Loading...
HomeMy WebLinkAbout2019-05-06; Traffic Safety Commission; ; INFORMATIONAL UPDATE ON STRIPING ON PALOMAR AIRPORT ROAD AT THE COSTCO DRIVEWAYItem # 3 Meeting Date: May 6, 2019 To: Traffic Safety Commission Staff Contact: John Kim, Senior Engineer john.kim@carlsbadca.gov or 760-602-2757 Subject: Informational update on striping on Palomar Airport Road at the Costco driveway Recommended Action Information only. Background and Discussion On November 5, 2018, staff presented to Traffic Safety Commission an informational item on the Right Turn Lanes adjacent to Bike Lanes as it pertained to the existing striping on eastbound Palomar Airport Road in the vicinity of Armada Drive/Costco Entrance. Staff will present a proposed plan to address some of the concerns that were discussed in November. Necessary Council Action None. Next Steps A work order will be issued to have our Streets Maintenance staff implement the proposed plan. Exhibits 1. Draft Work Order CITY OF CARLSBAD PUBLIC WORKS DEPARTMENT TO: MICHAEL O'BRIEN, PUBLIC WORKS SUPERINTENDENT FROM: MARSHALL PLANTZ, TRANSPORTATION DIRECTOR WORK ORDER LOCATION: Palomar Airport Road e/o Paseo Del Norte PROJECT: Modify Existing Bike Lane Striping to Detail 39A Striping JUSTIFICATION: Per Direction From City Traffic Engineer ARMSTRONG GARDEN CENTER NO. DATE ___ By---1E._ TR# ------RES/ORD# _N/~A~_ HANSEN# THE FLOWER FIELDS --------------------------<l=--!!!!I ·----------------- - - - ------~-- _ii __ -------------------104' I I ~ I I f ~~~~ ~ =P-I· 8'·1 µ 6" BLACK 6" WHITE DETAIL 39A -----------------NOT TO SCALE ---------~~-_ro_~~ oa ~rr~--:--~=~ = = = -~LO_~R_Am_POR_T ~-~~~------------= = = = _ro_A~_AM_~-~ ~~~-------~ ~ -------------------------------------i--------------------------------------------7--:-_ ~ ~G~:=;~============ • Iii 104'-------i ~=====~~============================ 925 CARL'S JR. DWY WORK TO BE DONE DWY CD USE BLACK PAINT TO CREATE 104 FEET OF DETAIL 39A STRIPING AS SHOWN ON THIS SHEET. WHEN COMPLETED, RETURN TO: (Traffic & Mobility Division) 951 COSTCO DATE COMPLETED ____ BY ___ _ 1. Lindy Pham Ext. 2768 Striping Revision at Palomar Airport Road and Costco Driveway Massoud Saberian, City Traffic Engineer John Kim, Senior Engineer Palomar Airport Road near Costco Entrances 2 Bike Lane Begins 3 4 5 6 7 8 9 Questions? 10