Loading...
HomeMy WebLinkAbout2016-06-07; City Council; 22305; Preliminary FY 2016-17 to FY 2030-31 Capital Improvement ProgramItem 4; pg. 1 CITY OF CARLSBAD -AGENDA BILL AB# MTG. DEPT. 22,305 06/7/16 FIN RECOMMENDED ACTION: PRELIMINARY FY 2016-17 TO FY 2030-31 CAPITAL IMPROVEMENT PROGRAM Accept report. Set public hearing for June 28, 2016. ITEM EXPLANATION: DEPT. HEAD CITY ATTY. CITYMGR. The Preliminary Capital Improvement Program {CIP) is a planning document as well as a budget document. It incorporates the current status of all of the city's capital funds with the capital construction budgets and development projections for the upcoming years, and then projects future revenues and expenditures for all known projects. The CIP is a financial planning document, not a commitment for spending. All construction costs are estimates and are reviewed and further refined each year. The information shown in years subsequent to Fiscal Year (FY) 2016-17 is to provide the most comprehensive overview of all the known future facilities the City of Carlsbad plans to construct. Overview-Fiscal Year 2016-17 The FY 2016-17 Capital Improvement Program outlines approximately $64.4 million in new appropriations to provide addi1ional funding for the continuation of existing projects as well as funding for new projects. Projected revenues during the same fiscal year are estimated at $51.7 million. As the city continues to grow and develop, there is a corresponding increase in the demand for development-related services and new facilities. To ensure that the necessary infrastructure and facilities are built on a schedule that meets or exceeds this demand, the citizens of Carlsbad adopted a Growth Management Plan in 1986. The Growth Management Plan states that unless an adequate level of facilities is available to meet new demands resulting from the city's growth, development cannot proceed. This Plan is the foundation for making decisions about the timing and prioritization of the capital projects under consideration. Staff began the CIP process by evaluating the existing construction schedules for city facilities in conjunction with the work load of the staff needed to complete the projects. In addition, staff considered the priority of the project based on the criteria shown below, as well as the availability of capital construction funding and alignment with City Council priorities and the Council and Community Vision. While evaluating the availability of funding, every effort was made to fund projects using the most restrictive funding source first. In addition to evaluating the availability of capital construction funds, operating fund impacts were also considered. Capital improvement projects are evaluated based on the following criteria: • Is the project required to ensure the health and safety of the citizens, as the result of a legal mandate? • Is the project needed for growth management compliance? • Is the project needed for other city standards? • Does the project complete or provide part ofthe basic infrastructure? DEPARTMENT CONTACT: Helga Stover 760-602-2429 helga.stover@carlsbadca.gov FOR CITY CLERKS USE ONLY. t COUNCIL ACTION: APPROVED CONTINUED TO DATE SPECIFIC D DENIED CONTINUED TO DATE UNKNOWN D CONTINUED D RETURNED TO STAFF D WITHDRAWN D OTHER-SEE MINUTES D AMENDED D Item 4; pg. 2 • Are there other reasons to construct the project (council priority, timing or funding opportunity, public demand, community and council vision)? • Are the operating funds available to operate the facility? Future Facilities The proposed 15 year CIP for FY 2016-17 to FY 2030-31 outlines approximately 235 continuing and new projects, at a cost of approximately $463.2 million as shown below: CIP Projects -All Future Project Costs Project Type Percent Tota I Cost Streets/Circulation 28% 128,648,553 Civic Projects 16% 75,224,860 Wastewater 21% 98,830,483 Parks 10% 45,229,920 Water 17% 79,482,800 Drainage 4% 17,603,507 Other (loans) 4% 18,180,162 Tota I Future 100% 463,200,285 The FY 2016-17 CIP is being driven by the city's commitment to ensure that facilities are available to serve the developing areas as well as the current residents. Carlsbad's philosophy has been to build quality capital facilities which meet and, at times, exceed Growth Management standards. Phasing projects over a period of years to match funding availability for construction and operations is often used to meet the needs of growth management. The FY 2016-17 Capital Improvement Program reflects the commitment of Carlsbad's City Council and staff to continue providing residents with a better quality of life. The proposed Capital Improvement Program for FY 2016-17 is an exhibit to this report (Exhibit 1). Staff is requesting that Council set the public hearing for adoption ofthe CIP, as well as for the city's Operating Budget, for the meeting of June 28, 2015. During this public hearing, comments from interested citizens are welcome. There will also be a public meeting, where staff will present to the citizens of Carlsbad and any interested parties, the FY 2016-17 Capital and Operating Budget, answer any questions, and gather comments to provide feedback to Carlsbad's City Council. This meeting will be held on June 21, 2016, at 6:00P.M. at the Faraday Building (1635 Faraday Avenue, Carlsbad) in Room 173B. ENVIRONMENTAL IMPACT: Acceptance ofthe Preliminary Capital Improvement Program does not qualify as a "project" under the California Environmental Quality Act (CEQA) per state CEQA Guideline Section 15378(b)(4). This section specifically states governmental fiscal activities that do not involve any commitment to any specific project that may result in a potentially significant environmental impact are not projects. FISCAL IMPACT: This is the Preliminary Capital Improvement Program and any changes made by staff or Council will be reflected in the Final Capital Improvement Program documents at the Operating Budget and Capital Improvement Program adoption on June 28, 2015. The total new appropriations on July 1, 2016 are currently planned to be $64,389A57 from the CIP funds shown on the attached schedules. Existing expenditures and appropriations shown in the attached schedules are through March 31, 2016. In addition, revenue projections are provided to show the cash flows and balances for each of the funds. Staff will continue to review the capital requirements for the city and may return with additional changes prior to the adoption of the CIP on June 28, 2016. Item 4; pg. 3 EXHIBITS: 1. FY 2016-17 Preliminary Capital Improvement Program Overview 2. FY 2016-17 Preliminary Capital Improvement Program Project Schedule 3. FY 2016-17 Preliminary Capital Improvement Program Fund Balance Schedules Item 4; pg. 4 2016-17 PRELIMINARY CAPITAL IMPROVEMENT PROGRAM OVERVIEW The City of Carlsbad Capital Improvement Program (CIP) is a 15 year planning document that outlines the expenditure plan for future capital projects and the corresponding revenues to pay for those expenditures. The CIP is a financial planning document, not a commitment for spending. All construction costs are estimates and are reviewed and further refined each year. Spending authorization is given only at the time the City Council formally adopts the proposed budget, and, at that time, funds are only appropriated for the upcoming fiscal year. Information is shown in subsequent years to provide the most comprehensive information about all of the known future facilities the City of Carlsbad plans to construct, refurbish, replace, or modify. The Fiscal Year (FY) 2016-17 Capital Improvement Program outlines approximately $64.4 million in new appropriations to provide additional funding for the continuation of existing projects as well as funding for new projects. Projected revenues during the same fiscal year are estimated at $51.7 million. As the city continues to grow and develop, there is a corresponding increase in the demand for development-related services and new facilities. To ensure that the necessary infrastructure and facilities are built on a schedule that meets or exceeds this demand, the citizens of Carlsbad adopted a Growth Management Plan in 1986. The Growth Management Plan states that unless a standard level of facilities is available to meet new demands resulting from the city's growth, development cannot proceed. This Plan is the foundation for making decisions about the timing and prioritization of the capital projects under consideration. A discussion of the city's Growth Management Plan is located at the end of this report. The remainder of the report explains the process and the results of the city's plan for its capital facilities. In addition to new facilities corresponding to new development, aging infrastructure requires maintenance and at times, replacement. About 50 percent of Carlsbad's comprehensive capital plan encompasses numerous asset management programs to ensure adequate inspection, maintenance, and replacement of buildings and parks, water, sewer and drainage systems, bridges, and roadways systems. It is still anticipated that the city will continue to meet its growth management standards. This reflects the Council's continued commitment to construct the facilities as needed to serve the current and anticipated development occurring throughout the city. PROJECT EVALUATION Projects that are shown in the CIP are generally defined as any construction (or reconstruction/replacement) of major infrastructure such as streets, libraries, parks, fire stations and administrative facilities, water, sewer and drainage facilities, and other facilities that are located on or in the ground. In most cases, the total construction cost of each of these assets is recorded and tracked as part of the city's inventory of capital infrastructure assets and other city-owned property. The CIP and the Operating Budget are integral parts of the total city financing plan. Each year, staff begins the process by evaluating the construction schedules for city facilities in conjunction with the workload of the staff needed to complete the projects. Staff considers City Council Goals and Work Plan, to ensure that the CIP is in alignment with the Council and Community Vision. In the FY 2016-17 CIP, there are approximately 235 continuing and new projects planned in the next 15 years. Item 4; pg. 5 2016-17 PRELIMINARY CAPITAL IMPROVEMENT PROGRAM Projects were analyzed using the criteria shown in the table. Project timing was also reviewed, including evaluation of the availability of capital construction funds, operating funds, and other resources needed. CAPITAL PROJECTS 1. 2. 3. 4. 5. Project Ranking Criteria Is the project required to ensure the health and safety of the citizens, as the result of a legal mandate? Is the project needed soon for growth management compliance? Is the project needed to meet specific city standards? (Traffic signals, street lights). Does the project complete or provide part of the basic infrastructure or complement a regional plan (example: a linking road segment)? Are there other reasons to construct the project (example: Council priority, timing or funding opportunity, public demand)? Are operating funds available to operate the facility? The following two sections provide information about the major capital projects. The first section focuses on projects planned in the next five years, and the second section contains an overview of the entire expenditure plan through FY 2030-31 (the next 15 years). All construction costs are estimates and only projects scheduled for FY 2016-17 funding receive appropriations. The information shown in the future years reflect the most comprehensive snapshot of the known future facilities and their associated cost at this point in time. THE NEXT FIVE YEARS PARK PROJECTS The city is currently implementing park projects which were a result of a needs assessment and subsequent updated master plans. The city worked with the community to identify current needs and priorities for parks and recreation programs, and summarized the input in the Parks & Recreation Department Master Plan. The city then updated individual master plans for Poinsettia Community Park, Aviara Community Park, Pine Avenue Community Park and Leo Carrillo Ranch Historic Park. Aviara Community Park Event Gathering Space and Picnic Areas-The additional park amenities include a large passive outdoor community social space, group picnic areas, a perimeter walking path and a warming kitchen complete with appliances to support outside catering and food and beverage services and small events. The total cost is $3.2 million. Poinsettia Park Multi-Use/Multi-Generational Community Center -As a result of the needs assessment, funds are included to study the feasibility of a multi-use, multi-generation indoor community center, located at Poinsettia Park, which will serve a larger cross section of the community. Additional planned improvements include a fenced dog park for both large and small dogs, pickleball courts, updated tot lots and a multi-sports arena with a picnic area and artificial turf field, at a total cost of $4.4 million. Item 4; pg. 6 2016-17 PRELIMINARY CAPITAL IMPROVEMENT PROGRAM Leo Carrillo Phase Ill -This historic park is located in the southeast quadrant of the city. Expenditures include restoration of the horse stables, implementation of an outdoor interpretive plan to educate and focus on the life and times of Leo Carrillo, his ranch years, and native people and plants. Also included is visitor way-finding signage and additional lighting. The total estimated cost is $2.4 million. Pine Avenue Park Community Facility and Garden Areas -The remaining elements of the park include a multi-purpose community center and gymnasium, a community garden with rentable plots, and a botanical/ornamental garden. The community center and gymnasium will include basketball, volleyball, gymnastics, multi-purpose rooms, meeting rooms, a teen center, and office space. This final phase of the park is estimated at $11.1 million. Robertson Ranch Master Plan -This 13 acre park site is located within the Robertson Ranch development located in the northeast quadrant of the city. Funding