FOR
CARLSBAD OAKS NORTH
PHASE 3
CT 97-13-03
Job No. 961005
Prepared: FEBRUARY 2008
Revised: MAY 2008
Prepared by:
O'DAY CONSULTANTS, INC.
2710 Loker Avenue West
Suite 100
Carlsbad, Califomia 92010
Tel: (760)931-7700
Fax: (760)931-8680
Tim Carroll RCE 55381
Exp. 12/31/08
Date
TABLE OF CONTENTS
SECTION 1
SECTION 2
INTRODUCTION
PROCEDURE
Vicinity Map
Intensity-Duration Design Chart
Isopluvial Maps
100-Year, 6-Hour
100-Year, 24-Hour
San Diego County Soils Interpretation Study
Runoff Coefficients
Nomograph for Determination of Tc for Natural Watersheds
Urban Areas Overland Time of Flow Curves
SECTIONS BASIN 1
Hydrology
100 year Analysis
Hydraulics
Hydraulic Cjrade Line
SECTION 4 INLET SIZING
SECTION 5 TEMPORARY DESILTATION BASINS
APPENDIX
Rancho Carlsbad Channel & Basin Project
POCKET
SECTION 1
INTRODUCTION
The purpose ofthis study is to analyze the proposed conditions for Phase 3 of Carlsbad Oaks
North Industrial Park. The 414 acre site is located east of El Camino Real and north of Palomar
Airport Road in the City of Carlsbad. The completed project will include 23 mass graded lots
and the extensions of Faraday Avenue to the City of Vista, and El Fuerte Street to an intersection
with Faraday Avenue.
Drainage facilities are designed to meet the requirements stated in the "Standards for Design and
Constmction of Public Works Improvements in the City of Carlsbad." All calculations shown
here are for ultimate development. Calculations for "Temporary Drainage" are done only where
this temporary condition creates greater flow than the ultimate condition.
Increases in runoff, including runoff from upstream of the project are accounted for by the
detention basin formed by Faraday Avenue. This detention basin design is covered by "Rancho
Carlsbad Channel & Basin Project" by Rick Engineering Company (see Appendix). This basin
is built on a fork of Agua Hedionda Creek, which runs east to west along the southerly third of
the site.
The storm drain for this phase of the project ties into Phase 2 of Carlsbad Oaks North, that
portion ofthe project is covered by "Hydrology and Hydraulic Study for Carlsbad Oaks North
Phase 2," on file at the City of Carlsbad.
PROCEDURE
The hydrology study followed the procedure in the 1985 San Diego County Drainage Manual for
a 100-year storm. For this location, ?6 = 2.8 and P24 = 4.9. Times of concentiration were based
on the following:
For Natural Areas:
Tc 60 11.9 L^ +10 minutes
H
For Urban Areas:
Tc = 1.8 (1.1 -QNID , with a minimum of 5 minutes
is
Additional time in pipes or channels was based on the average velocity in those facilities.
Intensity was determined by:
I = 7.44 P6 T6 •^''^
I;\961005\HYDROLOGY\PHASE 3\Rpt_Phase3.doc
The rational method was used to determine flows:
Q = CIA, where
Q = flow in cubic feet per second
C = nmoff coefficient, based on land use and soil type.
For this project, the soil type is 'B' for the northem half, 'C for the wetiands
and 'D' for the southerly slopes (see Section 2).
I = intensity
A - area, in acres
Phase 1 of this project, including the down-stream pipes for Phases 2 and 3, was designed prior
to the adoption of the 2003 San Diego County Hydrology Manual. The 2003 manual states:
"This manual should not be used when there is already an established flood flow." Therefore, the
hydrologic analyses are being performed according to the 1985 San Diego County Hydrology
Manual.
A Hydraulic Study was then done to confinn pipe sizes and eliminate pressure flow whenever
possible. To be conservative, the diversion of "low-flows" into pollution basins at diverter boxes
was ignored. The advanced Engineering software (AES) Pipeflow Hydraulics computer program
was used to calculate the hydraulics of the storm drain pipe system for the ultimate conditions of
the proposed site. The program estimates the gradually varying water surface profile by
balancing the energy equation at user-specific locations.
The AES pipeflow program analyzes both the supercritical and subcritical flow. From this
program the hydraulic grade line, the energy grade line and losses were determined for the
ultimate conditions.
The head loss computations were based on LACRD, LACFCD, and OCEMA current design
manuals.
The junction analysis was based on the L.A. Thomas equation.
SUMMARY
The Hydrologic Analysis performed during the Phase 1 portion of the project showed that Basin
1 generated 385.5 cfs of runoff fi-om 112.13 acres. The analysis of the same basin for Phase 2
showed an increase in runoff of 20.4 cfs to 416.4 cfs for Basin 1. The analysis of the same basin
for Phase 3 showed an additional increase of 1.1 cfs for Basin 1. The overall increase in mnoff
into Agua Hedionda Creek is acceptable due to the previously mentioned detention basin formed
by the Faraday Avenue and El Fuerte Street as designed by Rick Engineering Company for the
"Rancho Carlsbad Channel & Basin Project" (see Appendix).
I:\961005\HYDROLOGY\PHASE 3\Rpt_Phase3.doc
SECTION 2
CITY OF ^ OCEANSIDE
HIGHWAY!
PACIFIC
OCEAN
BUSINESS PARK DR.
CITY or ENCINITAS
VICINITY MAP
NO SCALE
Directions for Appllcationr:
U From precipitation maps determine 6 hr.
24 hr. amolints for the selected frequen
These maps are printed.In the County Hy
Manual (10, 50 and 100 yr. maps include
Design and Procedure Manual).
2) Adjust 6 hr.'precipitation (if necessar
that it is within the range of 45X to 6
the 24 hr. precipitation. (Mot applica
to Desert)
3) Plot 6 hr. precipitation bn the right s
of the chart.
4) Draw a line through 'the point parallel
plotted lines. *
5) This line is the Intensity-duration cur
the location being analyzed.
Application Form:
0) Selected Frequency 1 yr.
1) P< Jn., P24-
2) Adjusted *Pg- .
3) tc"
4) I • in/hr.
'24 in.
In.
*Not Applicable to Desert Region
This chart replaces, the Intensity- {
Duration-Frequency curves used since *
1965. r
COUNTY OF SAN OIEGO
OEPARTHENT OF SANITATION 6-
FLOOO CONTaOL
IO •o cc
33
CZ
A] rn
?o 33-
30'
15'
'•5'
U.S. Dt PAR TMtK I" OF COMMERCE
Al. OCKANIC ANO AY:
SPECIAL STUUltS UliAMCII. Or i-'iCli Of II
30'
100-YEAR. 24-IIOljR PRECIPITATION
-2flvlS0PLUVIALS oV 100 -YEAR 24-HOUn
pnEciPiTATioli IN WHS OF AN IMCII
I
CUUTTTY OF SAN DIEGO
DEPARTMENT OF SANITATION &
FLOOD CONTROL
ro o
21
o
c
:^ m
SI
100-YEAR 6-HOUR PRECIPITATIOM
-20> ISOPLUVIALS lOO-YEAJl 6-HOUn
PRECIFilWl IH SLii:;
SPECIAL STUDIES DRANCH, OFFICE OF II
3Q» _
116
U.S. DEPARTMEN
NATIONAL OCEANIC AND ATS C.SHIIEKIC A»"|'"""*J!°!!
(i
TABLE 2
RUNOFF COEFFICIENTS (RATIONAL METHOD)
DEVELOPED AREAS (URBAN)
Land Use
Residential:
Single Family
Huiti-Units
Mobile homes
Rural (lots greater than 1/2 acre)
Commerci al (2)
80% Impervious
Industrial (2)
90% Impervious
Coefficient. C -
Soil Type(U
A B C 0
M .50 .55.
M .50 .60 .70
M .50 .55 .65
.30 .35 M .'•5
.70 .75 .80 .85
.80 .85 .90 .95
NOTES:
(^Obtain soil type from Appendices IX-CI thru IHL-Zk.
(2)where actual^conditions deviate significantly from the tabulated impervious-
ness values of 80% or 90%, the values given for coefficient C. may be revised
by multiplying 80% or 90% by the ratio of actual imperviousness to the
tabulated imperviousness. However, fn no case shall the final coefficient
be less than 0.50. For example: Consider commercial property on D soil.
Actual imperviousness • 50%
Tabulated imperviousness - 80%
. Revised C - 50 ^ 0.85 • 0.53
80
FIGURE 144
III.199 APPENDIX IX-B
H
—sroao
-4 aaa
-2ooo
—zaaa
7c
I
.385
^/77e of co/JCe/t/raJ/'arr
e/ZSec^/Ve shoe //na (See //ppcm/ixY ai) ^
/?>
/iff/as
v^/aaa
^ SOO
- aao
TOO
60O \
JO
'SOO
-400
.360
-20O
'/ao
\
S —
4-
\ 2-
\
\ -
\ -
-SO
-40
— 30
- ZO
as-
i AOD TEN MINUTES TO \
\ COMPUTED TIME OF CON- \
I CENTRATION-
— /O
iFIGURE i4.13
rse/
4 —
1^4^0
--SOOO'
\
2000
—/aoo
— /£ao
— /<4O0
— /2oa
— /ooo
— 900
'800
— roo
— SOO
-SOO
— 400
— 300
\
/i^/»u/es
/ao
/£a
./oo
90
ao
ro
-so
so
— 40
— 30
-ZO
• /a
• /s
/*
/2
-/a
• 9
a
7
• 6
— 4
— 3
SAN DIEGO COUNTY
DEPARTMENT OF SPECIAL DISTRICT SERVICES
OESIGN MANUAL
APPROVED •• ^t^^^, ^Tr-
NOMOGRAPH FOR OETERMINATION
OF TIME OF CONCENTRATION (Tc)
FOR NATURAL WATERSHEDS
SOO
: I e/rg//i a/" /r/owif • SCO /A
S/o/aa ' AO y«
CaeMc/a/7/ o/ /?u/7o//. C • SO
_ /_fcv_'
SAN OIEGO CCUNTY
CEPARTME.MT OF SPECIAL OISTRICT SE.RVICES
DESIGN .MANUAL
U33AN AREAS OVE.^LANO TIME
OF FLOW CURV'S
PART 2
CONSTRUCTION WTERIALS
SECTION 200 - ROCK MATERIALS
200-1.1 General (p. 66)
Add: "Alternate Rock Materials - Tvoe "S" «
scribed In Section 400 n,ay be used. less specHI-
cally prohibited In Speclal Provisions"! ^
200-1.6 Stone for Riprap (p. 69)
'Idual cla$5es of rocks
conform to the follow;
PERCENTAGE. URGER T^N*
JrotectTon lUtlV'^^i ^'^^^^^ °' ^"^"^^ slope protection shall conform to the following:
CUSSES
Rock
Sizes 2 Ton 1 Ton
1/2
Ton 1 1/4
Ton
No. 2
Backing
No. 3
Backing
4 Ton
2 Ton
I Ton
1/2 Ton
1/4 Ton
200 Ib
75 Ib
25 lb
5 Ib
1 Ib
fTfc..,
0-5
50-100
95-100
0-5
50-100
95-100
0-5
50-100
95-100
0-5
50-100
95-100 0-5
25-75
90-100
0-5
25-75
90-100
size iTIted n+K ! K ^^'^ smallest
icST?an«':Tth1L" determined on' a weigh"? llVl
t^e fo^aT ^th Pf'"'=«"+«9« shown In the
Of any clasi ofr^''^" Individual pieces
Dieces larnJ +h ^ """"^^ °^ Individual
ulTe%i:iZf'cUsl':' ^"^"^^^ "^•^''^ 'n the.
•200-1.6.1 Selection of Riprap and Filter
Blanket HoterT51
Vel. Rock iRIprap
IFt/Sec Class Thick-
M) I (2) ness "T"
No. 3|
Back-
6-7 Ing .6
No. 2
Back-I
7-8 I Ing | 1.0
Fac-
8-9.5 Ing 1.4
9.5-11 Light 2.0
1/4
n-13| Ton 2.7
1/2
13-151 Ton 3.4
15-1711 Ton 4.3
.17-20 2 Ton 5.4
filter Blanket (3)
H)per Layer(s)
Opt. 1 Opt. 2|
Sec. Sec.
200 400 lOpt. 3 <4) I (4) I (5)
3/16" C2 O.G.
1/4" B3 O.G.
3/8" D.G.
1/2"
3/4",
1 1/2"
P.B.
3/4"
1" —
3/4",
1 1/2"
P.B.
1/2"
ILower I ILayerI
(6)
3/4",
1 1/2"
P.B. I Sandi
Sand I
Type B Sand
Type B Sand
(1) Average velocity In pipe or bottoin velocity In
energy dissipator, whichever Is greaterT
iot*^!'n*^Kr'''"P '""^ "'"ket class Is not available, use next larger class.
SECTION 3
Basin 1
Hydrology
C605P1.OUT
San Diego County Rational Hydrology Program
CIVILCADD/CIVILDESIGN Engineering software, (c) 1993 version 3.2
Rational method hydrology program based on
San Diego county Flood Control Division 1985 hydrology manual
Rational Hydrology Study Date: 01/31/08
CARLSBAD OAKS NORTH
PROPOSED - BASIN 1
G:\ACCTS\961005\C605Pl.OUT
PHASE 3
********* Hydrology Study control information **********
O'Day consultants, San Deigo, California - S/N 10125
Rational hydrology study storm event year is 100.0
Map data precipitation entered:
6 nour, precipitation(inches) = 2.800
24 hour precipitation(inches) = 4.900
Adiusted 6 hour precipitation (inches) = 2.800
P6/P24 =57.1%
san Diego hydrology manual 'C values used
Runoff coefficients by rational method
process from Point/Station 105.000 to Point/Station 105.500
**** INITIAL AREA EVALUATION ****
Decimal fraction soil group A = 0.000
Decimal fraction soil group B = 1.000
Decimal fraction soil group C = 0.000
Decimal fraction soil group D = 0.000
[INDUSTRIAL area type ]
initial subarea flow distance = 100.00(Ft.)
Highest elevation = 490.00(Ft.)
Lowest elevation = 488.00(Ft.)
Elevation difference = 2.00(Ft.)
Time of concentration calculated by the urban
areas overland flow method (App X-C) = 3.57 min.
TC = [1.8*(l.l-C)*distanceA.5)/(% slopeA(l/3)]
TC = [1.8*(l.l-0.8500)*(100.00A.5)/( 2.00A(l/3)]= 3.57
Setting time of concentration to 5 minutes
Rainfall intensity (i) = 7.377 for a 100.0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0.850
Subarea runoff = 0.627(CFS)
Total initial stream area = 0.100(Ac.)
Process from Point/Station 105.500 to Point/Station 106.000
**** IMPROVED CHANNEL TRAVEL TIME ****
upstream point elevation =
Downstream point elevation =
Channel length thru subarea
Channel base width
Slope or 'Z' of left channel bank = 20.000
Page 1
488.00(Ft.)
480.00(Ft.)
400.00(Ft.)
0.000(Ft.)
C605P1.OUT
Slope or 'Z' of right channel bank = 20.000
Estimated mean flow rate at midpoint of channel =
Manning's 'N' = 0.015
Maximum depth of channel =
Flow(q) thru subarea = 6.
Depth of flow = 0.297(Ft.),
Channel flow top width = 11,862(Ft.)
Flow Velocity = 3.92(Ft/s)
Travel time = 1.70 min.
Time of concentration = 6.70 min.
critical depth = 0.375(Ft.)
Adding area flow to channel
Decimal fraction soil group A = 0.000
1.000(Ft.)
,898(CFS)
Average velocity =
6.898(CFS)
3.922(Ft/s)
Decimal fraction soil
Decimal fraction soil
Decimal fraction soil
[INDUSTRIAL area type
Rainfall intensity =
group B = 1.000
group
group
= 0.000
= 0.000
] 6.108(in/Hr) for a 100.0 year storm
Runoff coefficient used for sub-area, Rational method,Q=KCIA, c = 0.850
Subarea runoff = 10.384(CFS) for 2.000(Ac.)
Total runoff = ll.Oll(CFS) Total area = 2.10(Ac.)
Process from Point/station
**** SUBAREA FLOW ADDITION ****
106.000 to Point/Station 106.000
Decimal fraction soil
Decimal fraction soil
Decimal fraction soil
Decimal fraction soil
[INDUSTRIAL area type
Time of concentration
Rainfall intensity =
group A
group B
group C
group D
0.000
1.000
0.000
0.000
6.70 min.
,108(ln/Hr) for a
Runoff coefficient used for sub-area. Rational
Subarea runoff = 9.346(CFS) for 1.800(Ac.)
Total runoff = 20.357(CFS) Total area =
100.0 year storm
method,Q=KCIA, C = 0.850
3.90(Ac.)
Process from Point/Station 106.000 to Point/Station 107.000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
upstream point/station elevation = 470.00(Ft.)
Downstream point/station elevation = 442.20(Ft.)
Pipe length = 80.00(Ft.) Manning's N = 0.013
No. of pipes = 1 Required pipe flow = 20.357(CFS)
Given pipe size = 18.00(ln.)
Calculated individual pipe flow = 20.357(CFS)
Normal flow depth in pipe = 7.10(in.)
Flow top width inside pipe = 17.59(ln.)
Critical depth could not be calculated.
Pipe flow velocity = 31.40(Ft/s)
Travel time through pipe = 0.04 min.
Time of concentration (TC) = 6,74 min.
Process from Point/Station 106,000 to Point/Station 107,000
**** CONFLUENCE OF MINOR STREAMS ****
Along Main Stream number: 1 in normal stream number 1
Stream flow area = 3.900(Ac.)
Page 2
C605P1.OUT
Runoff from this stream = 20.357(CFS)
Time of concentration = 6,74 min.
Rainfall intensity = 6.083(ln/Hr)
Process from Point/Station 108.000 to Point/Station 109,000
**** INITIAL AREA EVALUATION ****
Decimal fraction soil group A = O.OOO
Decimal fraction soil group B = 1.000
Decimal fraction soil group C = 0,000
Decimal fraction soil group D = 0.000
[INDUSTRIAL area type ]
Initial subarea flow distance = 25.00(Ft,)
Highest elevation = 487,00(Ft,)
Lowest elevation = 486.50(Ft,)
Elevation difference = 0.50(Ft.)
Time of concentration calculated by the urban
areas overland flow method (App x-c) = 1.79 min.
TC = [1.8*(l.l-C)*distanceA,5)/(% slopeA(i/3)]
TC = [l,8*(l.l-0,8500)*( 25.00A.5)/( 2,00A(l/3)]= 1.79
Settinq time of concentration to 5 minutes
Rainfall intensity (I) = 7.377 for a 100.0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0.850
Subarea runoff = 0.063(CFS)
Total initial stream area = 0.010(Ac)
Process from Point/Station 109,000 to Point/Station
**** STREET FLOW TRAVEL TIME + SUBAREA FLOW ADDITION ****
107.000
Top of Street segment elevation = 486.500(Ft.)
End of street segment elevation = 454.500(Ft.)
Length of street segment = 700.000(Ft.)
Height of curb above gutter flowline = 6.0(in.)
Width of half street (curb to crown) = 26.000(Ft.)
Distance from crown to crossfall grade break = 24.500(Ft.)
Slope from gutter to grade break (v/hz) = 0.020
slope from grade break to crown (v/hz) = 0.020
Street flow is on [1] side(s) of the street
Distance from curb to property line = 10.000(Ft.)
Slope from curb to property line (v/hz) = 0.020
Gutter width = 1.500(Ft.)
Gutter hike from flowline = 1.500(ln.)
Manning's N in gutter = 0.0150
Manning's N from gutter to grade break = 0.0150
Manning's N from grade break to crown = 0,0150
Estimated mean flow rate at midpoint of street =
Depth of flow = 0.081(Ft.), Averaqe velocity =
Streetflow hydraulics at midpoint of street travel.
Halfstreet flow width = 1.500(Ft.)
Flow velocity = 2.36(Ft/s)
Travel time = 4.94 min. TC = 9.94 min.
Adding area flow to street
user specified 'C' value of 0.730 given for subarea
4.735(ln/Hr) for a 100.0 year storm
0.092(CFS)
2.360(Ft/s)
Rainfall intensity =
Runoff coefficient used for sub-area, Rational method,Q=KCIA, C = 0.730 Subarea runoff =
Total runoff =
3.284(CFS) for 0,950(Ac.)
3.346(CFS) Total area = 0.96(Ac.)
Street flow at end of street = 3.346(CFS)
Half street flow at end of street = 3.346(CFS)
Page 3
C605P1.OUT
Depth of flow = 0.264(Ft.), Average velocity = 4.257(Ft/s)
Flow width (from curb towards crown)= 8.455(Ft.)
Process from Point/Station 109.000 to Point/Station
**** CONFLUENCE OF MINOR STREAMS ****
107.000
Along Main Stream number: 1 in normal stream number 2
Stream flow area = 0.960(Ac,)
Runoff from this stream = 3.346(CFS)
Time of concentration = 9.94 min.
Rainfall intensity = 4.735(in/Hr)
Summary of stream data:
Stream
NO.
Flow rate
(CFS)
TC
(min)
Rainfall Intensity
(in/Hr)
m
20.357 6.74
9.94 2 3.346
Qmax(l) =
1.000 * 1.000 *
1.000 * 0.678 *
Qmax(2) =
0.778 * 1.000 * 1.000 * 1,000 *
6,083
4.735
20.357) +
3.346) +
20.357) +
3.346) +
22.625
19.190
Total of 2 streams to confluence:
Flow rates before confluence point:
20,357 3,346
Maximum flow rates at confluence using above data:
22.625 19.190
Area of streams before confluence:
3.900 0.960
Results of confluence:
Total flow rate = 22.625(CFS)
Time of concentration = 6.742 min.
Effective stream area after confluence = 4.860(Ac.)
process from Point/Station 107.000 to Point/Station
**** PIPEFLOW TRAVEL TIME (User specified size) ****
110.000
Upstream point/station elevation = 441.50(Ft.)
Downstream point/station elevation = 441.30(Ft.)
Pipe length = 5.00(Ft.) Manning's N = 0.013
NO. of pipes = 1 Required pipe flow = 22.625(CFS)
Given pipe size = 24.00(in.)
calculated individual pipe flow = 22.625(CFS)
Normal flow depth in pipe = 12.00(ln.)
Flow top width inside pipe = 24.00(ln.)
Critical Depth = 20.34(ln.)
Pipe flow velocity = 14.40(Ft/s)
Travel time through pipe = 0.01 min.
Time of concentration (TC) = 6.75 min.
Process from Point/Station 107.000 to Point/Station
**** CONFLUENCE OF MAIN STREAMS ****
110.000
Page 4
C605P1.OUT
The following data inside Main Stream is listed:
In Main Stream number: 1
Stream flow area = 4.860(Ac,)
Runoff from this stream = 22,625(CFS)
Time of concentration = 6,75 min.
Rainfall intensity = 6,080(in/Hr)
Program is now starting with Main Stream No, 2
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 108,000 to Point/Station 108,100
**** INITIAL AREA EVALUATION ****
Decimal fraction soil group A = 0,000
Decimal fraction soil group B = 1,000
Decimal fraction soil group C = 0.000
Decimal fraction soil group D = 0.000
[INDUSTRIAL area type ]
Initial subarea flow distance = 26.00(Ft.)
Highest elevation = 487.00(Ft.)
Lowest elevation = 486,50(Ft,)
Elevation difference = 0,50(Ft,)
Time of concentration calculated by the urban
areas overland flow method (App x-c) = 1,85 min,
TC = [l,8*(l,l-C)*distanceA,5)/(% slopeA(l/3)]
TC = [l,8*(l.l-0,8500)*( 26,00A,5)/( l,92A(l/3)]= 1,85
Settinq time of concentration to 5 minutes
RainfaTl intensity (l) = 7,377 for a 100,0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0,850
Subarea runoff = 0,063(CFS)
Total initial stream area = 0.010(Ac.)
++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 108.100 to Point/Station 110.500
**** STREET FLOW TRAVEL TIME + SUBAREA FLOW ADDITION ****
Top of street segment elevation = 486.500(Ft,)
End of street segment elevation = 454.500(Ft.)
Length of street segment = 700,000(Ft.)
Height of curb above gutter flowline = 6,0(ln.)
width of half street (curb to crown) = 26,000(Ft,)
Distance from crown to crossfall grade break = 24.500(Ft,)
slope from gutter to grade break (v/hz) = 0.020
Slope from grade break to crown (v/hz) = 0.020
Street flow is on [1] side(s) of the street
Distance from curb to property line = 10.000(Ft.)
Slope from curb to property line (v/hz) = 0.020
Gutter width = 1.500(Ft.)
Gutter hike from flowline = 1.500(in.)
Manning's N in gutter = 0.0150
Manning's N from gutter to grade break = 0.0150
Manning's N from grade break to crown = 0.0150
Estimated mean flow rate at midpoint of street = 0.090(CFS)
Depth of flow = 0.080(Ft.), Average velocity = 2.344(Ft/s)
Streetflow hydraulics at midpoint of street travel:
Halfstreet flow width = 1.500(Ft.)
Flow velocity = 2.34(Ft/s)
Travel time = 4.98 min. TC = 9.98 min.
Adding area flow to street
User specified 'C' value of 0.800 given for subarea
Rainfall intensity = 4.724(ln/Hr) for a 100.0 year storm
Runoff coefficient used for sub-area. Rational method,Q=KCIA, C = 0.800
Page 5
c605Pl,OUT
Subarea runoff = 3.288(CFS) for 0.870(Ac.)
Total runoff = 3.351(CFS) Total area = 0,88(Ac)
Street flow at end of street = 3,351(CFS)
Half street flow at end of street = 3.351(CFS)
Depth of flow = 0.264(Ft,), Average velocity = 4.258(Ft/s)
Flow width (from curb towards crown)= 8.460(Ft.)
++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 108.100 to Point/Station 110,500
**** CONFLUENCE OF MINOR STREAMS ****
Along Main Stream number: 2 in normal stream number 1
Stream flow area = 0.880(Ac)
Runoff from this stream = 3.351(CFS)
Time of concentration = 9,98 min.
Rainfall intensity = 4.724(in/Hr)
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 110,510 to Point/Station 110,520
**** INITIAL AREA EVALUATION ****
Decimal fraction soil group A = 0,000
Decimal fraction soil group B = 1,000
Decimal fraction soil group C = 0,000
Decimal fraction soil group D = 0,000
[INDUSTRIAL area type ]
Initial subarea flow distance = 100,00(Ft.)
Highest elevation = 484.00(Ft.)
Lowest elevation = 482.00(Ft.)
Elevation difference = 2.00(Ft.)
Time of concentration calculated by the urban
areas overland flow method (App x-c) = 3.57 min.
TC = [1.8*(l.l-C)*distanceA,5)/(% slopeA(l/3)]
TC = [l,8*(l,l-0,8500)*(100.00A,5)/( 2.00A(l/3)]= 3,57
Setting time of concentration to 5 minutes
RainfaTl intensity (l) = 7.377 for a 100.0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0.850
Subarea runoff = 0.314(CFS)
Total initial stream area = 0.050(Ac.)
Process from Point/Station 110.520 to Point/Station 110.530
**** IMPROVED CHANNEL TRAVEL TIME ****
Upstream point elevation = 482.00(Ft.)
Downstream point elevation = 474.00(Ft.)
Channel length thru subarea = 450.00(Ft.)
Channel base width = 0.000(Ft.)
Slope or 'Z' of left channel bank = 20.000
Slope or 'Z' of right channel bank = 20.000
Estimated mean flow rate at midpoint of channel = 12.573(CFS)
Manning's 'N' =0.015
Maximum depth of channel = 1.000(Ft.)
Flow(q) thru subarea = 12.573(CFS)
Depth of flow = 0.380(Ft.), Average velocity = 4.360(Ft/s)
Channel flow top width = 15.189(Ft.)
Flow velocity = 4.36(Ft/s)
Travel time = 1.72 min.
Time of concentration = 6.72 min.
Critical depth = 0.477(Ft.)
Page 6
C605P1.OUT
Adding area flow to channel
Decimal fraction soil group A = 0.000 Decimal fraction soil group B = 1.000
Decimal fraction soil group C = 0.000
Decimal fraction soil group D = 0,000
[INDUSTRIAL area type
Rainfall intensity = ] 6,096(ln/Hr) for a 100.0 year storm
Runoff coefficient used for sub-area. Rational method,Q=KCIA, C = 0.850
Subarea runoff = 20.261(CFS) for 3.910(Ac.)
Total runoff = 20.575(CFS) Total area = 3,96(Ac,)
++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/station 110,530 to Point/Station 110,500
**** PIPEFLOW TRAVEL TIME (user specified size) ****
upstream point/station elevation = 465,00(Ft.)
Downstream point/station elevation = 444,00(Ft.)
Pipe length = 60,00(Ft,) Manning's N = 0,013
NO. of pipes = 1 Required pipe flow = 20,575(CFS)
Given pipe size = 24,00(in.)
Calculated individual pipe flow = 20.575(CFS)
Normal flow depth in pipe = 6.36(in.)
Flow top width inside pipe = 21.19(in.)
critical Depth = 19,52(in.)
Pipe flow velocity = 30,86(Ft/s)
Travel time through pipe = 0,03 min.
Time of concentration (TC) = 6,75 min.
m ++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 110,530 to Point/Station 110.500
**** CONFLUENCE OF MINOR STREAMS ****
Along Main Stream number: 2 in normal stream number 2
Stream flow area = 3,960(Ac,)
Runoff from this stream = 20,575(CFS)
Time of concentration = 6.75 min.
Rainfall intensity = 6.077(in/Hr)
Summary of stream data:
Stream
NO,
Flow rate
(CFS) TC
(min)
Rainfall intensity
(in/Hr)
3.351
20.575
Qmax(l) =
Qmax(2) =
1.000 *
0.777 *
1.000 *
1.000 *
9.98
6.75
1.
1.
000 *
000 *
0.677 *
1.000 *
4.724
6.077
3.351) +
20.575) +
3.351) +
20.575) +
19.345
22.842
Total of 2 streams to confluence:
Flow rates before confluence point:
3.351 20.575
Maximum flow rates at confluence using above data:
19.345 22.842
Area of streams before confluence:
0.880 3.960
Results of confluence:
Total flow rate = 22.842(CFS)
Page 7
C605P1.OUT
Time of concentration = 6.753 min.
Effective stream area after confluence = 4.840(Ac)
Process from Point/Station 110,500 to Point/Station 110.000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
upstream point/station elevation = 443.67(Ft.)
Downstream point/station elevation = 441.33(Ft.)
Pipe length = 44.00(Ft.) Manning's N = 0.013
No, of pipes = 1 Required pipe flow = 22,842(CFS)
Given pipe size = 24.00(ln,)
Calculated individual pipe flow = 22,842(CFS)
Normal flow depth in pipe = ll,ll(ln,)
Flow top width inside pipe = 23,93(In,)
critical Depth = 20,42(ln,)
Pipe flow velocity = 16.05(Ft/s)
Travel time through pipe = 0,05 min.
Time of concentration (TC) = 6,80 min.
++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 110,500 to Point/Station 110,000
**** CONFLUENCE OF MAIN STREAMS ****
The following data inside Main stream is listed:
in Main Stream number: 2
Stream flow area = 4,840(Ac)
Runoff from this stream = 22.842(CFS)
Time of concentration = 6,80 min.
Rainfall intensity = 6.051(ln/Hr)
Summary of stream data:
Stream
NO.
Flow rate
(CFS)
TC
(min)
Rainfall intensity
(in/Hr)
22.625
22.842
Qmax(l) =
Qmax(2) =
.000 *
,000 *
0.995 *
1.000 *
6.75
6.80
1,000 *
0,993 *
,000 *
,000 *
6.080
6.051
22.625) +
22.842) +
22.625) +
22.842) +
45.299
45.360
Total of 2 main streams to confluence:
Flow rates before confluence point:
22.625 22.842
Maximum flow rates at confluence using above data:
45.299 45.360
Area of streams before confluence:
4.860 4.840
Results of confluence:
Total flow rate = 45.360(CFS)
Time of concentration = 6.798 min.
Effective stream area after confluence 9.700(Ac.)
Page 8
c605Pl,OUT
Process from Point/Station 110.000 to Point/Station 104.000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
upstream point/station elevation = 441.00(Ft.)
Downstream point/station elevation = 432.60(Ft.)
Pipe length = 120,66(Ft,) Manning's N = 0,013
NO, of pipes = 1 Required pipe flow = 45.360(CFS)
Given pipe size = 24.00(ln,)
Calculated individual pipe flow = 45.360(CFS)
Normal flow depth in pipe = 15.66(in,)
Flow top width inside pipe = 22,86(in,)
Critical depth could not be calculated.
Pipe flow velocity = 20.91(Ft/s)
Travel time through pipe = 0,10 min.
Time of concentration (TC) = 6,89 min.
Process from Point/station 110.000 to Point/Station 104.000
**** CONFLUENCE OF MAIN STREAMS ****
The following data inside Main Stream is listed:
In Main Stream number: 1
Stream flow area = 9.700(Ac)
Runoff from this stream = 45,360(CFS)
Time of concentration = 6.89 min.
Rainfall intensity = 5.996(ln/Hr)
Program is now starting with Main Stream No. 2
Process from Point/Station 101.000 to Point/Station 102.000
**** INITIAL AREA EVALUATION ****
Decimal fraction soil group A = 0.000
Decimal fraction soil group 8 = 1.000
Decimal fraction soil group C = 0.000
Decimal fraction soil group D = 0.000
[RURAL (greater than 1/2 acre) area type ]
Time of concentration computed by the
natural watersheds nomograph (App x-A)
TC = [11.9*length(Mi)A3)/(elevation change)]A.385 *60(min/hr) + 10 min.
Initial subarea flow distance = 850.00(Ft.)
Highest elevation = 540.00(Ft.)
Lowest elevation = 448,00(Ft.)
Elevation difference = 92.00(Ft.)
TC=[(11.9*0.1610A3)/( 92.00)]A,385= 3,31 + 10 min. = 13.31 min.
Rainfall intensity (I) = 3.923 for a 100.0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0.350
Subarea runoff = 18.536(CFS)
Total initial stream area = 13.500(Ac,)
Process from Point/Station 102.000 to Point/Station 103.000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
Upstream point/station elevation = 448.00(Ft.)
Downstream point/station elevation = 446.00(Ft.)
Pipe length = 160.00(Ft.) Manning's N = 0.013
NO, of pipes = 1 Required pipe flow = 18,536(CFS)
Given pipe size = 24.00(ln.)
Calculated individual pipe flow = 18.536(CFS)
Page 9
C605P1.OUT
Normal flow depth in pipe = 15.26(in.)
Flow top width inside pipe = 23.10(in.)
Critical Depth = 18.60(ln,)
Pipe flow velocity = 8.79(Ft/s)
Travel time through pipe = 0,30 min.
Time of concentration (TC) = 13,61 min.
Process from Point/Station 103,000 to Point/Station
**** PIPEFLOW TRAVEL TIME (User specified size) ****
104,000
upstream point/station elevation = 446.00(Ft,)
Downstream point/station elevation = 432.60(Ft,)
Pipe length = 335,00(Ft,) Manning's N = 0.013
No. of pipes = 1 Required pipe flow = 18,536(CFS)
Given pipe size = 24,00(ln.)
calculated individual pipe flow = 18,536(CFS)
Normal flow depth in pipe = 10,70(ln.)
Flow top width inside pipe = 23,86(ln,)
critical Depth = 18.60(ln,)
Pipe flow velocity = 13,69(Ft/s)
Travel time through pipe = 0.41 min.
Time of concentration (TC) = 14.02 min.
Process from Point/station 103,000 to Point/Station 104,000
**** CONFLUENCE OF MAIN STREAMS ****
The following data inside Main Stream is listed:
In Main Stream number: 2
Stream flow area = 13,500(Ac)
Runoff from this stream = 18,536(CFS)
Time of concentration = 14,02 min.
Rainfall intensity = 3,793(ln/Hr)
Summary of stream data:
Stream
NO,
Flow rate
(CFS) TC
(min)
Rainfall intensity
(in/Hr)
45.360
18.536
Qmax(l) =
Qmax(2) =
6.89
14.02
1.000 *
1.000 *
0.633 *
1.000 *
1.000 *
0.492 *
1.000 *
1.000 *
5.996
3.793
45.360) +
18.536) +
45.360) +
18.536) +
54.473
47.230
Total of 2 main streams to confluence:
Flow rates before confluence point:
45,360 18,536
Maximum flow rates at confluence using above data:
54,473 47,230
Area of streams before confluence:
9.700 13,500
Results of confluence:
Total flow rate = 54.473(CFS)
Time of concentration = 6.895 min.
Page 10
C605P1.OUT
Effective stream area after confluence = 23.200(Ac)
Process from Point/Station 104,000 to Point/Station 111,000
**** PIPEFLOW TRAVEL TIME (user specified size) ****
upstream point/station elevation = 432.10(Ft.)
Downstream point/station elevation = 426.83(Ft.)
Pipe length = 75.34(Ft.) Manning's N = 0.013
NO. of pipes = 1 Required pipe flow = 54.473(CFS)
Given pipe size = 36,00(ln,)
Calculated individual pipe flow = 54.473(CPS)
Normal flow depth in pipe = 13.73(in.)
Flow top width inside pipe = 34.97(in.)
critical Depth = 28,77(ln,)
Pipe flow velocity = 21,99(Ft/s)
Travel time through pipe = 0,06 min.
Time of concentration (TC) = 6.95 min.
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 104.000 to Point/Station 111.000
**** CONFLUENCE OF MINOR STREAMS ****
Along Main Stream number: 1 in normal stream number 1
Stream flow area = 23.200(Ac.)
Runoff from this stream = 54.473(CFS)
Time of concentration = 6,95 min.
Rainfall intensity = 5,965(ln/Hr)
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 111,100 to Point/Station 111.200
**** INITIAL AREA EVALUATION ****
Decimal fraction soil group A = 0.000
Decimal fraction soil group B =1.000
Decimal fraction soil group C = 0.000
Decimal fraction soil group D = 0.000
[INDUSTRIAL area type ]
initial subarea flow distance = 100.00(Ft.)
Highest elevation = 461.00(Ft.)
Lowest elevation = 459.00(Ft.)
Elevation difference = 2.00(Ft,)
Time of concentration calculated by the urban
areas overland flow method (App x-C) = 3.57 min.
TC = [l,8*(l,l-C)*distanceA,5)/(% slopeA(l/3)]
TC = [1.8*(l.l-0.8500)*(100.00A,5)/( 2,OOA(l/3)]= 3,57
Setting time of concentration to 5 minutes
Rainfall intensity (I) = 7,377 for a 100,0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0.850
Subarea runoff = 0.314(CFS)
Total initial stream area = 0.050(Ac.)
Process from Point/Station 111.200 to Point/Station 111.300
**** IMPROVED CHANNEL TRAVEL TIME ****
Upstream point elevation = 459.00(Ft.)
Downstream point elevation = 455.00(Ft.)
Channel length thru subarea = 200.00(Ft.)
Page 11
m C605P1.OUT
Channel base width = 0.000(Ft.)
Slope or 'z' of left channel bank = 20.000
Slope or 'Z' of right channel bank = 20.000
Estimated mean flow rate at midpoint of channel = 3,543(CFS)
Manning's 'N' = 0,015
Maximum depth of channel = 1.000(Ft.)
Flow(q) thru subarea = 3.543(CFS)
Depth of flow = 0,231(Ft.), Average velocity = 3,320(Ft/s)
Channel flow top width = 9,240(Ft.)
Flow velocity = 3.32(Ft/s)
Travel time = 1.00 min.
Time of concentration = 6.00 min.
critical depth = 0.287(Ft.)
Adding area flow to channel
Decimal fraction soil group A = 0.000
Decimal fraction soil group B = 1.000
Decimal fraction soil group C = 0.000
Decimal fraction soil group D = 0,000
[INDUSTRIAL area type ]
Rainfall intensity = 6.556(in/Hr) for a 100.0 year storm
Runoff coefficient used for sub-area. Rational method,Q=KCIA, C = 0.850
Subarea runoff = 5.740(CFS) for 1.030(Ac.)
Total runoff = 6.053(CFS) Total area = 1.08(Ac)
++++++++++++++4-+++++++++++++++++++++++++++++++++++++++++++++^
process from Point/Station 111,300 to Point/Station 111,300
**** SUBAREA FLOW ADDITION ****
Decimal fraction soil group A = 0,000
Decimal fraction soil group B = 1,000
Decimal fraction soil group C = 0,000
Decimal fraction soil group D = 0,000
[INDUSTRIAL area type ]
Time of concentration = 6,00 min.
Rainfall intensity = 6,556(ln/Hr) for a 100,0 year storm
Runoff coefficient used for sub-area. Rational method,Q=KCIA, C = 0,850
subarea runoff = 5,573(CFS) for 1.000(Ac.)
Total runoff = 11.626(CFS) Total area = 2.08(Ac.)
process from Point/Station 111,300 to Point/Station 111.000 **** PIPEFLOW TRAVEL TIME (User specified size) ****
upstream point/station elevation = 454.00(Ft.)
Downstream point/station elevation = 427.00(Ft.)
Pipe length = 50.00(Ft.) Manning's N = 0.013
No. of pipes = 1 Required pipe flow = 11,626(CFS)
Given pipe size = 18,00(ln.)
Calculated individual pipe flow = 11.626(CFS)
Normal flow depth in pipe = 4.72(in.)
Flow top width inside pipe = 15.84(ln.)
critical Depth = 15.58(in.)
Pipe flow velocity = 31,46(Ft/s)
Travel time through pipe = 0.03 min.
Time of concentration (TC) = 6.03 min,
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ Process from Point/station 111,300 to Point/Station 111.000
**** CONFLUENCE OF MINOR STREAMS ****
Page 12
C605P1,OUT
Along Main Stream number: 1 in normal stream number 2
Stream flow area = 2,080(Ac,)
Runoff from this stream = 11.626(CFS)
Time of concentration = 6,03 min.
Rainfall intensity = 6,537(ln/Hr)
Summary of stream data:
Stream
NO.
Flow rate
(CFS)
TC
(min)
Rainfall intensity
(in/Hr)
54.473
11,626
6.95
6,03
5,965
6.537
Qmax(l) =
Qmax(2) =
1,000 *
0.912 *
1,000
1,000
1,000 *
1.000 *
0,867 *
1,000 *
54.473) +
11,626) +
54,473) +
11.626) +
65,081
58,881
Total of 2 streams to confluence:
Flow rates before confluence point:
54.473 11.626
Maximum flow rates at confluence using above data:
65,081 58.881
Area of streams before confluence:
23.200 2.080
Results of confluence:
Total flow rate = 65,081(CFS)
Time of concentration = 6.952 min.
Effective stream area after confluence = 25,280(Ac,)
Process from Point/Station 111,000 to Point/Station
**** PIPEFLOW TRAVEL TIME (User specified size) ****
112,500
upstream point/station elevation = 426,50(Ft,)
Downstream point/station elevation = 409.00(Ft,)
Pipe length = 250.02(Ft,) Manning's N = 0,013
NO, of pipes = 1 Required pipe flow = 65.081(CFS)
Given pipe size = 36,00(ln,)
Calculated individual pipe flow = 65.081(CFS)
Normal flow depth in pipe = 15.14(ln.)
Flow top width inside pipe = 35.54(in.)
critical Depth = 31.02(ln.)
Pipe flow velocity = 23.08(Ft/s)
Travel time through pipe = 0.18 min.
Time of concentration (TC) = 7.13 min.
Process from Point/Station 112.500 to Point/Station
**** PIPEFLOW TRAVEL TIME (user specified size) ****
112.000
upstream point/station elevation = 409.67(Ft.)
Downstream point/station elevation = 393.00(Ft.)
Pipe length = 204.33(Ft,) Manning's N = 0.013
NO. of pipes = 1 Required pipe flow = 65.081(CFS)
Given pipe size = 36.00(ln.)
Calculated individual pipe flow = 65.081(CFS)
Normal flow depth in pipe = 14,51(ln,)
Flow top width inside pipe = 35.32(in.
Page 13
.)
C605P1.OUT
critical Depth = 31.02(in.)
Pipe flow velocity = 24.40(Ft/s)
Travel time through pipe = 0.14 min.
Time of concentration (TC) = 7.27 min.
Process from Point/Station 112,500 to Point/Station 112,000
**** CONFLUENCE OF MAIN STREAMS ****
The following data inside Main stream is listed:
In Main Stream number: 1
Stream flow area = 25.280(Ac)
Runoff from this stream = 65,081(CFS)
Time of concentration = 7.27 min.
Rainfall intensity = 5,794(ln/Hr)
Program is now starting with Main Stream No, 2
Process from Point/Station
**** INITIAL AREA EVALUATION
110.000 to Point/Station
****
107.000
26.00(Ft.)"
]
Decimal fraction soil group A = 0.000
Decimal fraction soil group B = 1.000
Decimal fraction soil group C = 0.000
Decimal fraction soil group D = 0,000
[INDUSTRIAL area type
Initial subarea flow distance =
Highest elevation = 454,65(Ft,)
Lowest elevation = 454.15(Ft.)
Elevation difference = 0,50(Ft,)
Time of concentration calculated by the urban
areas overland flow method (App x-C) = 1.85 min.
TC = [l,8*(l.l-C)*distanceA,5)/(% slopeA(l/3)]
TC = [l,8*(l,l-0,8500)*( 26,00A.5)/( 1,92A(1/3)]= 1,85
Setting time of concentration to 5 minutes
Rainfall intensity (I) = 7,377 for a 100,0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0,850
Subarea runoff = 0.063(CFS)
Total initial stream area = 0.010(Ac.)
Process from Point/Station
**** STREET FLOW TRAVEL TIME
107.000 to Point/Station 112.100
SUBAREA FLOW ADDITION ****
Top of Street segment elevation = 454.150(Ft.)
End of street segment elevation = 405.750(Ft.)
Length of street segment = 660.000(Ft.)
Height of curb above gutter flowline = 6.0(in.)
Width of half street (curb to crown) = 26.000(Ft.)
Distance from crown to crossfall grade break = 24.500(Ft.)
Slope from gutter to grade break (v/hz) = 0.020
Slope from grade break to crown (v/hz) = 0.020
Street flow is on [1] side(s) of the street
Distance from curb to property line = 10.000(Ft.)
Slope from curb to property line (v/hz) = 0.020
Gutter width = l,500(Ft,)
Gutter hike from flowline = l,500(ln,)
Manning's N in gutter = 0.0150
Manning's N from gutter to grade break = 0.0150
Manning's N from grade break to crown = 0.0150
Page 14
Decimal
Decimal
Decimal
A = 0.000
group B = 1.000
C605P1.OUT
Estimated mean flow rate at midpoint of street = 0.112(CPS)
Depth of flow = 0.080(Ft,), Average velocity = 2.957(Ft/s)
Streetflow hydraulics at midpoint of street travel:
Halfstreet flow width = 1.500(Ft.)
Flow velocity = 2,96(Ft/s)
Travel time = 3.72 min, TC = 8,72 min.
Adding area flow to street
Decimal fraction soil group
fraction soil
fraction soil
fraction soil
[INDUSTRIAL area type
Rainfall intensity =
Runoff coefficient used for sub-area,
Subarea runoff = 6,921(CFS) for
Total runoff = 6,984(CFS) Total
Street flow at end of street = 6
Half street flow at end of street =
Depth of flow = 0.303(Ft,), Average velocity = 6,067(Ft/s)
Flow width (from curb towards crown)= 10,391(Ft,)
group
group
= 0,000
= 0,000
]
5,153(in/Hr) for
Rational
l,580(Ac.)
area =
.984(CFS)
6,984(CFS)
100.0 year storm
method,Q=KCIA, C = 0,850
l,59(Ac.)
Process from Point/Station 107.000 to Point/Station 112.100
**** CONFLUENCE OF MINOR STREAMS ****
Along Main Stream number: 2 in normal stream number 1
Stream flow area = 1,590(AC.)
Runoff from this stream = 6.984(CFS)
Time of concentration = 8,72 min.
Rainfall intensity = 5.153(ln/Hr)
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 112.400 to Point/Station 112.300
**** INITIAL AREA EVALUATION ****
= 100,00(Ft,)'
]
Decimal fraction soil group A = 0,000
Decimal fraction soil group B = 1.000
Decimal fraction soil group C = 0.000
Decimal fraction soil group D = 0,000
[INDUSTRIAL area type
Initial subarea flow distance
Highest elevation = 443.50(Ft.)
Lowest elevation = 441,50(Ft,)
Elevation difference = 2,00(Ft.)
Time of concentration calculated by the urban
areas overland flow method (App x-C) = 3.57 min.
TC = [1.8*(l.l-c)*distanceA,5)/(% slopeA(i/3)]
TC = [1.8*(l,l-0.8500)*(100.00A.5)/( 2.00A(l/3)]= 3.57
Setting time of concentration to 5 minutes
RainfaTl intensity (I) = 7.377 for a 100.0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0.850
subarea runoff = 0.627(CFS)
Total initial stream area = 0.100(Ac.)
Process from Point/Station 112.300 to Point/Station 112.200
**** IMPROVED CHANNEL TRAVEL TIME ****
upstream point elevation =
Downstream point elevation =
441.50(Ft.)
437.00(Ft.)
Page 15
(#
5.017(CFS)
C605P1.OUT
Channel length thru subarea = 300.00(Ft.)
Channel base width = 0.000(Ft.)
Slope or 'z' of left channel bank = 20,000
Slope or 'Z' of right channel bank = 20,000
Estimated mean flow rate at midpoint of channel =
Manning's 'N' = 0,015
Maximum depth of channel = 1.000(Ft,)
Flow(q) thru subarea = 5.017(CFS)
Depth of flow = 0,278(Ft,), Average velocity = 3.251(Ft/s)
Channel flow top width = ll,110(Ft,)
Flow Velocity = 3,25(Ft/s)
Travel time = 1,54 min.
Time of concentration = 6,54 min.
critical depth = 0,330(Ft,)
Adding area flow to channel
DecimaT fraction soil group A = 0,000
Decimal fraction soil group B = 1,000
Decimal fraction soil
Decimal fraction soil
[INDUSTRIAL area type
Rainfall intensity =
group
group
= 0,000
= 0,000
]
Kdiriictii iiiLCMaiLy = 6,205(in/Hr) for a 100.0 year storm
Runoff coefficient used for sub-area. Rational method,Q=KCIA, C = 0.850
Subarea runoff = 7.384(CFS) for l,400(Ac,)
Total runoff = 8,012(CPS) Total area = 1.50(Ac,)
Process from Point/Station 112.200 to Point/Station
**** SUBAREA FLOW ADDITION ****
112,200
Decimal fraction soil group A
Decimal fraction soil group B
Decimal fraction soil group C
Decimal fraction soil group D
[INDUSTRIAL area type
Time of concentration
Rainfall intensity =
0,000
1.000
0,000
0,000
]
6.54 min,
^ 6,205(in/Hr) for a 100.0 year storm
Runoff coefficient used for sub-area, Rational method,Q=KCIA, C = 0.850
subarea runoff = 10.444(CFS) for 1.980(Ac.)
