HomeMy WebLinkAbout2020-06-02; City Council; ; Public Hearing on TransNet Local Street Improvement Program of Projects for Fiscal Years 2020-21 through 2024-25CA Review __RC__
Meeting Date: June 2, 2020
To: Mayor and City Council
From: Scott Chadwick, City Manager
Staff Contact: Jonathan Schauble, Senior Engineer
jonathan.schauble@carlsbadca.gov, 760-602-2762
Subject: Public Hearing on TransNet Local Street Improvement Program of
Projects for Fiscal Years 2020-21 through 2024-25
Recommended Action
Hold a public hearing and adopt a resolution approving the Carlsbad TransNet Local Street
Improvement Program of Projects for fiscal years 2020-21 through 2024-25 for inclusion in the
2020 update to the TransNet Program of Projects, which will be programmed as Amendment
No. 14 to the 2018 San Diego Association of Governments Regional Transportation
Improvement Program.
Executive Summary
To use county TransNet1 funds for local transportation projects, cities and other member
agencies of San Diego Association of Governments, or SANDAG, must approve programs of
projects every two years. These programs, which list local transportation projects, are then
incorporated into the TransNet Program of Projects, a program of proposed highway, arterial
roadway, transit and bikeway projects for the entire county.
In addition to projects using TransNet Funds, each agency’s program of projects must also
include transportation projects that are regionally significant and increase transportation
capacity, regardless of their funding sources.
To obtain the TransNet funding for Carlsbad projects, the City Council is required to hold a
public hearing to consider and approve the Carlsbad Program of Projects. The signed resolution
(Exhibit 1) approving the Carlsbad program is due to SANDAG by June 17, 2020. The city’s
program will then be incorporated into SANDAG’s amendment to the 2018 Regional
Transportation Improvement Program and submitted to the state for approval.
Staff recommends approval of the Carlsbad TransNet Local Street Improvement Program of
Projects for fiscal years 2020-21 through 2024-25 for inclusion in the 2020 update to the
TransNet Program of Projects for the entire county.
1 TransNet is a countywide transportation sales tax first approved by county voters in 1987.
June 2, 2020 Item #6 Page 1 of 11
Discussion
Background
SANDAG, as the Regional Transportation Commission, is required by state and federal laws to
develop and adopt an updated Regional Transportation Improvement Program every two years.
This is a multi-year list of projects submitted by cities and other jurisdictions in the county
identifying transportation projects that are eligible to use the sales tax funds generated through
TransNet.
In addition to the federal and state requirements, the San Diego Transportation Improvement
Program Ordinance and Expenditure Plan2 requires that SANDAG prepare a five-year TransNet
Program of Projects, also every two years.
Each member agency of SANDAG that wants to spend TransNet and/or certain federal or state
funds must approve its own program of projects every two years. In addition to the projects
using those funding sources, the program must include projects that will increase
transportation capacity, regardless of their funding sources. The federal Metropolitan Planning
and Air Quality Conformity Regulations also require inclusion of all capacity-increasing road
projects for air quality emissions modeling and analysis.
The City Council approved the city’s 2018 submission of program of projects on June 12, 2018,
(Resolution No. 2018-100) and that program was then incorporated into SANDAG’s 2018
Regional Transportation Improvement Program.
This year’s update
The 2020 update to the program covers fiscal years 2020-21 to 2024-25. The Regional
Transportation Improvement Program is being amended rather than formally updated this year
as a result of a change in federal law.
On Sept. 27, 2019, the U.S. Environmental Protection Agency and the National Highway Traffic
Safety Administration issued the Safer Affordable Fuel-Efficient Vehicle Rule – One National
Program. This rule went into effect on Nov. 26, 2019. The rule revoked California’s authority to
set its own greenhouse gas emission standards and zero-emission vehicle mandates. Because
California greenhouse gas standards and zero-emission vehicle mandates are included in the
emissions modeling tool developed by the California Air Resources Board and approved by the
EPA for use in determining air quality conformity in California, the tool can no longer be used to
show that transportation improvement plans meet air quality requirements.
That change led the California Department of Transportation to cancel the scheduled biennial
update to the current 2018 Regional Transportation Improvement Program.
So, to meet the requirements of the TransNet Extension Ordinance, SANDAG will prepare an
update to the TransNet Program of Projects covering the five-year period from fiscal year 2020-
2 The TransNet Extension Ordinance, approved by San Diego County voters in 2004, extended the initial San Diego
Transportation Improvement Program Ordinance (Proposition A, 1987) for a forty-year period commencing on
April 1, 2008.
