HomeMy WebLinkAbout2021-01-21; Clean Energy Alliance JPA; ; Clean Energy Alliance Operational, Administrative and Regulatory Affairs Update111•1100-
CLEAN ENERGY ALLIANCE
Staff Report
DATE: January 21, 2021
TO: Clean Energy Alliance Board of Directors
FROM: Barbara Boswell, Interim Chief Executive Officer
ITEM 6: Clean Energy Alliance Operational, Administrative and Regulatory Affairs Update
RECOMMENDATION
1)Receive and File Operational and Administrative Update Report from Interim CEO.
2)Receive Community Choice Aggregation Regulatory Affairs Report from Special Counsel.
BACKGROUND AND DISCUSSION
This report provides an update to the Clean Energy Alliance (CEA) Board regarding the status of the
operational, administrative, and regulatory affairs activities.
OPERATIONAL UPDATE
CEA is meeting its milestones for the implementation of its community choice aggregation (CCA)
program and is on track to begin serving customers in May 2021/June 2021. (Attachment A - Clean
Energy Alliance Timeline of Implementation Action Items).
CEA Launch Schedule
San Diego Gas & Electric (SDG&E) has been working over the past several years on their Customer
Information System replacement program, known as Envision. They had committed to, and were on
track, for a January 4, 2021 go live, despite the challenges of working remote in the COVID-19
environment. With a January 2021 go live, SDG&E committed to supporting the CEA launch of May
2021. On Friday July 10, CEA staff, its regulatory attorney Ty Tosdal and data manager Calpine Energy
Solutions participated in a call with San Diego Community Power and SDG&E regarding the recently
approved California Public Utilities Commission (CPUC) Decision D. 20-06-003, which requires the
Investor-Owned Utilities (IOU) to adopt rules and policy changes designed to reduce the number of
residential disconnections, provide assistance with debt forgiveness, and offer extended payment plans.
The program, known as Arrearage Management Payment program, is required to be implemented by
April 2021. This timing has presented a challenge to SDG&E to keep its go live date of January 4, 2021,
while also meeting the requirements of the decision. SDG&E submitted a letter to the CPUC requesting
an extension to September 30, 2021, for implementing the new procedures and policies required by the
decision. This request was denied by the CPUC, resulting in SDG&E postponing implementation of its
January 21, 2021
Admin & Regulatory Update
Page 2 of 6
Envision project to April 2021. The postponement of the Envision go live date impacts CEA's
implementation.
CEA and its consultants have worked diligently with SDG&E to develop a launch schedule that minimized
impact to CEA while also minimizing the risk of incorrect bills being sent to customers. SDG&E and CEA
have agreed to a two-phased schedule with accounts transitioning to CEA in May and June 2021, and
the Board authorized the Interim Chief Executive Officer to enter into a letter agreement with SDG&E
memorializing the phased approach. The May 2021 Phase 1 would include the transition of Solana
Energy Alliance customers to CEA as well as customers in Carlsbad and Del Mar who do not have
complex billing plans. Those customers who have been identified with complex billing plans would
transition in June 2021. Staff continues to work with Ca'pine and SDG&E to fine tune the customer list
for each phase.
CEA Communications and Marketing Update
Work continues on CEA's communications and marketing initiatives. The updated website went live on
December 1, 2020. Next deliverables include Brand Standards (letterhead, email signatures, etc.);
establishing social media presence; creation of communications tools (FAQs, information sheets); and
development of customer notices.
Community Advisory Committee
The first meeting of the CEA Community Advisory Committee took place on December 3. Alternate
Board Member Dwight Worden was ratified as CAC Chair, pursuant to Board identification that the
Board Alternate appointment would serve as CAC Chair, and Dr. Don Mosier was elected Vice Chair. The
CAC is very enthused and look forward to working on programs to support CEA's success.
