HomeMy WebLinkAbout2020-06-02; City Council; ; Public Hearing on TransNet Local Street Improvement Program of Projects for Fiscal Years 2020-21 through 2024-25CA Review __RC__ Meeting Date: June 2, 2020 To: Mayor and City Council From: Scott Chadwick, City Manager Staff Contact: Jonathan Schauble, Senior Engineer jonathan.schauble@carlsbadca.gov, 760-602-2762 Subject: Public Hearing on TransNet Local Street Improvement Program of Projects for Fiscal Years 2020-21 through 2024-25 Recommended Action Hold a public hearing and adopt a resolution approving the Carlsbad TransNet Local Street Improvement Program of Projects for fiscal years 2020-21 through 2024-25 for inclusion in the 2020 update to the TransNet Program of Projects, which will be programmed as Amendment No. 14 to the 2018 San Diego Association of Governments Regional Transportation Improvement Program. Executive Summary To use county TransNet1 funds for local transportation projects, cities and other member agencies of San Diego Association of Governments, or SANDAG, must approve programs of projects every two years. These programs, which list local transportation projects, are then incorporated into the TransNet Program of Projects, a program of proposed highway, arterial roadway, transit and bikeway projects for the entire county. In addition to projects using TransNet Funds, each agency’s program of projects must also include transportation projects that are regionally significant and increase transportation capacity, regardless of their funding sources. To obtain the TransNet funding for Carlsbad projects, the City Council is required to hold a public hearing to consider and approve the Carlsbad Program of Projects. The signed resolution (Exhibit 1) approving the Carlsbad program is due to SANDAG by June 17, 2020. The city’s program will then be incorporated into SANDAG’s amendment to the 2018 Regional Transportation Improvement Program and submitted to the state for approval. Staff recommends approval of the Carlsbad TransNet Local Street Improvement Program of Projects for fiscal years 2020-21 through 2024-25 for inclusion in the 2020 update to the TransNet Program of Projects for the entire county. 1 TransNet is a countywide transportation sales tax first approved by county voters in 1987. June 2, 2020 Item #6 Page 1 of 11 Discussion Background SANDAG, as the Regional Transportation Commission, is required by state and federal laws to develop and adopt an updated Regional Transportation Improvement Program every two years. This is a multi-year list of projects submitted by cities and other jurisdictions in the county identifying transportation projects that are eligible to use the sales tax funds generated through TransNet. In addition to the federal and state requirements, the San Diego Transportation Improvement Program Ordinance and Expenditure Plan2 requires that SANDAG prepare a five-year TransNet Program of Projects, also every two years. Each member agency of SANDAG that wants to spend TransNet and/or certain federal or state funds must approve its own program of projects every two years. In addition to the projects using those funding sources, the program must include projects that will increase transportation capacity, regardless of their funding sources. The federal Metropolitan Planning and Air Quality Conformity Regulations also require inclusion of all capacity-increasing road projects for air quality emissions modeling and analysis. The City Council approved the city’s 2018 submission of program of projects on June 12, 2018, (Resolution No. 2018-100) and that program was then incorporated into SANDAG’s 2018 Regional Transportation Improvement Program. This year’s update The 2020 update to the program covers fiscal years 2020-21 to 2024-25. The Regional Transportation Improvement Program is being amended rather than formally updated this year as a result of a change in federal law. On Sept. 27, 2019, the U.S. Environmental Protection Agency and the National Highway Traffic Safety Administration issued the Safer Affordable Fuel-Efficient Vehicle Rule – One National Program. This rule went into effect on Nov. 26, 2019. The rule revoked California’s authority to set its own greenhouse gas emission standards and zero-emission vehicle mandates. Because California greenhouse gas standards and zero-emission vehicle mandates are included in the emissions modeling tool developed by the California Air Resources Board and approved by the EPA for use in determining air quality conformity in California, the