HomeMy WebLinkAbout2014-08-26; Municipal Water District; 787; Extend Agreement with Carollo EngineersCARLSBAD MUNICIPAL WATER DISTRICT -AGENDA BILL
16
AB#
MTG.
DEPT.
787
08-26-14
PW-UTIL
APPROVAL OF AMENDMENT NO. 3 TO EXTEND
THE PROFESSIONAL SERVICE AGREEMENT WITH
CAROLLO ENGINEERS FOR ENGINEERING
SERVICES ON THE PRESSURE CONTROL
HYDROELECTRIC FACILITY AT MAERKLE
RESERVOIR, PROJECT NO. 5025
DEPT. DIRECTOR
GEN. COUNSEL
CITY MGR.
RECOMMENDED ACTION:
Adopt Resolution No. . 1499 _ approving Amendment No. 3 to extend the professional services
agreement with Carollo Engineers for engineering services on the Pressure Control Hydroelectric Facility
at Maerkle Reservoir, Project No. 5025.
ITEM EXPLANATION:
On September 22, 2009, by Resolution No. 1376, the Board approved the award of a Professional
Services Agreement with Carollo Engineers to provide a feasibility report, preliminary design,
environmental reports, final design and construction support services. The term of the agreement was
effective for a period of three (3) years and included an allowance to amend to extend it for two (2)
additional one (1) year periods. The scope of the agreement was subsequently amended to provide
additional specialty engineering services through the completion of the construction phase of the
project. In addition to the amended scope two (2) amendments to the agreement have been executed
extending the term two times with a final period ending of September 22, 2014.
The duration of the construction phase has been extended due to a later delivery date of the project's
hydroelectric generator. Services from Carollo Engineering are necessary through the installation and
testing of the hydroelectric generator. Installation and testing are now anticipated to be completed
during the month of December 2014. Amendment No. 3 will extend the duration of the term original
agreement with Carollo Engineering for an additional 1-year term with revised end date of September
21, 2015.
The project site is approximately one mile north of Faraday Avenue on a 51.87 acre parcel owned by
CMWD for Maerkle Reservoir as shown on Exhibit 2. Access to the property is from Applewood Lane in
the City of Vista. The project includes installing a hydroelectric generator to receive relatively high
pressure water from the San Diego County Water Authority's Tri-Agencies Pipeline Connection No. 3, and
then converting this pressure to produce up to 135 kilowatts of electrical power prior to discharging the
water to either the 10 million gallon (MG) Maerkle Tank or 200 MG Maerkle Dam Reservoir.
DEPARTMENT CONTACT: Mark Biskup at 760-602-2763 or email davidahles@carisbadca.gov
FOR SECRETARY USE.
BOARD ACTION: APPROVED
DENIED
CONTINUED
WITHDRAWN
AMENDED
vZT^ CONTINUED TO DATE SPECIFIC •.
• CONTINUED TO DATE UNKNOWN •
• RETURNED TO STAFF •
• OTHER- SEE MINUTES •
• REPORT RECEIVED •
FISCAL IMPAa:
There are no additional cost resulting from Amendment No. 3 to Profession Service Agreement with Carollo
Engineering. The following table shows the project cost summary.
PROJEa COST SUMMARY FOR PRESSURE CONTROL HYDROELECTRIC FACILITY AT MAERKLE RESERVOIR
(PROJECTNO. 5025)
DESIGN, ENVIRONMENTAL, AND PERMIT PHASE
Engineering Consultant Services and Staff Overhead $459,371
CONSTRUCTION PHASE
Construction Contract with Environmental Construction, Inc. $1,094,652
Construction Contingency $100,000
Construction Support Services (Carollo Engineers) $97,472
Construction Management and Inspection $85,040
CONSTRUCTION PHASE SUBTOTAL $1,377,164
TOTAL PROJECT COST $1,836,573
CURRENT APPROPRIATION $2,000,000
ENVIRONMENTAL IMPACT:
The project is exempt from the California Environmental Quality Act (CEQA) per State CEQA Guidelines Section
15303(d) - New Construction or Conversion of Small Structures. The City Planner filed a Notice of Exemption with
the County of San Diego on October 18, 2011.
EXHIBITS:
1. Adopt Resolution No. 1499 approving Amendment No. 3 to extend the professional
services agreement with Carollo Engineers for engineering services for the Pressure Control
Hydroelectric Facility at Maerkle Reservoir, Project No. 5025.
2. Location Map
3. Amendment No. 3 to Extend Agreement for Professional Engineering Services with Carollo Engineers
for Engineering Services on the Pressure Control Hydroelectric Facility at Maerkle Reservoir, Project
No. 5025.