Risk Oversight Committee
The Energy Risk Management Policy, adopted by the CEA Board November 19, 2020, directs
establishment of the Risk Oversight Committee (ROC), selected by the Chief Executive Officer. The CEO
has identified the following as members of the ROC:
Chief Executive Officer, Chair
Board Chair
Chief Financial Officer
General Counsel
Pacific Energy Advisors, to serve as technical advisors
The first meeting of the ROC is scheduled for February 4, 2021, and quarterly thereafter.
Expansion of Clean Energy Alliance
The Board will be reviewing and updating the Outreach Matrix at this meeting. There have been no
contacts made since the last meeting.
January 21, 2021
Admin & Regulatory Update
Page 3 of 6
Discussions with Key Potential CEA Customers
Staff has continued its discussions with San Diego County Water Agency (SDCWA) regarding Clean
Energy Alliance and implications to SDCWA of its electric accounts within CEA territory becoming
customers. SDCWA staff anticipates a SDCWA Board discussion regarding CCA at an upcoming Board
meeting. CEA staff has also had discussions with Walmart regarding CEA and its products and services as
compared to SDG&E.
Resource Adequacy Compliance
As a load serving entity serving customers in 2021, CEA has an obligation to procure Resource Adequacy
(RA), based on quantities allocated by CPUC and California Independent System Operator (CAISO). RA
procurements do not supply any energy to CEA or its customers, rather it commits the seller to be
available to supply energy to the grid if called upon by the CAISO and reduce the possibility of outages.
This process is key to ensuring grid reliability. CEA successfully procured all its RA requirements and is
fully compliant with its RA obligation.
Long-Term Renewable Procurement
As a load serving entity, CEA will be required to procure 65% of its minimum state required renewable
portfolio standards in contracts of 10-years or longer. To ensure compliance with this requirement,
CEA's initial renewable energy solicitation is underway. The solicitation process, from beginning through
final execution can be lengthy, particularly in light of the impacts of COVID-19 on the renewable
development industry. The solicitation opened on July 1, 2020, with proposals due July 27, 2020. CEA's
consultant, Pacific Energy Advisors, has identified a short list of projects and negotiations are
proceeding. It is anticipated final contracts will be before the Board in first quarter 2021.
Staff has also begun discussions with SDG&E regarding entering into bilateral agreements for the
procurement of renewable energy. These discussions are on-going, and any proposed agreement will be
brought to the CEA Board for approval.
Administrative and Operational Policies
During the coming months as CEA prepares for its implementation and operation, policies will be
brought to the Board for consideration in future Board meetings. The policies as proposed will be based
on Government Code or regulatory requirements and best practices of successfully operational CCAs.
The policies and timeline as currently anticipated are:
February 18 Board Meeting
•Investment Policy
January 21, 2021
Admin & Regulatory Update
Page 4 of 6
Contracts $50,000 - $100,000 entered into by Interim Chief Executive Officer
VENDOR DESCRIPTION AMOUNT
None
REGULATORY UPDATE
CEA's regulatory attorney, Ty Tosdal, will provide an update to the Board on the following regulatory
activities:
SDG&E 2021 ERRA Forecast Proceeding (A.20-04-014)
Annual proceeding in which SDG&E sets its energy generation and Power Charge Indifference
Adjustment rates for the coming year.
SDG&E 2020 ERRA Trigger (A20.12.007)
The 2020 ERRA Trigger application addresses an undercollection SDG&E has incurred in 2020. The
application addresses how the undercollection will be addressed through rate increases in 2021.
2020 Renewable Portfolio Standards (RPS) Procurement Plans (R.18-07-003)
CEA previously submitted its 2020 Renewable Portfolio Standards (RPS) Procurement Plan with the
CPUC. The CPUC has ordered many CCAs, IOUs and Energy Service Providers (ESP) to submit additional
information regarding its plans to meet the state's renewable energy goals.
FISCAL IMPACT
There is no fiscal impact by this action.
