HomeMy WebLinkAboutCDP 2017-0023; SHERIDAN PLACE; FINAL SOILS REPORT; 2018-06-26Project No. FC-18-06-132
June 26, 2018
IE General Engineering
Mr. Matt Parker
1440 Beaumont A venue, Suite A2-130
Beaumont, California 92233
§.lfl§ GEOTECHNICAL SOLUTIONS, INC.
Consulting Geotechnical Engineers & Geologists
593 1 Sea Lion Place, Suite I 09
Carlsbad, California 920 I 0
Office: 760-602-7815
smsgeosol.inc@gmail.com
Report of Geotechnical Engineering Observations And Compaction Testing, Remedial Pad
Grading, Proposed Single-Family Residential Development, 3913 Sheridan Place, Carlsbad,
California
Submitted herewith please find the following summary report of our geotechnical engineering
observations and compaction testing completed by our firm in connection with the remedial grading
for the proposed new building pad at the above-referenced property. Approximate limits of the
compacted fill areas at the property are delineated on the enclosed Approximate Compaction Tests
Location Map (Figure 1 ), reproduced from the project available grading plan.
Overall, remedial grading operations for the project new building pad development chiefly consisted
of removals of the upper soft and compressible soils to the underlying dense undisturbed Terrace
Deposits, but not less than 3 feet minimum, and placing back the removed soils as properly
compacted fills to achieve final pad grades. Remedial pad grading operations within the designated
limits were performed under engineering observations and compaction testing services provided by
this office from June 6, 2018 through June 20, 2018.
I. REFERENCES
The following pertinent reports and documents prepared by this office were used as a basis of our
engineering observations and compaction testing services.
1. "Preliminary Grading Plan, 3 913 Sheridan Place, Carlsbad, California," prepared by bHA,
Inc., dated June 1, 2017.
2. "Geotechnical Investigation, Proposed Single-Family Residence, Sheridan Place, Carlsbad,
California (APN 206-042-47-00)," prepared by SMSGeotechnical Solutions Inc., Project
No. GI-17-02-107, dated March 27, 2017.
Report of Geotechnical Engineering Observations and Compaction Testing
Remedial Pad Grading, 3913 Sheridan Place, Carlsbad, California
II. GEOTECHNICAL CONDITIONS
June 26, 2018
Page2
Geotechnical conditions at the project property were found to be substantially the same as described
in the referenced report. In general, pre-remedial grading conditions consisted of a mostly natural
to locally disturbed, relatively level ground surfaces. The project property was generally underlain
by a relatively shallow section ofloose and compressible undifferentiated topsoil/disturbed natural
ground, on the order of 2.5 feet thick, over dense silty sandstone Terrace Deposits.
III. LABORATORY TESTING
Pertaining maximum dry densities and optimum moisture contents (ASTM D1557) for the onsite
representative soil types were obtained from the project Geotechnical Investigation report, dated
March 27, 2017. (see References). An additional maximum dry densities and optimum moisture
content test was performed on a sample of minor import soils needed to complete grading and
achieve final design pad grades. Pertinent test results are summarized in the enclosed Compaction
Test Results sheet.
IV. GROUND PREPARATION AND GRADING OPERATIONS
Prior to the remedial grading operations, any surface vegetation, roots and tree stumps were removed
and cleared for the project areas, as appropriate. Upper surficial soft and compressible soils within
the Approximate Limits of Pad Grading areas (see attached Approximate Compaction Tests
Location Map, Figure 1) encompassing the main and detached accessory building envelope plus a
minimum of 3 feet outside the perimeter were then stripped and removed. Removals were extended
to a minimum depth of 3 feet below rough finish pad grade, exposing the underlying dense natural
Terrace Deposits throughout. All exposed bottom of removals and over-excavations were visually
examined, and probed to assure competent Terrace Deposits exposures suitable for receiving new
fills.
Minor sandy import soil from a local export site was needed to complete grading and achieve design
pad grades. Earth deposits generated from the onsite removals and remedial grading operations as
well as the imported soils were manufactured into a uniform mixture predominantly consisting of
sandy to silty sand (SM/SP) deposits ranging to very low expansion potential (Expansion Index less
than 20) based on ASTM D4829 classification.