Total runoff = 18.455(CFS) Total area = 3.48(Ac.)
18,455(CFS)
Process from Point/Station 112,200 to Point/Station
**** PIPEFLOW TRAVEL TIME (User specified size) ****
Upstream point/station elevation = 425,00(Ft,)
Downstream point/station elevation = 394,80(Ft,)
Pipe length = 80,00(Ft,) Manning's N = 0.013
NO. of pipes = 1 Required pipe flow =
Given pipe size = 24.00(ln.)
Calculated individual pipe flow = 18.455(CFS)
Normal flow depth in pipe = 5.91(ln.)
Flow top width inside pipe = 20.68(in.)
critical Depth = 18.56(in.)
Pipe flow velocity = 30.72(Ft/s)
Travel time through pipe = 0.04 min.
Time of concentration (TC) = 6.58 min.
112.100
Process from Point/Station 112.200 to Point/Station
**** CONFLUENCE OF MINOR STREAMS ****
Page 16
112.100
C605P1.OUT
Along Main Stream number: 2 in normal stream number 2
Stream flow area = 3,480(Ac.)
Runoff from this stream = 18.455(CFS)
Time of concentration = 6,58 min.
Rainfall intensity = 6,179(in/Hr)
Summary of stream data:
Stream
NO.
Flow rate
(CPS)
TC
(min)
Rainfall Intensity
(in/Hr)
1
2
6,984
18.455
Qmax(l) =
Qmax(2) =
1,000 *
0.834 *
8,72
6.58
1
1
5,153
6,179
,000
,000
000
000
0.755
1,000
6.984) +
18.455) +
6.984) +
18.455) +
22.376
23,726
Total of 2 streams to confluence:
Flow rates before confluence point:
6,984 18,455
Maximum flow rates at confluence using above data:
22,376 23,726
Area of streams before confluence:
1.590 3,480
Results of confluence:
Total flow rate = 23,726(CFS)
Time of concentration = 6.581 min.
Effective stream area after confluence = 5.070(Ac.)
++^
Process from Point/Station
**** PIPEFLOW TRAVEL TIME (User
112.100 to Point/Station
specified size) ****
112.000
upstream point/station elevation = 394.50(Ft.)
Downstream point/station elevation = 394.00(Ft.)
Pipe length = 5,00(Ft,) Manning's N = 0.013 NO, of pipes = 1 Required pipe flow = 23,726(CFS)
Given pipe size = 24,00(ln,)
calculated individual pipe flow = 23.726(CFS)
Normal flow depth in pipe = 9.52(In.)
Flow top width inside pipe = 23.48(In.)
critical Depth = 20.72(in.)
Pipe flow velocity = 20.45(Ft/s)
Travel time through pipe = 0.00 min.
Time of concentration (TC) = 6,59 min.
Process from Point/Station
**** CONFLUENCE OF MAIN STREAMS
112.100 to Point/Station
****
112.000
The following data inside Main Stream is listed:
in Main Stream number: 2
Stream flow area = 5.070(Ac.)
Runoff from this stream = 23.726(CFS)
Time of concentration = 6.59 min.
Rainfall intensity = 6.177(in/Hr)
Program is now starting with Main Stream No. 3
page 17
C605P1.OUT
process from Point/Station
**** INITIAL AREA EVALUATION
110,000 to Point/Station 110.500
****
]
Decimal fraction soil group A = 0,000
Decimal fraction soil group B = 1,000
Decimal fraction soil group C = 0,000
Decimal fraction soil group D = 0.000
[INDUSTRIAL area type
Initial subarea flow distance = 26,00(Ft,)
Highest elevation = 455,15(Ft,)
Lowest elevation = 454,65(Ft.)
Elevation difference = 0,50(Ft,)
Time of concentration calculated by the urban areas overland flow method (App x-C) = 1.85 min,
TC = [1.8*(l.l-C)*distanceA,5)/(% slopeA(l/3)]
TC = [l,8*(l.l-0,8500)*( 26.00A,5)/( 1,92A(1/3)]= 1.85
Setting time of concentration to 5 minutes
RainfaTl intensity (I) = 7,377 for a 100,0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0.850
subarea runoff = 0.063(CPS)
Total initial stream area = 0.010(Ac.)
Process from Point/Station 110.500 to Point/Station
**** STREET FLOW TRAVEL TIME + SUBAREA FLOW ADDITION ****
112.600
Top of Street segment elevation = 454.650(Ft.)
End of street segment elevation = 405.550(Ft.)
Length of street segment = 660,000(Ft,)
Height of curb above gutter flowline = 6,0(ln,)
width of half street (curb to crown) = 26,000(Ft,)
Distance from crown to crossfall grade break = 24.500(Ft.)
Slope from gutter to grade break (v/hz) = 0,020
Slope from grade break to crown (v/hz) = 0.020
Street flow is on [1] side(s) of the street
Distance from curb to property line = 10.000(Ft.)
Slope from curb to property line (v/hz) = 0.020
Gutter width = 1.500(Ft.)
Gutter hike from flowline = l,500(ln.)
Manning's N in gutter = 0.0150
Manning's N from gutter to grade break = 0,0150
Manning's N from grade break to crown = 0,0150
Estimated mean flow rate at midpoint of street =
Depth of flow = 0,069(Ft,), Average velocity =
Streetflow hydraulics at midpoint of street travel
Halfstreet flow width = l,500(Ft,)
Flow velocity = 2.71(Ft/s)
0,078(CFS)
2,712(Ft/s)
Travel time = 4,06 min
Adding area flow to street
DecimaT fraction soil group
Decimal fraction soil
Decimal fraction soil group
Decimal fraction soil group
[INDUSTRIAL area type
Rainfall intensity =
TC =
A = 0,000
group B = 1,000
9.06 min.
= 0,000
= 0,000
]
5,029(ln/Hr) for a
Runoff coefficient used for sub-area, Rational
subarea runoff = 2,052(CPS) for 0,480(Ac,)
Total runoff = 2.115(CFS) Total area =
Street flow at end of street = 2,115(CFS)
Page 18
100,0 year storm
method,Q=KCIA, C = 0.850
0.49(Ac.)
C605P1,OUT
Half street flow at end of street = 2.115(CFS)
Depth of flow = 0,219(Ft,), Average velocity = 4.632(Ft/s)
Flow width (from curb towards crown)= 6.207(Ft.)
++ Process from Point/Station 110,500 to Point/Station 112,600
**** CONFLUENCE OF MINOR STREAMS ****
Along Main stream number: 3 in normal stream number 1
Stream flow area = 0,490(Ac)
Runoff from this stream = 2,115(CFS)
Time of concentration = 9,06 min.
Rainfall intensity = 5,029(in/Hr)
Process from Point/Station 112,700 to Point/Station
**** INITIAL AREA EVALUATION ****
112,800
Decimal fraction soil group A = 0.000
Decimal fraction soil group B = 1,000
Decimal fraction soil group C = 0.000
Decimal fraction soil group D = 0.000
[INDUSTRIAL area type ]
initial subarea flow distance = 100,00(Ft,)
Highest elevation = 436,00(Ft,)
Lowest elevation = 434,00(Ft.)
Elevation difference = 2,00(Ft,)
Time of concentration calculated by the urban
areas overland flow method (App X-C) = 3,57 min,
TC = [1.8*(l.l-C)*distanceA.5)/(% slopeA(l/3)]
TC = [1.8*(l.l-0.8500)*(100.00A.5)/( 2.00A(1/3)]= 3.57
Setting time of concentration to 5 minutes
RainfaTl intensity (I) = 7.377 for a 100.0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0,850
subarea runoff = 0,627(CFS)
Total initial stream area = 0,100(Ac.)
Process from Point/Station 112.800 to Point/Station
**** IMPROVED CHANNEL TRAVEL TIME ****
112.900
upstream point elevation = 434.00(Ft.)
Downstream point elevation = 428.00(Ft.)
Channel length thru subarea = 400.00(Ft.)
Channel base width = 0.000(Ft.)
Slope or 'Z' of left channel bank = 20.000
Slope or 'Z' of right channel bank = 20.000
Estimated mean flow rate at midpoint of channel =
Manning's 'N' = 0.015
Maximum depth of channel = 1.000(Ft.)
Flow(q) thru subarea = 13,074(CFS)
Depth of flow = 0,398(Ft,), Average velocity =
Channel flow top width = 15,912(Ft,)
Flow velocity = 4,13(Ft/s)
Travel time = 1,61 min.
Time of concentration = 6.61 min.
critical depth = 0.484(Ft.)
Adding area flow to channel
DecimaT fraction soil group A = 0.000
Decimal fraction soil group B = 1.000
Page 19
13.074(CFS)
4.131(Ft/s)
m Decimal fraction soil group
Decimal fraction soil group
[INDUSTRIAL area type
Rainfall intensity = 6
c605Pl,OUT
C = 0,000
D = 0,000
] ^ ,159(ln/Hr) for a 100.0 year storm
Runoff coefficient used for sub-area. Rational method,Q=KClA, C = 0.850
subarea runoff = 20,785(CFS) for 3,970(Ac,)
Total runoff = 21,412(CPS) Total area = 4,07(Ac)
Process from Point/Station 112,900 to Point/Station
**** PIPEFLOW TRAVEL TIME (User specified size) ****
upstream point/station elevation = 415,00(Ft,)
Downstream point/station elevation = 396.50(Ft,)
Pipe length = 80.00(Ft,) Manning's N = 0.013
No, of pipes = 1 Required pipe flow = 21,412(CFS)
Given pipe size = 24.00(ln.)
Calculated individual pipe flow = 21,412(CFS)
Normal flow depth in pipe = 7.22(In.)
Flow top width inside pipe = 22,01(in,)
critical Depth = 19,86(in,)
Pipe flow velocity = 26,91(Ft/s)
Travel time through pipe = 0.05 min.
Time of concentration (TC) = 6,66 min.
112.600
Process from Point/Station 112.900 to Point/Station
**** CONFLUENCE OF MINOR STREAMS ****
112,600
Along Main Stream number: 3 in normal stream number 2
Stream flow area = 4,070(Ac,)
Runoff from this stream = 21.412(CPS)
Time of concentration = 6.66 min.
Rainfall intensity = 6,130(ln/Hr)
Summary of stream data:
Stream
NO,
Flow rate
(CFS) TC
(min)
Rainfall intensity
(in/Hr)
2,115
21.412
Qmax(l) =
Qmax (2) =
1.000 *
0.820 *
1.000 *
1.000 *
9.06
6.66
1
1
,000 *
,000 *
0.736 *
1.000 *
5.029
6.130
2,115) +
21,412) +
2,115) +
21,412) +
19,683
22,968
Total of 2 streams to confluence:
Flow rates before confluence point:
2,115 21,412
Maximum flow rates at confluence using above data:
19,683 22,968
Area of streams before confluence:
0,490 4,070
Results of confluence:
Total flow rate = 22.968(CFS)
Time of concentration = 6,663 min.
Effective stream area after confluence = 4,560(Ac.)
Page 20
C605P1,OUT
Process from Point/Station 112.600 to Point/Station 112.000
**** PIPEFLOW TRAVEL TIME (user specified size) ****
upstream point/station elevation = 396,20(Ft,)
Downstream point/station elevation = 394.00(Ft,)
Pipe length = 45.00(Ft.) Manning's N = 0,013
NO. of pipes = 1 Required pipe flow = 22,968(CFS)
Given pipe size = 24,00(in.)
Calculated individual pipe flow = 22.968(CFS)
Normal flow depth in pipe = ll,41(in,)
Flow top width inside pipe = 23,97(in,)
critical Depth = 20,46(ln.)
Pipe flow velocity = 15.58(Ft/s)
Travel time through pipe = 0.05 min.
Time of concentration (TC) = 6.71 min.
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 112,600 to Point/Station 112,000
**** CONFLUENCE OF MAIN STREAMS ****
The following data inside Main Stream is listed:
in Main Stream number: 3
Stream flow area = 4.560(Ac.)
Runoff from this stream = 22.968(CFS)
Time of concentration = 6.71 min.
Rainfall intensity = 6.101(ln/Hr)
Summary of stream data:
Stream Flow rate TC Rai nfal1 Intensity
No. (CFS) (mi n) (in/Hr)
1 65 .081 7 27 5.794
2 23 ,726 6 59 6.177
3 22 ,968 6 71 6,101
Qmax(l) =
1,000 * 1.000 * 65 .081) +
0,938 * 1.000 * 23 .726) +
0,950 * 1.000 * 22 .968) + = 109,148
Qmax(2) =
1.000 * 0.906 * 65 .081) +
1,000 * 1.000 * 23 ,726) +
1.000 * 0.981 * 22 .968) + = 105.200
Qmax(3) =
1.000 * 0.923 * 65 ,081) +
0.988 * 1.000 * 23 ,726) +
1.000 * 1.000 * 22 ,968) + = 106.472
Total of 3 main streams to confluence:
Flow rates before confluence point:
65.081 23.726 22.968
Maximum flow rates at confluence using above data:
109.148 105.200 106.472
Area of streams before confluence:
25.280 5.070 4,560
Results of confluence:
Total flow rate = 109.148(CFS)
Time of concentration = 7.272 min.
Page 21
m C605P1.OUT
Effective stream area after confluence = 34.910(Ac.)
Process from Point/Station 112.000 to Point/Station 113.000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
upstream point/station elevation = 392,50(Ft,)
Downstream point/station elevation = 386,50(Ft,)
Pipe length = 42.49(Ft,) Manning's N = 0.013 NO. of pipes = 1 Required pipe flow = 109.148(CPS)
Given pipe size = 42.00(in.)
Calculated individual pipe flow = 109.148(CFS) Normal flow depth in pipe = 15.45(In.)
Flow top width inside pipe = 40,50(ln,)
Critical Depth = 37,96(ln,)
Pipe flow velocity = 33,98(Ft/s)
Travel time through pipe = 0.02 min.
Time of concentration (TC) = 7.29 min.
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 112.000 to Point/Station 113,000
**** CONFLUENCE OF MAIN STREAMS ****
The following data inside Main Stream is listed:
In Main Stream number: 1
Stream flow area = 34,910(Ac.)
Runoff from this stream = 109,148(CPS)
Time of concentration = 7.29 min.
Rainfall intensity = 5.783(In/Hr)
Program is now starting with Main Stream No, 2
++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 113,100 to Point/Station 113,200
**** INITIAL AREA EVALUATION ****
Decimal fraction soil group A = 0.000
Decimal fraction soil group B = 1.000 Decimal fraction soil group C = 0.000
Decimal fraction soil group D = 0.000
[INDUSTRIAL area type ]
Initial subarea flow distance = 100.00(Ft.)
Highest elevation = 456,00(Ft.)
Lowest elevation = 454.00(Ft.)
Elevation difference = 2.00(Ft,)
Time of concentration calculated by the urban
areas overland flow method (App x-C) = 3.57 min.
TC = [1.8*(l.l-C)*distanceA,5)/(% slopeA(l/3)]
TC = [l,8*(l,l-0.85OO)*(100.O0A.5)/( 2.00A(1/3)]= 3.57
Setting time of concentration to 5 minutes
RainfaTl intensity (I) = 7.377 for a 100.0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0.850
Subarea runoff = 0.627(CFS)
Total initial stream area = 0.100(Ac.)
Process from Point/Station 113,200 to Point/Station 113.300
**** IMPROVED CHANNEL TRAVEL TIME ****
Upstream point elevation = 545.00(Ft.)
Page 22
m C605P1.OUT
Downstream point elevation = 450.00(Ft.)
Channel length thru subarea = 400.00(Ft.)
Channel base width = 0,000(Ft.)
Slope or 'z* of left channel bank = 20.000
Slope or 'Z' of right channel bank = 20.000
Estimated mean flow rate at midpoint of channel =
Manning's 'N' = 0,015
Maximum depth of channel = 1.000(Ft,)
Flow(q) thru subarea = 5,017(CFS)
Depth of flow = 0,165(Ft,), Average velocity =
Channel flow top width = 6,619(Ft,)
Flow velocity = 9,16(Ft/s)
Travel time = 0,73 min.
Time of concentration = 5.73 min,
critical depth = 0.330(Ft.)
Adding area flow to channel
DecimaT fraction soil group A = 0,000
fraction soil group B = 1.000
fraction soil group C = 0,000
group D = 0,000
Deci mai
Decimal
Decimal fraction soil
[INDUSTRIAL area type
Rainfall intensity =
]
5.017(CFS)
9,160(Ft/s)
Kainraii im.enbiLy = 6,758(ln/Hr) for a ' 100.0 year storm
Runoff coefficient used for sub-area, Rational method,Q=KCIA, C = 0,850
subarea runoff = 8,042(CFS) for l,400(Ac.)
Total runoff = 8,669(CFS) Total area = l,50(Ac,)
Process from Point/Station 113.300 to Point/Station 113.300
**** SUBAREA FLOW ADDITION ****
Decimal fraction soil group A = 0.000
Decimal fraction soil group B = 1.000
Decimal fraction soil group C = 0.000
Decimal fraction soil group D = 0.000
[INDUSTRIAL area type
Time of concentration = 5.73 min.
Rainfall intensity = 6.758(ln/Hr) for a 100.0 year storm
Runoff coefficient used for sub-area. Rational method,Q=KCIA, C
subarea runoff = 19.186(CFS) for 3.340(Ac)
Total runoff = 27.856(CFS) Total area = 4.84(Ac.)
]
= 0.850
27.856(CFS)
Process from Point/Station 113.300 to Point/Station 113.400
**** PIPEFLOW TRAVEL TIME (User specified size) ****
upstream point/station elevation = 440.00(Ft.)
Downstream point/station elevation = 433.30(Ft,)
Pipe length = 70,00(Ft,) Manning's N = 0.013
NO. of pipes = 1 Required pipe flow =
Given pipe size = 30.00(in.)
calculated individual pipe flow = 27.856(CFS)
Normal flow depth in pipe = 9.55(in.)
Flow top width inside pipe = 27.95(in.)
critical Depth = 21.59(ln.)
Pipe flow velocity = 20,72(Ft/s)
Travel time through pipe = 0,06 min.
Time of concentration (TC) = 5.78 min.
Process from Point/Station 113.400
Page 23
to Point/Station 113.500
C605P1.OUT
**** PIPEFLOW TRAVEL TIME (User specified size) ****
upstream point/station elevation = 433,00(Ft,)
Downstream point/station elevation = 391.00(Ft,)
Pipe length = 590.00(Ft,) Manning's N = 0.013
NO, of pipes = 1 Required pipe flow = 27,856(CFS)
Given pipe size = 30.00(in,)
Calculated individual pipe flow = 27.856(CFS)
Normal flow depth in pipe = 10.32(In.)
Flow top width inside pipe = 28.51(in.)
critical Depth = 21.59(ln,)
Pipe flow velocity = 18,63(Ft/s)
Travel time through pipe = 0.53 min.
Time of concentration (TC) = 6,31 min.
++ Process from Point/Station 113,400 to Point/Station 113,500
**** CONFLUENCE OF MINOR STREAMS ****
Along Main stream number: 2 in normal stream number 1
Stream flow area = 4,840(Ac)
Runoff from this stream = 27,856(CFS)
Time of concentration = 6,31 min.
Rainfall intensity = 6,348(ln/Hr)
Process from Point/Station 113,400 to Point/Station
**** INITIAL AREA EVALUATION ****
113,450
User specified 'C value of 0.850 given for subarea
initial subarea flow distance = 46.00(Ft,)
Highest elevation = 442,40(Ft,)
Lowest elevation = 440,70(Ft.)
Elevation difference = 1.70(Ft,)
Time of concentration calculated by the urban
areas overland flow method (App X-C) = 1,97 min.
TC = [1.8*(l.l-C)*distanceA,5)/(% slopeA(l/3)]
TC = [l,8*(l,l-0.8500)*( 46.00A.5)/( 3,70A(l/3)]= 1.97
setting time of concentration to 5 minutes
RainfaTl intensity (l) = 7.377 for a 100.0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0.850
subarea runoff = 0.063(CFS)
Total initial stream area = 0.010(Ac.)
process from Point/Station 113.450 to Point/Station
**** STREET FLOW TRAVEL TIME + SUBAREA FLOW ADDITION ****
Top of Street segment elevation = 440.700(Ft.)
End of street segment elevation = 400.800(Ft.)
Length of street segment = 660.000(Ft.)
Height of curb above gutter flowline = 6.0(in.)
Width of half street (curb to crown) = 26.000(Ft.)
Distance from crown to crossfall grade break = 24,500(Ft,)
Slope from gutter to grade break (v/hz) = 0,020
Slope from grade break to crown (v/hz) = 0,020
Street flow is on [1] side(s) of the street
Distance from curb to property line = 10,000(Ft,)
Slope from curb to property line (v/hz) = 0,020
Gutter width = l,500(Ft.)
Page 24
113.460
C605P1.OUT
Gutter hike from flowline = 1.500(in,)
Manning's N in gutter = 0.0150
Manning's N from gutter to grade break = 0,0150
Manning's N from grade break to crown = 0.0150
Estimated mean flow rate at midpoint of street = 0.082(CFS)
Depth of flow = 0.073(Ft.), Averaqe velocity = 2.541(Ft/s)
Streetflow hydraulics at midpoint of street travel:
Halfstreet flow width = 1.500(Ft.)
Flow velocity = 2.54(Ft/s)
Travel time = 4,33 min, TC = 9,33 min.
Adding area flow to street
User specified 'C' value of 0,850 given for subarea
Rainfall intensity = 4.934(in/Hr) for a 100,0 year storm
Runoff coefficient used for sub-area. Rational method,Q=KCIA, C = 0,850
subarea runoff = 2,558(CPS) for 0.610(AC)
Total runoff = 2,621(CFS) Total area = 0.62(Ac)
Street flow at end of street = 2,621(CFS)
Half street flow at end of street = 2.621(CFS)
Depth of flow = 0.238(Ft,), Average velocity = 4,481(Ft/s)
Flow width (from curb towards crown)= 7.167(Ft,)
++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 113,460 to Point/Station 113.500
**** PIPEFLOW TRAVEL TIME (User Specified size) ****
upstream point/station elevation = 392,85(Ft,)
Downstream point/station elevation = 390,70(Ft,)
Pipe length = 43.25(Ft,) Manning's N = 0,013
No, of pipes = 1 Required pipe flow = 2,621(CFS)
Given pipe size = 18,00(ln,)
Calculated individual pipe flow = 2,621(CFS)
Normal flow depth in pipe = 4,07(In.)
Flow top width inside pipe = 15.05(In.)
Critical Depth = 7.35(ln.)
Pipe flow velocity = 8.76(Ft/s)
Travel time through pipe = 0.08 min.
Time of concentration (TC) = 9,41 min,
++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 113.460 to Point/Station 113,500
**** CONFLUENCE OF MINOR STREAMS ****
Along Main stream number: 2 in normal stream number 2
Stream flow area = 0,620(Ac)
Runoff from this stream = 2.621(CFS)
Time of concentration = 9.41 min.
Rainfall intensity = 4,906(ln/Hr)
Process from Point/Station 113,400 to Point/Station 113,470
**** INITIAL AREA EVALUATION ****
user specified 'C' value of 0.850 given for subarea
initial subarea flow distance = 46.00(Ft.)
Highest elevation = 442,40(Ft,)
Lowest elevation = 441.30(Ft,)
Elevation difference = l,10(Ft,)
Time of concentration calculated by the urban
areas overland flow method (App x-C) = 2,28 min.
TC = [1.8*(l.l-C)*distanceA,5)/(% slopeA(i/3)]
Page 25
m c605Pl,OUT
TC = [1.8*(l.l-0.8500)*( 46.00A.5)/( 2,39A(l/3)]= 2.28
Setting time of concentration to 5 minutes
RainfaTl intensity (I) = 7,377 for a 100,0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0,850
subarea runoff = 0,063(CFS)
Total initial stream area = 0,010(Ac,)
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++^
Process from Point/Station 113,470 to Point/Station 113,480
**** STREET FLOW TRAVEL TIME + SUBAREA FLOW ADDITION ****
Top of street segment elevation = 441.300(Ft.)
End of street segment elevation = 400.800(Ft.)
Length of street segment = 600.000(Ft.)
Height of curb above gutter flowline = 6.0(ln,)
Width of half street (curb to crown) = 26.000(Ft.)
Distance from crown to crossfall grade break = 24.500(Ft.)
Slope from gutter to grade break (v/hz) = 0.020
Slope from grade break to crown (v/hz) = 0.020
Street flow is on [1] side(s) of the street
Distance from curb to property line = 10.000(Ft.)
Slope from curb to property line (v/hz) = O.02O
Gutter width = l,500(Ft,)
Gutter hike from flowline = l,500(ln,)
Manning's N in gutter = 0.0150 Manning's N from gutter to grade break = 0,0150
Manning's N from grade break to crown = 0,0150 Estimated mean flow rate at midpoint of street = 0,090(CFS) Depth of flow = 0.074(Ft,), Average velocity = 2.715(Ft/s)
Streetflow hydraulics at midpoint of street travel:
Halfstreet flow width = 1.500(Ft.)
Flow velocity = 2.71(Ft/s)
Travel time = 3.68 min, TC = 8.68 min. Adding area flow to street User specified 'C' value of 0,850 given for subarea Rainfall intensity = 5.167(ln/Hr) for a 100,0 year storm
Runoff coefficient used for sub-area, Rational method,Q=KCIA, C = 0.850
subarea runoff = 3.865(CPS) for 0.880(Ac)
Total runoff = 3.928(CPS) Total area = 0.89(Ac.)
Street flow at end of street = 3.928(CFS)
Half street flow at end of street = 3.928(CFS)
Depth of flow = 0.262(Ft,), Average velocity = 5.131(Ft/s)
Flow width (from curb towards crown)= 8.332(Ft.)
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 113,480 to Point/Station 113.500
**** PIPEFLOW TRAVEL TIME (User specified size) ****
upstream point/station elevation = 391.25(Ft.) Downstream point/station elevation = 390.70(Ft.) Pipe length = 5.25(Ft,) Manning's N = 0.013
NO. of pipes = 1 Required pipe flow = 3.928(CPS) Given pipe size = 18.00(in.) Calculated individual pipe flow = 3.928(CFS)
Normal flow depth in pipe = 4.13(in.)
Flow top width inside pipe = 15.14(ln.) Critical Depth = 9.10(ln,)
Pipe flow velocity = 12,83(Ft/s)
Travel time through pipe = 0,01 min. Time of concentration (TC) = 8,69 min.
Page 26
C605P1.OUT
Process from Point/Station 113.480 to Point/Station
**** CONFLUENCE OF MINOR STREAMS ****
113,500
Along Main Stream number: 2 in normal stream number 3
Stream flow area = 0,890(Ac)
Runoff from this stream = 3.928(CFS)
Time of concentration = 8,69 min.
Rainfall intensity = 5.165(in/Hr)
Summary of stream data:
Stream
NO,
Flow rate
(CPS)
TC
(min)
Rainfall Intensity
(in/Hr)
1
2
3
Qmax(l)
27.856
2.621
3.928
6,31
9.41
8.69
6,348
4,906
5.165
Qmax(2) =
Qmax(3) =
000
000
000
1,000
0,671
0,726
0,773
1.000
0,950
0,814
1,000
1,000
1.
1.
1.
1.
0.
,000
,000
,000
,000
,923
1.000
27,856) +
2.621) +
3,928) +
27,856) +
2,621) +
3,928) +
27,856) +
2,621) +
3.928) +
32,467
27.882
29.013
Total of 3 streams to confluence:
Flow rates before confluence point:
27,856 2,621 3,928
Maximum flow rates at confluence using above data:
32,467 27,882 29,013
Area of streams before confluence:
4.840 0.620 0.890
Results of confluence:
Total flow rate = 32,467(CPS)
Time of concentration = 6,312 min.
Effective stream area after confluence = 6,350(Ac,)
Process from Point/Station 113,500 to Point/Station 113,000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
upstream point/station elevation = 390,67(Ft.)
Downstream point/station elevation = 387.17(Ft.)
Pipe length = 70.00(Ft.) Manning's N = 0.013
NO, of pipes = 1 Required pipe flow = 32,467(CPS)
Given pipe size = 30.00(ln.)
Calculated individual pipe flow = 32.467(CFS)
Normal flow depth in pipe = 12.33(In.)
Flow top width inside pipe = 29.52(in.)
critical Depth = 23.27(in.)
Pipe flow velocity = 17.08(Ft/s)
Travel time through pipe = 0.07 min.
Time of concentration (TC) = 6.38 min.
Page 27
m C605P1.OUT
process from Point/Station 113.500 to Point/Station
**** CONFLUENCE OF MAIN STREAMS ****
113.000
The following data inside Main Stream is listed:
In Main stream number: 2
Stream flow area =
Runoff from this stream
Time of concentration =
Rainfall intensity =
Summary of stream data:
6.350(Ac.)
32.467(CFS)
6.38 min.
6.304(in/Hr)
Stream
No.
Flow rate
(CFS)
TC
(mi n)
Rainfall intensity
(in/Hr)
109.148
32,467
Qmax(l) =
Qmax(2) =
1.000 *
0,917 *
1,000 *
1,000 *
7.29
6,38
1,000 *
1,000 *
0.875 *
1,000 *
5.783
6.304
109,148) +
32.467) +
109,148) +
32.467) +
138,933
127,960
Total of 2 main streams to confluence:
Flow rates before confluence point:
109.148 32.467
Maximum flow rates at confluence using above data:
138,933 127,960
Area of streams before confluence:
34,910 6,350
Results of confluence:
Total flow rate = 138,933(CPS)
Time of concentration = 7,293 min.
Effective stream area after confluence = 41.260(Ac.)
Process from Point/Station 113.000 to Point/Station 114.000
**** PIPEFLOW TRAVEL TIME (user specified size) ****
upstream point/station elevation = 386.00(Ft.)
Downstream point/station elevation = 373.25(Ft.)
Pipe length = 218,46(Ft.) Manning's N = 0.013
NO. of pipes = 1 Required pipe flow = 138.933(CPS)
Given pipe size = 48.00(ln,)
Calculated individual pipe flow = 138,933(CFS)
Normal flow depth in pipe = 21,12(in,)
Flow top width inside pipe = 47,65(In,)
critical Depth = 42,00(ln,)
Pipe flow velocity = 26,08(Ft/s)
Travel time through pipe = 0,14 min.
Time of concentration (TC) = 7.43 min.
Process from Point/Station 113.000 to Point/Station
**** CONFLUENCE OF MINOR STREAMS ****
114,000
Along Main Stream number: 1 in normal stream number 1
Page 28
C605P1.OUT
Stream flow area = 41.260(Ac.)
Runoff from this stream = 138.933(CFS)
Time of concentration = 7,43 min.
Rainfall intensity = 5.713(ln/Hr)
Process from Point/Station 114.100 to Point/Station 114.200
**** INITIAL AREA EVALUATION ****
Decimal fraction soil group A = 0.000
Decimal fraction soil group B = 1.000
Decimal fraction soil group C = 0.000
Decimal fraction soil group D = 0.000
[INDUSTRIAL area type ]
Initial subarea flow distance = 100.00(Ft,)
Highest elevation = 409,50(Ft,)
Lowest elevation = 407,50(Ft.)
Elevation difference = 2,00(Ft,)
Time of concentration calculated by the urban
areas overland flow method (App X-C) = 3,57 min,
TC = [1.8*(l,l-C)*distanceA,5)/(% slopeA(l/3)]
TC = [l,8*(l,l-0,8500)*(100.00A.5)/( 2,00A(1/3)]= 3,57
Setting time of concentration to 5 minutes
RainfaTl intensity (I) = 7.377 for a 100,0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0,850
subarea runoff = 0.627(CFS)
Total initial stream area = 0.100(Ac,)
Process from Point/Station 114.200 to Point/Station 114.300
**** IMPROVED CHANNEL TRAVEL TIME ****
upstream point elevation = 407,50(Ft.)
Downstream point elevation = 403,00(Ft.)
Channel length thru subarea = 300.00(Ft.)
Channel base width = 0,000(Ft,)
Slope or 'Z' of left channel bank = 20.000
Slope or 'Z' of right channel bank = 20.000
Estimated mean flow rate at midpoint of channel = 12.541(CFS)
Manning's 'N' = 0.015
Maximum depth of channel = 1.000(Ft.)
Flow(q) thru subarea = 12.541(CFS)
Depth of flow = 0.392(Ft.), Average velocity = 4.088(Ft/s)
Channel flow top width = 15.666(Ft.)
Flow Velocity = 4.09(Ft/s)
Travel time = 1.22 min.
Time of concentration = 6.22 min.
Critical depth = 0.477(Ft.)
Adding area flow to channel
DecimaT fraction soil group A = 0.000
Decimal fraction soil group B = 1.000
Decimal fraction soil group C = 0.000
Decimal fraction soil group D = 0.000
[INDUSTRIAL area type ]
Rainfall intensity = 6.406(in/Hr) for a 100.0 year storm
Runoff coefficient used for sub-area, Rational method,Q=KCIA, C = 0.850
subarea runoff = 20,692(CPS) for 3,800(Ac,)
Total runoff = 21.319(CFS) Total area = 3.90(Ac.)
Page 29
m
C605P1.OUT
Process from Point/Station 114.300 to Point/Station 114.000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
Upstream point/station elevation = 391,10(Ft,)
Downstream point/station elevation = 374.92(Ft.)
Pipe length = 48.00(Ft.) Manning's N = 0,011
NO. of pipes = 1 Required pipe flow = 21,319(CFS)
Given pipe size = 24,00(ln.)
Calculated individual pipe flow = 21,319(CFS)
Normal flow depth in pipe = 6,01(in.) Flow top width inside pipe = 20,79(In.)
Critical Depth = 19.82(in.)
Pipe flow velocity = 34.64(Ft/s)
Travel time through pipe = 0.02 min.
Time of concentration (TC) = 6.25 min.
++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 114,300 to Point/Station 114,000
**** CONFLUENCE OF MINOR STREAMS ****
Along Main Stream number: 1 in normal stream number 2
Stream flow area = 3,900(Ac)
Runoff from this stream = 21.319(CPS)
Time of concentration = 6.25 min.
Rainfall intensity = 6,391(ln/Hr)
Summary of stream data:
Stream Flow rate TC Rainfall Intensity
NO, (CPS) (min) (in/Hr)
1 138,933 7,43 5,713
2 21,319 6,25 6,391
Qmax(l) =
Qmax(2) =
1.000 * 1,000 * 138.933) +
0.894 * 1.000 * 21.319) + = 157.990
1.000 * 0.840 * 138.933) +
1.000 * 1.000 * 21,319) + = 138.081
Total of 2 streams to confluence:
Flow rates before confluence point:
138.933 21.319
Maximum flow rates at confluence using above data:
157.990 138,081
Area of streams before confluence:
41,260 3,900
Results of confluence:
Total flow rate = 157.990(CPS)
Time of concentration = 7,432 min.
Effective stream area after confluence = 45,160(Ac,)
Process from Point/Station 114,000 to Point/Station 115,000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
Upstream point/station elevation = 372,92(Ft,)
Downstream point/station elevation = 354,27(Ft,)
Pipe length = 329,68(Ft,) Manning's N = 0.013
No. of pipes = 1 Required pipe flow = 157.990(CFS)
Given pipe size = 48.00(in.)
Page 30
C605P1.OUT
calculated individual pipe flow = 157.990(CFS)
Normal flow depth in pipe = 22.92(in.)
Flow top width inside pipe = 47.95(in.)
Critical Depth = 43,84(in,)
Pipe flow velocity = 26,65(Ft/s)
Travel time through pipe = 0.21 min.
Time of concentration (TC) = 7,64 min.
process from Point/station 114,000 to Point/Station
**** CONFLUENCE OF MINOR STREAMS ****
115,000
Along Main Stream number: 1 in normal stream number 1
Stream flow area = 45.160(Ac,)
Runoff from this stream = 157,990(CFS)
Time of concentration = 7,64 min.
Rainfall intensity = 5,613(in/Hr)
Process from Point/Station 112,600 to Point/Station
**** INITIAL AREA EVALUATION ****
115,350
Decimal fraction soil group A = 0,000
Decimal fraction soil group B = 0,000
Decimal fraction soil group C = 0.000
Decimal fraction soil group D = 1,000
[INDUSTRIAL area type ]
Note: user entry of impervious value, Ap = 0,850
initial subarea flow distance = 100,00(Ft,)
Highest elevation = 404,50(Ft,)
Lowest elevation = 397,72(Ft,)
Elevation difference = 6,78(Ft,)
Time of concentration calculated by the urban
areas overland flow method (App X-C) = 1,93 min,
TC = [l,8*(l,l-C)*distanceA.5)/(% slopeA(l/3)]
TC = [l,8*(l,l-0,8972)*(100,00A,5)/( 6,78A(1/3)]= 1.93
Setting time of concentration to 5 minutes
RainfaTl intensity (l) = 7.377 for a 100.0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0.897
subarea runoff = 0.331(CFS)
Total initial stream area = 0.050(Ac.)
Process from Point/Station 115,350 to Point/Station
**** STREET FLOW TRAVEL TIME + SUBAREA FLOW ADDITION ****
Top of Street segment elevation = 397,720(Ft,)
End of Street segment elevation = 369.260(Ft.)
Length of street segment = 500.000(Ft,)
Height of curb above gutter flowline = 6.0(in.)
Width of half street (curb to crown) = 26.000(Ft.)
Distance from crown to crossfall grade break = 24.500(Ft.)
Slope from gutter to grade break (v/hz) = 0.094
Slope from grade break to crown (v/hz) = 0.020
Street flow is on [1] side(s) of the street
Distance from curb to property line = 10.000(Ft.)
Slope from curb to property line (v/hz) = 0,020
Gutter width = l,500(Ft,)
Gutter hike from flowline = l,330(ln.)
Manning's N in gutter = 0.0150
Page 31
115,300
C605P1,OUT
Manning's N from gutter to grade break = 0,0150
Manning's N from grade break to crown = 0.0150
Estimated mean flow rate at midpoint of street = 0,480(CFS)
Depth of flow = 0.142(Ft,), Average velocity = 3,125(Ft/s)
Streetflow hydraulics at midpoint or street travel:
Halfstreet flow width = 3,049(Ft,)
Flow velocity = 3,12(Ft/s)
TC = Travel time = 2,67 min
Adding area flow to street
DecimaT fraction soil group
Decimal fraction soil
Decimal fraction soil
Decimal fraction soil
[INDUSTRIAL area type
7,67 mm.
A = 0,000
group B = 0,000
group
group
= 0,000
= 1.000
]
Note: user entry of impervious value, Ap = 0,700
Rainfall intensity = 5,599(ln/Hr) for a 100.0 year storm
Runoff coefficient used for sub-area,
Subarea runoff = 3.724(CFS) for
Total runoff = 4.055(CPS) Total
Street flow at end of street = 4
Half street flow at end of street =
Depth of flow = 0.257(Ft,), Average velocity = 4.830(Ft/s)
Flow width (from curb towards crown)= 8.826(Ft.)
Rational method,Q=KCIA, C = 0.739
0.900(Ac.)
area = 0,95 (Ac)
055(CFS)
4,055(CFS)
++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 115.300 to Point/Station 115.000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
Upstream point/station elevation = 357.61(Ft,)
Downstream point/station elevation = 355,43(Ft.)
Pipe length = 43,25(Ft,) Manning's N = 0,013
NO, of pipes = 1 Required pipe flow = 4,055(CFS)
Given pipe size = 24,00(ln,)
Calculated individual pipe flow = 4.055(CPS)
Normal flow depth in pipe = 4,59(ln,)
Flow top width inside pipe = 18,87(In,)
Critical Depth = 8.48(ln.)
Pipe flow velocity = 9,68(Ft/s)
Travel time through pipe = 0.07 min.
Time of concentration (TC) = 7.74 min.
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 115.300 to Point/Station 115.000
**** CONFLUENCE OF MINOR STREAMS ****
Along Main Stream number: 1 in normal stream number 2
Stream flow area = 0.950(Ac,)
Runoff from this stream = 4,055(CFS)
Time of concentration = 7,74 min.
Rainfall intensity = 5.565(ln/Hr)
++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 112.100 to Point/Station 115.250
**** INITIAL AREA EVALUATION ****
Decimal fraction soil
Decimal fraction soil
Decimal fraction soil
Decimal fraction soil
[INDUSTRIAL area type
group A = 0.000
group B = 0.000
group
group
= 0,000
= 1,000
Page 32
C605P1.OUT
Note: user entry of impervious value, Ap = 0,700
Initial subarea flow distance = 100,00(Ft.)
Highest elevation = 405,90(Ft.)
Lowest elevation = 399.35(Ft,)
Elevation difference = 6,55(Ft,)
Time of concentration calculated by the urban
areas overland flow method (App x-C) = 3.47 min,
TC = [1.8*(l,l-C)*distanceA.5)/(% slopeA(l/3)]
TC = [1.8*(l,l-0,7389)*(100.00A.5)/( 6,55A(l/3)]= 3.47
Setting time of concentration to 5 minutes
RainfaTl intensity (I) = 7,377 for a 100,0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0,739
Subarea runoff = 0,164(CFS)
Total initial stream area = 0,030(Ac)
Process from Point/Station 115,250 to Point/Station 115,200
**** STREET FLOW TRAVEL TIME + SUBAREA FLOW ADDITION ****
Top of street segment elevation = 399.350(Ft,)
End of street segment elevation = 369,700(Ft,)
Length of street segment = 540,000(Ft,)
Height of curb above gutter flowline = 6,0(In.)
Width of half street (curb to crown) = 26,000(Ft,)
Distance from crown to crossfall grade break = 24,500(Ft,)
Slope from gutter to grade break (v/hz) = 0,094
Slope from grade break to crown (v/hz) = 0,020
Street flow is on [1] side(s) of the street
Distance from curb to property line = 10.000(Ft,)
Slope from curb to property line (v/hz) = 0,020
Gutter width = l,500(Ft,)
Gutter hike from flowline = l,330(in.)
Manning's N in gutter = 0.0150
Manning's N from gutter to grade break = 0.0150
Manning's N from grade break to crown = 0.0150
Estimated mean flow rate at midpoint of street = 0.223(CPS)
Depth of flow = 0.104(Ft,), Average velocity = 3,071(Ft/s)
Streetflow hydraulics at midpoint or street travel:
Halfstreet flow width = 1.500(Ft.)
Flow velocity = 3.07(Ft/s)
Travel time = 2,93 min. TC = 7,93 min.
Adding area flow to street
DecimaT fraction soil group A = 0.000
Decimal fraction soil group B = 0.000
Decimal fraction soil group C = 0,000
Decimal fraction soil group D = 1.000
[INDUSTRIAL area type ]
Note: user entry of impervious value, Ap = 0,700
Rainfall intensity = 5,479(ln/Hr) for a 100.0 year storm
Runoff coefficient used for sub-area. Rational method,Q=KCIA, C = 0,739
subarea runoff = 2.955(CFS) for 0,730(Ac,)
Total runoff = 3,119(CFS) Total area = 0.76(Ac.)
Street flow at end of street = 3.119(CFS)
Half street flow at end of street = 3.119(CFS)
Depth of flow = 0.240(Ft.), Average velocity = 4.478(Ft/s)
Flow width (from curb towards crown)= 7.974(Ft.)
Process from Point/Station 115.200 to Point/Station 115.000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
Page 33
C605P1.OUT
upstream point/station elevation = 356,77(Ft,)
Downstream point/station elevation = 356.24(Ft.)
Pipe length = 5,25(Ft.) Manning's N = 0.013
No. of pipes = 1 Required pipe flow = 3.119(CFS)
Given pipe size = 18,00(ln.)
Calculated individual pipe flow = 3,119(CPS)
Normal flow depth in pipe = 3,72(in,)
Flow top width inside pipe = 14,57(in,)
Critical Depth = 8,06(ln.)
Pipe flow velocity = 11,84(Ft/s)
Travel time through pipe = 0.01 min.
Time of concentration (TC) = 7.94 min.
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++^
Process from Point/station 115,200 to Point/Station 115,000
**** CONFLUENCE OF MINOR STREAMS ****
Along Main Stream number: 1 in normal stream number 3
Stream flow area = 0,760(Ac.)
Runoff from this stream = 3,119(CFS)
Time of concentration = 7,94 min.
Rainfall intensity = 5,476(ln/Hr)
Summary of stream data:
Stream
No.
Flow rate
(CPS) TC
(min)
Rainfall Intensity
(in/Hr)
1
2
3
Qmax(l)
157.990
4,055
3.119
Qmax(2) =
Qmax(3) =
1.000
1.000
1.000
0.991
000
000
0,976
0,984
1.000
,64
,74
,94
1,000
0,987
0,962
1,000
1,000
0,975
1,000
1,000
1.000
5.613
5.565
5,476
157.990) +
4.055) +
3.119) +
157.990) +
4.055) +
3.119) +
157.990) +
4.055) +
3.119) +
164.992
163.726
161.231
Total of 3 streams to confluence:
Flow rates before confluence point:
157.990 4.055 3.119
Maximum flow rates at confluence using above data:
164.992 163.726 161.231
Area of streams before confluence:
45.160 0.950 0.760
Results of confluence:
Total flow rate = 164.992(CPS)
Time of concentration = 7.638 min.
Effective stream area after confluence = 46.870(Ac.)
Process from Point/Station 115,000 to Point/Station **** PIPEFLOW TRAVEL TIME (User specified size) **** 116,000
Upstream point/station elevation = 354.27(Ft.)
Page 34
C605P1,OUT
Downstream point/station elevation = 352,00(Ft.)
Pipe length = 40.47(Ft.) Manning's N = 0,013
NO, of pipes = 1 Required pipe flow = 164,992(CPS)
Given pipe size = 48,00(ln,)
Calculated individual pipe flow = 164.992(CPS)
Normal flow depth in pipe = 23.58(ln,)
Plow top width inside pipe = 47.99(ln.)
Critical Depth = 44,36(ln,)
Pipe flow velocity = 26,87(Ft/s)
Travel time through pipe = 0.03 min.
Time of concentration (TC) = 7.66 min.
process from Point/Station 115.000 to Point/Station 116.000
**** CONFLUENCE OF MAIN STREAMS ****
The following data inside Main Stream is listed:
In Main Stream number: 1
Stream flow area = 46.870(Ac)
Runoff from this stream = 164,992(CPS)
Time of concentration = 7.66 min.
Rainfall intensity = 5.601(ln/Hr)
Program is now starting with Main Stream No, 2
Process from Point/Station 2401,000 to Point/Station 2402.000
**** INITIAL AREA EVALUATION ****
Decimal fraction soil group A = 0,000
Decimal fraction soil group B = 1,000
Decimal fraction soil group C = 0,000
Decimal fraction soil group D = 0.000
[INDUSTRIAL area type ]
initial subarea flow distance = 100,00(Ft,)
Highest elevation = 398,00(Ft,)
Lowest elevation = 397,00(Ft,)
Elevation difference = 1.00(Ft,)
Time of concentration calculated by the urban
areas overland flow method (App X-C) = 4.50 min,
TC = [1.8*(l,l-C)*distanceA,5)/(% slopeA(l/3)]
TC = [l,8*(l,l-0,8500)*(100.00A,5)/( 1.00A(l/3)]= 4.50
Settinq time of concentration to 5 minutes
RainfaTl intensity (l) = 7.377 for a 100.0 year storm
Effective runoff coefficient used for area (Q=KCIA) is c = 0.850
subarea runoff = 0.627(CFS)
Total initial stream area = 0.100(Ac.)
Process from Point/Station 2402.000 to Point/Station 2403.000
**** IMPROVED CHANNEL TRAVEL TIME ****
upstream point elevation = 397,00(Ft,)
Downstream point elevation = 390,00(Ft.)
Channel length thru subarea = 330.00(Ft.)
Channel base width = 0.000(Ft.)
Slope or 'Z' of left channel bank = 20.000
Slope or 'Z' of right channel bank = 20.000
Estimated mean flow rate at midpoint of channel = 3.449(CFS)
Manning's 'N' =0.015
Maximum depth of channel = 1.000(Ft.)
Page 35
C605P1.OUT
Flow(q) thru subarea = 3.449(CFS)
Depth of flow = 0,226(Ft,), Average velocity =
Channel flow top width = 9.047(Ft,)
Flow Velocity = 3,37(Ft/s)
Travel time = 1,63 min.
Time of concentration = 6.63 min.
Critical depth = 0.283(Ft.)
Adding area flow to channel
3.371(Ft/s)
DecimaT fraction soil group
Decimal fraction soil group
Decimal fraction soil group
Decimal fraction soil group
[INDUSTRIAL area type
Rainfall intensity = 6,
Runoff coefficient used for
Subarea runoff =
Total runoff =
A =
B =
C =
D =
.000
,000
,000
,000
] 149(ln/Hr) for a
sub-area. Rational
4.704(CFS) for 0.90O(AC.)
331(CFS) Total area =
100.0 year storm
method,Q=KCIA, C = 0.850
1.00(Ac.)
Process from Point/Station 2403,000 to Point/Station 2403.000
**** SUBAREA FLOW ADDITION ****
Decimal fraction soil group A = 0,000
Decimal fraction soil group B = 1,000
Decimal fraction soil group C = 0,000
Decimal fraction soil group D = 0,000
[INDUSTRIAL area type
Time of concentration
Rainfall intensity =
]
6,63 min,
6,149(ln/Hr) for a 100.0 year storm
Runoff coefficient used for sub-area. Rational method,Q=KCIA, c = 0,850
Subarea runoff = 10,453(CPS) for 2,000(Ac.)
Total runoff = 15,784(CFS) Total area = 3,00(Ac,)
Process from Point/Station 2403,000 to Point/Station
**** PIPEFLOW TRAVEL TIME (User specified size) **** 2404,000
Upstream point/station elevation = 380,00(Ft.)
Downstream point/station elevation = 372.00(Ft.)
Pipe length = 450.00(Ft.) Manning's N = 0.013
No. of pipes = 1 Required pipe flow = 15.784(CPS)
Given pipe size = 30.00(ln.)
Calculated individual pipe flow = 15,784(CFS)
Normal flow depth in pipe = ll,04(ln,)
Flow top width inside pipe = 28,94(in.)
Critical Depth = 16.10(in.)
Pipe flow velocity = 9.64(Ft/s)
Travel time through pipe = 0.78 min.
Time of concentration (TC) = 7.41 min.
Process from Point/Station 2404.000 to Point/Station
**** SUBAREA FLOW ADDITION ****
2404.000
Decimal fraction soil
Decimal fraction soil
Decimal fraction soil
Decimal fraction soil
[INDUSTRIAL area type
Time of concentration
group A
group B
group C
group D
0.000
1.000
0,000
0,000
7.41 min.
