HomeMy WebLinkAbout2018-05-22; City Council; ; Plans and specifications and authorization for the city clerk to advertise for bids for the Palomar Airport Road Widening at Paseo Del Norte~ CITY COUNCIL
~ Staff Report
Meeting Date:
To:
From:
Staff Contact:
May 22, 2018
Mayor and City Council
Kevin Crawford, City Manager
Daniel Zimny, Assistant Engineer
Daniel.Zimny@carlsbadca.gov or 760-602-7551
CA Review ..Ji!;_
Subject: Plans and specifications and authorization for the city clerk to advertise
for bids for the Palomar Airport Road Widening at Paseo Del Norte.
Recommended Action
Adopt a Resolution approving the plans and specifications and authorizing the city clerk to
advertise for bids for the Palomar Airport Road Widening at Paseo Del Norte, Project Nos. 6043
and 6044 (Project), and approving an additional appropriation of Transnet Local Funds in the
amount of $388,000.
Executive Summary
The Project is located at the intersection of Palomar Airport Road at Paseo Del Norte and will
enhance the performance of the left turn and right turn movements from eastbound Palomar
Airport Road to Paseo Del Norte. The left turn modification, identified as Capital Improvement
Project (CIP) No. 6043, will extend the existing left turn pocket from eastbound Palomar Airport
Road to northbound Paseo Del Norte. The right turn lane improvement, identified as CIP No.
6044, will create a new dedicated right turn lane from eastbound Palomar Airport Road to
southbound Paseo Del Norte. The Carlsbad Municipal Code requires the City Council to adopt
plans and specifications for all construction projects that are to be formally bid when the value
exceeds the limits established by the Public Contract Code including the alternative provisions
of the Uniform Public Construction Cost Accounting Act. The Public Contract Code limit is
$175,000. The construction cost estimates for these two Projects are $178,345 and $845,000
respectively, and therefore this Project is subject to this requirement.
Discussion
Two separate CIP projects will fund the proposed improvements along eastbound Palomar
Airport Road at Paseo Del Norte. The left turn lane improvements, identified as CIP No. 6043,
will extend the existing left turn pocket 175 feet by removing a portion of the raised concrete
median. The right turn lane improvement, identified as CIP No. 6044, will create a new
dedicated right turn lane. The new right turn lane will be 250 feet in length and within public
right of way that was dedicated by the adjacent private developers as a condition of their
previous development approvals. In addition to the turn lane improvements, the Project
includes related traffic signal modification, pedestrian upgrades, Class II bike lane, and storm
water quality improvements, all of which will improve the level of service at the intersection for
all modes of travel.
May 22, 2018 Item #4 Page 1 of 6
Fiscal Analysis
The total estimated construction costs for the Project is $1,023,345. A summary of estimated
construction costs and the available funds for each funding source contributing to the Project
are shown in the tables below. The first table summarizes the CIP No. 6043 contribution to the
Project, which is funded by Transnet Local Funds:
PALOMAR AIRPORT ROAD AND PASEO DEL NORTE LEFT TURN LANE, CIP NO. 6043
Current to Date Appropriation -Palomar Airport Road and Paseo Del Norte $233,000 Left Turn Lane, CIP No. 6043
Current to Date Expenditures/Encumbrances -Palomar Airport Road and $76,655 Paseo Del Norte Left Turn Lane, CIP No. 6043
TOTAL AVAILABLE PALOMAR AIRPORT ROAD LEFT TURN LANE, PROJECT $156,345 NO. 6043
Construction Contract (Estimated) $132,000
Construction Contingency (Estimated) $26,500
Construction Management, Inspection and Material Testing (Estimated) $19,845
TOTAL ESTIMATED CONSTRUCTION COSTS $178,345
REMAINING BALANCE AFTER PROJECT NO. 6043 -$22,000
ADDITIONAL APPROPRIATION NEEDED $22,000 ,.