in the amount of $200,000 is included for the development of a master plan. CIVIC FACILITY IMPROVEMENTS Civic facilities include a variety of facilities from which the city can offer its services to the public. Barrio Street Lighting -An analysis of the need for additional street lighting throughout the Barrio resulted in a project to add pedestrian scaled lighting around the perimeter of Pine Avenue Park, at a cost of $660,000. Maintenance & Operations Center -This city facility will bring together offices, the maintenance yard, a warehouse, and parking to accommodate the various work groups at one location, currently planned near the existing Safety Center and Fleet yard. The total estimated project cost is $29.8 million. Facilities Maintenance -As the city facilities begin to age, maintenance and repair projects are needed to keep them in good condition. In the next five years, $8.6 million has been allocated to projects, including projects at the following locations: • Aviara Community Park-Synthetic turf replacement • Beach Access Repairs/Upgrades • Cannon Park Restroom • City Facility Accessibility Upgrades • Hosp Grove Park Improvements • Ocean Street Restroom • Pine Avenue Park Synthetic Turf Replacement Item 4; pg. 7 2016-17 PRELIMINARY CAPITAL IMPROVEMENT PROGRAM Trails -Additional funding is Included for the Lake Calavera Trails system for restrooms and a drinking fountain. Village and Barrio Public Gathering Spaces -Funding in the amount of $345,000 is included to conduct outreach to determine the best locations for public gathering spaces, and, once locations have been identified, to prepare design concepts, illustrating outdoor gathering places with varied amenities. STREET AND CIRCULATION PROJECTS People of all ages and abilities want to go places safely and conveniently in Carlsbad. Whether they drive, walk, bike, or ride a bus or train. The livable streets concept, also called "complete streets," acknowledges that streets are an important part of the livability of today's communities and ought to be for everyone. Carlsbad has made livable streets a priority when planning and constructing improvements to city roadways. In addition to constructing improvements, the city continues to invest in the maintenance and operation of the transportation infrastructure by providing timely repairs and rehabilitation of the public assets associated with the roadways and public rights of way throughout the city. ADA Improvements-ADA projects throughout the city are scheduled for $1 million in funding over the next five years. The project includes various accessibility improvements, including sidewalk curb ramps and pedestrian signals. Avenida Encinas Widening -Widening to full secondary arterial standards along Avenida Encinas from Palomar Airport Road to just south of Embarcadero Lane is scheduled for design in FY 2016- 17. The CIP includes $5.4 million to fund this project in the next five years. Bridge Preventative Maintenance Program -This is a new program designed to perform preventative maintenance activities on bridges throughout the city, at a total cost of $1.5 million. Carlsbad Boulevard Pedestrian Lighting -This project will install pedestrian scale lighting along both sides of Carlsbad Boulevard between Tamarack Avenue and State Street at a total cost of $1.3 million. Carlsbad Boulevard and Tamarack Avenue Pedestrian Improvements -Improvements at the intersection of Carlsbad Boulevard and Tamarack Avenue includes installation of new concrete curb, gutter, sidewalk and pedestrian ramps at a total cost of $2.9 million. Concrete Repair and Maintenance-The proposed spending plan included $1 million in the next five years for repairs to sidewalks, curb and gutter, pedestrian ramps, driveway approaches and cross gutters. El Camino Real Widening -There are a number of projects that are scheduled over the next five years that will focus on the widening of El Camino Real, in addition to other improvements, such as median construction. The projects include widening from Cassia Road to Camino Vida Roble, Arenal Road to La Costa Avenue, Lisa Street to Crestview Drive and Tamarack Avenue to Chestnut Avenue. In the next five years, $5.1 million in additional funding is included for these projects, which are expected to cost over $20 million by completion. Intersection Improvements-Two intersection projects along El Camino Real, at Cannon Road and at College Boulevard are scheduled to receive an additional $2.6 million in the next five years. Pavement Management-Carlsbad's local streets are maintained on a regular cycle to ensure a good riding surface and to extend the life of the streets. Part of the maintenance program is the Item 4; pg. 8 2016-17 PRELIMINARY CAPITAL IMPROVEMENT PROGRAM sealing and overlay of the existing street surface. In addition, any problem areas are addressed as they are identified. The FY 2016-17 CIP has $12.6 million budgeted in the next five years for this program. Parking Lot Maintenance Program -Parking lot maintenance is a relatively new program and is scheduled to receive funding of $845,000 in the next five years. Poinsettia Lane Extension from Cassia Road to Skimmer Court -Completion of this segment of Poinsettia Lane is the final link between Aviara Parkway and El Camino Real. The total cost is estimated at $14 million. Road Diet and Traffic Calming Projects along Chestnut Avenue, Valley Street, Kelly Drive, and La Costa Avenue -Several projects are planned in the next five years to provide complete street solutions so that the varied user of these roads, including pedestrians and bicyclists, are provided for in a balanced and equitable manner. The total cost is estimated at $9 million. Traffic Signals -In the next five years, four traffic signal installations are planned at the following locations, at a total cost of $780,000: • El Fuerte Street and Rancho Pancho • Faraday Avenue and Camino Hills Drive • Faraday Avenue and Palmer Way • La Costa Avenue and Levante Street Village and Barrio Traffic Circles -Installation of traffic circles at intersections throughout the Village and Barrio is planned at a total cost of $1 .2 million. WATER/WASTEWATER PROJECTS The city's water and wastewater projects are vital to the continued health and welfare of its citizens. Most new lines are built and paid with impact fees collected with new development. As the city ages, it will become necessary to repair and replace the lines that already exist, and an increase in these projects is anticipated in future years. In the next five years, an additional $43.2 million in funding is scheduled for both new and replacement water and sewer projects. Vista/Carlsbad Interceptor & Agua Hedionda Lift Station Replacement-This project consists of a set of individual projects that will ultimately construct a parallel sewer interceptor system to accommodate existing and future sewer flows from the cities of Vista and Carlsbad. The individual projects include a main in Jefferson Street, replacement of the Agua Hedionda Lift Station, and a main from the lift station to the Encina Wastewater Facility. The overall total cost estimate for this set of projects totals $68 million, of which approximately 64 percent is funded by the City of Vista and 36 percent by the City of Carlsbad. Wastewater Other wastewater facilities scheduled for construction or replacement within the next five years include: • Buena Interceptor Sewer Improvements • Faraday/EI Camino Real Sewer Replacement • Foxes Landing Lift Station Wetwell and Pump Replacement Item 4; pg. 9 2016-17 PRELIMINARY CAPITAL IMPROVEMENT PROGRAM • Las Palmas Trunk Sewer • Marron Road • North Batiquitos • Quarry Creek Sewer Extension In addition to the new construction and replacement projects and ongoing condition assessments, repairs and upgrades to the city's wastewater facilities are expected to cost $3.5 million in the next five years. Water Lines Major water facilities scheduled for construction or replacement within the next five years are estimated at $38 million, and include the following locations: • Aviara Parkway and Plum Tree • Carlsbad Boulevard -South of Avenida Encinas • Carlsbad Boulevard-Terramar • Fire Flow System Improvements • La Costa High Reservoir Inlet Pipeline • Maerkle Pump Station Improvements and Transmission Main • Maerkle Reservoir Floating Cover Replacement • Santa Fe II Inlet Pipeline Recycled Water Expansion Expansion to the Carlsbad Water Recycling Facility, including construction of additional pipelines and a reservoir, are anticipated to cost $33 million. These facilities are expected to meet the 76 percent increase in future recycled water demand. The expansion is expected to increase the recycled water supply from 4 to up to 8 million gallons per day (mgd). With diminishing potable water resources available, alternative supplies such as recycled and desalinated water become increasingly important in supplementing the total water supply. DRAINAGE PROJECTS The city's drainage infrastructure plays an important role in handling storm water runoff flows, as well as maintaining the water quality of the city's creeks , lagoons and ocean. Carlsbad supports programs that will ensure that all water bodies within the city are safe and clean and, where possible, open to the public at all times. The system consists of drainage pipes 30-inches or larger in diameter, large concrete and rock lined channels, permanent sedimentation basins and miscellaneous large facilities. As the city continues to age, it will become necessary to repair and replace the lines that already exist. An additional $3.3 million will be added to the program in the next five years. Item 4; pg. 10 2016-17 PRELIMINARY CAPITAL IMPROVEMENT PROGRAM CAPITAL PROJECTS THROUGH FISCAL YEAR 2029-30 The CIP for FY 2016-17 to FY 2030-31 outlines approximately 235 projects at a cost of $463 million as shown below: CIP Projects -All Future Project Costs Project Type Percent Tota I Cost Stre ets/Ci rcu I a ti on 28% 128,648,553 Civic Projects 16% 75,224,860 Wastewater 21% 98,830,483 Parks 10% 45,229,920 Water 17% 79,482,800 Drainage 4% 17,603,507 Other (loans) 4% 18,180,162 Tota I Future 100% 463,200,285 OVERVIEW OF FY 2016-17 TO 2030-31 The spending plan includes $45.2, million, or 10 percent for future park development projects located within all four quadrants of the city. Approximately 28 percent of future expenditures, or $128.6 million, are planned for street and traffic signal construction projects. Projects include several road-widening projects, road diet and traffic calming projects, Carlsbad Boulevard Realignment, and funding for sidewalk construction, concrete repair work, ADA projects, and parking lot and pavement maintenance. Wastewater projects are expected to cost over $98.8 million, or 21 percent for numerous pipeline construction and rehabilitation projects, as well as improvements to the Encina Wastewater Treatment facility. Future water and recycled water projects include construction of new waterlines, both potable and recycled, and expansion of the Carlsbad Water Recycling Facility. Replacement of existing potable waterlines and reservoir improvements are also included in this category. A total of $79.5 million, or 17 percent of the total CIP, is planned for these projects. Construction and maintenance of civic facilities such as libraries, administrative buildings, and police and fire facilities are currently estimated at $75.2 million, or 16 percent of the total planned capital expenditures to build out. Drainage projects are 4 percent of the total spending plan, at $17.6 million and the remaining 4 percent, or $18.2 million are for loans and repayments. There are times when one fund will loan money to another fund to cover a temporary shortfall due to the timing of revenues and expenditures. UNFUNDED PROJECTS There are several projects identified in the CIP for which there is no identifiable funding source and, in some cases, where only partial funding has been identified. The city will investigate obtaining possible outside funding, such as federal and state grants, loans, or other financing sources. Once funding is identified for these projects, the project costs will have to be reviewed and updated to reflect actual cost estimates. The unfunded projects do not receive annual inflationary increases. Item 4; pg. 11 2016-17 PRELIMINARY CAPITAL IMPROVEMENT PROGRAM These projects are: • Agua Hedionda Channel (partial)* • Business Park Recreational Facility (partial) • Cannon Lake Park • Cannon Road -Reach 4B -Cannon Road/College Boulevard to City Limits (partial) • Carlsbad Boulevard Widening Mountain View to Northerly City Limits (partial)** • Carlsbad Boulevard/Palomar Airport Road Improvements (partial)** • Carlsbad Boulevard Realignment, Segments 3-5 • Hosp Grove/Buena Vista Lagoon Improvements • Pine Avenue Park-Madison Property Phase 2 • Robertson Ranch (NE Quadrant) Park Development (partial) (*) The Agua Hedionda Channel project is funded in part with Planned Local Drainage Area fees. The unfunded amount is listed in this section. (**) These projects are in the Traffic Impact Fee (TIF) program approved by the City Council on May 12, 2009, which was planned to generate enough revenue to pay for 20 percent of the total cost of these projects, the remaining 80 percent is unfunded. FUTURE GROWTH AND DEVELOPMENT There are a variety of revenues that are used to fund the capital projects. In order to estimate revenues received from development, several assumptions about the rate and type of future development need to be made. These assumptions can change from year-to-year and tend to correlate with the economic climate. Every year, city staff evaluates all existing and future private development projects and compares this information to the capacity of the city using adopted general plans. Information about existing development activity combined with estimates of how remaining net developable land might develop is then summarized to prepare future projections about when and where residential and non-residential development will occur. The following table shows the number of residential units and non-residential square feet of development