June 2, 2020 Item #6 Page 2 of 11
21 through fiscal year 2024-25. This update will be programmed as an amendment to the 2018
Regional Transportation Improvement Program, which will continue until further direction is
provided by Caltrans. This will be Amendment No. 14 to the 2018 Regional Transportation
Improvement Program.
The SANDAG Board of Directors, acting as the San Diego County Regional Transportation
Commission, approves the TransNet Program of Projects as an element of the Regional
Transportation Improvement Program. The 2020 TransNet Program of Projects is scheduled for
consideration by the SANDAG Board of Directors on Sept. 11, 2020.
Carlsbad’s proposed Program of Projects
The proposed Carlsbad Program for fiscal years 2020-21 through 2024-25 (Exhibit 1,
Attachment A) includes projects with the following funding sources: • Federal funds – administered by Caltrans
• TransNet Local Street Improvement Funds – administered by SANDAG
• Local funds from the city’s funds, including traffic impact fees and gas tax
• Local funds from developers
Federal funds included in the program are from the Safe, Accountable, Flexible, Efficient
Transportation Equity Act: A Legacy for Users High Priority Project Funds that were repurposed
for the El Camino Real Widening Project from Cassia Road to Camino Vida Roble.
TransNet Local Funds are programmed for a variety of projects, including Americans with
Disabilities Act improvements, various roadway improvements, pavement management
program, traffic signal improvements and roadway lighting projects.
The city program of projects also includes various capacity-increasing roadway projects along
regionally significant arterial roadways, regardless of the funding source. Some of these
projects are funded by city funds such as traffic impact fees or funding from adjacent private
development. New projects added to the city’s 2020 program in this category include:
Widening El Camino Real from Sunny Creek Road to Jackspar Drive by adding an
additional through lane (Capital Improvement Program Project No. 6094, previously
presented to the City Council on May 5, 2020, and rescheduled for City Council
consideration on June 9, 2020)
Widening southbound Melrose Drive at Palomar Airport Road to provide an additional
through-lane (CIP Project No. 6034, Resolution No. 2019-270)
Widening southbound College Boulevard at Palomar Airport Road to add an additional
through-lane (CIP Project No. 6028, Resolution No. 2019-270)
The program may be amended as needed on a quarterly basis during the two-year period.
These amendments must go through SANDAG’s amendment procedures for approval.
June 2, 2020 Item #6 Page 3 of 11
Funding requirements
The TransNet Extension Ordinance places certain requirements on local jurisdictions regarding
the use of TransNet funds:
No more than 30% of cumulative TransNet revenues shall be spent on local street and
road maintenance projects.
All new projects or major reconstruction projects funded by TransNet revenues shall
accommodate travel by pedestrians and bicyclists. Any deviation from this requirement
shall be clearly noticed as part of that local jurisdiction’s public hearing process.
The required minimum annual level of local discretionary funds to be expended for
street and road purposes will be met throughout the five-year period consistent with
the most recent Maintenance of Effort Requirements adopted by SANDAG.
Local jurisdictions must collect an amount equivalent to $2,583.82, plus all applicable
annual increases, from the private sector for each newly constructed residential housing
unit in that jurisdiction, unless exempted under the TransNet Extension Ordinance, and
shall contribute these funds to the Regional Transportation Congestion Improvement
Program.
Local jurisdictions must establish a separate Transportation Improvement Account for
TransNet revenues with the interest earned spent only for those purposes for which the
funds were allocated.
Each project of $250,000 or more will be clearly designated during construction with
TransNet project funding identification signs.
Fiscal Analysis
Approving the Regional Transportation Improvement Program is a requirement under state law
for receiving TransNet, state or federal funds. Approval of the Regional Transportation
Improvement Program ensures eligibility for funding and programs the funding for future
obligations.
Inclusion in the Regional Transportation Improvement Program, however, is not a guarantee
that projects will receive the stated funding. The amounts shown in Attachment A to the
Resolution are the best available estimates of project costs and anticipated funding. The city is
not obligated to proceed with a project included in the Regional Transportation Improvement
Program if funding falls short or is not available.
Next Steps
Staff will submit the necessary documents to SANDAG, which will qualify the city to receive
TransNet, state and federal funds.
Environmental Evaluation (CEQA)
This activity is statutorily exempt from the California Environmental Quality Act under CEQA
Guidelines Section 15276, which states that the act does not apply to adoption of a regional
transportation improvement program. However, individual projects developed as part of these
programs remain subject to CEQA.
June 2, 2020 Item #6 Page 4 of 11
Public Notification
Public notice of this item was published in accordance with the Ralph M. Brown Act and,
because this item is a public hearing, notice was posted 10 days before the scheduled meeting
date.
