HomeMy WebLinkAbout2021-02-18; Clean Energy Alliance JPA; ; Clean Energy Alliance Operational, Administrative and Regulatory Affairs UpdateNEW-
CLEAN ENERGY ALLIANCE
Staff Report
DATE: February 18, 2021
TO: Clean Energy Alliance Board of Directors
FROM: Barbara Boswell,.Interim Chief Executive Officer
ITEM 5: Clean Energy Alliance Operational, Administrative and Regulatory Affairs Update
RECOMMENDATION
1)Approve Issuance of Interest Letter to Prospective New Member Agencies.
2)Receive and File Operational and Administrative Update Report from Interim CEO.
3)Receive Community Choice Aggregation Regulatory Affairs Report from Special Counsel.
BACKGROUND AND DISCUSSION
This report provides an update to the Clean Energy Alliance (CEA) Board regarding the status of the
operational, administrative, and regulatory affairs activities.
OPERATIONAL UPDATE
CEA is meeting its milestones for the implementation of its community choice aggregation (CCA)
program and is on track to begin serving customers in May 2021/June 2021. (Attachment A - Clean
Energy Alliance Timeline of Implementation Action Items).
CEA Launch Schedule
San Diego Gas & Electric (SDG&E) has been working over the past several years on their Customer
Information System replacement program, known as Envision. They had committed to, and were on
track, for a January 4, 2021 go live, despite the challenges of working remote in the COVID-19
environment. With a January 2021 go live, SDG&E committed to supporting the CEA launch of May
2021. On Friday July 10, CEA staff, its regulatory attorney Ty Tosdal and data manager Calpine Energy
Solutions participated in a call with San Diego Community Power and SDG&E regarding the recently
approved California Public Utilities Commission (CPUC) Decision D. 20-06-003, which requires the
Investor Owned Utilities (IOU) to adopt rules and policy changes designed to reduce the number of
residential disconnections, provide assistance with debt forgiveness, and offer extended payment plans.
The program, known as Arrearage Management Payment program, is required to be implemented by
April 2021. This timing has presented a challenge to SDG&E to keep its go live date of January 4, 2021
while also meeting the requirements of the decision. SDG&E submitted a letter to the CPUC requesting
an extension to September 30, 2021 for implementing the new procedures and policies required by the
decision. This request was denied by the CPUC, resulting in SDG&E postponing implementation of its
February 18, 2021
Admin & Regulatory Update
Page 2 of 5
Envision project to April 2021. The postponement of the Envision go live date impacts CEA's
implementation.
CEA and its consultants have worked diligently with SDG&E to develop a launch schedule that minimized
impact to CEA while also minimizing the risk of incorrect bills being sent to customers. SDG&E and CEA
have agreed to a two-phased schedule with accounts transitioning to CEA in May and June 2021, and
the Board authorized the Interim Chief Executive Officer to enter into a letter agreement with SDG&E
memorializing the phased approach. The May 2021 Phase 1 would include the transition of Solana
Energy Alliance customers to CEA as well as customers in Carlsbad and Del Mar who do not have
complex billing plans. Those customers who have been identified with complex billing plans would
transition in June 2021. Staff continues to work with Calpine and SDG&E to fine tune the customer list
for each phase.
CEA Communications and Marketing Update
Work continues on CEA's communications and marketing initiatives. The updated website went live on
December 1, 2020. Brand Standards (letterhead, email signatures, etc.) have been provided; social
media presence has been established on Facebook, Twitter, and Instagram; creation of communications
tools (FAQs, information sheets) and development of customer notices are underway. Tripepi Smith is
also working on the customer outreach strategy.
Community Advisory Committee
The Community Advisory Committee held its special meeting on February 4, 2021. The focus of the
meeting was on CEA's customer outreach and communications. The Committee Members will be
identifying key community groups that CEA should engage as part of its outreach strategy.
Risk Oversight Committee
The Risk Oversight Committee (ROC) held its first meeting on February 4, 2021. The ROC received a
report from Pacific Energy Advisors regarding power supply procurements. CEA is currently compliant
with its Energy Risk Management Policy.
Expansion of Clean Energy Alliance
At its January 21, 2021 meeting, the CEA Board updated the Agency Outreach Matrix. Staff recommends
for the next step, letters be sent to prospective agencies that provides an update on where CEA is in its
CCA launch and offering to set up a meeting to initiate conversations between the agencies.
Discussions with Key Potential CEA Customers
Staff continues its discussions with San Diego County Water Agency (SDCWA) regarding Clean Energy
Alliance and implications to SDCWA of its electric accounts within CEA territory becoming customers.
SDCWA staff anticipates a SDCWA Board discussion regarding CCA at an upcoming Board meeting. CEA
staff was contacted by management of Encina Wastewater Authority regarding CEA's upcoming launch,
and the two agencies are working together regarding Encina's energy needs and CEA's role in meeting
those needs.
February 18, 2021
Adm in & Regulatory Update
Page 3 of 5
Resource Adequacy Compliance
As a load serving entity serving customers in 2021, CEA has an obligation to procure Resource Adequacy
(RA), based on quantities allocated by CPUC and California Independent System Operator (CAISO). RA
procurements do not supply any energy to CEA or its customers, rather it commits the seller to be
available to supply energy to the grid if called upon by the CAISO and reduce the possibility of outages.
