HomeMy WebLinkAbout1991-01-29; Municipal Water District; 076; Update on Water Reclamation Master PlanAB# D76
MTG. l/29/91
DEPT.
F-- cm 1 - AGEND’ BILL L- i;.,L& fi
I TITLE: UPDATE ON WATER
RECLAMATION MASTER PLAN
RECOMMENDED ACTION:
Hear presentation and direct staff as appropriate.
ITEM EXPLANATION:
Staff will provide overview and update the Board on the status of the Water Reclamation
Master Plan. Update on the status of the State Low-Interest Loan Application.
FISCAL IMPACT:
No specific impact will result from this update and status report. .
.
EXHIBlTS:
None.
MANAGEMENT AND
OPERATING PLAN
CARLSBAD MUNICIPAL WATER DISTRICT
November 6,lQQO
EXECUTIVE SUMMARY
EXECUTIVE SUMMARY
The report which follows presents the results of the study to develop a management
and operating plan for the Carlsbad Municipal Water District which is now a
subsidiary district of the City of Carlsbad. The principal focus of the study was to
identify and evaluate alternative approaches for organizing and providing water and
related services consistent with the following primary objectives.
. To maintain the high quality ofwater service and related programs over
the short, medium, and longer range.
. To plan, organ&e, and deliver high quality water services in as an
efficient and effective manner as possible.
To this end, the study evaluated a variety of alternatives for organizing and delivering
water services. These ranged from maintaining the District organization as a
distinct, subsidiary organization apart from the regular city administrative structure
to dismantling the District organization as it now stands and assigning component
programs, responsibilities, and staff to the various City departments.
The study’s principal findings are as follows:
. The full range of customer-oriented services (account maintenance and
billing; meter reading and repair; response to complaints; conservation
programming and services) could be improved if all customer-related
services were under common management.
. Under the current organizatlon of responsibilities between and among
the District and the City Engineer, there is some overlap and duplica-
tion of effort in operating and service areas related to development
review and control. Additionally, responsibilities related to administra-
tion of capital improvement projects impacting water and street
facilities are not clearly detied between the District and the City
Engineer.
. While there appear to be few opportunities to achieve major efficiencies
or service improvements through consolidation of water and sewer field
maintenance services in the short-term, longer term cost avoidance
opportunities could be achieved through common management and
scheduling of sewer and water field maintenance personnel as the
reclaimed water system comes on line.
. As the reclaimed water system increases in scope and importance,
i
consolidated responsibilities for sewer and water planning and
coordi.naUon could ensure consistent attention to capacity planning and
securing of supply sources for both water and reclaimed water.
. Over time, effective administrative practice suggests that the District be
folded into the City’s major administrative and support systems to: (1)
eliminate duplication of staff resources devoted to administrative
activities; and (2) Ensure that the District’s practices in such areas as
recruiting and selection, personnel management, financial management,
and purchasing are consistent with City-wide policies and practices.
Given these findings, the study’s primary recommendations are as follows:
. Adopt the long-range objective of broadening the District’s current
scope of staff, programs, and responsibilities to include water,
wastewater, and reclaimed water services as a Utilities Department
within the City’s operating and adminisirative structure. This would
include consolidating responsibilities for and statf involved in:
e Plarming, design, and plan check for water, reclaimed water, and sewer services.
All customer-related services including water billing, meter
reading, and conservation programming related to water and
reclaimed water.
- Water supply and distributfon operations.
Water and sewer system maintenance.
. Establish the Community Development Department, City Engineer as
responsible for: (1) Inspection of all public improvements related to
development and capital projects involving sewer and water facilities:
and (2) Contract administration for all capital projects, including water
capital projects.
. Bring the existing District operation under etisting City administrative
policies and cenlxJize management and support system responsibilities
with the appropriate City department including: ( 1) Personnel
Management; (2) Financial Management: (3) Purchasing; (4) Vehicle
Maintenance: and (4) Risk Management.
Full implementation of the Utilities Department concept, as well as the other major
recommendations noted above, will require transfer of employees between and
among the existing District organization and City departments including Finance,
Utilities and Maintenance, and the City Engineer. The bulk of employee transfers
would involve assigning City employees to the expanded District organizatlon to fully
implement the recommended Utilities Department.
Full implementation of the recommended UUliUes Department should be viewed as
a longer range goal and implementation focused on achieving that goal should be
approached cautiously to avoid service disruption, negative impact on programs, and
unnecessary staff discomfort. The report provides a suggested implementation
sequence which consists of the following major components.
. The first key implementation step will involve tra.nsiUoning the District
from an autonomous administrative entity to a department which is
integrated into the City’s administrative structure.
. Any additional organizational adjustments, including all anticipated
inter-unit staff transfers, must be deferred until a strategy for
integrating current District employees into the City’s compensation and
fringe benefit structure has been developed. Current differentials in
compensation and benefit values between the District and the City
appear to be significant enough to provide a barrier to organizallonal
adjustments involving staff transfers until a strategy for addressing
these compensation differentials has been developed.
. Once a compensation and benefit transition strategy has been developed
and negotiated, the report recommends sequential implementation of
the organizational adjustments which would culminate in a full scale
Utilities Department. These steps will probably require several years
and each should be fully implemented and digested before the next is
addressed. Pages 31 through 35 in the main body of the report outline
the recommended implementation sequence.
iii
TABLE OF CONTENTS
section
EXECUTIVE SUMMARY
1.
2.
3.
4.
5.
6.
7.
8.
9.
OVERVIEW OF CURRENT OPERATIONS AND
INTERORGANIZATIONAL RELATIONSHIPS . . . . . . . . . . . .
SUMMARY OF INITIAL ISSUES RAISED
DURING INTERVIEWS . . . . . . . . . . . . . . . . . . . . . . . . . . . .
FINDINGS RELATED TO ORGANIZATIONAL AND
MANAGEMENT ISSUES . . . . . . . . . . . . . . . . . . . . . . . . . . .
EVALUATION OF ALTERNATIVE ORGANIZATIONAL
AND MANAGEMENT APPROACHES TO ADDRESSING
CURRENT AND POTENTIAL FUTURE ISSUES . . . . . . . . . .
COMPENSATION AND BENEFIT ISSUES IMPACTING
ORGANIZATIONAL CHANGE . . . . . . . . . . . . . . . . . . . . . . . .
DESCRIPTION OF LEGAL BARRIERS IMPACTING
ORGANIZATIONAL CHANGE . . . . . . . . . . . . . . . . . . . . . . . .
RECOMMENDATIONS RELATED TO INTEGRATING
THE DISTRICT INTO CITY OF CARLSBAD
OPERATIONS . . . . . . . . . . . . . . . . . . . . . . . . . , . . . . . . . . .
RECOMMENDATIONS RELATED TO ESTABLISHING
A UTILITIES DEPARTMENT . . . . . . . . . . . . . . . . . . . . . . . .
w?e Number
2
4
7
11
23
24
25
26
PHASING PLAN FOR IMPLEMENTING RECOMMENDATIONS 28
APPENDICES
A PROFILE OF STAFF ASSIGNMENTS AND
RESPONSIBILITIES FOR THE CARLSBAD
MUNICIPAL WATER DISTRICT . . . . . . . . . . . . . . . . . . . . . . Al
B INITIAL ISSUES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Bl
PROPOSED MANAGEMENT AND OPERATING PLAN
FOR THE CARLSBAD MUNICIPAL WATER DISTRICT
The report which follows summa&es conclusions and recommendations
related to how the Carlsbad Municipal Water District should fit into the structure
and service organization of the City of Carlsbad, now that the District has become
a subsidiary district. The primary focus of the project was to review the services,
functions, and operations of the District, and identify how they currently or
potentially relate to the functions and services of the City. Based on this analysis,
the focus of the project was to identify and evaluate how to best organ&e these
services from the perspective of the following criteria.
. To ensure maintenance of a quality water services program both now
and in coming years.
. To determine if duplication of effort and fragmentation of control
related to the planning, engineering, operations, maintenance, and
customer services associated with the water services program does
exist, and if so, to explore approaches for eliminating that duplication.
. To consider the impact of future developments such as expansion of the
reclaimed water program on organization and operating alternatives.
. To determine how the District, which is currently an autonomous
organization from the perspective of compensation and administrative
systems, can and should function within the administrative and support
structure of the City of Carlsbad, now that it is a subsidiary district.
A key issue involved in structuring and evaluating alternatives, involves the
agreement between the City and the District which was negotfated and signed at the
Ume of reorganizaUon. A significant provision of that agreement includes the
following statement:
“All benefits and rights to existing employees shall be continued at levels not
less than currently enjoyed. These benefits and rights include vacation, sick
-l-
leave, insurance, retirement programs, employment contracts, and seniority.”
