans for
Aviara & Poinsettia Parks
Dec. 23:Received 30 percent construction plans for
Leo Carrillo Ranch stables restoration and
new restrooms
Aviara Community Park
Refined Design
•Community room
•Large shade structure
over group picnic area
•Outdoor fireplace
•Passive lawn area
•Small stage with
shade structure
•Picnic nodes
Aviara Community Park
Bird’s eye view looking north
Aviara Community Park
Community room and shade structure
Poinsettia Community Park Master Plan
Dog Park -View looking northwest
Poinsettia Community Park Master Plan
Multi purpose arena sports field
•Regulation size
arena field
•Bleachers
•Warm-up areas
•Picnic areas
Poinsettia Community Park
Playground –View looking northwest
Pine Avenue Community Park
Community Center –Refined Design
•New drop-off area
•Visual & physical
connection to Senior Center
•Building oriented towards
street frontages
•EV charging station
Pine Avenue Community Park
Community Center -View looking northeast from drop-off
Pine Avenue Community Park
Ornamental & Community Gardens –Refined Design
•Ornamental garden
(drought tolerant)
•Community gathering
plaza w/shade structure
•Picnic areas
•Seating areas
•Community garden with
raised planters
•Demonstration area
Pine Ave. Community Park Master Plan
•Community center and gardens –phase II
–Concept plan in final refinement stage
Leo Carrillo Ranch Park Master Plan
•Restoration of stables & construction of restroom
–Kick off meeting: Sept. 29
–30 percent Design submittal:
Dec. 23
Aviara Community Park Synthetic Turf
•Replacement of soccer field’s synthetic turf
-Construction commenced in mid-Dec.
-Construction to be completed by early Feb.
Lake Calavera Trails Master Plan
Pre-fabricated Restroom
•Consultant hired for design –mid October
-ADA unisex restroom
-Drinking fountain
-Shade porch
Private Development Projects
•Commercial
•Residential
North 40 Urban Farm
•60,000 s.f.building
•Wholesale floral market
•Micro-brewery and tasting room
•Organic garden and culinary demo kitchen
•Locally-sourced produce market
•Phase 1 scheduled to open April 2017
Westin Hotel and Timeshare
•71 Hotel rooms
•36 Timeshare units
•144,000 s.f.including ground floor garage
•December 2015 Planning Commission
Robertson Ranch West Village
•308 single family homes
•100 senior apartments
•264 market-rate apartments
•Internal streets under construction
•El Camino Real widening underway
•156 acres –92 acres open space
•636 residential units
•1.5-ac. community facilities site and trails
•1.3-ac. park and ride
•Mass grading, storm drain, bridge underway
Quarry Creek
Seagrove
•47 two and three-story townhomes
•Live-work units, includes 6 affordable
•1,200 to 3,000 s.f.
•Models open
•Priced from the mid $900’s
QUESTIONS?