HomeMy WebLinkAbout2020-12-03; Safety Center Renovation Project Update - District 2; Gomez, PazTo· the members of the:
COUNCIL
Da ;JDCA ✓ CC ✓
CM ✓ocM{3) ✓
Council Memorandum
Dec.3,2020
To: Honorable Mayor Hall and Members of the City Council
From: Paz Gomez, Deputy City Manager, Publi Works
Via: Geoff Patnoe, Assistant City Manager
Re: Safety Center Renovation Project Update (District 2)
{city of
Carlsbad
Memo ID #2020257
This memorandum provides an update on the status of the Safety Center Renovation Project,
Capital Improvement Program {CIP) Project No. 4715 {Project).
Background
The Safety Center, which is located at 2560 Orion Way, is more than 30 years old and has not
been significantly renovated. The Safety Center houses the headquarters of the
Police and Fire Departments and was recently renamed as Police and Fire Headquarters.
The Project scope includes upgrades to interior finishes, expansion of select functional areas
due to staffing increases, infrastructure upgrades and Climate Action Plan {CAP)-compliant
measures. These Project upgrades currently do not include the Emergency Operations Center
{EOC)/conference room wing of the building (i.e., EOC, conferente rooms, kitchenette,
restrooms, etc.) The Project does include roof replacement, which includes roof work over the
EOC wing. There is a separate CIP Project for the EOC wing of the building, which will be
discussed later.
The Project was initially added to the CIP during fiscal year 2014-15. Attachment A details the
scope changes and funding history to date. The total budget appropriation to date is
approximately $8 million.
In coordination and collaboration with the Police and Fire Departments, the Project scope and
design have developed over several years into one that comprehensively addresses building
infrastructure needs, energy efficiency upgrades and essential safety and security
improvements in a more efficient office layout for the departments.
Proposition H
Carlsbad Municipal Code Chapter 1.24 codifies Proposition H, an initiative passed by voters in
1982 to require voter authorization for real property purchase or improvement projects that
cost in excess of $1 million of General Fund money. In 2005, City Council updated the
Proposition H Guidelines to clarify that "Improvements to Real Property" do not include
replacement, repair, maintenance, routine refurbishment or upgrades of existing facilities.
Public Works Branch
Fleet and Facilities Department
405 Oak Avenue I Carlsbad, CA 92008 I 760-434-2980 t
Council Memo -Safety Center Renovation Project Update (District 2)
Dec.3,2020
Page 2
On July 31, 2018, City Council adopted Resolution No. 2018-151, which found the Project
"exempt from the expenditure limit in Carlsbad Municipal Code Section 1.24.030 because it is a
repair and upgrade of an existing facility."
In March 2020, staff evaluated the need to upgrade the building to be compliant with the
Essential Services Buildings Seismic Safety Act of 1986 (ESBSSA). On May 5, 2020, City Council
approved amending the architect's agreement to incorporate structural engineering design
services into the design work for the Project (Resolution No. 2020-076), which did not include
the EOC wing of the building at the time. Subsequently, $6.6 million was programmed in the CIP
for fiscal year 2021-22 for construction of the Project's structural upgrades.
Recently during the design process, additional items of infrastructure work were identified
related to California Building Code upgrades that are required as a condition of permitting the
Project. Therefore, the $6.6 million estimate for structural upgrade costs has increased to
approximately $9.4 million, which includes $2.8 million of building code upgrade costs.
EOC Reconfiguration CIP Project
A separate CIP project addresses necessary upgrades to the city's EOC, which is the
EOC Reconfiguration Project, CIP Project No. 4719. It was added to the CIP in
fiscal year 2015-16 with a total budget appropriation of approximately $1.9 million. The scope
includes new furnishings, computers, software, network equipment, communications, and
lighting and acoustic improvements that will upgrade the EOC/conference room wing to current
standards for emergency response. It does not include structural upgrades to comply with
ESBSSA.
This EOC Reconfiguration Project will create scalable digital media switching and control
infrastructure. The EOC Reconfiguration Project will enable emergency response decision
makers to quickly review and evaluate information from any number of different sources in a
collaborative setting. These analog and digital audio and video sources from both on-site and
remote locations must be displayed to, and/or monitored by, the entire EOC area, operational
groups, individuals and/or combinations thereof. As the flow of information changes during an
emergency response with the unfolding and evolving scenario, the system must be flexible. This
project therefore allows for the operator to quickly access and display information from a wide
variety of inputs to a variety of output locations and display devices.