The second table summarizes the CIP No. 6044 contribution to the Project, which is funded by
Transnet Local Funds:
PALOMAR AIRPORT ROAD AND PASEO DEL NORTE RIGHT TURN LANE, CIP NO. 6044
Current to Date Appropriation -Palomar Airport Road and Paseo Del Norte $564,000 Right Turn Lane, CIP No. 6044
Current to Date Expenditures/Encumbrances -Palomar Airport Road and $85,000 Paseo Del Norte Right Turn Lane, CIP No. 6044
TOTAL AVAILABLE PALOMAR AIRPORT ROAD RIGHT TURN LANE, PROJECT $479,000 NO. 6044
Construction Contract (Estimated) $625,000
Construction Contingency (Estimated) $125,000
Construction Management, Inspection and Material Testing (Estimated) $95,000
TOTAL ESTIMATED CONSTRUCTION COSTS $845,000
REMAINING BALANCE AFTER PROJECT NO. 6044 -$366,000
ADDITIONAL APPROPRIATION NEEDED $366,000
May 22, 2018 Item #4 Page 2 of 6
Next Steps
A Request for Bids to construct the Project will be advertised. Responses will be evaluated and
the lowest responsive and responsible bidder will be identified by city staff. Staff will then
return to City Council with a recommendation to award the contract to the identified bidder.
The typical time from authorization to bid to the execution of the construction contract is four
to six months and the construction contract for this Project provides for three and a half
months to construct the Project improvements.
Environmental Evaluation (CEQA)
The Project is exempt from the California Environmental Quality Act (CEQA) per State CEQA
Guidelines Section 15301(c) -Minor alteration of existing facilities, including streets, sidewalks,
gutters, and similar facilities involving negligible expansion. A Notice of Exemption was filed in
the office of the San Diego County Clerk on Feb. 20, 2018 for a 30-day public review.
Public Notification
This item was noticed in accordance with the Ralph M. Brown Act and was available for public
viewing and review at least 72 hours prior to the scheduled meeting date. The public will be
notified in advance of the construction activities using multiple media methods such as sign age,
email, website, and other city communication channels. The construction contractor will also be
required to notify the public of construction activities.
Exhibits
1. City Council Resolution.
2. Location Map.
3. Contract documents, including plans and specifications, are on file at the Public Works
Department of the City of Carlsbad.
May 22, 2018 Item #4 Page 3 of 6
RESOLUTION NO. 2018-075
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CARLSBAD,
CALIFORNIA, APPROVING THE PLANS AND SPECIFICATIONS AND
AUTHORIZING THE CITY CLERK TO ADVERTISE FOR BIDS FOR THE PALOMAR
AIRPORT ROAD WIDENING AT PASEO DEL NORTE, PROJECT NOS. 6043 AND
6044, AND APPROVING AN ADDITIONAL APPROPRIATION OF TRANSNET
LOCAL FUNDS IN THE AMOUNT OF $388,000.
EXHIBIT I
WHEREAS, the City Council of the City of Carlsbad, California, has determined it necessary,
desirable, and in the public interest to construct the Palomar Airport Road Widening at Paseo Del
Norte, Project Nos. 6043 and 6044 (Project); and
WHEREAS, the plans, specifications and contract documents for the Project are on file in the
Public Works Department of the City of Carlsbad and are incorporated by reference herein; and
WHEREAS, the Project is exempt from CEQA per State CEQA Guidelines Sections 15301(c)
(Existing streets, sidewalks, gutters, bicycle and pedestrian trails, and similar facilities); and
WHEREAS, an additional appropriation of funds from the Transnet Local Fund in the amount of
$388,000 is needed.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad, California, as
follows:
1. That the above recitations are true and correct.
2. That the plans and specifications for the Palomar Airport Road Widening at Paseo Del
Norte, Project Nos. 6043 and 6044, are hereby approved.
3. That the administrative services director is authorized to appropriate funds in the
amount of $388,000 to the Project from the Transnet Local Fund.
4. The city clerk of the City of Carlsbad is hereby authorized and directed to publish, in
accordance with State law, a Notice to Contractors Inviting Bids for the construction of the Palomar
Airport Road Widening at Paseo Del Norte, Project Nos. 6043 and 6044, in accordance with the plans,
specifications, and contract documents referred to herein.
•
May 22, 2018 Item #4 Page 4 of 6
PASSED, APPROVED AND ADOPTED at a Regular Meeting of the City Council of the City of
Carlsbad on the 22nd day of May, 2018, by the following vote, to wit:
AYES:
NOES:
ABSENT:
M. Hall, K. Blackburn, M. Schumacher, C. Schumacher, M. Packard.
None.
None.
(SEAL)
May 22, 2018 Item #4 Page 5 of 6