Exhibits
1. City Council Resolution
June 2, 2020 Item #6 Page 5 of 11
RESOLUTION NO. 2020-096
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CARLSBAD,
CALIFORNIA, APPROVING THE CARLSBAD TRANSNET LOCAL STREET
IMPROVEMENT PROGRAM OF PROJECTS FOR FISCAL YEARS 2020-21
THROUGH 2024-25 FOR INCLUSION IN THE 2020 UPDATE TO THE TRANSNET
PROGRAM OF PROJECTS WHICH WILL BE PROGRAMMED AS AMENDMENT
NO. 14 TO THE 2018 SAN DIEGO ASSOCIATION OF GOVERNMENTS
(SANDAG) REGIONAL TRANSPORTATION IMPROVEMENT PROGRAM (RTIP).
Exhibit 1
WHEREAS, on Nov. 4, 2004, the voters of San Diego County approved the San Diego
Transportation Improvement Program Ordinance and Expenditure Plan (TransNet Extension
Ordinance); and
WHEREAS, the TransNet Extension Ordinance provides that SANDAG, acting as the !Regional
Transportation Commissionj[PGIJ, shall approve every two years a multi-year program of projects
submitted by local jurisdictions identifying those transportation projects eligible to use transportation
sales tax (i.e., TransNet) Funds; and
WHEREAS, the City of Carlsbad was provided with an estimate of annual TransNet local street
improvement revenues for fiscal years 2020-21 through 2024-25; and
WHEREAS, the City of Carlsbad has held a noticed Public Hearing with an agenda item that
clearly identified the proposed list of projects prior to approval of the projects by its authorized
legislative body, City Council, in accordance with Section 5(A) of the TransNet Extension Ordinance and
Rule 7 of SAN DAG Board Policy No. 31.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad, California, as
follows:
1. That the above recitations are true and correct.
2. ~hat pursuant to Section 2(C)(l) of the TransNet Extension Ordinance, the City of
Carlsbad certifies that no more than 30% of its cumulative revenues shall be spent on
local street and road maintenance projects.j[PmJ
3. That pursuant to Section 4(E)(3) of the TransNet Extension Ordinance, the City of
Carlsbad certifies that all new projects, or major reconstruction projects, funded by
TransNet revenues shall accommodate travel by pedestrians and bicyclists, and that any
exception to this requirement permitted under the Ordinance and proposed shall be
clearly noticed as part of the City of Carlsbad's public hearing process.
June 2, 2020 Item #6 Page 6 of 11
4. That pursuant to Section 8 of the TransNet Extension Ordinance, the City of Carlsbad
certifies that the required minimum annual level of local discretionary funds to be
expended for street and road purposes will be met throughout the five-year period
consistent with the most recent Maintenance of Effort Requirements adopted by
SANDAG.
5. That pursuant to Section 9A of the TransNet Extension Ordinance, the City of Carlsbad
certifies that it will exact an amount equivalent to $2,583.82, plus all applicable annual
increases, from the private sector for each newly constructed residential housing unit in
that jurisdiction (unless exempted under the TransNet Extension Ordinance,) and shall
contribute such exactions to the Regional Transportation Congestion Improvement
Program (RTCIP).
6. That pursuant to Section 13 of the TransNet Extension Ordinance, the City of Carlsbad
certifies that it has established a separate Transportation Improvement Account for
TransNet revenues with interest earned expended only for those purposes for which the
funds were allocated.
7. That pursuant to Section 18 of the TransNet Extension Ordinance, the City of Carlsbad
certifies that each project of $250,000 or more will be clearly designated during
construction with TransNet project funding identification signs.
8. That the City of Carlsbad does hereby certify that all other applicable provisions of the
TransNet Extension Ordinance and SANDAG Board Policy No. 31 have been met.
9. That the City of Carlsbad agrees to indemnify, hold harmless, and defend SAN DAG, the
San Diego County Regional Transportation Commission, and all officers and employees
thereof against all causes of action or claims related to City of Carlsbad's TransNet
funded projects.
10. That the Carlsbad TransNet Local Street Improvement Program of Projects for fiscal
years 2020-21 to 2024-25 attached to this Resolution as Attachment A is hereby
approved for inclusion in the 2020 San Diego Association of Governments Regional
Transportation Improvement Program.
June 2, 2020 Item #6 Page 7 of 11
PASSED, APPROVED, AND ADOPTED at a _Special Meeting of the City Council of the City of
Carlsbad on the 2nd day of June 2020, by the following vote, to wit:
AYES:
NAYS:
ABSENT:
Hall, Blackburn, Bhat-Patel, Schumacher.
