HomeMy WebLinkAbout2003-12-02; Municipal Water District; 561; Construction of Recycled Water Transmission Main4B# 561
JITG. 12/02/03
IEPT. ENG
RECOMMENDED ACTION:
TITLE: ACCEPTING BIDS AND AWARDING A CONTRACT FOR
THE CONSTRUCTION OF THE ALGA ROAD, POINSETTIA LANE,
AND MELROSE DRIVE RECYCLED WATER TRANSMISSION MAIN FOR THE ENCINA BASIN WATER RECLAMATION PROGRAM,
AND APPROPRIATING FUNDS CITY MGR. %- PHASE II PROJECT, PROJECT NO. 3887-B,
Adopt Resolution No. 1197 accepting bids and awarding a contract for the construction of the Alga Road, Poinsettia Lane, and Melrose Drive Recycled Water Transmission Main, for the Encina Basin Water Reclamation Program, Phase II Project, Project No. 3887-8, and appropriating funds.
9. ARB, Inc.
10. Vadnais Corporation
11. Don Kelly Construction
12. 4-Point Pipeline
13. CA Southwest Construction
ITEM EXPLANATION:
Lake Forest, CA $3,596,218
San Diego, CA $3,779,783
Sahuarita, AZ $3,871,675
El Cajon, CA $3,935,255
San Diego, CA $4,411,600
The Alga Road, Poinsettia Lane, and Melrose Drive Recycled Water Transmission Mains, Project No. 3887-8, construction contract is part of the Encina Basin Water Reclamation Program, Phase II Project (Phase 11). The pipelines will enable the recycled water processed at the Carlsbad Water Recycling Facility (CWRF), which is currently under construction, and the existing Meadowlark Reclamation Facility, to reach the District’s Phase II recycled water customers. Included in this construction contract are two separate pipelines. One pipeline will be installed from Rancho Santa Fe Road to El Camino Real within Melrose Drive and Poinsettia Lane and consists of approximately 9,200 feet of 30-inch diameter transmission main. The second separate transmission pipeline will be constructed within Alga Road from El Camino Real east to Alicante Road and consist of approximately 3,200 feet of pipeline ranging in size from 8-inches to 12-inches in diameter.
On August 19, 2003, the Board of Directors approved the plans and specifications for the Alga Road, Poinsettia Lane, and Melrose Drive Recycled Water Transmission Main, Project No. 3887-8, and directed the Secretary to advertise for construction bids. On October 14, 2003, the following thirteen (1 3) sealed bids were received:
The Engineer’s Estimate for construction of Project No. 3887-8 was $3,575,000. Erreca’s, Inc.,
submitted the lowest bid in the amount of $2,870,648. The documents submitted by Erreca’s, Inc.,
for the project have been reviewed and analyzed by the engineering staff and found to be in order.
The Engineering staff, therefore, recommends the award of Project No. 3887-8 construction
contract to Erreca’s, Inc.
561 Page 2 of Agenda Bill No.
I Construction Cost (Erreca's, Inc.)
ENVIRONMENTAL REVIEW:
2,870,648
The pipeline project is a part of the Phase II Project, Encina Basin Water Reclamation Program
(Phase 11). A Mitigated Negative Declaration (MND) was prepared for the Phase II project.
TheCarlsbad City Council approved the MND on January 25, 2000 under Case No. EIA 99-09,
Resolution No. 2000-37. The United States Department of the Interior completed their review of the
Phase II project for compliance with the National Environmental Policy Act (NEPA) and formally
approved the NEPA on March 1,2002.
Construction Contingency (5%)
Inspection, Testing, and Construction ManaQement (5%)
FISCAL IMPACT:
143,500
143.500
The estimated cost of the subject pipeline project is summarized in Table 1 below:
3887A
38878
I I Design $420,000 1
Reach 2 Ave. Encinas 424,000
Alga, Poinsettia, Melrose 3.578.000
3887D I Cannon/College 557,000
Table 2 summarizes the total project cost of all the pipeline contracts comprising the Encina Basin
Water Reclamation Program, Phase II Pipeline Project 3887. All costs in Table 2 are estimates.
The costs shown in bold are already awarded for construction.
3887E
3887F
Poinsettia Lane Reach C 600,000
Aviara Park 0
3887G I Rancho Santa Fe Road, Phase I
I 38876 I Industrial Parks I 5.625.000 I
126,000
3887G
3887H
Rancho Santa Fe Road, Phase II
El Camino Real. Cassia to PAR
869,000
1.81 1 .OOO
Page 3 of Agenda Bill No. 561
This project is part of the overall Encina Basin Water Reclamation Program, Phase II Project.
Previous appropriations for this overall project total $38.2 million. The project is being funded from a
Bureau of Reclamation Grant, a State Water Resources Control Board Grant and low-interest loan,
and an EPA Grant. Council previously approved advances in the amount of $14.5 million from the
Water Replacement Fund to provide cash up front for the project. This advance is expected to be
repaid once the loan and grant funds are received.