Site new fills were moisture conditioned to or slightly above the optimum moisture levels,
depending on the final manufactured fill mixtures, processed into uniform materials, placed in thin
( approximately 8 inches thick) horizontal lifts and mechanically compacted with heavy construction
equipments, consisting of a Case 921F Wheel Loader, Ingersoll Rand DD-24 double drum roller,
and a Bobcat to a minimum 90% of the corresponding laboratory maximum density per ASTM
D1557. Water was provided with a fire hose.
Report of Geotechnical Engineering Observations and Compaction Testing
Remedial Pad Grading, 3913 Sheridan Place, Carlsbad, California
June 26, 2018
Page3
Engineering observation of the grading operations and compaction testing of the fills placed within
the remedial grading areas were provided by this office from June 6 through 20, 2018. Approximate
limits of the remedial pad grading works and field compaction test locations, as roughly established
in the field by a hand level and pacing/tap measure form staking provided by others, or relative to
identifiable features located at the site and noted on the project plans are shown on the enclosed
Approximate Compaction Tests Location Map, Figure 1.
Field density tests establishing both the in-place dry densities and moisture contents were performed
in accordance with the ASTM D 1556 (Sand Cone) and ASTM D693 8 (Nuclear Gauge) test methods,
as the fill placement progressed. Test locations were placed to provide the best possible coverage.
Areas oflow compaction, as indicated by the field density tests, were brought to the attention of the
project contractor. These areas were reworked by the contractor and retested. Field compaction test
results including pertinent bottom of over-excavation and test elevations are tabulated on the
enclosed Compaction Test Result sheet. Engineering observations and compaction test results
indicated that the fills within the approved areas (see Approximate Limits of Pad Grading on the
enclosed Approximate Compaction Tests Location Map, Figure 1) were properly placed and
compacted to at least 90% of the corresponding maximum dry density at the tested locations.
Site preparations and remedial pad grading were conducted in substantial conformance with Chapter
18 (Soils and Foundations) and Appendix "J" (Grading) of the 2016 California Building Code
(CBC), applicable codes, the Grading Ordinance for the city of Carlsbad and current engineering
standards, as appropriate. All observations and testing were conducted by a representative from this
office under direct supervision of the project geotechnical engineering.
V. CONCLUSIONS AND RECOMMENDATIONS
In our opinion, site excavations, remedial building pad grading operations, fill placement and
compaction procedures were completed in substantial conformance with the project approved plans,
city of Carlsbad grading ordinances, applicable codes and current engineering standards, and are
acceptable for their intended use.
All conclusions and recommendations including soil design parameters, geotechnical
foundation/slab designs and improvement sections provided in the referenced Geotechnical
Investigation report dated March 27, 2017 stay unchanged, as specified therein and should be
considered in the final designs and implemented during the construction phase, where applicable
and as appropriate.
VI. ADDITIONAL GEOTECHNICAL OBSERVATIONS AND TESTING
This office should be notified before any of the following operations begin in order to schedule
appropriate testing and/or field observations for confirmation and approval of the completed work:
Report of Geotechnical Engineering Observations and Compaction Testing
Remedial Pad Grading, 3913 Sheridan Place, Carlsbad, California
June 26, 2018
Page4
1. Foundations and Utility Trenches: Engineering observations or testing will also be
required for the following work prior to foundation and slab concrete pours:
a) Observe the plumbing and utility trenches after the pipes are laid and prior to backfilling.
Backfill soils within trenches 12-inches or more in depth shall be compacted by
mechanical means to a minimum of 90% of the corresponding maximum dry density,
unless otherwise specified. Jetting or flooding of the backfill is not allowed. Care
should be taken not to crush the utilities or pipes during the compaction of the trench
backfill.
b) Test the plumbing trenches beneath the floor slabs for minimum compaction
requirements prior to sand and moisture barrier placement.
c) Observe the bottom of the footing trenches for proper compaction levels, and design
minimum footing widths and embedment.
e) Confirm footing reinforcement size and placement, slab thickness and reinforcing, sand
thickness and moisture barrier placement.