tool can no longer be used to show that transportation improvement plans meet air quality requirements. That change led the California Department of Transportation to cancel the scheduled biennial update to the current 2018 Regional Transportation Improvement Program. So, to meet the requirements of the TransNet Extension Ordinance, SANDAG will prepare an update to the TransNet Program of Projects covering the five-year period from fiscal year 2020- 2 The TransNet Extension Ordinance, approved by San Diego County voters in 2004, extended the initial San Diego Transportation Improvement Program Ordinance (Proposition A, 1987) for a forty-year period commencing on April 1, 2008. June 2, 2020 Item #6 Page 2 of 11 21 through fiscal year 2024-25. This update will be programmed as an amendment to the 2018 Regional Transportation Improvement Program, which will continue until further direction is provided by Caltrans. This will be Amendment No. 14 to the 2018 Regional Transportation Improvement Program. The SANDAG Board of Directors, acting as the San Diego County Regional Transportation Commission, approves the TransNet Program of Projects as an element of the Regional Transportation Improvement Program. The 2020 TransNet Program of Projects is scheduled for consideration by the SANDAG Board of Directors on Sept. 11, 2020. Carlsbad’s proposed Program of Projects The proposed Carlsbad Program for fiscal years 2020-21 through 2024-25 (Exhibit 1, Attachment A) includes projects with the following funding sources: • Federal funds – administered by Caltrans • TransNet Local Street Improvement Funds – administered by SANDAG • Local funds from the city’s funds, including traffic impact fees and gas tax • Local funds from developers Federal funds included in the program are from the Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users High Priority Project Funds that were repurposed for the El Camino Real Widening Project from Cassia Road to Camino Vida Roble. TransNet Local Funds are programmed for a variety of projects, including Americans with Disabilities Act improvements, various roadway improvements, pavement management program, traffic signal improvements and roadway lighting projects. The city program of projects also includes various capacity-increasing roadway projects along regionally significant arterial roadways, regardless of the funding source. Some of these projects are funded by city funds such as traffic impact fees or funding from adjacent private development. New projects added to the city’s 2020 program in this category include:  Widening El Camino Real from Sunny Creek Road to Jackspar Drive by adding an additional through lane (Capital Improvement Program Project No. 6094, previously presented to the City Council on May 5, 2020, and rescheduled for City Council consideration on June 9, 2020)  Widening southbound Melrose Drive at Palomar Airport Road to provide an additional through-lane (CIP Project No. 6034, Resolution No. 2019-270)  Widening southbound College Boulevard at Palomar Airport Road to add an additional through-lane (CIP Project No. 6028, Resolution No. 2019-270) The program may be amended as needed on a quarterly basis during the two-year period. These amendments must go through SANDAG’s amendment procedures for approval. June 2, 2020 Item #6 Page 3 of 11 Funding requirements The TransNet Extension Ordinance places certain requirements on local jurisdictions regarding the use of TransNet funds:  No more than 30% of cumulative TransNet revenues shall be spent on local street and road maintenance projects.  All new projects or major reconstruction projects funded by TransNet revenues shall accommodate travel by pedestrians and bicyclists. Any deviation from this requirement shall be clearly noticed as part of that local jurisdiction’s public hearing process.  The required minimum annual level of local discretionary funds to be expended for street and road purposes will be met throughout the five-year period consistent with the most recent Maintenance of Effort Requirements adopted by SANDAG.  Local jurisdictions must collect an amount equivalent to $2,583.82, plus all applicable annual increases, from the private sector for each newly constructed residential housing unit in that jurisdiction, unless exempted under the TransNet Extension Ordinance, and shall contribute these funds to the Regional Transportation Congestion Improvement Program.  Local jurisdictions must establish a separate Transportation Improvement Account for TransNet revenues with the interest earned spent only for those purposes for which the funds were allocated.  