None.
None.
MATT HALL, Mayor
(SEAL)
June 2, 2020 Item #6 Page 8 of 11
CIP#
RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL
CB04B El Camino Real and
Cannon Road
Intersection of El Camino Real and Cannon Road in Carlsbad, along the
northbound side of El Camino Real just south of Cannon Road, re-stripe
to provide three through lanes, add a separate ped/bike bridge structure on the northbound side of El Camino Real over Agua Hedionda Creek.TransNet LSI $0 6042
TransNet - LSI: CR Local Funds $913 $2,402 $3,315
TOTAL $913 $2,402 $0 $0 $0 $0 $3,315
RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL
CB12 College Boulevard Reach
A
College Boulevard from Badger Lane to Cannon Road (.8 miles) in
Carlsbad, construct a new segment of College Blvd to provide 4-lane
roadway with raised median, bike lanes and sidewalks/trails in accordance with major arterial standards.TransNet LSI $0 3636
TN LSI CarryOver $1,205 $1,205
TransNet - LSI: CR Local Funds $418 $1,295 $1,500 $1,500 $24,087 $28,800
TOTAL $418 $2,500 $1,500 $1,500 $0 $24,087 $30,005
RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL
CB13 Poinsettia Lane Reach E Poinsettia Lane from Cassia Drive to Skimmer Court (.3 miles) in
Carlsbad, construct new 4-lane roadway with median, bike lanes, and
sidewalks/trails to major arterial standards.TransNet LSI $0 3922
TransNet - LSI: CR PROJECT COMPLETED IN 2020 - Expected to be opened in October 202 Local Funds $14,081 $14,081
TOTAL $14,081 $0 $0 $0 $0 $0 $14,081
RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL
CB20 Pavement Management -
Overlay
On various streets throughout the City, pavement overlay 1 inch or
greater and miscellaneous roadway section spot repairs.TransNet LSI $1,500 $1,500 $1,500 $4,500 6001
TN LSI CarryOver $0
TransNet - LSI: CR Local Funds $3,500 $3,500 $2,000 $2,000 $2,000 $13,000
TOTAL $3,500 $3,500 $3,500 $3,500 $3,500 $17,500
RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL
CB21 Pavement Management -
Slurry Seal
Along various roadways, construct/apply street sealing and
construct minor roadway pavement section repairs. TransNet LSI $0 6001
TransNet - LSI: Maint Local Funds $1,000 $1,000 $1,000 $1,000 $1,000 $5,000
TOTAL $1,000 $1,000 $1,000 $1,000 $1,000 $5,000
RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL
CB22 Avenida Encinas - Widen
from Palomar Airport Road
to Embarcadero Lane
Avenida Encinas from Palomar Airport Road southerly to existing
improvements adjacent to the Embarcadero Lane; roadway
widening and parkway construction/improvements.TransNet LSI $0 6004
TransNet - LSI: CR Local Funds $170 $5,177 $5,347
TOTAL $170 $0 $5,177 $0 $0 $0 $5,347
RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL
CB31 El Camino Real Widening -
La Costa Ave to Arenal Road
Along El Camino Real from 700 feet north of La Costa Avenue to
Arenal Road, widening along the southbound side of the roadway
to provide three travel lanes, sidewalk, and a bike lane in
accordance with Prime Arterial Standards
TransNet LSI $0 6051
TransNet - LSI: CR Local Funds $3,200 $1,800 $5,000
TOTAL $0 $3,200 $1,800 $0 $0 $0 $5,000
RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL
CB32 El Camino Real Widening - Poinsettia Lane to Camino
Vida Roble
El Camino Real from Poinsettia Lane to Camino Vida Roble – in
Carlsbad, restripe from Poinsettia Lane to Cinnabar Way and
widen El Camino Real from Cinnabar Way to Camino Vida Roble,
along the northbound/east side of the roadway to provide three travel lanes, sidewalk, and a bike lane in accordance with Arterial
Street standards.TN LSI CarryOver $70 $1,535 $1,605 6072
TransNet - LSI: CR FED Earmark $8 $1,432 $1,440
TOTAL $78 $2,967 $0 $0 $0 $0 $3,045
RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL
CB34 Palomar Airport Road and
Paseo Del Norte Right
Turn Lane
Palomar Airport Road from I-5 to Paseo Del Norte (.1 miles) - in Carlsbad,
widening along eastbound Palomar Airport Road to provide a dedicated
right turn lane to southbound Paseo Del Norte TN LSI CarryOver $169 $841 $1,010 6044
TransNet - LSI: CR Project to be completed in 2020 Local Funds $4 $113 $117
TOTAL $173 $954 $0 $0 $0 $0 $1,127
RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL
CB35 Palomar Airport Road and
Paseo Del Norte Left Turn Lane
Palomar Airport Road from I-5 to Paseo Del Norte (.1 miles) - In