used in calculating estimated revenues for FY 2016-17 and subsequent years to build out. Projected Development Residential and Non-Residential Construction Residential Non-Residential Year Units Square Feet 2016-17 755 601,098 2017-18 402 375,651 2018-19 189 208,732 2019-20 190 200,646 2020-21 135 190,796 2021-26 1,731 2,182,473 2027-buildout 2,252 3,300,889 Totals 5,654 7,060,285 Item 4; pg. 12 2016-17 PRELIMINARY CAPITAL IMPROVEMENT PROGRAM Finance Department staff prepare financial forecasting schedules to ensure that funding will be sufficient for construction of capital projects as planned in the CIP. In addition to evaluating whether or not capital funds are sufficient, significant operating cost impacts and availability of staff resources are also considered in evaluating the timing of projects. Where funding discrepancies occur, alternative financing methods and project timing are again evaluated and recommendations are made to resolve the discrepancies. About 5,600 residential units are anticipated for future development, and it is currently estimated that the city is about 90 percent built out. Future development estimates increased over the prior fiscal year estimates, because in FY 2015-16 the updated General Plan added units to meet the housing element requirements of the city. Residential development for FY 2016-17 is projected at 755 units, and, over the next five years should average 334 units per year. The amount of non- residential development is projected at about 1.6 million square feet over the next five years, a decrease of 600,000 square feet from the prior five year period. Projects include several neighborhood commercial/retail developments, a winery and culinary center, hotels and timeshares, and other office and mixed use projects. Development estimates provide data for estimating future fee revenues, which are calculated by multiplying each applicable development fee by the estimated number of dwelling units and/or square feet of construction expected during each year. REVENUES Over the next 15 years, revenues for Capital Projects are an estimated $570 million and are segregated into five major funding sources: (1) fees generated by development in Carlsbad, (2) special district fees and taxes (Community Facilities Districts and Bridge and Thoroughfare Benefit Districts), (3) water and wastewater replacement funds, (4) infrastructure replacement funds (other than wastewater and water), and (5) other sources, including grants, bond issues, and contributions from other agencies. Capital Improvement Program Revenues FY2016-17 to FY2030-31 Other Agencies 16% Infrastructure Replacement Transfers 26% $642.8 million Developer Fees 25% Utility Replacement Transfers 30% Financing Districts 5% Item 4; pg. 13 2016-17 PRELIMINARY CAPITAL IMPROVEMENT PROGRAM Approximately 25 percent of all capital revenue is received as a result of development, and is dependent upon assumptions made about the city's annual growth in dwelling units and commercial/industrial square feet. Development revenues include Public Facilities Fees (PFF), Traffic Impact Fees (TIF), Park-In-Lieu Fees (PIL), Planned Local Drainage (PLD) Fees, Water Connection Fees (MFF), and Sewer Connection charges. Revenue from special districts, such as Community Facilities Districts (CFD) and Bridge and Thoroughfare Benefit Districts (BTD) comprise 4 percent of the total. Water and wastewater replacement revenues generated by user fees equal approximately 30 percent of total revenues, and are used to pay for replacement of existing water and sewer facilities. Infrastructure replacement revenues, equal to 28 percent, are transfers from the city's General Fund, which are being set aside to pay for replacement of major capital facilities other than wastewater and water facilities. The remaining 17 percent consists of revenues from other agencies and include federal and state grants, the county sales tax program (TransNet) and contributions from cities, developers, and other agencies. CALCULATION OF FUTURE FEES The revenue projections in the Capital Improvement Program reflect the growth assumptions identified in the previous section. The following information delineates how those assumptions were applied to estimate future development revenues. The mix of multi-family and single-family residential units is assumed to be 35 percent and 65 percent, respectively, and reflects the anticipated mix of residential development for each Local Facilities Management Zone. The building permit valuation used for computing Public Facilities Fees is $198,400 per multi-family dwelling unit, and $366,800 per single-family dwelling unit. A building permit valuation of $51 per square foot of construction is used to calculate non-residential Public Facilities Fees. In order to calculate estimated revenues for Traffic Impact Fees, the number of average daily trips was computed for each type of development use. An attached multi-family residential dwelling unit is assigned either eight or six trips and a detached single-family unit is assigned 10 trips per day. The trips-per-day value for commercial and industrial buildings are 40 and eight trips per 1,000 square feet of development, respectively, although the actual volume of trips generated by commercial/industrial building can vary widely depending on the ultimate land use. Community Facilities District No. 1 is a citywide district established to finance various civic facilities required under the city's Growth Management Plan. CFD No. 3 was established for the Faraday Avenue and Melrose Drive Extensions east of El Camino Real, as well as the extension of El Fuerte. Park-in-Lieu Fees are collected for the purchase and development of parkland within each quadrant of the city, and the fees are based on the acquisition cost of parkland. Projects in the CIP funded with Park-in-Lieu Fees include future park site acquisition, development and restoration. Bridge and Thoroughfare Fee Districts are formed by property owners to finance specific road construction projects located within the district boundaries. Poinsettia Lane -Aviara Parkway (BTD No. 2) was formed to finance the construction of Poinsettia Lane between Aviara Parkway and El Camino Real and Aviara Parkway between Palomar Airport Road and Poinsettia Lane. Item 4; pg. 14 2016-17 PRELIMINARY CAPITAL IMPROVEMENT PROGRAM SUMMARY The FY 2016-17 CIP is being driven by the city's commitment to ensure that facilities are available to serve the developing areas as well as the current residents. Carlsbad's philosophy has been to build quality capital facilities, which meet and, at times, exceed Growth Management standards, in addition to reflecting the needs and wants of all who live, work and play in Carlsbad. Phasing projects over a period of years to match funding availability for construction and operations is often used to meet the needs of growth management. The FY 2016-17 Capital Improvement Program reflects the commitment of Carlsbad's City Council and staff to continue providing its residents with a better quality of life. GROWTH MANAGEMENT PLAN The Growth Management Plan was developed and voted into law by the citizens of Carlsbad in 1986. The plan was established to manage development within the city by linking residential, commercial, and industrial development directly to standards for availability of public services and facilities. The Growth Management Plan has established precise standards for 11 public facilities. Standards must be met at all times as growth occurs. Facilities for which standards have been established are as follows: -City Administrative -Library -Wastewater Treatment -Parks -Circulation -Drainage -Fire -Open Space -Schools -Sewer Collection -Water Distribution The plan requires that appropriate public facilities be available, in conformance with the adopted performance standards, as development occurs. Unless all of the 11 public facility standards have been met, no new development can occur. The Growth Management Plan impacts both the Operating Budget and the Capital Improvement Program. The detailed level of planning required by Growth Management has allowed Carlsbad's Capital Improvement Program to anticipate the funding needed for capital improvements in the next 15 years. The timing of construction of facilities is governed by the rate of development and the 11 performance standards. New public facilities often require additional staffing and other resources, which affects the Operating Budget. Facilities such as community centers, parks, and fire stations have been constructed and opened to the public under this program. The Capital Improvement Program has been designed to specifically address areas where new or expanded facilities will be needed to maintain compliance with the adopted performance standards. With the adoption of the FY 2016-17 CIP, compliance with the Growth Management Plan is continued. Item 4; pg. 15 PROJ. 10 ---40081 35721 35724 35722 35723 ------40131 40132 ~ 40141 40151 ------40161 40171 ~ 40191 --- ---40701 40601 40031 47151 47152 ------__!:!L NA NA 40201 ~ --- ---3B661 NEW ------__!:!L NA --- 47171 38961 NEW NEW 471B1 47251 47191 47192 47201 47211 ~ 47141 NA 47081 47091 NEW 47221 47231 47241 ~ PROJECT TITLE CIVIC PROJECTS ADMINISTRATIVE FACILITIES CIVIC CENTER MAINTENANCE AND OPERATIONS CENTER MAINTENANCE AND OPERATIONS CENTER-ART MAINTENANCE AND OPERATIONS CENTER MAINTENANCE AND OPERATIONS CENTER DOWNTOWN AREA PROJECTS BARRIO STREET LIGHTING BARRIO STREET LIGHTING VILLAGE PUBLIC GATHERING SPACES STUDY VIllAGE AND BARRIO BIKE & PEDESTRIAN WAYFINDING VILLAGE AND BARRIO TRAFFIC CIRClES VILLAGE AND BARRIO TRAFFIC CIRCLES VILLAGE AND BARRIO TRAFFIC CIRCLES - VILLAGE DECORATIVE LIGHTING VILLAGE PARKING WAYFINDING VILLAGE SAFETY liGHTING VILLAGE AND BEACH STREfTSCAPE POLICE & FIRE FACILITIES CARLSBAD SAFfTY TRAINING FACilllY-FIREARMS RANGE NOISE MITIGATION FIRE STATION NO.2 FEASIBILITY STUDY FIRE STATION NO.3 RELOCATION SAFETY CENTER IMPROVEMENTS SAFETY CENTER IMPROVEMENTS LIBRARY FACILITIES COLE LIBRARY EXPANSION COLE LIBRARY EXPANSION COLE LIBRARY EXPANSION (BROWNLEY DONATION) COLE LIBRARY IMPROVEMENTS (INCLUDES IRF FUNDING) DOVE LIBRARY IMPROVEMENTS (INCLUDES IRF FUNDING) TRAILS LAKE CALAVERA TRAILS MASTER PLAN/CONSTRUCTION (PROP C) TRAIL CONNECTIVITY TO TAMARACK STATE BEACH (PROP C) MISCELLANEOUS CITYWIDE PROJECTS CFD#l ADMINISTRATION OPEN SPACE AND TRAILS (PROP C) SUBTOTAL CIVIC PROJECTS FACILITIES MAINTENANCE AVIARA COMMUNilY PARK SOCCER FIELD SYNTHfTICTURF REPLACEMENT BEACH ACCESS REPAIR/UPGRADES CANNON PARK RESTROOM CITY FACILITY ACCESSIBILITY UPGRADES CITY HALL COMPLEX REFURBISHMENT CITY HAll EffiRIOR REFURBISHMENT EMERGENCY CENTER RECONFIGURATION EMERGENCY CENTER RECONFIGURATION FARADAY REHABILITATION FIRE STATION N0.1 REFURBISHMENT FIRE STATION NO.2 REFURBISHMENT FLEfT MAINTENANCE REFURBISHMENT FUTURE FACILITIES MAINTENANCE PROJECTS HARDING CENTER REFURBISHMENT HOLIDAY PARK FACILITIES MAINTENANCE HOSP GROVE PARK IMPROVEMENTS MAERKLE RESERVOIR SOLAR PROJECT MISCEllANEOUS BUILDING IMPROVEMENTS MONROE STREET POOL REPLACEMENT OCEAN STREff RESTROOM FY 2016-17 TO 2030-31 PRELIMINARY CAPITAL IMPROVEMENT PROGRAM FUND CFD#l CFD#l CFD#l WATERREPL SEWERREPL GCC OTHER GCC GCC GCC TRANSNET-LOC SEWERREPL GCC GCC GCC GCC GCC GCC PFF IRF GCC CFDIIl PFF GCC GCC GCC GCC GCC CFD#l GCC IRF IRF GCC GCC IRF GCC GCC IRF IRF IRF IRF IRF IRF IRF IRF IRF GCC IRF IRF GCC TOTAL COST 30 567,000 17,861,264 143,000 7 674,000 4,113,000 760,000 137,500 345,000 250,000 315,000 1,025,000 160,000 177,800 105,000 234,678 635,000 350,500 50,000 9,352,000 1,400,000 2,013 500 5,645,000 11,250,000 1,000,000 5,300,000 6,046,119 1,063,250 200,000 440 000 3,714,760 112,328,371 868,000 767,500 600,000 300,000 919,000 2,250,000 1,658,000 200,000 939,000 150,000 375,000 975,000 14,000,000 115,000 50,000 848,000 250,000 2,500,000 350,000 652,000 PRIOR EXP/ENC 424 4,542,224 5,000 81,750 75,975 37,453 146,515 68,312 233,3B8 507,BB4 26,000 6,698 8,B46,117 954 5,072,019 4,839,359 709,593 25,199,665 798,693 341,795 3,264 530 213,016 108,038 26,5BS 24,3B8 110,474 4,500 300 103,355 BALANCE FORWARD 99,576 13,319,040 143,000 7,674,000 4,108,000 100 000 55,750 174 025 277,547 31,285 36,688 1290 127,116 324,500 43,302 505,883 1,399,046 2,013,500 227,981 1,206,760 163,657 32,031,946 69,307 175,705 919,000 2,246,736 1657,470 200 000 725 984 41,962 348,415 950 612 4,526 45,500 249,700 146,645 100 000 YEAR 1 2016-17 50,000 660,000 345,000 145,000 40,000 190,000 200,000 110,000 3,714,760 5,454,760 250,000 600,000 100,000 84B,OOO 150,000 250,000 652,000 YEAR 2 2017-18 440,000 60,000 110,000 610,000 100,000 1,000,000 150,000 YEAR 3 2018-19 440,000 60,000 110,000 610,000 100,000 1,000,000 150,000 YEAR4 2019-20 110,000 110,000 1,000,000 150,000 YEARS 2020-21 1,000,000 150,000 YEAR 6-10 2022-26 30,417,000 30,417,000 5,000,000 750,000 YEAR 11-15 2027-31 5,645,000 11,250,000 1,000,000 17,895,000 5,000,000 750,000 Item 4; pg. 16 I PROJ. ID ~ ~ NEW 47111 ---NA ~ 46031 46032 46033 ~ --- ---46011 38011 --- ---~ 46041 46042 46061 36491 46001 46051 46052 --- ---38372 39252 ~ ~ 46021 46023 46022 NA NA 66091 ~ NA 33381 ~ NA 66171 NA ~ NA NA 36363 NA ~ NA NA NA 39192 NA ~ ~ ~ PROJECT TITLE PARKS ElECTRONIC SCOREBOARD REPLACEMENTS PINE AVENUE PARK SYNTHETIC TURF REPLACEMENT SAFETY TRAINING CENTER WATER RECIRCULATING SYSTEM STUDY SENIOR CENTER CONFERENCE ROOM REFURBISHMENT SUBTOTAL FACILITIES MAINTENANCE PARK DEVELOPMENT PROJECTS NORTHWEST QUADRANT PARKS BUSINESS PARK RECREATIONAL FACllllY (PARTIAL FUNDING) OUTDOOR ADVENTURE PARK FEASIBilllY STUDY PINE AVENUE PARK -PHASE 2(COMMUNI1Y FACllllY AND GARDEN AREAS) PINE AVENUE PARK -PHASE 2 (COMMUNITY FACILITY AND GARDEN AREAS) PINE AVENUE PARK -PHASE 2 (COMMUNITY FACILITY AND GARDEN AREAS)-ART VETERAN'S MEMORIAL PARK (All QUADRANTS) NORTHEAST QUADRANT PARKS CALAVERA PARK GATEWAY IMPROVEMENTS ROBERTSON RANCH PARK DEVELOPMENT {PARTIAL FUNDING) SOUTHWEST QUADRANT PARKS AVIARA COMMUNITY PARK AVIARA COMMUNITY PARK AMPHITHEATER AND PICNIC AREAS AVIARA COMMUNI1Y PARK AMPHITHEATER AND PICNIC AREAS· ART AVIARA COMMUNITY PARK WARMING KITCHEN AND RESTROOM AVIARA REIMBURSEMENT AGREEMENT MULTI-USE, MULTIGENERATIONALINDOOR