Loading...
HomeMy WebLinkAbout2020-10-20; City Council; ; Appropriation of Additional Funds in the Amount of $136,000 and Increase of the Construction Contingency by $60,000 for the Palomar Airport Road Widening Project Meeting Date: Oct. 20, 2020 To: Mayor and City Council From: Scott Chadwick, City Manager Staff Contact: Valerie Airey, Municipal Projects Manager valerie.airey@carlsbadca.gov, 760-602-2764 Subject Appropriation of Additional Funds in the Amount of $136,000 and Increase of the Construction Contingency by $60,000 for the Palomar Airport Road Widening Project Recommended Action Adopt a resolution authorizing the appropriation of an additional $136,000 from the Gas Tax Fund and authorizing an increase of the construction contingency by $60,000 for the Palomar Airport Road Widening Project, Capital Improvement Program project nos. 6043 and 6044. Executive Summary The project, which was awarded on July 23, 2019, has experienced construction delays that require additional funding for construction costs, construction management, inspection, materials testing, engineering and associated staff support. As noted in Carlsbad Municipal Code Section 3.28.040.D.3, City Council authorization is required to appropriate additional funds to Capital Improvement Program project budgets and authorize an increase in the city manager’s authority to approve construction change orders. The recommended actions exceed the city manager’s procurement authority and require City Council authorization. Discussion On July 23, 2019, the City Council adopted Resolution No. 2019-128 and awarded a $741,463.10 contract to Just Construction, Inc., for construction of the project, which consists of improvements along eastbound Palomar Airport Road at Paseo Del Norte. The left-turn lane modification, identified as Capital Improvement Program Project No. 6043, will extend the existing left-turn pocket on eastbound Palomar Airport Road on the approach to northbound Paseo Del Norte an additional 175 feet to the west by removing a portion of the raised concrete median. The right-turn lane improvement, identified as CIP Project No. 6044, will create a new, dedicated right-turn lane on eastbound Palomar Airport Road on the approach to southbound Paseo Del Norte. To date, the contractor has completed the median improvements, and is currently working on the traffic-signal modifications, right-turn lane and right-of-way improvements. The contractor was initially scheduled to mobilize and begin work on March 3, 2020. But before then, the city directed the contractor to postpone its mobilization to mitigate anticipated construction impacts to nearby businesses. The contractor then submitted a change order Oct. 20, 2020 Item #3 Page 1 of 6 request in the amount of $132,121 for reimbursement of direct costs and indirect unabsorbed home office overhead costs as a result of the delay. Staff reviewed the claim and established it merits reimbursement of eligible direct and indirect costs in the amount of $42,381.27 because it relates to the delay in start of the work. The contractor has stated that it does not agree with the city’s determination of merit and valuation of costs and has therefore refused to sign a contract change order for resolution of this impact. To ensure that the contractor is reimbursed timely for verified work, the city has executed a unilateral change order to the contract in the amount of $42,381.27 to reimburse the contractor for verified costs. The city has issued payment for this verified work with the project’s October 2020 progress payment. Separately, work on the project has been impacted by the presence of unforeseen buried utilities, as well as contractor delays. These unforeseen conditions have necessitated changes to the original scope of work, as well as additional management and oversight of the project as a result of a longer construction duration with a total estimated cost of $17,618.73. With the unilateral change order of $42,381.27 for the delay in start of the work and unforeseen condition costs of $17,618.73, for a total cost increase of approximately $60,000, staff requests the City Council’s authorization to increase the project’s construction contingency by $60,000, from $135,000 to $195,000. Staff also seeks City Council’s authorization to appropriate an additional $80,000 for construction management, inspection, materials testing, engineering and associated staff support required for management and oversight of the project over a longer duration. Altogether, staff requests a total increase in appropriation of $136,000, which is the remaining balance required since $4,941 is currently still available. (To specify, $60,000 + $80,000 = $140,000 - $4,941 = $135,059, rounded up to $136,000) Staff estimates a total increase in the project budget in the amount of $136,000 based upon known issues and the contractor’s current estimated completion date of November 2020. However, the contractor has