Carlsbad, lengthen the left turn pocket along eastbound Palomar Airport Road to northbound Paseo Del Norte TN LSI CarryOver $113 $60 $173 6043
TransNet - LSI: CR Project to be completed in 2020 Local Funds $7 $40 $47
TOTAL $120 $100 $0 $0 $0 $0 $220
RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL
CB36 Carlsbad Boulevard Realignment study the realignment of Carlsbad Blvd including the relocation of the southbound lanes of Carlsbad Blvd to the east and the construction of
complete street and multi use trail improvements along the coastal
corridor TransNet LSI $0 6031
TransNet - LSI: CR TN LSI CarryOver $3,000 $250 $3,250
TOTAL $3,000 $250 $0 $0 $0 $0 $3,250
2020 TransNet Program of Projects
FY 2020-21 to FY 2024-25
in '000s
City of CARLSBAD
ATTACHMENT A
June 2, 2020 Item #6 Page 9 of 11
RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL
CB37 El Camino Real and College Blvd Intersection
Improvements
Improve El Camino Real along the southbound approach to the
intersection with College Blvd. to provide three thru lanes and a
signal controlled right turn lane TransNet LSI $0 6071
TransNet - LSI: CR Local Funds $213 $813 $1,026
TOTAL $213 $813 $0 $0 $0 $0 $1,026
RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL
CB43 ADA Improvements Construct Priority Level 1 and Priority Level 2 ADA Improvements per the
City of Carlsbad Transition Plan for Public Rights-of-way TN LSI CarryOver $995 $805 $65 $130 $65 $2,060 6049
TransNet - LSI: CR Local Funds $0
TOTAL $995 $805 $65 $130 $65 $0 $2,060
RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL
CB44 Traffic Signal - RAMS City of Carlsbad annual operations and maintenance cost share for the
Regional Arterial Management System, (RAMS); TransNet - LSI RAMS
of $12 is programmed each year.TransNet LSI $12 $12 $12 $12 $12 $60
TransNet - LSI: CR Local Funds $0
TOTAL $0 $12 $12 $12 $12 $12 $60
RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL
CB45 Carlsbad Boulevard and
Tamarack Ave Pedestrian
Improvement Project (part
of lump sum V17)
Reconfigure the intersection and the approaches to the
intersection and provide enhanced facilities for pedestrians,
transit users and bicyclists; (Bike, Ped, and Neighborhood Safety
Program) SANDAG approved TransNet/ATP swap on October
TransNet BPNS $94 $960 $1,054 6058
TDA - Bicycles $0
TransNet - LSI: CR Local Funds $501 $1,075 $1,576
TOTAL $595 $2,035 $0 $0 $0 $0 $2,630
RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL
CB46 Terramar Area Complete Street Improvements in Carlsbad, construct complete street improvements including the reconfiguration of the curbline and the addition of medians, pedestrian
crossings and parkway improvements TN LSI CarryOver $1,000 $1,000 6054
TransNet - LSI: CR Local Funds $1,213 $7,437 $2,450 $11,100
TOTAL $1,213 $8,437 $2,450 $0 $0 $0 $12,100
RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL
CB47 Carlsbad Village Drive and
Grand Avenue
Improvements
in Carlsbad, provide mid-block pedestrian crossing improvements and
sidewalk/parkway improvements at the approaches to the railroad track
crossings TransNet LSI $1,320 $1,320 n/a
TransNet - LSI: CR Local Funds $0
TOTAL $0 $1,320 $0 $0 $0 $1,320
RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL
CB48 Chestnut Avenue
Complete Street
Improvements Valley
Street to I-5
in Carlsbad, complete street improvements including sidewalk
improvements and traffic calming features such as bulb outs and medians
TN LSI CarryOver $1,080 $1,080 n/a
TransNet - LSI: CR Local Funds $0
TOTAL $0 $0 $1,080 $0 $0 $0 $1,080
RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL
CB49 Kelly Drive and Park Drive
Complete Street
Improvements
in Carlsbad, complete street improvements including new curblines,
sidewalk and multi use trail improvements and traffic calming features
such as bulb outs and medians TN LSI CarryOver $575 $3,600 $4,175 6075
TransNet - LSI: CR Local Funds $130 $130
TOTAL $575 $3,730 $0 $0 $0 $0 $4,305
RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL
CB50 Valley Street Road Diet
and Traffic Calming
in Carlsbad, on Valley Street, north of Chestnut, reconfigure to a complete
street with high visibility crosswalks, mid-block bulbouts, bike lanes, and
parking in select areas.TransNet LSI $1,645 $1,645 n/a
TransNet - LSI: CR Other Subtotal $0
TOTAL $0 $0 $1,645 $0 $0 $0 $1,645
RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL
CB51 Adaptive Traffic Signal
Program
in Carlsbad, construct fiber optic communications upgrades and install
traffic measuring systems and adaptive signal control systems to
implement adpative traffic signal control along these roadways.TransNet LSI $855 $855 6326
TN LSI CarryOver $1,330 $457 $1,787
TransNet - LSI: CR Local Funds $1,000 $1,000
TOTAL $2,185 $1,457 $0 $0 $0 $0 $3,642
RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL
CB52 Carlsbad Village and
Barrio Traffic Circles
in Carlsbad, at eight intersection locations in the Village and Barrio,
construct traffic circles at key intersections to calm traffic TN LSI CarryOver $42 $983 $1,025 4015
TransNet - LSI: CR Local Funds $55 $3,095 $3,150
TOTAL $97 $4,078 $0 $0 $0 $0 $4,175
RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL
CB53 Carlsbad Blvd. Pedestrian
Roadway Lighting
in Carlsbad, install pedestrian roadway lighting TN LSI CarryOver $65 $1,260 $1,325 6068
TransNet - LSI: CR Local Funds $0
TOTAL $65 $1,260 $0 $0 $0 $0 $1,325
RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL
CB54 State Street Improvements
at Northwest Corner with
Grand Avenue
in Carlsbad, widen the roadway to accommodate additional on street
parking, close driveway access and reconstruction of the parkway to
conform with the new curbline TN LSI CarryOver $325 $325 6082
TransNet - LSI: CR Local Funds $0
TOTAL $0 $0 $325 $0 $0 $0 $325
June 2, 2020 Item #6 Page 10 of 11
RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL
CB55 Christiansen Avenue
Improvements
in Carlsbad, construct new curbline, sidewalk and parkway improvements TN LSI CarryOver $310 $310 n/a
TransNet - LSI: CR Local Funds $0 $0
TOTAL $0 $0 $310 $0 $0 $0 $310
RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL
CB56 Chestnut Avenue
Complete Street
Improvements - I-5 to the
Railroad
in Carlsbad, prepare a project study report to identify the scope of work
for the construction of complete street improvements including traffic
calming and pedestrian improvements TN LSI CarryOver $85 $85 6069
TransNet - LSI: CR Local Funds $0 $0
TOTAL $0 $0 $85 $0 $0 $0 $85
RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL
CB58 Street Light Bulb
Replacement Program
in Carlsbad, replace light bulbs with LED bulbs TransNet LSI $445 $445 6062
TN LSI CarryOver $850 $2,030 $2,880
TransNet - LSI: Maint Local Funds $320 $320
TOTAL $1,615 $0 $0 $0 $0 $0 $3,645
RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL
CB59 El Camino Real Widening -
Sunny Creek to Jackspar Along El Camino Real from Sunnycreek to Jackspar, widen along
the southbound side of the roadway to provide three travel lanes,
sidewalk, and a bike lane in accordance with Prime Arterial TransNet LSI $2,984 $2,984 6094
TransNet - LSI: CR NEW PROJECT FOR 2020 POP UPDATE TN LSI CarryOver $1,016 $1,016
TOTAL $0 $4,000 $0 $0 $0 $0 $4,000
RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL
CB60 Melrose Drive and
Palomar Airport Road Improvements
Widen southbound Melrose Drive to provide an additional through lane TransNet LSI $0 6034
TransNet - LSI: CR NEW PROJECT FOR 2020 POP UPDATE Local Funds $99 $612 $711
TOTAL $99 $612 $0 $0 $0 $0 $711
RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL
CB61 Palomar Airport Road and College Blvd
Improvements
Widen southbound College Blvd to add an additional through lane
TransNet LSI $0 6028
TransNet - LSI: CR NEW PROJECT FOR 2020 POP UPDATE Local Funds $349 $646 $995
TOTAL $349 $646 $0 $0 $0 $0 $995
Projected TransNet - LSI Revenue $2,996 $3,383 $3,683 $3,804 $3,933 $17,799
Programmed TransNet LSI $2,996 $2,977 $1,512 $1,512 $1,512 $10,509
Programmed TransNet LSI Carry Over $15,042 $1,865 $130 $65 $0 $17,102
Total TransNet Programmed $18,038 $4,842 $1,642 $1,577 $1,512 $27,611
June 2, 2020 Item #6 Page 11 of 11
NOTICE OF PUBLIC HEARING
NOTICE IS HEREBY GIVEN that the City Council of the City of Carlsbad will hold a public hearing
at the Council Chamber, 1200 Carlsbad Village Drive, Carlsbad, California, at 3:00 p.m. on
Tuesday, June 2, 2020, to consider approving the Carlsbad Transnet Local Street Improvement
Program of Projects for fiscal years 2020/21 through 2024/25 for inclusion in SANDAG's
Regional Transportation Improvement Program. The Carlsbad Program of Projects consists of
the following:
