CARLSBAD MUNICIPAL WATER DISTRICT - AGENDA BILL
AB# 634
MTG. 5/22/07
DEPT. ENG
APPROVE AN INCREASE IN APPROPRIATIONS FOR
SAN MARCOS BOULEVARD WIDENING
PROJECT NO. 6005
DEPT. HEACptlXJft^T^-jr -»«5' «"-'
CITYATTY. ' ($!>
CITYMGR. 4£>
RECOMMENDED ACTION:
Adopt Resolution No. 1298 approving and authorizing an increase in appropriations for the
San Marcos Boulevard Widening, Project No. 6005.
ITEM EXPLANATION:
It was discovered during construction that a portion of the proposed median on San Marcos Boulevard
had to be redesigned and additional pavement removal and replacement quantities and facility
relocations were needed at the intersection of San Marcos Boulevard and Rancho Santa Fe Road.
The redesign work was completed by San Marcos and a construction change order proposal was
obtained from the contractor.
The additional unforeseen work requires additional funds to be appropriated for the San Marcos
Boulevard Widening in the amount of $250,000. This results in a need to increase the contingency for
the San Marcos Boulevard Widening portion of the construction contract from $459,423 to $709,423.
In accordance with Section I B7 of the agreement with the City of San Marcos, the Public Works
Director for the City of San Marcos has reviewed and approved the change order work and concurs in
increasing the project's contingency by $250,000 (see attached letter).
The contingency increase of $250,000 results in a need to increase the total appropriation
for the street widening portion of the project, Project No. 6005, from $2,734,147 to $2,984,147
(Table 1). All funds allocated and expended for the construction of the roadway work will be
reimbursed by the City of San Marcos under the existing agreement between the District and City of
San Marcos.
ENVIRONMENTAL IMPACT:
The City of San Marcos is the lead agency for environmental review. A Mitigated Negative Declaration
was prepared by the City of San Marcos in accordance with California Environmental Quality Act
(CEQA) guidelines. The CMWD San Marcos Boulevard Water Transmission Main Replacement,
Project No. 3956, was included in the Mitigated Negative Declaration for the widening project.
Since the project is located within the City of San Marcos, the City of Carlsbad does not have
regulatory jurisdiction.
FOR CITY CLERKS USE ONLY.
BOARD ACTION: APPROVED
DENIED
CONTINUED
WITHDRAWN
AMENDED
D
D
D
D
CONTINUED TO DATE SPECIFIC D
CONTINUED TO DATE UNKNOWN D
RETURNED TO STAFF D
OTHER - SEE MINUTES D
Page 2
FISCAL IMPACT:
The revised total cost of constructing the San Marcos Boulevard Widening Project is shown in
Table 1. This table reflects increasing the construction contingency budget by $250,000 and results in
a need to increase the appropriation for Project No. 6005 by $250,000. No adjustment is required for
the San Marcos Boulevard Transmission Main, Project No. 3956, appropriation.
TABLE 1
SAN MARCOS BOULEVARD WIDENING, PROJECT NO. 6005^
Construction Contract (J. Fletcher Creamer & Sons, Inc.)
Current Construction Contingencies Appropriation
Requested Contingency Increase Amount
Current Construction Management, Inspection, and Material Testing
(Nolte Associates)
TOTALCOST - -.-•' ' ,- ••:••. •- .-••• ••"• • \ *• -. -;v:;.v^
CURRENT APPROPRIATION
ADDITIONAL APPROPRIATION REQUESTED
$2,094,232
459,423
$250,000
$180,492
W.^Jt&MAftW-
i'.i.:.''$2^147v-
$250,000
EXHIBITS:
1.
2.
3.
Location Map.
Resolution No.1298 approving an increase in appropriations for the
San Marcos Boulevard Widening, Project No. 6005.
Letter from City of San Marcos.
DEPARTMENT CONTACT: Patrick Vaughan, (760) 602-2780, pvaug@ci.carlsbad.ca.us
LOCATION MAP
NOT TO SC/1LC
CITY OF OCEANS**
PACIFICOCEAN
SITE
PROJECT NAME
SAN MARCOS BOULEVARD WATER TRANSMISSION PIPELINE
REPLACEMENT AND STREET WIDENING
PROJECT
6005
EXHIBIT
1
DRMM BY. SCOU EVANS. CARLSBAD ENGINEERING DEPT. 3/5/07 C: \CANTM.\/(Hi£S\3956-«005.DI4G M
1
RESOLUTION NO. 1298
2
3
4
5
6
7
8
9
10
11
12
13
24
25
26
27
28
A RESOLUTION OF THE BOARD OF DIRECTORS OF CARLSBAD
MUNICIPAL WATER DISTRICT (CMWD), APPROVING AN INCREASE
IN APPROPRIATIONS FOR SAN MARCOS BOULEVARD WIDENING,
PROJECT NO. 6005.