Page 36
C605P1.OUT
Rainfall intensity = 5.724(ln/Hr) for a 100.0 year storm
Runoff coefficient used for sub-area. Rational method,Q=KCIA, C = 0.850
Subarea runoff = 15.910(CFS) for 3.270(Ac,)
Total runoff = 31.694(CFS) Total area = 6.27(Ac,)
Process from Point/Station 2404,000 to Point/Station 2304,000
**** PIPEFLOW TRAVEL TIME (user specified size) ****
upstream point/station elevation = 369,88(Ft,)
Downstream point/station elevation = 367.86(Ft,)
Pipe length = 100,90(Ft.) Manning's N = 0,011
NO, of pipes = 1 Required pipe flow = 31,694(CPS)
Given pipe size = 30.00(ln,)
Calculated individual pipe flow = 31,694(CFS)
Normal flow depth in pipe = 14,32(In,)
Flow top width inside pipe = 29,97(in.)
Critical Depth = 22,99(ln.)
Pipe flow velocity = 13.69(Ft/s)
Travel time through pipe = 0.12 min.
Time of concentration (TC) = 7,53 min.
Process from Point/Station 2404,000 to Point/Station 2304,000
**** CONFLUENCE OF MINOR STREAMS ****
Along Main Stream number: 2 in normal stream number 1
Stream flow area = 6.270(Ac,)
Runoff from this stream = 31,694(CFS)
Time of concentration = 7,53 min.
Rainfall intensity = 5,664(ln/Hr)
Process from Point/Station 2301.000 to Point/Station
**** INITIAL AREA EVALUATION ****
2302.000
group A
group B
group C
group D
0,000
1,000
0,000
0,000
= 100,00(Ft,)' ]
Decimal fraction soil
Decimal fraction soil
Decimal fraction soil
Decimal fraction soil
[INDUSTRIAL area type
Initial subarea flow distance
Highest elevation = 390,00(Ft,)
Lowest elevation = 388,00(Ft.)
Elevation difference = 2.00(Ft,)
Time of concentration calculated by the urban
areas overland flow method (App x-c) = 3,57 min,
TC = [l,8*(l,l-C)*distanceA.5)/(% slopeA(l/3)]
TC = [l,8*(l,l-0,8500)*(100,00A.5)/( 2.00A(1/3)]= 3.57
Setting time of concentration to 5 minutes
RainfaTl intensity (I) = 7.377 for a 100.0 year storm
Effective runoff coefficient used for area (Q=KCIA) is c = 0.850
Subarea runoff = 0,627(CFS)
Total initial stream area = 0.100(Ac.)
Process from Point/Station 2302.000 to Point/Station
**** IMPROVED CHANNEL TRAVEL TIME ****
2303.000
Page 37
C605P1.OUT
Upstream point elevation = 388.00(Ft.)
Downstream point elevation = 385.00(Ft.)
Channel length thru subarea = 430.00(Ft.)
Channel base width = 0.000(Ft,)
Slope or 'Z' of left channel bank = 20,000
Slope or 'Z' of right channel bank = 20.000
Estimated mean flow rate at midpoint of channel
Manning's 'N' =0,015
Maximum depth of channel = 1.000(Ft,)
Flow(q) thru subarea = 9,720(CFS)
Depth of flow = 0,411(Ft,), Average velocity
Channel flow top width = 16.435(Ft.)
Flow Velocity = 2.88(Ft/s)
Travel time = 2,49 min.
Time of concentration = 7.49 min.
Critical depth = 0.430(Ft.)
Adding area flow to channel
DecimaT fraction soil group A
group B
group C
group D
9.720(CFS)
2.879(Ft/s)
0.000
1.000
0.000
0.000
Decimal fraction soil Decimal fraction soil
Decimal fraction soil
[INDUSTRIAL area type ] Rainfall intensity = 5,685(ln/Hr) for a 100.0 year storm
Runoff coefficient used for sub-area. Rational method,Q=KCiA, C = 0.850
subarea runoff = 14.013(CFS) for 2.900(Ac.)
Total runoff = 14,640(CFS) Total area = 3.00(Ac,)
++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 2303,000 to Point/Station 2303.000
**** SUBAREA FLOW ADDITION ****
Decimal fraction soil group A = 0,000
Decimal fraction soil group B = 1.000
Decimal fraction soil group C = 0,000
Decimal fraction soil group D = 0,000
[INDUSTRIAL area type
Time of concentration
Rainfall intensity =
] 7,49 min,
5.685(ln/Hr) for a 100,0 year storm
Runoff coefficient used for sub-area, Rational method,Q=KCIA, C = 0,850
subarea runoff = 6.378(CFS) for 1.320(Ac.)
Total runoff = 21.018(CFS) Total area = 4,32(Ac,)
Process from Point/Station 2303,000 to Point/Station 2304,000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
upstream point/station elevation = 375,00(Ft,)
Downstream point/station elevation = 368.03(Ft.)
Pipe length = 42,37(Ft,) Manning's N = 0,011
No, of pipes = 1 Required pipe flow = 21.018(CPS)
Given pipe size = 24,00(ln,)
calculated individual pipe flow = 21.018(CPS)
Normal flow depth in pipe = 7.16(in,)
Flow top width inside pipe = 21.96(ln,)
critical Depth = 19,71(in,)
Pipe flow velocity = 26.71(Ft/s)
Travel time through pipe = 0.03 min.
Time of concentration (TC) = 7.52 min.
Page 38
•
C605P1.OUT
Process from Point/Station 2303.000 to Point/Station
**** CONFLUENCE OF MINOR STREAMS ****
2304.000
Along Main Stream number: 2 in normal stream number 2
Stream flow area = 4.320(Ac.)
Runoff from this stream = 21,018(CFS)
Time of concentration = 7.52 min.
Rainfall intensity = 5.672(ln/Hr)
Summary of stream data:
Stream
NO,
Flow rate
(CFS)
TC
(min)
Rainfall Intensity
(in/Hr)
1
2
Qmax(l)
31.694
21,018
Qmax(2) =
1,000
0.999
.000
.000
7,
7,
53
52
1,
1
000
000
0.998
1.000
5,664
5.672
31,694) +
21.018) +
31,694) +
21,018) +
52,683
52.643
Total of 2 streams to confluence:
Flow rates before confluence point:
31,694 21.018
Maximum flow rates at confluence using above data:
52,683 52,643
Area of streams before confluence:
6,270 4,320
Results of confluence:
Total flow rate = 52,683(CFS)
Time of concentration = 7,532 min.
Effective stream area after confluence = 10.590(Ac,)
Process from Point/Station 2304,000 to Point/Station
**** PIPEFLOW TRAVEL TIME (User specified size) ****
upstream point/station elevation = 367,53(Ft,)
Downstream point/station elevation = 354,89(Ft.)
Pipe length = 252,70(Ft.) Manning's N = 0.013
No. of pipes = 1 Required pipe flow = 52.683(CFS)
Given pipe size = 30.00(ln.)
Calculated individual pipe flow = 52.683(CPS)
Normal flow depth in pipe = 16.30(ln.)
Flow top width inside pipe = 29.89(ln.)
critical Depth = 27.96(ln.)
Pipe flow velocity = 19.33(Ft/s)
Travel time through pipe = 0.22 min.
Time of concentration (TC) = 7.75 min.
2405.000
Process from Point/Station 2304.000 to Point/Station
**** CONFLUENCE OF MINOR STREAMS ****
2405.000
Along Main stream number: 2 in normal stream number 1
Stream flow area = 10.590(Ac,)
Runoff from this stream = 52.683(CPS)
Time of concentration = 7.75 min.
Rainfall intensity = 5.561(In/Hr)
Page 39
#
C605P1.OUT
process from Point/Station 2411,000 to Point/Station 2412.000
**** INITIAL AREA EVALUATION ****
Decimal fraction soil group A = 0,000
Decimal fraction soil group B = 1.000
Decimal fraction soil group C = 0,000
Decimal fraction soil group D = 0,000
[INDUSTRIAL area type ]
Initial subarea flow distance = 93,00(Ft.)
Highest elevation = 383.18(Ft.)
Lowest elevation = 381.46(Ft.)
Elevation difference = 1.72(Ft.)
Time of concentration calculated by the urban
areas overland flow method (App X-C) = 3,54 min.
TC = [1.8*(l,l-C)*distanceA,5)/(% slopeA(l/3)]
TC = [1.8*(l,l-0,8500)*( 93,OOA.5)/( 1.85A(l/3)]= 3.54
setting time of concentration to 5 minutes
RainfaTl intensity (I) = 7.377 for a 100.0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0,850
Subarea runoff = 0.063(CPS)
Total initial stream area = 0,010(Ac,)
Process from Point/Station 2412,000 to Point/Station 2413,000
**** STREET FLOW TRAVEL TIME + SUBAREA FLOW ADDITION ****
Top of street segment elevation = 381,460(Ft,)
End of street segment elevation = 366.000(Ft,)
Length of street segment = 295.000(Ft.)
Height of curb above gutter flowline = 6,0(ln.)
width of half street (curb to crown) = 26.000(Ft,)
Distance from crown to crossfall grade break = 24.500(Ft,)
Slope from gutter to grade break (v/hz) = 0,020
Slope from grade break to crown (v/hz) = 0,020
Street flow is on [1] side(s) of the street
Distance from curb to property line = 10,000(Ft,)
Slope from curb to property line (v/hz) = 0,020
Gutter width = 1.500(Ft.)
Gutter hike from flowline = l,500(in,)
Manning's N in gutter = 0.0150
Manning's N from gutter to grade break = 0.0150
Manning's N from grade break to crown = 0.0150
Estimated mean flow rate at midpoint of street = 0.077(CFS)
Depth of flow = 0.074(Ft.), Averaqe velocity = 2.373(Ft/s)
streetflow hydraulics at midpoint of street travel:
Halfstreet flow width = 1.500(Ft.)
Flow velocity = 2.37(Ft/s)
Travel time = 2.07 min. TC = 7.07 min.
Adding area flow to street
DecimaT fraction soil group A = 0.000
Decimal fraction soil group B = 1,000
Decimal fraction soil group C = 0,000
Decimal fraction soil group D = 0,000
[INDUSTRIAL area type ]
Rainfall intensity = 5.899(in/Hr) for a 100,0 year storm
Runoff coefficient used for sub-area. Rational method,Q=KCIA, C = 0.850
Subarea runoff = 2.307(CFS) for 0.460(Ac.)
Total runoff = 2.369(CPS) Total area = 0.47(Ac.)
Street flow at end of street = 2.369(CFS)
Page 40
•
c605Pl,OUT
Half street flow at end of street = 2,369(CFS)
Depth of flow = 0,236(Ft,), Average velocity = 4,145(Ft/s)
Flow width (from curb towards crown)= 7.074(Ft.)
++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 2413,000 to Point/Station 2504.000
**** PIPEFLOW TRAVEL TIME (user specified size) ****
upstream point/station elevation = 356.37(Ft,)
Downstream point/station elevation = 355,89(Ft,)
Pipe length = 4,75(Ft.) Manning's N = 0.013
NO, of pipes = 1 Required pipe flow = 2,369(CFS)
Given pipe size = 18,00(ln,)
Calculated individual pipe flow = 2.369(CPS)
Normal flow depth in pipe = 3,25(In,)
Flow top width inside pipe = 13,84(in.)
Critical Depth = 6.99(ln.)
Pipe flow velocity = 10.92(Ft/s)
Travel time through pipe = 0.01 min.
Time of concentration (TC) = 7,08 min,
++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 2413,000 to Point/Station 2504,000
**** CONFLUENCE OF MINOR STREAMS ****
Along Main Stream number: 2 in normal stream number 2
stream flow area = 0,470(Ac,)
Runoff from this stream = 2,369(CFS)
Time of concentration = 7,08 min.
Rainfall intensity = 5.895(ln/Hr)
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++
process from Point/Station 2411.000 to Point/Station 2414.000
**** INITIAL AREA EVALUATION ****
Decimal fraction soil group A = 0.000
Decimal fraction soil group B = 1.000
Decimal fraction soil group C = 0.000
Decimal fraction soil group D = 0.000
[INDUSTRIAL area type ]
Initial subarea flow distance = 74.00(Ft.)
Highest elevation = 383.18(Ft.)
Lowest elevation = 381.46(Ft.)
Elevation difference = 1.72(Ft.)
Time of concentration calculated by the urban areas overland flow method (App x-C) = 2.92 min.
TC = [1.8*(l.l-C)*distanceA.5)/(% slopeA(l/3)]
TC = [1.8*(l.l-0.8500)*( 74,00A.5)/( 2,32A(l/3)]= 2.92
Setting time of concentration to 5 minutes
RainfaTl intensity (I) = 7.377 for a 100.0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0.850
Subarea runoff = 0,063(CPS)
Total initial stream area = 0.010(Ac.)
Process from Point/Station 2414.000 to Point/Station 2415.000
**** STREET FLOW TRAVEL TIME + SUBAREA FLOW ADDITION ****
Top of Street segment elevation = 381.460(Ft.)
Page 41
m C605P1.OUT
End of street segment elevation = 366.000(Ft.)
Length of street segment = 280,000(Ft,)
Height of curb above gutter flowline = 6,0(in,)
width of half street (curb to crown) = 26.000(Ft.)
Distance from crown to crossfall grade break = 24.500(Ft.)
Slope from gutter to grade break (v/hz) = 0,020
Slope from grade brealc to crown (v/hz) = 0,020
Street flow is on [1] side(s) of the street
Distance from curb to property line = 10.000(Ft.)
Slope from curb to property line (v/hz) = 0.020
Gutter width = l,500(Ft,)
Gutter hike from flowline = l,500(ln,)
Manning's N in gutter = 0.0150
Manning's N from gutter to grade break = 0.0150
Manning's N from grade breaR to crown = 0.0150
Estimated mean flow rate at midpoint of street = 0.075(CFS)
Depth of flow = 0.072(Ft.), Average velocity = 2.400(Ft/s)
Streetflow hydraulics at midpoint of street travel:
Halfstreet flow width = 1.500(Ft.)
Flow velocity = 2.40(Ft/s)
Travel time = 1,94 min, TC = 6,94 min.
Adding area flow to street
DecimaT fraction soil group A = 0.000
Decimal fraction soil group B = 1.000
Decimal fraction soil group C = 0.000
Decimal fraction soil group D = 0.000
[INDUSTRIAL area type ]
Rainfall intensity = 5.969(in/Hr) for a 100.0 year storm
Runoff coefficient used for sub-area. Rational method,Q=KCIA, C = 0.850
Subarea runoff = 1.928(CPS) for 0.380(Ac.)
Total runoff = 1.991(CFS) Total area = 0.39(Ac.)
Street flow at end of street = 1.991(CFS)
Half street flow at end of street = 1.991(CFS)
Depth of flow = 0.224(Ft,), Average velocity = 4,069(Ft/s)
Flow width (from curb towards crown)= 6.466(Ft,)
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 2415,000 to Point/Station 2405,000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
Upstream point/station elevation = 358,03(Ft.)
Downstream point/station elevation = 355.89(Ft.)
Pipe length = 42.75(Ft.) Manning's N = 0.013
No. of pipes = 1 Required pipe flow = 1.991(CFS)
Given pipe size = 18.00(ln.)
Calculated individual pipe flow = 1.991(CFS)
Normal flow depth in pipe = 3.54(ln.)
Flow top width inside pipe = 14.31(in.)
Critical Depth = 6.37(ln.)
Pipe flow velocity = 8.10(Ft/s)
Travel time through pipe = 0.09 min.
Time of concentration (TC) = 7.03 min.
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 2415,000 to Point/Station 2405,000
**** CONFLUENCE OF MINOR STREAMS ****
Along Main Stream number: 2 in normal stream number 3
Stream flow area = 0,390(Ac.)
Runoff from this stream = 1.991(CFS)
Time of concentration = 7.03 min.
Page 42
Rainfall intensity =
Summary of stream data:
C605P1.OUT
5.921(ln/Hr)
Stream
NO.
Flow rate
(CPS)
TC
(min)
Rainfall Intensity
(in/Hr)
1
2
3
Qmax(l)
Qmax(2) =
Qmax(3) =
683 7 75
369 7 08
991 7 03
1,000 * 1.000 *
0.943 * 1,000 *
0,939 * 1,000 *
1.000 * 0.913 *
1,000 * 1,000 *
0,996 * 1,000 *
1.000 * 0,907 *
1.000 * 0.993 *
1.000 * 1.000 *
5,561
5,895
5.921
52.683) +
2,369) +
1.991) +
52,683) +
2.369) +
1.991) +
52,683) +
2.369) +
1,991) +
56.787
52.470
52.145
Total of 3 streams to confluence:
Flow rates before confluence point:
52.683 2,369 1.991
Maximum flow rates at confluence using above data:
56,787 52,470 52,145
Area of streams before confluence:
10.590 0,470 0,390
Results of confluence:
Total flow rate = 56.787(CPS)
Time of concentration = 7.750 min.
Effective stream area after confluence = 11.450(Ac.)
process from Point/Station 2405.000 to Point/Station 116,000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
Upstream point/station elevation = 354,39(Ft.)
Downstream point/station elevation = 352.50(Ft.)
Pipe length = 37.79(Ft.) Manning's N = 0,013
No. of pipes = 1 Required pipe flow = 56.787(CFS)
Given pipe size = 36.00(ln.)
Calculated individual pipe flow = 56.787(CFS)
Normal flow depth in pipe = 15.40(in.)
Plow top width inside pipe = 35.62(in.)
critical Depth = 29.31(ln.)
Pipe flow velocity = 19.67(Ft/s)
Travel time through pipe = 0.03 min.
Time of concentration (TC) = 7.78 min.
Process from Point/Station 2405.000 to Point/Station
**** CONFLUENCE OF MAIN STREAMS ****
116.000
The following data inside Main Stream is listed:
In Main stream number: 2
Stream flow area = 11.450(Ac.)
Runoff from this stream = 56.787(CFS)
Time of concentration = 7.78 min.
Page 43
Rainfall intensity =
Summary of stream data;
Stream
NO.
Flow rate
(CPS)
C605P1.OUT
.546(ln/Hr)
TC
(min)
Rainfall intensity
(in/Hr)
•
1
2
164,992
56,787
Qmax(l) =
Qmax(2) =
1,000 *
1,000 *
0,990 *
1.000 *
,66
.78
1,000
0.985
1,000
1.000
5.601
5,546
164,992) +
56.787) +
164.992) +
56.787) +
220.912
220.150
Total of 2 main streams to confluence:
Flow rates before confluence point:
164,992 56,787
Maximum flow rates at confluence using above data:
220,912 220,150
Area of streams before confluence:
46,870 11,450
Results of confluence:
Total flow rate = 220,912(CPS)
Time of concentration = 7,663 min.
Effective stream area after confluence = 58,320(Ac,)
Process from Point/Station 116.000 to Point/Station
**** PIPEFLOW TRAVEL TIME (User specified size) ****
116.500
upstream point/station elevation = 351,00(Ft.)
Downstream point/station elevation = 341,90(Ft.)
Pipe length = 218,77(Ft,) Manning's N = 0.013
NO. of pipes = 1 Required pipe flow = 220.912(CPS)
Given pipe size = 54.00(in.)
Calculated individual pipe flow = 220.912(CPS)
Normal flow depth in pipe = 28.59(in.)
Flow top width inside pipe = 53.91(ln.)
critical Depth = 49.91(ln,)
Pipe flow velocity = 25,82(Ft/s)
Travel time through pipe = 0,14 min.
Time of concentration (TC) = 7,80 min.
Process from Point/Station 116.000 to Point/Station
**** CONFLUENCE OF MINOR STREAMS ****
116,500
Along Main Stream number: 1 in normal stream number 1
Stream flow area = 58,320(Ac,)
Runoff from this stream = 220,912(CPS)
Time of concentration = 7.80 min.
Rainfall intensity = 5.536(in/Hr)
Process from Point/Station 115,100 to Point/Station
**** INITIAL AREA EVALUATION ****
Page 44
c605Pl,OUT
Decimal fraction soil group A = 0.000
Decimal fraction soil group B = 0,000
Decimal fraction soil group C = 0,000
Decimal fraction soil group D = 1,000
[INDUSTRIAL area type ]
Note: user entry of impervious value, Ap = 0.850
Initial subarea flow distance = 26,00(Ft,)
Highest elevation = 369,76(Ft.)
Lowest elevation = 369.26(Ft,)
Elevation difference = 0.50(Ft,)
Time of concentration calculated by the urban
areas overland flow method (App X-C) = 1,50 min.
TC = [1.8*(l.l-C)*distanceA,5)/(% slopeA(l/3)]
TC = [1.8*(l,l-0.8972)*( 26,00A,5)/( l,92A(l/3)]= 1.50
Setting time of concentration to 5 minutes
RainfaTl intensity (I) = 7.377 for a 100.0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0,897
subarea runoff = 0,066(CFS)
Total initial stream area = 0,010(Ac,)
++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 115.200 to Point/Station 116,600
**** STREET FLOW TRAVEL TIME + SUBAREA FLOW ADDITION ****
Top of Street segment elevation = 369,260(Ft,)
End of street segment elevation = 358,870(Ft,)
Length of street segment = 305,000(Ft,)
Height of curb above gutter flowline = 6.0(in.)
width of half street (curb to crown) = 26,000(Ft.)
Distance from crown to crossfall grade break = 24,500(Ft,)
Slope from gutter to grade break (v/hz) = 0,094
Slope from grade break to crown (v/hz) = 0,020
Street flow is on [1] side(s) of the street
Distance from curb to property line = 10,000(Ft,)
slope from curb to property line (v/hz) = 0,020
Gutter width = l,200(Ft,)
Gutter hike from flowline = l,330(ln,)
Manning's N in gutter = 0,0150
Manning's N from gutter to grade break = 0,0150
Manning's N from grade break to crown = 0,0150
Estimated mean flow rate at midpoint of street = 0,080(CPS)
Depth of flow = 0,084(Ft.), Average velocity = 2.082(Ft/s)
Streetflow hydraulics at midpoint of street travel:
Halfstreet flow width = 1.200(Ft.)
Flow velocity = 2.08(Ft/s)
Travel time = 2.44 min. TC = 7.44 min.
Adding area flow to street
DecimaT fraction soil group A = 0.000
Decimal fraction soil group B = 0.000
Decimal fraction soil group c = 0.000
Decimal fraction soil group D = 1.000
[INDUSTRIAL area type ]
Note: user entry of impervious value, Ap = 0.850
Rainfall intensity = 5.708(ln/Hr) for a 100.0 year storm
Runoff coefficient used for sub-area, Rational method,Q=KCIA, C = 0.897
Subarea runoff = 2.151(CFS) for 0.420(Ac)
Total runoff = 2.217(CPS) Total area = 0.43(Ac.)
Street flow at end of street = 2.217(CPS)
Half street flow at end of street = 2.217(CFS)
Depth of flow = 0,258(Ft,), Average velocity = 3.470(Ft/s)
Flow width (from curb towards crown)= 7.463(Ft.)
Page 45
C605P1.OUT
Process from Point/Station 116,600 to Point/Station
**** PIPEFLOW TRAVEL TIME (User Specified size) ****
116.500
Upstream point/station elevation = 344,00(Ft,)
Downstream point/station elevation = 343,40(Ft.)
Pipe length = 5.25(Ft.) Manning's N = 0,013
No, of pipes = 1 Required pipe flow = 2,217(CFS)
Given pipe size = 18,00(ln.)
Calculated individual pipe flow = 2.217(CFS) Normal flow depth in pipe = 3,05(in,)
Flow top width inside pipe = 13.50(ln.)
Critical Depth = 6.75(ln,)
Pipe flow velocity = 11.19(Ft/s)
Travel time through pipe = 0.01 min.
Time of concentration (TC) = 7.45 min.
process from Point/station 116,600 to Point/Station 116,500
**** CONFLUENCE OF MINOR STREAMS ****
Along Main Stream number: 1 in normal stream number 2
Stream flow area = 0,430(Ac.)
Runoff from this stream = 2.217(CPS)
Time of concentration = 7,45 min.
Rainfall intensity = 5,705(ln/Hr)
Summary of stream data:
Stream
No.
Flow rate
(CPS) TC
(min)
Rainfall intensity
(in/Hr)
1 220.912 7.80
2 2,217 7,45
Qmax(l) =
1,000 * 1,000 *
0,970 * 1,000 *
Qmax(2) =
1,000 * 0.954 *
1,000 * 1,000 *
5,536
5,705
220,912) +
2,217) +
220,912) +
2,217) +
223,064
213,063
Total of 2 streams to confluence:
Flow rates before confluence point:
220,912 2,217
Maximum flow rates at confluence using above data:
223,064 213.063
Area of streams before confluence:
58,320 0,430
Results of confluence:
Total flow rate = 223.064(CFS)
Time of concentration = 7.805 min.
Effective stream area after confluence = 58.750(Ac,)
Process from Point/Station 116.500 to Point/Station 117.000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
Upstream point/station elevation = 341.90(Ft.)
Downstream point/station elevation = 341.00(Ft.)
Page 46
m C605P1.OUT
Pipe length = 21.58(Ft.) Manning's N = 0.013
No, of pipes = 1 Required pipe flow = 223,064(CFS)
Given pipe size = 54,00(in.)
Calculated individual pipe flow = 223.064(CFS)
Normal flow depth in pipe = 28,73(In,)
Flow top width inside pipe = 53.89(in.)
critical Depth = 49.99(in.)
Pipe flow velocity = 25.91(Ft/s)
Travel time through pipe = 0,01 min.
Time of concentration (TC) = 7,82 min.
Process from Point/Station 116,500 to Point/Station
**** CONFLUENCE OF MAIN STREAMS ****
117,000
The following data inside Main Stream is listed:
in Main Stream number: 1
Stream flow area = 58,750(Ac,)
Runoff from this stream = 223,064(CFS)
Time of concentration = 7.82 min.
Rainfall intensity = 5,529(in/Hr)
Program is now starting with Main Stream No, 2
Process from Point/Station
**** INITIAL AREA EVALUATION
2407,000 to Point/Station 2408.000 ****
Decimal fraction soil group A = 0,000
Decimal fraction soil group B = 1,000
Decimal fraction soil group C = 0,000
Decimal fraction soil group D = 0,000
[INDUSTRIAL area type ]
initial subarea flow distance = 200.00(Ft,)
Highest elevation = 399,00(Ft.)
Lowest elevation = 395,00(Ft,)
Elevation difference = 4,00(Ft,)
Time of concentration calculated by the urban
areas overland flow method (App X-C) = 5,05 min.
TC = [l,8*(l,l-C)*distanceA,5)/(% slopeA(l/3)]
TC = [l,8*(l,l-0,8500)*(200,OOA.5)/( 2,OOA(l/3)]= 5.05
Rainfall intensity (i) = 7.329 for a 100.0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0.850
subarea runoff = 0.623(CPS)
Total initial stream area = 0.100(Ac.)
process from Point/Station 2408,000 to Point/Station
*«** IMPROVED CHANNEL TRAVEL TIME ****
2409.000
395.00(Ft.)
390,00(Ft,)
350.00(Ft,)
0,000(Ft,)
bank = 20,000
Upstream point elevation =
Downstream point elevation =
Channel length thru subarea
Channel base width
Slope or 'Z' of left channel
Slope or 'Z' of right channel bank = 20.000
Estimated mean flow rate at midpoint of channel =
Manning's 'N' = 0.015
Maximum depth of channel = 1.000(Ft.)
Flow(q) thru subarea = 4,361(CFS)
Depth of flow = 0.266(Ft,), Average velocity =
Page 47
4.361(CFS)
3.082(Ft/s)
C605P1.OUT
Channel flow top width = 10.639(Ft.)
Flow velocity = 3.08(Ft/s)
Travel time = 1.89 min.
Time of concentration = 6.94 min,
critical depth = 0,313(Ft,)
Adding area flow to channel
DecimaT fraction soil group A = 0,000
Decimal fraction soil group B = 1.000
Decimal fraction soil group C = 0.000
Decimal fraction soil group D = 0,000
[INDUSTRIAL area type ]
Rainfall intensity = 5,969(in/Hr) for a 100,0 year storm
Runoff coefficient used for sub-area. Rational method,Q=KCIA, C = 0,850
Subarea runoff = 6.088(CFS) for l,200(Ac,)
Total runoff = 6,711(CFS) Total area = l,30(Ac.)
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 2409,000 to Point/Station 2410.000
**** PIPEFLOW TRAVEL TIME (User Specified size) ****
Upstream point/station elevation = 380,00(Ft.)
Downstream point/station elevation = 370,00(Ft,)
Pipe length = 500,00(Ft.) Manning's N = 0.013
NO, of pipes = 1 Required pipe flow = 6,711(CFS)
Given pipe size = 24,00(in,)
Calculated individual pipe flow = 6.711(CFS)
Normal flow depth in pipe = 7,46(ln,)
Flow top width inside pipe = 22.22(in.)
Critical Depth = 11.01(in.)
Pipe flow velocity = 8.06(Ft/s)
Travel time through pipe = 1.03 min.
Time of concentration (TC) = 7.98 min.
++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/station 2410,000 to Point/Station 2410,000
**** SUBAREA FLOW ADDITION ****
Decimal fraction soil group A = 0.000
Decimal fraction soil group B = 1,000
Decimal fraction soil group C = 0,000
Decimal fraction soil group D = 0,000
[INDUSTRIAL area type ]
Time of concentration = 7,98 min.
Rainfall intensity = 5.458(ln/Hr) for a 100.0 year storm
Runoff coefficient used for sub-area. Rational method,Q=KCIA, C = 0.850
Subarea runoff = 10.206(CFS) for 2.200(Ac.)
Total runoff = 16.918(CFS) Total area = 3. 50(Ac)
Process from Point/Station 2410.000 to Point/Station 123.000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
upstream point/station elevation = 370.00(Ft.)
Downstream point/station elevation = 364,00(Ft,)
Pipe length = 750,00(Ft,) Manning's N = 0,010
No, of pipes = 1 Required pipe flow = 16,918(CFS)
Given pipe size = 36,00(ln,)
calculated individual pipe flow = 16,918(CPS)
Normal flow depth in pipe = 11.43(in,)
Flow top width inside pipe = 33.51(ln.)
Page 48
C605P1.OUT
Critical Depth = 15.78(in.)
Pipe flow velocity = 8,78(Ft/s)
Travel time through pipe = 1,42 min.
Time of concentration (TC) = 9,40 min.
process from Point/Station 123,000 to Point/Station 123,000
**** SUBAREA FLOW ADDITION ****
Decimal fraction soil group A = 0,000
Decimal fraction soil group B = 1,000
Decimal fraction soil group C = 0,000
Decimal fraction soil group D = 0,000
[INDUSTRIAL area type ]
Time of concentration = 9.40 min.
Rainfall intensity = 4,909(in/Hr) for a 100.0 year storm
Runoff coefficient used for sub-area. Rational method,Q=KCIA, C = 0.850
subarea runoff = 36,556(CFS) for 8,760(Ac,)
Total runoff = 53,474(CFS) Total area = 12,26(Ac,)
Process from Point/Station 123,000 to Point/Station
**** PIPEFLOW TRAVEL TIME (User specified size) ****
117,000
upstream point/station elevation = 354.17(Ft.)
Downstream point/station elevation = 342.17(Ft.)
Pipe length = 60.00(Ft.) Manning's N = 0.013
NO. of pipes = 1 Required pipe flow = 53.474(CFS)
Given pipe size = 36.00(ln.)
calculated individual pipe flow = 53.474(CFS)
Normal flow depth in pipe = 10.32(In.)
Flow top width inside pipe = 32.56(ln.)
critical Depth = 28,49(ln,)
Pipe flow velocity = 31.95(Ft/s)
Travel time through pipe = 0.03 min.
Time of concentration (TC) = 9.43 min.
Process from Point/Station 123,000 to Point/Station
**** CONFLUENCE OF MAIN STREAMS ****
117,000
The following data inside Main Stream is listed:
in Main Stream number: 2
Stream flow area = 12,260(Ac)
Runoff from this stream = 53.474(CFS)
Time of concentration = 9.43 min.
Rainfall intensity = 4.899(in/Hr)
Program is now starting with Main stream No. 3
Process from Point/Station
**** INITIAL AREA EVALUATION
115.300 to
****
Point/Station 115.200
Decimal fraction
Decimal fraction
Decimal fraction
Decimal fraction
[INDUSTRIAL area
initial subarea
soil
soil
soil
soil
group
group
group
group
A
B
c
D
0.000
1.000
0.000
0,000
type
flow distance = 26.00(Ft.)
Page 49
]
C605P1.OUT
Highest elevation = 369,76(Ft,)
Lowest elevation = 369.26(Ft,)
Elevation difference = 0.50(Ft,)
Time of concentration calculated by the urban
areas overland flow method (App x-C) = 1,85 min,
TC = [l,8*(l,l-C)*distanceA.5)/(% slopeA(l/3)]
TC = [l,8*(l,l-0,8500)*( 26.00A,5)/( l,92A(l/3)]= 1,85
Setting time of concentration to 5 minutes
RainfaTl intensity (I) = 7,377 for a 100,0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0,850
subarea runoff = 0,063(CPS)
Total initial stream area = 0.010(Ac)
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++^
Process from Point/station 115.200 to Point/Station 121.000
**** STREET FLOW TRAVEL TIME + SUBAREA FLOW ADDITION ****
Top of Street segment elevation = 369,260(Ft,)
End of street segment elevation = 357,050(Ft,)
Length of street segment = 330,000(Ft,)
Height of curb above gutter flowline = 6,0(ln,)
width of half street (curb to crown) = 26,000(Ft,)
Distance from crown to crossfall grade break = 24.500(Ft,)
Slope from gutter to grade break (v/hz) = 0,020
Slope from grade break to crown (v/hz) = 0.020
Street flow is on [1] side(s) of the street
Distance from curb to property line = 10.000(Ft.)
Slope from curb to property line (v/hz) = 0.020
Gutter width = 1.500(Ft,)
Gutter hike from flowline = l,500(ln,)
Manning's N in gutter = 0.0150
Manning's N from gutter to grade break = 0.0150
Manning's N from grade break to crown = 0.0150
Estimated mean flow rate at midpoint of street =
Depth of flow = 0.081(Ft.), Averaqe velocity =
Streetflow hydraulics at midpoint of street travel:
Halfstreet flow width = 1.500(Ft.)
Flow velocity = 2.12(Ft/s)
0.083(CFS)
2.122(Ft/s)
Travel time = 2.59 min. TC = 7,59 min.
Adding area flow to street
DecimaT fraction soil group A = 0.000
Decimal fraction soil group B = 1.000
Decimal fraction soil group C = 0.000
Decimal fraction soil group D = 0.000
[INDUSTRIAL area type ]
Rainfall intensity = 5.635(ln/Hr) for a
Runoff coefficient used for sub-area, Rational method,Q=KCIA, C = 0.850
Subarea runoff = 3.113(CPS) for 0,650(Ac,)
Total runoff = 3.176(CFS) Total area = 0.66(Ac.)
Street flow at end of street = 3.176(CFS)
Half street flow at end of street = 3.176(CFS)
Depth of flow = 0.268(Ft.), Average velocity = 3.878(Ft/s)
Flow width (from curb towards crown)= 8.648(Ft.)
100.0 year storm
Process from Point/Station 121.000 to Point/Station 117.000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
Upstream point/station elevation = 344.92(Ft.)
Downstream point/station elevation = 342.67(Ft.)
Pipe length = 42.25(Ft.) Manning's N = 0.013
Page 50
m C605P1.OUT
No. of pipes = 1 Required pipe flow = 3.176(CFS)
Given pipe size = 30,00(ln.)
Calculated individual pipe flow = 3.176(CFS)
Normal flow depth in pipe = 3,76(ln.)
Flow top width inside pipe = 19,88(in.)
critical Depth = 7,01(ln,)
Pipe flow velocity = 8,92(Ft/s)
Travel time through pipe = 0,08 min.
Time of concentration (TC) = 7.67 min.
++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 121,000 to Point/Station 117,000
**** CONFLUENCE OF MAIN STREAMS ****
The following data inside Main Stream is listed;
In Main Stream number: 3
Stream flow area = 0,660(Ac,)
Runoff from this stream = 3,176(CFS)
Time of concentration = 7.67 min.
Rainfall intensity = 5,598(ln/Hr)
Summary of stream data:
Stream
No,
Flow rate
(CPS) TC
(min)
Rainfall intensity
(in/Hr)
1
2
3
Qmax(l)
223.064
53.474
3.176
Qmax(2) =
Qmax(3) =
7.82
9.43
7.67
1, 000 * 1. 000 *
1, 000 * 0. 829 *
0, 988 * 1. 000 *
0, 886 * 1. 000 *
1. 000 * 1. 000 *
0. 875 * 1. 000 *
1. 000 * 0. 981 *
1. 000 * 0. 813 *
1. 000 * 1. 000 *
5.529
4.899
5.598
223.064) +
53.474) +
3,176) +
223,064) +
53,474) +
3,176) +
223,064) +
53,474) +
3.176) +
270,527
253,891
265,509
Total of 3 main streams to confluence:
Flow rates before confluence point:
223,064 53.474 3.176
Maximum flow rates at confluence using above data:
270.527 253.891 265.509
Area of streams before confluence:
58.750 12.260 0.660
Results of confluence:
Total flow rate = 270.527(CFS)
Time of concentration = 7.819 min.
Effective stream area after confluence = 71.670(Ac.)
++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++^
process from Point/Station 117.000 to Point/Station 118.000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
upstream point/station elevation = 340.67(Ft.)
Page 51
C605P1.OUT
Downstream point/station elevation = 326.46(Ft.)
Pipe length = 285.56(Ft.) Manning's N = 0.013
No. of pipes = 1 Required pipe flow = 270.527(CPS)
Given pipe size = 54.00(ln,)
calculated individual pipe flow = 270,527(CPS)
Normal flow depth in pipe = 30,66(in,)
Flow top width inside pipe = 53.50(ln,)
Critical depth could not be calculated.
Pipe flow velocity = 29,01(Ft/s)
Travel time through pipe = 0,16 min.
Time of concentration (TC) = 7.98 min,
++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 117,000 to Point/Station 118.000
**** CONFLUENCE OF MINOR STREAMS ****
Along Main Stream number: 1 in normal stream number 1
Stream flow area = 71,670(Ac,)
Runoff from this stream = 270,527(CFS)
Time of concentration = 7,98 min.
Rainfall intensity = 5.456(ln/Hr)
++++++++++++++++++++++++++++++++++++++++4-+++++++++++++++++^
Process from Point/Station 2501,000 to Point/Station 2502,000
**** INITIAL AREA EVALUATION ****
User specified 'C value of 0,850 given for subarea
initial subarea flow distance = 100,00(Ft.)
Highest elevation = 396,00(Ft,)
Lowest elevation = 394.00(Ft,)
Elevation difference = 2.00(Ft,)
Time of concentration calculated by the urban
areas overland flow method (App x-C) = 3,57 min,
TC = [1.8*(l,l-C)*distanceA.5)/(% slopeA(i/3)]
TC = [l,8*(l.l-0,8500)*(100,OOA.5)/( 2,00A(l/3)]= 3,57
Setting time of concentration to 5 minutes
RainfaTl intensity (I) = 7,377 for a 100,0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0,850
Subarea runoff = 0,627(CFS)
Total initial stream area = 0.100(Ac.)
process from Point/Station 2502.000 to Point/Station 2503.000
**** IMPROVED CHANNEL TRAVEL TIME ****
upstream point elevation = 394.00(Ft.)
Downstream point elevation = 389.00(Ft.)
Channel length thru subarea = 300.00(Ft,)
Channel base width = 0,000(Ft.)
Slope or 'Z' of left channel bank = 20.000
Slope or 'Z' of right channel bank = 20,000
Estimated mean flow rate at midpoint of channel = 3.762(CPS)
Manning's 'N' =0.015
Maximum depth of channel = 1.000(Ft.)
Flow(q) thru subarea = 3.762(CPS)
Depth of flow = 0.244(Ft.), Average velocity = 3.147(Ft/s)
Channel flow top width = 9,779(Ft,)
Flow velocity = 3.15(Ft/s)
Travel time = 1.59 min.
Time of concentration = 6.59 min.
Page 52
C605P1.OUT
critical depth = 0.293(Ft.)
Adding area flow to channel
User specified 'C value of 0,850 given for subarea
Rainfall intensity = 6,175(ln/Hr) for a 100.0 year storm
Runoff coefficient used for sub-area. Rational method,Q=KCIA, C = 0,850
Subarea runoff = 5.248(CFS) for 1.000(Ac,)
Total runoff = 5,875(CFS) Total area = 1.10(Ac,)
Process from Point/Station 2503,000 to Point/Station 2503,000
**** SUBAREA FLOW ADDITION ****
user specified 'C value of 0,850 given for subarea
Time or concentration = 6.59 mm.
Rainfall intensity = 6.175(in/Hr) for a 100.0 year storm
Runoff coefficient used for sub-area, Rational method,Q=KCIA, C = 0.850
subarea runoff = 12.596(CFS) for 2,400(Ac,)
Total runoff = 18,472(CPS) Total area = 3.50(Ac,)
Process from Point/station 2503,000 to Point/Station 2504.000
**** PIPEFLOW TRAVEL TIME (User Specified size) ****
Upstream point/station elevation = 380.00(Ft.)
Downstream point/station elevation = 375.00(Ft,)
Pipe length = 480,00(Ft,) Manning's N = 0.011
No, of pipes = 1 Required pipe flow = 18,472(CPS)
Given pipe size = 24,00(ln,)
calculated individual pipe flow = 18,472(CFS)
Normal flow depth in pipe = 14.47(In.)
Flow top width inside pipe = 23.48(In.)
critical Depth = 18,58(in,)
Pipe flow velocity = 9,33(Ft/s)
Travel time through pipe = 0,86 min.
Time of concentration (TC) = 7,45 min,
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 2504,000 to Point/Station 2504,000
**** SUBAREA FLOW ADDITION ****
user specified 'C' value of 0.850 given for subarea
Time of concentration = 7,45 mm.
Rainfall intensity = 5,706(in/Hr) for a 100,0 year storm
Runoff coefficient used for sub-area. Rational method,Q=KCIA, c = 0.850
Subarea runoff = 20,274(CFS) for 4,180(Ac,)
Total runoff = 38,746(CFS) Total area = 7,68(Ac.)
Process from Point/Station 2504.000 to Point/Station 118.500
**** PIPEFLOW TRAVEL TIME (User specified size) ****
upstream point/station elevation = 368.20(Ft.)
Downstream point/station elevation = 329.36(Ft.)
Pipe length = 111.90(Ft.) Manning's N = 0.013
NO. of pipes = 1 Required pipe flow = 38.746(CFS)
Given pipe size = 30,00(ln,)
calculated individual pipe flow = 38.746(CFS)
Normal flow depth in pipe = 8,12(in,)
Flow top width inside pipe = 26,66(ln,)
Page 53
C605P1,OUT
Critical Depth = 25.20(ln.)
Pipe flow velocity = 36.09(Ft/s)
Travel time through pipe = 0.05 min.
Time of concentration (TC) = 7.50 min.
Process from Point/station 118,500 to Point/Station
**** PIPEFLOW TRAVEL TIME (User specified size) **** 118.000
Upstream point/station elevation = 329,03(Ft,)
Downstream point/station elevation = 328,13(Ft.)
Pipe length = 45,24(Ft.) Manning's N = 0,013
NO. of pipes = 1 Required pipe flow = 38.746(CFS)
Given pipe size = 30.00(ln,)
Calculated individual pipe flow = 38,746(CFS)
Normal flow depth in pipe = 17,95(In,)
Flow top width inside pipe = 29.41(ln,)
Critical Depth = 25,20(ln,)
Pipe flow velocity = 12.63(Ft/s)
Travel time through pipe = 0,06 min.
Time of concentration (TC) = 7,56 min.
Process from Point/Station 118,500 to Point/Station 118,000
**** CONFLUENCE OF MINOR STREAMS ****
Along Main stream number: 1 in normal stream number 2
Stream flow area = 7,680(Ac,)
Runoff from this stream = 38.746(CFS)
Time of concentration = 7,56 min.
Rainfall intensity = 5.652(ln/Hr)
Summary of stream data:
Stream
NO.
Flow rate
(CPS)
TC
(mi n)
Rainfall Intensity
(in/Hr)
1 270,527 7.98
2 38.746 7.56
Qmax(l) =
1.000 * 1.000 *
0.965 * 1.000 *
Qmax(2) =
1.000 * 0.947 *
1.000 * 1.000 *
5.456
5.652
270.527) +
38.746) +
270.527) +
38.746) +
307.928
294,861
Total of 2 streams to confluence:
Flow rates before confluence point:
270,527 38,746
Maximum flow rates at confluence using above data:
307.928 294,861
Area of streams before confluence:
71,670 7.680
Results of confluence:
Total flow rate = 307,928(CPS)
Time of concentration = 7.983 min.
Effective stream area after confluence = 79.350(Ac.)
Process from Point/Station 118.000 to Point/Station
Page 54
119.000
C605P1.OUT
**** PIPEFLOW TRAVEL TIME (User specified size) ****
Upstream point/station elevation = 326.13(Ft.)
Downstream point/station elevation = 301,50(Ft,)
Pipe length = 310.00(Ft.) Manning's N = 0,013
NO, of pipes = 1 Required pipe flow = 307,928(CFS)
Given pipe size = 54,00(In,)
calculated individual pipe flow = 307,928(CPS)
Normal flow depth in pipe = 28,76(ln,)
Flow top width inside pipe = 53,89(ln,)
Critical depth could not be calculated.
Pipe flow velocity = 35,77(Ft/s)
Travel time through pipe = 0.14 min.
Time of concentration (TC) = 8,13 min,
++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 118,000 to Point/Station 119,000
**** CONFLUENCE OF MINOR STREAMS ****
Along Main Stream number: 1 in normal stream number 1
Stream flow area = 79.350(Ac,)
Runoff from this stream = 307,928(CFS)
Time of concentration = 8,13 min.
Rainfall intensity = 5,393(ln/Hr)
Process from Point/Station 120,000 to Point/Station 121,000
**** INITIAL AREA EVALUATION ****
Decimal fraction soil group A = 0,000
Decimal fraction soil group B = 1,000
Decimal fraction soil group C = 0,000
Decimal fraction soil group D = 0,000
[RURAL (greater than 1/2 acre) area type ]
Initial subarea flow distance = 65,00(Ft,)
Highest elevation = 386.00(Ft.)
Lowest elevation = 356.00(Ft.)
Elevation difference = 30.00(Ft.)
Time of concentration calculated by the urban
areas overland flow method (App x-C) = 3.03 min.
TC = [1.8*(l,l-C)*distanceA,5)/(% slopeA(i/3)]
TC = [1.8*(l.l-0.3500)*( 65.00A.5)/( 46.15A(l/3)]= 3.03
Setting time of concentration to 5 minutes
RainfaTl intensity (I) = 7.377 for a 100.0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0.350
Subarea runoff = 0.026(CFS)
Total initial stream area = 0.010(Ac.)
Process from Point/Station 121,000 to Point/Station 122.000
**** STREET FLOW TRAVEL TIME + SUBAREA FLOW ADDITION ****
Top of Street segment elevation = 356,000(Ft,)
End of street segment elevation = 316,000(Ft,)
Length of street segment = 590,000(Ft,)
Height of curb above gutter flowline = 6,0(ln,)
Width of half street (curb to crown) = 26,000(Ft,)
Distance from crown to crossfall grade break = 24,500(Ft.)
Slope from gutter to grade break (v/hz) = 0.020
Slope from grade break to crown (v/hz) = 0.020
Page 55
m C605P1.OUT
Street flow is on [1] side(s) of the street
Distance from curb to property line = 10,000(Ft.)
Slope from curb to property line (v/hz) = 0,020
Gutter width = 1.500(Ft,)
Gutter hike from flowline = 1.500(ln,)
Manning's N in gutter = 0.0150
Manning's N from gutter to grade break = 0,0150
Manning's N from grade break to crown = 0,0150
Estimated mean flow rate at midpoint of street = 0,045(CPS)
Depth of flow = 0,057(Ft,), Average velocity = 2,279(Ft/s)
Streetflow hydraulics at midpoint of street travel:
Halfstreet flow width = 1,500(Ft.)
Flow velocity = 2,28(Ft/s)
Travel time = 4.32 min, TC = 9,32 min.
Adding area flow to street
user specified 'C' value of 0.530 given for subarea
Rainfall intensity = 4,939(in/Hr) for a 100.0 year storm
Runoff coefficient used for sub-area. Rational method,Q=KCIA, C = 0.530
subarea runoff = 3.795(CFS) for l,450(Ac,)
Total runoff = 3,821(CFS) Total area = l,46(Ac)
Street flow at end of street = 3,821(CFS)
Half street flow at end of street = 3,821(CFS)
Depth of flow = 0,260(Ft,), Average velocity = 5,107(Ft/s)
Flow width (from curb towards crown)= 8,228(Ft,)
+++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 122,000 to Point/Station 119,000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
upstream point/station elevation = 305,50(Ft,)
Downstream point/station elevation = 304,50(Ft,)
Pipe length = 42.25(Ft,) Manning's N = 0,013
No. of pipes = 1 Required pipe flow = 3.821(CFS)
Given pipe size = 18.00(in.)
Calculated individual pipe flow = 3.821(CFS)
Normal flow depth in pipe = 5.96(in,)
Flow top width inside pipe = 16,94(In,)
critical Depth = 8.96(ln,)
Pipe flow velocity = 7,49(Ft/s)
Travel time through pipe = 0,09 min.
Time of concentration (TC) = 9,41 min.
Process from Point/Station 122,000 to Point/station 119.000
**** CONFLUENCE OF MINOR STREAMS ****
Along Main Stream number: 1 in normal stream number 2
stream flow, area = 1.460(Ac.)
Runoff from this stream = 3.821(CFS)
Time of concentration = 9.41 min.
Rainfall intensity = 4.907(in/Hr)
Process from Point/Station 123.000 to Point/Station 124.000
**** INITIAL AREA EVALUATION ****
Decimal fraction soil group A = 0.000
Decimal fraction soil group B = 1.000
Decimal fraction soil group C = 0.000
Decimal fraction soil group D = 0.000
Page 56
C605P1.OUT
[RURAL (greater than 1/2 acre) area type ]
Initial subarea flow distance = 30.00(Ft,)
Highest elevation = 372,00(Ft,)
Lowest elevation = 356,00(Ft,)
Elevation difference = 16,00(Ft.)