Given the above, the analysis also included comparison of District and City
compensaUon and benefit structures to identify major differences which could
provide barriers to any realignment in organization and service delivery responsibili-
ties.
The report opens with an overview of how the District currently functions and
identifies key relationships between the District and other departments and
operating functions of the City of Carlsbad.
1. CURRENT DISTRICT OPERATIONS INTERFACE WITH CITY ACTMTlES
INANUMBEROFAREAS
During the early stages of the study, the project team interviewed most District
staff and key managers and supervisors in City operations either currently or
potentially related to water service programs. The purpose of these initial interviews
was to develop an understanding of District operations and to identify how the
District inter-relates with various City services and unit. Appendix A to this report
provides a detailed description of the basic responsibilities of District staff and
indicates how they interface with City staff and operations. Major conclusions which
can be drawn from the information presented in the Appendix are summarized in
the paragraphs which follow.
Although the District is now organized as a subsidiary district to the City of
Carlsbad, it essentially functions as an autonomous organization entity with
independent administrative systems and procedures including:
-2-
. Compensation structure and administration
. Personnel policies, procedures, and systems
. Purchasing controls and requirements
. Financial structure including supporting systems involving accounting,
investment management, and the like.
. Direct operations support activities such as vehicle and equipment
maintenance.
At each level of and across each District subordinate operating unit, District
and City staff interface in a number of areas related to administration, management,
and operations. Key areas which can be highlighted based on the information
presented in Appendix A include the following:
. Administration: With the transition to subsidiary district status, there
is increased involvement between the District Engineer/District Manager
and the City Manager. Top level District management staff are being
incorporated into the City management team. The focus of this
involvement is to establish a chain of accountability from the City
Manager to the District General Manager and his staff and align the
District with high priority management programs and the management
team being developed by the City Manager.
. Finance: While they currently operate Iwo distinct financial systems,
the District and the City interface in regard to establishing and setting
water rates which are currently arranged in two component parts
related to the cost structure of water service programs experienced by
the District and the City.
. EncEineering and Inspection: The District and the City interface from
several perspectives:
Development review and control -- both are involved in reviewing,
inspecting, and approving development improvements. Under the current practice, the City Engineer and the District adminis-
ter independent processes from the point of application through
final inspection.
Capital project design and construction -- The District/City
relationship focuses on those District capital projects which
3-
impact City facilities. These primarily include distribution
system projects which impact the street network. Key areas of
interface include the following:
. . Sequencing projects to avoid installing or upgrading
waterlines which require digging up and resurfacing newly
resurfaced or reconstructed streets.
. . Traffic control planning and implementation during the
construction period.
l . Bidding projects and subsequent contract administration
and inspection.
. ODerations and Maintenance Water operations (control and provision
of water to the distribution system) is an essentially distinct function
with no real interface with operations of other City operating units.
From the maintenance perspective, current interfaces are limited to
responding to customer complaints related to water leaks and other
supply problems. The meter reading unit in the Utilities and Mainte-
nance DeparUnent handles leaks from the meter to the structure, while
District field maintenance staff handle distribution system leaks beyond
the meter.
2. A VARIETY OF POTENTIAL SERVICE EFFECTIVENESS AND EFFIClENCY
ISSUES WERE ANALYZED TO PROVIDE THJ3 E3ASIS FOR EVALUATING
ALTERNATIVE MANAGEMENT AND OPERATING APPROACHES
Early in the project, District and City staff were interviewed to identify
potential areas of overlap, duplication of effort, or fragmentation of responsibility
related to water service delivery resulting from involvement of an essentially
autonomous District organizatlon and City operating units in the various aspects of
system planning and operations.
Appendix B to this report highlights potential issues raised by staff during
initial interviews or identified by the project team as a result of these interviews.
Major potential issue areas explored over the course of the project can be
summarized as follows:
4
. Customer Services and Customer Complaint Response -- Reflecting the
fact that responsibility for responding to customer service requests is
divided between the City’s UUlity and Maintenance department and the
Carlsbad Municipal Water District. This has the potential to lead to
confusion on the part of the customer regarding which unit should be
contacted to resolve problems regarding water leaks, supply, and
quality.
. Coordinated Control of Planning and Implementation of Water
Conservation Programs -- Given the Finance Department’s responsib-
ility for administration of the water billing system (data source for
analysis of consumption patterns); meter readers who are assigned to
the Utility and Maintenance Department (who operate in the field and
represent resources which can be employed to identify consumption
abuses); and assignment of responsibility for conservation program
planning and public information dissemination to the District.
. Development Review and Control -- Potential overlap and duplication of
effort related to sewer and water improvement inspections and the
requirement for applicants to saUsfy two sets of bonding, application,
and plan check requirements as imposed by the City Engineer and the
District.
. Capital Proiect Planning and ImplementaUon -- Involving potential
fragmentation and confusion of responsibilities, especially in the area
of water distribution system replacement or construction projects
which impact the street network. Issues raised during initial interviews
revolved around the absence of definition of clear responsibility for
contract administration, traffic control, inspection, and other compara-
ble activities related to capital projects in which both the District and
the City Engineer’s departments were involved.
. Operations and Maintenance -- Characterized by potential issues related
to opportunities to increase staff uti&aUon and/or moderate future
staffing growth across all funcUons including such areas as:
If meter reading and water field maintenance staff were organized
under the same umbrella, would there be any potential to shift
or balance field maintenance workload to free up meter reader
staff time to handle increased meter reading workload without
commensurate staff increases?
The potential to cross utilize water maintenance and sewer
maintenance staff to increase staff utilizatlon in both functions.
-5-
Potential overlap or duplicatfon in the vehicle and equipment
inventories employed to support water and sewer iield mainte-
nance operations given assignment of these responsibilities and
staff to different organizatlonal units.
In addition to these areas which surround current operations, potential future
considerations were also surfaced in the initial analysis. For example, would the
current allocation of planning and maintenance responsibilities to the District and
other City functions support or detract from the cost-effective implementation of the
reclaimed water program in future years? This includes:
. Allocation of responsibility for coordination of sewage treatment and
collection issues to the City Engineer and the UUliUes and Maintenance
Director and his staff -- responsibilities which will involve issues related
to supply of reclaimed water as the program develops and expands.
. Concurrently, assignment of responsibility for reclaimed water
distribuUon and system planning to the Carlsbad Municipal Water
District.
. Future potential to moderate growth in field maintenance staff required
to maintain the reclaimed water system through consolidated manage-
ment and control of water and sewer field maintenance personnel and
equipment.
Finally, a variety of “people” issues and perceptions were identified which
impact structuring and evaluating organizational alternatives for delivering water and
water related services both now and in future years. They include:
. Historical atUtudes about how well related units function, especially in
the areas of engineering and inspection. Interviews clearly indicate the
District staff believe that the District approach to reviewing and
inspecting developer improvements and managmg capital projects from
plannin g through design, contract administration, and fmal inspection
are best controlled through dedicated, in-house staff. There is a clear
attitude that any loss of direct control in these areas would adversely
impact service quality.
. There is a clear concern among District staff about the potential loss of
compensation and benefit advantages which could occur as a result of
compensation and benefit advantages which could occur as a result of
any adjustment in existing organization, configuration, and responsibili-
ties.
The paragraphs which follow indicate which of these issue areas were
validated by analysis completed during the course of the project.
3. OUR ANALYSIS INDICATES THAT EXTERNALLY FOCUSED SERVICES
AND SOME ASPECTS OF CURRENT AND FUTURE INTERNAL OPERA-
TIONS COULD BENEFIT FROM ORGANIZATIONAL REALIGNMENT OF
RESPONSIBILITIES
Based on follow-up analysis conducted by the project team, a set of findings
related to the potential issues described in Section 2 were developed. These fmdings
which are described in the following paragraphs are subsequently employed to
structure and evaluate organizational and service delivery alternaUves.
(1) The Full Rawe Of Customer Services Could Be Improved If All Customer
Related Services And Responsibilities Were Under Common Management
Principal findings related to the customer services area are as follows:
. Based on the existing set of multi-organizational unit responsibilities for
customer accounts and billing, meter reading, and response to
customer complaints, the system is not simple or convenient for the
customer in regard to the person, unit, or place to contact to resolve a
problem or obtain information.
. More importantly, the organizational fragmentation of customer
accounts and billing, field meter readers, and conservation program
responsibilities, complicates the development, implementation, and
maintenance of a coordinated and controlled water conservaUon
program.
