HomeMy WebLinkAbout2020-12-15; City Council; ; Appropriation of an Additional $195,000 for the Palomar Airport Road Widening ProjectMeeting Date: Dec. 15, 2020
To: Mayor and City Council
From: Scott Chadwick, City Manager
Staff Contact: Babaq Taj, Engineering Manager
babaq.taj@carlsbadca.gov, 760-637-0006
Subject: Appropriation of an Additional $195,000 for the Palomar Airport Road
Widening Project
Recommended Action
Adopt a resolution authorizing appropriation of an additional $195,000 from the Gas Tax Fund
for the Palomar Airport Road Widening Project, Capital Improvement Program, project nos.
6043 and 6044.
Executive Summary
The project requires an additional appropriation of $195,000 for construction support services,
including public outreach, engineering support, construction management, inspection,
materials testing and staff time to support the management and close-out through an extended
construction duration.
Under Carlsbad Municipal Code Section 3.28.040.D.3, the City Council’s authorization is
required to appropriate additional funds to Capital Improvement Program project budgets.
Discussion
Background
On July 23, 2019, the City Council awarded a contract to Just Construction, Inc. to construct the
project for an amount not to exceed $741,463.10 and authorizing approval of construction
change orders up to $135,000 (City Council Resolution 2019-128). The project consists of
improvements along eastbound Palomar Airport Road at the intersection with Paseo Del Norte.
The left-turn lane modification, identified as CIP Project No. 6043, will extend the existing left-
turn pocket on eastbound Palomar Airport Road on the approach to northbound Paseo Del
Norte an additional 175 feet to the west by removing a portion of the raised concrete median.
The right-turn lane improvement, identified as CIP Project No. 6044, will create a new,
dedicated right-turn lane on eastbound Palomar Airport Road on the approach to southbound
Paseo Del Norte. The project began Dec. 17, 2019, which, under the contract, set the initial
completion date as March 27, 2020, but the project has encountered delays.
On Nov. 19, 2019, the City Council appropriated additional funds in the amount of $125,000 for
construction support services. (Resolution 2019-237)
Dec. 15, 2020 Item #7 Page 1 of 6
On Oct. 20, 2020, the City Council appropriated additional funds in the amount of $136,000 for
construction support services to complete the project. (Resolution 2020-207)
Since Oct. 20, 2020, the project has incurred additional delays. Staff estimates the contractor to
complete the remainder of the construction in January 2021, with the administrative close-out
and final resolution of any remaining potential claims or disputes by April 2021.
Staff requests an additional appropriation of $195,000 for necessary construction support
services to complete the project over a longer-than-expected construction duration. These
services include construction management, inspection, materials testing, public outreach and
engineering services.
As reported to the City Council on Oct. 20, 2020, the contractor has claimed that it has incurred
potential damages totaling $650,000, but has not submitted its claims through the informal
dispute-resolution process identified in the contract. Resolution of outstanding disputes will be
addressed under the terms of the contract. This has the potential to result in a request that the
council appropriate additional funds for this project in the future.
Fiscal Analysis
Funding from two sources has been appropriated for the project in the past: $300,084 from the
Gas Tax Fund and $1,175,916 from Prop A – Local Funds (TransNet, the countywide sales tax for
transportation projects). An additional funding appropriation in an amount of $195,000 from
the Gas Tax Fund is required to complete the project. Sufficient funding is available. The
additional requested gas tax funds will be distributed to Capital Improvement Program projects
nos. 6043 and 6044 in the amounts of $57,353 and $137,647, respectively. The available funds
and distribution of funds for each project are shown in the following table:
Palomar Airport Road Widening Project, Capital Improvement Program
project nos. 6043 and 6044
Total appropriation to date (Gas Tax Fund and TransNet) $1,476,000
Total expenditures and encumbrances to date $1,476,000
Current project account balance – CIP project nos. 6043 and 6044 $0
Additional construction support services $195,000
Total estimated additional project costs $195,000
Remaining balance after CIP project nos. 6043 and 6044 $(195,000)
Additional appropriation needed $195,000
Dec. 15, 2020 Item #7 Page 2 of 6
Distribution of additional appropriated funds
Additional appropriation – Palomar Airport Road and Paseo Del Norte left-turn
lane, CIP Project No. 6043 $57,353
Additional appropriation – Palomar Airport Road and Paseo Del Norte right-
turn lane, CIP Project No. 6044 $137,647
Next Steps
Upon City Council approval and authorization of the additional appropriation, staff will
appropriate the additional funds and set them aside for this project.
Staff will continue to monitor the progress of construction and notify the City Council of known
impacts that could delay the completion of construction beyond January 2021 or additional
increases to the project budget. Staff will return to the City Council for authorization if
additional appropriation is needed.
Environmental Evaluation (CEQA)
The project is exempt from the California Environmental Quality Act under CEQA per CEQA
Guidelines Section 15301(c), which covers the minor alteration of existing facilities including
streets, sidewalks, gutters, and similar facilities involving negligible or no expansion. A notice of
exemption was filed in the office of the San Diego County Clerk on Feb. 20, 2018, for a 30-day
period of public review.