2. Fine Grading and Improvements:
a) Observe placement and perform compaction testing for fills placed under any conditions
12 inches or more in depth, to include:
• Pad perimeter contour grading for establishing positive (minimum 2%) drainage
away from the building.
• Utility and storm trench backfills.
0 Retaining wall back drainage and backfills compaction testing. Minimum 90%
compaction levels are also required for wall backfills.
0 Spreading or placement of soil obtained from any excavation (spoils from footings,
underground utilities, etc.).
b) Observation and testing of subgrade (and base layer, if any required) in the access
driveway areas, perimeter side yards and beneath patios, sidewalks, etc., prior to
placement of finish paving or concrete surface.
c) Any operation not included herein which requires our testing, observation, or
conformation for submittal to the appropriate agencies.
Report of Geotechnical Engineering Observations and Compaction Testing
Remedial Pad Grading, 3913 Sheridan Place, Carlsbad, California
VII. DRAINAGE
June 26, 2018
Page 5
The owner/developer is responsible for insuring adequate measures are taken to properly finish
grade the building pad after the structures and other improvements are in-place so that the drainage
waters from the graded pad and improved sites as well as adjacent properties are directed away from
the new building foundations. Stormwater and swface run off water should not be allowed to
impact or saturate natural and graded ground surfaces, fills and backfills, foundation bearing and
sub grade soils. Only the amount of water to sustain vegetation life should be provided.
A minimum of 2% gradient should be maintained away from all foundations. Roof gutters and
downspouts should be installed and all discharge from downspouts should be led away from the
foundations and slab to a suitable location. Install area drains in the yards for collection and
disposal of surface water.
Planter areas adjacent to foundations should not to allowed. Site retaining walls should be provided
a well-constructed back drainage. Planting large trees behind site retaining walls and near the
building foundations should be avoided.
It should be noted that shallow groundwater conditions may develop in areas where no such
conditions existed prior to site development. This can be contributed to by substantial increases of
surface water infiltration resulting from landscape irrigation which was not present prior to the site
development. It is almost impossible to absolutely prevent the possibility of shallow water
conditions developed from excessive landscape irrigation over the entire site, and onsite drainage
facilities. Therefore, we recommend that shallow water conditions, if developed, be immediately
remedied by implementing appropriate measure, which may include the installation of sub-drain(s)
consisting of a 4-inch diameter perforated pipe (SDR 35) surrounded in ¾-inch rocks all wrapped
in filter fabric.
The property owner(s) should be made aware that altering drainage patterns, landscaping, the
addition of patios, planters, and other improvements, as well as over-irrigation and variations in
seasonal rainfall, all affect subsurface moisture conditions, which in turn affect structural and overall
slope performance.
VIII. LIMITATIONS
Our description of the remedial grading operations, as well as observations and testing services
described herein, are limited to the work performed by this office during the period from June 6,
2018 through June 20, 2018. The recommendations provided herein have been based on our field
observations and testing, as noted. No representations are made as to the quality or extent of
materials not observed and tested.
Report of Geotechnical Engineering Observations and Compaction Testing
Remedial Pad Grading, 3913 Sheridan Place, Carlsbad, California
June 26, 2018
Page 6
All geotechnical information, test location and mapping on the enclosed Approximate Compaction
Tests Location Map are based on rough field measurements for the purpose of geotechnical
presentations only.
This report is issued with the understanding that the owner or his representative is responsible for
ensuring that the information and recommendations are provided to the project architect/structural
engineer and respective contractors so that they can be incorporated into the plans and implemented
at the site. Necessary steps shall be taken to ensure that the project general contractor and
subcontractors carry out such recommendations during construction.
The project geotechnical engineer should also be provided the opportunity to field verify the
foundation trenching, and foundations/slab steel reinforcement prior to placing concrete. If the
project geotechnical engineer is not provided the opportunity of making these reviews and
observations, he can assume no responsibility for misinterpretation of his recommendations.
This report should be considered valid for permit purposes for a period of six months and is subject
to review by our firm following that time. IF ANY CHANGES ARE MADE IN THE FINAL PAD
SIZE, LINES AND GRADES, BUILDING LOCATION, ELEVATIONS, ETC., PRIOR TO THE
CONSTRUCTION, THIS REPORT WILL BECOME INVALID AND FURTHER
ENGINEERING AND RECOMMENDATIONS WILL BECOME NECESSARY.