12) There Is Some Overlap And Duplication Of Effort In ODeratinp And
Senrice Areas Related To Develooment Review And Control
Principal issues include:
. Need for applicants to make application, submit plans, and post bonds
with both the District and the City. Service and responsiveness could
-7-
clearly be improved by coordinating or consolidating application and
bonding requirements.
. While limited in terms of the number of personnel involved, there is
duplication of effort between the City Engineer and the District in
regard to current separation of responsibility for inspection of sewer
and water improvements related to new construction. This involves two
inspector positions in the District and varying levels of inspection
effort, primarily through contract service personnel, but currently
transitioning to in-house staff, in the City Engineer’s operation.
(3) Responsibilities Related To Administration Of Capital Improvement Proiects
Impacting Water And Street Facilities Are Not Clearlv Defined
Follow-up analysis indicated that there appeared to be no signiiicant issues
related to the current planning and design of water capital projects including special
facilities [e.g., reservoirs, major pump stations, etc.) or distribution system
improvements. Principal fmdings include the following:
. There is sufficient workload to fully utilize existing engineering
positions in the District solely on water projects, no matter where staff
are assigned.
. More complex water facility projects are accomplished by consulting
engineers operating under the District Engineer’s direction and control.
Again, there appear to be no issues associated with quality, capacity
planning, and the like.
Conversely, currently, and in the past, some issues have arisen related to
construction and contract administration of water projects which impact the City’s
street network and require participation by both District and City Engineer staff.
Issues have included responsibility for design and implementation of traffic control
plans; timely bidding and completion of some projects given differing priorities
between District and City Engineer programs; and belief on the City Engineer’s part
that the City should deal with contractors with “one voice.”
a
(4) While There Appear To Be Few Opportunities To Achieve Maior Efficiencies
Or Service Improvements Through Consolidation Of Water and Sewer Field
Maintenance Services In The Short-Term, Longer Term Cost Avoidance Opportunities Could Be Achieved As The Reclaimed Water Svstem Comes On
Line
Analysis indicates that the staffing of both water and sewer maintenance
operations is relatively modest. Similarly there is no significant duplication
of major vehicles and equipment available to support the two functions. As
a result, consolidation would probably achieve no significant economies of
scale over the short-term. Potential improvements would probably be limited
to:
. Elimination of the need for one supervisory position at the Construc-
tion and Maintenance Superintendent level.
. If cross-training was accomplished, a potential to better schedule work,
given the fact that both sewer and water crews are on a 4/10 work
schedule.
. Similarly, with cross-training, duplicate emergency standby on nights
and weekends could be eliminated.
Over the longer term, as the reclaimed water system comes on line,
consolidated management of water and sewer field maintenance forces could
moderate staffing increases in both functions required to provide maintenance
services to the expanding sewer collection and water distribution networks as
well as the reclaimed water system as reclaimed water distribution systems
are accepted for maintenance.
Similarly, if meter readers were included within the same organizational
framework as field maintenance staff, there is the potential to better schedule
work related to meter replacement and repair, potentially freeing up meter
-9-
reader time to handle increasing meter reading requirements without
commensurate staffing increases.
(5) As The Reclaimed Water Svstem Increases In Scope And Importance,
Consolidated Responsibilitv For Sewer And Water Planning And Coordination
Should be Considered
Analysis indicates there are no significant issues related to current
approaches to water capacity planning or coordination of sewage treatment
services with the Encina Authority. These responsibilities are currently
divided between the District (water issues), and the City Engineer and Utilities
and Maintenance Director (various aspects of the sewer and sewage treatment
program). However, as time passes and the reclaimed water program
increases in importance and scope, there could be some advantages to
consolidating control of sewer and water issues since the sewage treatment
relationship and agreements are key to access to treated water for distribution
through the reclaimed water system. Consolidation of responsibilities could
ensure consistent attention to capacity Plannmg and securing of supply
sources for both water and reclaimed water.
(6) Over Time Effective Administrative Practice Would Swest That The District Be Folded Into The CiiVs Maior Administrative And Support Systems
Given the existing autonomous structure and operation of the District
as described earlier in this report, there is a duplicatton of administrative staff
and existence of distinct and different administrative systems between the
District and the City. Key issues are as follows:
. Now that it is a subsidiary District and part of the City’s management
and program structure, major administrative systems should be
-lO-
brought into line with overall City practice, especially in the areas of:
Personnel policies, procedures, and programs.
Purchasing policies and controls
Risk management and loss control programs
. Concurrently as a stand-alone operation, the District currently devotes
staff resources to activities and functions which could be absorbed by
existing City Units and staff. These include:
Accounting and Financial management
Payroll
Vehicle and equipment maintenance
Risk management and loss control
Purchasing
. Similarly, some programs in the City are receiving increasing manage-
ment attention and emphasis, including affirmaUve action recruiting
and selection: staff development and training; and compensation
management. As a subsidiary district which is part of the City of
Carlsbad, it appears the District ought to be subject to and benefit from
these new programs and emphasis in the human resource management
area.
4. THREE ALTERNATIVE APPROACHES TO ADDRESSING THESE CURRENT
AND POTENTIAL FUTURE ISSUES WERE DEVELOPED AND EVALUATED
Given the issues noted above, the project team structured three potential
alternatives which could provide the basis for a long-range management and
operating plan for the Carlsbad Municipal Water District. While there are variattons
on each alternative which could be developed and implemented, the alternatives
displayed in this sectfon represent three distinctly different long-range targets which
could be established as a goal for integrating the Carlsbad Municipal Water District
-ll-
into City operations. The sections which follow present each alternative.
( 1) Alternative One: Estabhsh A Full Services Utilities Department Combining All
Kev Sewer, Water, and Reclaimed Water Operations
The first of the three alternatives involves transitioning the District from
a water services agency to a Utility Department functioning within the
administrative structure of the City of Carlsbad. Exhibit I, which follows this
page, shows how a Utilities Department could be organized and staffed.
Principal features of the organizational alternative displayed in the exhibit are
as follows:
. All customer services related functions, including utility billing, meter
reading, and conservation programming and planning are consolidated
within the Utilities Department. With this consolidation, the Utilities
Department would serve as the single point of contact for all customer
service requests and questions.
. The organization groups all sewer and water field maintenance
functions under a single Operations Manager as shown in the Exhibit.
Consolidated management would provide the basis for combined work
scheduling for all field work resources: maintenance staff cross
training; and joint utilization of staff to meet the full scope of field
maintenance requirements including activities currently handled by
meter reading personnel.
. Consolidated responsibility for all aspects of planning, engineering,
design, and i.nspecUon of sewer, water, and reclaimed water projects,
This would involve:
Providing for an Engineering Manager, comparable in training
and responsibility to a Chief Engineer to oversee all engineering-
related activities within the Utilities Department.
Assigning the UUliUes Director responsibility for over-ah planning
and coordination of water, sewer, and reclaimed water programs.
-1%
L
0‘ c t 3 .p
D
3g- au $ 0-l 2
3 .g t iis .- P Lu 5
“, 0
,&i cz I
c .- fi? $LI .
4c
Assigning responsibility for all aspects of engineering design,
inspection, and contract administration to the Utilities’ Engi-
neering Unit as depicted in Exhibit I. This would involve
separate water and sewer engineering design units, but would
consolidate inspection services as shown in the exhibit.
. The proposed UUliUes Department would be fully integrated into the
basic administrative structure of the City of Carlsbad including:
- Transferring responsibility for financial management, including
accounting, payroll, and investment management to the Finance
Department.
Bringing Utility Department staff, including existing District
personnel, under the City personnel system with all personnel
related services provided by the Human Resources Department.
Incorporating the Utilities Department into City purchasing, risk
management, and vehicle maintenance systems.
Implementation of AlteraUve One would require substantial organiza-
Uonal adjustment and transfer of personnel and responsibilities as follows:
. District accounting staff (Accountant and Accounting Office Assistant)
would be transferred to the Finance Department.
. Utility billing staff would be transferred from the Finance Department
to the Utility Department with work stations at the existing Carlsbad
Water District office.
. The meter reading unit would be transferred from the UUliUes and
Maintenance Department to the new UUIities Department.
. Field sewer system maintenance responsibilities and staff would be
transferred from the Utilities and Maintenance Department to the new
Utilities Department.
. Responsibilities related to sewer facilities design and inspection would
be transferred from the City Engineer to the new Utilities Department.
Because there are no dedicated staff involved in these functions and
consulting engineers and inspectors are primarily utilized for design
and inspection, transfer of responsibility would not significantly impact
staff assigned to the City Engineer’s Office.