Time of concentration calculated by the urban
areas overland flow method (App x-c) = 1,96 min,
TC = [1.8*(l,l-C)*distanceA,5)/(% slopeA(i/3)] TC = [l,8*(l,l-0,3500)*( 30.00A,5)/( 53.33A(l/3)]= 1,96 Setting time of concentration to 5 minutes
RainfaTl intensity (i) =. 7.377 for a 100,0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0.350 Subarea runoff = 0,026(CFS)
Total initial stream area = 0.010(Ac)
++++++++++++++++++++++++++++++++++++++++++4-+++++++++++++^
Process from Point/Station 124,000 to Point/Station 125,000
**** STREET FLOW TRAVEL TIME + SUBAREA FLOW ADDITION ****
Top of street segment elevation = 356,000(Ft,)
End of street segment elevation = 316.000(Ft.)
Length of street segment = 590,000(Ft,)
Height of curb above gutter flowline = 6.0(ln.)
width of half street (curb to crown) = 26,000(Ft,)
Distance from crown to crossfall grade break = 24,500(Ft,)
Slope from gutter to grade break (v/hz) = 0,020
Slope from grade break to crown (v/hz) = 0,020
Street flow is on [1] side(s) of the street
Distance from curb to property line = 10,000(Ft,)
Slope from curb to property line (v/hz) = 0,020
Gutter width = l,500(Ft.)
Gutter hike from flowline = l,500(ln,)
Manning's N in gutter = 0,0150
Manning's N from gutter to grade break = 0,0150
Manning's N from grade break to crown = 0,0150
Estimated mean flow rate at midpoint of street = 0.033(CFS)
Depth of flow = 0,051(Ft,), Average velocity = 2,107(Ft/s)
Streetflow hydraulics at midpoint of street travel:
Halfstreet flow width = l,500(Ft,)
Flow velocity = 2,ll(Ft/s)
Travel time = 4,67 min, TC = 9.67 min.
Adding area flow to street
user specified 'C' value of 0.860 given for subarea
Rainfall intensity = 4.822(ln/Hr) for a 100.0 year storm
Runoff coefficient used for sub-area. Rational method,Q=KCIA, C = 0.860
Subarea runoff = 2.156(CFS) for 0,520(Ac.)
Total runoff = 2,182(CPS) Total area = 0,53(Ac.)
street flow at end of street = 2.182(CPS)
Half street flow at end of street = 2.182(CPS)
Depth of flow = 0,224(Pt.), Average velocity = 4.498(Ft/s)
Flow width (from curb towards crown)= 6.434(Pt.)
Process from Point/Station 125.000 to Point/Station 119.000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
Upstream point/station elevation = 305.00(Ft.)
Downstream point/station elevation = 304,50(Ft,)
Pipe length = 4,25(Ft,) Manning's N = 0.013
No. of pipes = 1 Required pipe flow = 2.182(CPS)
Given pipe size = 18.00(ln.)
Page 57
C605P1.OUT
calculated individual pipe flow = 2.182(CPS)
Normal flow depth in pipe = 3,00(ln,)
Flow top width inside pipe = 13,42(in,)
Critical Depth = 6,69(ln,)
Pipe flow velocity = ll,24(Ft/s)
Travel time through pipe = 0,01 min.
Time of concentration (TC) = 9.67 min.
Process from Point/Station 125,000 to Point/Station 119,000
**** CONFLUENCE OF MINOR STREAMS ****
Along Main Stream number: 1 in normal stream number 3
Stream flow area = 0.530(Ac,)
Runoff from this stream = 2,182(CFS)
Time of concentration = 9,67 min.
Rainfall intensity = 4.820(in/Hr)
Summary of stream data:
Stream
NO.
Flow rate
(CPS) TC
(min)
Rainfall Intensity
(in/Hr)
1
2
3
Qmax(l)
Qmax(2) =
Qmax(3) =
928 8 13
821 9 41
182 9 67
1.000 * 1,000 *
1.000 * 0,864 *
1.000 * 0,840 *
0.910 * 1.000 *
1.000 * 1,000 *
1.000 * 0,973 *
0.894 * 1,000 *
0.982 * 1,000 *
1.000 * 1.000 *
5,393
4,907
4.820
307.928) +
3.821) +
2,182) +
307,928) +
3,821) +
2,182) +
307.928) +
3,821) +
2,182) +
313,061
286,107
281,128
Total of 3 streams to confluence:
Flow rates before confluence point:
307.928 3.821 2.182
Maximum flow rates at confluence using above data:
313.061 286.107 281.128
Area of streams before confluence:
79.350 1.460 0.530
Results of confluence:
Total flow rate = 313.061(CFS)
Time of concentration = 8.127 min.
Effective stream area after confluence = 81.340(Ac.)
Process from Point/Station 119.000 to Point/Station 128.000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
upstream point/station elevation = 301.00(Ft,)
Downstream point/station elevation = 295,16(Ft.)
Pipe length = 63.92(Ft.) Manning's N = 0.013
NO, of pipes = 1 Required pipe flow = 313.061(CFS)
Given pipe size = 60.00(ln.)
calculated individual pipe flow = 313.061(CFS)
Page 58
C605P1,OUT
Normal flow depth in pipe = 26,30(in,)
Flow top width inside pipe = 59,54(ln,)
critical Depth = 56.58(ln,)
Pipe flow velocity = 37,80(Ft/s)
Travel time through pipe = 0,03 min.
Time of concentration (TC) = 8.16 min,
+++++++++++++++++++++++++++++++++++++++++++++++++++++++
process from Point/Station 119,000 to Point/Station 128,000
**** CONFLUENCE OF MAIN STREAMS ****
The following data inside Main Stream is listed:
In Main Stream number: 1
Stream flow area = 81,340(Ac,)
Runoff from this stream = 313,061(CFS)
Time of concentration = 8.16 min.
Rainfall intensity = 5,381(in/Hr)
Program is now starting with Main Stream No, 2
++++++++++4-+++++++++++++++++++++++++++++++++4-+++++++++++
Process from Point/Station 164,000 to Point/Station 165,000
**** INITIAL AREA EVALUATION ****
User specified 'C' value of 0,880 given for subarea
initial subarea flow distance = 460,00(Ft,)
Highest elevation = 366,00(Ft,)
Lowest elevation = 360,00(Ft,)
Elevation difference = 6,00(Ft,)
Time of concentration calculated by the urban
areas overland flow method (App x-C) = 7,77 min.
TC = [1.8*(l.l-C)*distanceA.5)/(% slopeA(l/3)]
TC = [1.8*(l.l-0,8800)*(460,00A,5)/( l,30A(l/3)]= 7,77
Rainfall intensity (I) = 5,550 for a 100,0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0,880
Subarea runoff = 18,608(CFS)
Total initial stream area = 3.810(Ac,)
++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Process from Point/Station 165,000 to Point/Station 132.000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
Upstream point/station elevation = 349,88(Ft,)
Downstream point/station elevation = 344,33(Ft,)
Pipe length = 120,60(Ft,) Manning's N = 0.013
NO. of pipes = 1 Required pipe flow = 18.608(CFS)
Given pipe size = 18,00(In.)
calculated individual pipe flow = 18.608(CPS)
Normal flow depth in pipe = 12.47(in.)
Flow top width inside pipe = 16.61(in.)
Critical depth could not be calculated.
Pipe flow velocity = 14.25(Ft/s)
Travel time through pipe = 0,14 min.
Time of concentration (TC) = 7.91 min.
Process from Point/Station 165,000 to Point/Station 132,000
**** CONFLUENCE OF MINOR STREAMS ****
Along Main Stream number: 2 in normal stream number 1
Page 59
m c605Pl,OUT
Stream flow area = 3,810(Ac)
Runoff from this stream = 18,608(CFS)
Time of concentration = 7,91 min.
Rainfall intensity = 5,486(ln/Hr)
++++++++++++++++++++++++4-+++++++++++++++++++++++4-++++++++++^
Process from Point/Station 129,000 to Point/Station 130.000
**** INITIAL AREA EVALUATION ****
user specified 'C value of 0,850 given for subarea
initial subarea flow distance = 570,00(Ft,)
Highest elevation = 437.00(Ft,)
Lowest elevation = 425.00(Ft,)
Elevation difference = 12.00(Ft,)
Time of concentration calculated by the urban
areas overland flow method (App X-C) = 8,38 min,
TC = [1.8*(l,l-C)*distanceA,5)/(% slopeA(l/3)]
TC = [1.8*(l.l-O.850O)*(570.0OA.5)/( 2.11A(l/3)]= 8.38
Rainfall intensity (l) = 5,286 for a 100,0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0,850
subarea runoff = 18,468(CPS)
Total initial stream area = 4.110(Ac,)
+4-++++++++++++++++++++++4-++++++++++++++++++++++++++++++++++++
Process from Point/Station 130,000 to Point/Station 131,000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
Upstream point/station elevation = 415.00(Ft,)
Downstream point/station elevation = 365.33(Ft,)
Pipe length = 121.73(Ft,) Manning's N = 0.013
NO, of pipes = 1 Required pipe flow = 18,468(CPS)
Given pipe size = 18,00(ln,)
Calculated individual pipe flow = 18,468(CFS)
Normal flow depth in pipe = 6,46(ln.)
Flow top width inside pipe = 17.27(in.)
Critical depth could not be calculated.
Pipe flow velocity = 32.42(Ft/s)
Travel time through pipe = 0.O6 min.
Time of concentration (TC) = 8.45 min.
Process from Point/Station 131.000 to Point/Station 132.000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
Upstream point/station elevation = 365.00(Ft.)
Downstream point/station elevation = 344.33(Ft.)
Pipe length = 287.00(Ft.) Manning's N = 0.013
NO. of pipes = 1 Required pipe flow = 18.468(CPS)
Given pipe size = 18.00(ln.)
Calculated individual pipe flow = 18.468(CPS)
Normal flow depth in pipe = 10,63(in,)
Flow top width inside pipe = 17,70(ln,)
Critical depth could not be calculated.
Pipe flow velocity = 17,01(Ft/s)
Travel time through pipe = 0.28 min.
Time of concentration (TC) = 8.73 min.
Process from Point/Station 131.000 to Point/Station 132.000
Page 60
C605P1.OUT
**** CONFLUENCE OF MINOR STREAMS ****
Along Main stream number: 2 in normal stream number 2
Stream flow area = 4.110(Ac,)
Runoff from this stream = 18.468(CPS)
Time of concentration = 8.73 min.
Rainfall intensity = 5,151(ln/Hr)
Summary of stream data:
stream
NO.
Flow rate
(CFS)
TC
(min)
Rainfall intensity
(in/Hr)
1
2
Qmax(l)
18.608
18,468
7.91
8.73
5.486
5,151
Qmax(2) =
1,000
1.000
0,939
1,000
1,000 *
0,907 *
000
000
18,608) +
18.468) +
18,608) +
18.468) +
35,357
35,940
Total of 2 streams to confluence:
Flow rates before confluence point:
18,608 18.468
Maximum flow rates at confluence using above data:
35,357 35,940
Area of streams before confluence:
3,810 4.110
Results of confluence:
Total flow rate = 35.940(CFS)
Time of concentration = 8,726 min.
Effective stream area after confluence = 7,920(Ac.)
Process from Point/Station 132,000 to Point/Station 132.100
**** PIPEFLOW TRAVEL TIME (User specified size) ****
upstream point/station elevation = 344,00(Ft,)
Downstream point/station elevation = 327,33(Ft,)
Pipe length = 228.63(Ft,) Manning's N = 0,013
NO, of pipes = 1 Required pipe flow = 35,940(CPS)
Given pipe size = 24.00(ln.)
Calculated individual pipe flow = 35,940(CFS)
Normal flow depth in pipe = 13,24(in.)
Plow top width inside pipe = 23.87(ln.)
critical depth could not be calculated.
Pipe flow velocity = 20,23(Ft/s)
Travel time through pipe = 0,19 min.
Time of concentration (TC) = 8.91 min.
process from Point/Station 132.100 to Point/Station 133,000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
upstream point/station elevation = 327,00(Ft,)
Downstream point/station elevation = 310.33(Ft.)
Pipe length = 146.07(Ft.) Manning's N = 0.013
NO. of pipes = 1 Required pipe flow = 35,940(CFS)
Given pipe size = 24.00(ln.)
calculated individual pipe flow = 35.940(CFS)
Page 61
m C605P1.OUT
Normal flow depth in pipe = 11.58(In.)
Flow top width inside pipe = 23.99(in,)
Critical depth could not be calculated.
Pipe flow velocity = 23,95(Ft/s)
Travel time through pipe = 0,10 min.
Time of concentration (TC) = 9,02 min,
+++++++++++++++++++++++++++++++++++++++4-4-4-++++++++++++++++
Process from Point/station 132.000 to Point/station 133,000
**** CONFLUENCE OF MINOR STREAMS ****
Along Main Stream number: 2 in normal stream number 1
Stream flow area = 7,920(Ac)
Runoff from this stream = 35.940(CFS)
Time of concentration = 9.02 min.
Rainfall intensity = 5,044(in/Hr)
Process from Point/Station 130.000 to Point/Station 134.000
**** INITIAL AREA EVALUATION ****
Decimal fraction soil group A = 0.000
Decimal fraction soil group B = 0,630
Decimal fraction soil group C = 0,370
Decimal fraction soil group D = 0,000
[INDUSTRIAL area type ]
initial subarea flow distance = 500.00(Ft.)
Highest elevation = 373.00(Ft.)
Lowest elevation = 364.00(Ft.)
Elevation difference = 9.00(Ft,)
Time of concentration calculated by the urban
areas overland flow method (App x-C) = 7,66 min,
TC = [1.8*(l.l-C)*distanceA.5)/(% slopeA(i/3)]
TC = [l,8*(l.l-0,8685)*(500,00A.5)/( l,80A(l/3)3= 7.66
Rainfall intensity (I) = 5.603 for a 100.0 year storm
Effective runoff coefficient used for area (Q=KCIA) is c = 0.868
Subarea runoff = 20.146(CFS)
Total initial stream area = 4.140(Ac.)
Process from Point/Station 134.000 to Point/station 133.000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
Upstream point/station elevation = 353.80(Ft.)
Downstream point/station elevation = 310,50(Ft,)
Pipe length = 129,60(Ft.) Manning's N = 0,013
NO, of pipes = 1 Required pipe flow = 20,146(CFS)
Given pipe size = 18.00(in,)
Calculated individual pipe flow = 20.146(CFS)
Normal flow depth in pipe = 7.14(in.)
Flow top width inside pipe = 17.61(ln,)
Critical depth could not be calculated.
Pipe flow velocity = 30,86(Ft/s)
Travel time through pipe = 0,07 min.
Time of concentration (TC) = 7.73 min.
Process from Point/Station 134.000 to Point/Station 133.000
**** CONFLUENCE OF MINOR STREAMS ****
Page 62
C605P1.OUT
Along Main Stream number: 2 in normal stream number 2
stream flow area = 4.140(Ac)
Runoff from this stream =
Time of concentration =
Rainfall intensity = 5.
Summary of stream data:
20.146(CFS)
7,73 min,
570(ln/Hr)
Stream
No.
Flow rate
(CPS) TC
(min)
Rainfall Intensity
(in/Hr)
35.940
20.146
9,02
7,73
Qmax(l) =
Qmax(2) =
1,000 *
0,905 *
1,000 *
1,000 *
1.000 *
1.000 *
0.857 *
1.000 *
5.
5.
35.940) +
20.146) +
35.940) +
20.146) +
044
570
54.181
50.957
Total of 2 streams to confluence:
Flow rates before confluence point:
35.940 20,146
Maximum flow rates at confluence using above data:
54,181 50,957
Area of streams before confluence:
7.920 4,140
Results of confluence:
Total flow rate = 54,181(CFS)
Time of concentration = 9,016 min.
Effective stream area after confluence = 12.060(Ac.)
+++++++++++++++++++++++++++++++4-++4-++++++++++++++++++++++++
Process from Point/station 133,000 to Point/Station 137.000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
Upstream point/station elevation = 310.00(Ft,)
Downstream point/station elevation = 302.60(Ft,)
Pipe length = 134,32(Ft.) Manning's N = 0,013
NO, of pipes = 1 Required pipe flow = 54,181(CFS)
Given pipe size = 24,00(ln,)
Calculated individual pipe flow = 54.181(CFS)
Normal flow depth in pipe = 20.16(ln,)
Flow top width inside pipe = 17,60(In,)
Critical depth could not be calculated.
Pipe flow velocity = 19.25(Ft/s)
Travel time through pipe = 0.12 min.
Time of concentration (TC) = 9.13 min.
Process from Point/Station 133,000 to Point/Station 137.000
**** CONFLUENCE OF MINOR STREAMS ****
Along Main Stream number: 2 in normal stream number 1
Stream flow area = 12.060(AC.)
Runoff from this stream = 54,181(CFS)
Time of concentration = 9,13 min.
Rainfall intensity = 5.002(ln/Hr)
Page 63
C605P1.OUT
Process from Point/Station 135,000 to Point/Station 132,000
**** INITIAL AREA EVALUATION ****
Decimal fraction soil group A = 0.000
Decimal fraction soil group B = 0,000
Decimal fraction soil group C = 1,000
Decimal fraction soil group D = 0.000
[RURAL (greater than 1/2 acre) area type ]
Initial subarea flow distance = 120.00(Ft.)
Highest elevation = 407,00(Ft.)
Lowest elevation = 355.00(Ft,)
Elevation difference = 52,00(Ft,)
Time of concentration calculated by the urban
areas overland flow method (App x-C) = 3,93 min,
TC = [1.8*(l.l-C)*distanceA,5)/(% slopeA(l/3)]
TC = [1.8*(l,l-0,4000)*(120,00A,5)/( 43.33A(l/3)]= 3,93
Setting time of concentration to 5 minutes
RainfaTl intensity (I) = 7,377 for a 100,0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0,400
subarea runoff = 0.030(CFS)
Total initial stream area = 0,010(Ac,)
+++++++++++4-++++++++++++++4-+++++++++4-++++++++++++++++++
Process from Point/Station 132,000 to Point/Station 136,000
**** STREET FLOW TRAVEL TIME + SUBAREA FLOW ADDITION ****
Top of Street segment elevation = 355.000(Ft.)
End of street segment elevation = 314.000(Ft,)
Length of street segment = 560.000(Ft.)
Height of curb above gutter flowline = 6.0(in,)
Width of half street (curb to crown) = 26.000(Ft.)
Distance from crown to crossfall grade break = 24.500(Ft.)
Slope from gutter to grade break tv/hz) = 0.020
Slope from grade break to crown (v/hz) = 0.020
Street flow is on [1] side(s) of the street
Distance from curb to property line = 10.000(Ft.)
Slope from curb to property line (v/hz) = O.02O
Gutter width = 1.500(Ft.)
Gutter hike from flowline = 1.500(ln.)
Manning's Nin gutter = 0.0150
Manning's N from gutter to grade break = 0.0150
Manning's N from grade break to crown = 0.0150
Estimated mean flow rate at midpoint of street = 0.057(CPS)
Depth of flow = 0.062(Ft.), Averaqe velocity = 2.496(Ft/s)
Streetflow hydraulics at midpoint or street travel:
Halfstreet flow width = 1.500(Ft.)
Flow velocity = 2.50(Ft/s)
Travel time = 3.74 min. TC = 8.74 min.
Adding area flow to street
user specified 'C value of 0.550 given for subarea
Rainfall intensity = 5.146(ln/Hr) for a 100.0 year storm
Runoff coefficient used for sub-area. Rational method,Q=KCIA, C = 0.550
Subarea runoff = 5.293(CFS) for l,870(Ac,)
Total runoff = 5,322(CPS) Total area = 1,88(Ac)
Street flow at end of street = 5.322(CFS)
Half street flow at end of street = 5.322(CFS)
Depth of flow = 0.281(Ft.), Average velocity = 5.684(Ft/s)
Flow width (from curb towards crown)= 9.301(Ft.)
Page 64
C605P1.OUT
Process from Point/Station 136.000 to Point/Station 137.000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
upstream point/station elevation = 303.60(Ft.)
Downstream point/station elevation = 303,10(Ft,)
Pipe length = 5,25(Ft,) Manning's N = 0,013
No, of pipes = 1 Required pipe flow =
Given pipe size = 18.00(in.)
Calculated individual pipe flow = 5
Normal flow depth in pipe = 4.93(In,)
Flow top width inside pipe = 16.06(in.)
critical Depth = 10.67(ln,)
Pipe flow velocity = 13,54(Ft/s)
Travel time through pipe = 0,01 min.
Time of concentration (TC) = 8,75 min
5.322(CFS)
322(CFS)
Process from Point/Station 136.000 to Point/Station
**** CONFLUENCE OF MINOR STREAMS ****
137,000
Along Main Stream number: 2 in normal stream number 2
Stream flow area = 1,880(Ac.)
Runoff from this stream = 5,322(CFS)
Time of concentration = 8,75 min.
Rainfall intensity = 5,143(ln/Hr)
Process from Point/Station 138.000 to Point/Station 139.000
**** INITIAL AREA EVALUATION ****
,000
,000
80.00(Ft.)"
]
Decimal fraction soil group A = 0.000
Decimal fraction soil group B = 0.000
Decimal fraction soil group C = 1
Decimal fraction soil group D = 0
[INDUSTRIAL area type
Initial subarea flow distance =
Highest elevation = 360.00(Ft.)
Lowest elevation = 355,00(Ft,)
Elevation difference = 5.00(Ft.)
Time of concentration calculated by the urban
areas overland flow method (App X-C) = 1.75 min.
TC = [1.8*(l.l-C)*distanceA.5)/(% slopeA(l/3)]
TC = [1.8*(l.l-0.9000)*( 80.00A.5)/( 6.25A(l/3)]= 1.75
Setting time of concentration to 5 minutes
RainfaTl intensity (I) = 7.377 for a 100.0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0.900
subarea runoff = 0.066(CFS)
Total initial stream area = 0.010(Ac,)
Process from Point/Station 139,000 to Point/Station 140,000
**** STREET FLOW TRAVEL TIME + SUBAREA FLOW ADDITION ****
Top of Street segment elevation = 355.000(Ft.)
End of street segment elevation = 314.000(Ft,)
Length of street segment = 560,000(Ft.)
Height of curb above gutter flowline = 6,0(ln,)
width of half street (curb to crown) = 26,000(Ft.)
Distance from crown to crossfall grade break = 24,500(Ft,)
Slope from gutter to grade break (v/hz) = 0.020
Page 65
m C605P1.OUT
Slope from grade break to crown (v/hz) = 0.020
Street flow is on [1] side(s) of the street
Distance from curb to property line = 10.000(Ft.)
Slope from curb to property line (v/hz) = 0.020
Gutter width = l,500(Ft.)
Gutter hike from flowline = 1.500(ln,)
Manning's N in gutter = 0,0150
Manning's N from gutter to grade break = 0.0150
Manning's N from grade break to crown = 0,0150
Estimated mean flow rate at midpoint of street = 0.093(CPS)
Depth of flow = 0.074(Ft,), Average velocity = 2,822(Ft/s)
Streetflow hydraulics at midpoint of street travel:
Halfstreet flow width = 1.500(Ft,)
Flow velocity = 2.82(Ft/s)
Travel time = 3.31 min, TC = 8,31 min.
Adding area flow to street
User specified 'C value of 0,760 given for subarea
Rainfall intensity = 5,317(ln/Hr) for a 100,0 year storm
Runoff coefficient used for sub-area. Rational method,Q=KCIA, C = 0.760
subarea runoff = 3,273(CFS) for 0.810(Ac,)
Total runoff = 3,340(CFS) Total area = 0,82(Ac.)
Street flow at end of street = 3,340(CFS)
Half street flow at end of street = 3,340(CFS)
Depth of flow = 0.248(Ft,), Average velocity = 5.099(Ft/s)
Flow width (from curb towards crown)= 7.640(Ft,)
++++4-+++++++++++++++++4-++++++++++++++++++++++++++++++++
Process from Point/Station 140.000 to Point/Station 137.000 **** PIPEFLOW TRAVEL TIME (User specified size) ****
upstream point/station elevation = 303,60(Ft,)
Downstream point/station elevation = 302,83(Ft.)
Pipe length = 43.25(Ft,) Manning's N = 0,013
NO, of pipes = 1 Required pipe flow = 3,340(CPS)
Given pipe size = 18,00(ln,)
Calculated individual pipe flow = 3.340(CFS)
Normal flow depth in pipe = 5.98(in.)
Flow top width inside pipe = 16,96(ln.)
Critical Depth = 8.36(ln.)
Pipe flow velocity = 6.51(Ft/s)
Travel time through pipe = 0.11 min.
Time of concentration (TC) = 8,42 min,
++++++++++++4-++++++++++++++++++++++++4-+++4-+++4-++++++++++++++
Process from Point/Station 140.000 to Point/Station 137,000
**** CONFLUENCE OF MINOR STREAMS ****
Along Main Stream number: 2 in normal stream number 3
Stream flow area = 0,820(Ac,)
Runoff from this stream = 3.340(CFS)
Time of concentration = 8,42 min.
Rainfall intensity = 5.272(in/Hr)
Summary of stream data:
Stream Flow rate TC Rainfall intensity
NO. (CPS) (min) (in/Hr)
1 54.181 9.13 5.002
2 5.322 8.75 5.143
3 3.340 8.42 5.272
Page 66
C605P1.OUT
1.000 * 1,000 * 54,181) +
0.972 * 1,000 * 5,322)
0.949 * 1.000 * 3.340) + = 62 525
1,000 * 0,958 * 54,181) 4-
1,000 * 1.000 * 5.322) 4-
0,976 * 1.000 * 3.340) 4- = 60 468
1.000 * 0,922 * 54.181) 4-
1,000 * 0.963 * 5.322) 4-
1.000 * 1,000 * 3,340) + = 58 .407
Qmax(l) =
Qmax(2) =
Qmax(3) =
Total of 3 streams to confluence:
Flow rates before confluence point:
54.181 5,322 3,340
Maximum flow rates at confluence using above data:
62,525 60,468 58,407
Area of streams before confluence:
12,060 1.880 0,820
Results of confluence:
Total flow rate = 62,525(CPS)
Time of concentration = 9,133 min.
Effective stream area after confluence = 14.760(Ac,)
4-4-4-4-4-4-4-4-4-+4-4-4-+4-4-4-4-+4-4-4-4-+4-4-+4-4-+4-4-4-4-+4-4-4-4-4-+4-+4-4-4-4-4-+4-+++4-4-4-4-4-4-4-4-+4-4-+4-+4-++
Process from Point/Station 137.000 to Point/Station 128.000
**** PIPEFLOW TRAVEL TIME (User Specified size) ****
upstream point/station elevation = 301,60(Ft,)
Downstream point/station elevation = 296,50(Ft,)
Pipe length = 85,49(Ft.) Manning's N = 0,013
No, of pipes = 1 Required pipe flow = 62.525(CPS)
Given pipe size = 36.00(in.)
Calculated individual pipe flow = 62.525(CFS)
Normal flow depth in pipe = 15.47(In.)
Flow top width inside pipe = 35.64(in.)
Critical Depth = 30.54(ln,)
Pipe flow velocity = 21,53(Ft/s)
Travel time through pipe = 0.07 min.
Time of concentration (TC) = 9.20 min.
Process from Point/Station 137.000 to Point/Station 128.000
**** CONFLUENCE OF MAIN STREAMS ****
The following data inside Main Stream is listed:
In Main Stream number: 2
Stream flow area = 14.760(Ac.)
Runoff from this stream = 62.525(CFS)
Time of concentration = 9.20 min.
Rainfall intensity = 4.979(ln/Hr)
Program is now starting with Main Stream No. 3
Process from Point/Station 126.000 to Point/Station 127.000
*«** INITIAL AREA EVALUATION ****
user specified 'C value of 0.860 given for subarea
Initial subarea flow distance = 630.00(Ft.)
Page 67
a
c605Pl,OUT
Highest elevation = 327.00(Ft,)
Lowest elevation = 315,00(Ft,)
Elevation difference = 12.00(Ft,)
Time of concentration calculated by the urban
areas overland flow method (App X-C) = 8.75 mm.
TC = [l,8*(l,l-C)*distanceA.5)/(% slopeA(l/3)3
TC = [l,8*(l.l-0.8600)*(630,00A.5)/( l,90A(l/3)]=
Rainfall intensity (I) = 5,143 for a 100,0 year-
Effective runoff coefficient used for area (Q=KCIA)
subarea runoff = 22,867(CFS)
Total initial stream area = 5,170(Ac,)
8.75
storm
is C = 0 860
4-4-4-4-+ + 4-r-r-rTTT^TT T , , •
Process from Point/Station 127,000 to Point/Station
**** PIPEFLOW TRAVEL TIME (User specified size) ****
22,867(CPS)
upstream point/station elevation = 302,70(Ft,)
Downstream point/station elevation = 297,86(Ft,)
Pipe length = 48,60(Ft.) Manning's N = 0,013
NO, of pipes = 1 Required pipe flow =
Given pipe size = 24,00(ln,)
Calculated individual pipe flow = 22,867(CPS)
Normal flow depth in pipe = 9,34(ln,)
Flow top width inside pipe = 23.40(in,)
critical Depth = 20,42(in,)
Pipe flow velocity = 20,22(Ft/s)
Travel time through pipe = 0,04 min.
Time of concentration (TC) = 8,79 min.
Process from Point/Station 127.000 to Point/Station
**** CONFLUENCE OF MAIN STREAMS ****
The following data inside Main Stream is listed:
in Main Stream number: 3
stream flow area = 5,170(Ac)
Runoff from this stream = 22,867(CPS)
Time of concentration = 8,79 min.
Rainfall intensity = 5,128(in/Hr)
Summary of stream data:
128.000
Stream
No.
Flow rate
(CPS)
TC
(min)
Rainfall intensity
(in/Hr)
1
2
3
Qmax(l)
313.061
62,525
22,867
Qmax(2) =
Qmax(3) =
8,16
9.20
8.79
5.381
4.979
5.128
1.000 * 1. 000 * 313 061) +
1.000 * 0. 887 * 62 525) +
1.000 * 0. 928 * 22 867) +
0.925 * 1. 000 * 313 061) +
1.000 * 1. 000 * 62 525) +
0.971 * 1. 000 * 22 867) +
0.953 * 1. 000 * 313 061) +
1.000 * 0 955 * 62 525) +
1.000 * 1 000 * 22 867) +
389.716
374.394
380.940
Page 68
C605P1.OUT
Total of 3 main streams to confluence:
Flow rates before confluence point:
313,061 62.525 22,867
Maximum flow rates at confluence using above data:
389,716 374.394 380.940
Area of streams before confluence:
81.340 14,760 5,170
Results of confluence:
Total flow rate = 389,716(CFS)
Time of concentration = 8,155 min.
Effective stream area after confluence = 101,270(Ac.)
Process from Point/Station 128,000 to Point/Station 144,000
**** PIPEFLOW TRAVEL TIME (user specified size) ****
Upstream point/station elevation = 294,83(Ft,)
Downstream point/station elevation = 283,50(Ft,)
Pipe length = 273.71(Ft,) Manning's N = 0,013
NO, of pipes = 1 Required pipe flow = 389,716(CFS)
Given pipe size = 60,00(ln.)
Calculated individual pipe flow = 389,716(CFS)
Normal flow depth in pipe = 38,25(ln,)
Flow top width inside pipe = 57,69(In,)
Critical depth could not be calculated.
Pipe flow velocity = 29.50(Ft/s)
Travel time through pipe = 0.15 min.
Time of concentration (TC) = 8.31 min.
Process from Point/Station 128.000 to Point/Station 144.000
**** CONFLUENCE OF MINOR STREAMS ****
Along Main Stream number: 1 in normal stream number 1
Stream flow area = 101.270(Ac.)
Runoff from this stream = 389.716(CFS)
Time of concentration = 8,31 min.
Rainfall intensity = 5,316(ln/Hr)
Process from Point/Station 141,000 to Point/Station **** INITIAL AREA EVALUATION **** 142,000
Decimal fraction soil group A = 0,000
Decimal fraction soil group B = 0,000
Decimal fraction soil group C = 1.000
Decimal fraction soil group D = 0.000
[INDUSTRIAL area type ]
Initial subarea flow distance = 420.00(Ft.)
Highest elevation = 346.00(Ft.)
Lowest elevation = 338.00(Ft.)
Elevation difference = 8.00(Ft.)
Time of concentration calculated by the urban
areas overland flow method (App x-C) = 5.95 min.
TC = [1.8*(l,l-C)*distanceA,5)/(% slopeA(i/3)]
TC = [l,8*(l.l-0,9000)*(420.00A,5)/( 1.90A(1/3)]= 5.95
Rainfall intensity (I) = 6,593 for a 100,0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0.900
Page 69
C605P1.OUT
Subarea runoff = 20,471(CFS)
Total initial stream area = 3.450(Ac,)
4-4-+4-4-4-4-4-4-44-+4-4-4-4-4-4-4-4-+4-4-4-+4-4-4-4-4-4-4-+++4-4-4-4-+4-4-4-4-4-4-4-4-4-+4-4-4-4-4-4-4-4-4-4-4-4-4-4-+4-4-4-4-4-
Process from Point/Station 142,000 to Point/Station 143.000 **** PIPEFLOW TRAVEL TIME (User specified size) ****
Upstream point/station elevation = 327,97(Ft.)
Downstream point/station elevation = 289.50(Ft.)
Pipe length = 130.30(Ft.) Manning's N = 0.013
NO. of pipes = 1 Required pipe flow = 20,471(CFS)
Given pipe size = 18.00(ln,)
Calculated individual pipe flow = 20.471(CFS)
Normal flow depth in pipe = 7,45(In,)
Flow top width inside pipe = 17.73(in,)
critical depth could not be calculated.
Pipe flow velocity = 29,64(Ft/s)
Travel time through pipe = 0,07 min.
Time of concentration (TC) = 6,03 min.
Process from Point/Station 143,000 to Point/station 144,000
**** PIPEFLOW TRAVEL TIME (user specified size) ****
Upstream point/station elevation = 287,17(Ft.)
Downstream point/station elevation = 286.17(Ft.)
Pipe length = 42,50(Ft.) Manning's N = 0.013
NO. of pipes = 1 Required pipe flow = 20,471(CFS)
Given pipe size = 24.00(in.)
Calculated individual pipe flow = 20,471(CFS)
Normal flow depth in pipe = 13,27(in,) Flow top width inside pipe = 23.87(in,)
Critical Depth = 19,48(In.)
Pipe flow velocity = 11.50(Ft/s)
Travel time through pipe = 0,06 min.
Time of concentration (TC) = 6,09 min.
Process from Point/Station 143,000 to Point/Station 144.000
**** CONFLUENCE OF MINOR STREAMS ****
Along Main stream number: 1 in normal stream number 2
Stream flow area = 3.450(Ac)
Runoff from this stream = 20.471(CFS)
Time of concentration = 6.09 min.
Rainfall intensity = 6.498(ln/Hr)
Summary of stream data:
Stream Flow rate TC Rainfall Intensity
NO. (CPS) (min) (in/Hr)
1 389.716 8.31 5.316
2 20.471 6.09 6.498
Qmax(l) =
1.000 * 1.000 * 389,716) 4-
0,818 * 1,000 * 20.471) + = 406.462
Qmax(2) =
1.000 * 0,732 * 389,716) 4-
1.000 * 1.000 * 20.471) 4- = 305.922
Page 70
m C605P1.OUT
Total of 2 streams to confluence:
Flow rates before confluence point:
389.716 20,471 Maximum flow rates at confluence using above data: 406.462 305.922 Area of streams before confluence:
101.270 3.450 Results of confluence:
Total flow rate = 406.462(CFS)
Time of concentration = 8,310 min.
Effective stream area after confluence = 104.720(Ac.)
4-4-+4-++4-4-4-+4-+4-4-4-+4-4-4-++4-++4-+4-4-4-4-+4-4-4-+4-4-4-4-4-4-4-4-+4-+4-4-4-+44-+4-4-4-4-4-+4-4-4-++4-4-4-4-+4-
Process from Point/Station 144,000 to Point/Station 147.000 **** PIPEFLOW TRAVEL TIME (User specified size) ****
Upstream point/station elevation = 283,17(Ft.)
Downstream point/station elevation = 279,50(Ft,)
Pipe length = 72,13(Ft,) Manning's N = 0,013
NO, of pipes = 1 Required pipe flow = 406,462(CPS)
Given pipe size = 60,00(in.)
calculated individual pipe flow = 406,462(CPS)
Normal flow depth in pipe = 36,70(in,)
Flow top width inside pipe = 58,48(ln.)
Critical depth could not be calculated.
Pipe flow velocity = 32.29(Ft/s)
Travel time through pipe = 0,04 min. Time of concentration (TC) = 8.35 min.
Process from Point/Station 144,000 to Point/Station 147,000
**** CONFLUENCE OF MINOR STREAMS ****
Along Main Stream number: 1 in normal stream number 1
Stream flow area = 104,720(Ac)
Runoff from this stream = 406,462(CFS)
Time of concentration = 8,35 min. Rainfall intensity = 5,301(ln/Hr)
Process from Point/Station 167,000 to Point/Station 125,000
**** INITIAL AREA EVALUATION ****
Decimal fraction soil group A = 0,000
Decimal fraction soil group B = 0,000
Decimal fraction soil group c = 1,000
Decimal fraction soil group D = 0,000
[INDUSTRIAL area type ]
initial subarea flow distance = 25,00(Ft.)
Highest elevation = 317.00(Ft.)
Lowest elevation = 316.50(Ft.)
Elevation difference = 0.50(Ft.)
Time of concentration calculated by the urban
areas overland flow method (App x-C) = 1.43 min.
TC = [1.8*(l.l-C)*distanceA.5)/(% slopeA(l/3)]
TC = [1.8*(l.l-0,9000)*( 25.00A,5)/( 2,00A(1/3)]= 1,43
Setting time of concentration to 5 minutes
RainfaTl intensity (I) = 7,377 for a 100,0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0,900
Page 71
C605P1,OUT
Subarea runoff = 0,066(CFS)
Total initial stream area = 0,010(Ac)
+4-+4-+4-4-4-4-++4-4-4-4-4-++4-4-4-4-++4-4-+4-+++4-+4-4-4-4-4-4-4-+4-4-4-4-4-+4-+4-4-4-4-4-4-4-+4-++4-4-+4-4-4-++4-4-
Process from Point/Station 125,000 to Point/Station 148,000
**** STREET FLOW TRAVEL TIME 4- SUBAREA FLOW ADDITION ****
Top of Street segment elevation = 316.500(Ft,)
End of street segment elevation = 292.000(Ft,)
Length of street segment = 410,000(Ft.)
Height of curb above gutter flowline = 6,0(ln,)
Width of half street (curb to crown) = 26,000(Ft,)
Distance from crown to crossfall grade break = 24,500(Ft,)
Slope from gutter to grade break (v/hz) = 0,020
Slope from grade break to crown (v/hz) = 0,020
Street flow is on [1] side(s) of the street
Distance from curb to property line = 10,000(Ft,)
Slope from curb to property line (v/hz) = 0,020
Gutter width = 1.500(Ft.)
Gutter hike from flowline = 1.500(In.)
Manning's N in gutter = 0,0150
Manning's N from gutter to grade break = 0.0150
Manning's N from grade break to crown = 0.0150
Estimated mean flow rate at midpoint of street = 0.079(CPS)
Depth of flow = 0.073(Ft.), Average velocity = 2.511(Ft/s)
Streetflow hydraulics at midpoint or street travel:
Halfstreet flow width = 1.500(Ft,)
Flow velocity = 2,51(Ft/s)
Travel time = 2.72 min. TC = 7.72 min.
Adding area flow to street
DecimaT fraction soil group A = 0.000
Decimal fraction soil group B = 0.000
Decimal fraction soil group C = 1.000
Decimal fraction soil group D = 0,000
[INDUSTRIAL area type ]
Rainfall intensity = 5,574(ln/Hr) for a 100,0 year storm
Runoff coefficient used for sub-area. Rational method,Q=KCIA, C = 0,900
Subarea runoff = 1,956(CFS) for 0.390(Ac.)
Total runoff = 2,023(CPS) Total area = 0,40(Ac,)
Street flow at end of street = 2,023(CPS)
Half street flow at end of street = 2.023(CPS)
Depth of flow = 0,223(Ft,), Average velocity = 4.211(Ft/s)
Flow width (from curb towards crown)= 6.396(Ft.)
Process from Point/Station 148.000 to Point/Station 147,000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
Upstream point/station elevation = 283,17(Ft,)
Downstream point/station elevation = 282.67(Ft,)
Pipe length = 4,75(Ft,) Manning's N = 0,013
NO, of pipes = 1 Required pipe flow = 2,023(CPS)
Given pipe size = 18,00(in.)
Calculated individual pipe flow = 2.023(CFS)
Normal flow depth in pipe = 2.98(ln.)
Flow top width inside pipe = 13.37(in.)
critical Depth = 6.43(in.)
Pipe flow velocity = 10.58(Ft/s)
Travel time through pipe = 0.01 min.
Time of concentration (TC) = 7,73 min.
Page 72
C605P1.OUT
Process from Point/Station 148,000 to Point/Station
**** CONFLUENCE OF MINOR STREAMS **** 147,000
Along Main Stream number: 1 in normal stream number 2
Stream flow area = 0,400(Ac)
Runoff from this stream = 2,023(CPS)
Time of concentration = 7,73 min.
Rainfall intensity = 5.570(ln/Hr)
Summary of stream data:
Stream
No.
Flow rate
(CFS)
TC
(min)
Rainfall intensity
(in/Hr)
1
2
Qmax(l)
406.462
2.023
8,35
7,73
5,301
5,570
Qmax(2) =
1,000
0.952
000
000
1,000
1.000
0,926
1,000
406,462) 4-
2,023) +
406.462) 4-
2,023) +
408.387
378,386
Total of 2 streams to confluence:
Flow rates before confluence point:
406.462 2,023
Maximum flow rates at confluence using above data:
408,387 378,386
Area of streams before confluence:
104,720 0,400
Results of confluence:
Total flow rate = 408,387(CPS)
Time of concentration = 8,347 min.
Effective stream area after confluence = 105.120(Ac.)
Process from Point/Station 147.000 to Point/Station 149,000 **** PIPEFLOW TRAVEL TIME (user specified size) ****
Upstream point/station elevation = 279,17(Ft,)
Downstream point/station elevation = 277.43(Ft.)
Pipe length = 34.00(Ft,) Manning's N = 0.013
NO, of pipes = 1 Required pipe flow = 408,387(CPS)
Given pipe size = 60.00(in.)
Calculated individual pipe flow = 408.387(CFS)
Normal flow depth in pipe = 36.75(ln.)
Flow top width inside pipe = 58.46(In.)
Critical depth could not be calculated.
Pipe flow velocity = 32.40(Ft/s)
Travel time through pipe = 0.02 min.
Time of concentration (TC) = 8.36 min.
Process from Point/Station 147.000 to Point/Station 149.000
**** CONFLUENCE OF MAIN STREAMS ****
The following data inside Main Stream is listed:
in Main stream number: 1
stream flow area = 105.120(Ac.)
Page 73
C605P1.OUT
Runoff from this stream = 408.387(CFS)
Time of concentration = 8.36 min.
Rainfall intensity = 5,294(ln/Hr)
Program is now starting with Main Stream No.
Process from Point/Station 150.000 to Point/Station
**** INITIAL AREA EVALUATION ****
151.000
user specified 'c' value of 0.400 given for subarea
Initial subarea flow distance = 40.00(Ft.)
Highest elevation = 360,00(Ft,)
Lowest elevation = 340,00(Ft,)
Elevation difference = 20.00(Ft,)
Time of concentration calculated by the urban
areas overland flow method (App x-C) = 2.16 min.
TC = [1.8*(l.l-C)*distanceA.5)/(% slopeA(l/3)]
TC = [1,8*(1,1-0,4000)*( 40,00A.5)/( 50.00A(l/3)]= 2,16
Setting time of concentration to 5 minutes
RainfaTl intensity (I) = 7.377 for a 100.0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0,400
Subarea runoff = 0,030(CFS)
Total initial stream area = 0.010(Ac)
#
Process from Point/Station 151,000 to Point/Station
**** STREET FLOW TRAVEL TIME + SUBAREA FLOW ADDITION ****
152,000
Top of Street segment elevation = 340.000(Ft,)
End of street segment elevation = 322,000(Ft,)
Length of street segment = 900,000(Ft,)
Height of curb above gutter flowline = 6,0(ln,)
width of half street (curb to crown) = 26,000(Ft.)
Distance from crown to crossfall grade break = 24.500(Ft.)
Slope from gutter to grade break (v/hz) = 0.020
Slope from grade break to crown (v/hz) = 0.020
Street flow is on [1] side(s) of the street
Distance from curb to property line = 10.000(Ft.)
Slope from curb to property line (v/hz) = 0.020
Gutter width = 1.500(Ft.)
Gutter hike from flowline = 1.500(ln.)
Manning's N in gutter = 0.0150
Manning's N from gutter to grade break = 0.0150
Manning's N from grade break to crown = 0.0150
Estimated mean flow rate at midpoint of street = 0.066(CFS)
Depth of flow = 0.083(Ft.), Average velocity = 1.593(Ft/s)
Streetflow hydraulics at midpoint of street travel:
Halfstreet flow width = 1.500(Ft.)
Flow velocity = 1.59(Ft/s)
Travel time = 9.42 min. TC = 14.42 min.
Adding area flow to street
user specified 'C value of 0.590 given for subarea
Rainfall intensity = 3.726(ln/Hr) for a 100.0 year storm
Runoff coefficient used for sub-area, Rational method,Q=KCIA, C = 0.590
Subarea runoff = 5.496(CFS) for 2.500(Ac.)
Total runoff = 5.526(CFS) Total area = 2.51(Ac.)
Street flow at end of street = 5.526(CFS)
Half street flow at end of street = 5.526(CFS)
Depth of flow = 0.340(Ft.), Average velocity = 3.502(Ft/s)
Flow width (from curb towards crown)= 12.274(Ft.)
Page 74
C605P1.OUT
Process from Point/Station 152.000 to Point/Station 153.000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
Upstream point/station elevation = 314.60(Ft.)
Downstream point/station elevation = 314,10(Ft.)
Pipe length = 5.25(Ft.) Manning's N = 0.013
No. of pipes = 1 Required pipe flow = 5,526(CPS)
Given pipe size = 18,00(In,)
Calculated individual pipe flow = 5,526(CFS)
Normal flow depth in pipe = 5,03(In,)
Flow top width inside pipe = 16,15(in,)
Critical Depth = 10,87(in,)
Pipe flow velocity = 13,68(Ft/s)
Travel time through pipe = 0,01 min.
Time of concentration (TC) = 14.42 min.
Process from Point/Station 152,000 to Point/Station
**** CONFLUENCE OF MINOR STREAMS ****
153,000
Along Main stream number: 2 in normal stream number 1
Stream flow area = 2,510(Ac,) Runoff from this stream = 5,526(CFS) Time of concentration = 14.42 min.
Rainfall intensity = 3,725(ln/Hr)
Process from Point/Station 154,000 to Point/station
**** INITIAL AREA EVALUATION ****
155,000
Decimal fraction soil group A = 0,000
Decimal fraction soil group B = 0.000
Decimal fraction soil group C = 0,000
Decimal fraction soil group D = 1,000
[INDUSTRIAL area type ]
Initial subarea flow distance = 30,00(Ft,)
Highest elevation = 340,60(Ft,)
Lowest elevation = 340,00(Ft,)
Elevation difference = 0,60(Ft.)
Time of concentration calculated by the urban
areas overland flow method (App x-C) = 1.17 min
TC = [1.8*(l.l-c)*distanceA.5)/(% slopeA(l/3)l
TC = [1.8*(l,l-0,9500)*( 30,OOA,5)/( 2,00A(1/3)]= 1.17 Setting time of concentration to 5 minutes RainfaTl intensity (l) = 7.377 for a 100.0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0 950
Subarea runoff = 0.070(CFS)
Total initial stream area = O.OlO(Ac)
Process from Point/Station 155.000 to Point/Station
**** STREET FLOW TRAVEL TIME 4- SUBAREA FLOW ADDITION ****
156,000
Top of Street segment elevation = 340,000(Ft.) End of street segment elevation = 322.000(Ft.) Length of street segment = 1000.000(Ft.)
Height of curb above gutter flowline = 6.0(ln.)
width of half street (curb to crown) = 26.000(Ft.)
Page 75
C605P1,OUT
Distance from crown to crossfall grade break = 24,500(Ft,)
Slope from gutter to grade break (v/hz) = 0,020
Slope from grade break to crown (v/hz) = 0,020
Street flow is on [1] side(s) of the street
Distance from curb to property line = 10,000(Ft,)
Slope from curb to property line (v/hz) = 0,020
Gutter width = 1.500(Ft.)
Gutter hike from flowline = l,500(in,)
Manning's N in gutter = 0.0150
Manning's N from gutter to grade break = 0.0150
Manning's N from grade break to crown = 0.0150
Estimated mean flow rate at midpoint of street = 0,103(CPS)
Depth of flow = 0,100(Ft,), Average velocity = l,709(Ft/s)
Streetflow hydraulics at midpoint of street travel:
Halfstreet flow width = l,500(Ft,)
Flow velocity = 1.71(Ft/s)
Travel time = 9,75 min. TC = 14.75 min.
Adding area flow to street
DecimaT fraction soil group A = 0,000
Decimal fraction soil group B = 0,000
Decimal fraction soil group c = 0.000
Decimal fraction soil group D = 1.000
[INDUSTRIAL area type ]
Rainfall intensity = 3.671(in/Hr) for a 100,0 year storm
Runoff coefficient used for sub-area, Rational method,Q=KCIA, C = 0.950
subarea runoff = 3,279(CFS) for 0,940(Ac,)
Total runoff = 3.349(CFS) Total area = 0,95(Ac)
Street flow at end of street = 3,349(CFS)
Half street flow at end of street = 3,349(CFS)
Depth of flow = 0.300(Ft.), Average velocity = 2,983(Ft/s)
Flow width (from curb towards crown)= 10,254(Ft,)
Process from Point/Station 156,000 to Point/Station 153.000
**** PIPEFLOW TRAVEL TIME (user specified size) ****
upstream point/station elevation = 314,70(Ft,)
Downstream point/station elevation = 313.60(Ft.)
Pipe length = 55,25(Ft.) Manning's N = 0,013
No, of pipes = 1 Required pipe flow = 3.349(CFS)
Given pipe size = 18,00(ln.)
Calculated individual pipe flow = 3,349(CPS)
Normal flow depth in pipe = 5.82(in,)
Flow top width inside pipe = 16.84(In.)
Critical Depth = 8.37(in.)
Pipe flow velocity = 6,78(Ft/s)
Travel time through pipe = 0,14 min.
Time of concentration (TC) = 14.89 min.
Process from Point/Station 156.000 to Point/Station 153.000
**** CONFLUENCE OF MINOR STREAMS ****
Along Main Stream number: 2 in normal stream number 2
Stream flow area = 0.950(AC,)
Runoff from this stream = 3,349(CFS)
Time of concentration = 14,89 min.