Each project of $250,000 or more will be clearly designated during construction with TransNet project funding identification signs. Fiscal Analysis Approving the Regional Transportation Improvement Program is a requirement under state law for receiving TransNet, state or federal funds. Approval of the Regional Transportation Improvement Program ensures eligibility for funding and programs the funding for future obligations. Inclusion in the Regional Transportation Improvement Program, however, is not a guarantee that projects will receive the stated funding. The amounts shown in Attachment A to the Resolution are the best available estimates of project costs and anticipated funding. The city is not obligated to proceed with a project included in the Regional Transportation Improvement Program if funding falls short or is not available. Next Steps Staff will submit the necessary documents to SANDAG, which will qualify the city to receive TransNet, state and federal funds. Environmental Evaluation (CEQA) This activity is statutorily exempt from the California Environmental Quality Act under CEQA Guidelines Section 15276, which states that the act does not apply to adoption of a regional transportation improvement program. However, individual projects developed as part of these programs remain subject to CEQA. June 2, 2020 Item #6 Page 4 of 11 Public Notification Public notice of this item was published in accordance with the Ralph M. Brown Act and, because this item is a public hearing, notice was posted 10 days before the scheduled meeting date. Exhibits 1. City Council Resolution June 2, 2020 Item #6 Page 5 of 11 RESOLUTION NO. 2020-096 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CARLSBAD, CALIFORNIA, APPROVING THE CARLSBAD TRANSNET LOCAL STREET IMPROVEMENT PROGRAM OF PROJECTS FOR FISCAL YEARS 2020-21 THROUGH 2024-25 FOR INCLUSION IN THE 2020 UPDATE TO THE TRANSNET PROGRAM OF PROJECTS WHICH WILL BE PROGRAMMED AS AMENDMENT NO. 14 TO THE 2018 SAN DIEGO ASSOCIATION OF GOVERNMENTS (SANDAG) REGIONAL TRANSPORTATION IMPROVEMENT PROGRAM (RTIP). Exhibit 1 WHEREAS, on Nov. 4, 2004, the voters of San Diego County approved the San Diego Transportation Improvement Program Ordinance and Expenditure Plan (TransNet Extension Ordinance); and WHEREAS, the TransNet Extension Ordinance provides that SANDAG, acting as the !Regional Transportation Commissionj[PGIJ, shall approve every two years a multi-year program of projects submitted by local jurisdictions identifying those transportation projects eligible to use transportation sales tax (i.e., TransNet) Funds; and WHEREAS, the City of Carlsbad was provided with an estimate of annual TransNet local street improvement revenues for fiscal years 2020-21 through 2024-25; and WHEREAS, the City of Carlsbad has held a noticed Public Hearing with an agenda item that clearly identified the proposed list of projects prior to approval of the projects by its authorized legislative body, City Council, in accordance with Section 5(A) of the TransNet Extension Ordinance and Rule 7 of SAN DAG Board Policy No. 31. NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad, California, as follows: 1. That the above recitations are true and correct. 2. ~hat pursuant to Section 2(C)(l) of the TransNet Extension Ordinance, the City of Carlsbad certifies that no more than 30% of its cumulative revenues shall be spent on local street and road maintenance projects.j[PmJ 3. That pursuant to Section 4(E)(3) of the TransNet Extension Ordinance, the City of Carlsbad certifies that all new projects, or major reconstruction projects, funded by TransNet revenues shall accommodate travel by pedestrians and bicyclists, and that any exception to this requirement permitted under the Ordinance and proposed shall be clearly noticed as part of the City of Carlsbad's public hearing process. June 2, 2020 Item #6 Page 6 of 11 4. That pursuant to Section 8 of the TransNet Extension Ordinance, the City of Carlsbad certifies that the required minimum annual level of local discretionary funds to be expended for street and road purposes will be met throughout the five-year period consistent with the most recent Maintenance of Effort Requirements adopted by SANDAG. 5. That pursuant to Section 9A of the TransNet Extension Ordinance, the City of Carlsbad certifies that it will exact an amount equivalent to $2,583.82, plus all applicable annual increases, from the private sector for each newly constructed residential housing unit in that jurisdiction (unless exempted under the TransNet Extension Ordinance,) and shall contribute such exactions to the Regional Transportation Congestion Improvement Program (RTCIP). 