COMMUNilY CENTER (STUDY) POINSffiiA COMMUNITY PARK-PHASE 3 POINSffiiA COMMUNITY PARK-PHASE 3-ART SOUTHEAST QUADRANT PARKS ALGA NORTE PARK-PHASE 1 PARK ALGA NORTE PARK· PHASE 1 (PROP C FUNDS) ~~G~ ~IGR+e PORK PII~~E;;!; 'lG' NQR+EP'RK Pli'<E2(PRQP£FY~JQ<) lEO CARRillO PARK-PHASE 3 LEO CARRillO PARK· PHASE 3-ART LEO CARRILLO PARK-PHASE 3 SUBTOTAL PARK PROJEGS DRAINAGE PROJECTS AGUA HEDIONDA CREEK STORM DRAIN OUTFALL(FAROL COURT) BUENA VISTA CREEK CHANNEL FENCING CMP REPlACEMENT PROGRAM DMP FACILITY AAA (JEFFERSON STREET) DMP FACILITY AAAA (MADISON STREET) DMP FACILITY AC (HIGHLAND DRIVE) DMP FACILITY AFA (HIDDEN VAllEY DRAINAGE RESTORATION) DMP FACILITY AFB (CALAVERA HILLS DRAINAGE RESTORATION) DMP FACILITY B & BN (AGUA HEDIONDA AND CALAVERA CREEK PLDA "B") DMP WETLAND CREATION OMP FACILITY BB 1 and 2 (WASHINGTON STREET) OMP FACILITY BCA (PARK DRIVE AND TAMARACK AVENUE PLOA "B") DMP FACllllY BCB (MAGNOLIA AVENUE) DMP FACILITY BFA (COUNTRY STORE) DMP FACllllY BFB-l & BFB-1 (TAMARACK ANDEl CAMINO REAL PLDA "B") DMP FACllllY BFB-U (El CAMINO REAL) DMP FACILITY BJ B, BNB AND BJ-1 (COLLEGE BOULEVARD/CANNON ROAD) DMP FACILITY BL·L (COLLEGE BLVD. BRIDGE REI MS. PLOA "B") DMP FACILITY BL-U (COLLEGE BOULEVARD) DMP FACllllY BM (CANTARINI/COLLEGE BOULEVARD BOX CULVERT) DMP FACllllY BQ (SUNNY CREEK) OMP FACILITY BR (CANTARINI/COLLEGE BOULEVARD PIPE DRAINAGE) OMP FACILITY Cl· CARLSBAD BOULEVARD ENCINAS CREEK BRIDGE PLDA "C") DMP FACllllY C2 (PASEO DEL NORTE) OMP FACILITY CA (AVENIDA ENCINAS) DMP FACllllY DBA (POINSETTIA VILLAGE) DMP FACILITY DBB (AVENIDA ENCINAS) FY 2016-17 TO 2030-31 PRELIMINARY CAPITAL IMPROVEMENT PROGRAM TOTAL PRIOR BALANCE YEAR 1 YEAR 2 YEAR 3 YEAR4 YEAR 5 YEAR 6-10 YEAR 11-15 FUND COST EXP/ENC FORWARD 2016-17 2017-18 2018-19 2019-20 2020-21 2022-26 2027-31 IRF 60,100 60,100 IRF 868,000 868,000 GCC 50,000 50,000 IRF 52,000 52,000 29,796,600 1,786,938 7,881,562 3,828,100 1,250,000 1,250,000 1,150,000 1,150,000 5,750,000 5,750,000 ZONES 4,486,000 4,486,000 GCC 122,500 62,419 60,081 Pll-NW 1,957,000 39,428 1,917,572 PFF 9,043,000 1,072,504 7,270,496 700,000 PFF 110,000 256 102 744 7,000 CFD#1 23,240,000 23,240,000 GCC 582,500 25,216 557,284 Pll-NE 2,700,000 200,000 2,500,000 PFF 0 Pll-SW 2,830,500 281,475 2,479,025 70,000 Pll·SW 31,300 3,168 27,432 700 PFF 300,000 300,000 Pll-SW 238,000 18,900 219,100 GCC 90,000 63,362 26 638 PFF 17,518,500 273,314 3,576,686 472,000 13,196,500 PFF 43 225 2,206 36,294 4,725 PFF 22,107,512 22,107,512 GCC 7,804,216 7,089,822 714 394 = g = 6+6;498 676,498 PFF 1,406,500 159,148 897,852 349,500 PFF 23,655 20,160 3,495 Pll-SE 959,100 814 958,286 96,270,006 31,876,042 19,164,044 1,807,420 13,196,500 30,226,000 IRF 596,700 216,977 379,723 GCC 200,000 28,884 171,116 IRF 2,859,360 2,080,659 778,701 PLD 289,534 289,534 PLD 416,500 416,500 PLD 921,408 921,408 PLD 91,608 91,608 PLD 163,164 163,164 PLD 3,643,066 3,452,476 190,590 PLD 955,000 685,000 270,000 PLD 1,086,065 1,086,065 PLD 1,068,613 1,481 1,067,132 PLD 468,096 468,096 PLD 963,673 963,673 PLD 904,329 904,329 PLD 138,220 138,220 PLD 2,761,644 2,249,448 512,196 PLD 1,816,101 1,816,101 PLD 384,509 384,509 PLD 204,077 204,077 PLD 131,355 131,355 PLD 180,773 180,773 PLD 2,539,565 2,371,227 168,338 PLD 727,730 727,730 PLD 529,402 529,402 PLD 167,215 167,215 PLD 429,108 429,108 Item 4; pg. 17 FY 2016-17 TO 2030-31 PRELIMINARY CAPITAL IMPROVEMENT PROGRAM I PROJ. TOTAL PRIOR BALANCE YEAR 1 YEAR 2 YEAR3 YEAR4 YEARS YEAR 6-10 YEAR 11-1S ID PROJECT TITLE FUND COST EXP/ENC FORWARD 2016-17 2017-18 2018-19 2019-20 2020-21 2022-26 2027-31 ~ DMP FACILITY DFA (BATIQUITOS LAGOON STORMWATER TREATMENn PLD 2S6,423 2S6,423 NA DMP FACILITY DH (ALTIVE PLACE CANYON RESTORATION) PLD 232,812 232,812 NA DMP FACILITY DQB (LA COSTA TOWN CENTER) PLD 74S,842 74S,842 NA DMP FACILITY DZ {POINSETTIA LANE) PLD 642,063 642,D63 NEW DRAINAGE MASTER PLAN UPDATE PLD 7SD,ODO 7SO,OOO 66161 FIRE STATION DRAINAGE IMPROVEMENTS GCC 22S,OOO 22S,OOO NEW HEADWALL REPLACEMENT PROGRAM IRF S10,000 S10,000 66061 KELLY DRIVE CHANNEL REPAIR IRF 1,161,000 312,896 848,104 NA KELLY DRIVE CHANNEL REPLACEMENT IRF 1,992,000 1,992,000 66021 LA COSTA AVENUE DRAINAGE IMPROVEMENTS IRF 492,1SO 18S,308 306,842 NEW LAGUNA DRIVE STORM DRAIN GAS TAX 370,000 370,000 NEW LAKE CALAVERA STORM DRAIN IMPROVEMENTS GCC 236,SOO 236,SOO 66141 MARCA PLACE DRAINAGE IMPROVEMENTS GAS TAX 6S,OOO 1,071 63,929 66082 NW QUADRANT STORM DRAIN IMPROVEMENT PROGRAM GAS TAX 6,090,S90 4,744,420 1,346,170 66111 PARK DRIVE DRAINAGE AND STREET IMPROVEMENTS GCC 243,000 60,1SS 182,84S 66042 ROMERIA DRAINAGE IMPROVEMENTS GAS TAX 348,000 337,2S7 10,743 66041 ROMERIA DRAINAGE IMPROVEMENTS GCC 299,000 293,770 S,230 66201 STORM DRAIN CONDITION ASSESSMENT IRF 1,000,000 33,236 66,764 100,000 100,000 100,000 100,000 100,000 400,000 SUBTOTAL DRAINAGE PROJECTS 40,296,19S 16,369,26S 6,323,423 2,419,720 740,000 100,000 100,000 100,000 4,208,101 9,93S,686 SEWER PROJECTS ENCINA WATER POLLUTION CONTROL FACILITY ---S8011 ENCINA CAPITAL PROJECTS SEWER REPL 93,389,9S8 12,982,780 S,080,440 3,121,112 4,2S8,483 4,114,2SS 4,438,S86 9,821,078 23,S60,79S 26,012,429 SEWER COLLECTION SYSTEM ---SS171 BATIQUITOS LIFT STATION PUMP REPLACEMENT SEWER REPL 90S,OOO 878,700 26,300 SS181 BUENA INTERCEPTOR REHAB AT ENCINA PLANT (REIMB) SEWER REPL 100,000 100,000 SS371 BUENA INTERCEPTOR SEWER ACCESS ROAD IMPROVEMENTS SEWER REPL 2SO,OOO 2SO,OOO SS011 BUENA INTERCEPTOR SEWER IMPROVEMENTS SEWER REPL 3,326,000 227,701 1,134,299 1,964,000 SS012 BUENA INTERCEPTOR SEWER IMPROVEMENTS SEWER CONN soo,ooo 173,200 326,800 ~ BUENA INTERCEPTOR SEWER REALIGNMENT-EAST SEGMENT SEWER REPL 1,987,000 S07,000 1,480,000 SS381 CHINQUAPIN LIFT STATION FORCE MAIN OUTFALL REALIGNMENT SEWER REPL 212,000 60,000 1S2,000 SS401 FARADAY & EL CAMINO REAL SEWER REPLACEMENT-ORION TO PAR SEWER CONN 1,S40,000 140,000 1,400,000 SS191 FLOW METER REPLACEMENTS SEWER REPL 1SO,OOO 44,691 10S,309 SS261 FOXES LANDING LIFT STATION WElWELLAND PUMP REPLACEMENT SEWER REPL 4,100,000 419,472 2,8S0,983 829,S4S SS281 GATESHEAD LIFT STATION REMOVAL SEWER REPL 1SO,OOO 1SO,OOO SS091 HOME PLANT PIPELINE AND LIFT STATION REPLACEMENT SEWER REPL 4,139,000 4,068,822 70,178 SS401 LAS PALM AS TRUNK SEWER SEWER CONN 2,420,000 430,000 1,990,000 3S371 NORTH AGUA HEDIONDA INTERCEPTOR-WEST SEGMENT SEWER REPL S,8S4,000 S,321,991 S32,009 NA NORTH BATIQUITOS INTERCEPTOR SEWER ACCESS ROAD IMPROVEMENTS SEWER REPL 2SO,OOO 2SO,OOO SS361 NORTH BATIQUITOS LIFT STATION FORCE MAIN REHABILITATION SEWER REPL sso,ooo 966 S49,034 SS311 NORTHWEST QUADRANT CIPP SEWER REHABILITATION SEWER REPL 700,000 473 699,S27 SS221 OCCIDENTAL SEWER IMPROVEMENTS SEWER REPL 849,000 691,686 1S7,314 SS201 ODOR AND CORROSION PREVENTION ASSESSMENT SEWER REPL 200,000 16,294 183,706 SS291 POINSETTIA LANE LIFT STATION EMERGENCY OVERFLOW BASIN SEWER REPL 1,200,000 11S,713 1,084,287 NA QUARRY CREEK SEWER EXTENSION (SBA "A"-REIMB. AGREEMENn OTHER S67,000 S67,000 NEW SCADA INTEGRATED MASTER PLAN SEWERREPL 80,000 80,000 SS301 SEWER EASEMENT ACCESS PROGRAM SEWERREPl 400,000 263 399,737 38401 SEWER LIFT STATION REPAIRS AND UPGRADES SEWERREPL 4,010,380 1,499,288 261,092 1SO,OOO 1SO,OOO 1SO,OOO 1SO,OOO 1SO,OOO 7SO,OOO 7SO,OOO SS131 SEWER LINE CONDITION ASSESSMENT SEWER REPl 2,633,000 67,396 S6S,604 200,000 200,000 200,000 200,000 200,000 soo,ooo soo,ooo SS031 SEWER LINE REFURBISHMENTS AND REPLACEMENT SEWERREPL 9,107,896 2,78S,346 1,372,SSO 330,000 330,000 330,000 330,000 330,000 1,6SO,OOO 1,6SO,OOO SS041 SEWER MONITORING PROGRAM SEWER CONN 6S6,000 204,627 121,373 22,000 22,000 22,000 22,000 22,000 110,000 110,000 SS331 SIMSBURY SEWER EXTENSION SEWER REPL 301,000 S7,740 243,260 SS241 TAMARACK SEWER RELOCATION AT RAILROAD RIGHT-OF-WAY SEWER REPl 2S2,000 2S2,000 SS341 TERRAMAR SEWER REPLACEMENT-EL ARBOL AND LOS ROBLES SEWER REPL 1,2SO,OOO 1,2SO,OOO SS1S1 VANCOUVER SEWER EXTENSION SEWER REPl 1,006,000 983,9SS 22,04S ~ VISTA CARLSBAD INTERCEPTER-REHABILITATION (VCl & VC2) SEWER REPL 141,000 20,000 121,000 34921 VISTA CARLSBAD INTERCEPTOR-AGUA HEDIONDA LS & FORCE MAIN (VC12-VC13) SEWER CONN 29,6SO,OOO 28,989,918 210,082 4SO,OOO SS082 VISTA CARLSBAD INTERCEPTOR-BUENA VISTA LIFT STATION & FORCE MAIN (VC-4) SEWER CONN S,72S,OOO 4,778,623 946,377 SS3S1 VISTA CARLSBAD INTERCEPTOR-BUENA VISTA LIFT STATION IMPROVEMENTS SEWER CONN 1,12S,OOO S99 149,401 22S,OOO 7SO,OOO 38861 VISTA CARLSBAD INTERCEPTOR -LAGOON BRIDGE REPLACEMENT (VCllB) SEWER CONN 8,S80,000 8,404,267 2S,733 1SO,OOO 39491 VISTA CARLSBAD INTERCEPTOR-REACH VC14 TO VClS SEWER CONN 20,200,000 19,847,28S 1S2,71S 200,000 39S01 VISTA CARLSBAD INTERCEPTOR-REACH VC3 SEWER CONN 2,688,200 S96,200 2,092,000 NEW WATER, RECYCLED, AND SEWER MASTER PLAN SEWER REPL 1SO,OOO 1SO,OOO SUBTOTAL SEWER PROJECTS 211,294,434 92,S61,796 19,902,1SS 8,616,6S7 7,694,483 7,690,45S 8,712,586 10,S23,078 26,S70,79S 29,022,429 WATER DISTRIBUTION SYSTEM NA AVIARA PARI<:WAY AND PLUM TREE WATERLINE WATER REPL 81S,OOO 81S,OOO Item 4; pg. 18 FY 2016-17 TO 2030-31 PRELIMINARY CAPITAL IMPROVEMENT PROGRAM I PROJ. TOTAL PRIOR BALANCE YEAR 1 YEAR2 YEAR 3 YEAR4 YEARS YEAR 6-10 YEAR 11-15 ID PROJECT TITLE FUND COST EXP/ENC FORWARD 2016-17 2017-18 2018-19 2019-20 2020-21 2022-26 2027-31 50421 BUENA VISTA PUMP STATION AND FOREBAY REMOVAL WATER REPL 150,000 150,000 ~ CARLSBAD BOULEVARD~ SOUTH OF AVENIDA ENCINAS WATER REPL 950,000 280,000 670,000 NEW CARLSBAD BOULEVARD WATERLINE REPLACEMENT ATTERRAMAR WATERREPL 1,930,000 1,930,000 50071 CATHODIC PROTECTION PROGRAM WATERREPL 1,246,702 169,688 1,077,014 50131 COLLEGE BOULEVARD~ CANNON ROAD TO BADGER LANE (375 ZONE) WATER CONN 1,060,000 183 1,059,817 50121 COLLEGE BOULEVARD-CANNON ROAD TO BADGER LANE (490 ZONE) WATER CONN 1,090,000 1,090,000 50331 CRESlVIEW DRIVE TRANSMISSION MAIN WATER REPL 240,000 240,000 50381 DESALINATED WATER FLOW CONTROL FACILITY WATER CONN 1,104,300 29,281 1,075,019 50391 E TANK DECOMMISSION (THE CROSSINGS ROAD) WATER REPL 300,000 150,000 150,000 50341 EL FUERTE AND CORINTIA STREET PRESSURE REDUCING STATION WATER REPL 800,000 800,000 50401 ELLERY PUMP STATION DECOMMISSION WATER REPL 250,000 200,294 49,706 50411 ELLERY WATER PUMP PROJECT WATER REPL 275,000 275,000 50431 FIRE FLOW SYSTEM IMPROVEMENTS WATER REPL 2,809,000 720,000 720,000 90,000 90,000 90,000 90,000 1,009,000 50251 HYDROELECTRIC GENERATOR AT MAERKLE RESERVOIR WATER REPL 2,000,000 1,971,438 28,562 NA HYDROELECTRIC GENERATOR AT PALOMAR AIRPORT ROAD/WHITE SANDS WATER REPL 2,160,000 85,000 2,075,000 50291 KELLY RANCH DOMESTIC WATER PRESSURE REDUCING STATION WATER REPL 560,000 560,000 NA LA COSTA HIGH RESERVOIR INLET PIPELINE WATER REPL 2,150,000 250,000 1,900,000 NEW LAKE CALAVERA MITIGATION WATER REPL 275,000 275,000 50351 LIMITED ACCESS PIPELINE RELOCATION PROGRAM WATER REPL 1,940,000 30,450 1,909,550 50091 MAERKLE FACILilY IMPROVEMENTS WATER REPL 2,135,200 1,132,242 1,002,958 50042 MAERKLE PUMP STATION IMPROVEMENTS WATER CONN 1,955,200 4,982 365,018 1,585,200 50361 MAERKLE RESERVOIR FLOATING COVER REPLACEMENT WATER REPL 13,055,000 1,332 1,268,668 8,730,000 3,055,000 50011 MAERKLE RESERVOIR TRANSMISSION MAIN WATER REPL 6,330,000 388,588 5,941,412 39041 MISCELLANEOUS PIPELINE REPLACEMENTS WATER REPL 11,433,000 347,658 1,085,342 1,000,000 1,000,000 1,000,000 1,000,000 3,000,000 3,000,000 NEW NORMALLY CLOSED VALVE (INSTALL MOTORIZED VALVE) WATERREPL 260,000 260,000 35311 OCEANSIDE WATER INTERTIE UPGRADE WATER REPL 115,000 115,000 ---50301 PARK DRIVE WATER LINE AND STREET IMPROVEMENTS WATER REPL 1,092,000 1,051,107 40,893 50451 POINSETTIA LANE-CASSIA ROAD TO SKIMMER COURT WATER CONN 300,000 300,000 50201 PRESSURE REDUCING STATION PROGRAM WATER REPL 1,102,000 370,199 731,801 NA RANCHO CARLSBAD GROUNDWATER SUPPLY WATER CONN 1,750,000 325,000 1,425,000 N/A RANCHO CARLSBAD GROUNDWATER SUPPLY WATER REPL 1,750,000 325,000 1,425,000 50241 RESERVOIR REPAIR AND MAINTENANCE PROGRAM WATER REPL 6,000,000 2,476,277 1,673,723 1,850,000 50371 ROBERTSON RANCH WATER TRANSMISSION MAIN WATERREPL 1,200,000 1,200,000 50441 SAN LUIS REV MISSION BASIN GROUNDWATER SUPPLY WATER CONN 8,527,500 27,500 8,500,000 50442 SAN LUIS REV MISSION BASIN GROUNDWATER SUPPLY WATERREPL 8,527,500 27,500 8,500,000 NA SANTA FE II INLET PIPELINE WATERREPL 2,838,000 470,000 2,368,000 50311 SANTA FE II RESERVOIR SITE DRAINAGE WATERREPL 645,000 491,431 153,569 50461 SANTA FE II RESERVOIR SITE ELECTRICAL IMPROVEMENTS WATERREPL 100,000 100,000 ~ SCADA INTEGRATED MASTER PLAN WATER REPL 360,000 360,000 50081 TRI-AGENCYWATER TRANSMISSION PIPELINE REPLACEMENT WATERREPL 6,455,000 1,976,805 4,478,195 NEW WATER CONDITION ASSESSMENT PROGRAM WATERREPL 2,000,000 200,000 200,000 200,000 200,000 200,000 500,000 500,000 50161 WATER MASTER PLAN UPDATE WATER CONN 700,000 586,412 113,588 50471 WATER SYSTEM INTERTIE CONNECTION WATERREPL 405,000 405,000 50191 WATER VALVE REPAIR/REPLACEMENT PROGRAM WATER REPL 13,600,002 532,353 317,649 1,250,000 1,250,000 1,250,000 1,250,000 1,250,000 3,250,000 3,250,000 NEW WATER, RECYCLED, AND SEWER MASTER PLAN WATERREPL 200,000 200,000 SUBTOTAL WATER DISTRIBUTION SYSTEM 114,940,404 11,760,720 28,417,484 15,660,200 5,710,000 4,105,000 5,828,000 4,525,000 12,334,000 26,600,000 RECYCLED WATER SYSTEM CARLSBAD WATER RECYCLING FACILilY (ENCINA CAPITAL PROJECTS) WATER REPL ---709,390 164,840 544,550 NEW CARLSBAD WATER RECYCLING FACILilY (ENCINA CAPITAL PROJECTS) RECL REPL 1,470,600 70,600 100,000 100,000 100,000 100,000 500,000 500,000 52051 ABANDON POTABLE SERVICES (NEW RECYCLED SERVICES) WATER REPL 560,000 49,690 340,310 170,000 52061 CWRF-CHLORINE CONTACTTANK COVERS WATER REPL 765,000 8,136 756,864 NA EL CAMINO REAL AND TAMARACK PUMP STATION REMOVAL WATER REPL 100,000 100,000 NEW RECYCLED WATER CONDITION ASSESSMENT PROGRAM RECL REPL 2,000,000 200,000 200,000 200,000 200,000 200,000 500,000 500,000 50271 RECYCLED WATER LINE-CWRFTO CHINQUAPIN WATER REPL 5,050,000 4,722,687 327,313 52071 RECYCLED WATER LINE-EL CAMINO REAL TO LA COSTA AVENUE WATER REPL 1,915,000 1,645,248 269,752 52092 RECYCLED WATER PHASE 3-CWRF EXPANSION RECLWATER 6,844,125 6,835,858 8,267 52091 RECYCLED WATER PHASE 3-CWRF EXPANSION WATER REPL 3,517,276 3,059,063 458,213 52082 RECYCLED WATER PHASE 3-PIPELINES RECLWATER 18,700,000 2,582,733 16,117,267 52081 RECYCLED WATER PHASE 3-PIPELINES WATER REPL 