-14-
. Consolidation of responsibility for all phases of sewer capacity planning
and relationships with sewage treatment agencies and authorities would
be placed with the Utilities Department.
The “fit” between the Utilities Department option and the resolution of
issues raised earlier in the report is summarized at the end of this section.
(2) Alternative Two: Ink&ate District Functions, Services And Personnel Into
Other Departments of the Citv of Carlsbad
Exhibit II which follows this page, outlines an alternative which would
essentially involve allocaUngresponsibility for and transferringvarious District
staff to those City departments with lead responsibility in each of the
operating and support service areas which characterize the existing District
organization and operation. Principal characteristics of this alternative would
be as follows:
. All engineering related functions (system planning, development review,
project design, and implementation) related to water and reclaimed
water systems would be assigned to the City Engineer and be allocated
to the various engineering sub-units based on the current organizatlon
of responsibility within the City Engineer Department.
-
. Financial management of water services would be centralized in the
Finance Department and treated to comparable financial management
approaches as other City enterprise fund operattons.
. Field operations would be incorporated into the Utilities and Mainte-
nance Department as shown in Exhibit II. This could include responsi-
bility for coordination and implementation of conservation program-
ming responsibilities.
Implementation of Alternative Two would essentially involve eliminating
the District as a distinct organfzatlonal enttty and reallocating staff, responsi-
bilities, and functions as described above.
-15-
c 0% .- f= -- G aa
I-
xi%. 3gg OIL 0
/
,5 .= .E
OF w
+
acnijj .Q’ii u .y.al m cj ‘5 5 r&:r
i
Y 7ii g 0. ‘G w 5 50 c fi 2
c
H I
F .g go . w U-J $F 0-c mw . a-5 8 .E . .= ij
2.z F3 $G”+
(3) Alternative Three: Moderatelv Adjust The Existing District To Provide One
Point of Contact For Water Customers
Exhibit III, which follows this page, shows the third distinct alternative
developed and evaluated by the project team. This approach would involve:
. Centralizing financial management and related accounting and payroll
services in the City Finance Department, comparable to Alternatives
One and Two.
. Centraking customer service responsibilities with the District or
successor water service organization. This would include both billing
and meter reading staff.
. Maintaining organizational distinction for water system engineering and
maintenance activities.
Staff and responsibilities transfers required to implement Alternative
Three would be limited to:
. Transfer of meter reading staff from the Utilities and Maintenance
Department to the DisUict/Water Department.
. Transfer of utility billing staff from the Finance Department to the
District/Water Department.
. Transfer the District Accountant and Accounting Office Assistant to the
City Finance Department.
Alternative III would also impact several positions in the existing
District organization:
. The administrative manager would transfer focus from basic adminis-
trative functions to oversight, design, and control of all customer
service operations and related programs.
. An Engineering Manager position (degreed engineer) would be estab-
lished to support the Water Services Manager by assuming hands-on
engineering activities including design, master plan maintenance,
developer contacts, and direcUon of day to day engineering activities.
This engineer would probably have to be registered if the Water
Services Manager was not a registered engineer.
-18-
i-
F ‘iI E5 $F .c m’ F’r W
. The Water Services Manager would increase responsibility for overall
unit administration and management.
Alternative Three could be implemented by retaining the District as an
essentially distinct 0rganizaUonal element within the City structure (i.e., with
the exception of finance and accounting), or integrating it into the City
administrative and operating structure, ultimately transiUoning to Water
Department status.
(4) Alternative One Is Most Consistent With Resolvixuf The Orpanizational
And Opera- Issues Identified Earlier In this Report
Exhibit IV, which follows this page, evaluates each of the three
alternatives in light of the issues and organizational and service delivery
objectives raised in Section 3 earlier in the report. Principal conclusions
which can be drawn from the comparative data shown in Exhibit V are as
follows :
. Alternative One provides the best “fit” in terms of addressing the
organizational, operating, and admInistrative issues IdenMed earlier in
the report. If fully implemented, it would coordinate related services
(especially in the planning area, given the relationship between
wastewater treatment, reclaimed water, and water supply), provide one
point of contact for customer services, and provide the opportunity for
staff cross-utilization, especially in the area of improvements inspection
and field maintenance staff services. Based on current operations, full
implementation, including transfer of responsibilities and personnel,
would be complicated because of the absence of full-time equivalent,
dedicated staff positions devoted to sewer facilities design and
inspection in the City Engineer’s Department.
. Alternative Two which involves integrating all District operations and
staff into existing City functions, is the least attractive alternative. As
structured, it would contribute to rather than resolve fragmentation in
water service planning and delivery. Additionally, this approach would
probably work against development and maintenance of a quality water
-2o-
: ‘i t I. t
2 t; ;i
5
ii C .r
.,;
5 i
;C -T 2:
: E
2 E c
4 I
I 1
I
i
i ;1 ., : c
. . . .
Eul I
. .
4
z= 3 cn
services program and would not result in significant service improve-
ments or operating efficiencies.
. Alternative Three is the least disruptive to implement and would
address issues related to customer service and conservation program-
ming. If interunit agreements could be developed to address issues
related to duplication and development review requirements and
processes and capital program implementation, Alternative Three would
serve to address most short-term issues idenMed over the course of
the analysis.
Based on the above, it appears the ideal solution is a combinatton of the three
alternatives. This combination, which is a variation on the Utilities Department
approach is explained in more detail in a subsequent section.
5. COMPENSATION AND BENEFIT STRUCTURE DIFFERENCES POSE A
SIGNIFICANT BARRIER TO ANY ORGANIZATIONAL ADJUSTMENT
WHICH INTEGRATES DISTRICT AND CITY STAFF
As an independent organization, the Carlsbad Municipal Water District has
developed its own compensation structure. This structure is based on periodic
comparisons with other water districts in Southern California, and adjusted in the
interim with cost of living based increases.
Analysis conducted during the study compared the District and City
compensation structures to determine the extent to which signiiicant differences
exist. Comparative analysis also addressed fringe benefit programs maintained by the
District and the City. Principal conclusions are as follows:
. The District compensation structure is significantly above the City’s
basic compensation plan based on a preliminary position by position
comparison. The existing “spread” is significant enough to propose
barriers to implementing any organizational adjustment which involved
integrating City and District employees in day to day working situations.
The major issue involves the potential for people to be assigned the
same work, but to receive significantly different compensatton.
-23-
. While many fringe benefits are the same, two significant differences
exist, which exacerbate issues related to compensation structure
differentials. They include the following:
- District employees have access to a deferred compensation plan
under which the District pays 50% of the amount employees
select to set aside. Thirty of thirty-one District employees
currently participate in the deferred compensation program.
Vacation and sick leave accrual and payout provisions for District
employees are significantly different than policies employed to
govern vacation and sick leave accrual and payout for City
employees. This translates into real dollar differences which
complement salary and compensation for District employees,
especially upon retirement or termination.
The project team has concluded that the differences are significant enough to
pose barriers to any organizational alternative or adjustment which involves
transferring staff or functions between or among the City and District organizational
units, It is clear that no personnel or functions should be transferred until a
strategy is developed for resolving compensation differences which is:
. In the spirit of Exhibit A to the City/District agreement cited at the
beginning of the report, which held no District employee would be
financially harmed by any organizational change implemented after
establishment of the District as a subsidiary district.
. Clearly understood by all employees likely to impact by any organiza-
Uonal change.
6. THERE ARE NO OTHER SIGNIFICANT BARRIERS TO ORGANIZATIONAL
ADJUSTMENT WHICH WOULD FOCUS ON INTEGRATING ALL OR
PORTIONS OF DISTRICT AND CITY OPERATIONS
With the exception of the compensation issues noted above, analysis indicates
that there are no legal or comparable barriers to organizational adjustments of any
scope. More speciilcally, the legal status of the District provides no barriers to
implementing alternative organizational approaches to delivering water services or
-24-
combining water service delivery operations with other functions as explored earlier
in the report. Available information clearly suggests that the preferable alternative
is to retain the District as a legal entity as currently established as a subsidiary
district to the City of Carlsbad.
. Dissolution of the District would require a lengthy LAFCO process and
could require an election.
. Dissolution would also result in loss of direct representation on the San
Diego Water Authority.
. Virtually any organizational adjustment within the City’s administrative
sUucture can be implemented without dissolution of the District, and
can be supported by a contract or contracts between the City and the
District as a legal entity.