Rainfall intensity = 3.650(ln/Hr)
Summary of stream data:
Stream Flow rate TC Rainfall intensity
Page 76
C605P1.OUT
NO, (CFS) (min) (in/Hr)
1 5,526 14.42 3,725
2 3,349 14,89 3,650 Qmax(l)
Qmax(2) =
1.000 * 1,000 * 5.526) +
1.000 * 0,969 * 3,349) 4- = 8,770
0.980 * 1,000 * 5,526) 4-
1.000 * 1,000 * 3,349) 4- = 8,762
Total of 2 streams to confluence:
Flow rates before confluence point:
5.526 3.349
Maximum flow rates at confluence using above data:
8,770 8,762
Area of streams before confluence:
2,510 0,950
Results of confluence:
Total flow rate = 8.770(CPS)
Time of concentration = 14,422 min.
Effective stream area after confluence = 3.460(Ac.)
Process from Point/station 153,000 to Point/Station 157,000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
Upstream point/station elevation = 313.27(Ft,)
Downstream point/station elevation = 305.33(Ft,)
Pipe length = 296,00(Ft.) Manning's N = 0.013
NO, of pipes = 1 Required pipe flow = 8,770(CFS)
Given pipe size = 18.00(ln,)
calculated individual pipe flow = 8,770(CFS)
Normal flow depth in pipe = 9,ll(in.)
Flow top width inside pipe = 18,00(in,)
critical Depth = 13.75(in.)
Pipe flow velocity = 9.78(Ft/s)
Travel time through pipe = 0.50 min.
Time of concentration (TC) = 14,93 min.
Process from Point/Station 157,000 to Point/Station 169,000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
upstream point/station elevation = 305,00(Ft,)
Downstream point/station elevation = 291.00(Ft.)
Pipe length = 241.53(Ft.) Manning's N = 0.013
NO. of pipes = 1 Required pipe flow = 8.770(CFS)
Given pipe size = 18.00(ln.)
Calculated individual pipe flow = 8.770(CFS)
Normal flow depth in pipe = 7.31(ln.)
Flow top width inside pipe = 17.68(In.)
critical Depth = 13,75(ln,)
Pipe flow velocity = 13.01(Ft/s)
Travel time through pipe = 0,31 min.
Time of concentration (TC) = 15.24 min.
Process from Point/Station 169.000 to Point/Station 160.000
Page 77
C605P1.OUT
**** PIPEFLOW TRAVEL TIME (user specified size) ****
upstream point/station elevation = 290,67(Ft.)
Downstream point/station elevation = 287,00(Ft.)
Pipe length = 105.70(Ft,) Manning's N = 0,013
No, of pipes = 1 Required pipe flow = 8,770(CFS)
Given pipe size = 18.00(ln,)
Calculated individual pipe flow = 8,770(CFS)
Normal flow depth in pipe = 8,44(in,)
Flow top width inside pipe = 17,97(in,)
Critical Depth = 13,75(In.)
Pipe flow velocity = 10.77(Ft/s)
Travel time through pipe = 0.16 min.
Time of concentration (TC) = 15,40 min,
4-4-4-4-4-4-4-4-4-44-4-4-4-++4-4-4-4-4-4-4-4-4-4-4-4-4-4-4-4-4-4-4-+4-4-4-4-4-++4-4-4-4-4-4-4-4-+4-4-+4-4-+4-4-4-4-4-4-4-4-4-4-4-4-
Process from Point/Station 169.000 to Point/Station 160,000
**** CONFLUENCE OF MINOR STREAMS ****
Along Main Stream number: 2 in normal stream number 1
Stream flow area = 3.460(Ac)
Runoff from this stream = 8.770(CFS)
Time of concentration = 15,40 min.
Rainfall intensity = 3,571(in/Hr)
Process from Point/Station 158,000 to Point/Station 152,000
**** INITIAL AREA EVALUATION ****
Decimal fraction soil group A = 0,000
Decimal fraction soil group B = 0.000
Decimal fraction soil group C = 1.000
Decimal fraction soil group D = 0.000
[INDUSTRIAL area type ]
Initial subarea flow distance = 30.00(Ft,)
Highest elevation = 322,60(Ft,)
Lowest elevation = 322.00(Ft,)
Elevation difference = 0.60(Ft,)
Time of concentration calculated by the urban
areas overland flow method (App X-C) = 1.57 min.
TC = [1.8*(l,l-C)*distanceA,5)/(% slopeA(l/3)]
TC = [l,8*(l,l-0,9000)*( 30,OOA.5)/( 2.00A(l/3)]= 1.57
Setting time of concentration to 5 minutes
RainfaTl intensity (I) = 7.377 for a 100.0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0.900
Subarea runoff = 0.066(CFS)
Total initial stream area = 0.010(Ac.)
Process from Point/Station 152.000 to Point/Station 159.000
**** STREET FLOW TRAVEL TIME 4- SUBAREA FLOW ADDITION ****
Top of Street segment elevation = 322.000(Ft.)
End of street segment elevation = 295.000(Ft.)
Length of street segment = 650,000(Ft.)
Height of curb above gutter flowline = 6.0(in.)
width of half street (curb to crown) = 26,000(Ft.)
Distance from crown to crossfall grade break = 24.500(Ft.)
Slope from gutter to grade break (v/hz) = 0.020
Slope from grade break to crown (v/hz) = 0.020
Page 78
0,130(CFS)
2.481(Ft/s)
C605P1.OUT
Street flow is on [1] side(s) of the street
Distance from curb to property line = 10,000(Ft.)
Slope from curb to property line (v/hz) = 0,020
Gutter width = 1.500(Ft.)
Gutter hike from flowline = l,500(in,)
Manning's N in gutter = 0,0150
Manning's N from gutter to grade break = 0,0150
Manning's N from grade break to crown = 0,0150
Estimated mean flow rate at midpoint of street =
Depth of flow = 0,094(Ft,), Average velocity =
Streetflow hydraulics at midpoint of street travel,
Halfstreet flow width = l,500(Ft.)
Flow velocity = 2,48(Ft/s)
Travel time = 4,37 min, TC = 9.37 min.
Adding area flow to street
user specified 'C' value of 0,570 given for subarea
Rainfall intensity = 4,921(in/Hr) for a 100,0 year storm
Runoff coefficient used for sub-area. Rational method,Q=KCIA, C = 0,570
Subarea runoff = 5.414(CFS) for l,930(Ac,)
Total runoff = 5,480(CFS) Total area = 1,94(Ac)
Street flow at end of street = 5.480(CFS)
Half street flow at end of street = 5,480(CFS)
Depth of flow = 0,306(Ft,), Average velocity = 4.612(Ft/s)
Flow width (from curb towards crown)= 10.568(Ft.)
Process from Point/Station 159.000 to Point/station
**** SUBAREA FLOW ADDITION ****
159.000
User specified 'c' value of 0,580 given for subarea
Time of concentration = 9,37 mm.
Rainfall intensity = 4,921(in/Hr) for a 100.0 year storm
Runoff coefficient used for sub-area. Rational method,Q=KCIA, C = 0,580
subarea runoff = 2.740(CFS) for 0.960(Ac,)
Total runoff = 8,220(CFS) Total area = 2,90(Ac.)
Process from Point/Station 159,000 to Point/Station
**** PIPEFLOW TRAVEL TIME (User specified size) ****
upstream point/station elevation = 286,27(Ft,)
Downstream point/station elevation = 285,90(Ft.)
Pipe length = 5.24(Ft.) Manning's N = 0,013
No, of pipes = 1 Required pipe flow = 8,220(CFS)
Given pipe size = 18.00(in.)
Calculated individual pipe flow = 8.220(CFS)
Normal flow depth in pipe = 6,69(In,)
Flow top width inside pipe = 17,40(in.)
Critical Depth = 13,32(in,)
Pipe flow velocity = 13,74(Ft/s)
Travel time through pipe = 0.01 min.
Time of concentration (TC) = 9.37 min.
160,000
Process from Point/Station 159.000 to Point/station
**** CONFLUENCE OF MINOR STREAMS ****
160.000
Along Main Stream number: 2 in normal stream number 2
Stream flow area = 2,900(Ac,)
Runoff from this stream = 8.220(CFS)
Page 79
Time of concentration =
Rainfall intensity =
c605Pl,OUT
9,37 min,
4,919(ln/Hr)
Process from Point/Station 158.000 to Point/Station 156.000
**** INITIAL AREA EVALUATION ****
group A
group B
group c
group D
= 0,000
= 0,000
= 1,000
= 0,000
Decimal fraction soil
Decimal fraction soil
Decimal fraction soil
Decimal fraction soil
[INDUSTRIAL area type ' ]
Initial subarea flow distance = 30.00(Ft,)
Highest elevation = 322.60(Ft.)
Lowest elevation = 322.00(Ft,)
Elevation difference = 0,60(Ft,)
Time of concentration calculated by the urban
areas overland flow method (App x-c) = 1,57 min,
TC = [l,8*(l.l-C)*distanceA.5)/(% slopeA(l/3)]
TC = [1.8*(l.l-0.9000)*( 30.00A,5)/( 2.00A(l/3)]= 1.57
Setting time of concentration to 5 minutes RainfaTl intensity (I) = 7,377 for a 100,0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0,900
Subarea runoff = 0.066(CFS)
Total initial stream area = 0.010(Ac,)
Process from Point/Station 156,000 to Point/Station
**** STREET FLOW TRAVEL TIME + SUBAREA FLOW ADDITION ****
161.000
Top of Street segment elevation = 322.000(Ft.)
End of street segment elevation = 295.000(Ft.)
Length of street segment = 680.000(Ft.)
Height of curb above gutter flowline = 6.0(ln.)
Width of half street (curb to crown) = 26.000(Ft.)
Distance from crown to crossfall grade break = 24.500(Ft,)
Slope from gutter to grade break (v/hz) = 0.020
Slope from grade break to crown (v/hz) = 0.020
Street flow is on [1] side(s) of the street
Distance from curb to property line = 10,000(Ft.)
Slope from curb to property line (v/hz) = 0.020
Gutter width = 1.500(Ft.)
Gutter hike from flowline = 1.500(ln,)
Manning's N in gutter = 0,0150
Manning's N from gutter to grade break = 0,0150
Manning's N from grade break to crown = 0,0150
Estimated mean flow rate at midpoint of street =
Depth of flow = 0.081(Ft,), Averaqe velocity =
Streetflow hydraulics at midpoint or street travel
Halfstreet flow width = l,500(Ft,)
Flow velocity = 2,21(Ft/s)
TC = 10,13 mi n,
0,088(CFS)
2,208(Ft/s)
Travel time = 5.13 mm.
Adding area flow to street
DecimaT fraction soil group
Decimal fraction soil
Decimal fraction soil
Decimal fraction soil
[INDUSTRIAL area type
Rainfall intensity =
A = 0,000
group B = 0,000
group
group
= 1,000
= 0.000
4,678(ln/Hr) for a
]
Runoff coefficient used for sub-area. Rational
Subarea runoff = 2.694(CFS) for
Page 80
0.640(Ac.)
100.0 year storm
method,Q=KCIA, c = 0, 900
C605P1.OUT
Total runoff = 2.761(CFS) Total area = 0.65(Ac)
Street flow at end of street = 2.761(CFS)
Half street flow at end of street = 2.761(CFS)
Depth of flow = 0,256(Ft,), Average velocity = 3,856(Ft/s)
Flow width (from curb towards crown)= 8,029(Ft,)
Process from Point/Station 161,000 to Point/Station 160,000
**** PIPEFLOW TRAVEL TIME (user specified size) ****
upstream point/station elevation = 287,50(Ft.)
Downstream point/station elevation = 285,50(Ft.)
Pipe length = 55.26(Ft,) Manning's N = 0,013
No. of pipes = 1 Required pipe flow =
Given pipe size = 18,00(ln,)
Calculated individual pipe flow = 2.
Normal flow depth in pipe = 4.52(in.)
Flow top width inside pipe = 15.61(ln.)
critical Depth = 7.57(in.)
Pipe flow velocity = 7.94(Ft/s)
Travel time through pipe = 0.12 min.
Time of concentration (TC) = 10.25 min
2.761(CFS)
761(CFS)
Process from Point/Station 161.000 to Point/Station
**** CONFLUENCE OF MINOR STREAMS ****
160.000
Along Main Stream number: 2 in normal stream number 3
Stream flow area = 0.650(Ac,)
Runoff from this stream = 2,761(CFS)
Time of concentration = 10.25 min.
Rainfall intensity = 4,644(ln/Hr)
Summary of stream data:
Stream
No.
Flow rate
(CPS) TC
(min)
Rainfall intensity
(in/Hr)
1
2
3
Qmax(l)
Qmax(2) =
Qmax(3) =
Total of 3 streams to confluence:
Flow rates before confluence point:
8,770 8.220 2.761
Maximum flow rates at confluence using above data:
16.861 16.083 16.357
Area of streams before confluence:
3.460 2.900 0.650
Page 81
770 15 .40 3 571
220 9 37 4 919
761 10 25 4 644
1.000 * 1.000 * 8,770) 4-
0.726 * 1.000 * 8,220) +
0.769 * 1.000 * 2,761) 4-= 16 861
1.000 * 0.609 * 8,770) +
1.000 * 1.000 * 8,220) +
1.000 * 0,915 * 2,761) 4-= 16 083
1.000 * 0,665 * 8.770) +
0.944 * 1.000 * 8.220) +
1.000 * 1,000 * 2.761) 4-= 16. 357
C605P1.OUT
Results of confluence:
Total flow rate = 16.861(CFS)
Time of concentration = 15.399 min.
Effective stream area after confluence = 7,010(Ac)
4-4-4-++4-4-+4-+4-4-++4-+4-4-4-+4-4-4-4-+4-4-4-4-44-4-+4-4-+4-4-4-+4-4-4-4-4-4-4-+4-4-4-4-4-4-4-4-4-4-4-4-4-4-4-4-4-4-4-4-4-4-
Process from Point/Station 160,000 to Point/Station 149,000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
upstream point/station elevation = 284.80(Ft,)
Downstream point/station elevation = 280,00(Ft,)
Pipe length = 92,50(Ft,) Manning's N = 0.013
NO, of pipes = 1 Required pipe flow = 16,861(CFS)
Given pipe size = 18,00(ln,)
Calculated individual pipe flow = 16.861(CPS)
Normal flow depth in pipe = 11.14(in,)
Flow top width inside pipe = 17.48(ln.)
Critical depth could not be calculated.
Pipe flow velocity = 14,67(Ft/s)
Travel time through pipe = 0.11 min.
Time of concentration (TC) = 15,50 min,
4-4-+4-++4-4-+4-4-+4-4-4-4-4-4-+4-4-4-4-4-4-4-4-4-4-+++4-4-4-++4-+4-4-4-4-4-4-4-4-4-++4-4-4-++4-4-4-4-4-4-++4-4-4-4-4-4-4-
Process from Point/Station 160.000 to Point/Station 149,000
**** CONFLUENCE OF MAIN STREAMS ****
The following data inside Main Stream is listed:
In Main Stream number: 2
Stream flow area = 7.010(Ac)
Runoff from this stream = 16,861(CFS)
Time of concentration = 15.50 min.
Rainfall intensity = 3.555(in/Hr)
Summary of stream data:
Stream Flow rate TC Rainfall Intensity
NO, (CPS) (min) (in/Hr)
1 408.387 8,36 5,294
2 16.861 15.50 3.555
Qmax(l) =
1.000 * 1.000 * 408.387) 4-
1.000 * 0.539 * 16.861) 4- = 417.484
Qmax(2) =
0.672 * 1,000 * 408,387) 4-
1.000 * 1.000 * 16.861) 4- = 291.148
Total of 2 main streams to confluence:
Flow rates before confluence point:
408,387 16,861
Maximum flow rates at confluence using above data:
417.484 291,148
Area of streams before confluence:
105.120 7,010
Results of confluence:
Total flow rate = 417.484(CFS)
Time of concentration = 8.365 min.
Effective stream area after confluence = 112.130(Ac.)
Page 82
C605P1.OUT
Process from Point/Station 149.000 to Point/Station 162,000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
upstream point/station elevation = 277,43(Ft,)
Downstream point/station elevation = 268,42(Ft,)
Pipe length = 175.80(Ft.) Manning's N = 0,013
NO. of pipes = 1 Required pipe flow = 417.484(CFS)
Given pipe size = 60.00(in,)
Calculated individual pipe flow = 417,484(CFS)
Normal flow depth in pipe = 37.27(in.)
Flow top width inside pipe = 58,21(ln.)
Critical depth could not be calculated.
Pipe flow velocity = 32.57(Ft/s)
Travel time through pipe = 0,09 min.
Time of concentration (TC) = 8,45 min.
Process from Point/station 162,000 to Point/Station 163,000
**** PIPEFLOW TRAVEL TIME (user specified size) ****
upstream point/station elevation = 268,00(Ft,)
Downstream point/station elevation = 230.10(Ft,)
Pipe length = 324,30(Ft,) Manning's N = 0,013
NO, of pipes = 1 Required pipe flow = 417,484(CPS)
Given pipe size = 60.00(ln,)
Calculated individual pipe flow = 417,484(CFS)
Normal flow depth in pipe = 28,90(in,)
Flow top width inside pipe = 59,96(in,)
Critical depth could not be calculated.
Pipe flow velocity = 44,62(Ft/s)
Travel time through pipe = 0,12 min.
Time of concentration (TC) = 8,58 min.
Process from Point/Station 163,000 to Point/Station 168,000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
upstream point/station elevation = 229,10(Ft,)
Downstream point/station elevation = 227,00(Ft,)
Pipe length = 167,87(Ft.) Manning's N = 0.013
No. of pipes = 1 Required pipe flow = 417,484(CFS)
Given pipe size = 66.00(ln,)
NOTE: Normal flow is pressure flow in user selected pipe size.
The approximate hydraulic grade line above the pipe invert is
7.686(Ft,) at the headworks or inlet of the pipe(s)
Pipe friction loss = 2,594(Ft,)
Minor friction loss = 7,192(Ft,) K-factor = 1,50
Critical depth could not be calculated.
Pipe flow velocity = 17,57(Ft/s)
Travel time through pipe = 0.16 min.
Time of concentration (TC) = 8,73 min.
End of computations, total study area = 112.13 (Ac.)
Page 83
Basin 1
Main Line
Hydraulics
m C605P1.RES
******************************************************************************
PIPE-PLOW HVDRAULICS COMPUTER PROGRAM PACKAGE
(Reference: WSPG COMPUTER MODEL HYDRAULICS CRITERION)
(c) copyright 1982-2001 Advanced Engineering Software (aes)
Ver. 8.0 Release Date: 01/01/2001 License ID 1423
Analysis prepared by:
O'Day consultants. Inc.
2710 Loker Avenue west. Suite 100
carlsbad, CA 92008
Tel: 760-931-7700 Fax: 760-931-8680
************************** DESCRIPTION OF STUDY **************************
* CARLSBAD OAKS PHASE 3 *
* PROPOSED BASIN I - MAIN LINE *
* i:\961005\Hydrology\Phase3\hydraulics\c605Pl,OUT *
**************************************************************************
FILE NAME: C605Pl,DAT
TIME/DATE OF STUDY: 08:42 01/31/2008
******************************************************************************
GRADUALLY VARIED FLOW ANALYSIS FOR PIPE SYSTEM
NODAL POINT STATUS TABLE
(Note: "*" indicates nodal point data used.) UPSTREAM RUN DOWNSTREAM RUN NODE MODEL PRESSURE PRESSURE4-PLOW PRESSURE4-
NUMBER PROCESS HEAD(FT)
14.40*
MOMENTUM(POUNDS) DEPTH(FT) MOMENTUM(POUNDS)
168.00-
HEAD(FT)
14.40* 31488.93 2 87 27941.34
} FRICTION } HYDRAULIC JUMP
163,10-
JUNCTION
14,89 32222.42 2 37* 35130.91
163,00-
FRICTION
11,77 28563.23 2 51* 34927.01
162,10-JUNCTION
4,90 DC 20226.54 3 20* 26566.54
162,00-
FRICTION
4,91 DC 20226.56 3 21* 26490.39
149.00-
FRICTION
4,90 DC 19481.37 3 35* 25412.83
147,10-
JUNCTION
4,89 DC 19481.14 3 41* 23992.49
147.00-
FRICTION
4,89 DC 19327.53 3 39* 23935.19
144,10-
JUNCTION
4,89 DC 19327.53 3 55* 22954.30
144,00-FRICTION
5,80 19034.84 3 26* 22879.91
128,10-
JUNCTION
4,87 DC 17999.34 3 47* 21641.00
128,00-
FRICTION
9.05 17697.12 2 34* 21623.96
119.10-
JUNCTION
4.71 DC 12617.13 2 42* 20801.36
119.OO-
FRICTION
4.40 DC 13750.19 2 51* 20738,32
HS, 10-
JUNCTION
4,40 DC 13750.18 3 53* 15051.52
118,00-
FRICTION
6.60 13234.29 2 76* 14651.43
117.10-4.33 DC 11091.87
Page 1
4 15* 11137.35
C605Pl,RES
} JUNCTION
117.00-
FRICTION
7 06 10839.96 2 56* 10973.26
116,55-
JUNCTION
6 44 10222.42 2 58* 10866,49
116.50-
FRICTION
6 57 10235.08 2 53* 10900,47
116,10-
JUNCTION
4 16 DC 8058,06 3 19* 8912.20
116,OO-FRICTION 5 46 6910,09 2 07* 8385,71
HS,05-JUNCTION 3 70 DC 5682,80 2 13* 8127,25
115,00-FRICTION 3 98 5404.68 1 96* 8223,26
114,10-JUNCTION 3 65 DC 5320.31 2 30* 6922,12
114.00-FRICTION 4 72 5110,59 1 84* 6890.53
113,io-JUNCTION
3 50 DC 4394.25 2 61* 4923,29
ns, 00-FRICTION
4 79 4024.67 1. 76* 4581.70
112.10-JUNCTION 3 16 DC 3116,91 2. 40* 3437,37
112,00-FRICTION 4 01 2268,72 1. 21* 3147,92
112.51-JUNCTION 2 59 DC 1752,67 1. 29* 2934.43
112,50-
FRICTION
2 59 DC 1752,68 1. 28* 2958,27
111,10-JUNCTION 2 59 DC 1752.67 1. 67* 2214,52
111,00-FRICTION 3 36 1634.27 1. 23* 2196,08
104,10-JUNCTION 2 40 DC 1361.83 1. 35* 1977.27
104,00-FRICTION 1 97 DC 1465.54 1. 36* 1836.95
110.10-JUNCTION 1 97*Dc 1465.54 1. 97*Dc 1465.54
110,00-
FRICTION
8 25* 1736.06 1. 25 550.21
107,00-7 78* 1644,39 1. 69 DC 487.23
MAXIMUM NUMBER OF ENERGY BALANCES USED IN EACH PROFILE = 25
NOTE: STEADY FLOW HYDRAULIC HEAD-LOSS COMPUTATIONS BASED ON THE MOST
CONSERVATIVE FORMULAE FROM THE CURRENT LACFCD WSPG COMPUTER PROGRAM.
*************************************************************j^j^,^Vt«A^««i^,A«jV****
DOWNSTREAM PIPE FLOW CONTROL DATA:
NODE NUMBER = 168.00 FLOWLINE ELEVATION = 227.00
PIPE FLOW = 417.50 CFS PIPE DIAMETER = 66.00 INCHES
ASSUMED DOWNSTREAM CONTROL HGL = 241.400 FEET
NODE 168,00 : HGL = < 241,400>;EGL= < 246.195>;FLOWLINE= < 227.000>
******************************************************************************
FLOW PROCESS FROM NODE 168,00 TO NODE 163,10 IS CODE = 1
UPSTREAM NODE 163,10 ELEVATION = 229.10 (HYDRAULIC JUMP OCCURS)
CALCULATE FRICTION LOSSES(LACFCD):
PIPE FLOW = 417,50 CFS PIPE DIAMETER = 66,00 INCHES
Page 2
PIPE LENGTH = 167,87 FEET
C605Pl,RES
MANNING'S N = 0.01300
HYDRAULIC JUMP: DOWNSTREAM RUN ANALYSIS RESULTS
===> NORMAL PIPEFLOW IS PRESSURE FLOW
NORMAL DEPTH(FT) = 5.50 CRITICAL DEPTH(FT)
~~2T37
5,24
UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) =
GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION:
DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+
CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS)
0.000 2.368 42,658 30,642 35130,91 38.215 2.483 40,090 27,455 33125.13
76.670 2.597 37,805 24,804 31352,68
115.403 2.712 35,762 22,584 29780.54
154.460 2.827 33,928 20.712 28381,65
167.870 2,866 33,347 20,144 27941,34
HYDRAULIC JUMP: UPSTREAM RUN ANALYSIS RESULTS
DOWNSTREAM CONTROL ASSUMED PRESSURE HEAD(FT) = 14,40
PRESSURE FLOW PROFILE COMPUTED INFORMATION:
DISTANCE FROM
CONTROL(FT)
0,000
167,870
PRESSURE+
MOMENTUM(POUNDS)
31488,93
32222,41
PRESSURE VELOCITY SPECIFIC
HEAD(FT) (FT/SEC) ENERGY(FT)
14,400 17.573 19.195
14,895 17,573 19,690
END OF HYDRAULIC JUMP ANALYSIS---
PRESSURE4-M0MENTUM BALANCE OCCURS AT 104,02 FEET UPSTREAM OF NODE 168,00 |
DOWNSTREAM DEPTH =14.707 FEET, UPSTREAM CONJUGATE DEPTH = 2,559 FEET |
NODE 163.10 : HGL = < 231.468>;EGL= < 259.742>;FLOWLINE= < 229.100>
******************************************************************************
FLOW PROCESS FROM NODE
UPSTREAM NODE 163.00
163.10 TO NODE 163.00 IS CODE = 5
ELEVATION = 230.10 (FLOW IS SUPERCRITICAL)
CALCULATE JUNCTION LOSSES:
PIPE
UPSTREAM
DOWNSTREAM
LATERAL #1
LATERAL #2
Q5
FLOW
(CFS)
417,50
417.50
0.00
0.00
DIAMETER
(INCHES)
60.00
66,00
0.00
0.00
ANGLE
(DEGREES)
0.00
0.00
0.00
FLOWLINE
ELEVATION
230.10
229.10
0,00
0,00
0,00===Q5 EQUALS BASIN INPUT===
CRITICAL
DEPTH(FT,)
4.90
5.24
0.00
0.00
VELOCITY
(FT/SEC)
42.360
42,671
0.000
0.000
LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED:
DY=(Q2 *V2-Ql*Vl*COS(DELTAl)-Q3 *V3 *COS(DELTA3)-
Q4*V4*COS(DELTA4))/((Al4-A2)*16.1)4-FRICTION LOSSES
UPSTREAM: MANNING'S N = 0.01300; FRICTION SLOPE = 0.10172
DOWNSTREAM: MANNING'S N = 0.01300; FRICTION SLOPE = 0.10429
AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS 0.10301
JUNCTION LENGTH = 4.00 FEET
FRICTION LOSSES = 0.412 FEET ENTRANCE LOSSES = 0.000 FEET
JUNCTION LOSSES = (DY4-HVl-HV2) +(ENTRANCE LOSSES)
JUNCTION LOSSES = ( 0.729)+( 0.000) = 0.729
NODE 163.00 : HGL = < 232.608>;EGL= < 260,471>;FLOWLINE= < 230,100>
******************************************************************************
Page 3
FLOW PROCESS FROM NODE
UPSTREAM NODE 162.10
C605P1.RES
163,00 TO NODE 162.10 IS CODE = 1
ELEVATION = 268,00 (FLOW IS SUPERCRITICAL)
CALCULATE FRICTION LOSSES(LACFCD):
PIPE FLOW = 417.50 CFS PIPE DIAMETER = 60,00 INCHES
PIPE LENGTH = 324,30 FEET MANNING'S N = 0,01300
NORMAL DEPTH(FT) = 2,41 CRITICAL DEPTH(FT) =
UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 3.20
GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION:
4.90
DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+
CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUN
0.000 3.205 31,394 18,518 26566,54
4.714 3.173 31,760 18,846 26836,46
9,735 3.141 32,136 19,187 27114,82
15,092 3.109 32,522 19.543 27401,88
20,818 3.077 32,920 19,915 27697,93
26,951 3.046 33,328 20,304 28003.28
33,536 3,014 33,748 20.709 28318,24
40,623 2,982 34,179 21,133 28643,14
48,273 2,950 34,623 21,576 28978,34
56,558 2,918 35,080 22,039 29324,19
65,561 2,886 35,550 22,523 29681.08
75,388 2,854 36,034 23,029 30049.42
86.162 2.822 36,532 23.558 30429.63
98.042 2,790 37,045 24,113 30822.16
111.223 2,759 37,573 24,694 31227,47
125.960 2,727 38.117 25,302 31646,06
142.588 2,695 38,678 25,939 32078,46
161.559 2,663 39,257 26,608 32525,22
183.511 2.631 39,853 27,309 32986.91
209.373 2.599 40,468 28,045 33464,14
240.590 2,567 41,103 28,818 33957,58
279.582 2,535 41,758 29,629 34467,88
324.300 2,508 42,347 30,371 34927,01
NODE 162,10 : HGL = < 271,205>;EGL= < 286.518>;FLOWLINE= < 268,000>
******************************************************************************
FLOW PROCESS FROM NODE 162,10 TO NODE 162.00 IS CODE = 5
UPSTREAM NODE 162.00 ELEVATION = 268.42 (FLOW IS SUPERCRITICAL)
CALCULATE JUNCTION LOSSES:
PIPE
UPSTREAM
DOWNSTREAM
LATERAL #1
LATERAL #2
Q5
FLOW
(CPS)
417.50
417.50
0.00
0.00
DIAMETER
(INCHES)
60.00
60.00
0.00
0.00
ANGLE
(DEGREES)
0.00
0.00
0.00
FLOWLINE
ELEVATION
268.42
268.00
0,00
0.00
0.00===Q5 EQUALS BASIN INPUT===
CRITICAL
DEPTH(FT.)
4.90
4.90
0.00
0.00
VELOCITY
(FT/SEC)
31.300
31.404
0.000
0.000
LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED:
DY=(Q2*V2-Ql*Vl*COS(DELTAl)-Q3*V3*COS(DELTA3)-
Q4*V4*COS(DELTA4))/((Al-^A2)*16.1)4-FRICTION LOSSES
UPSTREAM: MANNING'S N = 0.01300; FRICTION SLOPE = 0.04637
DOWNSTREAM: MANNING'S N = 0.01300; FRICTION SLOPE = 0.04675
AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS 0,04656
JUNCTION LENGTH = 4.00 FEET
FRICTION LOSSES = 0.186 FEET ENTRANCE LOSSES = 0.000
JUNCTION LOSSES = (DY4-HV1-HV2) + (ENTRANCE LOSSES)
Page 4
FEET
C605P1.RES
JUNCTION LOSSES = ( 0.328)+( 0.000) = 0.328
NODE 162,00 : HGL = < 271.634>;EGL= < 286,847>;FL0WLINE= < 268,420>
*************************************************************************^^***
FLOW PROCESS FROM NODE
UPSTREAM NODE 149,00
162,00 TO NODE 149,00 IS CODE = 1
ELEVATION = 277.43 (FLOW IS SUPERCRITICAL)
CALCULATE FRICTION LOSSES(LACFCD):
PIPE FLOW = 417.50 CFS PIPE DIAMETER = 60,00 INCHES
PIPE LENGTH = 175,80 FEET MANNING'S N = 0.01300
NORMAL DEPTH(FT) = 3.11 CRITICAL DEPTH(FT) =
"iTis
4.90
UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) =
GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION:
DISTANCE FROM
CONTROL(FT)
0.000
8.270
16.944
26.056
35.650
45.770
56.473
67.821
79.888
92.762
106.547
121.369
137,383
154,779
173,799
175,800
FLOW DEPTH
(PT)
3,353
3,343
3,334
3,324
3,314
3,304
3,294
3.284
3.274
.264
.255
.245
.235
.225
3.215
3.214
3,
3,
3,
3,
3,
VELOCITY
(FT/SEC)
29,812
29,911
30,012
30,113
30,214
30,317
30,420
30,525
30,630
30,736
30,843
30.951
31,060
31,169
31,280
31.290
SPECIFIC
ENERGY(FT)
17,163
17,245
17.328
17.413
17.498
17.585
17.673
17.762
17.852
17,943
18,035
18.129
18.224
18.320
18.417
18,427
PRESSURE4-
MOMENTUM(POUNDS)
25412,83
25484,60
25557,05
25630,21
25704,05
25778,61
25853,88
25929,88
26006.60
26084,05
26162,25
26241,20
26320,90
26401,36
26482,60
26490.39
NODE 149,00 : HGL = < 280.783>;EGL= < 294.593>;FLOWLINE= < "277"430>
**********************************************^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
FLOW PROCESS FROM NODE
UPSTREAM NODE 147.10
149.00 TO NODE 147.10 IS CODE = 1
ELEVATION = 279.17 (FLOW IS SUPERCRITICAL)
CALCULATE FRICTION LOSSES(LACFCD):
PIPE FLOW = 408,40 CFS PIPE DIAMETER = 60,00 INCHES
PIPE LENGTH = 34.00 FEET MANNING'S N = 0.01300
NORMAL DEPTH(FT) = 3.06 CRITICAL DEPTH(FT) =
UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 3.41
GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION:
4.89
DISTANCE FROM
CONTROL(FT)
0.000
7.672
15.740
24.239
33.211
34,000
DEPTH VELOCITY SPECIFIC
(FT) (FT/SEC) ENERGY(FT)
3.410 28.619 16.136
3,396 28.750 16.239
3,382 28.882 16.343
3,368 29.016 16.450
3,355 29.151 16.558
3,353 29.162 16.567
PRESSURE+
MOMENTUM(POUNDS)
23992.49
24083.62
24176.00
24269.64
24364.56
24372.51
NODE 147.10 : HGL = < 282.580>;EGL= < 295.306>;FLOWLINE= <
Page 5
279.170>
m C605P1.RES
******************************************************************************
FLOW PROCESS FROM NODE
UPSTREAM NODE 147.00
147,10 TO NODE 147,00 IS CODE = 5
ELEVATION = 279.50 (FLOW IS SUPERCRITICAL)
CALCULATE JUNCTION LOSSES:
PIPE
UPSTREAM
DOWNSTREAM
LATERAL #1
LATERAL #2
Q5
FLOW DIAMETER ANGLE FLOWLINE
(CFS) (INCHES) (DEGREES) ELEVATION
406.50 60,00 0,00 279.50
408,40 60,00 - 279,17
1,90 18,00 90.00 282,67
0,00 0.00 0.00 0,00
0.00===Q5 EQUALS BASIN INPUT===
CRITICAL
DEPTH(FT,)
4,89
4,89
0,52
0,00
VELOCITY
(FT/SEC)
28.715
28,628
3,500
0,000
LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED:
DY=(Q2*V2-Ql*Vl*COS(DELTAl)-Q3*V3*COS(DELTA3)-
Q4*V4*COS(DELTA4))/((Al4-A2)*16,1)4-FRICTI0N LOSSES
UPSTREAM: MANNING'S N = 0,01300; FRICTION SLOPE = 0,03795
DOWNSTREAM: MANNING'S N = 0,01300; FRICTION SLOPE = 0,03759
AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS 0,03777
JUNCTION LENGTH = 4,00 FEET
FRICTION LOSSES = 0,151 FEET ENTRANCE LOSSES = 0,000 FEET
JUNCTION LOSSES = (DY4-HVl-HV2) +(ENTRANCE LOSSES)
JUNCTION LOSSES = ( 0.384)4-( 0,000) = 0.384
NODE 147.00 : HGL = < 282.887>;EGL= < 295.691>;FLOWLINE= < 279.500>
******************************************************************************
FLOW PROCESS FROM NODE
UPSTREAM NODE 144,10
147,00 TO NODE 144,10 IS CODE = 1
ELEVATION = 283,17 (FLOW IS SUPERCRITICAL)
CALCULATE FRICTION LOSSES(LACFCD):
PIPE FLOW = 406,50 CFS PIPE DIAMETER = 60,00 INCHES
PIPE LENGTH = 72,13 FEET MANNING'S N = 0.01300
NORMAL DEPTH(FT) = 3.06 CRITICAL DEPTH(FT) =
UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 3,55
GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION:
4.89
DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE4-
CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS)
0.000 3.548 27.277 15.108 22954.30
7.009 3.528 27.440 15,228 23065.28
14.411 3.509 27.607 15,350 23178.43
22.240 3.489 27.776 15,476 23293.80
30.537 3.469 27.948 15,606 23411.43
39.348 3.450 28.122 15,738 23531.34
48.727 3.430 28.300 15,874 23653.58
58.736 3.411 28,480 16,014 23778.19
69.447 3.391 28,663 16.157 23905.21
72.130 3.387 28,707 16,191 23935.19
NODE 144.10 : HGL = < 286.718>;EGL= < 298.278>;FLOWLINE= < 283.170>
******************************************************************************
FLOW PROCESS FROM NODE 144.10 TO NODE 144.00 IS CODE = 5
UPSTREAM NODE 144.00 ELEVATION = 283.50 (FLOW IS SUPERCRITICAL)
CALCULATE JUNCTION LOSSES:
PIPE FLOW DIAMETER ANGLE FLOWLINE
(CFS) (INCHES) (DEGREES) ELEVATION
Page 6
CRITICAL
DEPTH(FT.)
VELOCITY
(FT/SEC)
UPSTREAM 389.70 60.00
DOWNSTREAM 406.50 60.00
LATERAL #1 16,80 24,00
LATERAL #2 0,00 0,00
Q5 0,00===Q5 EQUALS BASIN INPUT===
C605P1.RES
0.00 283.50 4,87
283,17 4.89
90.00 286,17 1,48
0,00 0,00 0,00
28,696
27,285
6,752
0,000
LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED:
DY=(Q2*V2-Ql*Vl*COS(DELTAl)-Q3*V3*COS(DELTA3)-
Q4*V4*COS(DELTA4))/( (Al4-A2) *16.1)4-FRICTION LOSSES
UPSTREAM: MANNING'S N = 0,01300; FRICTION SLOPE = 0,03863
DOWNSTREAM: MANNING'S N = 0,01300; FRICTION SLOPE = 0,03356
AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS 0,03609
JUNCTION LENGTH = 4.00 FEET
FRICTION LOSSES = 0,144 FEET ENTRANCE LOSSES = 0.000
JUNCTION LOSSES = (DY+HVl-HV2)4-(ENTRANCE LOSSES)
JUNCTION LOSSES = ( 1.273)+( 0.000) = 1.273
NODE 144,00 : HGL = < 286.765>;EGL= < 299.551>;FLOWLINE= < 283,500>
******************************************************************************
PEET
FLOW PROCESS FROM NODE
UPSTREAM NODE 128,10
144.00 TO NODE 128,10 IS CODE = 1
ELEVATION = 294.83 (FLOW IS SUPERCRITICAL)
CALCULATE FRICTION LOSSES(LACFCD):
PIPE FLOW = 389.70 CFS PIPE DIAMETER = 60.00 INCHES
PIPE LENGTH = 273,71 FEET MANNING'S N = 0,01300
NORMAL DEPTH(FT) = 3,19 CRITICAL DEPTH(FT) =
UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 3,47
4,87
GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION:
DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE4-
CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUN[
0,000 3.467 26.812 14,637 21641.00
8.071 3.456 26.907 14,705 21703.17
16.545 3.445 27.004 14,775 21766,04
25,460 3.434 27.102 14,846 21829,62
34,855 3,422 27.200 14,918 21893.92
44,778 3,411 27.299 14,991 21958.94
55.284 3.400 27.399 15,065 22024,68
66,436 3.389 27.501 15,140 22091,17
78.308 3,378 27.603 15.216 22158,40
90.987 3,366 27.706 15.293 22226,37
104,579 3,355 27,810 15.372 22295,11
119.209 3.344 27,915 15.451 22364,62
135.033 3.333 28,020 15.532 22434.89
152.241 3.322 28.127 15.614 22505,95
171.075 3.310 28.235 15.697 22577,80
191.847 3.299 28.344 15.782 22650.45
214.965 3.288 28,454 15,868 22723.91
240.984 3,277 28,565 15,955 22798.18
270.682 3.266 28,677 16,043 22873,28
273.710 3.265 28.687 16.051 22879,91
NODE 128,10 : HGL = < 298,297>;EGL= < 309,467>;FLOWLINE= < 294.830>
******************************************************************************
FLOW PROCESS FROM NODE 128,10 TO NODE 128,00 IS CODE = 5
UPSTREAM NODE 128,00 ELEVATION = 295.16 (FLOW IS SUPERCRITICAL)
CALCULATE JUNCTION LOSSES:
Page 7
C605Pl,RES
PIPE
UPSTREAM
DOWNSTREAM
LATERAL #1
LATERAL #2
Q5
FLOW
(CPS)
313.10
389,70
56,10
20,50
DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY
(INCHES)
60,00
60,00
36,00
24,00
(DEGREES)
0,00
90.00
90.00
ELEVATION
295.16
294.83
296.83
297.83
DEPTH(FT,)
4.71
4.
2.
1.
87
43
62
(FT/SEC)
34,723
26,820
9,152
7,503
0.00===Q5 EQUALS BASIN INPUT===
LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED:
DY=(Q2*V2-Ql*Vl*COS(DELTAl)-Q3*V3*COS(DELTA3)-
Q4*V4*COS(DELTA4))/((Al+A2)*16,1)+FRICTI0N LOSSES
UPSTREAM: MANNING'S N = 0,01300; FRICTION SLOPE = 0,07260
DOWNSTREAM: MANNING'S N = 0.01300; FRICTION SLOPE = 0,03274
AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS 0,05267
JUNCTION LENGTH = 4.00 FEET
FRICTION LOSSES = 0,211 FEET ENTRANCE LOSSES = 0.000 FEET
(DY+HVl-HV2)4-(ENTRANCE LOSSES)
( 6,755)4-( 0.000) = 6,755
JUNCTION LOSSES =
JUNCTION LOSSES =
NODE 128,00 : HGL = < 297,500>;EGL= < 316.221>;FLOWLINE= < 295,160>
******************************
FLOW PROCESS FROM NODE
UPSTREAM NODE 119.10
128,00 TO NODE 119,10 IS CODE = 1
ELEVATION = 301,00 (FLOW IS SUPERCRITICAL)
CALCULATE FRICTION LOSSES(LACFCD):
PIPE FLOW = 313.10 CFS PIPE DIAMETER = 60,00 INCHES PIPE LENGTH = 63,92 FEET MANNING'S N = 0, 01300
NORMAL DEPTH(FT) 2,19 CRITICAL DEPTH(FT) 4,71
UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 2.42
GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION:
DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE4-
CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS)
0,000 2,417 33,283 19.629 20801,36
6.015 2,408 33,443 19.786 20893,22
12.326 2.399 33,605 19,946 20986,03
18.961 2.390 33,768 20,107 21079.81
25.949 2,381 33.933 20.272 21174.56
33.325 2,372 34,099 20,438 21270,30
41.130 2,363 34.267 20,608 21367,04
49.410 2,354 34.436 20,780 21464,79
58.219 2,345 34.607 20,954 21563,57
63.920 2,340 34.712 21,061 21623,96
NODE 119.10 : HGL = < 303,417>;EGL= < 320,629>;FLOWLINE= < 301.000>
******************************************************************************
FLOW PROCESS FROM NODE
UPSTREAM NODE 119.00
119.10 TO NODE 119.00 IS CODE = 5
ELEVATION = 301.50 (FLOW IS SUPERCRITICAL)
CALCULATE JUNCTION LOSSES:
PIPE
UPSTREAM
DOWNSTREAM
LATERAL #1
LATERAL #2
Q5
FLOW
(CPS)
307.90
313.10
3.30
1.90
DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY
(INCHES)
54.00
60.00
18.00
18.00
(DEGREES) ELEVATION
0.00
90.00
90.00
301.50
301.00
304.00
304.00
DEPTH(FT,)
4.40
4.71
0.69
0.52
(FT/SEC)
33.728
33.294
4.142
3.500
0.00===Q5 EQUALS BASIN INPUT===
Page 8
C605Pl,RES
LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED: DY=(Q2*V2-Ql*Vl*COS(DELTAl)-Q3*V3*COS(DELTA3)-
Q4*V4*COS (DELTA4))/((A14-A2) * 16,1)+FRICTION LOSSES
UPSTREAM: MANNING'S N = 0,01300; FRICTION SLOPE = 0.06811
DOWNSTREAM: MANNING'S N = 0,01300; FRICTION SLOPE = 0.06485
AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS 0,06648
JUNCTION LENGTH = 4.00 FEET
FRICTION LOSSES = 0,266 FEET ENTRANCE LOSSES = 0,000 FEET
JUNCTION LOSSES = (DY4-HVl-HV2)4-(ENTRANCE LOSSES)
JUNCTION LOSSES = ( l,047)+( 0,000) = 1,047
NODE 119,00 : HGL = < 304,012>;EGL= < 321,677>;FLOWLINE= < 301,500>
******************************************************************************
FLOW PROCESS FROM NODE
UPSTREAM NODE 118,10
119.00 TO NODE 118,10 IS CODE = 1
ELEVATION = 326,13 (FLOW IS SUPERCRITICAL)
CALCULATE FRICTION LOSSES(LACFCD):
PIPE FLOW = 307,90 CFS PIPE DIAMETER = 54,00 INCHES
PIPE LENGTH = 310,00 FEET MANNING'S N = 0,01300
NORMAL DEPTH(FT) = 2.40 CRITICAL DEPTH(FT) = 4,40
UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) 3,53
GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION:
DISTANCE FROM
CONTROL(FT)
0,000
3,171
6,621
10,374
14,461
18,917
23.783
29,106
34,942
41,356
48,429
56,256
64,955
74,672
85.593
97,956
112,076
128.379
147.464
170.208
197.973
233.040
279.689
310.000
FLOW DEPTH
(FT)
3.532
3.487
3.442
3.396
3.351
3.305
3.260
3.214
3.169
3.123
.078
,032
,987
942
896
2,851
2,805
2,760
2,714
2.669
2.623
2.578
2.532
2,512
VELOCITY
(FT/SEC)
22,982
23.276
23,583
23,903
24,237
24,585
24.947
25,324
25.717
26,127
26.554
26,998
27.462
27,946
28.450
28.977
29,526
30.100
30,700
31,327
31.982
32,668
33.386
33,718
SPECIFIC
ENERGY(FT)
11,739
11,905
12.083
12.274
12.478
12.696
12.929
13.179
13.445
13.729
14.033
14.358
14,705
15,076
15.473
15.897
16.351
16.837
17.358
17.917
18,516
19.159
19.851
20.177
PRESSURE4-
MOMENTUM(POUNDS)
15051,52
15189.57
15335,61
15489,90
15652.73
15824,42
16005,31
16195,77
16396.17
16606,96
16828.57
17061,50
17306,26
17563,41
17833.57
18117.37
18415.51
18728,74
19057,88
19403,78
19767.40
20149,75
20551.93
20738.32
NODE 118,10 : HGL = < 329,663>;EGL= < 337,869>;FL0WLINE= < 326,130>
******************************************************************************
FLOW PROCESS FROM NODE 118,10 TO NODE 118.00 IS CODE = 5
UPSTREAM NODE 118.00 ELEVATION = 326,46 (FLOW IS SUPERCRITICAL)
CALCULATE JUNCTION LOSSES:
PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY
(CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT,) (FT/SEC)
Page 9
• UPSTREAM
DOWNSTREAM
LATERAL #1
LATERAL #2
Q5
270.
307.
50
90
37.40
0.00
54.00
54.00
30,00
0,00
C605Pl,RES
0,00
60,00
0,00
326.46
326.13
328.13
0.00
4.33
4.40
2.07
0.00
26,499
22,989
8,608
0,000
0.00===Q5 EQUALS BASIN INPUT===
03941
02666
0.000 FEET
LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED:
DY=(Q2*V2-Ql*Vl*COS(DELTAl)-Q3*V3*COS(DELTA3)-
Q4*V4*COS(DELTA4))/((Al4-A2) *16,1)4-FRICTION LOSSES
UPSTREAM: MANNING'S N = 0,01300; FRICTION SLOPE = 0,
DOWNSTREAM: MANNING'S N = 0,01300; FRICTION SLOPE = 0.
AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS 0,03303
JUNCTION LENGTH = 4.00 FEET
FRICTION LOSSES = 0.132 FEET ENTRANCE LOSSES =
JUNCTION LOSSES = (DY4-HVl-HV2)4^(ENTRANCE LOSSES)
JUNCTION LOSSES = ( 2.251)4-( 0,000) = 2,251
NODE 118,00 : HGL = < 329.216>;EGL= < 340,120>;FLOWLINE= < 326,460>
******************************************************************************
FLOW PROCESS FROM NODE 118,00 TO NODE 117,10 IS CODE = 1
UPSTREAM NODE 117.10 ELEVATION = 340,67 (FLOW IS SUPERCRITICAL)
CALCULATE FRICTION LOSSES(LACFCD):
PIPE FLOW = 270,50 CFS PIPE DIAMETER = 54.00 INCHES
PIPE LENGTH = 310,82 FEET MANNING'S N = 0,01300
NORMAL DEPTH(FT) = 2.63 CRITICAL DEPTH(FT) =
UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 4,15
4,33
GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION:
DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE4-
CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS)
0,000 4,153 17,629 8.982 11137.35
1,242 4,092 17,806 9.018 11171.95
2,839 4.031 18,000 9,064 11215.73
4,804 3.969 18,209 9,121 11268.58
7,157 3,908 18,434 9,188 11330.53
9,928 3.847 18,676 9,267 11401,66
13,150 3,786 18,934 9,356 11482.12
16,867 3,725 19.209 9,458 11572,13
21,133 3.664 19.501 9,573 11671,96
26,012 3.603 19,810 9,701 11781,92
31,582 3.542 20,139 9,843 11902,37
37,942 3,481 20,486 10,001 12033,74
45,210 3.420 20,853 10,176 12176,49
53,538 3.358 21,242 10.369 12331,14
63.116 3.297 21,652 10.582 12498,28
74.191 3,236 22.086 10.815 12678,54
87,091 3,175 22.544 11.072 12872,62
102,259 3,114 23.028 11.354 13081,31
120,321 3,053 23.540 11.663 13305,45
142.193 2,992 24.082 12.002 13545,98
169.299 2.931 24,654 12.375 13803,93
204,027 2.870 25,260 12.784 14080.45
250.857 2,809 25,902 13.233 14376.77
310,820 2.756 26.491 13.660 14651.43
NODE 117,10 : HGL = < 344.823>;EGL= < 349.652>;FLOWLINE= < 340.670>
******************************************************************************
Page 10
C605Pl,RES
FLOW PROCESS FROM NODE 117,10 TO NODE 117.00 IS CODE = 5
UPSTREAM NODE 117,00 ELEVATION = 341,00 (FLOW IS SUPERCRITICAL)
CALCULATE JUNCTION LOSSES:
PIPE
UPSTREAM
DOWNSTREAM
LATERAL #1
LATERAL #2
Q5
FLOW DIAMETER ANGLE
(CFS) (INCHES) (DEGREES)
223,10 54,00 0,00
270.50 54,00
44,70 36.00 90,00
2,70 30,00 90,00
FLOWLINE
ELEVATION
341,00
340,67
342.17
342,67
CRITICAL
DEPTH(FT,)
4,17
4.33
2.18
0,54
VELOCITY
(FT/SEC)
23,900
17,635
8,132
0.864
0.00===Q5 EQUALS BASIN INPUT===
LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED:
DY=(Q2 *V2-Ql*Vl*COS(DELTAl)-Q3*V3*COS(DELTA3)-
Q4*V4*COS(DELTA4))/( (Al4-A2) *16.1)4-FRICTION LOSSES
UPSTREAM: MANNING'S N = 0.01300; FRICTION SLOPE = 0,03374
DOWNSTREAM: MANNING'S N = 0.01300; FRICTION SLOPE = 0,01640
AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS 0.02507
JUNCTION LENGTH = 4,00 FEET
FRICTION LOSSES = 0.100 FEET ENTRANCE LOSSES = 0.000 FEET
JUNCTION LOSSES = (DY4-HV1-HV2)4-(ENTRANCE LOSSES)
JUNCTION LOSSES = ( 2,777)4-( 0,000) = 2,777
NODE 117,00 : HGL = < 343,558>;EGL= < 352,428>;FLOWLINE= < 341,000>
******************************************************************************
FLOW PROCESS FROM NODE 117,00 TO NODE 116,55 IS CODE = 1
UPSTREAM NODE 116.55 ELEVATION = 341,90 (FLOW IS SUPERCRITICAL)
CALCULATE FRICTION LOSSES(LACFCD):
PIPE FLOW = 223,10 CFS PIPE DIAMETER = 54,00 INCHES
PIPE LENGTH = 21,58 FEET MANNING'S N = 0.01300
NORMAL DEPTH(FT) = 2.40 CRITICAL DEPTH(FT) =
UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 2,58
4,17
GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION:
DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE4-
CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS)
0,000 2,583 23.612 11.246 10866.49
6.104 2,576 23.696 11.300 10898,20
12,506 2.568 23.780 11.354 10930,19
19,232 2.561 23.865 11.410 10962,48
21,580 2.558 23.893 11.428 10973,26
NODE 116.55 : HGL = < 344,483>;EGL= < 353,146>;FLOWLINE= < 341,900>
******************************************************************************
FLOW PROCESS FROM NODE 116,55 TO NODE 116,50 IS CODE = 5
UPSTREAM NODE 116.50 ELEVATION = 341.90 (FLOW IS SUPERCRITICAL)
CALCULATE JUNCTION LOSSES:
PIPE
UPSTREAM
DOWNSTREAM
LATERAL #1
LATERAL #2
Q5
FLOW
(CPS)
220.90
223.10
2.20
0.00
DIAMETER
(INCHES)
54.00
54,00
18,00
0,00
ANGLE
(DEGREES)
0.00
90.00
0.00
FLOWLINE
ELEVATION
341.90
341.90
343.40
0,00
CRITICAL
DEPTH(FT.)
4.16
4.17
0.56
0.00
VELOCITY
(FT/SEC)
24.009
23.620
1.655
0.000
0.00===Q5 EQUALS BASIN INPUT===
LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED:
Page 11
m C605P1.RES
DY=(Q2*V2-Ql*Vl*COS(DELTAl)-Q3*V3*COS(DELTA3)-
Q4*V4*COS(DELTA4))/( (Al4-A2) * 16,1)4-FRICTION LOSSES
UPSTREAM: MANNING'S N = 0.01300; FRICTION SLOPE = 0,03435
DOWNSTREAM: MANNING'S N = 0,01300; FRICTION SLOPE = 0.03272
AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS 0.03354
JUNCTION LENGTH = 1.00 FEET
FRICTION LOSSES = 0,034 FEET ENTRANCE LOSSES = 0,000 FEET
JUNCTION LOSSES = (DY4-HV1-HV2)4-(ENTRANCE LOSSES)
JUNCTION LOSSES = ( 0,233)4-( 0.000) = 0.233
NODE 116.50 : HGL = < 344.428>;EGL= < 353.379>;FLOWLINE= < 341.900>
******************************************************************************
FLOW PROCESS FROM NODE
UPSTREAM NODE 116.10
116,50 TO NODE 116.10 IS CODE = 1
ELEVATION = 351.00 (FLOW IS SUPERCRITICAL)
CALCULATE FRICTION LOSSES(LACFCD):
PIPE FLOW = 220,90 CFS PIPE DIAMETER = 54,00 INCHES
PIPE LENGTH = 218.77 FEET MANNING'S N = 0,01300
NORMAL DEPTH(FT) = 2.38 CRITICAL DEPTH(FT) = 4,16
UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 3.19
GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION:
DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE4-
CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS)
0,000 3,187 18,337 8.411 8912.20
3,525 3.155 18,540 8.495 8975.14
7,325 3,123 18.749 8.584 9040.92
11,426 3.091 18.964 8.678 9109,62
15.859 3.058 19,186 8.778 9181,31
20,656 3,026 19,414 8.882 9256.11
25,859 2.994 19,649 8.993 9334,09
31.511 2,962 19.891 9.110 9415,38
37,668 2.930 20.141 9.233 9500,06
44.393 2,898 20.398 9.362 9588.26
51.762 2,866 20.662 9.499 9680,10
59.868 2.834 20.935 9.643 9775,70
68.822 2,801 21.217 9.796 9875,20
78,765 2,769 21.507 9,956 9978.73
89,874 2,737 21.806 10,125 10086,43
102.375 2,705 22.115 10.304 10198.47
116,568 2,673 22.433 10,492 10315.01
132,860 2,641 22.762 10.691 10436,22
151,819 2.609 23.102 10.901 10562.28
174.278 2,576 23.452 11.122 10693,38
201.533 2,544 23.814 11.356 10829.73
218.770 2,528 24.001 11.479 10900,47
NODE 116.10 : HGL = < 354.187>;EGL= < 359.411>;FLOWLINE= < 351.000>
******************************************************************************
FLOW PROCESS FROM NODE 116.10 TO NODE 116.00 IS CODE = 5
UPSTREAM NODE 116.00 ELEVATION = 352.00 (FLOW IS SUPERCRITICAL)
CALCULATE JUNCTION LOSSES:
PIPE
UPSTREAM
DOWNSTREAM
LATERAL #1
FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY
(CFS) (INCHES) (DEGREES) ELEVATION DEPTH(FT.) (FT/SEC)
165.00 48.00 0.00 352.00 3.70 25.093
220.90 54.00 - 351.00 4.16 18.342
55.90 36.00 90.00 353.00 2.42 9.133
Page 12
m C605Pl,RES
LATERAL #2 0,00 0.00 0.00 0,00
Q5 0,00===Q5 EQUALS BASIN INPUT===
0,00 0,000
JUNCTION LENGTH =
FRICTION LOSSES =
LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED:
DY=(Q2*V2-Ql*Vl*COS(DELTAl)-Q3*V3*COS(DELTA3)-
Q4*V4*COS(DELTA4))/((Al4-A2)*16.1)4-FRICTION LOSSES
UPSTREAM: MANNING'S N = 0,01300; FRICTION SLOPE = 0,04677
DOWNSTREAM: MANNING'S N = 0,01300; FRICTION SLOPE = 0.01747
AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS 0,03212
4,00 FEET
0.128 FEET ENTRANCE LOSSES = 0.000 FEET
JUNCTION LOSSES = (DY+HVl-HV2)4-(ENTRANCE LOSSES)
JUNCTION LOSSES = ( 4.439)4-( 0.000) = 4.439
NODE 116.00 : HGL = < 354.073>;EGL= < 363.851>;FLOWLINE= < 352.000>
******************************************************************************
FLOW PROCESS FROM NODE 116.00 TO NODE 115.05 IS CODE = 1
UPSTREAM NODE 115,05 ELEVATION = 354,43 (FLOW IS SUPERCRITICAL)
CALCULATE FRICTION LOSSES(LACFCD):
PIPE FLOW = 165,00 CFS PIPE DIAMETER = 48,00 INCHES
PIPE LENGTH = 40,47 FEET MANNING'S N = 0.01300
NORMAL DEPTH(FT) = 1,93 CRITICAL DEPTH(FT) =
UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 2.13
3.70
GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION:
DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+
CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS)
0.000 2,133 24,199 11,232 8127,25
4.683 2.125 24.317 11,313 8161,52
9.601 2,117 24.436 11,395 8196.18
14.776 2.109 24.557 11.478 8231.24
20,233 2,100 24.678 11.563 8266.71
25,999 2,092 24.801 11.649 8302.60
32.105 2,084 24.925 11.737 8338.91
38,589 2.075 25.051 11.826 8375.63
40,470 2,073 25.085 11.851 8385.71
m
NODE 115.05 : HGL = < 356.563>;EGL= < 365,662>;FLOWLINE= < 354,430>
******************************************************************************
FLOW PROCESS FROM NODE 115.05 TO NODE 115.00 IS CODE = 5
UPSTREAM NODE 115.00 ELEVATION = 354.99 (FLOW IS SUPERCRITICAL)
CALCULATE JUNCTION LOSSES:
PIPE
UPSTREAM
DOWNSTREAM
LATERAL #1
LATERAL #2
Q5
FLOW
(CFS)
158.00
165.00
4.00
3.00
DIAMETER
(INCHES)
48.00
48.00
18.00
18.00
ANGLE
(DEGREES)
0.00
90.00
90.00
FLOWLINE
ELEVATION
354.99
354.43
355.43
356.24
CRITICAL
DEPTH(FT.)
3.65
3.70
0,77
0,66
VELOCITY
(FT/SEC)
25,822
24,206
2,420
4.018
0.00===Q5 EQUALS BASIN INPUT===
LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED:
DY=(Q2*V2-Ql*Vl*COS(DELTAl)-Q3*V3*COS(DELTA3)-
Q4*V4*COS(DELTA4))/((Al+A2)*16.1)4-FRICTION LOSSES
UPSTREAM: MANNING'S N = 0.01300; FRICTION SLOPE = 0.
DOWNSTREAM: MANNING'S N = 0.01300; FRICTION SLOPE = 0.
AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS 0.04723
Page 13
05195
04252
JUNCTION LENGTH
FRICTION LOSSES
JUNCTION LOSSES
JUNCTION LOSSES
C605P1.RES
10.03 FEET
0,474 FEET ENTRANCE LOSSES = 0,000 FEET
(DY4-HVl-HV2)4-(ENTRANCE LOSSES)
( 1.641)4-( 0,000) = 1.641
NODE 115.00 : HGL = < 356.949>;EGL= < 367.303>;FLOWLINE= < 354.990>
******************************************************************************
FLOW PROCESS FROM NODE 115.00 TO NODE 114.10 IS CODE = 1
UPSTREAM NODE 114.10 ELEVATION = 372.92 (FLOW IS SUPERCRITICAL)
CALCULATE FRICTION LOSSES(LACFCD):
PIPE FLOW = 158.00 CFS PIPE
PIPE LENGTH = 329.68 FEET
DIAMETER = 48.00 INCHES
MANNING'S N = 0,01300
NORMAL DEPTH(FT) = 1.93 CRITICAL DEPTH(FT) = 3,65
UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 2.30
GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION:
DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE4-
CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS)
0,000 2,303 21 089 9 213 6922.12
4,005 2,288 21 255 9 308 6966.11
8,241 2,273 21 424 9 405 7011,02
12,728 2,258 21 596 9 505 7056,87
17,490 2,244 21 771 9 608 7103.67
22,555 2,229 21.948 9 714 7151.45
27,955 2.214 22 129 9 823 7200,23
33.727 2,199 22 313 9 935 7250,03
39.913 2,184 22 501 10 051 7300,88
46.566 2,170 22 691 10 170 7352.79
53.745 2,155 22 885 10 292 7405,78
61.526 2,140 23 083 10 419 7459.90
69.998 2,125 23 283 10 548 7515.15
79.274 2.110 23 488 10 682 7571.57
89.494 2,096 23 696 10 820 7629.17
100.840 2,081 23 908 10 962 7688.00
113.551 2,066 24 124 11 109 7748.07
127.953 2,051 24 344 11 260 7809,43
144.499 2,036 24 568 11 415 7872.08
163.854 2,022 24 797 11 575 7936.08
187.052 2.007 25 029 11 740 8001.45
215.822 1.992 25 266 11 911 8068.23
253.405 1.977 25 508 12 087 8136.44
307,089 1,962 25 754 12 268 8206.13
329,680 1.959 25 814 12 313 8223.26
NODE 114.10 : HGL = < 375,223>;EGL= < 382,133>;FLOWLINE= < 372,920>
******************************************************************************
FLOW PROCESS FROM NODE 114,10 TO NODE 114,00 IS CODE = 5
UPSTREAM NODE 114.00 ELEVATION = 373.25 (FLOW IS SUPERCRITICAL)
CALCULATE JUNCTION LOSSES;
PIPE
UPSTREAM
DOWNSTREAM
LATERAL #1
LATERAL #2
Q5
FLOW
(CPS)
138.90
158.00
19.10
0.00
DIAMETER
(INCHES)
48.00
48,00
24.00
0.00
ANGLE FLOWLINE
(DEGREES) ELEVATION
0.00 373.25
372,92
374.92
0.00
90.00
0.00
0.00===Q5 EQUALS BASIN INPUT===
Page 14
CRITICAL
DEPTH(FT.)
3.50
3,65
1.57
0.00
VELOCITY
(FT/SEC)
24,582
21,096
7.211
0.000
C605P1.RES
LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED:
DY=(Q2*V2-Ql*Vl*COS(DELTAl)-Q3*V3*COS(DELTA3)-
Q4*V4*COS(DELTA4))/((Al4-A2)*16. D+FRICTION LOSSES
UPSTREAM: MANNING'S N = 0.01300; FRICTION SLOPE = 0.04972
DOWNSTREAM: MANNING'S N = 0,01300; FRICTION SLOPE = 0,03048
AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS 0,04010
JUNCTION LENGTH = 4,00 FEET
FRICTION LOSSES = 0.160 FEET ENTRANCE LOSSES = 0,000 FEET
JUNCTION LOSSES = (DY+HVl-HV2)4-(ENTRANCE LOSSES)
JUNCTION LOSSES = ( 2,341)+( 0,000) = 2,341
NODE 114,00 : HGL = < 375.092>;EGL= < 384,474>;FLOWLINE= < 373.250>
******************************************************************************
FLOW PROCESS FROM NODE 114.00 TO NODE 113,10 IS CODE = 1
UPSTREAM NODE 113.10 ELEVATION = 386,00 (FLOW IS SUPERCRITICAL)
CALCULATE FRICTION LOSSES(LACFCD):
PIPE FLOW = 138,90 CFS PIPE DIAMETER = 48,00 INCHES
PIPE LENGTH = 218.46 PEET MANNING'S N = 0.01300
NORMAL DEPTH(FT) = 1.76 CRITICAL DEPTH(FT) =
UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 2.61
3.50
GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION:
DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+
CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNC
0,000 2,610 15,990 6,582 4923,29
2.090 2.576 16.233 6,670 4970,36
4.366 2.542 16.484 6,764 5020,09
6.848 2.508 16,745 6,864 5072,59
9.556 2.474 17,015 6.972 5127,96
12,515 2,440 17,296 7.088 5186.33
15,753 2,406 17.587 7.212 5247.83
19.303 2.372 17.889 7.344 5312.59
23.205 2.338 18,203 7.486 5380.75
27,504 2.304 18.529 7.638 5452.49
32,256 2.270 18.868 7,801 5527.95
37,527 2.236 19,220 7,976 5607.33
43.399 2,202 19.586 8.163 5690.80
49,973 2.168 19.968 8,363 5778.58
57,379 2.134 20,365 8,578 5870.87
65,781 2.100 20,778 8,808 5967.93
75.398 2.066 21.209 9.055 6069.98
86,525 2.032 21.659 9.321 6177.32
99,577 1.998 22.128 9,606 6290.22
115.162 1.964 22,618 9,913 6409.01
134,223 1.930 23,131 10,243 6534.02
158,340 1.896 23,666 10,598 6665.62
190.478 1.862 24,226 10,981 6804.20
218,460 1.842 24,574 11,224 6890.53
NODE 113.10 • HGL = < 388, 610>;EGL= < 392,582>;FLOWLINE= < 386.000:
******************************************************************************
FLOW PROCESS FROM NODE 113.10 TO NODE 113.00 IS CODE = 5
UPSTREAM NODE 113,00 ELEVATION = 386,33 (FLOW IS SUPERCRITICAL)
CALCULATE JUNCTION LOSSES:
PIPE FLOW DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY
Page 15
UPSTREAM
DOWNSTREAM
LATERAL #1
LATERAL #2
Q5
C605Pl,RES
(DEGREES) ELEVATION DEPTH(FT,) (FT/SEC)
0,00 386,33 3,16 20.510
386.00 3,50 15,995
45,00 387,00 1,77 6,876
0.00 0,00 0,00 0,000
0.00===Q5 EQUALS BASIN INPUT===
(CFS) (INCHES)
109,10 48,00
138.90 48.00
29.80 36.00
0.00 0.00
LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED:
DY=(Q2 *V2-Ql*Vl*COS(DELTAl)-Q3 *V3 *COS(DELTAS)-
Q4*V4*COS(DELTA4))/((Al+A2)*16.1)+FRICTI0N LOSSES
UPSTREAM: MANNING'S N = 0.01300; FRICTION SLOPE = 0,03612
DOWNSTREAM: MANNING'S N = 0,01300; FRICTION SLOPE = 0.01617
AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS 0,02615
5,00 FEET
0,131 FEET ENTRANCE LOSSES = 0,000 FEET
JUNCTION LOSSES = (DY+HVl-HV2)+(ENTRANCE LOSSES)
JUNCTION LOSSES = ( 2,038)+( 0,000) = 2,038
NODE 113,00 : HGL = < 388.088>;EGL= < 394.621>;FLOWLINE= < 386.330>
******************************************************************************
JUNCTION LENGTH =
FRICTION LOSSES =
FLOW PROCESS FROM NODE
UPSTREAM NODE 112.10
113.00 TO NODE 112.10 IS CODE = 1
ELEVATION = 391,16 (FLOW IS SUPERCRITICAL)
CALCULATE FRICTION LOSSES(LACFCD):
PIPE FLOW = 109.10 CFS PIPE
PIPE LENGTH = 75,00 FEET
DIAMETER = 48.00 INCHES
MANNING'S N = 0.01300
NORMAL DEPTH(FT) = 1.50 CRITICAL DEPTH(FT) = 3.16
UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) 2,40
GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION:
DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+
CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS)
0,000 2.402 13,839 5,378 3437,37
1,437 2.366 14,092 5,452 3473,34
3.023 2.330 14,355 5.532 3511.82
4.772 2.294 14.630 5.620 3552.93
6.703 2.258 14.916 5.715 3596,78
8,836 2.222 15,214 5.818 3643.53
11,194 2.186 15,525 5.931 3693,30
13,805 2.150 15,849 6.053 3746,26
16,703 2.114 16,188 6.185 3802,57
19.925 2.078 16,542 6.329 3862,42
23.518 2.041 16.912 6.485 3925,99
27.539 2.005 17.299 6.655 3993,49
32.056 1.969 17.704 6.839 4065.16
37.156 1.933 18.129 7.040 4141,24
42.947 1.897 18.574 7.258 4222,00
49.569 1.861 19.041 7.494 4307,74
57.207 1.825 19.532 7.752 4398,75
66.112 1.789 20.047 8.033 4495.40
75.000 1.758 20.504 8.291 4581.70
NODE 112,10 HGL = < 393, 562>;EGL= < 396.538>;FL0WLINE= < 391.160>
******************************************************************************
FLOW PROCESS FROM NODE 112.10 TO NODE 112.00 IS CODE = 5
UPSTREAM NODE 112.00 ELEVATION = 392.16 (FLOW IS SUPERCRITICAL)
CALCULATE JUNCTION LOSSES:
Page 16
C605P1.RES
PIPE
UPSTREAM
DOWNSTREAM
LATERAL #1
LATERAL #2
Q5
FLOW DIAMETER ANGLE
(CFS) (INCHES) (DEGREES
65.10 36.00 O.OC
109.10 48,00
22.30 24,00
21.70 24,00
(DEGREES) ELEVATION
FLOWLINE CRITICAL VELOCITY
0.00
90,00
90,00
392,16
391,16
393,16
393,16
DEPTH(FT,)
2.59
3,16
1.68
1.67
(FT/SEC)
24,279
13,843
7,897
7,763
0.00===Q5 EQUALS BASIN INPUT===
LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED:
DY=(Q2*V2-Ql*Vl*COS(DELTAl)-Q3*V3*COS(DELTA3)-
Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES
UPSTREAM: MANNING'S N = 0.01300; FRICTION SLOPE = 0.08043
DOWNSTREAM: MANNING'S N = 0,01300; FRICTION SLOPE = 0.01274
AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS 0.04659
JUNCTION LENGTH = 4,00 FEET
FRICTION LOSSES = 0,186 FEET ENTRANCE LOSSES = 0,000 FEET
(DY+HVl-HV2)+(ENTRANCE LOSSES)
( 5,989)+( 0,000) = 5,989
JUNCTION LOSSES =
JUNCTION LOSSES =
NODE 112.00 : HGL = < 393,374>;EGL= < 402.527>;FLOWLINE= < 392.160>
******************************************************************************
FLOW PROCESS FROM NODE
UPSTREAM NODE 112,51
112,00 TO NODE 112.51 IS CODE = 1
ELEVATION = 408.67 (FLOW IS SUPERCRITICAL)
CALCULATE FRICTION LOSSES(LACFCD):
PIPE FLOW = 65.10 CFS PIPE DIAMETER = 36.00 INCHES
PIPE LENGTH = 201.82 FEET MANNING'S N = 0.01300
NORMAL DEPTH(FT) = 1.21 CRITICAL DEPTH(FT) =
UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 1.29
GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION:
2.59
DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+
CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS)
0.000 1.286 22.480 9.138 2934.43
2.907 1.283 22,552 9.186 2942.96
5.950 1.280 22.625 9,233 2951.55
9.142 1.277 22,698 9,282 2960,20
12.496 1.274 22,771 9,330 2968,90
16.028 1,271 22,845 9,380 2977,67
19.757 1,267 22,919 9,429 2986,49
23.704 1,264 22,994 9,480 2995.37
27.894 1,261 23,069 9.530 3004.32
32.356 1,258 23,145 9.581 3013.32
37.126 1,255 23,221 9.633 3022.39
42.247 1,252 23,298 9,686 3031.51
47,769 1,249 23,375 9,738 3040.70
53,759 1,246 23,453 9,792 3049.96
60,296 1,243 23.531 9,846 3059.27
67,487 1,239 23.609 9,900 3068,65
75,469 1,236 23.688 9,955 3078,10
84,429 1,233 23.768 10.011 3087,61
94,628 1,230 23.848 10.067 3097.18
106,450 1,227 23,929 10.123 3106,83
120,491 1.224 24.010 10.181 3116.53
137,747 1.221 24,091 10.239 3126.31
160,086 1,218 24,173 10.297 3136.15
191.706 1.215 24.256 10.356 3146.07
201.820 1.214 24,272 10.367 3147.92
Page 17
NODE
C605P1.RES
112,51 : HGL = < 409,956>;EGL= < 417.808>;FLOWLINE= < 408.670>
******************************************************************************
FLOW PROCESS FROM NODE 112.51 TO NODE 112,50 IS CODE = 5
UPSTREAM NODE 112.50 ELEVATION = 409.00 (FLOW IS SUPERCRITICAL)
CALCULATE JUNCTION LOSSES:
PIPE
UPSTREAM
DOWNSTREAM
LATERAL #1
LATERAL #2
Q5
FLOW
(CPS)
65.10
65.10
0.00
0,00
DIAMETER ANGLE FLOWLINE CRITICAL VELOCITY
(INCHES)
36,00
36,00
0,00
0.00
(DEGREES) ELEVATION
0.00
0,00
0,00
409.00
408.67
0.00
0.00
DEPTH(FT,)
2.59
2.59
0.00
0.00
(FT/SEC)
22.689
22.487
0.000
0,000
0.00===Q5 EQUALS BASIN INPUT===
LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED:
DY=(Q2*V2-Ql*Vl*COS(DELTAl)-Q3*V3*COS(DELTA3)-
Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES
UPSTREAM: MANNING'S N = 0,01300; FRICTION SLOPE = 0,06685
DOWNSTREAM: MANNING'S N = 0,01300; FRICTION SLOPE = 0,06525
AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS 0.06605
JUNCTION LENGTH = 4.00 FEET
FRICTION LOSSES = 0,264 FEET ENTRANCE LOSSES = 0,000 FEET
JUNCTION LOSSES = (DY+HV1-HV2)+(ENTRANCE LOSSES)
JUNCTION LOSSES = ( 0,463)+( 0,000) = 0,463
NODE 112,50 : HGL = < 410,278>;EGL= < 418,271>;FLOWLINE= < 409,000>
******************************************************************************
FLOW PROCESS FROM NODE
UPSTREAM NODE 111,10
112,50 TO NODE 111,10 IS CODE = 1
ELEVATION = 426.50 (FLOW IS SUPERCRITICAL)
CALCULATE FRICTION LOSSES(LACFCD):
PIPE FLOW = 65,10 CFS PIPE DIAMETER = 36.00 INCHES
PIPE LENGTH = 250,02 FEET MANNING'S N = 0,01300
NORMAL DEPTH(FT) = 1,26 CRITICAL DEPTH(FT) =
UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 1.67
GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION:
2.59
DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+
CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUN
0.000 1,668 16.122 5.706 2214.52
1.932 1,652 16.318 5.789 2235.20
3,995 1,635 16.519 5,875 2256,56
6,202 1.619 16.725 5,965 2278,63
8.566 1.603 16,937 6,060 2301,43
11.105 1.587 17,154 6,159 2324,98
13.838 1.570 17,377 6,262 2349,32
16.785 1.554 17,607 6,371 2374,46
19.973 1.538 17,842 6,484 2400,44
23,433 1,522 18,084 6.603 2427.28
27,201 1,505 18,332 6.727 2455,01
31,320 1,489 18,588 6,857 2483,67
35,845 1,473 18,850 6,994 2513,29
40,843 1,456 19,120 7,137 2543.90
46,397 1,440 19,398 7.287 2575,54
52,616 1.424 19,684 7.444 2608,24
59,644 1.408 19,979 7.609 2642,06
67.673 1.391 20,282 7.783 2677.02
76.976 1.375 20.594 7.965 2713,19
Page 18
87,950
101,211
117,794
139,636
171,092
226,133
250,020
C605Pl,RES
1,359 20.916
1.343 21.247
1.326 21,589
1.310 21,941
1.294 22,305
1,278 22,680
1,278 22,682
8.156
8.357
8,568
8,790
,024
,270
,271
9,
9.
9.
2750.59
2789.29
2829.33
2870,78
2913.69
2958,12
2958,27
NODE 111.10 : HGL = < 428.168>;EGL= < 432.206>;FLOWLINE= < 426.500>
*************************************************************^^^^^^^^^^^^^^^^^
FLOW PROCESS FROM NODE 111.10 TO NODE 111.00 IS CODE = 5
UPSTREAM NODE 111.00 ELEVATION = 426.83 (FLOW IS SUPERCRITICAL)
CALCULATE JUNCTION LOSSES:
PIPE
UPSTREAM
DOWNSTREAM
LATERAL #1
LATERAL #2
Q5
FLOW
(CPS)
54.50
65,10
10,60
0,00
DIAMETER
(INCHES)
36,00
36,00
18,00
0,00
ANGLE FLOWLINE
(DEGREES) ELEVATION
0,00
90,00
0,00
426,83
426,50
428,00
0,00
0,00===Q5 EQUALS BASIN INPUT===
CRITICAL
DEPTH(FT,)
2,40
2,59
1.25
0.00
VELOCITY
(FT/SEC)
19.963
16.127
6,735
0,000
m
LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED:
DY=(Q2*V2-Ql*Vl*COS(DELTAl)-Q3*V3*COS(DELTA3)-
Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES
UPSTREAM: MANNING'S N = 0.01300; FRICTION SLOPE = 0.
DOWNSTREAM: MANNING'S N = 0.01300; FRICTION SLOPE = 0.
AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS 0.04024
JUNCTION LENGTH = 4,00 FEET
FRICTION LOSSES = 0,161 FEET ENTRANCE LOSSES =
JUNCTION LOSSES = (DY+HVl-HV2)+(ENTRANCE LOSSES)
JUNCTION LOSSES = ( 2,042)+( 0,000) = 2.042
05366
02682
0,000 FEET
NODE 111,00 : HGL = < 428,060>;EGL= < 434,248>;FLOWLINE= < 426,830>
*****************************************************^^^^^^^^^^^^^^^^^^^^^^^^^
FLOW PROCESS FROM NODE 111,00 TO NODE 104,10 IS CODE = 1
UPSTREAM NODE 104,10 ELEVATION = 431,60 (FLOW IS SUPERCRITICAL)
CALCULATE FRICTION LOSSES(LACFCD):
PIPE FLOW = 54,50 CFS PIPE
PIPE LENGTH = 75,34 FEET DIAMETER = 36,00 INCHES
MANNING'S N = 0,01300
NORMAL DEPTH(FT) = 1,18 CRITICAL DEPTH(FT) = 2.40
UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) 1.35
GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION:
DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC
CONTROL(FT) (FT) (FT/SEC) ENERGY(FT)
0.000 1,349 17.682 6.207
2.413 1,342 17.801 6.266
4.955 1.335 17.922 6.326
7.637 1,328 18.044 6.387
10.473 1,321 18.168 6.450
13.477 1.314 18.294 6.514
16.668 1,307 18.421 6.580
20.065 1.300 18.550 6,647
23,692 1,293 18.680 6.715
27,578 1,287 18.813 6.786
31,757 1.280 18.947 6.857
Page 19
PRESSURE+
MOMENTUM(POUNDS)
1977.27
1988.53
1999.96
2011.57
2023.36
2035.33
2047.48
2059,83
2072,36
2085,09
2098.02
C605P1.RES
36.269 1,273 19,083 6.931 2111.15
41.164 1,266 19,221 7.006 2124,49
46.504 1.259 19.360 7,083 2138.04
52,366 1.252 19,502 7.161 2151,80
58,852 1,245 19,646 7,242 2165,78
66,092 1,238 19,792 7.324 2179,99
74,266 1,231 19,939 7.409 2194.41
75,340 1,230 19.956 7.418 2196.08
NODE 104.10 : HGL = < 432,949>;EGL= < 437,807>;FLOWLINE= < 431.600>
******************************************************************************
FLOW PROCESS FROM NODE
UPSTREAM NODE 104,00
104,10 TO NODE 104.00 IS CODE = 5
ELEVATION = 432.60 (FLOW IS SUPERCRITICAL)
CALCULATE JUNCTION LOSSES;
PIPE
UPSTREAM
DOWNSTREAM
LATERAL #1
LATERAL #2
Q5
FLOW
(CPS)
45.40
54.50
9,10
0.00
DIAMETER ANGLE
(INCHES)
24,00
36,00
24,00
0,00
(DEGREES)
0,00
90,00
0,00
FLOWLINE CRITICAL VELOCITY
ELEVATION
432,60
431,60
433,10
0,00
DEPTH(FT,)
1.97
2.40
1.08
0,00
0.00===Q5 EQUALS BASIN INPUT===
(FT/SEC)
19,910
17,688
5,277
0,000
LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED:
DY=(Q2*V2-Q1*V1*C0S(DELTA1)-Q3*V3*C0S(DELTA3)-
Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES
UPSTREAM: MANNING'S N = 0.01300; FRICTION SLOPE = 0,06172
DOWNSTREAM: MANNING'S N = 0,01300; FRICTION SLOPE = 0,03861
AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS 0,05017
JUNCTION LENGTH = 4.00 FEET
FRICTION LOSSES = 0,201 FEET ENTRANCE LOSSES = 0,000 FEET
(DY+HVl-HV2)+(ENTRANCE LOSSES)
( 2.311)+( 0.000) = 2.311
JUNCTION LOSSES =
JUNCTION LOSSES =
NODE 104.00 : HGL = < 433.963>;EGL= < 440.118>;FLOWLINE= < 432,600>
******************************************************************************
FLOW PROCESS FROM NODE
UPSTREAM NODE 110,10
104.00 TO NODE 110.10 IS CODE = 1
ELEVATION = 441,00 (FLOW IS SUPERCRITICAL)
CALCULATE FRICTION LOSSES(LACFCD):
PIPE FLOW = 45,40 CFS PIPE DIAMETER = 24,00 INCHES PIPE LENGTH = 120.66 FEET MANNING'S N = 0. 01300
NORMAL DEPTH(FT) 1.31 CRITICAL DEPTH(FT) 1.97
UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 1.97
GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION:
DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+
CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS)
0,000 1.971 14.490 5,233 1465,54
0,162 1.944 14.561 5.239 1466,61
0,594 1.918 14.653 5.253 1469.49
1,253 1.891 14,761 5.276 1473.89
2,123 1.864 14.884 5,307 1479.68
3.200 1.838 15,022 5.344 1486.76
4.487 1.811 15.174 5.388 1495.08
5.995 1,784 15.338 5.440 1504.63
7.738 1,758 15.516 5.498 1515.39
9.739 1,731 15.707 5.564 1527.36
Page 20
C605Pl,RES
12,024 1.704 15,911 5,638 1540,56
14,628 1.678 16,129 5,720 1555,00
17.596 1,651 16,360 5,810 1570,72
20.983 1,625 16,606 5,909 1587,75
24,860 1,598 16.866 6.018 1606.13
29.321 1,571 17,141 6,136 1625.91
34.491 1,545 17,432 6,266 1647,15
40.536 1,518 17,739 6.407 1669,91
47.696 1,491 18,064 6,561 1694,27
56.317 1,465 18,406 6.729 1720.28
66.942 1,438 18,768 6.911 1748.06
80.479 1,412 19,150 7.109 1777,68
98,632 1,385 19,553 7.325 1809,25
120,660 1,363 19,903 7.518 1836.95
NODE 110,10 : HGL = < 442,971>;EGL= < 446,233>;FLOWLINE= < 441,000>
***************************************************************************^^*
FLOW PROCESS FROM NODE 110,10 TO NODE 110,00 IS CODE = 5
UPSTREAM NODE 110,00 ELEVATION = 441,33 (FLOW IS AT CRITICAL DEPTH)
CALCULATE JUNCTION LOSSES:
PIPE
UPSTREAM
DOWNSTREAM
LATERAL #1
LATERAL #2
Q5
FLOW
(CFS)
22,60
45.40
22,80
0,00
DIAMETER
(INCHES)
24,00
24,00
24,00
0,00
ANGLE
(DEGREES)
90,00
90,00
0,00
FLOWLINE
ELEVATION
441,33
441.00
441.33
0,00
0.00===Q5 EQUALS BASIN INPUT===
CRITICAL
DEPTH(FT,)
1,69
1,97
1,70
0.00
VELOCITY
(FT/SEC)
7,194
14,495
7,257
0.000
LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED:
DY=(Q2*V2-Ql*Vl*COS(DELTAl)-Q3*V3*COS(DELTA3)-
Q4*V4*COS(DELTA4))/((Al+A2)*16,l)+FRICTION LOSSES
UPSTREAM: MANNING'S N = 0.01300; FRICTION SLOPE = 0,00998
DOWNSTREAM: MANNING'S N = 0,01300; FRICTION SLOPE = 0,03655
AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS 0,02326
JUNCTION LENGTH = 4.00 FEET
FRICTION LOSSES = 0,093 FEET ENTRANCE LOSSES = 0.000 FEET
JUNCTION LOSSES = (DY+HVl-HV2)+(ENTRANCE LOSSES)
JUNCTION LOSSES = ( 4,149)+( 0.000) = 4,149
NODE 110.00 : HGL = < 449.579>;EGL= < 450.382>;FLOWLINE= < 441.330>
************************************************************* ******^^^^.j^.^.j^^^^.j^
FLOW PROCESS FROM NODE 110.00 TO NODE 107.00 IS CODE = 1
UPSTREAM NODE 107.00 ELEVATION = 441.85 (FLOW IS UNDER PRESSURE)
CALCULATE FRICTION LOSSES(LACFCD):
PIPE FLOW = 22.60 CFS PIPE DIAMETER = 24,00 INCHES
PIPE LENGTH = 5.25 FEET MANNING'S N = 0,01300
SF=(Q/K)**2 = (( 22,60)/( 226,218))**2 = 0,00998
HF=L*SF = ( 5,25)*(0,00998) = 0.052
NODE 107.00 : HGL = < 449.631>;EGL= < 450.435>;FLOWLINE= < 441.850>
*************************************************************************^^^^^
UPSTREAM PIPE FLOW CONTROL DATA:
NODE NUMBER = 107.00 FLOWLINE ELEVATION = 441.85
ASSUMED UPSTREAM CONTROL HGL = 443.54 FOR DOWNSTREAM RUN ANALYSIS
END OF GRADUALLY VARIED FLOW ANALYSIS
D
Page 21
C2129L.RES
******************************************************************************
PIPE-FLOW HYDRAULICS COMPUTER PROGRAM PACKAGE
(Reference: WSPG COMPUTER MODEL HYDRAULICS CRITERION)
(c) Copyright 1982-2001 Advanced Engineering Software (aes)
ver, 8,0 Release Date: 01/01/2001 License ID 1423
Analysis prepared by:
O'Day Consultants, inc.
2710 Loker Avenue West, Suite 100
Carlsbad, CA 92008
Tel: 760-931-7700 Fax: 760-931-8680
************************** DESCRIPTION OF STUDY **************************
* CARLSBAD OAKS PHASE 3 *
* STA 21+29 LT WHIPTAIL *
* l:\961005\Hydrology\Phase3\Hydraulics\C2129L,OUT *
**************************************************************************
FILE NAME: C2129L.DAT
TIME/DATE OF STUDY: 10:15 01/31/2008
******************************************************************************
GRADUALLY VARIED FLOW ANALYSIS FOR PIPE SYSTEM
NODAL POINT STATUS TABLE
(Note: "*" indicates nodal point data used.)
UPSTREAM RUN DOWNSTREAM RUN
NODE MODEL PRESSURE PRESSURE+ FLOW PRESSURE+
NUMBER PROCESS HEAD(FT) MOMENTUM(POUNDS) DEPTH(FT) MOMENTUM(POUNDS)
117,00- 2,40 DC 1327.31 1.00* 2758,59
} FRICTION
123.10- 2,38*Dc 1327.12 2.38*Dc 1327,12
MAXIMUM NUMBER OF ENERGY BALANCES USED IN EACH PROFILE = 25
NOTE: STEADY FLOW HYDRAULIC HEAD-LOSS COMPUTATIONS BASED ON THE MOST
CONSERVATIVE FORMULAE FROM THE CURRENT LACFCD WSPG COMPUTER PROGRAM,
******************************************************************************
DOWNSTREAM PIPE FLOW CONTROL DATA:
NODE NUMBER = 117,00 FLOWLINE ELEVATION = 342,17
PIPE FLOW = 53,50 CFS PIPE DIAMETER = 36.00 INCHES
ASSUMED DOWNSTREAM CONTROL HGL = 344.570 FEET
NODE 117.00 : HGL = < 343,166>;EGL= < 353.742>;FLOWLINE= < 342,170>
******************************************************************************
FLOW PROCESS FROM NODE 117.00 TO NODE 123.10 IS CODE = 1
UPSTREAM NODE 123,10 ELEVATION = 354.17 (FLOW IS SUPERCRITICAL)
CALCULATE FRICTION LOSSES(LACFCD):
PIPE FLOW = 53.50 CFS PIPE DIAMETER = 36.00 INCHES
PIPE LENGTH = 60.00 FEET MANNING'S N = 0.01300
NORMAL DEPTH(FT) = 0.86 CRITICAL DEPTH(FT) = 2.38
UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 2.38
GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION:
DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+
CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS)
0.000 2.376 8.908 3.609 1327.12
Page 1
C2129L.RES
0.018 2,315 9,136 3,612 1328,39
0.074 2,255 9.385 3,623 1332.29
0,174 2,194 9.654 3.642 1339.01
0.323 2,134 9,947 3.671 1348,73
0,529 2,073 10,265 3,710 1361,67
0.799 2,012 10.610 3,762 1378,09
1.144 1.952 10.986 3,827 1398,28
1,577 1,891 11,394 3,908 1422,56
2.112 1,830 11,840 4.008 1451,32
2,769 1.770 12,326 4.130 1485.00
3.570 1,709 12.858 4,278 1524,11
4.547 1,648 13.442 4,456 1569,24
5.735 1,588 14,084 4,670 1621,09
7.185 1,527 14,792 4.927 1680,48
8,961 1.467 15,575 5.236 1748,40
11,151 1,406 16,445 5.608 1826.01
13,876 1,345 17.416 6.058 1914,72
17,311 1,285 18,504 6.604 2016,24
21,713 1,224 19,728 7,271 2132,66
27,489 1,163 21,115 8,091 2266,57
35.329 1,103 22.695 9,106 2421.20
46,539 1,042 24.509 10.375 2600,66
60,000 0,996 26.091 11.572 2758,59
NODE 123.10 : HGL = < 356.546>;EGL= < 357,779>;FL0WLINE= < 354,170>
******************************************************************************
UPSTREAM PIPE FLOW CONTROL DATA:
NODE NUMBER = 123.10 FLOWLINE ELEVATION = 354,17
ASSUMED UPSTREAM CONTROL HGL = 356.55 FOR DOWNSTREAM RUN ANALYSIS
END OF GRADUALLY VARIED FLOW ANALYSIS
D
Page 2
m BOBCAT.RES
******************************************************************************
PIPE-FLOW HYDRAULICS COMPUTER PROGRAM PACKAGE
(Reference: WSPG COMPUTER MODEL HYDRAULICS CRITERION)
(c) copyright 1982-2001 Advanced Engineering Software (aes)
ver. 8.0 Release Date: 01/01/2001 License ID 1423
Analysis prepared by:
O'Day Consultants, Inc.
2710 Loker Avenue West, Suite 100
Carlsbad, CA 92008
Tel: 760-931-7700 Fax: 760-931-8680
************************** DESCRIPTION OF STUDY **************************
* CARLSBAD OAKS PHASE 3 *
* PROPOSED BOBCAT CT, *
* l:\961005\Hydrology\Phase3\Hydraulics\BOBCAT,RES *
**************************************************************************
FILE NAME: BOBCAT.DAT
TIME/DATE OF STUDY: 09:10 01/31/2008
******************************************************************************
GRADUALLY VARIED FLOW ANALYSIS FOR PIPE SYSTEM
NODAL POINT STATUS TABLE
(Note: "*" indicates nodal poi nt data used.)
UPSTREAM RUN DOWNSTREAM RUN
NODE MODEL PRESSURE PRESSURE+ FLOW PRESSURE+
NUMBER PROCESS HEAD(FT) MOMENTUM(POUNDS) DEPTH(FT) MOMENTUM(POUNDS)
116,00-2,44 DC 1443,04 1.35* 2141.45
} FRICTION
2405,50-2.44 DC 1443.04 1.39* 2067.96
} JUNCTION
3405,00-2.33 DC 1461.16 1,40* 2013.75
} FRICTION
2304,00-2.33*DC 1461.16 2.33*Dc 1461.16
MAXIMUM NUMBER OF ENERGY BALANCES USED IN EACH PROFILE = 25
NOTE: STEADY FLOW HYDRAULIC HEAD-LOSS COMPUTATIONS BASED ON THE MOST
CONSERVATIVE FORMULAE FROM THE CURRENT LACFCD WSPG COMPUTER PROGRAM.
******************************************************************************
DOWNSTREAM PIPE FLOW CONTROL DATA:
NODE NUMBER = 116.00 FLOWLINE ELEVATION = 352.50
PIPE FLOW = 56,80 CFS PIPE DIAMETER = 36,00 INCHES
ASSUMED DOWNSTREAM CONTROL HGL = 354,900 FEET
*NOTE: ASSUMED DOWNSTREAM CONTROL DEPTH( 2,40 FT,)
IS LESS THAN CRITICAL DEPTH( 2.44 FT.)
===> CRITICAL DEPTH IS ASSUMED AS DOWNSTREAM CONTROL DEPTH
FOR UPSTREAM RUN ANALYSIS
NODE 116,00 : HGL = < 353.847>;EGL= < 359,142>;FLOWLINE= < 352.500>
******************************************************************************
FLOW PROCESS FROM NODE 116.00 TO NODE 2405.50 IS CODE = 1
UPSTREAM NODE 2405.50 ELEVATION = 354.39 (FLOW IS SUPERCRITICAL)
CALCULATE FRICTION LOSSES(LACFCD):
PIPE FLOW = 56,80 CFS PIPE DIAMETER = 36.00 INCHES
PIPE LENGTH = 37.79 FEET MANNING'S N = 0,01300
NORMAL DEPTH(FT) = 1,28 CRITICAL DEPTH(FT) = 2,44
Page 1
BOBCAT,RES
UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 1.39
GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION:
DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+
CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNDS)
0.000 1.390 17,716 6.267 2067.96
2.870 1,386 17,787 6.302 2074.89
5,881 1,382 17,858 6.337 2081.89
9,044 1.377 17.930 6,372 2088,96
12,375 1.373 18,002 6,409 2096,09
15.888 1,369 18,075 6,445 2103.28
19,604 1,365 18,149 6,482 2110,55
23,544 1,360 18,223 6,520 2117,88
27.734 1.356 18,298 6,558 2125.28
32,205 1.352 18,373 6,597 2132.74
36,992 1.348 18.449 6,636 2140,28
37.790 1,347 18,461 6,642 2141,45
NODE 2405,50 : HGL = < 355.780>;EGL= < 360.657>;FL0WLINE= < 354.390>
******************************************************************************
FLOW PROCESS FROM NODE 2405.50 TO NODE 3405,00 IS CODE = 5
UPSTREAM NODE 3405,00 ELEVATION = 354.89 (FLOW IS SUPERCRITICAL)
CALCULATE JUNCTION LOSSES:
PIPE
UPSTREAM
DOWNSTREAM
LATERAL #1
LATERAL #2
Q5
FLOW DIAMETER ANGLE
(CFS) (INCHES)
52.70 30,00
56,80 36,00
2,20 18.00
1,90 18.00
FLOWLINE CRITICAL VELOCITY
(DEGREES) ELEVATION
0.00
90,00
90.00
354.89
354,39
355,89
355,89
DEPTH(FT,)
2,33
2,44
0,56
0,52
(FT/SEC)
18,686
17.722
3.655
3.500
0.00===Q5 EQUALS BASIN INPUT===
04575
03770
0.000 FEET
LACFCD AND OCEMA FLOW JUNCTION FORMULAE USED:
DY=(Q2*V2-Ql*Vl*COS(DELTAl)-Q3*V3*COS(DELTA3)-
Q4*V4*COS(DELTA4))/((A1+A2)*16.1)+FRICTION LOSSES
UPSTREAM: MANNING'S N = 0.01300; FRICTION SLOPE = 0.
DOWNSTREAM: MANNING'S N = 0.01300; FRICTION SLOPE = 0.
AVERAGED FRICTION SLOPE IN JUNCTION ASSUMED AS 0.04173
JUNCTION LENGTH = 4.00 FEET
FRICTION LOSSES = 0,167 FEET ENTRANCE LOSSES =
JUNCTION LOSSES = (DY+HVl-HV2)+(ENTRANCE LOSSES)
JUNCTION LOSSES = ( l,052)+( 0.000) = 1,052
NODE 3405,00 : HGL = < 356,287>;EGL= < 361,709>;FLOWLINE= < 354,890>
******************************************************************************
FLOW PROCESS FROM NODE 3405,00 TO NODE 2304,00 IS CODE = 1
UPSTREAM NODE 2304,00 ELEVATION = 367,53 (FLOW IS SUPERCRITICAL)
CALCULATE FRICTION LOSSES(LACFCD):
PIPE FLOW = 52,70 CFS PIPE DIAMETER = 30,00 INCHES
PIPE LENGTH = 252,70 FEET MANNING'S N = 0.01300
NORMAL DEPTH(FT) = 1.36 CRITICAL DEPTH(PT) = 2.33
UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 2.33
GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION:
DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC
Page 2
PRESSURE+
BOBCAT, RES
OL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNC
0,000 2.331 11.055 4.230 1461.16
0.074 2,292 11.176 4.233 1461.95
0,298 2,253 11,310 4,241 1464.27
0,673 2,214 11,457 4.254 1468.10
1.206 2,176 11,618 4.273 1473.44
1.909 2.137 11,792 4,297 1480.30
2,795 2,098 11.980 4,328 1488.73
3,882 2,059 12,182 4,364 1498.75
5,190 2,020 12,398 4,408 1510.42
6,746 1.981 12,629 4,459 1523.80
8.584 1,942 12,875 4,518 1538,98
10,743 1,903 13.139 4,585 1556.03
13,273 1,864 13,419 4,662 1575.05
16,238 1,825 13,718 4,749 1596.15
19.717 1.787 14,036 4,848 1619.45
23.815 1,748 14,375 4,958 1645,08
28.669 1,709 14,736 5,083 1673,20
34,466 1,670 15,122 5,223 1703,97
41,470 1,631 15.532 5,379 1737,58
50,069 1,592 15.970 5.555 1774,23
60,864 1,553 16.439 5.752 1814,17
74,867 1,514 16,939 5.973 1857.64
93.972 1,475 17,475 6,220 1904,94
122,445 1,437 18,049 6,498 1956,40
173,970 1,398 18.665 6,811 2012.38
252,700 1.397 18.680 6,819 2013.75
NODE 2304,00 : HGL = < 369,861>;EGL= < 371,760>;FLOWLINE= < 367,530>
******************************************************************************
UPSTREAM PIPE FLOW CONTROL DATA:
NODE NUMBER = 2304,00 FLOWLINE ELEVATION = 367,53
ASSUMED UPSTREAM CONTROL HGL = 369,86 FOR DOWNSTREAM RUN ANALYSIS
END OF GRADUALLY VARIED FLOW ANALYSIS
D
Page 3
2415, RES
^^^y**7^**************************************************************************
PIPE-FLOW HYDRAULICS COMPUTER PROGRAM PACKAGE
(Reference: WSPG COMPUTER MODEL HYDRAULICS CRITERION)
(c) copyright 1982-2001 Advanced Engineering software (aes)
ver, 8,0 Release Date: 01/01/2001 License ID 1423
Analysis prepared by:
O'Day Consultants, Inc,
2710 Loker Avenue west. Suite 100
carlsbad, CA 92008
Tel: 760-931-7700 Fax: 760-931-8680
************************** DESCRIPTION OF STUDY **************************^
* CARLSBAD OAKS PHASE 3 *
* PROPOSED BOBCAT CT INLET (SOUTH) . ^ ^ * * i-\961005\Hvdroloqy\Phase3\Hydraulics\2415,res .^.^.^.^^.^ *t;***i************************************^
FILE NAME: 2415,DAT
TIME/DATE OF STUDY: 09:25 01/31/2008
******************************************************************************
GRADUALLY VARIED FLOW ANALYSIS FOR PIPE SYSTEM
NODAL POINT STATUS TABLE
(Note: "*" indicates nodal point data used,)
UPSTREAM RUN DOWNSTREAM RUN
NODE MODEL PRESSURE PRESSURE+ FLOW PRESSURE+
NUMBER PROCESS HEAD(FT) MOMENTUM(POUNDS) DEPTH(FT) MOMENTUM(POUNDS)
2405.00- 1.20* 56.66 0,30 32.09
} FRICTION } HYDRAULIC JUMP
2415.00- 0.53*Dc 21.55 0.53*Dc
MAXIMUM NUMBER OF ENERGY BALANCES USED IN EACH PROFILE = 25^^
NOTE- STEADY FLOW HYDRAULIC HEAD-LOSS COMPUTATIONS BASED ON THE MOST
CONSERVATIVE FORMULAE FROM THE CURRENT LACFCD WSPG COMPUTER PROGRAM.