Public Notification
Public notice of this item was posted in keeping with the Ralph M. Brown Act and it was
available for public viewing and review at least 72 hours before the scheduled meeting date.
Exhibits
1.City Council Resolution
2.Location map
Dec. 15, 2020 Item #7 Page 3 of 6
RESOLUTION NO. 2020-239
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CARLSBAD,
CALIFORNIA, AUTHORIZING APPROPRIATION OF ADDITIONAL FUNDS IN THE
AMOUNT OF $195,000 FROM THE GAS TAX FUND FOR THE PALOMAR
AIRPORT ROAD WIDENING PROJECT, CAPITAL IMPROVEMENT PROGRAM
(CIP) PROJECT NOS. 6043 AND 6044 (PROJECT)
WHEREAS, on July 23, 2019, the City Council of the City of Carlsbad, California adopted
Resolution No. 2019-128, awarding a contract to Just Construction, Inc. (Contractor) in an amount not
to exceed $741,463.10 for the Project, and authorized approval of construction change orders up to
$135,000; and
WHEREAS, on Nov. 19, 2019, the City Council adopted Resolution No. 2019-237, authorizing an
additional appropriation in the amount of $125,000 for construction support services, which includes
public outreach, engineering support, construction management, inspection, materials testing and
staff time; and
WHEREAS, on Oct. 20, 2020, the City Council adopted Resolution No. 2020-207, authorizing an
additional appropriation in the amount of $136,000 for construction support services to complete the
Project; and
WHEREAS, staff has determined an additional $195,000 of funding is required to provide the
necessary services for construction management, inspection, materials testing, public outreach, and
engineering support through an extended construction duration; and
WHEREAS, sufficient Gas Tax funds in the amount of $195,000 are available to complete the
Project; and
WHEREAS, the city planner has determined that the Project is exempt from the California
Environmental Quality Act (CEQA) per State CEQA Guidelines Section 15301(c) - minor alteration of
existing facilities including streets, sidewalks, gutters, and similar facilities involving negligible or no
expansion, and none of the exceptions described in CEQA Section 15300.2 are applicable to this project.
A Notice of Exemption was filed in the office of the San Diego County Clerk on Feb. 20, 2018 for a 30-
day public review.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad, California, as
follows:
1. That the above recitations are true and correct.
Dec. 15, 2020 Item #7 Page 4 of 6
2. That the deputy city manager, administrative services is authorized and directed to
appropriate funds from the Gas Tax Fund in the amount of $57,353 and $137,647 to the Palomar
Airport Road and Paseo Del Norte Left-Turn Lane Project (CIP Project No. 6043) and the Palomar Airport
Road and Paseo Del Norte Right-Turn Lane Project (CIP Project No. 6044), respectively, for a total
appropriation of $195,000 in support of construction of the Project.
PASSED, APPROVED AND ADOPTED at a Regular Meeting of the City Council of the City of
Carlsbad on the 15th day of December, 2020, by the following vote, to wit:
AYES: Hall, Blackburn, Acosta, Bhat-Patel, Schumacher.
NAYS: None.
ABSENT: None.
MATT HALL, Mayor
fb\--
BARBARA ENGLESON, City Clerk
(SEAL)
Dec. 15, 2020 Item #7 Page 5 of 6
Exhibit 2
Dec. 15, 2020 Item #7 Page 6 of 6
Babaq Taj, Engineering Manager
Dec. 15, 2020
Appropriation of an Additional
$195,000 for the Palomar Airport
Road Widening Project
Recommendation
•Adopt a resolution for the appropriation of
additional funds in an amount of $195,000
from the Gas Tax Fund for the Palomar Airport
Road Widening Project, Capital Improvement
Program, Project Nos. 6043 and 6044
Background
•Construction delays have increased the city’s
cost to complete the project. The project
requires additional funding for necessary
construction support services, including: public
outreach; engineering support; construction
management, inspection and materials testing;
and staff time
•The project consists of improvements along Palomar Airport Road at the
intersection with Paseo Del Norte
•The improvements will extend the existing left-turn pocket on eastbound
Palomar Airport Road on the approach to northbound Paseo Del Norte and
create a new, dedicated right-turn lane on eastbound Palomar Airport
Road on the approach to southbound Paseo Del Norte
Palomar Airport Rd.
Next Steps
•The project is approximately 80% complete; anticipated
to be complete in January 2021
•Staff will continue to manage the project and oversee
the safety, quality and progress of this high-provide
project in the city’s right of way
•Staff will notify City Council if the completion of the
project is anticipated to be delayed beyond January
2021
Recommendation
•Adopt a resolution for the appropriation of
additional funds in the amount of $195,000
from the Gas Tax Fund for the Palomar Airport
Road Widening Project, Capital Improvement
Program Project Nos. 6043 and 6044
Thank you