ATTACHMENTS
Attachment A - Clean Energy Alliance Timeline of Implementation Action Item
Attachment B — Tosdal APC Regulatory Update Report
January 21, 2021
Admin & Regulatory Update
Page 5 of 6
Attachment A
Board Actions/Activity
Staff/Consultant Activity
. Marketing/Customer Outreach
January 21, 2021
Admin & Regulatory Update
Page 6 of 6
Clean Energy Alliance
Timeline of Action Items
CCA Program Related
liming Description Status
3rd Qtr
'20
4th Qtr
'20
1st Qtr
'21 Apr-21 May-21 Jun-21 141-21
9/1/20 Marketing/Customer Outreach Plan Development & Kickoff Complete I
I
Marketing Strategic Plan Complete
Logo Design Complete
Website Refresh Complete
9/17/20 Bid Evaluation and Criteria Scoring System Complete
9/17/20 Award Scheduling Coordinator Services Complete
10/15
&
11/19
11/19/20 Introduce/Adopt Energy Risk Management Policy Complete
10/15/20 Records Retention Policy Complete
System Testing with SDG&E In Progress
1/21/21 Credit Solution In Progress
1/21/21 (IA Default Products/programs/renewable energy policies In Progress
2/1/21 Create Customer Pre- and Post-Enrollment Notices t
1/21/21 Social Media Policy
1/21/21 Debt Issuance Policy
2/1121 Set up Call Center/Scripti ng/IVR Recordings
2/18/21 Rate Setting
2/18/21 Investment Policy
Energy Supply Procurement - Short Term Renewable &Conventional
3/1/21 Customer Noticing
5/1/21 Launch - 2 phases May &June 2021
Key:
CCA Launch
Attachment B
Clean Energy Alliance
Board Update
January 14, 2021
T SDAL Ty Tosdal
Tosdal APC ENERGY & ENVIRONMENTAL LAW
Overview
•SDG&E 2021 ERRA Forecast (A. 20-04-014)
•SDG&E's 2020 ERRA Trigger A. 20-12-007)
•2020 RPS Procurement Plans (R. 18-07-003)
•Percent Income Payment Plan (R. 18-07-005)
SDG&E's 2021 ERRA Forecast
Application
•The Alternate Proposed Decision (APD) requiring SDG&E to
incorporate departing load into sales forecast was adopted.
•There will be no drastic reduction in SDG&E rates.
•The System Average Percent Change (SAPC) allocation
method adopted.
SDG&E's advice letter to be issued before February 1, 2021,
will provide additional details.
SDG&E's 2020 ERRATrigger
SDG&E has applied for a modest rate increase.
•San Diego CCAs submitted a Joint Protest on January 5, 2021.
•SDG&E has committed to applying the energy requirements
approved in the ERRA Forecast proceeding.
•San Diego CCAs Propose March 4, 2021, Commission Vote for
implementation June 1.
2020 RPS Procurement Plans
•CEA and other CCAs, ESPs and IOUs are ordered to provide
additional details to multiple sections of the RPS Plans by
February 15, 2021.
•PEA is currently working on the amendments to CEA's RPS
Procurement Plan narrative and RNS calculations.
•SDG&E's request to hold RPS sales solicitations in 2021 is
approved.
RPS Progress to Target
Comparison
fignre 1:Aggregated lOttProgiess 0300.403034RPS
Mr"
50000
4JIIU hut
100 11111 I
CCAs Proven rowan., 60% RPS
4400
34000
3000
La
111111111
CIAalin scam Ds, pan me Er Ca t ..--. ed
Source: CPUC Proposed
Decision on 2020 RPS Plans,
Filed December 11, 2020.
Percentage of Income
Payment Plan (PIPP)
•The program aims to assist customers with the lowest income
and provides a fixed, minimum bill based on income.
•Party comments reflect wide disagreement regarding PIPP
income eligibility and program parameters.
•CalCCA supports PIPP as a 12-18 month pilot for IOUs only
and PPP as cost recovery mechanism.
•SDG&E opposes the PIPP program entirely, citing duplicative
nature of CARE/FERA and other factors.
Supporting Materials
Supporting materials referenced in this presentation can be
found at the following link:
https://www.dropbox.com/sh/4sdi7dczafu3w27/AACCZGmnC00
9fLrXRxVzE59a?d1=0