6. That pursuant to Section 13 of the TransNet Extension Ordinance, the City of Carlsbad certifies that it has established a separate Transportation Improvement Account for TransNet revenues with interest earned expended only for those purposes for which the funds were allocated. 7. That pursuant to Section 18 of the TransNet Extension Ordinance, the City of Carlsbad certifies that each project of $250,000 or more will be clearly designated during construction with TransNet project funding identification signs. 8. That the City of Carlsbad does hereby certify that all other applicable provisions of the TransNet Extension Ordinance and SANDAG Board Policy No. 31 have been met. 9. That the City of Carlsbad agrees to indemnify, hold harmless, and defend SAN DAG, the San Diego County Regional Transportation Commission, and all officers and employees thereof against all causes of action or claims related to City of Carlsbad's TransNet funded projects. 10. That the Carlsbad TransNet Local Street Improvement Program of Projects for fiscal years 2020-21 to 2024-25 attached to this Resolution as Attachment A is hereby approved for inclusion in the 2020 San Diego Association of Governments Regional Transportation Improvement Program. June 2, 2020 Item #6 Page 7 of 11 PASSED, APPROVED, AND ADOPTED at a _Special Meeting of the City Council of the City of Carlsbad on the 2nd day of June 2020, by the following vote, to wit: AYES: NAYS: ABSENT: Hall, Blackburn, Bhat-Patel, Schumacher. None. None. MATT HALL, Mayor (SEAL) June 2, 2020 Item #6 Page 8 of 11 CIP# RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL CB04B El Camino Real and Cannon Road Intersection of El Camino Real and Cannon Road in Carlsbad, along the northbound side of El Camino Real just south of Cannon Road, re-stripe to provide three through lanes, add a separate ped/bike bridge structure on the northbound side of El Camino Real over Agua Hedionda Creek.TransNet LSI $0 6042 TransNet - LSI: CR Local Funds $913 $2,402 $3,315 TOTAL $913 $2,402 $0 $0 $0 $0 $3,315 RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL CB12 College Boulevard Reach A College Boulevard from Badger Lane to Cannon Road (.8 miles) in Carlsbad, construct a new segment of College Blvd to provide 4-lane roadway with raised median, bike lanes and sidewalks/trails in accordance with major arterial standards.TransNet LSI $0 3636 TN LSI CarryOver $1,205 $1,205 TransNet - LSI: CR Local Funds $418 $1,295 $1,500 $1,500 $24,087 $28,800 TOTAL $418 $2,500 $1,500 $1,500 $0 $24,087 $30,005 RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL CB13 Poinsettia Lane Reach E Poinsettia Lane from Cassia Drive to Skimmer Court (.3 miles) in Carlsbad, construct new 4-lane roadway with median, bike lanes, and sidewalks/trails to major arterial standards.TransNet LSI $0 3922 TransNet - LSI: CR PROJECT COMPLETED IN 2020 - Expected to be opened in October 202 Local Funds $14,081 $14,081 TOTAL $14,081 $0 $0 $0 $0 $0 $14,081 RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL CB20 Pavement Management - Overlay On various streets throughout the City, pavement overlay 1 inch or greater and miscellaneous roadway section spot repairs.TransNet LSI $1,500 $1,500 $1,500 $4,500 6001 TN LSI CarryOver $0 TransNet - LSI: CR Local Funds $3,500 $3,500 $2,000 $2,000 $2,000 $13,000 TOTAL $3,500 $3,500 $3,500 $3,500 $3,500 $17,500 RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL CB21 Pavement Management - Slurry Seal Along various roadways, construct/apply street sealing and construct minor roadway pavement section repairs. TransNet LSI $0 6001 TransNet - LSI: Maint Local Funds $1,000 $1,000 $1,000 $1,000 $1,000 $5,000 TOTAL $1,000 $1,000 $1,000 $1,000 $1,000 $5,000 RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL CB22 Avenida Encinas - Widen from Palomar Airport Road to Embarcadero Lane Avenida Encinas from Palomar Airport Road southerly to existing improvements adjacent to the Embarcadero Lane; roadway widening and parkway construction/improvements.TransNet LSI $0 6004 TransNet - LSI: CR Local Funds $170 $5,177 $5,347 TOTAL $170 $0 $5,177 $0 $0 $0 $5,347 RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL CB31 El Camino Real Widening - La Costa Ave to Arenal Road Along El Camino Real from 700 feet north of La Costa Avenue to Arenal