******************************************************************************
DOWNSTREAM PIPE FLOW CONTROL DATA:
NODE NUMBER = 2405.00 FLOWLINE ELEVATION = 355,89
PIPE FLOW = 2,00 CFS PIPE DIAMETER = 18,00 INCHES
ASSUMED DOWNSTREAM CONTROL HGL = 357.090 FEET
'"NODE~'2405'00'rHGL = < 357.090>; EGL= < 357.117>; FLOWLINE= < 355.890>
^^****************************************************************************
FLOW PROCESS FROM NODE 2405.00 TO NODE 2415.00 IS CODE = 1
UPSTREAM NODE 2415.00 ELEVATION = 358.03 (HYDRAULIC JUMP OCCURS)
CALCULATE FRICTION LOSSES(LACFCD):
PIPE FLOW = 2.00 CFS PIPE DIAMETER = 18.00 INCHES
PIPE LENGTH = 42.75 FEET MANNING'S N = 0.01300
HYDRAULIC JUMP: DOWNSTREAM RUN ANALYSIS RESULTS
"NORMAL'DEPTH(FT) = 0.30 CRITICAL DEPTH(FT) = 0.53
UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) =
GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION:
DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+
Page 1
2415 RES
MOMENTUM(POUNC L(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUNC
0,000 0,533 3,552 0.729 21.55
0.007 0.524 3,640 0,730 21,56
0,031 0,514 3,732 0.731 21.60
0.072 0.505 3.828 0,732 21.66
0,134 0,495 3,929 0,735 21.74
0,217 0,486 4.035 0,739 21.86
0.326 0.476 4,146 0,743 22,00
0,463 0,467 4,263 0,749 22,17
0.633 0.457 4,386 0,756 22,37
0,839 0,448 4,516 0,765 22.61
1,088 0.438 4.653 0,775 22.88
1.387 0,429 4,797 0,786 23,19
1,742 0.419 4,949 0.800 23.54
2.166 0,410 5,110 0,815 23,92
2,671 0,400 5,281 0,834 24,36
3,274 0.391 5.462 0.854 24,84
3.998 0,381 5.654 0,878 25.37
4,872 0.372 5,859 0,905 25.96
5,940 0.362 6,077 0,936 26,61
7.266 0,353 6,310 0,971 27,32
8,945 0.343 6,558 1,012 28,10
11.143 0.334 6.825 1,058 28,95
14.165 0,324 7.111 1.110 29,89
18,704 0.315 7.419 1.170 30,92
26,975 0.305 7.751 1.239 32,05
42,750 0,305 7.761 1.241 32.09
HYDRAULIC JUMP: UPSTREAM RUN ANALYSIS RESULTS
DOWNSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 1,20
GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION:
DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+
CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUN[
0.000 1,200 1.319 1.227 56.66
0.513 1.173 1.348 1.202 54.27
1.023 1.147 1.379 1.176 51.95
1.532 1.120 1,413 1.151 49.70
2.037 1.093 1.449 1.126 47,51
2.539 1.067 1,488 1,101 45.40
3.038 1.040 1,529 1,076 43.35
3.533 1.013 1.574 1,052 41.38
4.024 0,987 1,622 1.027 39.48
4.510 0.960 1,674 1,003 37.66
4,991 0.933 1,730 0,980 35.92
5.465 0.907 1.790 0,956 34.27
5.931 0.880 1.856 0.933 32.69
6.389 0.853 1,926 0,911 31.21
6.838 0.827 2,003 0,889 29.81
7.274 0.800 2.086 0,868 28.51
7.698 0.773 2,177 0.847 27.30
8,105 0.747 2,276 0.827 26.19
8,493 0.720 2.385 0.808 25.18
8,857 0.693 2.504 0.791 24.28
9,194 0.667 2.636 0.774 23.49
9,497 0.640 2.781 0.760 22.83
9,757 0.613 2.942 0.748 22.29
9.964 0.587 3.123 0.738 21.89
10,103 0,560 3.324 0.732 21.64
10,155 0.533 3.552 0.729 21.55
42,750 0.533 3.552 0.729 21.55
Page 2
2415.RES
END OF HYDRAULIC JUMP ANALYSIS
I PRESSURE+MOMENTUM BALANCE OCCURS AT 6,12 FEET UPSTREAM OF NODE 2405,00
I DOWNSTREAM DEPTH = 0.869 FEET, UPSTREAM CONJUGATE DEPTH = 0,305 FEET
NODE 2415.00 : HGL = < 358,563>;EGL= < 358,759>;FLOWLINE= < 358,030>
****************************************************************************^^
UPSTREAM PIPE FLOW CONTROL DATA:
NODE NUMBER = 2415,00 FLOWLINE ELEVATION = 358.03
ASSUMED UPSTREAM CONTROL HGL = 358.56 FOR DOWNSTREAM RUN ANALYSIS
END OF GRADUALLY VARIED FLOW ANALYSIS
D
Page 3
m 2413,RES
******************************************************************************
PIPE-FLOW HYDRAULICS COMPUTER PROGRAM PACKAGE
(Reference: WSPG COMPUTER MODEL HYDRAULICS CRITERION)
(c) copyright 1982-2001 Advanced Engineering Software (aes)
ver, 8,0 Release Date: 01/01/2001 License ID 1423
Analysis prepared by:
O'Day Consultants, inc,
2710 Loker Avenue West, Suite 100
carlsbad, CA 92008
Tel: 760-931-7700 Fax: 760-931-8680
************************** DESCRIPTION OF STUDY **************************
* CARLSBAD OAKS PHASE 3 *
* PROPOSED BOBCAT CT INLET (NORTH) *
* i:\961005\Hydrology\Phase3\Hydraulics\2413,res *
**************************************************************************
FILE NAME: 2413,DAT
TIME/DATE OF STUDY: 09:20 01/31/2008
******************************************************************************
GRADUALLY VARIED FLOW ANALYSIS FOR PIPE SYSTEM
NODAL POINT STATUS TABLE
(Note: "*" indicates nodal point data used,)
UPSTREAM RUN DOWNSTREAM RUN
NODE MODEL PRESSURE PRESSURE+ FLOW PRESSURE+
NUMBER PROCESS HEAD(FT) MOMENTUM(POUNDS) DEPTH(FT) MOMENTUM(POUNDS)
2405.00- 1,20* 58,91 0,36 36,95
} FRICTION } HYDRAULIC JUMP
2413.00- 0,59*DC 27,21 0,59*DC 27,21
MAXIMUM NUMBER OF ENERGY BALANCES USED IN EACH PROFILE = 25
NOTE: STEADY FLOW HYDRAULIC HEAD-LOSS COMPUTATIONS BASED ON THE MOST
CONSERVATIVE FORMULAE FROM THE CURRENT LACFCD WSPG COMPUTER PROGRAM,
******************************************************************************
DOWNSTREAM PIPE FLOW CONTROL DATA:
NODE NUMBER = 2405,00 FLOWLINE ELEVATION = 355,89
PIPE FLOW = 2,40 CFS PIPE DIAMETER = 18,00 INCHES
ASSUMED DOWNSTREAM CONTROL HGL = 357,090 FEET
NODE 2405,00 : HGL = < 357.090>;EGL= < 357.129>;FLOWLINE= < 355.890>
******************************************************************************
FLOW PROCESS FROM NODE 2405.00 TO NODE 2413.00 IS CODE = 1
UPSTREAM NODE 2413.00 ELEVATION = 356.37 (HYDRAULIC JUMP OCCURS)
CALCULATE FRICTION LOSSES(LACFCD):
PIPE FLOW = 2.40 CFS PIPE DIAMETER = 18.00 INCHES
PIPE LENGTH = 4,75 FEET MANNING'S N = 0,01300
HYDRAULIC JUMP: DOWNSTREAM RUN ANALYSIS RESULTS
NORMAL DEPTH(FT) = 0.27 CRITICAL DEPTH(FT) = 0.59
UPSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 0.59
GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION:
DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+
Page 1
CONTROL(FT)
0,000
0,006
0.023
0,055
0,101
0,165
0,249
0,356
0,488
0,651
0,849
1,089
1.377
1,724
2,141
2,644
3,254
4,001
4,750
(FT)
0,586
0,574
0,561
0,548
0,536
0,523
0,511
0,498
0,486
0,473
0,461
0,448
0.435
0.423
0.410
0.398
0.385
0.373
0.362
2413,
(FT/SEC)
3.750
3.861
3,978
4,102
4,233
4,371
4,519
4,676
4,842
5,020
5,211
5.414
5,632
5,867
6,119
6,392
6,686
7,006
7.286
RES
ENERGY(FT)
0,805
0,805
0,807
0,810
0.814
0.820
0.828
0.838
0.850
0.865
0.882
0.903
0.928
0.958
0,992
1,033
1,080
1,135
1,187
MOMENTUM(POUNDS)
27,21
27,24
27,30
27,41
27,57
27,78
28,04
28,36
28.74
29.19
29,70
30,30
30.97
31.74
32.60
33,56
34,65
35,86
36,95
HYDRAULIC JUMP: UPSTREAM RUN ANALYSIS RESULTS
DOWNSTREAM CONTROL ASSUMED FLOWDEPTH(FT) = 1.20
GRADUALLY VARIED FLOW PROFILE COMPUTED INFORMATION:
DISTANCE FROM FLOW DEPTH VELOCITY SPECIFIC PRESSURE+
CONTROL(FT) (FT) (FT/SEC) ENERGY(FT) MOMENTUM(POUN
0,000 1.200 1.583 1.239 58.91
0,229 1,175 1,615 1.216 56.75
0,456 1,151 1,649 1.193 54,66
0,681 1,126 1.686 1.170 52,63
0,905 1.102 1.725 1.148 50,65
1,127 1.077 1.766 1.126 48,74
1.347 1.053 1.811 1.104 46,89
1,565 1.028 1.858 1.082 45,11
1.780 1.004 1.909 1.060 43,39
1,993 0.979 1.964 1.039 41.75
2,202 0,954 2.022 1.018 40.17
2,408 0,930 2.085 0.997 38,68
2,609 0,905 2.152 0.977 37,25
2,806 0.881 2.224 0.958 35,91
2.997 0,856 2.302 0.939 34,64
3.182 0,832 2.385 0.920 33.46
3.361 0.807 2.476 0.902 32.37
3.531 0.783 2.573 0.885 31.37
3.691 0.758 2.679 0.870 30.46
3.841 0.733 2.794 0.855 29.65
3.977 0.709 2.919 0.841 28.94
4.098 0.684 3.055 0.829 28.35
4.200 0.660 3.205 0.819 27.87
4.280 0.635 3.369 0,812 27.51
4.332 0.611 3.550 0.807 27.29
4.352 0.586 3.750 0.805 27.21
4.750 0.586 3.750 0.805 27.21
END OF HYDRAULIC JUMP ANALYSIS
PRESSURE+MOMENTUM BALANCE OCCURS AT 3.77 FEET UPSTREAM OF NODE 2405.00 |
DOWNSTREAM DEPTH = 0.745 FEET, UPSTREAM CONJUGATE DEPTH = 0.454 FEET |
NODE 2413.00 : HGL = < 356.956>;EGL= < 357.175>;FLOWLINE= < 356.370>
I******************************************************************************
Page 2
2413.RES
UPSTREAM PIPE FLOW CONTROL DATA:
NODE NUMBER = 2413.00 FLOWLINE ELEVATION = 356.37
ASSUMED UPSTREAM CONTROL HGL = 356.96 FOR DOWNSTREAM RUN ANALYSIS
END OF GRADUALLY VARIED FLOW ANALYSIS
D
m
Page 3
Basin lA
Hydrology
96051A.OUT
San Diego County Rational Hydrology Program
CIVILCADD/CIVILDESIGN Engineering Software, (c) 1993 Version 3.2
Rational method hydrology program based on
San Diego County Flood Control Division 1985 hydrology manual
Rational Hydrology Study Date: 02/06/08
CARLSBAD OAKS PHASE 3
PROPOSED BASIN lA
G:\ACCTS\961005\9605Al.OUT
********* Hydrology Study Control information **********
O'Day Consultants, San Deigo, California - S/N 10125
Rational hydrology study storm event year is 100.0
Map data precipitation entered:
6 hour, precipitation(inches) = 2,800
24 hour precipitation(inches) = 4.900
Adjusted 6 hour precipitation (inches) = 2.800
P6/P24 = 57,1%
San Diego hydrology manual 'C values used
Runoff coefficients by rational method
Process from Point/Station 1.000 to Point/Station 2.000
**** INITIAL AREA EVALUATION ****
Decimal fraction soil group A = 0,000
Decimal fraction soil group B = 1.000
Decimal fraction soil group C = 0,000
Decimal fraction soil group D = 0,000
[INDUSTRIAL area type ]
initial subarea flow distance = 100,00(Ft,)
Highest elevation = 398,40(Ft.)
Lowest elevation = 397.00(Ft.)
Elevation difference = 1.40(Ft.)
Time of concentration calculated by the urban
areas overland flow method (App x-C) = 4.02 min.
TC = [1.8*(l,l-C)*distanceA.5)/(% slopeA(i/3)]
TC = [1.8*(l,l-0.8500)*(100.00A.5)/( 1.40A(l/3)]= 4.02
Setting time of concentration to 5 minutes
RainfaTl intensity (I) = 7.377 for a 100.0 year storm
Effective runoff coefficient used for area (Q=KCIA) is C = 0.850
Subarea runoff = 0.941(CFS)
Total initial stream area = 0.150(Ac.)
Process from Point/Station 2.000 to Point/Station 3.000
**** IRREGULAR CHANNEL FLOW TRAVEL TIME ****
Estimated mean flow rate at midpoint of channel = 4.233(CFS)
Depth of flow = 0.300(Ft.), Average velocity = 0.939(Ft/s)
******* Irregular Channel Data ***********
Page 1
96051A.OUT
Information entered for subchannel number 1 Point number
1
2
3
Manning's 'N'
'X' coordinate
0.00
50.00
100.00
friction factor = 0.040
coordinate
1.00
0.00
1.00
Sub-Channel flow = 4.233(CFS)
flow top width = 30.032(Ft.)
' velocity= 0,939(Ft/s)
' area = 4,510(Sq,Ft)
' ' Froude number = 0,427
Upstream point elevation = 397,000(Pt,)
Downstream point elevation = 395.800(Ft.)
Flow length = 150.000(Ft.)
Travel time = 2.66 min.
Time of concentration = 7.66 min.
Depth of flow = 0.300(Ft.)
Average velocity = 0.939(Ft/s)
Total irregular channel flow = 4
irregular channel normal depth above
Average velocity of channel(s) = 0
233(CPS)
invert elev. =
939(Ft/s)
0.300(Ft.)
Sub-Channel No, 1 critical depth = 0,213(Ft,)
critical flow top width = 21,289(Ft,)
' ' ' critical flow velocity= 1.868(Ft/s)
' ' ' critical flow area = 2,266(Sq,Ft)
Adding area flow to channel
group A
group B
group C
group D
DecimaT fraction soil
Decimal fraction soil
Decimal fraction soil
Decimal fraction soil
[INDUSTRIAL area type
Rainfall intensity = 5
Runoff coefficient used for
Subarea runoff =
Total runoff =
0,000
1.000
0.000
0.000
] 601(in/Hr) for a
sub-area. Rational
4.999(CFS) for 1.050(Ac,)
5,940(CFS) Total area =
100.0 year storm
method,Q=KCiA, C = 0.850
1.20(Ac.)
Process from Point/Station
**** SUBAREA FLOW ADDITION ****
3.000 to Point/Station 3.000
Decimal fraction soil
Decimal fraction soil
Decimal fraction soil
Decimal fraction soil
[INDUSTRIAL area type
Time of concentration
Rainfall intensity =
group A = 0.000
group B = 1.000
group C = 0.000
group D = 0.000
= 7.66 min. ]
5.601(in/Hr) for a
Runoff coefficient used for sub-area. Rational
Subarea runoff = 3.809(CPS) for 0.800(Ac.)
Total runoff = 9.748(CFS) Total area =
100.0 year storm
method,Q=KCIA, C = 0.850
2.00(Ac.)
Process from Point/Station 3.000 to Point/Station 4.000
**** PIPEFLOW TRAVEL TIME (User specified size) ****
upstream point/station elevation = 387.80(Ft.)
Downstream point/station elevation = 385.55(Ft.)
Page 2
96051A,OUT
Pipe length = 225,00(Ft,) Manning's N = 0,013
No. of pipes = 1 Required pipe flow = 9.748(CFS) Given pipe size = 24.00(ln.)
calculated individual pipe flow = 9.748(CPS)
Normal flow depth in pipe = 11,02(In,) Flow top width inside pipe = 23,92(in.)
critical Depth = 13,41(in,)
Pipe flow velocity = 6,93(Ft/s)
Travel time through pipe = 0.54 min.
Time of concentration (TC) = 8.20 min.
End of computations, total study area = 2.00 (Ac )
Page 3
>-flMMHHHHM^C*' I 'i' llli'lllllllWMlllillilHil M
SECTION 4
INLET SIZING
BOBCAT COURT
Node#2413rSTA 9+38.45 LT^
Calculated Flowrate Q = 2.4 cfs
Capacitv of Curb Inlet
Sump: Q = 3.87L(H)'^3/2
IfL = 4',H = 0.29' OK
USE 5' TYPE 'B' C.I.
Node#2415 (STA 9+38.45 RT^
Calculated Flowrate Q = 2.0 cfs
Q = 0.7L(a+y)^3/2 (a = 0.333')
S = 6.90% (Approaching street)
Y = 0.22'
Q/L = 0.288
L = 6.94'
USE 8' TYPE 'B-1'C.I.
FIGURE 27.3
«»<»«>€ OiLT
» • T i , o
DtAWPt.£: ONE SIDE
Cirtn; 0, 10 5, J
I I I
M 40 so
III-27.7
SECTION 5
Temporary
Desilting Basin Calculations
Carlsbad Oaks North
J.N. 961005/5
Prepared By:
O'DAY CONSULTANTS, INC.
2710 Loker Avenue West, Suite 100
Carlsbad, CA 92008
DESILTING BASIN CALCTIf ATTONS
SECTION DESCRIPTION
Surface Area Calculations Explanation
Soil Loss Calculations Explanation
Dewatering Calculation Explanation
4 Basin Sizing, Soil Loss, & Outlet Works Calculation
Spreadsheets
5 Exhibits
SECTION 1
Surface Area Calculations
According to the Fact Sheet for Water Quality Order 99-08-DWQ issued by the State
Water Resources Control Board (SWRCB), sediment basins shall, at a minimum, be
designed and maintained as follows:
Option 1: Pursuant to local ordinance for sediment basin design and maintenance,
provided that the design efficiency is as protective or more protective of water
quality than Option 3.
OR
Option 2: Sediment basin(s), as measured firom the bottom ofthe basin to the principal
outlet, shall have at least a capacity equivalent to 3,600 cubic feet of storage
per acre draining into the sediment basin. The length of the basin shall be
more than twice the width ofthe basin. The length is determined by measuring
the distance between the inlet and the outlet; and the depth must not be less
than three feet nor greater than five feet for safety reasons and for maximimi
efficiency.
OR
Option 3: Sediment basin(s) shall be designed using the standard equation:
A,= 1.2QA^,
Where: Ag is the minimum surface area for trapping soil particles of a certain
size; V, is the settling velocity of the design particle size chosen; and
Q=CxIxA where Q is the discharge rate measured in cubic feet per second; C
is the runoff coefficient; I is the precipitation intensity for the 10-year, 6-hour
rain event and A is the area draining into the sediment basin in acres. The
design particle size shall be the smallest soil grain size determined by wet sieve
analysis, or the fme silt sized (0,01 mm) particle, and the Vj used shall be 100
percent of the calculated settling velocity.
The length is detennined by measuring the distance between the inlet and the
outlet; the length shall be more than twice the dimension as the width; the
depth shall not be less than three feet nor greater than five feet for safety
reasons and for maximum efficiency (two feet of storage, two feet of capacity).
The basin(s) shall be located on the site where it can be maintained on a year-
round basis and shall be maintained on a schedule to retain the two feet of
capacity;
OR
Option 4: The use ofan equivalent surface area design or equation, provided that the
design efficiency is as protective or more protective of water quality than
Option 3.
Sediment basins for Carlsbad Oaks were designed to satisfy the requirements ot Option
i, using the following parameters:
Appendix II-A-4 ofthe San Diego County Hydrology Manual gives the precipitation for
a 10-year, 6-hour storm as 1.9 mches for this project. (See Exhibit "A")
P = 1.9 inches/6 hours
I = 0 J2 avg. inches/hour (per Goldman et al., p. 8.16)
Appendix IX ofthe San Diego County Hydrology Manual gives the runoff coefficients
for this project as C=0 JS to C=0.45. (See Exhibit "B*0
Table 8.1 of the Erosion and Sediment Control Handbook (See Exhibit "C") gives the
settling velocity for a 0,01 mm sized particle as Vs = 0.00024 feet/second.
The San Diego County Soils Interpretation Study gives the soil classification for this
project as "B**, "C, and "D", (See Exhibit "D")
FOR BASIN CALCULATION SUMMARY SPREADSHEET SEE SECTION 4
SECTION 2
SOIL LOSS CALCULATIONS
CHAPTER 5 OF THE EROSION AND SEDIMENT CONTROL HAlsmRnoy
DISCUSSES CALCULATING SOIL LOSS WITH THE UNIVERSAL SOIL LOSS
EQUATION
a,2« Tk* BquatioK
Th«fM«lfmofllM
A- KX JCXLSXCXP
Jl « nb(UlwQaiwiadii,faiiaOlt -toni/Mn X la/hr
K- •oltMdfliilHyteetM'.teaa/Mraptrwdtaf I
'c " n!!!iuiy^ tMtQf, i'—lm
i* « tralM ewiM BraoH
RAINFALL INDEX "R"
RAINFALL EROSION INDEX "R" IS BASED ON THE GEOGRAPHICAL
n
I
fit- 5.3 DiitributioB of ttorm type* in tha
N.W Mt«ie«. VtMk, »4 Wyomin,
clloL U u"""^ '"""^ ^year. «... ...ral, ,n
Th» dUhiMicw k padi intentHy m idkKtid fal tha cotiBdMrti of ttl* iqiM.
tion fbr ths niBbl fictw. Fiiun M il • giapUeil Nina^
tioM, Tlx aqiutiMii, alM ihom M tho cotvot foe OMh faMlividaal itom ^po,
UK
JI-37p^ typon
"P" FOR THIS EQUATION IS THE PRECIPITATION FOR A 2-YEAR, 6-HOUR
STORM EVENT, APPENDIX II-A-2 FROM THE SAN DIEGO COUNTY
HYDROLOGY MANUAL GIVES P = 1.4 (SEE EXHIBIT "E")
R = 16.55*P'^2.2
= 16.55*1.4^2,2
= 34.7
SOIL FACTOR "K"
FROM THE SOILS REPORT, THE SITE CONSISTS OF 50% SAND AND 50% CLAY
AND SILT, ASSUMING HALF OF THE 50% IS CLAY. THE OTHER HALF SILT
K = 0.24 (SEE TABLE BELOW)
pgRcmr CM
CLAY
i t 9 a i * * *
^ CMCgNT SANO
0 LENGTH SLOPE AND STEEPNESS FACTOR "LS"
SLOPE LENGTH AND STEEPNESS FACTOR "LS" IS CALCULATED USING TABLE 5.5 OF
THE EROSION AN SEDIMENT CONTROL HANDBOOK (SEE EXHIBIT "F")
FOR BASIN CALCULATION SUMMARY SEE SECTION 4
VEGETATION COVER FACTOR "C"
THE COVER FACTOR TABLE LISTED BELOW IS USED FOR AREA
UNDER CONSTRUCTION OR CULTIVATION. TO BE CONSERVATIVE
THE HIGHEST VALUE IS ASSUMED.
C=I.O
VAMIMUM CValaMhvMLa
9»%tmtm.mmmltrmmm.m»mutA flit M
Itmutakt WKvUk,%*om/mttm 11.1 t/kai, with wm»^ «« M
aa*.Jutot ftS i»
4t«M/kM{lL*VMbl
. IU lib I
xptaati.
EROSION CONTROL PRACTICE FACTOR "P'*
THE P VALUES LISTED BELOW ARE GIVEN FOR AREAS UNDER
CONSTRUCTION OR CULTIVATION. TO BE CONSERVATIVE,
THE HIGHEST VALUE WAS ASSUMED.
P=L3
8<irfiM» eomlltl— f TtlM
fVunpajfi uxt unootk
TnckMlM >l«af eoatDur* U
Puacha4 itnv
%>u«li, tfiHUla'cut
Lo«M to IS-IB (30-oa) cUptk 0*
'Tmd Mwto ariMU4 u* tad imn •lap*.
rTM<Mftoori<M*4pw«IMto<aMoiM, b» Tlob IA aad
0'
SECTION 5.31. PAGES 5.27 TO 5,28 LISTS A STEP BY STEP PROCEDURE FOR
USING THE UNIVERSAL SOIL LOSS EQUATION (SEE EXHIBIT "G")
FOR SOIL LOSS CALCULATION SUMMARY SPREADSHEET SEE SECTION 4
(i
SECTION 3
t|r-
~"•WIWIII 'a^' JH
: ^
~ A£(^<0.O^Sf7^^ - IAJ5.
t
U—
SECTION 4
sin A - Lof 20
Desiltation Basin Calculations StandDioe Calculations
Q = CxlxA
c = 0.45 Tc = 5 min. (see Desilting Basin Tributary Area Exhibit)
'avg ~ Pe/e hr. 1 = 7.64 in./hr
P6 = 1.9 in. (per 10 yr-6 hr Isopluvial) Q = 7.2 cfs
'avg ~ 0.32 in./hr h = 1 ft.
Pad A = 1.89 ac.
Slope A = 0.28 ac. Case 1 Case 2
Total A = 2.17 ac. Q = CPh^ Q = CA(2gh)^'^
Qavg ~ 0.308979 cfs C = 3.0 C = 0.67
P = 2.40074 ft A= 1.34 ft^
A,= 1.2QA/s d = 0.76 ft d= 1.31 ft
v,= 0.00024 ft/sec 24" pipe
min. As = 1545 sf
actual As = 2619 sf
il Loss Calculations
A=RxKxLSxCxP
R=16.55(p)"
p = 1.4 in. (per 2yr-6 hr. Isopluvial)
R = 34.70
K = 0.24 (CIE2, CmE2, & CnG2 soils - per Table 5-2)
C = 1.0 (Bare areas - per Table 5-5)
P = 1.0 (Pacl^ed & Smooth - per Table 5-6) Basin Dewatering Calculations
Area Use % Area Length" Slope/ Grade LS"* Ao = As(2H)"'
Slope 13.1% 45 2:1 12 3600(T)C„(g)'''
Pad 86.9% 300 2% 0.28
3600(T)C„(g)'''
"* = See Desilting Basin Tributary Area Exhibit
'" = Per Figure 5-5
Avg. LS = 1.81
A= 15.07 tn/yr/ac
Loss = 32.7 tn/yr
= 594 cf
H= 2 ft
T = 40 hr
Cd = 0.6
g = 32.2 ft/sec
Ao= 0.010684 ft^
= 1.54 in^
sinB- Lot 21
Desiltation Basin Calculations
Qavg ~ C X igyg X A
standpipe Calculations
Q = CxlxA
c = 0.45 Tc = 5 min. (see Desilting Basin Tributary Area Exhibit)
'avg ~ Pe/e hr. 1 = 7.64 in./hr.
P8 = 1.9 in. (per 10 yr-6 hr. Isopluvial) Q = 14.8 cfs
'avg ~ 0.32 in./hr h = 1 ft.
Pad A = 3.11 ac.
Slope A = 0.77 ac. Case 1 Case 2
Total A = 3.88 ac. Q = CPh^ Q = CA(2gh)^'^
Qavg ~ 0.552695 cfs C = 3.0 C = 0.67
P = 4.939174 ft A= 2.75 ft^
As = 1.2Q/Vs d = 1.57 ft d= 1.87 ft
Vs = 0.00024 ft/sec 24" pipe
min. As = 2763 sf
actual As = 4075 sf
^0/7 Loss Calculations
W= RxKxLSxCxP
R=16.55(p) 2.2
P = 1.4 in. (per2yr-6 hr. Isopluvial)
R = 34.70
K = 0.24 (CIE2, CmE2, & CnG2 soils - per Table 5-2)
C = 1.0 (Bare areas - per Table 5-5)
P = 1.0 (Packed & Smooth - per Table 5-6) Basin Dewaterina Calculations
Area Use % Area Length** Slope/ Grade LS*** Ao = As(2H)'''
Slope 19.9% 40 1.5:1 16.88 3600(T)C<i(g)"'
Pad 80.1% 350 2% 0.29
3600(T)C<i(g)"'
" = See Desilting Basin Tributary Area Exhibit
"* = Per Figure 5-5
Avg. LS = 3.60
A = 29.95 tn/yr/ac
pil Loss = 116.2 tn/yr
= 2112 cf
H= 2 ft
T = 40 hr
Cd = 0.6
g = 32.2 ft/sec
Ao= 0.016623 ft"
= 2.39 in^
sin C - Fill Area Lot 22
Desiltation Basin Calculations
Qavg ~ C X igvg X A
Standpipe Calculations
Q = CxlxA
c = 0.45 Tc = 5 min. (see Desilting Basin Tributary Area Exhibit)
'avg ~ Pe/e hr. 1 = 7.64 in./hr.
P6 = 1.9 in. (per 10 yr.-6 hr. Isopluvial) Q = 15.1 cfs
'avg 0.32 in./hr h = 1 ft.
Pad A = 3.14 ac.
Slope A = 0.81 ac. Case 1 Case 2
Total A = 3.94 ac. Q = CPh^'^ Q = CA(2gh)^'^
Qavg ~ 0.561691 cfs C = 3.0 C = 0.67
P = 5.019569 ft A = 2.80 ft^
As = 1.2Q/V, d = 1.60 ft d= 1.89 ft
Vs = 0.00024 fl/sec 24" pipe
min. As = 2808 sf
actual A, = 4459 sf
Oil Loss Calculations
RxKxLSxCxP
R=16.55(p) 2.2
p = 1.4
R = 34.70
K = 0.24
C = 1.0
P = 1.0
Area Use % Area Length** Slope/ Grade LS***
Slope 20.4% 50 1.5:1 18.87
Pad 79.6% 430 2% 0.31
Basin Dewaterina Calculations
\1/2 Ao= A,(2H)'
3600(T)Cd(g) 1/2
'* = See Desilting Basin Tributary Area Exhibit
'** = Per Figure 5-5
Avg. LS= 4.10
A= 34.18 tn/yr/ac
H =
T =
Cd =
g =
2
40
0.6
32.2
ft
hr
ft/sec
Ao= 0.018190 ft"
Loss= 134.7 tn/yr
= 2449 cf
2.62 in''
sin D- Lot 23
Desiltation Basin Calculations
Qavg ~ C X igvg X A
Standpipe Calculations
Q = CxlxA
c = 0.45 Tc = 5 min. (see Desilting Basin Tributary Area Exhibit)
'avg ~ P6/6 hr. 1 = 7.64 in./hr.
P6 = 1.9 in. (per 10 yr.-6 hr. Isopluvial) Q = 15.7 cfs
'avg ~ 0.32 in./hr h = 1 ft.
PadA = 3.81 ac.
Slope A = 0.30 ac. Case 1 Case 2
Total A = 4.11 ac. Q = CPh^'^ Q = CA(2gh)^'^
Qavg ~ 0.585675 cfs C = 3.0 C = 0.67
P = 5.233905 ft A= 2.92 ft^
As = 1.2QA/, d = 1.67 ft d= 1.93 ft
v,= 0.00024 ft/sec 24" pipe
min. As = 2928 sf
actual As = 2930 sf
Loss Calculations
= RxKxLSxCxP
R=16.55(p) 2.2
P = 1.4 in. (per 2yr -6 hr. Isopluvial)
R = 34.70
K = 0.24 (CIE2, CmE2, & CnG2 soils - per Table 5-2)
C = 1.0 (Bare areas - per Table 5-5)
P = 1.0 (Packed & Smooth - per Table 5-6) Basin Dewaterina Calculations
Area Use % Area Length** Slope/ Grade LS*** Ao = As(2H)"'
Slope 7.3% 55 2:1 13.21 3600(T)Cd(g)"'
Pad 92.7% 300 2% 0.28
3600(T)Cd(g)"'
** — = See Desilting Basin Tributary Area Exhibit
Per Figure 5-5
Avg. LS= 1.22
A= 10.19 tn/yr/ac
pil Loss'
H ••
J-
Cd =
g =
2 ft
40 hr
0.6
32.2 ft/sec
41.9 tn/yr
762 cf
Ao= 0.011952 ft"
= 1.72 in^
l^^sinE- Lof 24 (WEST)
Desiltation Basin Calculations
Qavg ~ C X iayg X A
C = 0.45
iavg = Pe/e hr.
Pe = 1.9 in. (per 10 yr.-6 hr. Isopluvial)
Tc:
I :
Standpipe Calculations
Q = CxlxA
5 min. (see Desilting Basin Tributary Area Exhibit)
7.64 in./hr.
'avg ~
PadA =
Slope A =
Total A =
Qavg ~
A,=
0.32 in./hr
2.00 ac.
0.00 ac.
2.00 ac.
0.285 cfs
1.2QA/s
0.00024 ft/sec
Q = 7.6 cfs
h= 1 ft.
Case 1
Q = CPh^
C= 3.0
P= 2.546913 ft
d = 0.81 ft
Case 2
Q = CA(2gh)^'^
C = 0.67
A =
d =
1.42 ft^
1.35 ft
18" pipe
min. As = 1425 sf
actual A, = 2355 sf
il Loss Calculations
T= RxKxLSxCxP
R=16.55(p) 2.2
p = 1.4 in. (per 2yr.-6 hr. Isopluvial)
R = 34.70
K= 0.24 (CIE2,CmE2,&CnG2 soils-per Table 5-2)
C = 1.0 (Bare areas - per Table 5-5)
P = 1.0 (Packed & Smooth - per Table 5-6) Basin Dewaterina Calculations
Area Use % Area Length** Slope/ Grade LS***
Slope 0.0% 0 2:1 0
Pad 100.0% 230 2% 0.26
See Desilting Basin Tributary Area Exhibit
" = Per Figure 5-5
Avg. LS = 0.26
A= 2.17 tn/yr/ac
il Loss:
Ao^ A,(2H) 1/2
3600(T)Cd(g) 1/2
4.3 tn/yr
79 cf
H= 2 ft
T = 40 hr
Cd = 0.6
g = 32.2 ft/sec
Ao = 0.009607 ft"
= 1.38 in^
inF- Lot 24 (NORTH)
Desiltation Basin Calculations
Qavg ~ C X i3yg X A
Standpipe Calculations
Q = CxlxA
c = 0.45 Tc = 7.4 min. (see Desilting Basin Tributary Area Exhibit)
'avg ~ P^Q hr. 1 = 5.93 in./hr.
P6 = 1.9 in. (per 10 yr.-6 hr. Isopluvial) Q = 17.3 cfs
'avg ~ 0.32 in./hr h = 1 ft.
Pad A = 5.83 ac.
Slope A = 0.00 ac. Case 1 Case 2
Total A = 5.83 ac. Q = CPh^ Q = CA(2gh)^'^
Qavg ~ 0.830775 cfs C = 3.0 C = 0.67
P = 5.765458 ft A = 3.21 ft^
A,= 1.2Q/V, d = 1.84 ft d = 2.02 ft
Vs = 0.00024 fl/sec 24" pipe
min. A, = 4154 sf
actual As = 4655 sf
il Loss Calculations
>=RxKxLSxCxP
R=16.55(p) 2.2
p = 1.4 in. (per2yr.-6 hr. Isopluvial)
R = 34.70
K = 0.24 (CIE2, CmE2, & CnG2 soils - per Table 5-2)
C = 1.0 (Bare areas - per Table 5-5)
P = 1.0 (Packed & Smooth - per Table 5-6) Basin Dewaterina Calculations
Area Use % Area Length** Slope/ Grade LS*" Ao = A,(2H)^'^
Slope 0.0% 0 2:1 0 3600(T)Cd(g)'"
Pad 100.0% 730 2% 0.36
3600(T)Cd(g)'"
' = See Desilting Basin Tributary Area Exhibit
'* = Per Figure 5-5
Avg. LS =
A:
I Loss ••
0.36
3.00 tn/yr/ac
17.5 tn/yr
318 cf
H= 2 ft
T = 40 hr
Cd = 0.6
g = 32.2 ft/sec
Ao= 0.018989 ft"
= 2.73 in^
^s/n G -Lot 24 (SOUTH)
Desiltation Basin Calculations Standpipe Calculations
Qavg "* C X igyg X A Q = CxlxA
c = 0.45 Tc = 10 min. (see Desilting Basin Tributary Area Exhibit)
'avg ~ P6/6 hr. 1 = 4.89 in./hr.
P6 = 1.9 in. (per 10 yr.-6 hr. Isopluvial) Q = 30.4 cfs
'avg ~ 0.32 in./hr h= 1 ft.
Pad A = 12.44 ac.
Slope A = 0.00 ac. Case 1 Case 2
Total A = 12.44 ac. Q = CPh^'^ Q = CA(2gh)^'^
Qavg ~ 1.7727 cfs C= 3.0 C= 0.67
P= 10.13071 ft A= 5.65 ft^
As = 1.2QA/, d= 3.23 ft d= 2.68 ft
Vs = 0.00024 ft/sec 42" pipe
min. As = 8864 sf
actual As = 9080 sf
^0/7 Loss Calculations
^=RxKxLSxCxP
R=16.55(p) 2.2
P = 1.4 in. (per 2yr.-6 hr. Isopluvial)
R = 34.70
K = 0.24 (CIE2, CmE2. & CnG2 soils - per Table 5-2)
C = 1.0 (Bare areas - per Table 5-5)
P = 1.0 (Packed & Smooth - per Table 5-6) Basin Dewaterina Calculations
Area Use % Area Length** Slope/ Grade LS*** Ao= As(2H)^''
Slope 0.0% 0 2:1 0 3600(T)Cd(g)'"
Pad 100.0% 1350 2% 0.43
3600(T)Cd(g)'"
= See Desilting Basin Tributary Area Exhibit
' = Per Figure 5-5
Avg. LS ••
A'
0.43
3.58 tn/yr/ac
iPil Loss = 44.5
810
tn/yr
cf
H = 2 ft
T = 40 hr
Cd = 0.6
g = 32.2 ft/sec
Ao = 0.037040 ft"
= 5.33 in^
sin H - Lot 25
Desiltation Basin Calculations
Qavg ~ C X iavg ^ ^
Standpipe Calculations
Q = c X I X A
c = 0.45 Tc = 5 min. (see Desilting Basin Tributary Area Exhibit)
'avg ~ P6/6 hr. 1 = 7.64 in./hr.
P6 = 1.9 in. (per 10 yr.-6 hr. Isopluvial) Q = 29.7 cfs
'avg ~ 0.32 in./hr h = 1 ft.
PadA = 6.41 ac.
Slope A = 1.37 ac. Case 1 Case 2
Total A = 7.78 ac. Q = CPh^^ Q = CA(2gh)^'^
Qavg ~ 1.10865 c:fs C = 3.0 C = 0.67
P = 9.90749 ft A = 5.52 ft^
A,= 1.2QA/s d = 3.16 ft d = 2.65 ft
Vs = 0.00024 ft/sec 36" pipe
min. As = 5543 sf
actual As = 5655 sf
il Loss Calculations
RxKxLSxCxP
2.2 R =16.55(p)^
p = 1.4
R = 34.70
K = 0.24
C = 1.0
P = 1.0
Area Use % Area Length** Slope/ Grade LS***
Slope 17.6% 85 2:1 16.43
Pad 82.4% 550 2% 0.34
'* = See Desilting Basin Tributary Area Exhibit
'** = Per Figure 5-5
Avg. LS = 3.17
A = 26.42 tn/yr/ac
Basin Dewaterina Calculations
Ao= As(2H)^"
3600(T)Cd(g)'"
H= 2 ft
T = 40 hr
Cd = 0.6
g = 32.2 ft/sec
Loss = 205.6 tn/yr
= 3738 cf
Ao = 0.023069 ft"
= 3.32 in^
sin I - Lot 26
Desiltation Basin Calculations
Qavg *" C X igyg X A
standpipe Calculations
Q = C X I x A
c = 0.45 Tc = 5 min. (see Desilting Basin Tributary Area Exhibit)
'avg ~ Pe/d hr. 1 = 7.64 in./hr.
P6 = 1.9 in. (per 10 yr.-6 hr. Isopluvial) Q = 15.5 cfs
'avg ~ 0.32 in./hr h = 1 ft.
Pad A = 3.55 ac.
Slope A = 0.52 ac. Case 1 Case 2
Total A = 4.07 ac. Q = CPh^^ Q = CA(2gh)^'^
Qavg ~ 0.579975 cfs C = 3.0 C = 0.67
P = 5.182967 ft A = 2.89 ft^
As = 1.2QA/s d = 1.65 ft d= 1.92 ft
Vs = 0.00024 ft/sec 24" pipe
min. As = 2900 sf
actual As = 3655 sf
il Loss Calculations
= RxKxLSxCxP
R=16.55(p) 2.2
p = 1.4
R = 34.70
K = 0.24
C = 1.0
P = 1.0 Basin Dewaterina Calculations
Area Use % Area Length** Slope/ Grade LS*** Ao = As(2H)'"
Slope 12.8% 55 2:1 13.21 3600(T)Cd(g)"'
Pad 87.2% 440 2% 0.32
3600(T)Cd(g)"'
'* = See Desilting Basin Tributary Area Exhibit
'** = Per Figure 5-5
Avg. LS= 1.97
A= 16.38 tn/yr/ac
il Loss = 66.7 tn/yr
= 1212 cf
H= 2 ft
T = 40 hr
Cd = 0.6
g = 32.2 ft/sec
Ao= 0.014910 ft"
= 2.15 in^
MODIFIED TYPE 'F'
TYPE 'F' CATCH BASIN
CAPACITY
r
110
- II
10
- 9
- 8
3>
UJ
X o m
o
IlJ
- 600
- 500
- 400
'- 300
. r 200
CHART I
EXAMPLE
5'> e' Bo* 0*75 cfl
0/B • I5cft/ft
HW
f«»t.''
/
(I)
./f 8
=.7-
inlat
(1)
(S)
(3)
D
1.75
1.90
2J05
3.S
3.6
4.1
- 6
- 5
- 4
- I
To UII icoli (2) er (3). projict
horizontally te icoli (I), then
UII streight inciinid lim through
0 ond 0 ieol»,or riverie oi
llluitrotid.
(2)
r- 9
- 8
- 7
- 6
-5
- 4
- .4
(3)
r- 10
- 8
- 7
- 6
- 5
- 4
.5
- .4
l- .30 35 L .35
euREi OP PUBLIC ROAOS JAN. I»63 K
HEADWATER DER,THL
FOR BbjKTcUirNTERtS'
WITH i:NLg:SrcQNXF(bL
mm
5-2!
OUTLET PIPES
O'Day Consultants Inc.
2710 Loker Avenue West, Suite 100
Carlsbad, CA 92008
Tel: (760) 931-7700 Fax: (760) 931-8680
Inside Diameter
( 24.00 in.)
loT 23
AAAAAAAAA.A.AAAAAAA.A.AA.A.
Water
* ( 10.02 in.)
( 0.835 ft.)
" v_
Circular Channel Section
Flowrate 15.700 CFS
Velocity 12.641 fps
Pipe Diameter 24.000 inches
Depth of Flow 10.020 inches
Depth of Flow 0.835 feet
Critical Depth 1.430 feet
Depth/Diameter (D/d) 0.418
Slope of Pipe 2.600 %
X-Sectional Area 1.242 sq. ft.
Wetted Perimeter 2.810 feet
AR*(2/3) 0.721
Mannings 'n' 0.011
Min. Fric. Slope, 24 inch
Pipe Flowing Full 0.345 %
m.
O'Day Consultants Inc.
2710 Loker Avenue West, Suite 100
Carlsbad, CA 92008
Tel: (760) 931-7700 Fax: (760) 931-8680
Inside Diameter
( 24.00 in.)
Water
( 8.76 in.)
{ 0.730 ft.)
I
Circular Channel Section
Flowrate
Velocity
Pipe Diameter
Depth of Flow
Depth of Flow
Critical Depth
Depth/Diameter (D/d) ....
Slope of Pipe
X-Sectional Area
Wetted Perimeter
AR*(2/3)
Mannings 'n'
Min. Fric. Slope, 24 inch
Pipe Flowing Full
7 600 CFS
7 331 fps
24 000 inches
8 758 inches
0 730 feet
0 985 feet
0 365
1 000 %
1 037 sq. ft
2 594 feet
0 563
0 Oil
0 081 %
O'Day Consultants Inc.
2710 Loker Avenue West, Suite 100
Carlsbad, CA 92008
Tel: (760) 931-7700 Fax: (760) 931-8680
Inside Diameter
( 18.00 in.)
* *
' Water ^
* ( 14.52 in.)
( 1.210 ft.)
* V
Circular Channel Section
Flowrate 17.3 00 CFS
Velocity 11.325 fps
Pipe Diameter 18.000 inches
Depth of Flow 14.518 inches
Depth of Flow 1.210 feet
Critical Depth Greater than Pipe Diameter
Depth/Diameter (D/d) 0.807
Slope of Pipe 2.000 %
X-Sectional Area 1.527 sq. ft.
Wetted Perimeter 3.346 feet
AR"(2/3) 0.905
Mannings 'n' 0.011
Min. Fric. Slope, 18 inch
Pipe Flowing Full 1.941 %
m.
O'Day Consultants Inc.
2710 Loker Avenue West, Suite 100
Carlsbad, CA 92008
Tel: (760) 931-7700 Fax: (760) 931-8680
LOT ^S TH)
Inside Diameter
( 24.00 in.)
*
* *
* *
* *
AAAAAAAAAAAAAAAAAAAAA
Water
* ( 8.42 in.)
( 0.702 ft.)
v
Circular Channel Section
Flowrate 30.400 CFS
Velocity 30.902 fps
Pipe Diameter 24.000 inches
Depth of Flow 8.424 inches
Depth of Flow 0.702 feet
Critical Depth 1.867 feet
Depth/Diameter (D/d) 0.351
Slope of Pipe 18.500 %
X-Sectional Area 0.984 sq. ft.
Wetted Perimeter 2.536 feet
AR*(2/3) 0.523
Mannings 'n' 0.011
Min. Fric. Slope, 24 inch
Pipe Flowing Full 1.293 %
O'Day Consultants Inc.
2 710 Loker Avenue West, Suite 100
Carlsbad, CA 92008
Tel: (760) 931-7700 Fax: (760) 931-8680
Inside Diameter
( 24.00 in.)
LOT LS
Water
( 10.64 in.)
( 0.887 ft.)
m circular Channel Section
V
29 700 CFS
22 089 fps
24 000 inches
Depth of Flow 10 639 inches
0 887 feet
Critical Depth 1 862 feet
Depth/Diameter (D/d) 0 443
Slope of Pipe 7 500 %
1 345 sq. ft
2 914 feet
AR*(2/3) 0 803
0 Oil
Min. Fric. Slope, 24 inch
1 234 %
r
O'Day Consultants Inc.
2710 Loker Avenue West, Suite 100
Carlsbad, CA 92008
Tel: (760) 931-7700 Fax: (760) 931-8680
LOT ZCD
Inside Diameter
( 24.00 in.)
* *
AAAAAAAAAAAAAAAAAAAAA
Water
I
* ( 9.95 in.)
( 0.829 ft.)
Circular Channel Section
Flowrate 15 500 CFS
Velocity 12 598 fps
24 000 inches
Depth of Flow 9 949 inches
Depth of Flow 0 829 feet
Critical Depth 1 424 feet
Depth/Diameter (D/d) 0 415
2 600 %
X-Sectional Area 1 231 sq. ft
Wetted Perimeter 2 798 feet
AR*(2/3) 0 .712
0 . Oil
Min. Fric. Slope, 24 inch
Pipe Flowing Full 0 .336 %
SECTION 5
4 ! " r •
i
d
M
i i • .
•I-I 1
: i County of San Diego
Hydrology Manu^
Raurfall Isopluvials
2 Year lUiniaU Eveat-6 Hours
Isopluvial (inctias)
/."//A/.
DPW ^GIS SGIS 431.1
Han: .Sai 1>I{B CiKOtJ!
County of San Diego
Hydrology Manual
County of San Diego
Hydrology Manual
Rainfall Isopluvials
infl -v^tr H«inf«ii Event - 6 Houw
laapkMiil (inctias)
RUNOFF COEFFICIENTS (RATIONAL METHOD)
LWD USE
(
a —
Soil Group (I)
A B C D
Undeveloped .30 .33 .40 .45
Residential:
Rural .50 .53 .40 . -*3
Single Famil/ .40 .43 .50 . 53
Multi-Units .45 .30 .60 . 70
Mobile Homes (2) .45 .50 .33 .65
Commercial (2)
30% Impervious
.70 . 73 .80 .35
Industrial (2)
90% Impervious
.80 .85 .90 .91
.VOTES;
(1) Obtain soil group from maps on file with the Department of Sanitation
and Flood Control.