Additional appropriations are being requested with this agenda bill and for another agenda bill before
the Council on this date, both for Recycled Water Phase 2 projects. The combined additional
appropriations equal $2,755,900. Funding will be provided by increasing the State Water Resource
Control Board Loan by this amount. Since this is a significant increase in the total project cost, staff
updated the revenue and expense projections (cash flows) to determine the impact this increase
would have on the future operations of the program. In addition to this $2,755,900 increase,
the anticipated federal grant funding was reduced by approximately $4 million due the uncertainty of
funding beyond the current fiscal year. Therefore, the additional loan amount could be as high as
$7 million.
On February 12, 2002, Council was provided information about the projected revenues and
expenses for the Recycled Water Program. At that time it was estimated that an annual operating
deficit of approximately $800,000 was likely once the project was complete. With the additional
costs and changes in anticipated funding, the deficit is now expected to be about $1 million per year,
thus requiring additional funding from potable water revenues and/or an increase in the water rate.
This deficit could be reduced if additional federal grant money is obtained, or if final project costs are
lower than what is being appropriated.
EXHIBITS:
1. Location Map.
2. Resolution No. accepting bids and awarding a contract for the construction of the Alga Road, Poinsettia Lane, and Melrose Drive Recycled Water Transmission Main, for the Encina Basin Water Reclamation Program, Phase II Project, Project No. 3887-8, and appropriating funds.
1197
DEPARTMENT CONTACT: David Ahles, (760) 602-2748, da hleaci. carlsbad. ca. us
3
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
1197 RESOLUTION NO.
A RESOLUTION OF THE BOARD OF DIRECTORS OF CARLSBAD
MUNICIPAL WATER DISTRICT (CMWD) ACCEPTING BIDS AND
AWARDING A CONTRACT FOR THE CONSTRUCTION OFTHE
ALGA ROAD, POINSElTIA LANE, AND MELROSE DRIVE
RECYCLED WATER TRANSMISSION MAIN, FOR THE ENCINA
BASIN WATER RECLAMATION PROGRAM, PHASE II PROJECT,
PROJECT NO. 3887-8, AND APPROPRIATING FUNDS.
WHEREAS, on August 19, 2003, the Board of Directors of the Carlsbad Municipal Water
3istrict approved plans and specifications for construction of the Alga Road, Poinsettia Lane, and
Melrose Drive Recycled Water Transmission Main, Project No. 3887-8; and
WHEREAS, thirteen (13) sealed bids were received on October 14, 2003 at 4:OO p.m. for
:he project; and
WHEREAS, the lowest responsive, responsible bid for the project was submitted by
Zrreca's, Inc., in the amount of $2,870,648; and
WHEREAS, the Board of Directors of the Carlsbad Municipal Water District has
jetermined it necessary, desirable, and in the public interest to construct the Alga Road,
'oinsettia Lane, and Melrose Drive Recycled Water Transmission Main, for the Encina Basin
Nater Reclamation Program, Phase II Project, Project No. 3887-8; and
WHEREAS, a Mitigated Negative Declaration has been adopted by the City of Carlsbad
3ity Council by Resolution 2000-37, dated January 25, 2000, as required by the California
Environmental Quality Act; and
WHEREAS, funding in the amount of $1 7,661,000 was appropriated for various pipeline
irojects including the Alga Road, Poinsettia Lane, and Melrose Drive Lanes; and
WHEREAS, the estimated cost to date for the various pipelines is $1 9,810,000.
NOW THEREFORE, BE IT RESOLVED by the Board of Directors of the Carlsbad
lllunicipal Water District of the City of Carlsbad, California, as follows:
1. That the above recitations are true and correct.
I!
/I
1
2
3
4
5
6
7
a
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
\.
2. That the low bid submitted by Erreca’s, Inc., in the amount of $2,870,648 is hereby
accepted and the President of the Board of Directors is hereby authorized to execute a contract
3n behalf of the CMWD for the construction of Project No. 3887-B.
3. That the Executive Manager is hereby authorized to approve construction change
xders up to $143,500 for Project No. 3887-B.
4. That the award of this contract is contingent upon Erreca’s, Inc., executing the
.equired contract and submitting the required bonds and insurance policies, as described in the
:ontract, within twenty (20) days of adoption of this resolution with the understanding that
:he Executive Manager may grant reasonable extensions of time.
5. That the Finance Director is authorized to appropriate an additional $2,149,000
from the Recycled Water Fund for the various pipeline projects.
PASSED, APPROVED AND ADOPTED at a special meeting of the Carlsbad Municipal
, 2003 by the following vote, to wit: Water District held on the 2nd day of December
AYES: Board Members Lewis, Finnila, Kulchin, Hall and Packard
NOES: None
ATTEST
/,-
I
Page 2 of 2 of Resolution No. 1197 (CMWD)
(SEAL)
LOCATION MAP
Nor rd SCALE
PROPOSED
PACIFIC OCEAN
PROJECT NAME PROJECT EXHIBIT
7 ALGA ROAD, POINSETTIA LANE, AND MELROSE DRIVE RECYCLED WATER TRANSMISSION MAIN FOR THE ENCINA BASIN WATER RECLAIMATION PROGRAM, PHASE II PROJECT
NUMBER
38878
HN BY: SCOTT EVANS, CARLSBAD ENGINEERING DEPT. 7/22/03 C: \CAPITAl\AHlES\3@87BDW