This process is key to ensuring grid reliability. CEA successfully procured all its RA requirements and is
fully compliant with its RA obligation.
Long-Term Renewable Procurement
As a load serving entity, CEA will be required to procure 65% of its minimum state required renewable
portfolio standards in contracts of 10-years or longer. To ensure compliance with this requirement,
CEA's initial renewable energy solicitation is underway. The solicitation process, from beginning through
final execution can be lengthy, particularly in light of the impacts of COVID-19 on the renewable
development industry. The solicitation opened on July 1, 2020, with proposals due July 27, 2020. CEA's
consultant, Pacific Energy Advisors, has identified a short list of projects and negotiations are
proceeding. It is anticipated final contracts will be before the Board in first quarter 2021.
Staff has also begun discussions with SDG&E regarding entering into bilateral agreements for the
procurement of renewable energy. These discussions are on-going, and any proposed agreement will be
brought to the CEA Board for approval.
Administrative and Operational Policies
During the coming months as CEA prepares for its implementation and operation, policies will be
brought to the Board for consideration in future Board meetings. The policies as proposed will be based
on Government Code or regulatory requirements and best practices of successfully operational CCAs.
The policies and timeline as currently anticipated are:
February 18 Board Meeting
•Investment Policy
Contracts $50,000 - $100,000 entered into by Interim Chief Executive Officer
REGULATORY UPDATE
CEA's regulatory attorney, Ty Tosdal, will provide an update to the Board on current regulatory
activities.
February 18, 2021
Admin & Regulatory Update
Page 4 of 5
FISCAL IMPACT
There is no fiscal impact by this action.
ATTACHMENTS
Attachment A - Clean Energy Alliance Timeline of Implementation Action Item
Attachment B —Tosdal APC Regulatory Update Report
February 18, 2021
Admin 84 Regulatory Update
Page 5 of 5
Attachment A.
Clean Energy Mance
Timeine of Action Items
CCA Program Related
liming Description Status
3rd Qtr
'20
4drilli
'20
1st QI3-
'21 Apr-21 May-21 Jun-21 Jul-21
9/3120 Marketing/C_ustomer Outreach Plan Development & tGckoff
9/17/20 Bid Evaluation and Criteria Scoring System Complete
9/17/20 Award Scheduling Coordinator Services Complete
11/19/20 Introduce/Ackrpt Energy Risk Management Policy Complete
10/15
&
11/19
10/15/20 Records Retention Policy Complete
,System Testing with SDG&E In progress
Set up Call Center/Scripting/1YR Recordings In Progress
1/21/21 Credit Solution Complete
2/18/21 CEA Default Products/programs/renewable energy policies
2/1/21 Create Customer Pre- and Post-Enrollment Notices In progress
1/21/21 Social Media Policy Complete
1/21/21 Debt Management Policy Complete
2/18/21 Investment Policy
3/1/21 Rate Setting
Energy Supply Procurement
3/1/21 Customer Noticing
5/1/21 , Launch - 2 phases May &June 2021
Key:
Board Actions/Activity
Staff/Consultant Activity
Marketing/Customer Outreach
La unch
A[Eachineirr
Clean Energy Alliance
Board Update
February 18, 2021
T SDAL Ty Tosdal
Tosdal APC ENERGY & ENVIRONMENTAL LAW
Overview
•SDG&E 2021 ERRA Forecast (A. 20-04-014)
•SDG&E's 2020 ERRA Trigger (A. 20-12-007)
•SDG&E's GRC Phase ll (A. 19-03-002)
•Emergency Reliability (R. 20-11-003)
SDG&E's 2021 ERRA Forecast
Application
•Annual proceeding updates SDG&E rates, PCIA
charges and EcoChoice rates for the next year.
•SDG&E has requested an extension until February 23,
2021 to implement SAPC method for bundled
generation rates.
•SDG&E plans to file a single advice letter incorporating
ERRA Forecast and ERRA Trigger decisions into
March 1, 2021 rates.
SDG&E's 2020 ERRA Trigger
•Final decision approves a 22-month amortization to reduce
rate shock.
•Decision denies CCA request for more process and relies
on Energy Division to verify accuracy of proposal despite
lack of support in the record.
•Access to data remains an ongoing issue under discussion
with SDG&E.
SDG&E's General Rate Case
Phase II
•SDG&E is proposing as part of a settlement agreement:
•To adopt a sales forecast that does not take into
account departing load for November nd December
2021; and
•To file a standalone application to update sales forecast
for 2022.
•CEA and SDCP filed a motion for party status, and it has
been granted.
•Statements are due next week regarding conflicts between
the ERRA decision and SDG&E's proposals.
Emergency Reliability
•Commission has ordered IOUs to buy capacity (resource
adequacy) to serve load in Summer 2021.
•Purpose of the order is to avoid power shortages that occurred
in Summer 2020.
•No specific capacity levels are identified.
•Costs to be recovered through the the Cost Allocation
Mechanism (CAM).
Supporting Materials
Supporting materials referenced in this presentation
can be found at the following link:
https://www.dropbox.com/shigtxam8z50t24wtIMAAS7aUH2eq
vY4E8VDczz82ca?d1=0