To accomplish this degree of flexibility, the audio and video content must be routed through a
matrix switching environment that supports flexible routing of source information to any pre-
identified destination. The main information technology (IT) components of the
EOC Reconfiguration Project will include procurement and installation of a main video wall
involving video displays and projection, an audio video matrix switching frame, video encoding
and decoding, audio amplification and distribution, and supporting equipment racks. Audio and
Council Memo -Safety Center Renovation Project Update (District 2)
Dec.3,2020
Page 3
video output will be shared with the city's designated alternate EOC located in the Faraday
Building conference room and the City Hall conference room.
This EOC Reconfiguration Project does not currently include seismic upgrades that will be
required to comply with ESBSSA. Staff recommends adding the seismic upgrades since it has
been determined that the EOC will stay in place for the foreseeable future and not be relocated
to another facility, as was previously considered.
Facility Name Change
On Nov. 17, 2020, City Council adopted Resolution No. 2020-219 to change the Safety Center
name to Police and Fire Headquarters.
Discussion
After further review, and for synergistic purposes, staff plans to incorporate the
EOC Reconfiguration Project, CIP Project No. 4719, into the Safety Center Renovation Project,
CIP Project No. 4715, and expand the combined project to include seismic upgrades of the EOC
wing. Finally, staff will rename the project as the Police and Fire Headquarters Renovation
Project, CIP Project No. 4715, to reflect the recent facility name change.
Ongoing assessment of the Police and Fire Headquarters' seismic and building code upgrades,
not including the EOC, showed a need for approximately $9.4 million in additional funding. Staff
will also request an additional appropriation to include design and construction of the seismic
upgrades for the EOC wing, which is currently estimated to cost approximately $2 million, for a
total request of an additional $11.4 million. Sufficient Infrastructure Replacement Funds are
available.
Following the Project bid results anticipated in fall 2021, staff plans to request City Council
award of a construction contract with the successful bidder for this combined work and
additional appropriation of approximately $11.4 million. With this additional $11.4 million
request to add to the current appropriation of $8 million, plus the addition of the
EOC Reconfiguration Project appropriation of $1.9 million, the total Project cost will be
approximately $21.3 million. The table below summarizes the estimated costs:
Police and Fire Headquarters Renovation Project Estimated Costs
(revised CIP Project No. 4715)
Safety Center Renovation Project (previous CIP Project No. 4715) $8 million
Additional seismic and building code upgrades (previous CIP Project No. 4715) $9.4 million
EOC Reconfiguration Project (CIP Project No. 4719) $1.9 million
Additional seismic upgrade of EOC wing $2 million
Total Estimated Costs $21.3 million
Council Memo -Safety Center Renovation Project Update (District 2)
Dec.3,2020
Page 4
Next Steps
In summer 2021, staff plans to request City Council approval offixtures, furnishings and
equipment for the Project as well as approval of the plans and specifications and authorization
to advertise the expanded Project for construction bids.
In fall 2021, staff plans to request City Council award of a construction contract with the
successful bidder for this work and additional appropriation of approximately $11.4 million
($9.4 million for the original seismic and building code upgrades and $2 million for the
additional EOC wing seismic work). The Project construction is expected to take up to
24 months to complete.
Attachment: A. Scope and Funding History, Safety Center Renovation, Capital Improvement
Program {CIP) Project No. 4715
cc: Scott Chadwick, City Manager
Celia Brewer, City Attorney
Gary Barberio, Deputy City Manager, Community Services
Laura Rocha, Deputy City Manager, Administrative Services
Neil Gallucci, Police Chief
Michael Calderwood, Fire Chief
Robby Contreras, Assistant City Attorney
Kevin Branca, Finance Director
Maria Callander, Information Technology Director
Jeff Murphy, Community Development Director
Ryan Green, Assistant Finance Director
John Maashoff, Public Works Manager
Steven Stewart, Municipal Projects Manager
Council Memo -Safety Center Renovation Project Update (District 2)
Dec.3,2020
Page 5
Attachment A
Scope and Funding History
Safety Center Renovation, Capital Improvement Program (CIP) Project No. 4715
Fiscal Year Scope Changes Budget Appropriation
FY 2014-15 Refurbish the Safety Center conference rooms, $200,000
which also serve as the city's Emergency
Operations Center
FY 2015-16 Safety and security upgrades in the main lobby $3,213,500
area; construct a structure to infill an opening in
the second floor
FY 2016-17 Additional improvements to accommodate $90,000
operational needs
FY 2017-18 Incorporate additional recommendations from a $1,352,450
2012 study by Faithful + Gould identifying
infrastructure replacement needs
FY 2018-19 Incorporate building code and Climate Action Plan $3,200,600
compliance measures
TOTAL APPROPRIATION TO DATE $8,056,550