HomeMy WebLinkAbout1991-08-06; Municipal Water District; 118; Amendment to 1991-92 Operating Budget’ -. CARLSBAD MUNICIPAL WATER DIS ClT=OF CARLSBAD - AGEN
AMENDMENT TO 1991-92 OP
FOR CARLSBAD MUNICIPAL
RECOMMENDED ACTION:
Adopt Resolution No. ?‘i 3 the Carlsbad Municipal Water District 1991-92
Operating Budget.
ITEM EXF’LJWATION:
A recent review of the 1991-92’ Carlsbad Municipal Water District Operating
Budget has shown that the figures presented as part of the budget document
were not the correct budget totals. Due to the constant change in water rate and
consumption assumptions during May and June, 1991, staff failed to provide the
appropriate fiscal figures to the Board for adoption. In addition, a mathematical
error within the submitted budget resulted in staff reporting a total budget figure
which was lower than it should have been. This error was found during the
process of entering the budget numbers into the computer as the books were
opened for 1991-92. Finally, for the first time, depreciation expenses now appear
within the expenses side of the budget. Although this is not a new expense, it
has not previously been shown as one. Depreciation consists of a $1 .l million
expense.
Although the corrected CMWD budget is higher than the one provided in the
preliminary budget document, it remains in balance. The cost increases in water
purchases are offset by additional revenues resulting from water sales. CMWD
expenses will total $7.4 million, with revenue totaling $7.7 million at the present
consumption levels.
FISCAL IMPACI?
Projected revenues are sufficient to accommodate estimated expenditures for the
Fiscal Year 1991-92.
EXHIBITS:
Resolution No. 3 47 adopting the amended 1991-92 Operating Budget for the
Carlsbad Municipal Water District.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
- RESOLUTION NO. 7 4 7
A RESOLUTION OF THE BOARD OF DIRECTORS OF THE
CARLSBAD MUNICIPAL WATER DISTRICT, AMENDING THE
FINAL OPERATING BUDGET FOR THE FISCAL YEAR 1991-92
WHEREAS, the Board of Directors of the Carlsbad Municipal Water District
has reviewed and adopted the Operating Budget for fiscal year 1991-92 and has
held such public hearings as ztre necessary prior to the adoption of the final
Operating Budget; and
WHEREAS, the Board of Directors of the Carlsbad Municipal Water District
has reviewed the amended 1991-92 Operating Budget.
NOW, THEREFORE, BE IT RESOLVED by the Board of Directors of the
Carlsbad Municipal Water District as follows:
1. That the above recitations are true and correct.
///
///
///
///
///
///
///
///
///
///
///
///
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18 /
19 1
23
24
25
26
27
28 1
2. ‘That certain documents now on file in the office of the City Clerk of the
City of Carlsbad entitled “City of Carlsbad, California 1991-92 Operating Budget” as
amended in accordance with Exhibit A attached hereto and incorporated by
reference herein, shall be and the same is hereby adopted as the final Operating
Budget for the Carlsbad Municipal Water District for the fiscal year 1991-92.
PASSED, APPROVED AND ADOPTED at a regular meeting of the Carlsbad
Municipal Water District Board of Directors held on the 6th day of
August , 1991, by the following vote, to wit:
AYES: Board Members Lewis, Kulchin, Larson and Stanton
NOES: None
ABSENT: Board Member Nygaard
ATTEST:
ALETHA L. RAUTENKRANZ, Secretary]
(SJ=u
_ Eb()K637 “iv
PROGRAM: WATER SUMARY FUND: GENERAL
DEPARTMENT: WATER SUtMARY SUMARY
PERSONNEL
MAINTENANCE OPERATION
CAPITAL OUTLAY
GRAND TOTAL
POSITIONS
1987-88 ACTUAL
S 1,363,DOO
4,536,005
157,527
S 6,056,262
31
1988-89 1989-90 1990-91
ACTUAL BUDGET BUDGET
t 1,591,931 s 1,5%,060 s 1,842,951
5,293,940 4,708,579 5,235,244
226,300 158,750 330,100
S 7,112,171 t 6,463,389 S 7,408,295
31 35 35
PROGRAM: ADMINISTRATION
FUND: WATER DISTRICT
DEPARTMENT: CARLSBAD WATER DISTRICT ACCT t5W-6310
-
PERSONNEL
MAINTENANCE OPERATION
CAPITAL OUTLAY
GRAND TOTAL
POSITIONS
1988-89
ACTUAL
s 220,000
4,369,206
61,429
0 4,650,635
6.0
1989-90
ACTUAL
s 313,644
5,021&O
67,000
S 5,402,084
6.6
1990-91
BUDGET
S 318,800 0 442,545
4,446,410 3.796.992
40,000 13,500
t 4,805,210
6.6
1991-92
BlJDGET
S 4,253.037
6.6
WORK PROGRAM:
Perform the administrative tasks necessary to provide Carl&ad with a water supply of sufficient quantity to
meet the demands required for health, safety and uelfare purposes. In addition, ensure that the available
supplies are used as efficiently as possible.