1 RESOLUTION NO. 1499
2 A RESOLUTION OF THE BOARD OF DIRECTORS OF CARLSBAD
MUNICIPAL WATER DISTRICT (CMWD), APPROVING
AMENDMENT NO. 3 TO EXTEND THE PROFESSIONAL SERVICES
4 AGREEMENT WITH CAROLLO ENGINEERING FOR ENGINEERING
SERVICES ON THE PRESSURE CONTROL HYDROELECTRIC FACILITY
5 AT MAERKLE RESERVOIR, PROJECT NO. 5025
6
7
8 WHEREAS, on September 22, 2009, by resolution No. 1376, the Board approved the
9 award of a Professional Services Agreement with Carollo Engineers for engineering services on
the Pressure Control Hydroelectric Facility at Maerkle Reservoir project ; and
WHEREAS, the current agreement expires on September 22, 2014; and
WHEREAS, it is in the best interest of the Carisbad Municipal Water District to extend
the agreement with Carollo Engineering for an additional one (1) year term to allow
engineering support services through completion ofthe construction phase ofthe project; and
WHEREAS, the Board of Directors ofthe Carisbad Municipal Water District, California
Ij has determined it necessary, desirable, and in the public interest to approve Amendment No. 3
18 extending the agreement with Carollo Engineering for engineering services on the Pressure
19 Control Hydroelectric Facility at Maerkle Reservoir and;
WHEREAS, sufficient funds exist in the Water Fund.
NOW, THEREFORE, BE IT RESOLVED by the Carisbad Municipal Water District Board of
the City of Carlsbad, California, as follows:
1. That the above recitations are true and correct.
2. That Amendment No. 3 to the Agreement with Carollo Engineers will extend the
agreement for an additional 1-year term that expires on September 22, 2015.
3. That Amendment No. 3 to the Agreement with Carollo Engineers is approved and
the Mayor is hereby authorized and directed to execute said amendment.
10
11
12
13
14
15
20
21
22
23
24
25
26
27
28
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
PASSED, APPROVED AND ADOPTED at a Special Meeting ofthe Board of Directors ofthe
Carisbad Municipal Water District of the City of Carlsbad on the 26*^ day of August, 2014, by
the following vote to wit:
AYES:
NOES:
ABSENT:
Board Members Hall, Packard, Wood, Schumacher and Blackburn.
None.
None.
MATT HALL, President
ATTEST:
BARBARA ENGLESON, Secretary
LOCATION MAP
NOT TO SCALE
MAERKLE RESERVOIR
PROJECT NAME
PRESSURE CONTROL HYDROELECTRIC FACILITY
AT MAERKLE RESERVOIR
PROJECT
NUMBER
5025
EXHIBIT
DRAWN BY: SCOTT EVANS, CARLSBAD UVUVES DEPT 8/18/10 C: \UmTIES DEPARTUENT\DESGN DIVISION\PLUUMER\5025.DWG 5
PWENG719
AMENDMENT NO. 3 TO EXTEND AGREEMENT FOR
PROFESSIONAL ENGINEERING SERVICES FOR THE PRESSURE CONTROL
HYDROELECTRIC FACILITY AT MAERKLE RESERVOIR
CAROLLO ENGINEERS, INC.
This Amendment No. 3 is entered into and effective as of the 26th day of
August , 2014, extending and amending the agreement dated September
23, 2009, (the "Agreement") by and between the Carisbad Municipal Water District, a Public
Agency organized under the Municipal Water Act of 1911, and a Subsidiary District of the City of
Carisbad, ("CMWD"), and Carollo Engineers, Inc., a Delaware corporation, ("Contractor")
(collectively, the "Parties") for the Pressure Control Hydroelectric Facility at the Maerkle reservoir,
Project No. 5025.
RECITALS
A. On October 17, 2012, the Parties executed Amendment No. 1 to the Agreement to
extend the Agreement for a period of one (1) year; and
B. On October 26, 2013, the Parties executed Amendment No. 2 to the Agreement to
Extend the Agreement for a period of one (1) year and alter the scope of work to include
management and analysis during construction; and
C. The Parties desire to extend the Agreement for a period of one (1) year.
NOW, THEREFORE, in consideration of these recitals and the mutual covenants
contained herein, CMWD and Contractor agree as follows:
1. The Agreement as may have been amended from time to time, is hereby extended
for a period of one (1) year ending on September 21, 2015.
2. All other provisions of the Agreement, as may have been amended form time to
time, shall remain in full force and effect.
3. All requisite insurance policies to be maintained by the Contractor pursuant to the
Agreement, as may have been amended form time to time, shall include coverage of the is
Amendment.
///
///
///
///
///
///
General Counsel Approved Version 1/30/13
1
PWENG719
4. The individuals executing this Amendment and the instruments referenced in it on
behalf of Contractor each represent and warrant that they have the legal power, right and actual
authority to bind Contractorto the terms and conditions of this Amendment.
CONTRACTOR
CAROLLO ENGINEERS, INC.,
a Delaware corporation
CARLSBAD MUNICIPAL WATER
DISTRICT, a Public Agency organized
under the Municipal Water Act of 1911,
and a Subsidiary District of the City of
Carisbad
By:
President
ATTEST:
BARBARA ENGL
£.^0^—
N
"^(^VA^IAU (mikll U ^m/Mh secretary
(print name/title)
If required by CMWD, proper notarial acknowledgment of execution by contractor must be
attached. If a corporation. Agreement must be signed by one corporate officer from each of the
following two groups.
Group A
Chairman,
President, or
Vice-President
Group B
Secretary,
Assistant Secretary,
CFO or Assistant Treasurer
Otherwise, the corporation must attach a resolution certified by the secretary or assistant
secretary under corporate seal empowering the officer(s) signing to bind the corporation.
APPROVED AS TO FORM:
CELIA A. BREWER, General Counsel
Assistant General
General Counsel Approved Version 1/30/13