2,497,530 1,086,014 1,411,516 52102 RECYCLED WATER PHASE 3-RESERVOIR RECLWATER 1,500,000 16,405 1,483,595 52101 RECYCLED WATER PHASE 3-RESERVOIR WATER REPL 300,000 1,045 298,955 ~ RECYCLED WATER VALVE & APPURTENANCE REPLACEMENT PROGRAM RECL REPL 750,000 50,000 50,000 50,000 50,000 50,000 250,000 250,000 NEW SCADA INTEGRATED MASTER PLAN RECL REPL 80,000 80,000 NEW WATER, RECYCLED, AND SEWER MASTER PLAN RECL REPL 150,000 150,000 SUBTOTAL RECYCLED WATER PROJECTS 46,908,921 20,171,719 22,016,602 720,600 350,000 350,000 450,000 350,000 1,250,000 1,250,000 CIRCULATION SYSTEM Item 4; pg. 19 PROJ. ID --- NEW 63221 NEW ~ ~ NA 63251 NA 39021 63021 ---63031 NA ~ 63141 39381 NA ~ ~ 63201 63202 63203 NEW 60491 60041 NEW NEW 60301 60581 60583 60142 60143 60162 60163 60531 60532 60533 60631 NA NEW 60311 60312 60541 NA NA NA NA 45091 45081 NEW ~ ~ NEW NEW 36362 ~ 60132 60561 60421 ~ PROJECT TITLE TRAFFIC SIGNALS ADAPTIVE TRAFFIC SIGNAL PROGRAM PEDESTRIAN CROSSINGS-CARLSBAD BOULEVARD/VILLAGE SIGNAL OPERATIONS MODIFICATIONS TRAFFIC SIGNAL-ALGA ROAD AND CAZADERO DRIVE TRAFFIC SIGNAL-ARMADA DRIVE AND FLEET STREET SOUTH TRAFFIC SIGNAL-ARMADA DRIVE AND GRAND PACIFIC RESORTS TRAFFIC SIGNAL-CAMINO DE lOS COCHES AND LA COSTA AVENUE TRAFFIC SIGNAL-CAMINO VIDA ROBLE AND YARROW DRIVE TRAFFIC SIGNAL -CANNON ROAD AND AVENIDA ENCINAS (REIMBURSEMENT) TRAFFIC SIGNAL-EL CAMINO REAL AND CHESTNUT AVENUE SIGNAL REPAIRS TRAFFIC SIGNAL-El CAMINO REAL AND TAMARACK AVENUE SIGNAL REPAIRS TRAFFIC SIGNAL-EL FUERTE STREET AND RANCHO PANCHO TRAFFIC SIGNAL~ FARADAY AVENUE AND CAMINO HILLS DRIVE TRAFFIC SIGNAL-FARADAY AVENUE AND PALMER WAY TRAFFIC SIGNAL-LA COSTA AVENUE AND LEV ANTE STREET TRAFFIC SIGNAL-MONROE STREET AND HOSP WAY TRAFFIC SIGNAL-POINSETTIA LANE AND BRIGANTINE ROAD TRAFFIC SIGNAL-TAMARACK AVENUE AND VALLEY STREET TRAFFIC SIGNAL PROGRAM TRAFFIC SIGNAL PROGRAM TRAFFIC SIGNAL PROGRAM-FIBER OPTIC SUBTOTAl TRAFFIC SIGNAl PROJECTS STREET PROJECTS ACTIVE VILLAGE CAMPAIGN ADA BEACH ACCESS STUDY ADA IMPROVEMENT PROGRAM AVEN!DA ENCINAS WIDENING-SOUTH OF PALOMAR AIRPORT ROAD BRIDGE PREVENTITIVE MAINTENANCE PROGRAM BTD#3 RECONCILIATION AND CLOSEOUT CAMINO HilLS AND JACKSPAR DRIVE SlOPE STABILIZATION CARLSBAD BLVD AND TAMARACK AVENUE PEDESTRIAN IMPROVEMENTS CARLSBAD BLVD AND TAMARACK AVENUE PEDESTRIAN IMPROVEMENTS CARLSBAD BLVD AND TAMARACK AVENUE PEDESTRIAN IMPROVEMENTS CARlSBAD BLVD BRIDGE CONCRETE BARRIER POWER PlANT CARLSBAD BLVD BRIDGE CONCRETE BARRIER POWER PLANT (LOCAL MATCH) CARLSBAD BLVD BRIDGE CONCRETE BARRIER RAILROAD CARLSBAD BLVD BRIDGE CONCRETE BARRIER RAILROAD (LOCAL MATCH) CARLSBAD BLVD BRIDGE RAILING EAST SIDE AT POWER PLANT DISCHARGE CARLSBAD BLVD BRIDGE RAILING EAST SIDE AT POWER PLANT DISCHARGE CARLSBAD BLVD BRIDGE RAILING EAST SIDE AT POWER PlANT DISCHARGE CARLSBAD BLVD EMERGENCY REPAIR CARLSBAD BLVD MEDIAN-TAMARACK AVENUE TO PINE AVENUE CARLSBAD BLVD PEDESTRIAN LIGHTING-TAMARACK TO STATE STREET CARLSBAD BLVD REALIGNMENT CARLSBAD BLVD REALIGNMENT CARLSBAD BLVD REALIGNMENT-CANNON TO MANZANO CARLSBAD BLVD REALIGNMENT-CANNON TO MANZANO-PARK CARLSBAD BLVD REALIGNMENT-CANNON TO MANZANO CARLSBAD BLVD REALIGNMENT-CANNON TO MANZANO CARLSBAD BLVD REALIGNMENT/ PALOMAR AIRPORT ROAD {SEGMENT2) (20%) CARLSBAD BLVD REALIGNMENT/ PALOMAR AIRPORT ROAD (SEGMENT2) (RTCIP / CARLSBAD BLVD WIDENING MOUNTAIN VIEW TO NORTHERLY CITY LIMITS (20%) CARLSBAD BLVD WIDENING MOUNTAIN VIEW TO NORTHERLY CITY LIMITS (RTCIP/, CARLSBAD STATE BEACH BLUFF RESTORATION CARLSBAD STATE BEACH GREENWAY IMPROVEMENTS CARLSBAD VILlAGE DR. & GRAND AVE. PEDESTRIAN AND CROSSING IMP. CARLSBAD VILLAGE DRIVE WIDENING-PONTIAC DRIVE TO VICTORIA AVENUE CHESTNUT AVENUE ROAD DIET AND TRAFFIC CALMING CHESTNUT COMPLETE STREET 1-5 TO RAILROAD PROJECT STUDY CHRISTIANSEN AVENUE IMPROVEMENTS COLLEGE BLVD REACH A AND CANNON ROAD REACH 4A COMPLETE STREET AND TRAFFIC CALMING PROGRAM CONCRETE REPAIR/REPLACEMENT PROGRAM EL CAMINO REAL AND AGUA HEDIONDA CREEK BRIDGE RAILING & SIDEWALK EL CAMINO REAL AND CANNON ROAD INTERSECTION IMPROVEMENTS EL CAMINO REAL AND CARLSBAD VILLAGE DRIVE DUAL LEFT TURNS FY 2016-17 TO 2030-31 PRELIMINARY CAPITAL IMPROVEMENT PROGRAM FUND TRANSNET-lOC GAS TAX GAS TAX GAS TAX GAS TAX GAS TAX GAS TAX GAS TAX PFF IRF IRF GAS TAX GAS TAX GAS TAX GAS TAX GAS TAX GAS TAX GAS TAX GCC IRF GCC TRANSNET-lOC GCC TRANSNET-LOC TIF IRF BTD#3 GCC GAS TAX TDA TRANSNET/BIKE FED GRNT TRANSNET-LOC FED GRNT TRANSNET-LOC GCC TRANSNET-LOC FEDGRNT GAS TAX GAS TAX TRANSNET-LOC TRANSNET-LOC GCC TIF GCC TRANSNET-LOC SEWER REPL TIF TIF TIF TIF GCC GCC TRANSNET-LOC TIF TRANSNET-LOC TRANSNET-LOC TRANSNET-LOC OTHER GAS TAX GAS TAX IRF TIF TIF TOTAL COST 1,200,000 200,000 150,000 210,000 190,000 190,000 190,000 190,000 150,000 276,000 2DO,DOD 190,000 190,000 190,000 210,000 210,000 19D,ODD 190,000 912,000 4,772,974 229,750 10,430,724 271,211 75,000 1,670,000 5,346,750 1,500,000 125,000 859,400 1,653,900 192,100 1,104,000 1,294,751 206,570 728,592 543,155 338,455 16,923 130,622 841,000 2,605,000 1,325,000 3,000,000 250,000 3,050,000 999,999 1,000,000 350,000 879,000 3,470,000 927,000 1,201,000 499,830 400,000 1,320,000 2,924,000 1,080,000 85,000 310,000 1,713,000 1,500,000 5,750,000 210,000 2,049,000 1,067,000 PRIOR EXP/ENC 195,270 300 276,000 172,500 900,737 3,543,728 223,371 5,311,906 247,563 15,897 169,750 26,477 101,797 262,033 23,325 728,592 303,868 192,935 1,528,892 555,266 393,642 245,358 418,408 1,565,361 756,725 BALANCE FORWARD 4,730 190,000 149,700 27,500 11,263 1,229,246 6,379 1,618,818 23,648 734,103 832,923 1,552,103 192,100 634,333 92,809 239,287 338,455 16,923 130,622 648,065 1,471,108 250,000 5,494,734 106,188 154,642 1,294,592 434,639 210,000 92,275 YEAR 1 2016-17 1,200,000 150,000 190,000 1,540,000 75,000 250,000 350,000 125,000 1,104,000 398,385 90,436 610,000 (3,000,000) 999,999 1,000,000 350,000 85,000 300,000 250,000 1,200,000 YEAR2 2017-18 190,000 190,000 250,000 2,431,000 350,000 715,000 1,080,000 310,000 300,000 250,000 YEAR 3 2018-19 190,000 210,000 400,000 250,000 2,746,000 300,000 1,320,000 300,000 250,000 YEAR4 2019-20 0 170,000 300,000 300,000 250,000 YEARS 2020-21 0 200,000 300,000 250,000 YEAR 6-10 2022-26 210,000 190,000 190,000 210,000 190,000 190,000 1,180,000 1,250,000 1,067,000 YEAR 11-15 2027-31 190,000 190,000 2,605,000 879,000 3,470,000 927,000 1,201,000 2,924,000 1,250,000 Item 4; pg. 20 I PROJ. ID NA 60S01 36432 36431 NA NA ~ 60S11 ~ NEW 39S71 39S71 39S72 39S73 39S74 ~ ---NA 60241 ~ NA 60341 603S1 NEW 60281 ~ 60431 60441 60S21 60012 60011 60013 39221 NA NA 60S71 60S72 60S91 39071 60371 NEW NEW 60192 60191 60021 NEW 60621 60401 60031 60601 NEW 60611 NEW NA NA NA ~ NA NA NA NA PROJECT TITLE EL CAMINO REAl AND COLLEGE BLVD INTERSECTION IMPROVEMENTS EL CAMINO REAL LEFT TURN LANE TO WESTBOUND TAMARACK AVENUE EL CAMINO REAL MEDIANS El CAMINO REAL MEDIANS EL CAMINO REAL RIGHT TURN LANE TO EAST BOUND ALGA ROAD EL CAMINO REAL WIDENING -CASSIA RD TO CAMINO VIDA ROBLE EL CAMINO REAL WIDENING-ARENAL ROAD TO LA COSTA AVENUE EL CAMINO REAL WIDENING-ARENAL ROAD TO LA COSTA AVENUE (RTCIP) EL CAMINO REAL WIDENING-USA STREET TO CRESTVIEW DRIVE EL CAMINO REAL WIDENING-SUNNY CREEK TO JACKSPAR EL CAMINO REAL WIDENING-TAMARACK AVENUE TO CHESTNUT AVENUE EL CAMINO REAL WIDENING-TAMARACK AVENUE TO CHESTNUT AVENUE (RTCIP) EL CAMINO REAL WIDENING-TAMARACK AVENUE TO CHESTNUT AVENUE EL CAMINO REAL WIDENING-TAMARACK A VENUE TO CHESTNUT AVENUE EL CAMINO REAL WIDENING-TAMARACK AVENUE TO CHESTNUT AVENUE FACILITY SAFETY AND PARKING LOT LIGHTING ASSESSMENT KELLY DRIVE AND PARK DRIVE ROAD DIET AND MULTIUSE TRAIL LA COSTA AVENUE-TRAFFIC CALMING LA COSTA AVENUE SLOPE REPAIR WEST OF ROMERIA STREET LEFTTURN LANE EXTENSIONS MELROSE DRIVE AND ALGA ROAD DUAL LEFT TURN LANES (RTCIP) MELROSE DRIVE RIGHT TURN LANE TO WEST BOUND PALOMAR AIRPORT ROAD MUTCD STREET NAME SIGN REPLACEMENT PROGRAM OCEAN STREET RECONFIGURATION CONCEPTS STUDY PALOMAR AIRPORT ROAD AND COLLEGE BLVD IMPROVEMENTS PALOMAR AIRPORT ROAD/EL FUERTE STREET RIGHT TURN LANE PALOMAR AIRPORT ROAD/PASEO DEL NORTE LEFT TURN LANE PALOMAR AIRPORT ROAD/PASEO DEL NORTE RIGHTTURN LANE PARKING LOT MAINTENANCE PROGRAM PAVEMENT MANAGEMENT PROGRAM PAVEMENT MANAGEMENT PROGRAM PAVEMENT MANAGEMENT PROGRAM (NON-JURIS FEES) POINSETTIA LANE-REACH E CASSIA ROAD TO SKIMMER COURT POINSETTIA LANE-REACHES A,B,C,F,G & AVIARA PKWY REIMB POINSETTIA LANE WIDENING-PASEO DEL NORTE TO BATIQUITOS DRIVE (RTCIP) PUBLIC BEACH ACCESS IMPROVEMENTS PUBLIC BEACH ACCESS IMPROVEMENTS RAILROAD DOUBLE TRACKING RANCHO SANTA FE ROAD NORTH-PHASE II (BRIDGE) RETROREFLECTIVITY SIGN REPLACEMENT PROGRAM ROADWAY IMPROVEMENTS-COASTAL AREA ANALYSIS & IMPLEMENTATION ROADWAY SLOPE STABILIZATION SIDEWALK/STREET CONSTRUCTION-VALLEY STREET MAGNOLIA AVENUE SIDEWALK/STREET CONSTRUCTION-VALLEY STREET MAGNOLIA AVENUE SIDEWALK/STREET CONSTRUCTION PROGRAM STATE STREET IMPROVEMENTS AT NW CORNER OF GRAND STREET LIGHTING REPLACEMENT PROGRAM TRAFFIC IMPACT FEE UPDATE TRAFFIC MONITORING PROGRAM TRAILS ROADWAY CROSSINGS {CATS) UTILITY UNDERGROUNDING PROGRAM STUDY WAYFINDING SIGN REPLACEMENT PROGRAM VALLEY STREET ROAD DIET AND TRAFFIC CALMING SUBTOTAL STREETS PROJECTS LOANS TO OTHER FUNDS LOAN-CFD #1 TO TIF LOAN -SEWER REPL TO SEWER CONN LOAN-PFFTO PIL-NW LOAN-PFF TO PIL-SW PFF LOAN TO PIL-NE FOR PARK SITE ACQUISITION SUBTOTAL FUTURE LOANS TO OTHER FUNDS REPAYMENTS/TRANSFERS GAS TAX TRANSFER TO GENERAL FUND (TRANSPORTATION OPERATING BUDGET) LOAN: Pll-NE TO PFF FOR PARK SITE ACQUISITION LOAN REPAY-SEWER CONN TO SEWER REPL LOAN REPAY-PIL-NWTO PFF FY 2016-17 TO 2030-31 PRELIMINARY CAPITAL IMPROVEMENT PROGRAM TOTAL PRIOR BALANCE YEAR 1 YEAR2 YEAR3 YEAR4 YEARS YEAR 6-10 YEAR 11-1S FUND COST EXP/ENC FORWARD 2016-17 2017-18 2018-19 2019-20 2020-21 2022-26 2027-31 GAS TAX S1S,OOO S1S,OOO TIF 286,000 286,000 GAS TAX 1,984,S30 37S,OOO 1,609,S30 PFF 909,SOO 68S,327 224,173 TIF 413,000 413,000 TRANSNET-LOC 2,820,000 32S,OOO 2,49S,OOO TIF 1,92S,OOO 1,92S,OOO TIF 62S,OOO 4SO,OOO 17S,OOO OTHER 2,392,000 2,392,000 TRANSNET-LOC 3,143,SOO 3,143,SOO TIF 4,107,022 3,979,0S8 11,964 116,000 TIF 4,S72,000 4,S72,000 TRANSNET-LOC 3,92S,88S 3,92S,612 273 TRANSNET-STP 378,400 344,410 S90 33,400 GAS TAX 662,633 662,633 IRF 6S,OOO 65,000 TRANSNET-LOC 3,875,000 2,360,000 1,S1S,OOO GAS TAX 863,000 863,000 GAS TAX 260,113 2SS,789 4,324 GAS TAX 200,000 200,000 TIF 1,166,000 1,166,000 TIF 561,000 95,633 46S,367 GAS TAX 7S6,187 738,426 17,761 GCC 9S,OOO 9S,OOO TIF 49S,SOO 34S,SS6 149,944 TIF 1,129,000 1,129,000 TRANSNET-LOC 233,000 233,000 TRANSNET-LOC S64,000 S64,000 IRF 1,S30,000 139,2S6 96S,744 42S,OOO GAS TAX 27,688,127 3,872,783 4,96S,344 1,4SO,OOO 1,4SO,OOO 1,4SO,OOO 7,2SO,OOO 7,2SO,OOO TRANSNET-LOC 37,446,37S 14,488,000 3,4S8,37S 1,SOO,OOO 1,SOO,OOO 1,SOO,OOO 7,SOO,OOO 7,SOO,OOO TRANSNET-LOC 17,032,47S 4,920,748 861,727 750,000 7SO,OOO 7SO,OOO 7SO,OOO 7SO,OOO 3,750,000 3,7SO,OOO BTD#2 13,986,000 261,6S8 1,824,342 9,000,000 soo,ooo 1,400,000 1,000,000 BTD#2 1,168,833 1,168,833 TIF 980,000 980,000 GCC 2,58S,OOO 43,061 2,0S6,939 48S,OOO IRF soo,ooo soo,ooo GCC 2SO,OOO 144,S12 105,488 RSF ROAD 20,671,000 20,1S2,182 518,818 GAS TAX 2,320,000 21,316 2,298,684 GCC 200,000 200,000 GAS TAX 4SO,OOO 359,000 91,000 WATER REPL 71,000 204 290,796 (220,000) TIF 1,974,236 172,480 1,S01,7S6 300,000 TIF 4,399,998 407,3SO 1,892,648 300,000 300,000 300,000 300,000 300,000 600,000 TRANSNET-LOC 325,000 325,000 TRANSNET-LOC 3,645,000 33,820 286,180 8SO,OOO 82S,OOO 825,000 82S,OOO TIF 200,000 200,000 TIF 2,102,900 7S3,860 293,040 96,000 96,000 96,000 96,000 96,000 480,000 96,000 GAS TAX 380,000 380,000 GCC 100,000 100,000 GAS TAX 1SO,OOO 4,337 14S,663 TRANSNET-LOC 1,64S,OOO 1,64S,OOO 235 585,472 68 268 267 42.168 652 23,830,220 10,743,000 11602 000 7 586 000 6 246 000 28,974 500 36166,833 CFD#l 2,230,162 2,230,162 SEWER REPL 4,700,000 4,700,000 PFF 800,000 800,000 PFF 1,100,000 1,100,000 PFF 4,S50,000 4,S50,000 13 380,162 13 380 162 0 0 0 0 0 0 0 0 GAS TAX 4,800,000 600,000 600,000 600,000 600,000 600,000 1,800,000 PIL-NE 4,SSO,OOO 4,SSO,OOO SEWER CONN 4,700,000 4,700,000 PIL-NW 800,000 800,000 Item 4; pg. 21 FY 2016-17 TO 2030-31 PRELIMINARY CAPITAL IMPROVEMENT PROGRAM I PROJ. TOTAL PRIOR BALANCE YEAR 1 YEAR 2 YEAR 3 YEAR4 YEARS YEAR 6-10 YEAR 11-15 ID PROJECfT!TlE FUND COST EXP/ENC FORWARD 2016-17 2017-18 2018-19 2019-20 2020-21 2022-26 2027-31 NA LOAN REPAY-Pll-SWTO PFF PIL-SW 1,100,000 1,100,000 NA TIFTOCFD#l TIF 2,230,162 50,000 so,ooo so,ooo so,ooo so,ooo so,ooo 1,930,162 SUBTOTAL LOAN REPAYMENTS 18,180,162 0 650,000 1,4SO,OOO 650,000 650,000 650,000 2,950,000 11,180,162 GRAND TOTAL All FUNDED PROJECTS 929,411,451 286,686,480 179,524,686 64,527,677 28,737,483 26,757,45S 24,586,586 23,544,078 126,830,896 168,216,110 UNFUNDED PROJECTS* OGII~ 11Eili8PIIlA GHAPINE" IPbllA "B" FAGibi=P' B I BPI) 9 delete BUSINESS PARK RECREATIONAL FACILITY (PARTIAL FUNDING) 6,600,000 CANNON LAKE PARK (6.7 ACRES) 2,243,000 GOPIPI8PI R8Ail REAGH q (PARfiAb FtiPIIliPIG! 