Road, widening along the southbound side of the roadway to provide three travel lanes, sidewalk, and a bike lane in accordance with Prime Arterial Standards TransNet LSI $0 6051 TransNet - LSI: CR Local Funds $3,200 $1,800 $5,000 TOTAL $0 $3,200 $1,800 $0 $0 $0 $5,000 RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL CB32 El Camino Real Widening - Poinsettia Lane to Camino Vida Roble El Camino Real from Poinsettia Lane to Camino Vida Roble – in Carlsbad, restripe from Poinsettia Lane to Cinnabar Way and widen El Camino Real from Cinnabar Way to Camino Vida Roble, along the northbound/east side of the roadway to provide three travel lanes, sidewalk, and a bike lane in accordance with Arterial Street standards.TN LSI CarryOver $70 $1,535 $1,605 6072 TransNet - LSI: CR FED Earmark $8 $1,432 $1,440 TOTAL $78 $2,967 $0 $0 $0 $0 $3,045 RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL CB34 Palomar Airport Road and Paseo Del Norte Right Turn Lane Palomar Airport Road from I-5 to Paseo Del Norte (.1 miles) - in Carlsbad, widening along eastbound Palomar Airport Road to provide a dedicated right turn lane to southbound Paseo Del Norte TN LSI CarryOver $169 $841 $1,010 6044 TransNet - LSI: CR Project to be completed in 2020 Local Funds $4 $113 $117 TOTAL $173 $954 $0 $0 $0 $0 $1,127 RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL CB35 Palomar Airport Road and Paseo Del Norte Left Turn Lane Palomar Airport Road from I-5 to Paseo Del Norte (.1 miles) - In Carlsbad, lengthen the left turn pocket along eastbound Palomar Airport Road to northbound Paseo Del Norte TN LSI CarryOver $113 $60 $173 6043 TransNet - LSI: CR Project to be completed in 2020 Local Funds $7 $40 $47 TOTAL $120 $100 $0 $0 $0 $0 $220 RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL CB36 Carlsbad Boulevard Realignment study the realignment of Carlsbad Blvd including the relocation of the southbound lanes of Carlsbad Blvd to the east and the construction of complete street and multi use trail improvements along the coastal corridor TransNet LSI $0 6031 TransNet - LSI: CR TN LSI CarryOver $3,000 $250 $3,250 TOTAL $3,000 $250 $0 $0 $0 $0 $3,250 2020 TransNet Program of Projects FY 2020-21 to FY 2024-25 in '000s City of CARLSBAD ATTACHMENT A June 2, 2020 Item #6 Page 9 of 11 RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL CB37 El Camino Real and College Blvd Intersection Improvements Improve El Camino Real along the southbound approach to the intersection with College Blvd. to provide three thru lanes and a signal controlled right turn lane TransNet LSI $0 6071 TransNet - LSI: CR Local Funds $213 $813 $1,026 TOTAL $213 $813 $0 $0 $0 $0 $1,026 RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL CB43 ADA Improvements Construct Priority Level 1 and Priority Level 2 ADA Improvements per the City of Carlsbad Transition Plan for Public Rights-of-way TN LSI CarryOver $995 $805 $65 $130 $65 $2,060 6049 TransNet - LSI: CR Local Funds $0 TOTAL $995 $805 $65 $130 $65 $0 $2,060 RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL CB44 Traffic Signal - RAMS City of Carlsbad annual operations and maintenance cost share for the Regional Arterial Management System, (RAMS); TransNet - LSI RAMS of $12 is programmed each year.TransNet LSI $12 $12 $12 $12 $12 $60 TransNet - LSI: CR Local Funds $0 TOTAL $0 $12 $12 $12 $12 $12 $60 RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL CB45 Carlsbad Boulevard and Tamarack Ave Pedestrian Improvement Project (part of lump sum V17) Reconfigure the intersection and the approaches to the intersection and provide enhanced facilities for pedestrians, transit users and bicyclists; (Bike, Ped, and Neighborhood Safety Program) SANDAG approved TransNet/ATP swap on October TransNet BPNS $94 $960 $1,054 6058 TDA - Bicycles $0 TransNet - LSI: CR Local Funds $501 $1,075 $1,576 TOTAL $595 $2,035 $0 $0 $0 $0 $2,630 RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL CB46 Terramar Area Complete Street Improvements in Carlsbad, construct complete street improvements including the reconfiguration of the curbline and the addition of medians, pedestrian crossings and parkway improvements TN LSI CarryOver $1,000 $1,000 6054 TransNet - LSI: CR Local Funds $1,213 $7,437 $2,450 $11,100 TOTAL $1,213 $8,437 $2,450 $0 $0 $0 $12,100 RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL CB47 Carlsbad Village Drive and Grand Avenue Improvements in Carlsbad, provide mid-block pedestrian crossing improvements and sidewalk/parkway improvements at the approaches to the railroad track