HomeMy WebLinkAbout2017-11-07; City Council; ; Adopt a Resolution approving plans and specifications and authorizing advertising for bids for the Drainage Master Plan Project: BCA - Tamarack Avenue, Park Drive and Monroe StreetSeveral smaller existing storm drain systems currently serve this basin. Drainage collected by
these systems will be consolidated and then rerouted into the new storm drain pipeline
creating a comprehensive drainage network throughout the basin. The Northwest Quadrant
Storm Drain Improvement Program will fund the improvements to the existing drainage
facilities.
Upon installation of the new storm drain system, the impacted roadways will receive a 2-inch
grind and overlay consistent with and funded by the city's Pavement Management Program.
Fiscal Analysis
The total estimated construction costs for the Project is $2,941,414. A summary of estimated
construction costs and the available funds for each funding source contributing to the Project
are shown in the tables below. The first table summarizes the Pavement Management Program
portion of the Project:
PAVEMENT MANAGEMENT PROGRAM, CIP NO. 6001
Current Appropriation -Pavement Management Program, CIP No. 6001 $8,527,062
Current Year Expenditures/Encumbrances -Pavement Management Program $805,941
Fund, CIP No. 6001
TOTAL AVAILABLE PAVEMENT MANAGEMENT PROGRAM, CIP NO. 6001 $7,721,121
Construction Contract (Engineer's Estimate) $749,840
Construction Contingency (estimated) $74,984
Construction Management, Inspection and Material Testing (estimated) $149,968
TOTAL ESTIMATED CONSTRUCTION COSTS $974,792
ADDITIONAL APPROPRIATION NEEDED $0
The second table summarizes the Northwest Quadrant Storm Drain Program portion of the
Project:
NORTHWEST QUADRANT STORM DRAIN PROGRAM, CIP NO. 6608
Current Appropriation -Northwest Quadrant Storm Drain Fund, CIP No. 6608 $1,121,746
Current Year Expenditures/Encumbrances -Northwest Quadrant Storm $75,166
Drain Fund, CIP No. 6608
TOTAL AVAILABLE NORTHWEST QUADRANT STORM DRAIN, CIP NO. 6608 $1,046,580
Construction Contract (Engineer's Estimate) $598,024
Construction Contingency (estimated) $59,802
Construction Management, Inspection and Material Testing (estimated) $119,605
TOTAL ESTIMATED CONSTRUCTION COSTS $777,431
ADDITIONAL APPROPRIATION NEEDED $0
November 7, 2017 Item #7 Page 2 of 7
As summarized in the third table below Planned Local Drainage Area B Funds will fund the new
storm drain system. During the final design of the new system a detailed engineering analysis
was completed and as a result the storm drain will vary in size from 24" diameter to 36"
diameter rather than a 24" diameter pipeline for the entire system as noted in the 2008
Drainage Master Plan. In addition the existing appropriation is based on the cost estimate as
incorporated in the 2008 Drainage Master Plan which needs to be increased to 2017 dollars to
account for inflation. As a result an additional appropriation of $391,105 from the Planned
Local Drainage Area B Fund is necessary to fund the construction as shown in the following
table:
DRAINAGE MASTER PLAN PROJECT BCA, CIP NO. 6617
Current Appropriation -Drainage Master Plan Project BCA, CIP No. 6617 $1,068,613
Current Expenditures/Encumbrances to Date -Drainage Master Plan Project $270,527
BCA Fund, CIP No. 6617
TOTAL AVAILABLE DRAINAGE MASTER PLAN PROJECT BCA, CIP NO. 6617 $798,086
Construction Contract (Engineer's Estimate) $914,763
Construction Contingency (estimated) $91,476
Construction Management, Inspection and Material Testing (estimated) $182,952
TOTAL ESTIMATED CONSTRUCTION COSTS $1,189,191
ADDITIONAL APPROPRIATION NEEDED $391,105
Next Steps
A Request for Bids to construct the Project will be advertised. Responses will be evaluated and
the lowest responsive and responsible bidder will be identified by city staff. Staff will then
return to City Council with a recommendation to award the contract to the identified bidder.