WHEREAS, a funding and administration agreement was approved by Resolution No.
1252, dated July 15, 2005, between the City of San Marcos and CMWD for the San Marcos
Transmission Main Replacement, and the San Marcos Boulevard Widening Project; and
WHEREAS, on January 17, 2006, by Resolution No. 1267, the Board of Directors of the
Carlsbad Municipal Water District awarded the construction contract for the San Marcos
Transmission Main Replacement, Project No. 3956, and the San Marcos Boulevard Widening,
Project No. 6005; and
WHEREAS, on April 3, 2007, an increase to the construction contingency of the
San Marcos Boulevard Widening, Project No. 6005, was approved by the Public Works Director of
14 the City of San Marcos and approved by the Carlsbad Municipal Water District pursuant to
15 Resolution 1295; and
WHEREAS, it is been determined once again to be necessary to increase construction
contingency of the San Marcos Boulevard Widening, Project No. 6005, by an amount of
18 $250,000, which has been approved by the Public Works Director of the City of San Marcos; and
19 WHEREAS, it is therefore necessary to increase the total appropriation for the San Marcos
20 Boulevard Widening, Project No. 6005, by an amount of $250,000.
21 NOW, THEREFORE, BE IT RESOLVED by the Board of Directors of Carlsbad Municipal
22 Water District (CMWD) of the City of Carlsbad, California, as follows:
1. That the above recitations are true and correct.
2. That the contingency for construction of the San Marcos Boulevard Widening,
Project No. 6005, shall be increased by $250,000 and the Executive Manager is hereby
authorized to approve construction change orders up to $709,423 for Project No. 6005.
3. That the appropriation for construction of the San Marcos Boulevard Widening,
Project No. 6005, shall be increased by $250,000 to a total amount of $2,984,147.
U
*
1 4. That the Finance Director is authorized to appropriate an additional $250,000 from
2 the General Capital Construction Fund for the San Marcos Boulevard Widening, Project No.
3 6005, with the understanding that the City of San Marcos will reimburse the City of Carlsbad
4 based on monthly progress payments approved by the City of Carlsbad.
5 '"
6 '"
7 HI
8 ///
9 ///
10 ///
11 ///
12 ///
13 ///
14 ///
15 ///
16 ///
17 ///
18 ///
19 ///
20 ///
21 ///
22 ///
23 ///
24 ///
25 ///
26 ///
27 ///
28 ///
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
PASSED, APPROVED AND ADOPTED at a Special Meeting of the Board of
Directors of the Carlsbad Municipal Water District of the City of Carlsbad on the 22nd
day of May 2007, by the following vote:
AYES: Board Members Lewis, Kulchin, Hall, Nygaard
NOES: None
ABSENT: Board Member Packard
ATTEST:
LORRAINE M. WOqp, Secretary<SEAL> '
Public Works Department
201 Mata Way
San Marcos, CA 92069-2948
3
Telephone
760. 752.7550
FAX: 760.752.7578
May 08, 2007
Mr. Bill Plumber
Deputy City Engineer
City of Carlsbad
1635 Faraday Ave.
Carlsbad, CA. 92008
SUBJECT: SAN MARCOS BL. TRANSMISSION MAIN AND ROAD IMPROVEMENTS
CMWD PROJECT NO. 3956 AND COSM CIP NO. 274
INCREASE TO COSM CONSTRUCTION CONTINGENCY
Dear Bill,
I have reviewed the PCO items No. 36, 37, 38, 39, 41, 42, and items described as "1st
Delay Claim", "Construction Mgmt." and "Striping Revisions" in Change Order No.6 to the
Fletcher Creamer and Sons contract. Per the reimbursement agreement dated July 15,
2005, Section 1B7, I authorize the construction contingency to be increased by
$250,000.00 (two hundred fifty thousand dollars and no cents).
Respectfully,
Michael Mercereau
Public Works Director
cc: Jim Chafe, Construction Manager
Jim Bozer, Project Manager
Mike Edwards, City Engineer