HomeMy WebLinkAbout1998-10-19; Parks & Recreation Commission; 1098-3; Skateboard Park UpdateAB# 1098-3
MTG. -.
DEPT. CSD
DIV. PK. PLAN.
STAFF: STEYAERT
DATE: 10-1 9-98
RECOMMENDED ACTION :
Accept and file staff update.
ITEM EXPLANATION :
The City Council recently approved the bid for development of the Skateboard Park. The Park
Development Coordinator will present a status update on its construction. A Ground Breaking
Ceremony has been scheduled for 3:30 p.m. on October 28, 1998 at the Public Safety and
Service Center. The location of the Skateboard Park is situated immediately east (and behind)
Fire Station #5.
EXHIBITS:
INFO TITLE :
SKATEBOARD PARK UPDATE
0
I 1. Award of Contract for Construction of Carlsbad Skate Park - City Council Agenda Bill.
c--
fi~# 14,842
WTG. 9108198
1. Sierra Pacific West
2 Wier Construction
SEPT. ENG
(with lighting) (without lighting)
$342,358 $254,432
$428,378 $358,763
c CITY OF CARLSBAD - AGENDA BILL
TITLE:
AWARD OF CONTRACT FOR
CONSTRUCTION OF THE CARLSBAD SKATE PARK
PROJECT NO. 3597
DEPT. HD
CITY MGRS
RECOMMENDED ACTION:
Adopt Resolution No. 98-303 accepting bids, appropriating an additional $1 85,066 from the
GCC and awarding the contract for Project No. 3597 for the construction of the Carlsbad Skate Park
to Sierra Pacific West.
ITEM EXPLANATION:
As part of the adoption of the 1997/98 Capital Improvement Program (CIP), the City Council
appropriated $330,000 for the design and construction of the skate park. The City entered into a
contract with David Evans and Associates to prepare a preliminary design report based on public
input from three workshops. Based on the input from the public on the skate park elements, a
preferred design alternative was approved by the Council earlier this year allowing the consultant to
prepare final design plans and the construction specification documents.
The Skate Park would be constructed and operated as follows:
15,000 square feet of skating surface on a parcel of approximately 40,000 square feet.
Lighted park allowing use until 10 p.m. consistent with other City parks.
Separation fencing between the park and Fire Station No. 5.
Informal turf seatinglviewing as well as dispersed bench locations.
An art element administered by the Arts Commission.
Xeriscape landscaping in addition to shade trees.
Drinking fountain.
Portable restroom.
Regulatory and informational signs.
On June 23, 1998, the Council approved the plans and specifications and authorized the City Clerk
to advertise for bids for the construction of the Carlsbad Skate Park on property located at the City's
Safety Center complex on the south side of Orion Way, just east of Fire Station No. 5.
The Purchasing Department received two (2) sealed bids on August 13, 1998. The bid
specifications requested costs for the base construction items and a separate price for the lighting
feature. A summary of the bid prices is shown below:
All bid documents submitted by Sierra Pacific West have been reviewed by staff and found to be in
order.
8.
L -- EXHIBIT 1
Page 2 of Agenda Bill No. ' 14,842
Budget
AVAILABLE BALANCE
Construction Estimate
Contingency (20%)
Project Administration & Inspection (1 0%)
Total Construction Costs
DEFICIT
Expenditures to date
CONSTRUCTION COSTS
ENVIRONMENTAL REVIEW AND PERMITS:
An Environmental Impact Assessment (EIA) for the site and project was carried out in accordance
with the California Environmental Quality Act (CEQA). On April 15, 1998, the Planning Commission
adopted Resolution No. 4270 approving a mitigated Negative Declaration to allow for the
construction and operation of the Carlsbad Skate Park.
$330,000
$260,000
-70,000
WITH LIGHTING WITHOUT LIGHTING
$342,358 $254,432
68,472 50,886
34,236 25,443
$445,066 $3 30,?6 1
<$A 85,066> <$70,761>
The Conditional Use Permit (CUP 98-05) was approved on April 15, 1998 pursuant to Planning
Commission Resolution No. 4271.
FISCAL IMPACT:
Expenditures for the preparation of the alternative design report, and completion of the plans and
specification document, including staff time, total $70,000 leaving $260,000 for construction and
project administration.
The cost estimate for the design, construction and administration of this project is as follows:
As can be seen on the above chart, the construction bid amount currently exceeds the established budget. Staff believes that the lack of interest in bidding the project and the hi h bid prices are due
Staff directed the consultant to review the bid package from Sierra Pacific West and prepare a report on the discrepancies between the Engineer's Estimate and the submittal bid prices. Based
to the unique nature and relatively small scale of the project as well as the unfavora %r-m--r e I c imate. __ . - _. --
c- L 4
on this
1.