If you have any questions or need clarification, please contact this office at your convenience.
Reference to our Project No. GI-18-06-132 will help to expedite our response to your inquiries.
We appreciate this opportunity to be of service to you.
§1'.I§ Geotechnical Solutions, Inc.
Distribution: Addressee (3, e-mail)
Attachments: Approximate Compaction Tests Location Map, Figure 1
Compaction Test Results Sheet
61'16 GEOTECHNICAL SOLUTIONS, INC.
PROJECT NO: PROJECT NAME: PROJECT LOCATION: COMPACTION TEST RESULTS FC-18-06-132 Sheridan Place Single-Family Residence 3913 Sheridan Place, Carlsbad LABORATORY MAXIMUM DRY DENSITY/ OPTIMUM MOISTURE CONTENT TEST RESULTS (ASTM 01557): Soil Type (2): Tan to Red-Brown Silty Sand. Soil Type (3): Medium Brown Silty Sand (Import). Maximum Dry Density: 129 .0 pcf Maximum Dry Density: 119 .0 pcf Optimum Moisture: 10% Optimum Moisture: 9% Note: Also see the project Geotechnical Investigation Report dated March 27, 2017 for different Soil Types. FIELD COMPACTION TEST RESULTS, ASTM D1556 (SAND CONE) AND ASTM D6938 (NUCLEAR GAUGE) TEST METHODS: Approximate Approximate Field Field Max. Relative Test Test Dry Soil Dry Date No. Test Elevation (MSL) Moisture Density Type Density Compaction Comments Location (ft) (%) (pct) (pct) (%) 06/06/2018 1 Northerly Pad/Building Areas 48.00'± 11 117.8 2 129.0 91 Bottom ofover-ex. @47.00'± 06/06/2018 2 Northerly, Garage Areas 48.00'± 11 116.8 2 129.0 91 06/07/2018 3 Southeasterly Pad Areas 48.00'± 11 116.5 2 129.0 90 Bottom of over-ex. @47.00'± 06/07/2018 4 Central, Building Areas 48.00'± 9 117.2 2 129.0 91 06/07/2018 5 Southwesterly, Spa Areas 48.00'± 8 116.6 2 129.0 90 06/20/2018 6 Northeasterly, Garage Areas Finish Pad Grade 8 117.8 2 129.0 91 06/20/2018 7 Northerly, Building Areas Finish Pad Grade 8 117.9 2 129.0 91 06/20/2018 8 Northwesterly, Accessory Finish Pad Grade 8 117.1 2 129.0 91 Building Areas 06/20/2018 9 Westerly Pad Areas Finish Pad Grade 9 118.1 2 129.0 92 06/20/2018 10 Southeasterly Building Areas Finish Pad Grade 10 116.l 2 129.0 90 06/20/2018 11 Central Building Areas Finish Pad Grade 8 108.8 3 119.0 91 §M§ GEOTECHNICAL SOLUTIONS, INC.
49.0J FS
48.27 IE
4" PVC/J" REDUCER
48.JJ IE
)6-042-26
/
I
0.5
" '
-I
6.250'
. Bott. of over-ex. @ 47 .00'+
MAIN BUILDING
_/,<:) .... . -~-,,
LOT 16
50.50 FF !
5D.00 PAO.
__ ,,,,,, ---
/
0. X
LANDSCAPING
0 •~ N2839'00"W 61.69'
MAP NO. 4751
LOT 15
L EXISTING BUILDING
I
1.0
I
';
/
EXISTING FENCE
TO BE REM0\1£D
8' PUBLIC UTILITY
EASEMENT PER
MAP NO. 4751
I
C
C.l i
; ~x1s!J
;~LiJ
i> I
2+59.5J
49.78 FS
4' PVC SEWER LA TERA!
\
I
I
FIGURE 1
GEOTECHNICAL LEGEND ,.--.,
i i t,_,J
@]
ApproL Limits of Pad Grading
ApproL Compaction Test Location