7. MAINTENANCE OF THE DISTRICT ORGANIZATlON AS AN AUTONOMOUS
ADMINISTRATIVE ENTITY WITHIN THE CITY STRUCTURE DOES NOT
APPEAR TO BE AN EFFECTIVE MANAGEMENT PRACTICE OVER THE
SHORT, MEDIUM. OR LONGER RANGE
Factors contributing to this conclusion include the following:
. Cost-Effectiveness -- Maintenance of separate administrative and
support functions within the District’s sU-ucture results in duplication
of administrative staff and support resources. All data indicate that
e&ding City administrative and support services (i.e., purchasing,
financial management and processing, risk management, personnel
management, and vehicle maintenance) could absorb the responsibility
for serving the District staff and operations without any increase in staff
resources. Additionally, with addnistrattve centralization, some
District staff could be employed to upgrade capacities in other City
0peraUng units.
. Compensation Structure and Policv -- Continuing existence of an
organization within the City government structure with significantly
dffferent compensation for comparable classifications can be expected
to be a continuing irritant and can complicate labor negotiations in the
compensation area.
. Differing Policies -- In such areas as personnel systems (e.g., affirmaUve
action, other aspects of redirected human resource management
-25-
programs being implemented by the City); purchasing policies and
control; and the like, could be viewed as gaps in the overall City
management structure.
8. THE CITY SHOULD ADOPT THE LONG-RANGE OBJECTIVE OF ESTAB-
LISHING A UTILITIES DEPARTMENT, BUT IMPLEMENT CHANGES
INCREMJ3NTALLY TO AVOID ORGANIZATIONAL “SHOCK” AND TO ALLOW
TA&E FOR INVOLVED STAFF TO MANAGE CHANGE
The project team has concluded that the most effective long-term organization-
al goal involves a modified version of the Utilities Department alternative shown as
Exhibit I earlier in this report. The basic components of the recommended Utilities
Department approach, once fully implemented, would be as follows:
. Consolidated responsibility for water, waste water, and reclaimed water services. This would include the following components once fully
implemented:
Planning, design, and plan check for water, reclaimed water, and
sewer services.
Consolidated customer service-related operations includingwater
billing, meter reading, and conservation programming related to
water and reclaimed water.
Water operations
Water and sewer system field maintenance.
. Adjustments to the development review and capital projects manage-
ment processes and systems which incorporate the following:
Establishing the Community Development Department, City
Engineer as the single point of application for a.U development
projects, including:
(1) Providing a single bonding requirement for construction of
required improvements;
-26-
(2) Circulating plans to the Utilities Department for plan
check of water and sewer improvements consistent with
how plans are circulated for other City departments for
review and plan check.
Consolidating responsibility for and staff assigned to inspection
of all public improvements including water and sewer systems,
under the City Engineer.
Consolidating responsibility for contract administration for all
capital projects, including water projects, under the City
Engineer.
. Retaining the District as a legal entity but absorbing the water planning,
engineering, operations, and maintenance functions as a City depart-
ment within the City of Carlsbad administrative and management framework. This would include bringing the existing District operation
under existing City policies and centralize management and administra-
Uve support systems in the following areas:
Personnel Management -- including compensation management,
recruiting and selection, staff development, and related personnel
services provided by the human resources department.
Financial Management -- including accounting, payroll, and
investment management to be provided by the City Finance
Department with water operations and services continuing as a
City enterprise fund. This should include elimination of
bifurcated rate setting and consideration of consolidation of all
financial operations and resources into a single water fund.
Purchasing Management -- all purchasing through and under the
policies of the City purchasing system.
Risk Management -- Safety training and related services to be
provided by the City Risk Management unit. This would include
management of exWing District insurance coverage and evalua-
tion of the adequacy and cost effectiveness of that coverage on a
continuing basis.
Vehicle Maintenance including transferring District vehicles to
the City Equipment Replacement Fund and system and having all
District equipment maintained by the City Vehicle Maintenance
Shop. This would require initial inspection of all District
vehicles by Fleet Maintenance (accomplishment of necessary
corrective maintenance to bring vehicles up to maintenance
-27-
standards as required), and acceptance of the fleet for mainte-
nance on a continuing basis.
Full implementation of the recommended utilities organization should be
viewed as the longer range goal, and implementation focused on achieving that goal
should be approached cautiously to avoid service disruption, negative impact on
programs, and unnecessary staff discomfort. The paragraphs which follow address
key steps related to moving to the proposed utility department organization.
9. CAREFUL, SEQUENTIAL IMPLEMENTATION OF THE PROPOSED UTILI-
TIES DEPARTMENT WILL NEED TO BEGIN WITH DEVELOPMENT OF A
STRATEGYTORESOLVECOMPENSATIONANDBENEFITDIFFERENTWLS
WHICH POSE THJX MAJOR BARRIER TO IMPLEMENTATION
Full implementation of the proposed Utilities Department will probably
require several years once compensation issues have been resolved. The timing of
each successive implementation step should be determined by City Management and
impacted staff based on two key factors:
. Success in achieving implementation of adjustments at each implemen-
tation step from the perspective of integrating staff and operations.
Each distinct organizational adjustment should be operatingsuccessful-
ly before the next implementation step is addressed.
. Capacity and development of key staff in regard to absorbing new and
different responsibilities resulting from organizational change and
reallocaUon of responsibility.
Based on these principals, the paragraphs which follow outline
recommended implementation phases to integrate the Carlsbad Municipal
Water District into City operations and move toward a consolidated Utilities
Department operation.
-28-
( 1) The First Kev Implementation Step Will Involve T’ran.siUonix@ The District
kom an Autonomous Administrative Entitv To A Department InteQrated Into
The Citv’s Administrative Structure
This initial step can be implemented without transfer of personnel or
any significant change in organization structure or assignment of responsibili-
ty. With the Administrative Manager of the District taking the lead and
coordinating with appropriate departmental staff in the City structure, basic
administrative and support programs in the following area should be
transitioned from the District to the responsible City department. City
policies and procedures should be adopted as the basis for day to day
administrative operations within the District. These include:
. Transitioning responsibility for personnel management from District
staff to the Human Resources Department. This should include:
Compensation administration involving maintenance of the
District’s separate compensation structure and plan as well as
development of the implementation of the &rate@ to transition
District staff to a compensation structure compatible with and
part of the overall City structure.
Recruiting and selection support
Af&maUve action program administration
Staff development including coordination of the performance
appraisal process.
. Incorporating the District into City purchasing systems and practices.
. Assigning the City Risk Manager responsibility for insurance adminis-
tration and safety program management as it impacts the District.
. Transitioning District vehicles and major equipment items to the City
Fleet Maintenance operation as previously described.
This initial step will involve significant change in the responsibilities of
-29-
the District Administrative Manager who currently has lead responsibility for
most programs outlined above. As the organization changes and integration
is effected, it is anticipated that the Administrative Manager position will
transition in responsibility and job content as follows:
. Have lead responsibility for coordinating the transition of administrative
and support responsibilities to appropriate City departments, including
orientation of District staff in new procedures, policies, and systems.
. As subsequent implementation steps unfold, have lead responsibility for
developing a consolidated customer service organization plus subse- quent implementation work steps.
. Potentially ultimately transitioning to an Assistant Director or compara-
ble position with increased involvement in programming, planning, and
implementation in support of the Utilities Director. The e,xtent to which
this adjustment occurs is dependent on whether or not the Utilities
Department is implemented as proposed in this report and responsibil-
iUes of the Utilities Director broadened and expanded, generating a
potential need for an Assistant Department head.
(2) Anv Additional OrganhaUonal Adluslment Leadine To The Recommended
Utilities Department Must Be Deferred Until Compensation And Benefit Issues
Are Resolved
As noted in previous paragraphs, some significant differences exist
between the District and the City compensation siructure. These differences
are significant enough to pose short-term barriers to any organizational
change inherent in the long-term move to a Utilities Department concept. As
a result, no additional implementation steps should be taken or personnel or
structures transferred until an acceptable strategy has been developed to “fit”
the District and City compensation structures. Steps required to address this
issue include the following:
-3O-
. The City and the District will need to conduct a detailed classification
and job content analysis of all District positions to determine where
each “fits” in relation to the City classification structure. This is a
critical step to ensure that each District employee is equitably dealt
with in any compensation plan transition. It should also incorporate
analysis of how some existing District positions could change in content
and responsibility given the transition from Water District to the
Utilities Department over the long range. Issues to be addressed in the
analysis include: ( 1) potential transition of the Administrative Manager
from current classiiicatlon to assistant department head status; (2)
impact of assignment of all customer service responsibilities and staff
on the Administrative Analyst position; and (3) longer range impact of
expanded responsibilities for the sewer maintenance and meter reader
units on a job content and classification of the Superintendent, Water
Operations, and Maintenance. A potential result of the job content and
classification study could be reclassification of City and/or District
positions which might reduce or eliminate the compensation differential
identified in previous analysis.