2.
3.
evaluation, the following three (3) issues resulted in increasing the construction costs:
Construction Schedule: The construction specifications requested that this project be
completed in thirty (30) working days (approximately 5 weeks). Due to the size of the
project, both the City and consultant project managers felt that this project can be completed
in the timeframe prescribed. However, during the discussions with the contractor, this short construction window required the acceleration of various work elements and the price is reflected accordingly.
Earthwork: The bid package estimates $82,000 for simple earthwork (Le., clearing and
grubbing, over-excavation, imported fill material and finish grading) which is approximately
$60,000 over the Engineer's Estimate. Based on the size of the site as well as the scope of the project, $82,000 seems excessive. This price may be driven by the shortened timeframe for project completion.
Lighting System: The specifications, based on the Parks Department recommendation,
proposes the installation of Musco lighting. The Engineer's Estimate for the lights was
$47,000 with the contractor proposing approximately $88,000 for the same lighting system. Musco lights are the finest fixtures available and are the most expensive. Musco lights are
used at most of the City's parks.
LOCATION ~ MAP
I
I
\"/
SI A:
ClW or OCtWSlOE
TE
t3OJECT NAME I PROJECT I EXHIBIT I NUMBER 3597 CARLSBAD SKATE PARK
2W
I Page 3 of Agenda Bill No. 14,kLL
The Council has the following options to consider:
t
, 1. Award the contract as designed (including lighting).
2. Award the contract without lighting (lights could be installed at a later date or private sponsor
Direct staff to redesign the project to reduce scope and cost. Revising the construction
specifications to increase the construction timeline, re-address the grading method, and
allow for "equal" or less expensive lighting has the potential to reduce the construction cost
by approximately $50,000-$60,000. These issues may also increase the contractors wishing
to bid on the revised project. Staff would have to re-advertise for bids thus delaying the
construction.
funding could be sought). 5 6- ,-- ,-l _- J
3,
Staff recommends that the City Council appropriate an additional $S85,066 from the General Fund
balance and award a contract for the construction of the Carlsbad Skate Park to Sierra Pacific West.
EXHIBITS:
1. Location Map.
2. Resolution No. 98-303 accepting bids, appropriating an additional $1 85,066 from the
General Fund balance and awarding the contract for Project No. 3597 for the construction of
the Carlsbad Skate Park to Sierra Pacific West.
I
I' !1
2
3
4
5
6
7
8
9
10
11
12
13
14
15 1
16
17
18
19
20
21
22
23
24
25
26
27
28
1
RESOLUTION NO. 98-303
A'RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
CARLSBAD, CALIFORNIA, ACCEPTING BIDS, APPROPRIATING AN ADDITIONAL $185,066 FROM THE GENERAL FUND
BALANCE AND AWARDING THE CONTRACT FOR PROJECT NO.
3597 FOR THE CONSTRUCTION OF THE CARLSBAD SKATE
PARK TO SIERRA PACIFIC WEST.
WHEREAS, plans have been reviewed by the City Council of the City of Carlsbad for the
construction of the Carlsbad Skate Park - Project No. 3597; and
WHEREAS, bids have been received by the City of Carlsbad for the construction of said
project ; and
WHEREAS, the low bid received to construct said project was submitted by Sierra Pacific
West and is responsive; and
WHEREAS, the low bid received to construct said project by Sierra Pacific West was in
the amount of $342,358; and
WHEREAS, the total estimated cost for the construction of said project, including contract
administration and construction contingencies, is $445,066; and
WHEREAS, the Council has previously appropriated $330,000 in the 1997-98 CIP for
design, construction, administration and inspection of said project.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad,
California, as follows:
1.
2.
That the above recitations are true and correct.
That the low bid of $342,358 submitted by Sierra Pacific West for Project No. 3597
for the construction of the Carlsbad Skate Park is accepted.
3. That Sierra Pacific West is to provide executed contract documents, suitable bonds
and proof of insurance to the City Purchasing Officer within twenty (20) days of adoption of this
resolution or such additional days that the City Manager, at his sole discretion, may allow. The
Mayor is hereby authorized to execute a contract therefor under said contingency.
Ill
Ill
Ill
lli
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
, t
4. That the Council authorizes the appropriations of an additional $185,066 frorfi the’ ~
1
General Fund balance for the construction of the Carlsbad Skate Park - Project NO. 3597.
PASSED, APPROVED AND ADOPTED at a regular meeting of the Carlsbad City Council
held on the day of , 1998 by the following vote, to wit:
AYES:
NOES:
ABSENT:
ATTEST:
CLAUDE A. LEWIS, Mayor
ALETHA L. RAUTENKRANZ, City Clerk (SEAL)