HomeMy WebLinkAbout3656; Interstate 5 Water Main Crossing 16 Inch; Interstate 5 Water Main Crossing 16 Inch; 1991-07-02m
FEASIBILITY STUDY
FOR
CARLSBAD MUNICIPAL
WATER DISTRICT
16 INCH WATER MAIN CROSSING
OF INTERSTATE 5 FREEWAY
PREPARED BY:
O'DAY CONSULTANTS
7220 AVENIDA ENCINAS
CARLSBAD, CA 92009
(619) 931-7700
JULY 2, 1991
91-1016
91-10X6
6-28-91
INTRODUCTION
The Carlsbad Municipal Water District's Master Plan identifies the
need for constructing a 16-inch water main across Interstate 5
freeway north of the Batiquitos Lagoon. The line would connect the
distribution system proposed for the Broccato land development
project, CT. 89-19, on the east side of the freeway with the
existing 16-inch water main in Navigator Circle on the west side of
the freeway. The line in Navigator Circle was constructed as part
of the improvements for the Batiquitos Lagoon Educational Park
Phase 1, C.T. 85-14. This feasibility study considers three
altemate alignments for the crossing on the north side of
Batiquitos Lagoon and evaluates rights-of-way, environmental
considerations and construction constraints.
LOCATION
Preliminary alignment plans A, B, and C are located north of the
Batiquitos Lagoon and south of Poinsettia Lane as shown on Exhibit
"A". Since the crossing must connect to Piovana Court on the east
side and Navigator Circle on the west side, the three altemate
alignments studied are located within a zone about three hundred
feet in length along the centerline of the freeway.
RIGHT-OF-WAY
WEST OF INTERSTATE 5; The connection to Navigator Circle would
require the construction of about 430 feet of water main in
undeveloped land known as Plaiming Area " D" now owned by Kaiza
Poinsettia Corporation who purchased this property from Sammis
Properties. An easement for the line from Navigator Circle to the
westerly R.O.W. line of Interstate 5 would have to be granted by
Kaiza Poinsettia Corporation. Exhibit "A" shows the main located
in a private road serving a proposed townhouse development.
Preparation and processing of the new master plan and tentative map
for this area is tentatively scheduled for completion within the
next two years.
INTERSTATE 5; The freeway right-of-way is approximately 600 feet
in width at this location. Because it is federally-funded, very
stringent regulations limit the crossing design and Calt:rans will
adhere to these requirements without concem for the impact on
construction costs. Briefly the major requirements are;
a. The alignment shall be a straight line from R.O.W. line
to R.O.W. line.
b. The water main shall be located within a steel casing
from R.O.W. line to R.O.W. line.
c. No stmctures shall be located within the R.O.W. lines,
including jacking and receiving pits.
d. Design and constmction of the crossing shall preclude
the need for water district personnel to enter the
freeway right-of-way to periodically perform routine
maintenance.
EAST OF INTERSTATE 5! For the connection to Piovana Court, about
250 feet of main would be constmcted in open-space lots 49 or 50.
An easement for the alignment could be requested from Odmark &
Thelan and the Davidson Companies Partnership, the developers of
Broccato, CT. 89-19, who are presently processing the development
plans and map with the City of Carlsbad. The alignment here is
controlled mainly by environmental considerations.
ENVIRONMENTAL CONSIDERATIONS
WEST OF INTERSTATE 5: There are no environmental issues identified
in Planning Area "D". Kaiza Poinsettia Corporation will be
revising the master plan prepared and approved for the Batiquitos
Ml Lagoon Educational Park, but the land use will not change and the
installation of the water main could conform to the proposed land
development plan.
m
INTERSTATE 5: The pavement and the man-made slopes within the
^ R.O.W. lines do not present any environmental constraints.
* EAST OF INTERSTATE 5; Water main location and constmction is
constrained at this location by the environmentally sensitive
wetlands of the Batiquitos Lagoon and by the approved design of the
^ Broccato project,
i« Not only is work prohibited in the wetlands, but work within a 100-
foot wide buffer zone around the wetlands is restrictive.
WW
The limits of the wetlands and the buffer zone are shown on Exhibit
"A" .
m
Ml
Plan "A" will allow the work, including the constmction and
operation of the boring and jacking pit, to be accomplished outside
the buffer zone and wetlands.