crossings TransNet LSI $1,320 $1,320 n/a TransNet - LSI: CR Local Funds $0 TOTAL $0 $1,320 $0 $0 $0 $1,320 RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL CB48 Chestnut Avenue Complete Street Improvements Valley Street to I-5 in Carlsbad, complete street improvements including sidewalk improvements and traffic calming features such as bulb outs and medians TN LSI CarryOver $1,080 $1,080 n/a TransNet - LSI: CR Local Funds $0 TOTAL $0 $0 $1,080 $0 $0 $0 $1,080 RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL CB49 Kelly Drive and Park Drive Complete Street Improvements in Carlsbad, complete street improvements including new curblines, sidewalk and multi use trail improvements and traffic calming features such as bulb outs and medians TN LSI CarryOver $575 $3,600 $4,175 6075 TransNet - LSI: CR Local Funds $130 $130 TOTAL $575 $3,730 $0 $0 $0 $0 $4,305 RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL CB50 Valley Street Road Diet and Traffic Calming in Carlsbad, on Valley Street, north of Chestnut, reconfigure to a complete street with high visibility crosswalks, mid-block bulbouts, bike lanes, and parking in select areas.TransNet LSI $1,645 $1,645 n/a TransNet - LSI: CR Other Subtotal $0 TOTAL $0 $0 $1,645 $0 $0 $0 $1,645 RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL CB51 Adaptive Traffic Signal Program in Carlsbad, construct fiber optic communications upgrades and install traffic measuring systems and adaptive signal control systems to implement adpative traffic signal control along these roadways.TransNet LSI $855 $855 6326 TN LSI CarryOver $1,330 $457 $1,787 TransNet - LSI: CR Local Funds $1,000 $1,000 TOTAL $2,185 $1,457 $0 $0 $0 $0 $3,642 RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL CB52 Carlsbad Village and Barrio Traffic Circles in Carlsbad, at eight intersection locations in the Village and Barrio, construct traffic circles at key intersections to calm traffic TN LSI CarryOver $42 $983 $1,025 4015 TransNet - LSI: CR Local Funds $55 $3,095 $3,150 TOTAL $97 $4,078 $0 $0 $0 $0 $4,175 RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL CB53 Carlsbad Blvd. Pedestrian Roadway Lighting in Carlsbad, install pedestrian roadway lighting TN LSI CarryOver $65 $1,260 $1,325 6068 TransNet - LSI: CR Local Funds $0 TOTAL $65 $1,260 $0 $0 $0 $0 $1,325 RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL CB54 State Street Improvements at Northwest Corner with Grand Avenue in Carlsbad, widen the roadway to accommodate additional on street parking, close driveway access and reconstruction of the parkway to conform with the new curbline TN LSI CarryOver $325 $325 6082 TransNet - LSI: CR Local Funds $0 TOTAL $0 $0 $325 $0 $0 $0 $325 June 2, 2020 Item #6 Page 10 of 11 RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL CB55 Christiansen Avenue Improvements in Carlsbad, construct new curbline, sidewalk and parkway improvements TN LSI CarryOver $310 $310 n/a TransNet - LSI: CR Local Funds $0 $0 TOTAL $0 $0 $310 $0 $0 $0 $310 RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL CB56 Chestnut Avenue Complete Street Improvements - I-5 to the Railroad in Carlsbad, prepare a project study report to identify the scope of work for the construction of complete street improvements including traffic calming and pedestrian improvements TN LSI CarryOver $85 $85 6069 TransNet - LSI: CR Local Funds $0 $0 TOTAL $0 $0 $85 $0 $0 $0 $85 RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL CB58 Street Light Bulb Replacement Program in Carlsbad, replace light bulbs with LED bulbs TransNet LSI $445 $445 6062 TN LSI CarryOver $850 $2,030 $2,880 TransNet - LSI: Maint Local Funds $320 $320 TOTAL $1,615 $0 $0 $0 $0 $0 $3,645 RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL CB59 El Camino Real Widening - Sunny Creek to Jackspar Along El Camino Real from Sunnycreek to Jackspar, widen along the southbound side of the roadway to provide three travel lanes, sidewalk, and a bike lane in accordance with Prime Arterial TransNet LSI $2,984 $2,984 6094 TransNet - LSI: CR NEW PROJECT FOR 2020 POP UPDATE TN LSI CarryOver $1,016 $1,016 TOTAL $0 $4,000 $0 $0 $0 $0 $4,000 RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL CB60 Melrose Drive and Palomar Airport Road Improvements Widen southbound Melrose Drive to provide an additional through lane TransNet LSI $0 6034 TransNet - LSI: CR NEW PROJECT FOR 2020 POP UPDATE Local Funds $99 $612 $711 TOTAL $99 $612 $0 $0 $0 $0 $711 RTIP ID Project Title Project Description PRIOR EXPEND. FY21 FY22 FY23 FY24 FY25 TOTAL CB61 