(2) Where actual conditions deviate significantly frora the tabulated
imperviousness values of 30% or 90%, the values given for coefficient
C, may be revised by multiplying 80% or 90% by the ratio of actuai
imperviousness to the tabulated imperviousness. However, in no casa
shall the final coefficient be less than 0.50. For example: Consider
ccnunercial property on D soil group.
Actual imperviousness = 50%
Tabulated imperviousness = 30'i
Revised C = X 0.35 = 0.5.i
&1« Kre»toa and 8e»Hme»t CoBfaol HMJtwu>w
TABLE 8.1 Surface Area RequiremenU ci Sediment Trap, and Basina
Partida siaa, bun
Settling veloci^,
tt/eec (m/sec)
0.6
0.2
ai
COS
0.0^
0.01
(coanasand)
(medium sand)
(flnaaand)
(cohna lilt)
(medium silt)
(iinaailt)
Suifaca area requirements,
ft'pwftVeee (ia*peimVeec
diacharia diMJiarga)
0.006 (clay)
ai9 (0.068)
0.067 (0.020)
0.02S (0.0070)
0.0062 (0.0019)
0.00O9& (0.00029)
0.00024 (0.000073)
0.00006 (0.000018)
6.3
17.9
52.2
193.6
1.250.0
5,000.0
20,000.0
(2a7)
(68.7)
(171.0)
(636.0)
(4,101.0)
(16,404.0)
(66,617.0)
Jl^t compcd of parUclM in the 0.01- to 0.02-mm r«,ge. A surfac. are. 4
ume. iMger would ba nailed to capture 5 percent more of Sue soU
A baluice between the cost-effecUvenea. of a certain baain size a^d th. deaire
to capture fin. partida muat b. achi.v«l. It i. de.ir.bl. to captur.^^™
water quality problem.. However. Table 8.1 .how. that. baain would hav. toS
^(Si Z ^''''^T," '''^'^ particular da^^?d«
0 005 mm and «naller. Beoauae of the high cost of trapping ve.y «aaU particle
the author, recommend 0.02 a. the deaign particle si^T for^diment b^Si
except in area, with coarse soils, where a larger design particle mayS
0^2^mm particle i. classified a. a medium silt by the*^l5So3 c^as^aS:
8.2d Basin Discharge Rate
The peak discharge, calculated by the rational or another approved method is
with water to tha top of it. ruer and then discharge at the rat. of inflow to th.
baam. A sediment b^m is not designed with a large water storage volume as k
a reservoir W the inflow exceeds the design peak flow used to ske th. riser tf,"
overflow should discharge down an emergency spiUway.
8.2e Design Runoff Rate
In the equation for surface area of a sediment baain. the discharge rate Q is »
shows that the discharge rate is, to a large extent, equal to the inflow. Th!
..ser IS sized to handle the peak inflow to the basin. The authors suggest de er
mining the surface area by the aoerage runoff of a IQ.year. 6-hr stTrm nstead
Sediment Retention Strueti
of th. peak flow. A aubstai
and basin efficiency ia not a
Consider a baain dengne
off rate. Th. av.iase rainfd
storm (Sec. 4.1f). On-, site i
ideal settUng condition, thi
soil (i..., 62 percent of the
particle.). .
If th. surface area of tb
would b. roughly 3 time.
Reclamation (10). 25 percei
period (Fig. 4.2). Since the
limeters) per hour,^ the pei
percent of the S-hr totaL Si
discharge rate (A i- 1.2Q/1
timM the average rate (509
flow would be about 3 times
sized for th. p.ak flow woul
partides with approximate
cle. Since the 0.02-mm part
with a settling velocity of
tured. These are approximi
Suppose a basin on a sit
rate. For th. purpose of iU
of the San Frandsco Bay i
tides, by weight, greater ti
0.02 mm). A basin with a la
ture the 0.01- to 0.02-mm |
67 percent of the eroded m;
cent (5/62) by tripling the
eflfective to size a baain^bj,
basin efflciency wiU not be
3.2f Settling Depth
If a basin is too shallow, w
settled particles and decre
grit-settling chambers at a
trolled to prevent particle
grit chamber (2) is:
I,.
'•l<Ji.v
.y
1
^BsE
LS value, for foUowing dope kngths I, ft (m)
Siope 90 100 lope gradient 10 20 30 40 50 60 70 80
(24.4)
90 100
atio «. % (3.0) (6.1) (9.1) (12.2) (15.2) (18.3) (21.3)
80
(24.4) (27.4) (30.5)
0.5 0.06 0.07 0.07 0.08 0.08 0.09 OM ao8 0S» aio
30:1 1 0.08 0.09 0.10 0.10 0.11 0.11 ai2 ai2 0.12 ai2 30:1
2 0.10 0.12 0.14 0.15 0.16 ai7 0.18 ai9 ai9 OM
3 0.14 0.18 0.20 0.22 0.23 0.25 0.26 0.27 0.28 029
4 0.16 0.21 0.25 0.28 aso 0J3 0J6 0.37 OM 0.40
20:1 5 0.17 0.24 0.29 0.34 0.38 a4i 0.45 a48 0.61 0.53 20:1
6 0.21 0.30 0.37 0.43 0.48 0.52 0.56 OJGO 0.64 0.67
7 0.26 0.37 0.45 a52 ass 0.64 aeo a74 a78 0.82
8 0.31 0.44 0.54 a63 &70 0.77 OJS 0.8S 0.94 OM
9 0.37 0.52 0.64 0.74 0J3 0.91 0.98 LOS Lll L17
10:1 10 0.43 0.61 0.75 a87 0.97 L06 LIS L22 1.30 1.37 10:1
IX 0.50 0.71 0.86 1.00 L12 1.22 1.32 1.41 1.50 1.58
8:1 12.5 0.61 0.86 1.05 1.22 IM 1.49 1.61 1.72 L82 1.92 8:1
IS 0.81 1.14 1.40 1.62 1.81 1.98 2.14 2.29 2.43 2.56
6:1 16.7 0.96 1.36 1.67 1.92 2.15 2.36 2.64 2.72 2.88 3.04
5:1 20 1.29 1.82 2.23 2.58 2.88 3.16 3.41 3.66 3.87 4.08
IK:1 22 1.51 2.13 2.61 3.37 3.69 3.99 4.27 4J3 4.77
4:1 25 1.86 2.63 3.23 3.73 4.16 4.66 4.93 5.27 &69 BM 4:1
30 2.51 3.56 4.36 6J03 5.62 6.16 6.65 7.11 7.64 IM
3;1 33.3 238 4.22 6.17 5.96 6.67 7.30 7.88 8.43 8.95 OAS
35 3.23 4.57 5.60 6.46 7JS 7J2 8.56 9.14 9.70 10.22
:K:1 40 4.00 5.66 6.93 8.00 8.95 9.80 10.59 11.32 1200 12.65 :K:1
45 4.81 6.80 8.33 9.61 10.76 11.77 12.72 13.60 14.42 16.20
2:1 50 5.64 7.97 9.76 11.27 12^ 13.81 14.91 16M 16.91 17.82 2:1
5fi 6.4fi 9.16 11.22 IXM 14.48 15.87 17.14 ISM 19.43 20.48
X:l 57 6.82 9.64 11.80 13.63 15.24 16.69 18.03 19.28 20.45 2L55 X:l
60 7.32 10.35 12.68 14.64 16.37 1733 19.37 2a71 21.96 23.16
)k:l 66.7 8.44 11.93 14.61 16.88 18.87 20.67 22.32 23.87 26J1 26.68 )k:l
70 8.98 12.70 15.55 17.96 20.08 21.99 23.76 26.3S 26.93
aoja 75 9.78 13.83 1&94 19.56 21J7 23.95 25.87 27J6 29J4 aoja
K:l 80 10.55 14.93 18.28 21.11 23.60 25.85 27.93 29J5 3L66 33.38 K:l
85 11.30 15.98 19.58 22.61 25.27 27.69 29.90 31.97 33.91 36.74
90 12.02 17.00 20.82 24.04 26.88 29.44 31J0 34.00 afi Off 38.01
95 12.71 17.97 22.01 25.41 28.41 31.12 33.62 36.94 38.12 40.18
l.l 100 13.36 18.89 23.14 26.72 29.87 32.72 35.34 87.78 4aOB 42.24
itoiliwd bom
1.41 X »'
10.000
( 65.41 4.56 X i + 0.066 LS >• topopiphif factor
i « atope Inith. ft (m X 0.3048)
I a aHpf ateapoma.
m « tqmntpt dapwiiiant apon ilop* ataapnaa'i
(02 for alopm < 1«, te alopat 1 to 8%.
0.4 for alapM 3.6 to 4.6X, and
O.SfaralaiMa>6X)
LS vaiuas Car fidlBwiog stope bogth. <, ft (m)
1 150 200 260 300 350 400 460 500 600 700 800 900 1000
1
1 (46) (61) (76) (91) (107) (122) (137) (162) (183) (213) (244) (274) (806)
i
;) aio oai au ai2 012 013 0.13 013 014 014 014 0.15 0.15
0il4 ai4 ai6 016 OU 016 017 017 018 018 019 019 020
; 0.23 0.26 026 028 02» O80 032 0.33 0.34 0.36 0.37 0.30 O40
* •
.0.32 035 038 O40 042 04S 0.45 046 0.4B 051 0.54 0.55 057
>
'1
0.47 0.53 068 062 066 O70 073 0.76 0.82 087 0.92 0.96 1.00
i
I 0.66 a76 085 09S LOO L07 LIS 1.2Q 1.31 L42 LSI 1.60 1.69
!•
( 0.82 0i96 1J06 1.16 L26 1.84 L43 L50 L66 1.78 LOO 2.02 2.13
LOl U7 LSO L4S L54 L65 1.75 1.84 zm 2.18 2.33 2.47 2.61
L21 L40 L57 L72 L85 IM 2.10 2.22 2.48 2.62 2.80 2.97 3.13
i'
1. L44 L66 L85 iM 2.19 2J5 2.49 2.62 2.87 3.10 3.32 3.52 3.71
v-IM LM 216 2.37 2.56 Z74 2.90 3.06 3.35 3.62 3.87 4.11 4.33
IM 2.23 2.60 2.74 2J16 3.16 3.35 3.53 3J7 4.18 4.47 4.74 4.99
i 235 2.72 iM ZM ZM 3.84 4.08 4.30 4.71 5.08 5.43 5.76 6.08
•If 3.13 3.62 *M iM 4.79 6.12 6.43 6.72 6.27 077 7.24 7.68 8.09
! 3.72 4.80 481 6X1 6.69 OOS &45 6J0 7.45 8.04 060 9.12 9.62
6U)0 6.77 6.46 7.06 7.63 8.16 8.66 9.12
6.84 &75 IM ZM ZM ZM 1012 10.67
7.21 8.83 031 lOaO 1L02 1L78 12.49 13.17
9.74 1L25 12.57 18.77 14.88 15.91 16.87 17.78
11.55 MM 14JU 16JS 17.64 18J6 2O00 2L00
9M 1079 11.64 12.24 12.90
1L68 12.62 13.49 14.31 15.08
14.43 15.58 16.66 17.67 18.63
19.48 21.04 22.48 23.86 85.15
28.10 24J6 26.67 28.29 29.82
12.62 14.46 1606 17.70 18.12 2044 21.68 22J6
15.60 17.89 2O01 2L91 23.67 25J0 26.84 28.29
18JB8 81.60 84^18 MM MM 8040 aSJM MM
2L83 2SL21 2018 3087 83.84 3065 S7J1 89.85
MM 38.97 8849 86.48 8088 40.97 48.46 46.80
J&M 27J>4 2BS1 3067 32.32
3099 83.48 35.79 87J)6 .40.01
87.28 40.32 42.99 45.60 48.07
43.66 47^6 5041 53.47 56.36
5018 64.20 67M 61.45 64.78
26.40 8048 8408 87J8 4082 43J0 45.72 4019
32.74 8060 4O10 43J1 4090 4011 6L77
32.68 87.74 4209 4022 4082 53.87 5060 6066
34.77 4015 4180 4017 53.11 5078 60.23 6048
37.87 43.73 4&80 68^6 57.85 6L85 65.60 6015
62.79 57.02 6096 64.66 6&15
6071 61.25 65.48 69.45 73Jil
6036 7060 75.47 8005 84.38
69.54 7012 8O80 85.17 89.78
75.75 8L82 87.46 92.77 97.79
4088 47J0 52.77 57.81 62.44 6075 7O80 74.63 81.76 8&31 94.41 10013 105.55
43.78 6056 66.51 6L91 6087 7L48 75.82 79.92 87.55 94.57 101.09 107.23 118.03
46.66 53.76 6O10 65.84 7LU 7O02 806S 84.99 9011 100.57 107.51 114.03 12020
49.81 66.88 68.68 68.69 7&17 8086 8&88 89.84 9042 10030 118.64 120.54 IZIM
5L74 6074 6079 78.17 7O03 84.48 8061 84.46 103.48 11L77 119.48 12&73 133.59
cm
Sampl9 Soil Lorn Calcutation; SttpityStep Procedure
1. Determine the R factor.
2. Boiwl on aoil sample particle size anolysio, determine th. Jf value from the
nomagraph (Fig. 5.6). Rep.at if you have more than on. loU aompl..
3. Divid. the site hito sections of unifonn slope gradient and length. Assign an
LS valu. to rach section (Table 6.5).
4. Choose the C valua(a) to represent a aeaaonal average of th. eifect of mulch
and vegetation (Table 5.6).
5. Sst the P factor boaad on th. final grading practic applied to th. slooea
(Table 5.7),
6. Multiply ths flvs factors togsthcr to obtain per acr. aoil loia.
7. Multiply soil lose per acr. by tha aerssgs to find th. total volum.. of 8.dim.nL
If tha soil loM pr.diction shows sxceaaive vohun. loat from ths sits, conaider'
(a) working only a portion of the ait. at ono tim., (b) altering th. alop. length
and gradient, or (c) incraaaing mulch application rat. or s.«ling.
APPENDIX
RANCHO CARLSBAD CHANNEL & BASIN PROJECT
(Job Number 13182)
June 30, 1998
Prepared for:
City of Carlsbad
2075 Las Palmas Drive
Carlsbad, Califomia 92009-1576
Dennis CTIgb^fHhg, M.S.
R.C.E. #32838
Exp. 6/02
Prepared By:
Rick Engineering Company
Water Resources Division
5620 Friars Road
;an Diego. Califomia 92110-2596
':-:19) 291 0707
^^^^H Introduction
This report has been prepared to summarize the hydrologic and hydraulic studies conducted
by Rick Engineering Company for tiie City of Carlsbad as part of the Rancho Carlsbad Channel and
Basin Project Rancho Carlsbad Mobile Home Park (RCMHP) is located north of El Camino Real
midway between College Boulevard and Tamarack Avenue. See the Vicinity Map on the next page.
RCMHP contains portions of both Agua Hedionda and Calaveras Creeks. Agua Hedionda Creek
flows westerly through die southem portion of RCMHP. Calaveras Creek flows soulliwesterly along
the northem property boundary. Calaveras Creek confluences with Agua Hedionda Creek within
RCMHP approximately 300 feet upstream of El Camino Real. The Federal Emergency Management
Agency (FEMA) Flood Insurance Rate Map (FIRM) shows that a large portion of RCMHP is
inundated by the lOO-year storm. See the FIRM in Map Pocket 1. The purpose ofthis study is to
provide recommendations for minimizmg the lOO-year flooding in RCMHP. These
recoinmendations include upstream detention basins to decrease the peak flow and on-site creek
improvements to increase the creek capacities.
Hydrologic Methodology
Hydrologic analyses were prepared to determine the 100-year peak discharge within RCMHP
and to analyze proposed detention scenarios. Two hydrologic analyses using the U. S. Army Corps
of Engineers' HEC-1 flood hydrograph program are included in this report. The first analysis
modeled the existing detention facilities and ultimate development. Ultimate development was
assumed in order to account for the maximum anticipated discharge in the watershed. The results
of the first analysis confirmed that the creeks in RCMHP are inadequate to convey the lOO-year
rTT- " " ~~~~ DCB.MDL:emn/Repoit/M3182.001 Prepared By: _ i mm\m Rick Engineering Company - Water Resources Division i u//ui/vo
storm Therefore, additional analyses were performed in order to study detention scenarios. The
HEC-1 analysis containing the most desirable detention scenano is mcluded m this report and is
based on the existing and four proposed detention facilities and ultimate development within the
entire watershed. The HEC-1 input and methodology are discussed below. The HEC-1 results are
discussed in the following section.
Prior to preparing the HEC-1 input, previous studies (listed in "References") for RCMHP
were reviewed and site visits were performed. The site visit objectives were to verify the watershed
bovmdary and major flow paths of both Agua Hedionda and Calaveras Creeks, detemiine existing
detention locations, and review proposed detention locations. Prior to the site,visits, the watershed
boundary and flow paths were delineated on the United States Geological Survey's (USGS)
quadrangle maps. The watershed was divided into sub-basins in order to obtain peak flows at
f-^^ existing and proposed detention facility locations and at locations listed in the current Flood
Insurance Study. The watershed boundary, flow paths, and sub-basin boundaries were verified
during the site visits and adjusted appropriately. See Map Pocket 2 for the RCMHP watershed
boimdary map.
During the site visits, existing detention facilities such as dams and road embankments were
noted. Two dams exist within the RCMHP watershed: Calaveras and Squires. Of these two, only
Calaveras dam provides significant detention. It is located within Calaveras Creek and detains the
upstream creek flows. On the other hand, Squires Dam is located at the upper end of a drainage
basin and provides minimal detention. The plans for Calaveras Dam were obtained firom the
Division of Safety of Dams (DSOD) and the outlet works and storage capacity were modeled in the
hydrologic analyses.
v; rs ~" "—' ~" DCB:MDL:emiL'RL-port/M31S2.001 PreparedBy: *^ n7/ni/g< Rick Engineering Company - Water Resources Division -> u//ui/:/a
Furthemiore, the following road embankments were identified as potential existing detention
facilities: Business Park Drive (south of Park Center Drive), Sycamore Avenue (north of Grand
Avenue), Shadowridge Drive (north of Antiqua Drive), Mekose Drive (north of Cannon Road), and
Mekose Drive (south of Aspen Way). As-built plans for these road crossings were obtained firom
the appropriate agencies. The culverts and storage capacities of the Sycamore Avenue, Shadowridge
Drive, and Mekose Drive (Cannon Road) facilities were modeled in the hyckologic analyses. The
Business Park Drive and Melrose Drive (Aspen Way) crossings were not modeled because the
culverts at these locations are large enough to convey most ofthe upstream flows with minimal
detention.
Two main criteria were considered in selecting potential proposed detention basin sites.
First, the facilities listed in the Master Drainage Plan were considered. Second, existing or proposed
road crossings were considered. Detention basin construction at road crossings provides several
benefits. Road crossings create a natural location for detention. They are cost-effective because the
road embankment is used for detention. They do not create a significant increase in environmental
impacts.
The above-mentioned sub-basins and detention facilities were modeled in the HEC-1
program. The program parameters include sub-basin area, rainfall distribution, lag time, and curve
number. These parameters were determined as follows: The sub-basin area was obtained firom the
USGS watershed boundary map. The rainfall distribution was based on storm duration and
frequency, as well as the sub-basin's geographic location. The lag time was based on sub-basin
characteristics such as topography, basin shape, vegetative cover, existing development, and stomi
duration. Both rainfall distribution and lag time were generated by utilizing the criteria outlined in
PreparedBy: ~ " DCB:MDL:ema'Report/J-131 S2.001
Rick Engineering Company - Water Resources Division 4 07;01,98
the County of San Diego Hydrology Manual. Curve numbers are a fimction of land use and soil
type. The land use coverages were obtained firom the City of Carlsbad's Geographic Information
I System (GIS). The land use was revised slightly in three locations according to a December 12,1997
exhibit from the City of Carlsbad. In open space areas, land use was based on vegetative cover
estimates obtained from the Soil Conservation Service's (SCS) San Diego County Soil Interpretation
Study Ground Cover maps, as well as field observations. The soil type coverages are delineated on
the SCS's Soil Survey maps. These coverages were obtained from the San Diego Association of
Govemments (SANDAG) in digital format. Once the land use and soil types were established, the
curve numbers were then calculated using the method outlinal in tfie San Diego County Hydrology
Manual.
The curve number, lag time, rainfall distribution, arid area for each sub-basin were generated
and input into the HEC-1 program. The HEC-1 program then computed the runoff hydrograph and
peak discharge for each sub-basm. The existing detention facilities were modeled in tiie first HEC-1
analysis, while both existing and proposed detention facilities were modeled in tiie second HEC-1
analysis.
i
I il
Hydrologic Results
j t Xhe results ofthe two aforementioned HEC-1 analyses for RCMHP are discussed below.
For the first HEC-1 analysis, which modeled the existing detention facilities and ultimate
development, botii six- and 24-hour, lOO-year storms were simulated. The 24-hour storm resulted
li In higher peak flow discharges at RCMHP for both creeks, tiius it was used in all subsequent
analyses.
I
I
_—-—rsr:— -— DCB:MDL:emn/Report/J-13182.001 Prepareauy. • • S n7;fii;08 Rick Engineering Company-Water Resources Division J u//ui/ya
(;C~ Appendix 1 contains the lOO-yeatr, 24-hour HEC-1 analysis for the RCMHP watershed witii tiie
existing detention facilities and ultimate development.
The second HEC-1 analysis modeled botii existmg and proposed detention facilities and
ultimate development. Several proposed detention scenarios were investigated and it was
determined that the most feasible scenario was the combination of four detention basins, all located
at proposed road crossings. Two of the proposed detention facilities are listed m die 1994 Master
Drainage Plan as Detention Basins BJB and BJ. these facilities are located immediately upstiream
of RCMHP Ul Calaveras Creek. Both ofthe distention basuis were designed as flow-by facilities.
A flow-by facility detams the higher creek flows, while allowing lower flows to pass through the
basin relatively undetained. The other two detention basins are fiirther upstream in Agua Hedionda
•
Creek at the proposed road extensions of N^elroise Drive (south of Aspen Way) and Faraday Avenue.
Both of the Agua Hedionda detention basins are flow-through types where all of the creek flow is
detained. All proposed detention facilities were designed to be outside DSOD's jurisdictional limits,
i.e., less than 50 acre-feet of storage volume and less than 25 feet high. Appendix 2 contains the
HEC-1 analysis ofthe lOO-year, 24-hour storm for the RCMHP watershed with both existmg and
proposed detention facilities and ultimate development.
Table 1 summarizes the results of both HEC-1 analyses. The table shows that with the
proposed detention basins, die peak discharge at RCMHP decreased by approximately 10 to 15
percent. Preliminary design of die proposed detention facilities are discussed below.
Prepared By; ~~ r OCB:MDL:emn,Report/M3182.00l
Rick Engineering Company - Water Resources Division O 07/01/98
Table 1
Comparison of 100-year, 24-hour Peak Flow Discharges with Existmg Detention FaciUties
and with Both Existhig and Proposed Detention Facilities
Ultimate Development
Rancho Carkbad Mobile Home Park
Creek , Fe9l(IHs«h«ni5«wi(li
CalaverasCreek 1,910 1,550
Agiia Hedionda (upstream of
confluence with CalaverasCreek)
8,050 7,600
Agua Hedionda (downstream of
confluence witii CalaverasCreek)
9,950 8,970
* cfs = cubic feet per second
Prepared By:
Rick Engineering Company - Water Resources Division
DCB:MDL:emn/Report/M 3182.001
07/01/98
pjeliminary designs were performed for each proposed detention facility to determme tiie
^ outiet works requked to achieve maximum detention, while maintaining tiie height and storage
volume below DSOD jurisdictional lunits. The prelkmnary design of each detention facility and tiie
results for each detention facility design are described below.
The most upstream proposed detention facility in Agua Hedionda Creek is at Mekose Drive.
This facility will be a flow-tiirough detention basin. Mekose Drive mns nortii-soutii and currentiy
ends just soutii of Aspen Way near tiie Carlsbad Corporate boundary. Futiure plans call for tiie
extension of Melrose Drive to Palomar Auport Road. An existing reinforced concrete box (RCB)
culvert conveys flow under Mekose Drive and is 10 feet wide by 7 feet high. The existmg Mekose
Drive embankment provides minunal detention because oftiie RGB's large capacity. Hydrologic
calculations show tiiat a 36-inch diameter openmg at tiiis location will detam tiie peak flow discharge
from approxunately 450 cubic feet per second (cfs) to 180 cfs. There are two altematives for
creating die 36-inch openmg. One is to replace die existing culvert witii a 36-inch RCP and tiie otiier
is to constmct a concrete bairier at tiie mlet witii a 36-inch diameter opening. The resultant storage
volume and ponded water surface elevation (WSEL) witii tiie new outiet works will be
approxunately 41 acre-feet and 329 feet, respectively. This will create an inundation area of
approximately seven acres. The estimated outiet velocities for tiie first and second altemative will
be 25 and 13 feet per second (fps), respectively. The velocity under the first altemative is greater
tfian die maximum desired velocity of 20 fps. The velocity calculation assumed that the proposed
36-inch RCP was constructed at tiie slope of the existing culvert, which is one percent. If this
altemative is selected, the final culvert design should analyze methods for reducing the outiet
velocity, such as placing the culvert at a flatter slope or using multiple small diameter culverts. A
DCB:MDL:emn/Report'M3182.001
PreparedBy: . . o 07/01/98
Rick Engineering Company - Water Resources Division o
c
^^^^conceptiial plan for tiie second altemative is mcluded m Map Pocket 3.
The otiier detention facility proposed for Agua Hedionda Creek is tiie Faraday Avenue flow-
tiirough detention basin. Cunrentiy, Faraday Avenue runs east-west and ends at Orion Stireet. The
extension of Faraday Avenue to Park Center Drive in tiie city of Vista is plarmed as part of Carlsbad
Oaks Nortii Busmess Park. The hydrologic calculations and prelkmnary design in tiiis report were
based on tiie proposed embankment and topographic mformation shown on tiie Tentative Map for
Carlsbad Oaks Nortii Business Park by O'Day Consultants, dated April 6,1998. The calculations
show tiiat a smgle 6-foot wide by 7-foot high RCB culvert will detam approxunately 49 acre feet of
storage volume and will pond up to an elevation of 240 feet. The mundation area will be
approxunately seven acres. The lOO-year peak discharge of 1,050 cfs entering tiie detention basin
wUl be defamed down to approxunately 780 cfs. The approxunate calculated outiet velocity will be
19 fps. A conceptual plan for tiiis detention facility is mcluded ui Map Pocket 4.
The two proposed detention facilities in Calaveras Creek are located just upstream of
RCMHP and were designed as flow-by basms. The first facility. Detention Basin BJB, is located
north of RCMHP at tiie proposed College Road extension and west oftiie proposed Cannon Road
extension. College Boulevard currentiy ends at El Cammo Real. North of RCMHP, tiie proposed
College Boulevard extension nms roughly east-west. College Boulevard intersects the proposed
Cannon Road extension at tiie northeast comer of RCMHP. Cannon Road currently ends east of
Interstate 5 at Paseo Del Norte. The proposed Cannon Road extension alignment will be parallel to
Calaveras Creek and unmediately north of RCMHP. The detention basm design consists of an
earthen embankment, outiet works, and a small berm. The embankment will have a 10-foot top
width and a 76-foot crest elevation with 2:1 (horizontal:vertical) side slopes. The outlet works
DCB:MDL:emn/Report/J-13182.001
PreparedBy: ... n 07/01/98 Rick Engineering Company - Water Resources Division y
^ ^ consistofasmglel0-footwideby7-foothighRCBanda48-inchRCP. The48-mchRCPjomstiie
^ RCB downstream oftiie embankment. The RCB tiien extends to Calaveras Creek. An emergency
spillway is also provided. The small benn will nm parallel to tiie creek for approxunately 1,200 feet.
The berm wiU have an approximate 74-foot crest elevation, 10-foot top widtii, 2:1
(horizontal:vertical) side slopes, and a wek section. The wek section, located near tiie embankment,
will allow flow to enter tiie basm at an approxunate WSEL of 73 feet Hydrologic calculations show
tiiat witii tiie outiet works described above, a storage volume of approxunately 49 acre feet will be
attamed. The resultant ponded WSEL will be approxunately 75 feet and tiie mundation area will be
approximately 15 acres. The peak discharge of 1,570 cfs entering the basin wUl be defamed down
to UOO cfe. The approxunate outiet velocity will be 19 fps for tiie RCB. See Map Pocket 5 for a
copy oftiie conceptiial design of Detention Basm BJB.
The otiier Calaveras Creek detention facility. Detention Basm BJ, is located northeast of
RCMHP at tiie proposed College Boulevard extension and east of tiie proposed Cannon Road
extension. The earthen embankment Avill have a crest elevation of approximately 81 feet a top widtii
of 10 feet and 2:1 side slopes. An emergency spillway will be provided. Approxunately 600 feet of
channel improvements upstream of tiie proposed embankment are necessary. The channel
improvements include gradmg the creek as follows: Trapezoidal-shaped grass-lined channel witii
a 3-foot bottom widtii, 4-foot deptii, and 2:1 side slopes. The hydrologic calculations showed that
a 6-foot wide by 3-foot high RCB would detain tiie peak flow of 670 cfs down to approxunately 350
cfs. The inundation area is approximately eight acres and tiie ponded WSEL is approximately 76
feet. The detention basin stores approximately 48 acre feet of water. The calculated outiet velocity
will be approximately 19 fps. See Map Pocket 6 for the conceptual plans for Detention Basin BJ.
DCB:MDL:emn/Report/M3182.001
PreparedBy: ..... IQ 07/01/98
Rick Engineering Company - Water Resources Division
c
As discussed above, witii tiie addition of tiie proposed detention facilities, the peak disciiarge
at RCMHP is decreased by approxunately 10 to 15 percent. All four of tiie proposed detention
facilities were designed to fall below DSOD's jurisdictional lunits. Also, all tiie facilities are located
at existmg or proposed road crossings and at least one foot of freeboard is mamtamed at tiie road
embankments. The results are summarized m Table 2, which contakis results such as outlet works,
velocity, peak flow discharge mto and out oftiie basm (Q^ and QJ, storage volume, ponded WSEL,
and surface area.
Prepared By: ... Rick Engineering Company - Water Resources Division 11
DCB:.MDL:cmn/Report/M3182.1)01
07/01/98
Table 2
Summary of Proposed Detention FaciUties
Rancho Carlsbad Cljannel and Basin Project
lOO-year, 24-hour Storm Event
Prepared By:
Rick Engineering Company - Water Resources Division 12
DCB:MDL:eimi/Repoit/M3182.001
07/01/98
Hydraulics
Hydraulic analyses were performed to detennme tiie amount of silt removal and re-gradmg
required to mmimize tiie lOO-year floodmg at RCMHP. In order to effectively analyze flood levels
in botii Agua Hedionda and Calaveras Creeks, tiie U.S. Army Corps of Engmeers HEC-2 Water
Surface Profiles program was used. The program is intended for calculating WSELs for steady
gradually varied flow mnatiiral or man-made chamiels. The effects of various obstructions such as
bridges and culverts may be considered in tiie computations. The program also has capabilities
available for assessing tiie effects of channel improvements.
The mput parameters were based on channel and overbank roughnesses, lOO-year discharge,
downstream WSEL, and topography. The channel and overbank roughnesses were determmed by
field observations. The lOO-year discharge was obtauied from tiie HEC-1 analysis in Appendix 2
modeling botii existing and proposed detention facilities. The downstream WSEL was estimated
in tiie HEC-2 analysis by usmg tiie slope-area metiiod. FEMA-approved HEC-2 cross-sections for
the area downstream of tiie site were included in tiie analysis. The lOO-year discharge for the
downstream area was obtained using tiie split-flow analysis from tiie Flood Insurance Study.
The existing topography was based on June. 1995 topographic maps by Manitou
Engineering. The topography was used to prepare cross-sections of botii creeks, as well as tiie
overbank areas. Since prior sUidies showed that tiie creeks were under-capacity, the original grading
plans for RCMHP were obtained and modeled in the HEC-2 analysis by using the channel
improvement option. The original grading plans were prepared October 15,1969 and approved by
the City on March 24,1971. The original design consisted of a trapezoidal chamiel vvith an overall
length of approximately 1.2 miles and included both Agua Hedionda and Calaveras Creeks within
Prepared By: _. . . Rick Engineering Company - Water Resources Division
RCMHP. The side slopes were 2:1 (horizontal:vertical) and tiie approximate bed slopes were 0.15
^ and 0.30 percent in Agua Hedionda Creek and Calaveras Creek, respectively. The bottom widtii of
Agua Hedionda Creek varied from 58 feet at tiie El Camino Real bridge to 44 feet upstiream of tiie
confluence. The approxunate channel deptii was 11.5 feet The bottom widtii and channel deptii of
Calaveras Creek were four feet and rnne feet respectively.
A HEC-2 analysis was performed based on tiie origmal design. The HEC-2 results showed
tiiat a large portion of RCMHP remamed mundated by tiie 100-year flood. In order to mcrease
channel capacity, additional channel unprovements were modeled m tiie HEC-2 analysis for tiie
downstream sections of botii creeks. At tiie El Cammo Real bridge, tiie bottom widtii was widened
to 87 feet Witiun tiie next 1.400 feet upstiream oftiie bridge, tiie bottom widtii tiien tapered down
to tiie origmal design bottom widtii of 44 feet m Agua Hedionda Creek and four feet m Calaveras
Creek.
The results oftiie hydraulic stiidy are contamed m Appendbc 3. The results are also depicted
on tiie RCMHP lOO-year Floodplam Map m Map Pocket 7. The map shows tiiat witii tiie proposed
detention facilities and channel unprovements discussed above, a majority of RCMHP will be
outside of die 100-year floodplain.
Maintenance Plan
This Maintenance Plan contains maintenance requirements for Aqua Hedionda and Calaveras
Creek witiiin RCMHP. This plan also contains requkements for tiie four upstieam detention basms.
It is vital that the creeks and detention basins be maintauied on a regular basis to ensure an
eptable level of flood protection for RCMHP. It is recommended tiiat the maintenance described acc'
. ~ DCB:MDL:emn/Report/J-i JI o^.OUl
PreparedBy: ^. . . 14 07/01/98 Rick Engineering Company-Water Resources Division it
below be perfonned annually prior to tiie rainy season and after any storm event exceedmg tiie 10-
^ yeai peak discharge.
Aqua Hedionda and Calaveras Creek must be mamtalned to prevent adverse siltation m each
creek. Siltation will reduce tiie flow capacity oftiie creeks and mcrease tiie likelihood of mundation
witiim tiie mobile home park. The first step is to devise a system for monitoring tiie silt level m each
creek This can be done usmg metal posts witii markkigs placed sbc mches apart. The posts should
be placed vertically m each creek at intervals not exceeding 500 feet The posts should extend at
least two feet above tiie creek bed and must be embedded deep enough so tiiat tiiey wiU not be
moved by large creek flows. A geotechnical engineer should be consulted for tiie requked
embedment deptii. Once tiie posts are mstalled, tiie silt level can be easily monitored by
mamtenance personnel. As tiie silt level reaches one foot tiie siU should be removed by
maintenance crews to the design elevations.
The topographic maps have been reviewed to detemikie tiie siltation tiiat has occurred in botii
creeks over tiie past few years. The design oftiie creeks witiiin tiie mobile home park is shown on
tiie grading plan for RCMHP approved March 24.1971. The creek bed elevations on tiie grading
plan served as the base elevations m determming tiie amount of siltation in each creek. A
comparison oftiie grading plan witii a June 1995 topographic map mdicates that tiie silt in Aqua
Hedionda and Calaveras Creek raised the creek beds as much as seven and five feet, respectively.
Therefore, siltation has occurred in Agua Hedionda and Calaveras Creek at a rate of up to 0.3 and
0.2 feet per year. Using these rates and an acceptable silt level of one foot indicates tiiat portions of
the creeks could require maintenance approximately once every three to five years. It is important
to point out that this is a rough approximation because the creek sikation will depend on the
DCB:MDL:cmn,Report/J-U 182.001
PreparedBy: ^. . . 15 07/01/98
Rick Engineering Company - Water Resources Division
" ... .
frequency and magnitude of firture storm events. It is likely tiiat futiire stonn events will not mknic
past events. Additionally, it is possible tiiat maintenance has been perfonned on tiie creek between
1971 and 1995, which would affect tiie calculated sUtation rates.
Mamtenance is also requked at each oftiie four detention basms. Mamtenance wUl mvolve
keeping tiie entrance to each oftiie detention basm outiet facilities free from silt Silt should be
removed from an entrance once tiie silt level reaches sbc mches above tiie entirance's flowline
elevation. The amount of deposition should be easy to detennme smce each outlet facility is a
known size. The silt should be removed a distance of 10 feet upstream oftiie faciUties entirance.
This WiU have mmunal enviromnental knpacti, and wiU restore tiie capacity oftiie outiet facility.
The maintenance steps described above are essential for protection of RCMHP. The
nmntenance must be perfonned routinely by quaUfied persomiel and a sufficient budget should be
established for tiie mamtenance. If any questions arise during die maintenance, a professional
engmeer specializmg ki water resources should be contacted.
Environmental Issues
The envkonmental issues associated witii tiie Rancho Carlsbad Channel & Baski Project
have been addressed by the envkomnental consultant RECON. and are summarized below. In
regards to tiie on-site chamiel sik removal and improvements, it is likely tiiat no enviromnental
mitigation wiU be necessary. In regards to tiie four proposed detention facflities, the direct impacts,
mitigation requirements, and potential kidkect enviromnental impacts are listed by habitat type m
Tables 3,4, and 5, respectively. Direct unpacts are from embankment constiuction. As mentioned
above all ofthe embankments are within footprints of fiitiire roadways. Mitigation requirements
PreparedBy: _. . . Rick Engineering Company - Water Resources Division
Appendix 1
I
100-year, 24-hour HEC-1 Analyst^ for Rancho Carlsbad Mobile Home Park
Ultimate Development with Existing Detention Basins
(File Name: rcmh24r.hcl)
Prepared I5> •
Rick Fnjinccrir.u '.".)in ' iiv, • W uor I'l: ii.ion
"!)CM:.MUI.:;mr. l<.;p'Vt J-13!X2.')r.|
RUNOFF SUWMARY
FLOW IN CUBIC PEET PER SECOtm
TIME IN HOURS, AREA IM SQUARE MILES
OPERATION STATION
PEAK
FLOW
TIME OF
PEAK
-^A'EPAGE FLOW FOP. M-^JCIIIUM PERIOD
6-HOtre 24-HOUR 72-HOUR
HYDROGRAPH AT BSNBCl 2744. 10.58
ROUTED TO RTBC2
ROUTED TO
HYDROGRAPH AT
2 COMBINED AT
ROUTED TO
HYOROGRAPH AT
2 COMBINED AT
HYDROGRAPH AT
ROtJTED TO
2 COMBINED AT
ROUTED TO
HYDROGRAPH AT
ROUTED TO
ROUTED TO
HYDROGRAPH AT
3 COMBINED AT
ROUTED TO
;i\TjROGRAPH AT
RTBCS
BSNBC3
BC2&BC3
RTBC4
BSNBC4
BC3&BC4
AHl
DETSYC
BC&AHl
RTAH2
AH3
DETSHADO
RTAH2
AH2
AHl-3 SBC
AH2-AH7
2743. 10.58
HYDROGRAPH AT BSNBC2 357. 10.00
2 COMBINED AT BC16BC2 3043. 10.50
3028. 10.58
749. 10.00
3683. 10.50
3649. 10.SS
184. 10.00
3798. 10.50
1802. 10.17
1786. 10.25
552S. 10.50
523S. 10.75
51S. 10.00
460. 10.17
457. 10.50
787. 10.00
6311. 10.58
6198. 10.67
::G. 10.CO
1453.
1453.
168.
1619.
1619.
353.
1969.
2052.
881.
2931.
2892 .
243.
243.
3489.
IDS.
598.
597.
69.
666.
664.
145.
809.
840.
363.
362.
1202.
1185 .
100 .
100 .
576.
575.
66.
642.
640.
140.
779.
776.
33.
309.
349.
349.
1158.
1141.
96.
36.
1381.
E.'VSIN
AREA
4.34
:iAXi:-nj;-s
STAGE
4.34 , 404.02
.55
4.89
4.89
1.18
6.07
6.38
2.83
2.83
9.21
9.21
.83
11.45
. 70
385.09
S.07 361.74
.31
351.95
.83 321.26
Tinte OF
MAX STAGE
10.58
10.58
10.58
10.25
10.50
;.OUTSD TC AH-)-AH5 •116. 10.OO 77 . 360.27 1.0.00
2 COMBINED AT COMBINB 1290. 10.08 664. 274. 264. 2.35
ROtTTED TO AH6-7
HYDROGRAPH AT AHB
ROUTBD TO AH8-7
HYDROGRAPH AT AH7
ROl]TED TO AH7-AH9
AH9 HYDROGRAPH AT
2 COMBINED AT COMBINB
ROtJTED TO AH9-10
HYDROGKAPH AT AHIO
2 COMBINED AT COMBINB
ROUTED TO AHIO-RCA
HYDROGRAPH AT RCA
3 COMBINED AT COMBINB
HYDROGRAPH AT Cl
ROUTED TO DBTNMBI.R
ROUTED TO
HYDROGRAPH AT
C1-C2
ca
ROtJTED TO DETCALA
ROUTED TO C2-C3
HYDROGRAPH AT C3
HYDROGRAPH AT C4
ROUTED TO
HYDROGRAPH AT
C3i-RCC
RCC
1266. 10.25
177. 10.00
174. 10.00
512. 10.08
4 COMBINED AT COMBINB 7995. 10.58
7663. 10.83
500. 10.08
7987.
7874.
338.
8025.
8025.
10.75
10.93
10.00
10.93
11.00
54. 10.90
8049. 11.00
531. 10.00
528. 10.00
373. 10.67
1545. 10.25
2 COMBINED AT COMBINE 1890. 10.25
1401. 11.00
1373. 11.17
448. 10.00
2 COMBINED AT COMBINE 1560. 11.08
667. 10.08
2 COMBINED AT COMBINE 1896. 10.67
1876. 11.08
73. 10.00
2 COMBINED AT COMBINE 1906. 11.03
664.
83.
83.
240.
4455.
4443.
235.
4671.
4669.
156.
4815.
4815.
24.
4838.
249.
249.
236.
761.
992.
748.
745.
209.
876 .
315.
1153 .
1153 .
1183 .
273.
34.
34.
98.
1831.
1831.
96.
1916.
1997.
64.
2060.
2058.
10.
2068.
102.
103.
99.
311.
293.
291.
85.
377.
129.
505.
503 .
14 .
2S3.
33.
33.
94.
1764.
1754.
93.
1846.
1941.
61.
2002.
1997.
10.
2007.
98.
9S.
95.
300.
395.
282.
281.
82.
363.
124.
487.
485.
2.35
.31
.31
1.12
15.33
15.23
1.00
16.33
16.33
3.59
4.41
1.24
5.65
5.65
.15
5 .30
161.74
160.24
103.49
49.72
.66
4.6.89
16.89
.11
17.00
.87
.87
.87
3.59
3.59 218.82
335.95
241.02
100.25
46.63
10.25
10.00
10.83
11.00
10.00
10.67
11.00
11.17
11.08
2 COMBINED AT COMBINE 9948. 11.00 6018. 2585. 2S0S . 22 .80
Appendix 2
lOO-year, 24-hour HEC-1 Analysis for Rancho Carlsbad Mobile Home Park
Ultimate Development with Existing and Proposed Detention Basins
(File Name: rccbpr.hcl)
r-5 — ~ DCB:MDL:emn/Report/M3182.001 Prepared By: . . mmi/o» Rick Engineering Company - Water Resources Division u//ui/^s
HYDKOGRAPH AT AH6 549. 10.00 261. 108. 104. .91
m
3 COMBINBO AT COMBINB
ROUTED TO DETNFARA
ROtJTED TO
HYDEiOGRAPH AT
ROUTED TO
HYDROGRAPH AT
AH6-7
AH8
AH8-7
AH7
4 COHBIMBO AT COMBINB
ROUTED TO
HYIXUXSRAPH AT
AH7-JU19
AH9
ROUTED TO
HYDROGRAPH AT AHIO
3 COMBINED AT COMBINB
ROUTED TO
HYDROGRAPH AT
AHIO-RCA
RCA
HYDROORJIPH AT
ROUTED TO
ROtTTBD TO
HYDROGRAPH AT
Cl
DETNMEUl
C1-C2
C3
2 COMBINED AT COMBINB
ROUTBD TO
ROtTTBD TO
HYDROGRAPH AT
DETCALA
C3-C3
C3
2 COMBINED AT COMBINE
ROUTED TO
HYDROGRAPH AT
ROUTED TO
DETNBJB
C4
DETNC4
1053. 10.08
777. 10.83
775. 11.00
177. 10.00
174. 10.00
513. 10.08
7531. 10.67
7236. 10.93
500. 10.08
2 COHBIMBO AT OXIBINB 7533. 10.83
AH9-10 7443. 11.00
338. 10.00
7594. 11.00
7581. 11.08
54. 10.00
3 COMBINED AT AOtJA 7603. 11.00
531. 10.00
528. 10.00
373. 10.67
1545. 10.35
1890. 10.35
1401. 11.00
1373. 11.17
448. 10.00
1560. 11.08
1196. 11.92
667. 10.08
352. 11.00
609.
606.
606.
83.
83.
340.
4404.
4393.
235.
4618.
4615.
156.
4759.
4759.
24.
4783.
349.
249.
236.
761.
992.
748.
745.
209.
876.
876.
31S.
297.
274.
273.
273.
34.
34.
98.
1831.
1820.
96.
1916.
1996.
64.
2060.
20SS.
10.
2068.
102.
102.
99.
311.
411.
393.
391.
85.
377.
377.
129.
129.
263.
263.
33.
33.
94.
1764.
1753.
92.
1845.
1940.
61.
2002.
1997.
10.
2O07.
98.
98.
95.
300.
395.
282.
281.
83.
363.
363.
124.
124.
2.35
263- a.35 240.33 X0.83
11.00 3.35 161.06
.31
•31 160.24
1.13
15.23
15.23
1.00
16.23
'16.23
.66
16.89
16.89
.11
17.00
.87
.87
.87
2.72
3.59
3.59
4.41
4.41
1.24
1.24
103.30
49.52
335.95
341.03
218.83
3.59 100.35
.83
74.77
76. 19
10.00
10.92
11.08
10.00
10.67
11.00
11.17
11.92
11.00
2 COMBINED AT COMBINE 1532. 11.83 1163. 505. 487. 5.65
RICK
ENGINEERING
i. COMPANY .San DieKU
Riverside Orange • Phoenix • Tucson
H tilcr Itc.soiirct's Division
Febraary 11,2004
Mr. Glen Van Peski
GVP Consultants
3764 Cavern Place
Carlsbad, Califomia 92008-6S8S
SUBJECT: CHANGES TO OUTLET STRUCTURES AT PROPOSED
MELROSE AND FARADAY DETENTION BASINS
(RICK ENGINEERING COMPANY JOB NUMBER 13182-D)
Dear Mr. Van Peski:
Rick Engineering Company has completed revisions to the hydrologic analysis for the watershed
tributary to Agua Hedionda Creek witiiin the Rancho Carlsbad Mobile Home Paric in the City of
Carlsbad, Califonua These revisions resulted in changes to the geometry ofthe outlet stmctuies
at the proposed Melrose and Faraday detention basins. This letter specifies the revised geometry
of each outlet stmcture.
Modifications to die HEC-1 hydrologic model included die following:
• Basin factors were reevaluated and changed appropriately based on the impact of new
environmental regulations and thek restrictions on the ultimate development of the
watershed. Lag times were recalculated based on the modified basin factors.
• Manning's roughness coefGcients in die stream routing were reevaluated and
modified in the HEC-1 where appropriate based on the impact of new environmental
regulations and their restrictions on the ultimate development in the watershed.
• The storage routing rating curve for the proposed Melrose detention basin was revised
based on the grading plans tided "Carlsbad Raceway" Project No. C.T, 98-10,
Drawing No. 409-1 A, Sheet 4 of 14, dated September 2002.
• The storage routing rating curve for the proposed Faraday detention basin was revised
based on the grading plans titled "Carlsbad Oaks North El Fuerte Street" Project No.
C.T. 97-13, Drawing No. XXX-XA, Sheet 3 of 7, dated April 2003, and grading plans
titled "Carlsbad Oaks North Faraday Avenue" Project No. C.T, 97-13, Drawing No.
XXX-XA, Sheets 9 and 10 of 19, dated March 2003.
Mr. Glen Van Peski
Febraary 11,2004
Page 2
The geometry of the Melrose outlet strachire was specified on die above-mentioned plans as a
36" reinforced concrete pipe (RCP) placed within the existing 10'x7' reinforced concrete box
(RCB). The RCP would mamtain tfie existing flowline elevation, and a concrete wall would be
constracted to block the void. The modified geometry consists of an orifice plate with a
rectangular opening of 5.6' wide by 4' tall in place of the 36" RCP. The existing flowline
elevation of 308 ft is maintained. This opening allows approximately 489 cfs out of the basin.
The ponded water surface elevation witiiin the basin is 330.5 ft, which results in approximately
49.3 ac-ft of storage.
On tiie above-mentioned grading plans, the geometry of tiie Faraday outiet strachire was
designated as a 6' by 7' RCB with a flowline elevation of 221.84 ft. The modified geometry
specifies a 4.3' wide by 5.7' tall RCB in place of the 6* by 7' RCB. The existing flowline
elevation of 221.84 ft is maintained. This opening allows approximately 642 cfs out ofthe basin.
The ponded water surface elevation within the basin is 241.4 fl, which results in approximately
49.8 ac-ft of storage.
The hydraulics of the outiet stractures are so sensitive that even the sUghtest change in the
dimensions results in significant fluctuations in storage volume. Ifthe stractures are constracted
with standardized dimensions (whole or half foot increments) they will not function properly. If
the outlet is too large it under-utilizes the available storage and increases the flow rate
downstream. If it is too small the basin will stora too much and exceed the 50 ac-ft maximum
volume limit per the regulations of the Division of Safety of Dams (DSOD).
Please forward this infonnation to the appropriate consultants so the grading plans can be
modified to reflect the new outlet structure geometries.
ff you have any questions regarding this letter please contact me at (619) 291-0707.
Sincerely,
RICK ENGINEERING COl
Dennis C. Bowling. M.
R.C.E. #32838, Exp. 06/06
Principal
DCB:KH:jc.001