CONSTRUCTION CONSTRAINTS
WEST OF INTERSTATE 5: Installation of the water main within
Planning Area "D" can be made by the standard open trench method.
If the main is to be installed prior to the constmction of the
proposed housing project, the private road design would have to be
finalized to ensure that the main is installed at the proper
elevations. It could be several years before this road design is
completed and approved.
INTERSTATE 5; Plan "A" as shown on Exhibit "A" will satisfy all
Caltrans requirements except for the location of the receiving pit.
This is shown on the plan at the intersection of the bored and
jacked segment and the existing slope on the west side of the
south-bound lanes. Trenching would be required on the slope to the
westerly R.O.W. line. The bored and jacked portion would be
approximately 400 feet long, which is about the maximum length for
boring with reasonable accuracy expected for line and grade.
However, this plan will require review by the Longitudinal
Encroachment Review Committee in Sacramento before it can be
approved. If Plan "A" is not approved with the receiving pit
located within the R.O.W. lines, then the boring operation would
have to be extended another 200 feet to meet a 75-foot deep shaft
constmcted on the west side of the freeway. (See profile on
Exhibit "A"). Note that Plans "B" and "C", while requiring much
shorter bores, have several angle points each and the jacking pits
are located within the freeway right-of-way, the wetlands, and the
buffer zones. Thus, plans "B" and "C" are least likely to be
approved by Caltrans and the Coastal Commission.
EAST OF INTERSTATE 5! As long as the jacking and boring pit is
located outside the buffer zone, there are no other major
constraints identified and installation of the water main should be
by the standard open trench method. An access road for future
maintenance of the water line should also be located outside the
buffer zone. Spoil from the boring operation must not be discarded
in the wetlands and buffer zone and water from the boring
operation, particularly if it contains oil, must not be allowed to
flow into the lagoon.
RECOMMENDATIONS
1. If the water main alignments on both sides of the freeway
are satisfactory to the District, Plan "A" should be
detailed and submitted to Caltrans for review and
approval. A preliminary constmction cost estimate for
Plan "A" is attached as Exhibit "B".
3
2. Since it is important that soils data be obtained to
evaluate the degree of difficulty that may be experienced
in the boring and jacking operation, the soils
investigation reports prepared for the constmction of
the freeway should be researched and the soils data added
to the crossing plan. If these records are not
available, soils borings should be made to obtain the
required information. The proposed drill hole locations
are shown on Exhibit "A", An encroachment permit will
have to be obtained from Caltrans to do the soils
investigation work.
91-1016
6-24-91
ITEM QF WORK UNIT
a. NAVIGATOR CIRCLE TO 1-5 R.O.W.
16" A.CP. MAIN L.F.
1" M.A.R. EA.
2" BLOWOFF EA.
EXHIBIT "B"
PRELIMINARY CONSTRUCTION COST ESTIMATE
PLAN A
UNIT COST
$
TOTAL UNITS
40.00
800.00
800.00
430
1
1
SUBTOTAL:
b. 1-5 CROSSING R.O.W. TO R.O.W.
c. 1-5 R.O.W. TO PIOVANA COURT
16" M.L.M.C. STL.
WATER MAIN
2" B.O.
MISC. GRADING
RESTORE SLOPES
L.F.
EA.
CY.
L.S.
1 70.00
800.00
2.00
3/000.00
SUBTOTAL:
240
1
2,500
SUBTOTAL:
TOTAL COST
$17,200
800
800
$18,800
1 JACKING PIT L.S. $10,000.00 $10,000
. 1 RECEIVING PIT L.S. 5,000.00 5,000
BORE & JACK 24" L.F. 140.00 400 56,000
STL.CASING
16" M.L.M.C STL. L.F. 70.00 400 28,000
WATER MAIN
<••«
WATER MAIN IN 24"
STL. CASING
L.F. 120.00 224 26,880
Wl RESTORE SLOPE L.S. 4,000.00 4,000
$129,880
$16,800
800
5,000
3,000
$25,600
TOTAL ESTIMATED CONSTRUCTION COST: $174,280
PLUS: 10% CONTINGENCIES 17,420
CIVIL ENGINEERING & SURVEYS 13,000
LANDSCAPE ARCHITECT 2,500
SOILS BORING & REPORT 3,500
TOTAL ESTIMATED COST: $210,700