. As the results of the job content and classification analysis become
clear, resulting information should provide the basis to develop a
strategy for resolving the existing salary and benefit differentials and
uphold the spirit of the initial agreement which maintains that no
employee would be harmed as a result of making the District a
subsidiary district. There are a variety of approaches which could be
taken to fashion a compensation transition strategy. These strategies
could range from:
“Grandfathering’ all existing District employees’ salaries and
fringe benefits at current levels until such time as they leave the
City’s employment.
For those District employees whose current compensation is
above counterpart City positions, “freeze” salaries until the City
structure catches up. For those District employees whose
salaries fell below counterpart City positions, increase compensa-
tion to eliminate any compensation differential at the Ume of
merger.
Adopting a system under which District employees (whose
compensation exceeded counterpart City positions) would receive
annual cash payments equivalent to all or part of the annual cost
of living rate increase, but would have base salaries frozen until
such time as the City salary structure catches up. As with the
second option above, District employees whose salaries fall below
counterpart City positions would have their compensation
31-
increased to eliminate differentials at the time of merger.
The approach ultimately adopted will need to reflect both the spirit and
provisions of Exhibit A to the reorganization agreement.
(3) Once A Compensation And Benefit ‘lbnsition Stratw Has Been Developed,
the Next Implementation Step Should Focus on E&ablish.i.ng an I&mated
Customer Service Orgmization
The third major implementation step should involve establishing
consolidated responsibility for all customer services activities as outlined in
Exhibits I and III earlier in the report. This would involve:
. Transferring utility billing and meter reading staff to the Districtievolv-
ing Utilities Department.
. Organizing and implementing a unifled customer service program which
addresses the following:
Consolidated responsibility for handling and responding to all
customer service requests and complaints.
Analyzing meter reader and field maintenance crew workload and
determining the feasibility of realigning workload responsibilities
related to meter repair and replacement as well as water leaks
currently handled by meter reading staff.
Linking resources in a comprehensive conservation program.
. Transfer District accounting staff to the Finance Department to expand
responsibilities involving handling both water related and other City
financial management and processing activities.
This step should be completed and fully digested before additional
organizational adjustments are attempted.
(4) Several Sequential Steps Should Be Taken To Improve Coordination Of
Development Review And Capital Improvement Related AcUvities
As the study concludes, there is a legitimate difference of opinion about
32-
how to resolve issues related to development related inspections and capital
project implementation and management. These differing opinions include:
. Concern among District staff and management about the impact of
separating responsibility for project design and planning from the
ultimate construction management and inspection of capital projects.
. Concern among the staff of the City Engineer’s Department regarding
project coordination and duplication of effort in inspections and
comparable activities.
There is validity to both sets of concerns. The project team feels the
following approach should be taken to address these issues in the context of
recommended organizational adjustments and the long-term goals related to
the establishment of a Utilities Department.
.
.
Immediately take steps to eliminate the need for developers to post
duplicates of bonds for completingrequired public improvements. This
can be accomplished without any organizational adjustment through
agreement and coordination between District staff and the City
Engineer. The District General Manager/District Engineer, assisted by
the Engineering Manager and the City Engineer should have responsi-
bility for working out an agreement and establishing a coordinated
process within 60 days of acceptance of this report.
Concurrently, explore ways to cross-utilize personnel and eliminate
duplication of effort in field inspections. Again, the District General
Manager/District Engineer and the City Engineer should explore ways
to use District inspectors to accomplish concurrent inspections of
sewer and water improvements, and to consider total inspection
workloads in utilizing the Capital Projects inspector assigned to the
District to handle other complex inspections as time is available. This
issue should also be addressed within 60 days of the report’s accep-
tance.
. Over the next 90 days, determine if interorganizational agreements can
be employed to resolve issues raised by all parties related to the capital
project management process. This should be the responsibility of the
District General Manager/District Engineer and the City Engineer and
should address the following:
e If concerns related to timely bidding and construction of priority
-33
water projects can be resolved without organizational adjust-
ments.
If issues related to coordination regarding capital projects
involving both agencies can be resolved by designating one agency
as having lead responsibility for the project, including both water
and street facility components.
The results of these steps dictate how engineering organizational
alternatives should be addressed as the Utilities Department implementation
is pursued. The project team supports the following approach:
. Over the short-term employ coordination and interorganizational
agreements as noted above to address issues.
. Over the longer term (once compensation issues have been resolved; the
District has been aligned with the City’s basic administrative structure;
and the customer service organization has been fully implemented),
move the centraiized responsibility for sewer, water, and reclaimed
water planning and progr annning to the Utilities Department. This will
involve:
Transitloning sewage treatment and sewer collection system
plannin g from the City Englneer and the Utilities and Mainte-
nance Director to the Utilities Department. Before these
responsibilities can be transitioned, the Utilities Department will
need to have an organization in place to accept these responsibil-
ities including:
l . An established Chief Engineer position to direct “hands
on” engineering and planning activities to free the Utilities
Manager to accept expanded planning and coordination
responsibilities.
. . In-house engineering capabilities to address capital
improvement projects design and planning needs related to both sewer and reclaimed water projects.
If interagency agreements and coordination have not been
successful in addressing issues noted above, transfer responsibil-
ity and staff related to all phases of inspection to the City
Engineer, and assign the City Engfneer responsibility for bidding
and managing the construction of all capital projects once
planned and developed.
(5) The Last Step Iu The Utilities Department Evolutionaw Process Would Involve
Transferring! Responsibilitv For Sewer Maintenance Operations Staff and
Services
The recommended customers services organization needs to be in place
and engineering organization and operating issues resolved before sewer
maintenance staff and related responsibilities are transferred from the
Utilities and Maintenance Department to the Utilities Department. From the
Implementation perspective, this will be the last step in the evolutionary
process.
* * * * *
The timing with which these recommended implementation steps proceed are
dependent on two major factors:
. The pace with which compensation differentials are resolved and a
reasonable strategy developed for integrating employees from both
organizations.
. As importantly, City management’s judgment regarding progress made
in establishing and accepting change at each step in the process.
The Appendices which follow provide supporting information related to
findings and recommendations contained in the main body of this report.
-3!5-
APPENDIXA
PROFILE OF STAFF ASSIGNMENTS
AND RESPONSIBILITIES FOR THE
CARLSBAD MUNICIPAL WATER DISTRICT
APPENDIX A (1)
PROFILE OF STAFF ASSIGNMENTS AND
RESPONSIBILITIES FOR THE
CARLSBAD MUNICIPAL WATER DISTRICT
The pages which follow describe the current staffing and responsibilities of
all positions in the Carlsbad Municipal Water District. Data were developed based
on interviewed staff both within the District organization and in the City of
Carlsbad departments and operations with which the District relate.
Separate sections are provided for each of the major organizational functions
within the District and the profile also describes how each unit and staff member
currently interfaces with various aspects of the City of Carlsbad operations.
1. ADMINISTRATION
APPENDIX A (2)
1. ADMINISTRATION
Number
Interface With
Position Actual Auth. Responsibility Other City
Operations
General Manager/ 1 1 Overall management/lead City Manager/Deputy
District Engineer administrative responsibility City Manager on
for District operations. With District
District moving to subsidiary plans/programs -
status, increasing other City staff
involvement/time related to Council
commitment to interaction agendas when
with City manager/top Council acting as
management staff plus more District Board of
executive level decision Directors.
making within District
structure (purchases,
expenditures, etc.) with
Commission moving to
advisory from administrative
role.
Executive Secretary 1 1 Clerical and administrative
support to General Manager/
District Engineer and
Administrative Manager.
Takes/prepares commission
minutes. Assists in
preparation of agendas/
commission packetsjetc.
Administrative 1 1 Responsible for supervision/ Interfaces with
Manager implementation of numerous
administrative procedures in departments as
District that include: Budget Division Head to
preparation and monitoring, provide/receive
investment management, information on
water rate calculation, service delivery
development of capital issues.
improvement program plans,
personnel and risk
management, City relations/
communications, preparation
of statistical progress reports, supervision of some clerical
and professional staff, acts in
General Manager capacity
during his absence.
APPENDIX A (3)
Number
Interface With
Position Actual Auth. Responsibility Other City
Operations
Administrative 1 1 Acts predominantly as Public N/A
Analyst Information Officer which
includes: Dissemination of
informational products to
community, customer service
in response to water
conservation questions,
brochure development, special
event planning, computer
database maintenance. In
addition, acts in analytical
capacity which has included
cost/benefit analysis of various
District sponsored
conservation programs to
include - rebates for use of low
flow devices, turf audits and
instructional programs to high
volume users.