9 delete CARLSBAD BOULEVARD MOUNTAIN VIEW TO NORTHERLY CITY LIMITS (PARTIAL FUNDING) 6,90S,600 CARLSBAD BOULEVARD/ PALOMAR AIRPORT ROAD (PARTIAL FUNDING) 14,109,600 CARLSBAD BOULEVARD REALIGNMENT-SEGMENTS 3-S 26,100,000 H85P GR8\IE/BIJEPIA \lls:t,O "'G88N REG'" IMPR8\IEMEPH5 9 delete PI PIE OHEPIIIE PARK MP.Il1SI8N PR8PER1Y, PHASE 2 9 delete ROBERTSON RANCH PARK DEVELOPMENT (PARTIAL FUNDING) 7,800,000 TOTAL UNFUNDED PROJECTS 63,758,200 Item 4; pg. 22 3 BTD NO.2 AVIARA PARKWAY-POINSETTIA LANE PRIOR YEAR 1 YEAR2 YEAR3 YEAR4 YEARS YEAR 6-1S YEARS 2016-17 2017-18 2018-19 2019-20 2020-21 2022-31 BEGINNING FUND BALANCE {1) N/A 9,219,758 375,160 34,176 70,316 179,640 40,788 REVENUES DEVELOPER FEES 1SS,402 1S9,016 36,140 109,324 1,261,148 2,381,638 TOTAL REVENUES N/A 155,402 159,016 36,140 109,324 1,261,148 2,381,638 CAPITAL PROJECTS POINSETTIA LANE-REACH E CASSIA ROAD TO SKIMMER COURT 2,086,000 9,000,000 SOO,OOO --1,400,000 1,000,000 POINSETTIA LANE-REACHES A,B,C,F,G & AVIARA PKWY REIMB -----1,168,833 TOTAL PROJECT EXPENDITURES 2,086,000 9,000,000 500,000 1,400,000 2,168,833 ENDING FUND BALANCE N/A 375,160 34,176 70,316 179,640 40,788 253,593 BTD NO. 3 CANNON ROAD WEST PRIOR YEAR 1 YEAR2 YEAR3 YEAR4 YEARS YEAR 6-1S YEARS 2016-17 2017-18 2018-19 2019-20 2020-21 2022-31 BEGINNING FUND BALANCE {1) N/A 544,085 443,085 537,586 632,087 726,590 827,093 REVENUES DEVELOPER FEES 24,000 94,S01 94,S01 94,S03 100,S03 3,S42,192 TOTAL REVENUES N/A 24,000 94,501 94,501 94,503 100,503 3,542,192 CAPITAL PROJECTS BTD#3 RECONCILIATION AND CLOSEOUT 12S,OOO ----- TOTAL PROJECT EXPENDITURES 125,000 ENDING FUND BALANCE N/A 443,085 537,586 632,087 726,590 827,093 4,369,285 COMMUNITY FACILITIES DISTRICT NO. 1 {CFD 1) PRIOR YEAR 1 YEAR2 YEAR3 YEAR4 YEARS YEAR6-1S YEARS 2016-17 2017-18 2018-19 2019-20 2020-21 2022-31 BEGINNING FUND BALANCE {1) N/A 61,596,513 62,252,953 62,856,228 63,443,096 64,091,168 65,055,137 REVENUES DEVELOPER SPECIAL TAXES 816,439 713,276 696,868 7S8,072 963,970 18,S2S,1S8 TOTAL REVENUES N/A 816,439 713,276 696,868 758,072 963,970 18,525,158 CAPITAL PROJECTS CFD#1 ADMINISTRATION -110,000 110,000 110,000 110,000 -- CIVIC CENTER 100,000 SO,OOO ----30,417,000 COLE LIBRARY EXPANSION ------S,64S,OOO LOAN -CFD #1 TO TIF 2,230,162 ---- MAINTENANCE AND OPERATIONS CENTER 17,861,264 ---- MAINTENANCE AND OPERATIONS CENTER-ART 143,000 ------ VETERAN'S MEMORIAL PARK {ALL QUADRANTS) ------23,240,000 TOTAL PROJECT EXPENDITURES 20,334,426 160,000 110,000 110,000 110,000 59,302,000 ENDING FUND BALANCE N/A 62,252,953 62,856,228 63,443,096 64,091,168 65,055,137 24,278,295 Item 4; pg. 23 GAS TAX FUND PRIOR YEAR 1 YEAR2 YEAR3 YEAR4 YEARS YEAR 6-15 YEARS 2016-17 2017-18 2018-19 2019-20 2020-21 2022-31 BEGINNING FUND BALANCE (1) N/A 5,065,918 3,902,845 4,365,772 3,629,699 3,293,626 2,957,553 REVENUES GAS TAX AND PROP 42 FUNDS 2,263,927 2,263,927 2,263,927 2,263,927 2,263,927 22,639,270 TOTAL REVENUES N/A 2,263,927 2,263,927 2,263,927 2,263,927 2,263,927 22,639,270 CAPITAL PROJECTS CARLSBAD BLVD AND TAMARACK AVENUE PEDESTRIAN IMPROVEMENTS 1,653,900 - - - - - - CARLSBAD BLVD EMERGENCY REPAIR 841,000 -- - -- CARLSBAD BLVD MEDIAN-TAMARACK AVENUE TO PINE AVENUE - - - - - -2,605,000 COMPLETE STREET AND TRAFFIC CALMING PROGRAM -300,000 300,000 300,000 300,000 300,000 - CONCRETE REPAIR/REPLACEMENT PROGRAM 2,000,000 250,000 250,000 250,000 250,000 250,000 2,500,000 EL CAMINO REAL AND COLLEGE BLVD INTERSECTION IMPROVEMENTS -515,000 - --- EL CAMINO REAL MEDIANS 1,984,530 - - -- EL CAMINO REAL WIDENING-TAMARACK AVENUE TO CHESTNUT AVENUE 662,633 - - - - - GAS TAX TRANSFER TO GENERAL FUND (TRANSPORTATION OPERATING BUDGE 600,000 600,000 600,000 600,000 600,000 1,800,000 LA COSTA AVENUE-TRAFFIC CALMING 863,000 - - - -- LA COSTA AVENUE SLOPE REPAIR WEST OF ROMERIA STREET 260,113 -- - -- LAGUNA DRIVE STORM DRAIN - -370,000 - - -- LEFT TURN LANE EXTENSIONS -200,000 - - - -- MARGA PLACE DRAINAGE IMPROVEMENTS 65,000 - - - - -- MUTCD STREET NAME SIGN REPLACEMENT PROGRAM 756,187 - - - --- NW QUADRANT STORM DRAIN IMPROVEMENT PROGRAM 6,090,590 - - -- PAVEMENT MANAGEMENT PROGRAM 8,838,127 - -1,450,000 1,450,000 1,450,000 14,500,000 PEDESTRIAN CROSSINGS-CARLSBAD BOULEVARDNILLAGE 200,000 - - - --- RETROREFLECTIVITY SIGN REPLACEMENT PROGRAM 2,320,000 -- - -- ROADWAY SLOPE STABILIZATION -359,000 91,000 ---- ROMERIA DRAINAGE IMPROVEMENTS 348,000 ----- SIGNAL OPERATIONS MODIFICATIONS -150,000 ----- TRAFFIC SIGNAL-ALGA ROAD AND CAZADERO DRIVE - ----210,000 TRAFFIC SIGNAL-ARMADA DRIVE AND FLEET STREET SOUTH -----190,000 TRAFFIC SIGNAL-ARMADA DRIVE AND GRAND PACIFIC RESORTS ------190,000 TRAFFIC SIGNAL-CAMINO DE LOS COCHES AND LA COSTA AVENUE 190,000 ------ TRAFFIC SIGNAL-CAMINO VIDA ROBLE AND YARROW DRIVE - -----190,000 TRAFFIC SIGNAL-EL FUERTE STREET AND RANCHO PANCHO -190,000 ----- TRAFFIC SIGNAL-FARADAY AVENUE AND CAMINO HILLS DRIVE - -190,000 - --- TRAFFIC SIGNAL-FARADAY AVENUE AND PALMER WAY --190,000 --- TRAFFIC SIGNAL-LA COSTA AVENUE AND LEV ANTE STREET -210,000 --- TRAFFIC SIGNAL-MONROE STREET AND HOSP WAY - -- -210,000 TRAFFIC SIGNAL-POINSETTIA LANE AND BRIGANTINE ROAD - - - --190,000 TRAFFIC SIGNAL-TAMARACK AVENUE AND VALLEY STREET - - - --190,000 TRAILS ROADWAY CROSSINGS (CATS) 380,000 - - -- WAYFINDING SIGN REPLACEMENT PROGRAM 150,000 - - --- 26,740,080 3,427,000 1,801,000 3,000,000 2,600,000 2,600,000 22,775,000 ENDING FUND BALANCE N/A 3,902,845 4,365,772 3,629,699 3,293,626 2,957,553 2,821,823 Item 4; pg. 24 GENERAL CAPITAL CONSTRUCTION (GCC) PRIOR YEAR 1 YEAR2 YEAR3 YEAR4 YEARS YEAR 6-15 YEARS 2016-17 2017-18 2018-19 2019-20 2020-21 2022-31 BEGINNING FUND BALANCE (1) N/A 24,827,391 16,124,132 16,024,132 15,924,132 15,924,132 15,924,132 REVENUES TRANSFERS, REPAYMENTS, OTHER - TOTAL REVENUES N/A CAPITAL PROJECTS ADA BEACH ACCESS STUDY -75,000 --- ALGA NORTE PARK-PHASE 1 (PROP C FUNDS) 7,804,216 ----- ALGA NORTE PARK-PHASE 2 ----- ALGA NORTE PARK-PHASE 2 (PROP C FUNDS) 676,498 --- BARRIO STREET LIGHTING 100,000 660,000 ---- BUENA VISTA CREEK CHANNEL FENCING 200,000 ---- CALAVERA PARK GATEWAY IMPROVEMENTS 582,500 ---- CAMINO HILLS AND JACKSPAR DRIVE SLOPE STABILIZATION 859,400 --- CANNON PARK RESTROOM -600,000 --- CARLSBAD BLVD BRIDGE RAILING EAST SIDE AT POWER PLANT DISCHARGE 338,455 - ---- CARLSBAD BLVD REALIGNMENT-CANNON TO MANZANO-PARK -999,999 --- CARLSBAD BLVD REALIGNMENT 250,000 - ---- CARLSBAD SAFETY TRAINING FACILITY-FIREARMS RANGE NOISE MITIGATION 350,500 ----- CARLSBAD STATE BEACH BLUFF RESTORATION 499,830 --- CARLSBAD STATE BEACH GREENWAY IMPROVEMENTS 400,000 ---- CITY FACILITY ACCESSIBILITY UPGRADES -100,000 100,000 100,000 --- CITY HALL EXTERIOR REFURBISHMENT 2,250,000 ----- COLE LIBRARY EXPANSION (BROWNLEY DONATION) ----1,000,000 COLE LIBRARY IMPROVEMENTS (INCLUDES IRF FUNDING) 5,300,000 ---- DOVE LIBRARY IMPROVEMENTS (INCLUDES IRF FUNDING) 6,046,119 ---- EMERGENCY CENTER RECONFIGURATION 1,658,000 - ---- FIRE STATION DRAINAGE IMPROVEMENTS 225,000 ----- FIRE STATION NO.2 FEASIBILITY STUDY 50,000 ---- LAKE CALAVERA TRAILS MASTER PLAN/CONSTRUCTION (PROP C) 873,250 190,000 ----- MAERKLE RESERVOIR SOLAR PROJECT 250,000 --- LAKE CALAVERA STORM DRAIN IMPROVEMENTS -236,500 -- MULTI-USE, MULTIGENERATIONAL INDOOR COMMUNITY CENTER (STUDY) 90,000 ---- OCEAN STREET RECONFIGURATION CONCEPTS STUDY -95,000 ---- OCEAN STREET RESTROOM -652,000 --- OPEN SPACE AND TRAILS (PROP C) -3,714,760 --- OUTDOOR ADVENTURE PARK FEASIBILITY STUDY 122,500 ----- PARK DRIVE DRAINAGE AND STREET IMPROVEMENTS 243,000 --- - - PUBLIC BEACH ACCESS IMPROVEMENTS 2,100,000 485,000 ---- RAILROAD DOUBLE TRACKING 250,000 -- ROADWAY IMPROVEMENTS-COASTAL AREA ANALYSIS & IMPLEMENTATION 200,000 -- ROMERIA DRAINAGE IMPROVEMENTS 299,000 --- SAFETY CENTER IMPROVEMENTS 2,013,500 ---- SAFETY TRAINING CENTER WATER RECIRCULATING SYSTEM STUDY 50,000 -- TRAFFIC SIGNAL PROGRAM 912,000 ---- - TRAFFIC SIGNAL PROGRAM-FIBER OPTIC 229,750 ----- - TRAIL CONNECTIVITY TO TAMARACK STATE BEACH (PROP C) -200,000 - --- UTILITY UNDERGROUNDING PROGRAM STUDY -100,000 --- VILLAGE AND BARRIO BIKE & PEDESTRIAN WAYFINDING 250,000 ---- VILLAGE AND BARRIO TRAFFIC CIRCLES 315,000 -- --- VILLAGE AND BEACH STREETSCAPE 635,000 --- VILLAGE DECORATIVE LIGHTING 177,800 ---- VILLAGE PARKING WAYFINDING 105,000 --- VILLAGE PUBLIC GATHERING SPACES STUDY 345,000 - VILLAGE SAFETY LIGHTING 234,678 -- TOTAL PROJECT EXPENDITURES 36,690,996 8,703,259 100,000 100,000 1,000,000 N/A 16,124,132 16,024,132 15,924,132 15,924,132 15,924,132 14,924,132 GRANTS • FEDERAL PRIOR YEAR 1 YEAR2 YEAR3 YEAR4 YEARS YEAR 6-15 YEARS 2016-17 2017-18 2018-19 2019-20 2020-21 2022-31 BEGINNING FUND BALANCE (1) N/A 0 0 0 0 0 0 REVENUES GRANT REVENUE 398,385 --- TOTAL REVENUES N/A 398,385 CAPITAL PROJECTS CARLSBAD BLVD BRIDGE CONCRETE BARRIER POWER PLANT 896,366 398,385 -- CARLSBAD BLVD BRIDGE CONCRETE BARRIER RAILROAD 728,592 -- CARLSBAD BLVD BRIDGE RAILING EAST SIDE AT POWER PLANT DISCHARGE 130,622 --- TOTAL PROJECT EXPENDITURES 1,755,580 398,385 ENDING FUND BALANCE N/A 0 0 0 0 0 0 Item 4; pg. 25 INFRASTRUCTURE MAINTENANCE & REPLACEMENT (IM&R) PRIOR YEAR 1 YEAR2 YEAR3 YEAR4 YEARS YEAR 6-15 YEARS 2016-17 2017-18 2018-19 2019-20 2020-21 2022-31 BEGINNING FUND BALANCE (1) N/A 80,936,637 86,520,537 94,604,537 103,036,537 111,868,537 121,079,537 REVENUES GENERAL FUND TRANSFER 9,460,000 9,684,000 9,982,000 10,382,000 10,661,000 117,366,000 TOTAL REVENUES N/A 9,460,000 9,684,000 9,982,000 10,382,000 10,661,000 117,366,000 CAPITAL PROJECTS AGUA HEDIONDA CREEK STORM DRAIN OUTFALL (FAROL COURT) 596,700 ------ AVIARA COMMUNITY PARK SOCCER FIELD SYNTHETIC TURF REPLACEMENT 868,000 ------ BEACH ACCESS REPAIR/UPGRADES 517,500 250,000 ----- BRIDGE PREVENTITIVE MAINTENANCE PROGRAM -350,000 350,000 300,000 300,000 200,000 - CITY HALL COMPLEX REFURBISHMENT 919,000 ----- CMP REPLACEMENT PROGRAM 2,859,360 -- EL CAMINO REAL AND AGUA HEDIONDA CREEK BRIDGE RAILING & SIDEWALK 210,000 --- EMERGENCY CENTER RECONFIGURATION 200,000 ---- FACILITY SAFETY AND PARKING LOT LIGHTING ASSESSMENT 65,000 ---- FARADAY REHABILITATION 939,000 ------ FIRE STATION NO.1 REFURBISHMENT 150,000 ------ FIRE STATION NO.2 REFURBISHMENT 375,000 ----- FLEET MAINTENANCE REFURBISHMENT 975,000 ----- FUTURE FACILITIES MAINTENANCE PROJECTS -1,000,000 1,000,000 1,000,000 1,000,000 10,000,000 HARDING CENTER REFURBISHMENT 115,000 --- HEADWALL REPLACEMENT PROGRAM -510,000 ---- HOLIDAY PARK FACILITIES MAINTENANCE 50,000 ----- HOSP GROVE PARK IMPROVEMENTS -848,000 ----- KELLY DRIVE CHANNEL REPAIR 1,161,000 ------ KELLY DRIVE CHANNEL REPLACEMENT ------1,992,000 LA COSTA AVENUE DRAINAGE IMPROVEMENTS 492,150 ---- MISCELLANEOUS BUILDING IMPROVEMENTS 250,000 150,000 150,000 150,000 150,000 150,000 1,500,000 MONROE STREET POOL REPLACEMENT 100,000 250,000 ----- PARKING LOT MAINTENANCE PROGRAM 1,105,000 425,000 ---- PARKS ELECTRONIC SCOREBOARD REPLACEMENTS -60,100 ----- PINE AVENUE PARK SYNTHETIC TURF REPLACEMENT -868,000 ----- PUBLIC BEACH ACCESS IMPROVEMENTS 500,000 ------ SAFETY CENTER IMPROVEMENTS 1,400,000 ------ SENIOR CENTER CONFERENCE ROOM REFURBISHMENT 52,000 ------ STORM DRAIN CONDITION ASSESSMENT 100,000 100,000 100,000 100,000 100,000 100,000 400,000 TRAFFIC SIGNAL-EL CAMINO REAL AND CHESTNUT AVENUE SIGNAL REPAIRS 276,000 ------ TRAFFIC SIGNAL-EL CAMINO REAL AND TAMARACK AVENUE SIGNAL REPAIRS 200,000 --- TRAFFIC SIGNAL PROGRAM 4,772,974 ---- TOTAL PROJECT EXPENDITURES 19,183,684 3,876,100 1,600,000 1,550,000 1,550,000 1,450,000 13,892,000 ENDING FUND BALANCE N/A 86,520,537 94,604,537 103,036,537 111,868,537 121,079,537 224,553,537 OTHER PRIOR YEAR1 YEAR2 YEAR3 YEAR4 YEARS YEAR 6-15 YEARS 2016-17 2017-18 2018-19 2019-20 2020-21 2022-31 BEGINNING FUND BALANCE (1) N/A 477,640 827,640 827,640 827,640 827,640 827,640 REVENUES OTHER FINANCING SOURCES 917,000 ----2,392,000 TOTAL REVENUES N/A 917,000 --2,392,000 CAPITAL PROJECTS BARRIO STREET LIGHTING 137,500 --- COLLEGE BLVD REACH A AND CANNON ROAD REACH 4A 1,713,000 --- EL CAMINO REAL WIDENING-LISA STREET TO CRESTVIEW DRIVE ---2,392,000 QUARRY CREEK SEWER EXTENSION (SBA "A"-REIMB. AGREEMENT) -567,000 --- TOTAL PROJECT EXPENDITURES 1,850,500 567,000 -2,392,000 ENDING FUND BALANCE N/A 827,640 827,640 827,640 827,640 827,640 827,640 Item 4; pg. 26 PARK-IN-LIEU NE PRIOR YEAR 1 YEAR2 YEAR3 YEAR4 YEARS YEAR 6-1S YEARS 2016-17 2017-18 2018-19 2019-20 2020-21 2022-31 BEGINNING FUND BALANCE (1) N/A 1,394,240 3,573,121 4,145,122 4,145,122 4,145,122 4,145,122 REVENUES DEVELOPER FEES 2,378,881 S72,001 --3,71S,331 TOTAL REVENUES N/A 2,378,881 572,001 -3,715,331 CAPITAL PROJECTS LOAN: PIL-NE TO PFF FOR PARK SITE ACQUISITION ------4,SSO,OOO ROBERTSON RANCH PARK DEVELOPMENT (PARTIAL FUNDING) -200,000 ---2,SOO,OOO TOTAL PROJECT EXPENDITURES 200,000 --7,050,000 ENDING FUND BALANCE N/A 3,573,121 4,145,122 4,145,122 4,145,122 4,145,122 810,453 PARK-IN-LIEU NW PRIOR YEAR 1 YEAR2 YEAR3 YEAR4 YEARS YEAR 6-1S YEARS 2016-17 2017-18 2018-19 2019-20 2020-21 2022-31 BEGINNING FUND BALANCE (1) N/A 372,619 570,399 34,518 298,637 577,032 848,290 REVENUES DEVELOPER FEES/LOANS 197,780 264,119 264,119 278,396 271,2S7 21,079,S48 TOTAL REVENUES N/A 197,780 264,119 264,119 278,396 271,257 21,079,548 CAPITAL PROJECTS LOAN REPAY-PIL-NW TO PFF --800,000 ---- PINE AVENUE PARK -PHASE 2 (COMMUNITY FACILITY AND GARDEN AREAS) 1,9S7,000 ----- TOTAL PROJECT EXPENDITURES 1,957,000 -800,000 - ENDING FUND BALANCE N/A 570,399 34,518 298,637 577,032 848,290 21,927,837 PARK-IN-LIEU SE PRIOR YEAR 1 YEAR2 YEAR3 YEAR4 YEARS YEAR 6-1S YEARS 2016-17 2017-18 2018-19 2019-20 2020-21 2022-31 BEGINNING FUND BALANCE (1) N/A 1,375,205 1,521,289 1,681,663 1,842,037 2,002,411 2,162,785 REVENUES DEVELOPER FEES 146,084 160,374 160,374 160,374 160,374 S,346 TOTAL REVENUES N/A 146,084 160,374 160,374 160,374 160,374 5,346 CAPITAL PROJECTS LEO CARRILLO PARK-PHASE 3 9S9,100 ---- TOTAL PROJECT EXPENDITURES 959,100 ENDING FUND BALANCE N/A 1,521,289 1,681,663 1,842,037 2,002,411 2,162,785 2,168,131 PARK-IN-LIEU SW PRIOR YEAR 1 YEAR2 YEAR3 YEAR4 YEARS YEAR 6-1S YEARS 2016-17 2017-18 2018-19 2019-20 2020-21 2022-31 BEGINNING FUND BALANCE (1) N/A 34,039 11,451 59,564 70,255 70,255 428,424 REVENUES DEVELOPER FEES/LOANS 48,112 48,112 10,692 -3S8, 169 700,300 TOTAL REVENUES N/A 48,112 48,112 10,692 358,169 700,300 CAPITAL PROJECTS AVIARA COMMUNITY PARK AMPHITHEATER AND PICNIC AREAS 2,760,SOO 70,000 ---- AVIARA COMMUNITY PARK AMPHITHEATER AND PICNIC AREAS-ART 30,600 700 ---- AVIARA REIMBURSEMENT AGREEMENT 238,000 ------ LOAN REPAY-PIL-SWTO PFF ------1,100,000 TOTAL PROJECT EXPENDITURES 3,029,100 70,700 1,100,000 N/A 11,451 59,564 70,255 70,255 428,424 28,724 Item 4; pg. 27 PARK FEE ZONES 5,13,16,17,18 PRIOR YEAR 1 YEAR2 YEAR3 YEAR4 YEARS YEAR 6-15 YEARS 2016-17 2017-18 2018-19 2019-20 2020-21 2022-31 BEGINNING FUND BALANCE (1) N/A 3,275,752 3,505,333 3,638,858 3,699,688 3,760,517 3,812,748 REVENUES DEVELOPER FEES 229,581 133,525 60,830 60,830 52,231 1,459,164 TOTAL REVENUES N/A 229,581 133,525 60,830 60,830 52,231 1,459,164 CAPITAL PROJECTS BUSINESS PARK RECREATIONAL FACILITY (PARTIAL FUNDING) -- - - -4,486,000 TOTAL PROJECT EXPENDITURES -4,486,000 ENDING FUND BALANCE N/A 3,505,333 3,638,858 3,699,688 3,760,517 3,812,748 785,912 PLANNED LOCAL DRAINAGE AREA FEES (PLDA) PRIOR YEAR 1 YEAR2 YEAR3 YEAR4 YEARS YEAR 6-15 YEARS 2016-17 2017-18 2018-19 2019-20 2020-21 2022-31 BEGINNING FUND BALANCE (1) N/A 5,134,667 5,259,817 5,716,331 6,027,835 6,333,478 6,582,972 REVENUES DEVELOPER FEES 1,560,150 726,515 311,504 305,642 249,494 8,240,035 TOTAL REVENUES N/A 1,560,150 726,515 311,504 305,642 249,494 8,240,035 CAPITAL PROJECTS DMP FACILITY AAA (JEFFERSON