Carlsbad Program of Projects Total Cost
El Camino Real and Cannon Road $3,315,000
College Boulevard Reach A $30,005,000
Poinsettia Lane Reach E (will be completed in 2020) $14,081,000
Pavement Management — Overlay $17,500,000
Pavement Management —Seal $5,000,000
Avenida Encinas — Widen from PAR to Embarcadero Lane $5,347,000
El Camino Real Widening La Costa Avenue to Arena! Road $5,000,000
El Camino Real Widening Poinsettia Lane to Camino Vida Roble $3,045,000
Palomar Airport Road Right Turn Lane to southbound Paseo Del Norte (will be
completed in 2020)
$1,127,000
Palomar Airport Road Left Turn Lane to northbound Paseo Del Norte (will be
completed in 2020)
$220,000
Carlsbad Boulevard Realignment $3,250,000
El Camino Real and College Boulevard Intersection Improvements (will be
completed in 2020)
$1,026,000
ADA Improvements $2,060,000
Traffic Signal - RAMS $60,000
Carlsbad Blvd and Tamarack Avenue Pedestrian Improvement Project $2,630,000
Terramar Area Complete Street Improvements $12,100,000
Carlsbad Village Drive and Grand Avenue Improvements $1,320,000
Chestnut Avenue Complete Street Improvements, Valley Street to 1-5 $1,080,000
Kelly Drive and Park Drive Complete Street Improvements $4,305,000
Valley Street Road Diet and Traffic Calming $1,645,000
Adaptive Traffic Signal Program $3,642,000
Carlsbad Village and Barrio Traffic Circles $4,175,000
Carlsbad Boulevard Pedestrian Roadway Lighting $1,325,000
State Street Improvements at northwest corner with Grand Avenue $325,000
Christiansen Avenue Improvements $310,000
Chestnut Avenue Complete Street Improvement, 1-5 to the railroad $85,000
Street Light Bulb Replacement Program $3,645,000
El Camino Real Widening Sunnycreek to Jackspar $4,000,000
Melrose Drive and Palomar Airport Road Improvements $711,000
Palomar Airport Road and College Boulevard Improvements $995,000
Copies of the staff report will be available on and after May 29, 2020. If you have any questions,
please contact Jon Schauble in the Public Works Division at (760) 602-2762 or
Jon.Schauble@carlsbadca.gov.
As a result of the waivers in State of California Executive Order N-29-20, the Brown Act permits
full participation of officials in meetings through video or audio teleconference. The meeting
can be viewed online at www.carlsbadca.gov or on the City's cable channel. Those persons
wishing to speak on this proposal and or participate in the meeting are cordially invited to send
an e-mail with their comments to the City Clerk at clerk@carlsbadca.gov before the agenda
item is heard at the June 2, 2020 City Council meeting. Your comments will be transmitted to
the City Council. If you desire to have your comment read into the record at the City Council
meeting, please indicate so in the first line of your e-mail and limit your e-mail to 500 words or
less. Emails will be read for three minutes each, unless the presiding officer (usually the Mayor)
changes the time.
If you challenge the selected projects in court, you may be limited to raising only those issues
raised by you or someone else at the public hearing described in this notice, or in written
correspondence to the City of Carlsbad, Attn: Office of the City Clerk, 1200 Carlsbad Village
Drive, Carlsbad, 92008, at or prior to the public hearing.
PUBLISH: May 22, 2020
CITY OF CARLSBAD
CITY COUNCIL
Hossein Ajideh, Engineering Manager
Jonathan Schauble, Senior Engineer
June 2, 2020
Carlsbad TransNet Local Street Improvement
Program of Projects for Fiscal Years 2020-21 through
2024-25
Staff Recommendation
Hold a public hearing and adopt a resolution approving
Carlsbad TransNet Local Street Improvement Program of
Projects for FYs 2020-21 to 2024-25 for inclusion in 2020
TransNet Program of Projects, which will be programmed as
an Amendment to 2018 SANDAG Regional Transportation
Improvement Program
2
Background
•TransNet, a countywide transportation sales tax approved by San Diego County voters in 1987
•In 2004, county voters approved TransNet Extension Ordinance
extending initial San Diego Transportation Improvement Program Ordinance for a forty-year period
•SANDAG, as Regional Transportation Commission, shall approve every two years a multi-year program of projects submitted by local jurisdictions identifying projects eligible to use TransNet Funds
3
What is Carlsbad Program of Projects (POP)?