indicated there may be additional potential impacts and costs that staff have not confirmed as meritorious at this point. The contract provides an informal dispute resolution process whereby the contractor may submit an appeal for additional compensation for claimed impacts and costs. To date, the contractor has not validated many of the potential claims and has not submitted change order requests for other potential claims. The city is aware of four potential claims the contractor has submitted through the informal dispute resolution process. These claims total approximately $650,000 in additional claimed compensation. Resolution of these disputes could result in additional requests for appropriation in the future. Fiscal Analysis There is $4,941 currently available for the project. Two funding sources have appropriated funds for the project: $164,084 from the Gas Tax Fund and $1,175,916 from city’s share of TransNet, the sales tax that funds transportation projects in the county. Based on the increase in construction contingency and the additional cost required to service the project over a longer duration, an additional funding appropriation in an amount of $136,000 from gas tax funds is required. The additional requested gas tax funds will be distributed to CIP project nos. 6043 and Oct. 20, 2020 Item #3 Page 2 of 6 6044 in the amounts of $40,000 and $96,000, respectively. The available funds and distribution of funds for each project are shown in the following table: Palomar Airport Road Widening Project, Capital Improvement Program project nos. 6043 and 6044 Total appropriation to date (Gas Tax Fund and TransNet) $1,340,000 Total expenditures and encumbrances to date $1,335,059 Current project account balance – Capital Improvement Program project nos. 6043 and 6044 $4,941 Construction contingency (estimated) $60,000 Construction management services (estimated) $80,000 Total estimated project costs $140,000 Remaining balance after Capital Improvement Program project nos. 6043 and 6044 $(135,059) Additional appropriation needed $136,000 Distribution of additional appropriated funds Additional appropriation – Palomar Airport Road and Paseo Del Norte left-turn lane, Capital Improvement Program Project No. 6043 $40,000 Additional Appropriation – Palomar Airport Road and Paseo Del Norte Right- Turn Lane, Capital Improvement Program Project No. 6044 $96,000 Next Steps Upon City Council approval and authorization of additional appropriation, staff will execute a new task order with Kleinfelder Construction Services, Inc., the city’s construction management consultant, for additional construction management, inspection and testing services. Staff will continue to pay the contractor for non-disputed work in a timely manner, while ensuring the remainder of the project is completed in conformance with the contract. Staff will continue to monitor progress and notify the City Council if known impacts could result in additional delays beyond November 2020 or additional increases to the project budget. Staff will return to the City Council for authorization if additional appropriation is needed. Environmental Evaluation (CEQA) The project is exempt from the California Environmental Quality Act under CEQA Guidelines Section 15301(c) - minor alteration of existing facilities including streets, sidewalks, gutters and similar facilities involving negligible or no expansion. A notice of exemption was filed in the office of the San Diego county clerk on Feb. 20, 2018, for a 30-day public review. Public Notification Public notice of this item was posted in keeping with the Ralph M. Brown Act and it was available for public viewing and review at least 72 hours before the scheduled meeting date. Exhibits 1. Resolution 2. Location map Oct. 20, 2020 Item #3 Page 3 of 6 RESOLUTION NO. 2020-207 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CARLSBAD, CALIFORNIA, AUTHORIZING APPROPRIATION OF ADDITIONAL FUNDS IN AN AMOUNT OF $136,000 FROM THE GAS TAX FUND FOR THE PALOMAR AIRPORT ROAD WIDENING PROJECT, CAPITAL IMPROVEMENT PROGRAM (CIP) PROJECT NOS. 6043 AND 6044 (PROJECT) AND INCREASING THE CONSTRUCTION CONTINGENCY FOR THE PROJECT BY $60,000 WHEREAS, on July 23, 2019, the City Council of the City of Carlsbad, California adopted Resolution No. 2019-128, awarding a $741,463.10 contract to Just Construction, Inc. (Contractor), for construction of the Palomar Airport Road Widening Improvements at Paseo Del Norte, CIP Project Nos. 6043 and 6044 (Project); with an additional construction contingency of $135,000; and WHEREAS, in March 2020, the City of Carlsbad postponed start of construction; and WHEREAS, the Contractor submitted a change order request in the amount of $132,121, of which staff has determined merit for reimbursement of costs in the amount of $42,381.27 regarding delay in start of the work; and WHEREAS, the Project has been further impacted by unforeseen conditions resulting in changes to the scope of work