STREET) - - - - - -289,534 DRAINAGE MASTER PLAN UPDATE 750,000 - - --- DMP WETLAND CREATION 685,000 270,000 - - -- DMP FACILITY AAAA (MADISON STREET) - - - - - -416,500 DMP FACILITY AC (HIGHLAND DRIVE) - - - - -921,408 DMP FACILITY AFA (HIDDEN VALLEY DRAINAGE RESTORATION) - - - - -91,608 DMP FACILITY AFB (CALAVERA HILLS DRAINAGE RESTORATION) - - - - --163,164 DMP FACILITY B & BN (AGUA HEDIONDA AND CALAVERA CREEK PLDA "B") 3,643,066 - - ---- DMP FACILITY BB 1 and 2 (WASHINGTON STREET) - - - - --1,086,065 DMP FACILITY BCA (PARK DRIVE AND TAMARACK AVENUE PLDA "B") 1,068,613 - - ---- DMP FACILITY BCB (MAGNOLIA AVENUE) - - - - --468,096 DMP FACILITY BFA (COUNTRY STORE) - - - ---963,673 DMP FACILITY BFB-L & BFB-1 (TAMARACK ANDEL CAMINO REAL PLDA "B") - - --904,329 DMP FACILITY BFB-U (EL CAMINO REAL) - - - - -138,220 DMP FACILITY BJ B, BNB AND BJ-1 (COLLEGE BOULEVARD/CANNON ROAD) 2,761,644 - - - - -- DMP FACILITY BL-L (COLLEGE BLVD. BRIDGE REIMB. PLDA "B") - -- -1,816,101 DMP FACILITY BL-U (COLLEGE BOULEVARD) - -- --384,509 DMP FACILITY BM (CANTARINI/COLLEGE BOULEVARD BOX CULVERT) - -- - -204,077 DMP FACILITY BQ (SUNNY CREEK) - - -- -131,355 DMP FACILITY BR (CANTARINI/COLLEGE BOULEVARD PIPE DRAINAGE) - - -- -180,773 DMP FACILITY C1 -CARLSBAD BOULEVARD ENCINAS CREEK BRIDGE PLDA "C") 2,539,565 - - - - - - DMP FACILITY C2 (PASEO DEL NORTE) -- - - - -727,730 DMP FACILITY CA (AVENIDA ENCINAS) -- - - - -529,402 DMP FACILITY DBA (POINSETTIA VILLAGE) - - - - -167,215 DMP FACILITY DBB (AVENIDA ENCINAS) -- - - -429,108 DMP FACILITY DFA (BATIQUITOS LAGOON STORMWATER TREATMENT) - - - - -256,423 DMP FACILITY DH (AL TIVE PLACE CANYON RESTORATION) --- - -232,812 DMP FACILITY DQB (LA COSTA TOWN CENTER) --- - -745,842 DMP FACILITY DZ (POINSETTIA LANE) ---- - -642,063 TOTAL PROJECT EXPENDITURES 10,012,888 1,435,000 270,000 11,890,007 ENDING FUND BALANCE N/A 5,259,817 5,716,331 6,027,835 6,333,478 6,582,972 2,933,000 Item 4; pg. 28 PUBLIC FACILITY FEE FUND (PFF) PRIOR YEAR 1 YEAR2 YEAR3 YEAR4 YEARS YEAR 6-15 YEARS 2016-17 2017-18 2018-19 2019-20 2020-21 2022-31 BEGINNING FUND BALANCE (1) N/A 11,565,944 14,885,339 17,554,317 18,874,911 20,125,731 21,859,240 REVENUES DEVELOPER FEES 4,856,115 2,668,978 1,320,594 1,250,819 1,733,509 33,056,613 TOTAL REVENUES N/A 4,856,115 2,668,978 1,320,594 1,250,819 1,733,509 33,056,613 CAPITAL PROJECTS ALGA NORTE PARK-PHASE 1 PARK 22,107,512 ---- AVIARA COMMUNITY PARK WARMING KITCHEN AND RESTROOM 300,000 ---- COLE LIBRARY EXPANSION -----11,250,000 EL CAMINO REAL MEDIANS 909,500 ------ FIRE STATION NO.3 RELOCATION 9,352,000 ----- LOAN-PFF TO PIL-NW 800,000 ------ LOAN-PFF TO PIL-SW 1,100,000 ------ LEO CARRILLO PARK-PHASE 3 1,057,000 349,500 ----- LEO CARRILLO PARK-PHASE 3-ART 20,160 3,495 --- PFF LOAN TO PIL-NE FOR PARK SITE ACQUISITION 4,550,000 ----- PINE AVENUE PARK -PHASE 2 (COMMUNITY FACILITY AND GARDEN AREAS) 8,343,000 700,000 ----- PINE AVENUE PARK -PHASE 2 (COMMUNITY FACILITY AND GARDEN AREAS)-AR 103,000 7,000 ---- POINSETTIA COMMUNITY PARK-PHASE 3 3,850,000 472,000 ----13,196,500 POINSETTIA COMMUNITY PARK-PHASE 3-ART 38,500 4,725 ----- TRAFFIC SIGNAL-CANNON ROAD AND AVENIDA ENCINAS (REIMBURSEMENT) 150,000 ----- TOTAL PROJECT EXPENDITURES 52,680,672 1,536,720 24,446,500 ENDING FUND BALANCE N/A 14,885,339 17,554,317 18,874,911 20,125,731 21,859,240 30,469,352 RANCHO SANTA FE ROAD PROJECT PRIOR YEAR 1 YEAR2 YEAR3 YEAR4 YEARS YEAR6-15 YEARS 2016-17 2017-18 2018-19 2019-20 2020-21 2022-31 BEGINNING FUND BALANCE (1) N/A 87,079 87,079 420,459 420,459 420,459 420,459 REVENUES DEVELOPER SPECIAL TAXES/OTHER AGENCIES -333,380 ---- TOTAL REVENUES N/A 333,380 - CAPITAL PROJECTS RANCHO SANTA FE ROAD NORTH-PHASE II (BRIDGE) 20,671,000 ---- TOTAL PROJECT EXPENDITURES 20,671,000 - ENDING FUND BALANCE N/A 87,079 420,459 420,459 420,459 420,459 420,459 Item 4; pg. 29 SEWER CONNECTION FEE FUND PRIOR YEAR 1 YEAR2 YEAR3 YEAR4 YEARS YEAR 6-1S YEARS 2016-17 2017-18 2018-19 2019-20 2020-21 2022-31 BEGINNING FUND BALANCE (1) N/A 3,649,190 1,708,499 2,018,407 724,634 679,475 805,342 REVENUES DEVELOPER FEES AND MISC. 894,709 409,908 724,427 2,068,841 147,867 S,109,2S9 OTHER AGENCY CONTRIBUTIONS (CITY OF VISTA) 201,600 672,000 ---- TOTAL REVENUES N/A 1,096,309 1,081,908 724,427 2,068,841 147,867 5,109,259 CAPITAL PROJECTS BUENA INTERCEPTOR SEWER IMPROVEMENTS SOO,OOO -- -- FARADAY & EL CAMINO REAL SEWER REPLACEMENT-ORION TO PAR 140,000 --1,400,000 --- LAS PALMAS TRUNK SEWER 430,000 1,990,000 - - --- LOAN REPAY-SEWER CONN TO SEWER REPL - - - --4,700,000 SEWER MONITORING PROGRAM 326,000 22,000 22,000 22,000 22,000 22,000 220,000 VISTA CARLSBAD INTERCEPTOR-BUENA VISTA LIFT STATION IMPROVEMENTS 1SO,OOO 22S,OOO 7SO,OOO --- VISTA CARLSBAD INTERCEPTOR-BUENA VISTA LIFT STATION & FORCEMAIN (VC S,72S,OOO -- - --- VISTA CARLSBAD INTERCEPTOR-AGUA HEDIONDA LS & FORCEMAIN (VC12-VC1< 29,200,000 4SO,OOO - - - -- VISTA CARLSBAD INTERCEPTOR-LAGOON BRIDGE REPLACEMENT (VC11 B) 8,430,000 1SO,OOO - - - VISTA CARLSBAD INTERCEPTOR-REACH VC14 TO VC1S 20,000,000 200,000 - -- VISTA CARLSBAD INTERCEPTOR-REACH VC3 --S96,200 2,092,000 -- TOTAL PROJECT EXPENDITURES 64,901,000 3,037,000 772,000 2,018,200 2,114,000 22,000 4,920,000 ENDING FUND BALANCE N/A 1,708,499 2,018,407 724,634 679,475 805,342 994,601 SEWER REPLACEMENT FUND PRIOR YEAR 1 YEAR2 YEAR3 YEAR4 YEARS YEAR 6-1S YEARS 2016-17 2017-18 2018-19 2019-20 2020-21 2022-31 BEGINNING FUND BALANCE (1) N/A 6,172,951 5,125,294 2,615,401 1,480,966 (386,460) (6,014,448) REVENUES TRANSFER FROM OPERATING FUND 4,3SS,OOO 4,472,S90 4,S97,820 4,731,160 4,873,090 S9,204,7S7 TOTAL REVENUES N/A 4,355,000 4,472,590 4,597,820 4,731,160 4,873,090 59,204,757 CAPITAL PROJECTS BATIQUITOS LIFT STATION PUMP REPLACEMENT 90S,OOO - ---- BUENA INTERCEPTOR REHAB AT ENCINA PLANT (REIMB) 100,000 - - --- BUENA INTERCEPTOR SEWER ACCESS ROAD IMPROVEMENTS 2SO,OOO - - --- BUENA INTERCEPTOR SEWER IMPROVEMENTS 1,362,000 -1,964,000 -- BUENA INTERCEPTOR SEWER REALIGNMENT-EAST SEGMENT --S07,000 1,480,000 - CARLSBAD BLVD REALIGNMENT-CANNON TO MANZANO -350,000 - - --- CHINQUAPIN LIFT STATION FORCE MAIN OUTFALL REALIGNMENT 60,000 1S2,000 - --- ENCINA CAPITAL PROJECTS 18,063,220 3,121,112 4,2S8,483 4,114,2SS 4,438,S86 9,821,078 49,S73,224 FLOW METER REPLACEMENTS 1SO,OOO - ---- FOXES LANDING LIFT STATION WETWELL AND PUMP REPLACEMENT 3,270,4SS 829,S4S - - --- GATESHEAD LIFT STATION REMOVAL 1SO,OOO ---- HOME PLANT PIPELINE AND LIFT STATION REPLACEMENT 4,139,000 - - - -- LOAN-SEWER REPL TO SEWER CONN 4,700,000 -- - -- MAINTENANCE AND OPERATIONS CENTER 4,113,000 -- - - -- NORTH AGUA HEDIONDA INTERCEPTOR-WEST SEGMENT S,8S4,000 -- - -- NORTH BATIQUITOS INTERCEPTOR SEWER ACCESS ROAD IMPROVEMENTS ---2SO,OOO - -- NORTH BATIQUITOS LIFT STATION FORCEMAIN REHABILITATION SSO,OOO -- - --- NORTHWEST QUADRANT CIPP SEWER REHABILITATION 700,000 -- - -- OCCIDENTAL SEWER IMPROVEMENTS 849,000 -- - - - ODOR AND CORROSION PREVENTION ASSESSMENT 200,000 -- - - - POINSETTIA LANE LIFT STATION EMERGENCY OVERFLOW BASIN 1,200,000 ----- SCADA INTEGRATED MASTER PLAN -80,000 ---- SEWER EASEMENT ACCESS PROGRAM 400,000 -- -- SEWER LIFT STATION REPAIRS AND UPGRADES 1,760,380 1SO,OOO 1SO,OOO 1SO,OOO 1SO,OOO 1SO,OOO 1,SOO,OOO SEWER LINE CONDITION ASSESSMENT 633,000 200,000 200,000 200,000 200,000 200,000 1,000,000 SEWER LINE REFURBISHMENTS AND REPLACEMENT 4, 1S7,896 330,000 330,000 330,000 330,000 330,000 3,300,000 SIMSBURY SEWER EXTENSION 301,000 - - - --- TAMARACK SEWER RELOCATION AT RAILROAD RIGHT-OF-WAY 2S2,000 --- - - - TERRAMAR SEWER REPLACEMENT-EL ARBOL AND LOS ROBLES 1,2SO,OOO --- - - VANCOUVER SEWER EXTENSION 1,006,000 -- - - - VILLAGE AND BARRIO TRAFFIC CIRCLES -40,000 60,000 60,000 - - - VISTA CARLSBAD INTERCEPTER-REHABILITATION (VC1 & VC2) --20,000 121,000 - - WATER, RECYCLED, AND SEWER MASTER PLAN -1SO,OOO --- TOTAL PROJECT EXPENDITURES 56,375,951 5,402,657 6,982,483 5,732,255 6,598,586 10,501,078 55,373,224 ENDING FUND BALANCE N/A 5,125,294 2,615,401 1,480,966 (386,460) (6,014,448) (2, 182,915) Item 4; pg. 30 TRAFFIC IMPACT FEES (TIF) PRIOR YEAR 1 YEAR2 YEAR3 YEAR4 YEARS YEAR 6-1S YEARS 2016-17 2017-18 2018-19 2019-20 2020-21 2022-31 BEGINNING FUND BALANCE (1) NIA 7,376,890 10,254,734 9,388,393 7,208,686 7,758,920 8,125,878 REVENUES DEVELOPER FEES 4,039,844 2,010,6S9 1,012,294 996,234 812,9S8 22,960,806 TOTAL REVENUES NIA 4,039,844 2,010,659 1,012,294 996,234 812,958 22,960,806 CAPITAL PROJECTS AVENIDA ENCINAS WIDENING-SOUTH OF PALOMAR AIRPORT ROAD 169,7SO -2,431,000 2,746,000 - CARLSBAD BLVD REALIGNMENT I PALOMAR AIRPORT ROAD (SEGMENT 2) (20%) ----879,000 CARLSBAD BLVD REALIGNMENT I PALOMAR AIRPORT ROAD (SEGMENT 2) (RTCIP -----3,470,000 CARLSBAD BLVD REALIGNMENT-CANNON TO MANZANO 6,0SO,OOO (3,000,000) ---- CARLSBAD BLVD WIDENING MOUNTAIN VIEW TO NORTHERLY CITY LIMITS (20%) ----927,000 CARLSBAD BLVD WIDENING MOUNTAIN VIEW TO NORTHERLY CITY LIMITS (RTCIF ------1,201,000 CARLSBAD VILLAGE DRIVE WIDENING-PONTIAC DRIVE TO VICTORIA AVENUE ----2,924,000 EL CAMINO REAL AND CANNON ROAD INTERSECTION IMPROVEMENTS 849,000 1,200,000 --- EL CAMINO REAL AND CARLSBAD VILLAGE DRIVE DUAL LEFT TURNS ----1,067,000 EL CAMINO REAL LEFT TURN LANE TO WESTBOUND TAMARACK AVENUE 286,000 ------ EL CAMINO REAL RIGHT TURN LANE TO EAST BOUND ALGA ROAD -----413,000 EL CAMINO REAL WIDENING -ARENAL ROAD TO LA COSTA AVENUE -1,92S,OOO ---- EL CAMINO REAL WIDENING-ARENAL ROAD TO LA COSTA AVENUE (RTCIP) 4SO,OOO 17S,OOO ---- EL CAMINO REAL WIDENING-TAMARACK AVENUE TO CHESTNUT AVENUE 3,991,022 116,000 --- EL CAMINO REAL WIDENING-TAMARACK AVENUE TO CHESTNUT AVENUE (RTCIF 4,S72,000 ----- MELROSE DRIVE AND ALGA ROAD DUAL LEFT TURN LANES (RTCIP) -----1,166,000 MELROSE DRIVE RIGHT TURN LANE TO WEST BOUND PALOMAR AIRPORT ROAD S61 ,000 ---- PALOMAR AIRPORT ROAD AND COLLEGE BLVD IMPROVEMENTS 49S,SOO ----- PALOMAR AIRPORT ROADIEL FUERTE STREET RIGHT TURN LANE -----1,129,000 POINSETTIA LANE WIDENING-PAS EO DEL NORTE TO BATIQUITOS DRIVE (RTCIP -----980,000 SIDEWALK/STREET CONSTRUCTION-VALLEY STREET MAGNOLIA AVENUE 1,674,236 300,000 ----- SIDEWALK/STREET CONSTRUCTION PROGRAM 2,299,998 300,000 300,000 300,000 300,000 300,000 600,000 TIF TO CFD#1 -SO,OOO SO,OOO so,ooo SO,OOO SO,OOO 1,980,162 TRAFFIC IMPACT FEE UPDATE 200,000 ---- TRAFFIC MONITORING PROGRAM 1,046,900 96,000 96,000 96,000 96,000 96,000 S76,000 TOTAL PROJECT EXPENDITURES 22,645,406 1,162,000 2,877,000 3,192,000 446,000 446,000 17,312,162 ENDING FUND BALANCE NIA 10,254,734 9,388,393 7,208,686 7,758,920 8,125,878 13,774,521 TRANSNET • BIKE PRIOR YEAR 1 YEAR2 YEAR3 YEAR4 YEARS YEAR 6-1S YEARS 2016-17 2017-18 2018-19 2019-20 2020-21 2022-31 BEGINNING FUND BALANCE (1) NIA . . REVENUES TRANSNET GRANT 1,104,000 --. - TOTAL REVENUES NIA 1,104,000 CAPITAL PROJECTS CARLSBAD BLVD AND TAMARACK AVENUE PEDESTRIAN IMPROVEMENTS -1,104,000 . --. - TOTAL PROJECT EXPENDITURES 1,104,000 ENDING FUND BALANCE NIA . Item 4; pg. 31 TRANSNET-LOCAL PRIOR YEAR 1 YEAR2 YEAR3 YEAR4 YEARS YEAR 6-1S YEARS 2016-17 2017-18 2018-19 2019-20 2020-21 2022-31 BEGINNING FUND BALANCE (1) N/A 11,892,923 7,716,487 4,801,687 2,294,471 1,646,231 3,792,366 REVENUES TRANSPORTATION TAXES 3,814,000 3,9S0,200 4,092,784 4,241,760 4,396,135 42,922,215 TOTAL REVENUES N/A 3,814,000 3,950,200 4,092,784 4,241,760 4,396,135 42,922,215 CAPITAL PROJECTS ACTIVE VILLAGE CAMPAIGN 271,211 --- --- ADA IMPROVEMENT PROGRAM 750,000 250,000 250,000 250,000 170,000 -- ADAPTIVE TRAFFIC SIGNAL PROGRAM -1,200,000 -- -- CARLSBAD BLVD BRIDGE CONCRETE BARRIER POWER PLANT (LOCAL MATCH) 116,134 90,436 -- -- CARLSBAD BLVD BRIDGE CONCRETE BARRIER RAILROAD (LOCAL MATCH) 543,155 - --- CARLSBAD BLVD BRIDGE RAILING EAST SIDE AT POWER PLANT DISCHARGE 16,923 ---- CARLSBAD BLVD PEDESTRIAN LIGHTING-TAMARACK TO STATE STREET -610,000 715,000 - --- CARLSBAD BLVD REALIGNMENT 3,000,000 ----- CARLSBAD BLVD REALIGNMENT-CANNON TO MANZANO 1,000,000 -- -- CARLSBAD VILLAGE DR. & GRAND AVE. PEDESTRIAN AND CROSSING IMP. --1,320,000 -- CHESTNUT AVENUE ROAD DIET AND TRAFFIC CALMING --1,080,000 - -- CHESTNUT COMPLETE STREET 1-5 TO RAILROAD PROJECT STUDY -85,000 ---- CHRISTIANSEN AVENUE IMPROVEMENTS --310,000 - --- EL CAMINO REAL WIDENING -CASSIA RD TO CAMINO VIDA ROBLE -325,000 2,495,000 ---- EL CAMINO REAL WIDENING-SUNNY CREEK TO JACKS PAR ---- --3,143,500 EL CAMINO REAL WIDENING-TAMARACK AVENUE TO CHESTNUT AVENUE 3,925,885 --- -- KELLY DRIVE AND PARK DRIVE ROAD DIET AND MULTIUSE TRAIL -2,360,000 -1,515,000 -- PALOMAR AIRPORT ROAD/PASEO DEL NORTE LEFT TURN LANE 233,000 - --- PALOMAR AIRPORT ROAD/PASEO DEL NORTE RIGHT TURN LANE 564,000 - --- PAVEMENT MANAGEMENT PROGRAM 17,946,37S --1,SOO,OOO 1,SOO,OOO 1,SOO,OOO 1S,OOO,OOO PAVEMENT MANAGEMENT PROGRAM (NON-JURIS FEES} S,782,47S 7SO,OOO 7SO,OOO 7SO,OOO 7SO,OOO 7SO,OOO 7,SOO,OOO STATE STREET IMPROVEMENTS AT NW CORNER OF GRAND -32S,OOO --- STREET LIGHTING REPLACEMENT PROGRAM 320,000 850,000 82S,OOO 82S,OOO 82S,OOO -- VILLAGE AND BARRIO TRAFFIC CIRCLES -14S,OOO 440,000 440,000 --- VALLEY STREET ROAD DIET AND TRAFFIC CALMING -- - -1,64S,OOO - - TOTAL PROJECT EXPENDITURES 33,469,158 7,990,436 6,865,000 6,600,000 4,890,000 2,250,000 25,643,500 ENDING FUND BALANCE N/A 7,716,487 4,801,687 2,294,471 1,646,231 3,792,366 21,071,081 TRANSNET -STP PRIOR YEAR 1 YEAR2 YEAR3 YEAR4 YEARS YEAR 6-1S YEARS 2016-17 2017-18 2018-19 2019-20 2020-21 2022-31 BEGINNING FUND BALANCE (1) N/A 33,400 - REVENUES TRANSPORTATION TAXES -- - --- TOTAL REVENUES N/A - CAPITAL PROJECTS EL CAMINO REAL WIDENING-TAMARACK AVENUE TO CHESTNUT AVENUE 34S,OOO 33,400 --- TOTAL PROJECT EXPENDITURES 345,000 33,400 - ENDING FUND BALANCE N/A TRANSPORTATION DEVELOPMENT ACT (TDA} PRIOR YEAR1 YEAR2 YEAR3 YEAR4 YEARS YEAR6-1S YEARS 2016-17 2017-18 2018-19 2019-20 2020-21 2022-31 BEGINNING FUND BALANCE (1} N/A - REVENUES TRANSNET REVENUE ---- -- TOTAL REVENUES N/A CAPITAL PROJECTS CARLSBAD BLVD AND TAMARACK AVENUE PEDESTRIAN IMPROVEMENTS 192,100 ---- TOTAL PROJECT EXPENDITURES 192,100 - ENDING FUND BALANCE N/A - Item 4; pg. 32 WATER CONNECTION-POTABLE PRIOR YEAR 1 YEAR2 YEAR3 YEAR4 YEARS YEAR 6-15 YEARS 2016-17 2017-18 2018-19 2019-20 2020-21 2022-31 BEGINNING FUND BALANCE (1) N/A 25,848,386 27,777,315 29,300,383 30,018,486 30,754,414 31,327,950 REVENUES DEVELOPER FEES 3,514,129 1,523,069 718,102 735,928 573,537 20,000,646 TOTAL REVENUES N/A 