•List of local transportation projects:
–use TransNet Funds
–use Federal or State Funds
–regionally significant and increase transportation capacity
•Five-Year Program –FYs 2020-21 to 2024-25
•June 12, 2018, Council approved Carlsbad POP for incorporation into SANDAG’s 2018 Regional Transportation Improvement Program
4
Why Carlsbad POP Needs Approval?
•To use TransNet Funds, member agencies of SANDAG
are required to hold a public hearing and approve their
programs of projects every two years
•These programs are incorporated into SANDAG Program
of Projects, a regional program of proposed
transportation projects for the entire county
5
What is Regional Transportation Improvement Program
(RTIP)?
•SANDAG is required by state and federal laws to develop and adopt an updated RTIP every two years
•Five-year planning and funding document
•Identifying transportation projects submitted by local jurisdictions
•Eligible to receive funding from Federal, State, and TransNet
•RTIP may be amended between updates
6
What is New?
•RTIP is being amended not updated this year
•2019, U.S. Environmental Protection Agency (EPA) and
National Highway Traffic Safety Administration issued
the Safer Affordable Fuel-Efficient Vehicle (SAFE) Rule
•Caltrans canceled 2020 update to RTIP
7
What’s Changed for Carlsbad?
•Need to approve 2020 Carlsbad POP and submit to
SANDAG for inclusion in 2020 TransNet POP (FYs 20-21
to 24-25)
•SANDAG will not prepare a 2020 RTIP
•SANDAG will prepare a 2020 TransNet POP which will
be programmed by amending 2018 RTIP
8
New Projects in 2020 POP
1.El Camino Real Widening Project –from Sunny Creek
to Jackspar
2.Melrose Drive and Palomar Airport Road
Improvements
3.Palomar Airport Road and College Blvd
Improvements
9
Project with Federal Funds
•El Camino Real Widening Project
–From Cassia Road to Camino Vida Roble
10
Projects with TransNet Funds
•ADA Improvement Program
•Adaptive Traffic Signal Program
•Carlsbad Blvd. and Tamarack Avenue Improvements
•Carlsbad Blvd. Pedestrian Roadway Lighting –North of Tamarack Avenue
•Carlsbad Blvd. Realignment
•Carlsbad Village and Barrio Traffic Circles
•Carlsbad Village Drive and Grand Avenue Improvements
•Chestnut Avenue Improvements –Valley Street to I-5
•Chestnut Avenue Improvements - I-5 to Railroad
•Christiansen Avenue Improvements
11
Projects with TransNet Funds
•College Boulevard Reach A
•El Camino Real Widening -Cassia Rd. to Camino Vida Roble
•Kelly Drive and Park Drive Improvements
•Palomar Airport Road and Paseo Del Norte Turn Lanes
•Pavement Management Program
•State Street Improvement at Grand Avenue
•Street Light Bulb Replacement Program
•Terramar Area Coastal Improvements
•Traffic Signal –Regional Arterial Management System
•Valley Street Road Diet and Traffic Calming
12
Non-TransNet Funded Projects
•Avenida Encinas Widening –PAR to Embarcadero Lane
•El Camino Real and Cannon Road
•El Camino Real and College Blvd. Intersection
•El Camino Real Widening –La Costa Ave to Arenal
•Poinsettia Lane Reach E (expected to be completed by Oct. 2020)
13
Next Steps
•Adopt a Resolution approving Carlsbad Program of Projects
•Submit the Resolution to SANDAG by June 17, 2020
•SANDAG holds a public hearing on Sept. 4, 2020
•SANDAG Board adopts 2020 TransNet POP and approve Amendment
No. 14 to 2018 RTIP on Sept. 25, 2020
•Federal approval of Amendment No. 14 anticipated by Nov. 16, 2020
14
Staff Recommendation
Hold a public hearing and adopt a resolution approving
Carlsbad TransNet Local Street Improvement Program of
Projects for FYs 2020-21 to 2024-25 for inclusion in 2020
TransNet Program of Projects, which will be programmed
as Amendment No. 14 to 2018 SANDAG Regional
Transportation Improvement Program
15