and project schedule delays in the amount of $17,618.73; and WHEREAS, staff requests that the Project's construction contingency be increased by $60,000 to cover the cost of delaying the start of work and changes in the scope of work; and WHEREAS, staff has determined an additional $80,000 in funding is required to provide the necessary services for construction management, inspection, material testing, engineering and staff support through an extended construction duration; and WHEREAS, sufficient Gas Tax funds in the amount of $136,000 are available to complete the Project; and WHEREAS, the city planner has determined that the Project is exempt from the California Environmental Quality Act (CEQA) per State CEQA Guidelines Section 15301(c) - minor alteration of existing facilities including streets, sidewalks, gutters, and similar facilities involving negligible or no expansion, and none of the exceptions described in CEQA Section 15300.2 are applicable to this project. A Notice of Exemption was filed in the office of the San Diego County Clerk on Feb. 20, 2018 for a 30- day public review. NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad, California, as follows: Oct. 20, 2020 Item #3 Page 4 of 6 IFoCk 1. That the above recitations are true and correct. 2. That the deputy city manager, administrative services is authorized and directed to appropriate funds from the Gas Tax Fund in the amount of $40,000 and $96,000 to the Palomar Airport Road and Paseo Del Norte Left-Turn Lane Project (CIP Project No. 6043) and the Palomar Airport Road and Paseo Del Norte Right-Turn Lane Project (CIP Project No. 6044), respectively, for a total appropriation of $136,000 in support of construction of the Project. 3. That the city manager or designee is hereby authorized to approve construction change orders for an additional amount of $60,000 for a total not-to-exceed amount of $195,000. 4. That the city planner has determined that the Project is exempt from the California Environmental Quality Act (CEQA) per State CEQA Guidelines Section 15301(c) - minor alteration of existing facilities including streets, sidewalks, gutters, and similar facilities involving negligible or no expansion, and none of the exceptions described in CEQA Section 15300.2 are applicable to this project. A Notice of Exemption was filed in the office of the San Diego County Clerk on Feb. 20, 2018 for a 30- day public review. PASSED, APPROVED AND ADOPTED at a Regular Meeting of the City Council of the City of Carlsbad on the 20th day of October, 2020, by the following vote, to wit: AYES: Hall, Blackburn, Bhat-Patel, Schumacher. NAYS: None. ABSENT: None. MATT HALL, Mayor AMat IV (OP( BARBARA ENGLESON, City Clerk (SEAL) CAP4 0 ...... -fr Oct. 20, 2020 Item #3 Page 5 of 6 Exhibit 2 Oct. 20, 2020 Item #3 Page 6 of 6 Babaq Taj, Engineering Manager Oct. 20, 2020 Appropriation of Additional Funds for the Palomar Airport Widening Project Recommendation •Adopt a resolution for the appropriation of additional funds in an amount of $136,000 from the Gas Tax Fund and authorizing an increase of the construction contingency by $60,000 for the Palomar Airport Road Widening Project, Capital Improvement Program Project Nos. 6043 and 6044 Background •Project consists of improvements along Palomar Airport Road at the intersection with Paseo Del Norte •Extends the existing left-turn pocket on eastbound Palomar Airport Road on the approach to northbound Paseo Del Norte, and creates a new dedicated right-turn lane on eastbound Palomar Airport Road on the approach to southbound Paseo Del Norte •Has experienced construction delays and requires additional funding for construction costs, construction management, inspection, materials testing, engineering and associated staff support. Background •Contractor was directed to postpone its March 3, 2020 mobilization to mitigate anticipated construction impacts to local businesses in the vicinity of the Project •Contractor submitted a change order request in the amount of $132,121 for reimbursement of direct and indirect costs as a result of the delay; staff has reviewed the claim and established merit for direct and indirect costs in the amount of $42,381.27 •Project has also been impacted by unforeseen buried utilities costs in the amount of $17,618.73 Next Steps •Upon City Council approval and authorization of additional appropriation, staff will execute a new task order for additional construction management, inspection and testing services. •Staff will continue to pay the Contractor for non-disputed work in a timely manner while ensuring the remainder of the Project is completed in conformance with the contract Recommendation •Adopt a resolution for the appropriation of additional funds in an amount of $136,000 from the Gas Tax Fund and authorizing an increase of the construction contingency by $60,000 for the Palomar Airport Road Widening Project, Capital Improvement Program Project Nos. 6043 and 6044. Thank you