PROGRAM ACTIVITIES:
Unifvinathe Amncies: Implement the plan to provide a smooth transition between the District and the City.
Drouaht Plaming: Implement the Drought Response Plan for 1991, which is &signed to reduce per capita demands
throughout the District’s service area.
Water Conservation: Meet all applicable water conservation targets, thus reducing the potential penalties that
may be assessed by the San Diego County Water Authority.
Leqislation: Have involvement in Federal and State legislative issues as they pertain to the water supply.
SIGNIFICANT CHANGES:
The uater billing function will be directed and operated by the District which implements the plan to meld both
the City and the District. An account Clerk II and an Account Clerk I wi 11 be transferred to the Uater District, uhile an Accountant and an Account Clerk II will be transferred to the City Finance Department.
_I
PROGRAH: MAINTENANCE AND OPERATIONS FUND: WATER DISTRICT DEPARTMENT: CARLSBAD WATER DISTRICT ACCT t 5D4-6320
PERSONNEL
MAINTENANCE OPERATION
CAPITAL OUTLAY
GRAND TOTAL
POSITIONS
WORK PROGRAM:
1988-89 198990 1990-91 1991-92
ACTUAL ACTUAL WDGET BUDGET
s 715,000 s 800,044 0 859,320 0 1,400,406
149,949 266,500 253,669 1,438,252
89,868 151,300 110,750 316,600
t 954.817 S 1,218,644 t 1,223,ir39 S 3.155.258
15 16 16 20.4
Provide Engineering Services for construction of the potable and reclaimed uater system. Provide Carl&ad uith
a uater supply of sufficient quantity and pressure that meets all applicable federal, State and local quality
standards.
PROGRAM ACTIVITIES:
Recleid Uater: Provide reclaimed water to the Phase I list of users as specified in the District's Uater
Reclamation Master Plan.
Plm Check: Review and correct plans for neu development in a tuo-ueek turnaround period.
Maooing: Develop and continuously update the computer based mapping system.
Desian: Reduce project costs by completing in-house design on various capital projects.
Svstem Maintenance: Maintain all uater facilities at a level to ensure safe and efficient operations.
Svstem Rermir: Repair all leaks imnediately to reduce uater loss, and perform the repsir with a minimm of
uater service disruption.
Safety: Eliminate uork related injuries and accidents.
SIGNIFICANT CHANGES:
Tuo Inspectors uill be transferred to the City's Municipal Projects program to implement the melding of the
Uater District with the City. Maintenance and operation costs have increased due to the representation of
depreciation expenses as a budgeted item for the first time.
c
PROGRAM: ENGINEERING
FUND: WATER DISTRICT
DEPARTMENT: CARLSBAD WATER DISTRICT
PERSONNEL
MAINTENANCE OPERATIDN
CAPITAL OUTLAY
GRAND TOTAL
POSITIONS
1988-89
ACTUAL
S 428,000
16,850
6,230
s 451,080
7.4
1989-90
ACTUAL
t 477,443
6,000
8,000
t 491,443
8.4
1990-91
BUDGET
t 417,940
8,500
8,000
t 434,400
8.4
1991-92
BUDGET
0 -o-
-D-
-o-
f -O-
-o-
WORK PROGRAM:
Provide engineering services for construction of the potable and reclaimed uater system.
PROGRAM ACTIVITIES:
None
SIGNIFICANT CHANGES:
This program has been integrated into one entitled Maintenance and Operations.