Environmental Evaluation (CEQA)
On Aug. 5, 2008, the City Council adopted Resolution No. 2008-229 certifying an Environmental
Impact Report (EIR) for the Drainage Master Plan Update (EIR 04-02). This project is a sub-
component (BCA) of the Drainage Master Plan and was analyzed in the EIR (Table 4.1.2). The
analysis stated impacts in the Coastal Zone during construction activities would be short term
and minimized with implementation of the applicable project design features/methods and
construction measures identified in Table 3-6 of the project EIR. The project has been conditioned
to implement these mitigation measures and the project is within the scope of the prior
environmental document and no further environmental documentation is required per CEQA
Guidelines Section 15162.
Public Notification
This item was noticed in accordance with the Ralph M. Brown Act and was available for public
viewing and review at least 72 hours prior to the scheduled meeting date. The public will be
notified in advance of the construction activities using multiple media methods such as sign age,
email, website, and other city communication channels. The construction contractor will also be
November 7, 2017 Item #7 Page 3 of 7
required to notify the public of construction activities. A communications consultant is currently
on contract to provide public outreach services on behalf of the city during construction.
Exhibits
1. Adopt a Resolution approving the plans and specifications and authorizing the city clerk to
advertise for bids for the Drainage Master Plan Project: BCA -Tamarack Avenue, Park Drive
and Monroe Street, Project Nos. 6001, 6608 and 6617, and approving an additional
appropriation of Planned Local Drainage Area B funds in the amount of $391,105.
2. Location Map.
3. Project plans, specifications and contract documents are on file at the Public Works
Department of the City of Carlsbad.
November 7, 2017 Item #7 Page 4 of 7
RESOLUTION NO. 2017-213
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CARLSBAD,
CALIFORNIA, APPROVING THE PLANS AND SPECIFICATIONS AND
AUTHORIZING THE CITY CLERK TO ADVERTISE FOR BIDS FOR THE DRAINAGE
MASTER PLAN PROJECT: BCA -TAMARACK AVENUE, PARK DRIVE AND
MONROE STREET, PROJECT NOS. 6001, 6608 AND 6617, AND APPROVING
AN ADDITIONAL APPROPRIATION OF PLANNED LOCAL DRAINAGE AREA B
FUNDS IN THE AMOUNT OF $391,105.
EXHIBIT I
WHEREAS, the City Council of the City of Carlsbad, California, has determined it necessary,
desirable, and in the public interest to construct the Drainage Master Plan Project: BCA -Tamarack
Avenue, Park Drive and Monroe Street, Project Nos. 6001, 6608 and 6617 (Project); and
WHEREAS, the plans, specifications and contract documents for said Project have been
prepared and are on file in the Public Works Department of the City of Carlsbad and are incorporated by
reference herein; and
WHEREAS, the city established a Planned Local Drainage Area Fee Program for the express
purpose of funding the improvements identified in the Drainage Master Plan, which includes said
Project; and
WHEREAS, an additional appropriation of funds from the Planned Local Area B fund in the
amount of $391,105 is needed; and
WHEREAS, the Project was previously evaluated in the Final Environmental impact Report (FEIR
04-02), certified on Aug. 5, 2008 (Reso. No. 2008-229), for the City of Carlsbad Drainage Master Plan
Update and no further Environmental Quality Act (CEQA) review is required under CEQA Guidelines
Section 15162.
November 7, 2017 Item #7 Page 5 of 7
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad, California, as
follows:
1. That the above recitations are true and correct.
2. That the plans, specifications and contract documents for the Drainage Master Plan
Project: BCA-Tamarack Avenue, Park Drive and Monroe Street, Project Nos. 6001, 6608 and 6617, are
hereby approved.
3. That the Administrative Services Director is authorized to appropriate funds in the
amount of $391,105 to the Project from the Planned Local Drainage Area B fund.
4. The city clerk of the City of Carlsbad is hereby authorized and directed to publish, in
accordance with State law, a Notice to Contractors Inviting Bids for the construction of the Drainage
Master Plan Project: BCA -Tamarack Avenue, Park Drive and Monroe Street, Project Nos. 6001, 6608
and 6617, in accordance with the plans, specifications and contract documents referred to herein.
PASSED, APPROVED AND ADOPTED at a Regular Meeting of the City Council of the City of
Carlsbad on the 7th day of November 2017, by the following vote, to wit:
AYES:
NOES:
ABSENT:
M. Hall, K. Blackburn, M. Schumacher, C. Schumacher, M. Packard.
None.
None. M=J1t#I//£
Ci'4YJoM-trrl&L-¼,
BARBARA ENGLESON, City Clerk (). '-
(SEAL)
November 7, 2017 Item #7 Page 6 of 7