Palomar Airport Road and College Blvd Improvements Widen southbound College Blvd to add an additional through lane TransNet LSI $0 6028 TransNet - LSI: CR NEW PROJECT FOR 2020 POP UPDATE Local Funds $349 $646 $995 TOTAL $349 $646 $0 $0 $0 $0 $995 Projected TransNet - LSI Revenue $2,996 $3,383 $3,683 $3,804 $3,933 $17,799 Programmed TransNet LSI $2,996 $2,977 $1,512 $1,512 $1,512 $10,509 Programmed TransNet LSI Carry Over $15,042 $1,865 $130 $65 $0 $17,102 Total TransNet Programmed $18,038 $4,842 $1,642 $1,577 $1,512 $27,611 June 2, 2020 Item #6 Page 11 of 11 NOTICE OF PUBLIC HEARING NOTICE IS HEREBY GIVEN that the City Council of the City of Carlsbad will hold a public hearing at the Council Chamber, 1200 Carlsbad Village Drive, Carlsbad, California, at 3:00 p.m. on Tuesday, June 2, 2020, to consider approving the Carlsbad Transnet Local Street Improvement Program of Projects for fiscal years 2020/21 through 2024/25 for inclusion in SANDAG's Regional Transportation Improvement Program. The Carlsbad Program of Projects consists of the following: Carlsbad Program of Projects Total Cost El Camino Real and Cannon Road $3,315,000 College Boulevard Reach A $30,005,000 Poinsettia Lane Reach E (will be completed in 2020) $14,081,000 Pavement Management — Overlay $17,500,000 Pavement Management —Seal $5,000,000 Avenida Encinas — Widen from PAR to Embarcadero Lane $5,347,000 El Camino Real Widening La Costa Avenue to Arena! Road $5,000,000 El Camino Real Widening Poinsettia Lane to Camino Vida Roble $3,045,000 Palomar Airport Road Right Turn Lane to southbound Paseo Del Norte (will be completed in 2020) $1,127,000 Palomar Airport Road Left Turn Lane to northbound Paseo Del Norte (will be completed in 2020) $220,000 Carlsbad Boulevard Realignment $3,250,000 El Camino Real and College Boulevard Intersection Improvements (will be completed in 2020) $1,026,000 ADA Improvements $2,060,000 Traffic Signal - RAMS $60,000 Carlsbad Blvd and Tamarack Avenue Pedestrian Improvement Project $2,630,000 Terramar Area Complete Street Improvements $12,100,000 Carlsbad Village Drive and Grand Avenue Improvements $1,320,000 Chestnut Avenue Complete Street Improvements, Valley Street to 1-5 $1,080,000 Kelly Drive and Park Drive Complete Street Improvements $4,305,000 Valley Street Road Diet and Traffic Calming $1,645,000 Adaptive Traffic Signal Program $3,642,000 Carlsbad Village and Barrio Traffic Circles $4,175,000 Carlsbad Boulevard Pedestrian Roadway Lighting $1,325,000 State Street Improvements at northwest corner with Grand Avenue $325,000 Christiansen Avenue Improvements $310,000 Chestnut Avenue Complete Street Improvement, 1-5 to the railroad $85,000 Street Light Bulb Replacement Program $3,645,000 El Camino Real Widening Sunnycreek to Jackspar $4,000,000 Melrose Drive and Palomar Airport Road Improvements $711,000 Palomar Airport Road and College Boulevard Improvements $995,000 Copies of the staff report will be available on and after May 29, 2020. If you have any questions, please contact Jon Schauble in the Public Works Division at (760) 602-2762 or Jon.Schauble@carlsbadca.gov. As a result of the waivers in State of California Executive Order N-29-20, the Brown Act permits full participation of officials in meetings through video or audio teleconference. The meeting can be viewed online at www.carlsbadca.gov or on the City's cable channel. Those persons wishing to speak on this proposal and or participate in the meeting are cordially invited to send an e-mail with their comments to the City Clerk at clerk@carlsbadca.gov before the agenda item is heard at the June 2, 2020 City Council meeting. Your comments will be transmitted to the City Council. If you desire to have your comment read into the record at the City Council meeting, please indicate so in the first line of your e-mail and limit your e-mail to 500 words or less. Emails will be read for three minutes each, unless the presiding officer (usually the Mayor) changes the time. If you challenge the selected projects in court, you may be limited to raising only those issues raised by you or someone else at the public hearing described in this notice, or in written correspondence to the City of Carlsbad, Attn: Office of the City Clerk, 1200 Carlsbad Village Drive, Carlsbad, 92008, at or prior to the public hearing. PUBLISH: May 22, 2020 CITY OF CARLSBAD CITY COUNCIL Hossein Ajideh, Engineering Manager Jonathan Schauble, Senior Engineer June 2, 2020 Carlsbad TransNet Local Street Improvement Program of Projects for Fiscal Years 2020-21 through 