Accountant 1 1 Oversees one accounting office Finance Department,
assistant and unit Accounting Division
responsibilities to include - for payment of water,
accounts receivable, journal major facilities fees,
entry, financial statements, etc.
computerized data entry,
maintenance of audit trails,
quarterly and annual report
preparation, etc.
Accounting Office 1 1 Accounts payable, payroll, petty Finance Department,
Assistant cash and limited clerical Accounting Division
duties as assigned. to pay for services
(i.e., gasoline, etc.)
rendered.
Receptionist 1 1 Directs incoming calls and
personnel to proper divisions or
units. Clerical duties as
assigned.
2. ENGINEERING
APPENDIX A (4)
2. ENGINEERING
Position
Zngineering
Manager
Number
Interface With
Actual Auth. Responsibility Other City
Operations
1 1 Job responsibilities and time Engineering
allocation in transition. Department
Previously heavy commitment Development Review
to development generated unit related to plan
facilities including: (1) checks and developer
Meeting with requirements.Utility
developers/engineers on coordination
district requirements related to meetings;
water facilities; (2) Plan responding to City
checking development related Planning Dept.
facilities’ plans; and (3) project inquiries;
Miscellaneous administrative work very closely
activities related to completion/ with City Fire
acceptance for maintenance of Marshal on new
facilities built by developers development and
including processing and upgrading of existing
closeout of subdivision, and systems.
relocation and reimbursement
agreements. Currently, less
time on board actually plan
checking and more time
devoted to: (1) Prime District
contact with developers/
developers’ engineers; (2)
Working with appropriate
developers involving
plans/facilities associated with
the reclaimed water system; (3)
Increasing involvement in
Master Plan maintenance in
support of General
Manager/District Engineer;
(4) Staff development/training
to support transition of plan
check workload; (5) More
involvement with District
C.I.P. management , and (6)
Revision of CMWD Standard
Specifications,
potable/reclaimed procedures
and design criteria.
APPENDIX A (5)
Position
Senior
Engineering
Technician
Engineering
Technician III
Engineering
Technician II
Number
Interface With
Actual Auth. Responsibility Other City
Operations
1 1 100% on in-house design of CIP Engineering
projects-primarily on Department:
replacement projects for water l Traffic
distribution piping systems. engineering for
Work has recently included traffic control
design/ preparation of requirements on
specifications for city street CIP projects.
improvements related l Coordinate
to/impacted by water system inclusion of
projects. Handles projects District C.I.P.
through bid (includes projects with City
preparation of bid package) C.I.P. projects
and responsible for design of when applicable.
project revisions once Utilities and
construction begins. Maintenance
Department:
l Meter shop input
related to water
service connection
replacements
triggered by CIP
projects.
1 1 In process of accomplishing l Major use of City
computerized mapping of all Mapping Section
District facilities. Will also be re: Old Downtown
responsible for computerized area, “Old City
mapping of all new reclaimed Service Area”.
water facilities. Maintains, l Familiar with City
posts to maps all district mapping
easements. Special projects as facilities.
assigned.
1 1 50% on plan check of new
facilities installed as a result
of subdivision construction
and individual buildings. 50%
on inspections of newly
constructed facilities. Serves
to “back-up”/handle overflow
workload from the two primary
inspectors.
APPENDIX A (6)
3. OPERATIONS AND MAINTENANCE
-
Number
Interface With
Position Actual Auth. Responsibility Other City
Operations
Superintendent - 1 1 Supervision/day-to-day Contact with utility
Water Operations oversight of operations and maintenance
and Maintenance maintenance staff and regarding vehicle
activities. Schedules staff and service, customer
directs/prioritized all service and water
maintenance projects/ service
activities. Increasing maintenance/
involvement in &I/laster Plan replacement.
maintenance and facilities
plan check perspective of
maintenance requirements
and issues.
System Operations 1 1 Oversees and participates in Contact with Utilities
Supervisor distribution/transmission and Maintenance
system of District’s potable Department and with
water. Duties include Quality Police Department
Control (testing), equipment dispatch during
maintenance, and emergency malfunction/
response. Position directly breakage of
supervises five operator unknown type
positions and all other duties pipeline.
associated with unit operation.
Senior System 1 1 See responsibilities listed Contact with Utilities
3perator below. In addition, position and Maintenance
possesses additional Department and with
certifications as compared to Police Department
system operator. dispatch during
malfunction/
breakage of
unknown type
pipeline.
System Operator II 4 4 Maintains all valving, Contact with Utilities
regulating, chlorinating, and Maintenance
pumping station, etc. facilities Department and with
and equipment; conducts Police Department
laboratory testing; maintains dispatch during
telemetry system; modifies malfunction/
water flow and transmission breakage of
bases on demand; responds to unknown type
emergencies and repairs pipeline.
equipment on 24-hour (on-call)
basis.
3. OPERATIONS AND MAINTENANCE
APPENDIX A (7)
3. OPERATIONS AND MAINTENANCE
Number
Interface With
Position Actual Auth. Responsibility Other City
Operations
Superintendent - 1 1 Supervision/day-to-day Contact with utility
Water Operations oversight of operations and maintenance
and Maintenance maintenance staff and regarding vehicle
activities. Schedules staff and service, customer
directslprioritized all service and water
maintenance projects/ service
activities. Increasing maintenance/
involvement in Master Plan replacement.
maintenance and facilities
plan check perspective of
maintenance requirements
and issues.
System Operations 1 1 Oversees and participates in Contact with Utilities
Supervisor distribution/transmission and Maintenance
system of District’s potable Department and with
water. Duties include Quality Police Department
Control (testing), equipment dispatch during
maintenance, and emergency malfunction/
response. Position directly breakage of
supervises five operator unknown type
positions and all other duties pipeline.
associated with unit operation.
Senior System 1 1 See responsibilities listed Contact with Utilities
Operator below. In addition, position and Maintenance
possesses additional Department and with
certifications as compared to Police Department
system operator. dispatch during
malfunction/
breakage of
unknown type
pipeline.
System Operator II 4 4 Maintains all valving, Contact with Utilities
regulating, chlorinating, and Maintenance
pumping station, etc. facilities Department and with
and equipment; conducts Police Department
laboratory testing; maintains dispatch during
telemetry system; modifies malfunction/
water flow and transmission breakage of
bases on demand; responds to unknown type
emergencies and repairs pipeline.
equipment on 24-hour (on-call)
basis.
APPENDIX A (8)
Position
Construction
Maintenance
Supervisor
Senior
Construction
Maintenance
Worker
Construction
Maintenance
Worker
Equipment
Operator
Facilities
Maintenance
Leadworker
Number
Interface With
Actual Auth. Responsibility Other City
Operations
1 1 Office and in-field supervisory Contact, but little
position overseeing operations interface of duties
of construction/maintenance with sewer crew or
crew as described below. meter shop during
Responsible for all duties installation or repair
associated with unit operation. projects involving
pipeline in same
area.
1 1 Acts in leadman capacity Contact, but little
overseeing in-field duties of interface of duties
construction/maintenance with sewer crew or
workers and equipment meter shop during
operator. Conducts other duties installation or repair
as described below. projects involving
pipeline in same
area.
2 2 Installs and repairs all main Contact, but little
pipeline and laterals that interface of duties
includes digging of trenches, with sewer crew or
laying of line, valves, fittings, meter shop during
fire hydrant installation, installation or repair
temporary blacktop patching projects involving
and all traffic control. pipeline in same
Completes new line area.
installations not to exceed 200-
300 yards. Also paints and
assists in maintaining fire
hydrants and fire sprinkler
check valves, raises valve
boxes in newly paved streets,
paints valve boxes, etc.
1 1 Operates heavy equipment Contact, but little
(back-hoe, etc.) for interface of duties
construction maintenance with sewer crew
crew in addition to above meter shop during
duties. installation or repair
projects involving
pipeline in same
area.
2 2 Responsible for grounds N/A
maintenance of eleven
reservoirs and main building
area to include: weeding,
sprinkler system
maintenance, trimming of
shrubbery, planting,
fertilization, etc.
APPENDIX A (9)
Position
Service
Coordinator
Storekeeper
Number
Interface With
Actual Auth. Responsibility Other City
Operations
1 1 Locates underground water Contact with other
utility pipes for all excavation utility divisions
projects; maintains fire during pipe location;
hydrants through barrel contact with Fire
inspection, joint lubrication Department on
and brush clearance; conducts inspection program.
all periodic maintenance on
District’s fleet vehicles.