3,514,129 1,523,069 718,102 735,928 573,537 20,000,646 CAPITAL PROJECTS COLLEGE BOULEVARD-CANNON ROAD TO BADGER LANE (490 ZONE) 1,090,000 ----- COLLEGE BOULEVARD-CANNON ROAD TO BADGER LANE (375 ZONE) 1,060,000 --- DESALINATED WATER FLOW CONTROL FACILITY 1,104,300 --- --- MAERKLE PUMP STATION IMPROVEMENTS 370,000 1,585,200 ---- POINSETTIA LANE-CASSIA ROAD TO SKIMMER COURT 300,000 ---- RANCHO CARLSBAD GROUNDWATER SUPPLY -----1,750,000 SAN LUIS REY MISSION BASIN GROUNDWATER SUPPLY 27,500 ---8,500,000 WATER MASTER PLAN UPDATE 700,000 --- --- TOTAL PROJECT EXPENDITURES 4,651,800 1,585,200 10,250,000 ENDING FUND BALANCE N/A 27,777,315 29,300,383 30,018,486 30,754,414 31,327,950 41,078,597 WATER CONNECTION-RECYCLED PRIOR YEAR 1 YEAR2 YEAR3 YEAR4 YEARS YEAR 6-15 YEARS 2016-17 2017-18 2018-19 2019-20 2020-21 2022-31 BEGINNING FUND BALANCE (1) N/A (338,619) 4,086,042 4,086,042 4,086,042 4,086,042 4,086,042 REVENUES RECYCLED WATER REVENUE 4,424,661 ----- TOTAL REVENUES N/A 4,424,661 -- CAPITAL PROJECTS RECYCLED WATER PHASE 3-PIPELINES 18,700,000 ----- RECYCLED WATER PHASE 3-CWRF EXPANSION 6,844,125 ---- RECYCLED WATER PHASE 3-RESERVOIR 1,500,000 ----- TOTAL PROJECT EXPENDITURES 27,044,125 - ENDING FUND BALANCE N/A 4,086,042 4,086,042 4,086,042 4,086,042 4,086,042 4,086,042 Item 4; pg. 33 WATER REPLACEMENT-POTABLE PRIOR YEAR 1 YEAR2 YEAR3 YEAR4 YEARS YEAR 6-15 YEARS 2016-17 2017-18 2018-19 2019-20 2020-21 2022-31 BEGINNING FUND BALANCE (1) N/A 9,535,591 243,591 (614,369) 267,278 (526,703) 247,715 REVENUES TRANSFER FROM OPERATING FUND 4,733,000 4,852,040 4,986,647 5,134,019 5,299,418 52,994,180 TOTAL REVENUES N/A 4,733,000 4,852,040 4,986,647 5,134,019 5,299,418 52,994,180 CAPITAL PROJECTS ABANDON POTABLE SERVICES (NEW RECYCLED SERVICES) 390,000 170,000 --- AVIARA PARKWAY AND PLUM TREE WATERLINE ---815,000 -- BUENA VISTA PUMP STATION AND FOREBAY REMOVAL 150,000 ----- CARLSBAD BOULEVARD-SOUTH OF AVENIDA ENCINAS ---280,000 670,000 - CARLSBAD BOULEVARD WATERLINE REPLACEMENT AT TERRAMAR -1,930,000 ---- CARLSBAD WATER RECYCLING FACILITY (ENCINA CAPITAL PROJECTS) 709,390 ---- CATHODIC PROTECTION PROGRAM 1,246,702 --- CRESTVIEW DRIVE TRANSMISSION MAIN 240,000 ------ CWRF-CHLORINE CONTACT TANK COVERS 765,000 ----- E TANK DECOMMISSION (THE CROSSINGS ROAD) 150,000 150,000 ---- EL CAMINO REAL AND TAMARACK PUMP STATION REMOVAL ---100,000 -- EL FUERTE AND CORINTIA STREET PRESSURE REDUCING STATION 800,000 ------ ELLERY PUMP STATION DECOMMISSION 250,000 ---- ELLERY WATER PUMP PROJECT 275,000 ------ FIRE FLOW SYSTEM IMPROVEMENTS 720,000 720,000 90,000 90,000 90,000 90,000 1,009,000 HYDROELECTRIC GENERATOR AT MAERKLE RESERVOIR 2,000,000 ----- HYDROELECTRIC GENERATOR AT PALOMAR AIRPORT ROAD/WHITE SANDS ----85,000 2,075,000 KELLY RANCH DOMESTIC WATER PRESSURE REDUCING STATION 560,000 ------ LA COSTA HIGH RESERVOIR INLET PIPELINE ---250,000 1,900,000 - LAKE CALAVERA MITIGATION -275,000 ---- LIMITED ACCESS PIPELINE RELOCATION PROGRAM 1,940,000 ----- MAERKLE FACILITY IMPROVEMENTS 2,135,200 ----- MAERKLE RESERVOIR FLOATING COVER REPLACEMENT 1,270,000 8,730,000 3,055,000 ---- MAERKLE RESERVOIR TRANSMISSION MAIN 6,330,000 ---- MAINTENANCE AND OPERATIONS CENTER 7,674,000 ----- MISCELLANEOUS PIPELINE REPLACEMENTS 1,433,000 -1,000,000 1,000,000 1,000,000 1,000,000 6,000,000 NORMALLY CLOSED VALVE (INSTALL MOTORIZED VALVE) 260,000 ---- OCEANSIDE WATER INTERTIE UPGRADE --115,000 ---- PARK DRIVE WATER LINE AND STREET IMPROVEMENTS 1,092,000 ----- PRESSURE REDUCING STATION PROGRAM 1,102,000 ------ RANCHO CARLSBAD GROUNDWATER SUPPLY -----1,750,000 RECYCLED WATER LINE-CWRF TO CHINQUAPIN 5,050,000 ----- RECYCLED WATER LINE-EL CAMINO REAL TO LA COSTA AVENUE 1,915,000 ----- RECYCLED WATER PHASE 3-CWRF EXPANSION 3,517,276 ----- RECYCLED WATER PHASE 3-PIPELINES 2,497,530 ----- RECYCLED WATER PHASE 3-RESERVOIR 300,000 ----- RESERVOIR REPAIR AND MAINTENANCE PROGRAM 4,150,000 ----1,850,000 ROBERTSON RANCH WATER TRANSMISSION MAIN 1,200,000 ----- SAN LUIS REY MISSION BASIN GROUNDWATER SUPPLY 27,500 ---8,500,000 SANTA FE II INLET PIPELINE ---470,000 2,368,000 - SANTA FE II RESERVOIR SITE DRAINAGE 645,000 ------ SANTA FE II RESERVOIR SITE ELECTRICAL IMPROVEMENTS 100,000 ----- SCADA INTEGRATED MASTER PLAN 360,000 ----- SIDEWALK/STREET CONSTRUCTION-VALLEY STREET MAGNOLIA AVENUE 291,000 (220,000) ---- TRI-AGENCY WATER TRANSMISSION PIPELINE REPLACEMENT 6,455,000 ----- WATER CONDITION ASSESSMENT PROGRAM -200,000 200,000 200,000 200,000 200,000 1,000,000 WATER SYSTEM INTERTIE CONNECTION 405,000 -- -- WATER VALVE REPAIR/REPLACEMENT PROGRAM 850,002 1,250,000 1,250,000 1,250,000 1,250,000 1,250,000 6,500,000 WATER, RECYCLED, AND SEWER MASTER PLAN -200,000 - --- - TOTAL PROJECT EXPENDITURES 58,635,600 14,025,000 5,710,000 4,105,000 5,928,000 4,525,000 28,684,000 ENDING FUND BALANCE N/A 243,591 (614,369) 267,278 (526,703) 247,715 24,557,895 Item 4; pg. 34 WATER REPLACEMENT-RECYCLED PRIOR YEAR 1 YEAR2 YEAR3 YEAR4 YEARS YEAR 6-15 YEARS 2016-17 2017-18 2018-19 2019-20 2020-21 2022-31 BEGINNING FUND BALANCE (1) N/A 12,597,759 13,187,159 14,012,499 14,877,801 15,786,853 16,745,008 REVENUES TRANSFER FROM OPERATING FUND 1,140,000 1,175,340 1,215,302 1,259,052 1 ,308,155 13,081,550 TOTAL REVENUES N/A 1,140,000 1,175,340 1,215,302 1,259,052 1,308,155 13,081,550 CAPITAL PROJECTS RECYCLED WATER CONDITION ASSESSMENT PROGRAM -200,000 200,000 200,000 200,000 200,000 1,000,000 CARLSBAD WATER RECYCLING FACILITY (ENCINA CAPITAL PROJECTS) -70,600 100,000 100,000 100,000 100,000 1,000,000 RECYCLED WATER VALVE & APPURTENANCE REPLACEMENT PROGRAM -50,000 50,000 50,000 50,000 50,000 500,000 SCADA INTEGRATED MASTER PLAN -80,000 ----- WATER, RECYCLED, AND SEWER MASTER PLAN 150,000 ----- TOTAL PROJECT EXPENDITURES 550,600 350,000 350,000 350,000 350,000 2,500,000 ENDING FUND BALANCE N/A 13,187,159 14,012,499 14,877,801 15,786,853 16,745,008 27,326,558 CHECK TOTAL BEG FUND BALANCE 282,675,959 282,675,959 CHECK TOTALS-REVENUES 51,672,799 36,887,528 32,548,924 34,830,880 35,486,741 451,376,007 51,672,799 36,887,528 32,548,924 34,830,880 35,486,741 451,376,007 CHECK TOTALS-EXPENDITURES 466,211,166 64,389,457 28,737,483 26,757,455 24,586,586 23,544,078 295,185,226 462,278,553 June 7, 2016 City Council Workshop Proposed FY 2016-17 to 2031 Capital Improvement Program Agenda •CIP process •Development projections •15 year outlook •1 year plan •Information about specific projects –Projects put into service 15-16 –City Council Goal projects –Projects of note –Complete list of new projects Budget Calendar Council meetings: •June 7 –Capital Improvement Program Workshop •June 14 –Operating Budget Workshop •June 28 –Public Hearing and Adoption of Operating and Capital Budget for Fiscal Year 2016-17 Other public meetings: •June 21 –Citizens’ Budget Workshop Citizens Budget Workshop When:Tuesday, June 21 Where:City of Carlsbad Faraday Center 1635 Faraday Avenue Room 173B Time:6 p.m. For additional information: City of Carlsbad Finance Department 760-602-2430 CIP Projects •Council Priority Projects •Community Vision •Legal Mandates •Growth Management Plan –Development Fee Programs –Facility Master Plans •Asset maintenance programs, inspection of facilities CIP Review Process and Criteria CIP Review Committee •Project criteria: –Safety –Council Priority Projects –Community Vision –Growth management –Availability of resources –Construction schedules Growth Management Plan City Administrative Drainage Wastewater Treatment Open Space Circulation Sewer Collection Fire Schools Parks Water Library Development Projections •Residential •Non-residential •Fees paid when building permits issued •Fees pay for facilities •Revenues & Expenditures ==> cash flows •Ensure funding available when projects planned Residential Development FY 2016-2017 = 755 Next 5 Years = 1671 Quarry Creek Robertson Ranch Village Misc. La Costa Oaks Poinsettia 61 Residential 1 3 2 5 Projects = 1603 of 1671 Residential Units / next 5 Years 2 3 1 4 5 5 4 Non-Residential Development FY 2016-17 = 601,098 Next 5 Years = 1,577,000 Non-Residential Development (square feet) •Lego Hotel (137,700) •North Urban Farms (61,464) •Carlsbad Oaks –commercial and industrial (360,998) •Viasat expansion (500,077) •Home 2 Carlsbad Suites (83,761) •Lot 9/Westin (121,450) Capital Project Funds Revenues -Next 15 years 13 Funding Sources Total Revenue = $643 Million (through 2031) $0 $50 $100 $150 $200 Development Fees Special Districts Utility Infrastructure Replacement Infrastructure Replacement Other Sources $ In millions Development Impact Fees $163 Million $0 $50 $100 $150 $200 Development Fees Special Districts Utility Infrastructure Replacement Infrastructure Replacement Other Sources $ In millions Special Districts $31 Million $0 $50 $100 $150 $200 Development Fees Special Districts Utility Infrastructure Replacement Infrastructure Replacement Other Sources $ In millions Utility/Infrastructure Replacement Funds $347 Million $0 $50 $100 $150 $200 Development Fees Special Districts Utility Infrastructure Replacement Infrastructure Replacement Other Sources $ In millions Other Revenue Funds $102 Million $0 $50 $100 $150 $200 Development Fees Special Districts Utility Infrastructure Replacement Infrastructure Replacement Other Sources $ In millions Total Project Expenditures FY 2016-17 to 2031 -$463 Million 0 20 40 60 80 100 120 140 $ In millions Revenues and Expenditures FY 2016-17 FY 2016-17 Revenues $51.7 Million 35% 2% 20% 18% 25% Infrastructure Repl. $9.5 M Water and Sewer Replacement $10.2 M Special Dist. $1 M Other Agencies $12.9 M Developer fees $18.1 M FY 2016-17 New Appropriations $64.4 Million Civic & Other, $9.9M, 16% Drainage, $2.3M, 4% Parks, $1.8M, 3% Water, $16.4M, 26% Sewer,$8.6M, 25% Streets,$25.4 M, 39% FY 2016-17 Total Appropriations New appropriations $ 64.4 million Continuing projects (*) $ 247.3 million Total capital budget $ 311.7 million (*) includes encumbrances FY 2016-17 Carry forward projects -$311.7 Million •Maintenance and Operations Center ($26 M) •Parks -Pine, Aviara, Poinsettia, Leo Carrillo ($18.2 M) •Drainage Projects ($7.6 M) •Sewer Projects ($64.5 M) •Water Projects ($72.7 M) •Street Projects ($50.8 M) 24 Capital Improvement Program •20 Projects put into service in FY 15/16 Projects Put Into Service in FY 2015/16 •Police and Fire Facilities –Fire Station Number 3 (Robertson Ranch) •Library Facilities –Cole Library –Dove Library •Facility Maintenance –Safety Training Center Solar Photo Voltaic •Parks –Aviara Comm. Park Soccer Field Synthetic Turf Replacement –Village Streetscape, Phase 2 •Drainage –Northwest Quadrant Storm Drain Program -Grand Avenue –CMP Replacement Program –La Gran Via –Romeria Drainage and La Costa Slope Repair •Transportation –2015 Concrete Repair Program –2015 Slurry Seal Program –2015 Overlay (Desal pipeline alignment) –Faraday Avenue Fiber Optic –Coastal Corridor Mobility Readiness Plan Projects Put Into Service in FY 2015/16 (Cont.) •Sewer –Buena Interceptor Sewer Improvements, Odor Control •Water –Tri-Agencies Water Transmission Main, Reach 2 Phase 1 –Ellery Pump Station Decommission •Recycled Water –Recycled Water Transmission Main, ECR -Alga Road to La Costa Avenue –Recycled Water pipeline, Palmer and Impala –Recycled Water Phase III pipeline expansion, Segments 1A and 7 Projects Put Into Service in FY 2015/16 (Cont.) City Council Goal: 29 Become a leader in multimodal transportation systems and creative approaches to moving people and goods through and within Carlsbad. –Chestnut, Valley Street to I-5 complete street –Carlsbad Blvd. Realignment, Manzano to southerly city limit –Kelly Drive and Park Drive complete street and multi use trail –Chestnut Avenue, I-5 to Railroad complete street study –Adaptive Traffic Signal Program City Council Goal: 30 Enhance Carlsbad’s coastline to ensure an exceptional experience in all the ways people want to enjoy it. –Ocean Street Beach Access Improvements –Carlsbad Blvd. and Tamarack Improvements –Terramar Coastal Improvements –Carlsbad Blvd. Realignment –Ocean Street Project Study Report –Carlsbad Blvd. Pedestrian Lighting -Tamarack Ave. to north city limit City Council Goal: 31 Enhance the health and vitality of the Village and Barrio, two neighborhoods that represent the historic heart of Carlsbad. –Village Decorative Lighting –Barrio Street Lighting –ADA Improvement Program –Village Public Gathering Spaces Study –Utility Undergrounding Program Study City Council Goal: 32 Lower the railroad tracks in a trench through the Village to improve safety, community connectivity, quality of life and economic value. –Railroad Double Tracking Plan for a new city hall that will meet the future workplace and operational needs of the city and the community. –Future space needs analysis for city staff and community meeting space Other Projects / Programs of Note •Facilities –Maintenance and Operations Center –Monroe Street Pool Replacement Project Study Report •Parks –Poinsettia Community Park Phase 3/Pickleball Courts –Ocean Street Beach Access Improvements –Robertson Ranch Master Plan 33 •Drainage –Drainage Master Plan Update –Drainage Master Plan Wetland Creation –Storm Drain Condition Assessment Program •Transportation –Pavement Management Program –Bridge Preventive Maintenance Program •Sewer/Water/Recycled Water –Master Plan Updates –Condition Assessment Programs Poinsettia Park Pickleball Courts Location-east of existing tennis court complex (original master plan location for stadium court 6 lighted regulation size courts Includes fencing and bleachers Budget amount requested: $472,000 Projects removed •Alga Norte Phase 2 From Unfunded List: •Agua Hedionda Channel •Cannon Road Reach 4 •Hosp Grove/Buena Vista Lagoon Recreational Improvements •Pine Avenue Park –Madison Property Questions and Comments 36 Action Item: Set Public Hearing for June 28, 2016 37 Citizens Budget Workshop When:Tuesday, June 21 Where:City of Carlsbad Faraday Center 1635 Faraday Avenue Room 173B Time:6 p.m. For additional information: City of Carlsbad Finance Department 760-602-2430 •Extra slides –not part of presentation •Water condition assessment program •Recycled water valve and appurtenance replacement program •Bridge preventative maintenance program •Storm drain condition assessment program