2024-25 Staff Recommendation Hold a public hearing and adopt a resolution approving Carlsbad TransNet Local Street Improvement Program of Projects for FYs 2020-21 to 2024-25 for inclusion in 2020 TransNet Program of Projects, which will be programmed as an Amendment to 2018 SANDAG Regional Transportation Improvement Program 2 Background •TransNet, a countywide transportation sales tax approved by San Diego County voters in 1987 •In 2004, county voters approved TransNet Extension Ordinance extending initial San Diego Transportation Improvement Program Ordinance for a forty-year period •SANDAG, as Regional Transportation Commission, shall approve every two years a multi-year program of projects submitted by local jurisdictions identifying projects eligible to use TransNet Funds 3 What is Carlsbad Program of Projects (POP)? •List of local transportation projects: –use TransNet Funds –use Federal or State Funds –regionally significant and increase transportation capacity •Five-Year Program –FYs 2020-21 to 2024-25 •June 12, 2018, Council approved Carlsbad POP for incorporation into SANDAG’s 2018 Regional Transportation Improvement Program 4 Why Carlsbad POP Needs Approval? •To use TransNet Funds, member agencies of SANDAG are required to hold a public hearing and approve their programs of projects every two years •These programs are incorporated into SANDAG Program of Projects, a regional program of proposed transportation projects for the entire county 5 What is Regional Transportation Improvement Program (RTIP)? •SANDAG is required by state and federal laws to develop and adopt an updated RTIP every two years •Five-year planning and funding document •Identifying transportation projects submitted by local jurisdictions •Eligible to receive funding from Federal, State, and TransNet •RTIP may be amended between updates 6 What is New? •RTIP is being amended not updated this year •2019, U.S. Environmental Protection Agency (EPA) and National Highway Traffic Safety Administration issued the Safer Affordable Fuel-Efficient Vehicle (SAFE) Rule •Caltrans canceled 2020 update to RTIP 7 What’s Changed for Carlsbad? •Need to approve 2020 Carlsbad POP and submit to SANDAG for inclusion in 2020 TransNet POP (FYs 20-21 to 24-25) •SANDAG will not prepare a 2020 RTIP •SANDAG will prepare a 2020 TransNet POP which will be programmed by amending 2018 RTIP 8 New Projects in 2020 POP 1.El Camino Real Widening Project –from Sunny Creek to Jackspar 2.Melrose Drive and Palomar Airport Road Improvements 3.Palomar Airport Road and College Blvd Improvements 9 Project with Federal Funds •El Camino Real Widening Project –From Cassia Road to Camino Vida Roble 10 Projects with TransNet Funds •ADA Improvement Program •Adaptive Traffic Signal Program •Carlsbad Blvd. and Tamarack Avenue Improvements •Carlsbad Blvd. Pedestrian Roadway Lighting –North of Tamarack Avenue •Carlsbad Blvd. Realignment •Carlsbad Village and Barrio Traffic Circles •Carlsbad Village Drive and Grand Avenue Improvements •Chestnut Avenue Improvements –Valley Street to I-5 •Chestnut Avenue Improvements - I-5 to Railroad •Christiansen Avenue Improvements 11 Projects with TransNet Funds •College Boulevard Reach A •El Camino Real Widening -Cassia Rd. to Camino Vida Roble •Kelly Drive and Park Drive Improvements •Palomar Airport Road and Paseo Del Norte Turn Lanes •Pavement Management Program •State Street Improvement at Grand Avenue •Street Light Bulb Replacement Program •Terramar Area Coastal Improvements •Traffic Signal –Regional Arterial Management System •Valley Street Road Diet and Traffic Calming 12 Non-TransNet Funded Projects •Avenida Encinas Widening –PAR to Embarcadero Lane •El Camino Real and Cannon Road •El Camino Real and College Blvd. Intersection •El Camino Real Widening –La Costa Ave to Arenal •Poinsettia Lane Reach E (expected to be completed by Oct. 2020) 13 Next Steps •Adopt a Resolution approving Carlsbad Program of Projects •Submit the Resolution to SANDAG by June 17, 2020 •SANDAG holds a public hearing on Sept. 4, 2020 •SANDAG Board adopts 2020 TransNet POP and approve Amendment No. 14 to 2018 RTIP on Sept. 25, 2020 •Federal approval of Amendment No. 14 anticipated by Nov. 16, 2020 14 Staff Recommendation Hold a public hearing and adopt a resolution approving Carlsbad TransNet Local Street Improvement Program of Projects for FYs 2020-21 to 2024-25 for inclusion in 2020 TransNet Program of Projects, which will be programmed as Amendment No. 14 to 2018 SANDAG Regional Transportation Improvement Program 15 Thank you 16