1 1 Maintains control over all N/A
inventory (parts) that District
uses to include: Supply re-
ordering; part distribution and
use; inventory control through
database maintenance; vendor
contacts; competitive bid
processing; etc. Also acts in
capacity of safety officer
providing safety classes/tips
and maintaining hazardous
material data sheets. finally
does occasional building
maintenance and small
equipment repair.
APPENDMB
POTENTIAL SERVICE DELIVERY
AND OPERATING ISSUES RESULTING
FROM EXISTING ORGANIZATIONAL
CONFIGURATION AND ASSIGNMENT OF
RESPONSlBILlTIES TO THE DISTRICT AND
CITY OF CARLSBAD DEPARTMENTS
APPENDIX B (1)
t3norafil-ral.SorviPa Area I Tcc13 PC v yv’““*“b’ UIL . AYV *II vu
1. Customer Contactq
l Opening and Closing
Service Accounts-
working relationship
between billing staff and
meter readers.
l Potential convenience for walk-in trade -
downtown versus District (or additional
satellite) of&e location.
l Cash control/handling procedures if billing
staff separated from basic Finance
Department operation.
l Potential fragmentation/inefficiencies
resulting from current physical separation
of billing staff and meter readers.
l Service complaints/ l Confusing division of responsibilities - not
questions by/from public. clear to public who to contact considering:
- Regular working hours. - District-leaks beyond meter connection.
- After hours. - Meter Staff-leaks - meter to structure.
- District-Water taste/smell issues.
- Billing Staff-bill/charge problems.
- District-emerging responsibilities for
water conservation/ consumption
monitoring control.
l Confusion also impacts Police Department
who question proper contact for emergency
calls on breakage after hours.
l Consumption control/
conservation/enforcement
l Who is responsible? Organizational
fragmentation in regard to resources/staff
with potential involvement in conservation
program-e.g., coordinated use of meter
readers for field identification of violators;
use of billing information to monitor/
analyze consumption patterns.
APPENDIX B (2)
nnaratinv’l.Comri~n Area I TCCI, PC v yw* U”.L”bJ VYL . IUV A*A. “U *““u””
2. Develonment Review and
Control
l Processing bonds/
agreements/fees/etc.
l Requirement for developers/applicants to
make application/process payments -
papers at multiple points (e.g., District/
Engineering) - convenience/coordination
impact. Duplicative requirements for
submitting plans, scheduling field
inspections, etc.
l Plan checks/field
inspections of installed
facilities.
l Potential duplication/overlap in field
inspections?
l Plan check quality/control
and service levels.
l Different approaches to staffing for plan
check (e.g., District - in-house; City heavier
use of consultants) - District staff concern
that quality/control would be lost it
integrated with City Engineering.
l Any real economies of scale/potential to
improve staff utilization if integrated?
l Current service levels differ in regard to
turn around time.
APPENDIX B (3)
Operating/Service Area Issues
3. (&&al Proiect Desielq
w&ion and Contract
Administration
l Design/engineering l Would/could coordination be improved if
design functions merged (e.g., water
projects in/near streets). Any
demonstrable evidence that coordination
currently a problem given staff level
working relationships?
l Are water projects sequenced/coordinated
with street improvement/replacement
priorities based on current
operations/planning approaches?
l Any real impact on staff utilizationl
completing planned projects given current
staffing/staffing approaches at District and
in Engineering?
l How would merger/integration of
engineering functions/responsibilities
impact coordination/control of master plan
maintenance; capital project sequencing;
APPENDIX B (4)
fhwrat.invIScwvirrP Area I Tccu PC v yY’u”“Aw UVL .A”” *A&vu
3. Cat&xl Proiect De&n+
on and Contract
Adam ‘stration
(con&~)
. Contract administration/
performance monitoring
and control.
AVVU””
l How to achieve coordinated approach to
bidding/selection/inspection/contract
management of water/streets projects?
l To what extent do current approaches to
bidding, selection, progress payment
approval, field inspection differ? To what
extent does divided responsibility negatively
impact contract administration?
l Any real duplication of effort in regard to
field inspection of capital projects given
current/expected future capital project
mix?
l To what extent do staffing approaches (e.g.,
District - in-house; City - heavier use of
consultant/contract services> differ and
actually impact control/quality of
contractor performance and facilities
constructed?
l District staff perception that use of contract
staff by Engineering results in staff
turnover - makes application of consistent
quality control in field inspection difficult.
APPENDIX B (5)
Operating/Service Area
4. Field Maintenance and i;omtruction
Issues
l Water operations. l No discernable relationship with other City
functions. Most probably, will continue to
function as discrete, stand-alone unit no
matter how water services ultimately
organized.
l Does current differentiation of water
services address actual responsibility vs.
“legal” responsibility (i.e.,Utilities
Maintenance Department conducting back-
flow testing vs. District ultimately
responsible for hazards associated with
improper inspection).
l Water/sewer
maintenance.
l Any real potential for improved utilization
of field maintenance staff if managed/
directed by common manager? Any
practical evidence that cross utilization
occurs in cities/jurisdictions in which
utilities operations consolidated under
common management?
l Would increased coordination/
consolidation have positive impact on
vehicle/equipment utilization? Any real
practical potential to cross utilize major
equipment given current inventories for
water and sewer units, potential “health
hazard” issues raised by cross utilization of
field equipment used by sewer and water,
as well as patterns of field maintenance
tasks and service activities?
l Inventory/stores control. l Potential to increase staff utilization if
water and sewer stores/inventory control
activities combined? Any common
materials currently maintained in
inventory to support water and sewer field
maintenance?
APPENDIX B (6)
Operating/Service Area
4. Field Maintenance and Construction (continued)
Issues
l Underground services
alert/identification.
l Any duplication of effort/scheduling -
coordination problems given current
division of responsibilities? How does
Utilities and Maintenance Department
currently handle? Who has responsibility?
l Emergency Standby l Any opportunity to improve cost-
effectiveness if utilities operations under
one management-in regard to after hours
standby/emergency call out crews, or are
skills/experience sufficiently diverse to
dictate continued diversification of
function?
5. Administration and Financial Serviceq.
l Accounting/related
financial processing/
control functions.
l With current distinct District operation,
most internal systems/workload related to
those systems parallel systems maintained
and staffed by the City. Any unique
characteristics of District requirements/
systems which dictate separate operations
vis-a-vis incorporating requirements to
support District like other City
Departments through central
administrative and financial services?
l What workload impact if basic financial
services centralized in Finance
Department ? Would reassignment of
District accounting/related financial staff
to Finance Department positively impact
utilization/provide Finance Department
capability of absorbing workload increases
(beyond those resulting from assumption of
District responsibilities) without
commensurate increases in Finance
Department staffing?
APPENDIX B (7)
Chm-nt.invl.Skvvir~ AT-OS I TCCUPC v yv* U’^“b, WV* . &WV *A* uu 1 *““u”Y
5. Administration and Fhancial Services. (contiuued)
l Billing functions/staff.
l Personnel systems/
services.
. Rate setting.
l Compensation system/
structure.
l Risk management/
insurance.
l Legal formation.
l If customer services activities consolidated
with District/Utilities Department/some
other organizational form, what impact of
physically removing billing staff from the
Finance Department (cross training/back-
up other staff? Counter coverage? etc.).
l How do current District programs/
priorities (e.g., Affirmative Action,
recruiting selection approaches) differ
from the City’s programs? Should they
now that District in subordinate district
status?
l Does bifurcated rate setting responsibility
(at the staff level) make sense? Is it
organizational or simply a communication
issue?
l How do City and District compensation
systems really differ on position by position
basis considering full dollar value of
compensation and fringe benefits? Are
differences significant enough to provide
barriers to organizational adjustment(s)?
l How do differences in City and District
access to insurance coverage impact
phasing/implementation of any
organizational adjustment?
l What special powers available to District
(e.g., financing flexibility, other?)
unavailable to the City? How do these
considerations impact organizational
options?
APPENDIX B (8)
OperatinglService Area
6. PlanninPIProwamming
Issues
l Sewer, water, and
reclaimed water services.
l Is there a “logical” operating and planning
fit between the District’s current water
service operation and sewer maintenance
services provided by the Utilities and
Maintenance Department? How, if at all,
does implementation of the reclaimed
water program impact that “fit”?
l If all utilities’ services merged, what
impact on/how handle sewer facilities
related engineering and plan check
services?
l Master planning. l Are City and District plans consistent from
perspective of “matching” required
resources (e.g., water capacity) with City
growth management plan in place? Does
current organizational arrangement
inhibit/promote/have no impact on
coordinated planning and resource
development?