Acceptance of Bids and Award of Contract to Portillo Concrete, Inc. for
the Fiscal Year 2020-21 Americans with Disabilities Act Improvement
Program
1
Recommended Action
Adopt a resolution accepting bids and awarding a contract to Portillo Concrete, Inc. for
construction of the fiscal year 2020-21 Americans with Disabilities Act, or ADA, Improvement
Program, Capital Improvement Program, or CIP, Project No. 6049-21, in an amount not to
exceed $640,650.
Executive Summary
The project will replace or retrofit existing curb ramps throughout District 1 (see Exhibit 2 -
Location Map) and is part of the city’s ongoing ADA Improvement Program.
On June 8, 2021, the City Council adopted Resolution No. 2021-128 approving the plans and
specifications and authorizing advertising the project for construction bids. The project was
advertised using the city’s formal bidding procedures. On July 8, 2021, staff received eight
construction bids, and the lowest responsive and responsible bidder was Portillo Concrete, Inc.,
or Portillo Concrete, with a bid in an amount of $640,650.
Carlsbad Municipal Code, or CMC, Sections 3.28.080(C) and 3.28.080(I)(6) require the City
Council’s approval for all formally bid contracts when the value exceeds $200,000, making the
project subject to this requirement.
Staff recommend acceptance of bids and award of the construction contract to Portillo
Concrete for the project, in an amount not to exceed $640,650.
Discussion
In 2013, the city adopted an ADA Transition Plan to provide a program to address accessibility
along the city’s public right-of-way. Implementation of the ADA Transition Plan will improve
accessibility and walking conditions for all users of the public right-of-way. The project will
replace 90 curb ramps and retrofit four existing curb ramps in District 1, bringing them into
compliance with current ADA standards.
Aug. 31, 2021 Item #4 Page 1 of 7
Implementation of these improvements is directly related to the City Council goal of “enhancing
the health and vitality of the Village and Barrio” and an example of the city’s organizational
values of stewardship and excellence.
As noted above, staff received eight sealed bids for construction of the project on July 8, 2021.
Staff reviewed the contract documents and determined Portillo Concrete was the lowest
responsive and responsible bidder. Portillo Concrete is responsive because its bid meets the
requirements of the bidding documents. The bidder is also deemed responsible because it
submitted a list of similar projects to show its capability and qualifications to perform the
specified work. The construction contract contains general performance standards and
references technical specifications, which if not met, allow the city to withhold payment. The
contract also includes a one-year warranty period from notice of completion.
Options
Staff provide the following options for the City Council’s consideration:
1. Accept bids and award a contract to Portillo Concrete for construction of the project in
an amount not to exceed $640,650.
Pros
• Portillo Concrete has been determined to be the lowest responsible and
responsive bidder
• Award of the contract complies with applicable CMC sections, including CMC
Sections 3.28.080(C) and 3.28.080(I)(6)
• Construction can start upon award of the contract
• Project is an example of the city’s organizational values of stewardship and
excellence
• Sufficient funding is available for the contract
Cons
• None identified
2. Do not accept the bids and do not award the contract to Portillo Concrete
Pros
• None identified
Cons
• Delays start of construction
• ADA ramp replacement issues will continue to exist and could potentially affect
pedestrian mobility in the project area
• Potential increase in construction costs due to delay in award
Staff recommend Option 1 for the City Council’s approval: Accept bids and award a contract to
Portillo Concrete for construction of the project in an amount not to exceed $640,650.
Aug. 31, 2021 Item #4 Page 2 of 7
Fiscal Analysis
Sufficient TransNet local funds are available to complete the project.1 Remaining funds will be
available for future ADA improvement projects. A summary of the estimated costs and available
funds is shown in the table below:
ADA Improvement Program, CIP Project No. 6049-21
Total appropriation to date $2,440,000
Total expenditures/encumbrances to date $1,198,366
Total available funding $1,241,634
Additional Project Costs
Construction contract - Portillo Concrete Inc. $640,650
Construction contingency (estimated) $65,000
Construction management, inspection and testing (estimated) $100,000
Total estimated construction costs $805,650
Remaining balance $435,984
Additional appropriation needed $0
Carlsbad Municipal Code Sections 3.28.040(C)(5) and 3.28.090(B) authorize the City Manager or
designee to approve change orders in an amount equal to the contingency set at the time of
project award, which is $65,000 for this project.
Next Steps
Once the City Council accepts bids and awards the construction contract to Portillo Concrete
staff will issue a purchase order, schedule a pre-construction meeting with Portillo Concrete
and issue a notice to proceed for construction of the project, which is expected to commence in
fall 2021.
The duration of the construction contract is 100 working days, not including rainy days and
delays from change orders that may extend the contract duration. Upon successful completion
of the project, which is expected to be in late 2021 or early 2022, a notice of completion will be
recorded to release bonds will be recorded.
Environmental Evaluation (CEQA)
The project is exempt from the California Environmental Quality Act under CEQA Guidelines
Section 15301(c), which covers the repair of existing public structures and facilities involving
negligible or no expansion.
Public Notification
Public notice of this item was posted in accordance with the Ralph M. Brown Act and it was
available for public viewing and review at least 72 hours prior to the scheduled meeting date.
1 TransNet is a countywide sales tax collected to fund regional transportation projects.
Aug. 31, 2021 Item #4 Page 3 of 7
Exhibits
1. City Council resolution
2. Location map
Aug. 31, 2021 Item #4 Page 4 of 7
RESOLUTION NO. 2021-199
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CARLSBAD,
CALIFORNIA,.ACCEPTING BIDS AND AWARDING A CONTRACT TO PORTILLO
CONCRETE! INC. FOR CONSTRUCTION OF THE FISCAL YEAR 2020-21
AMERICANS WITH DISABILITIES ACT IMPROVEMENT PROGRAM, CAPITAL
IMPROVEMENT PROGRAM PROJECT NO. 6049-21
WHEREAS, the City Council of the City of Carlsbad, California has determined it necessary,
desirable and in the public interest to construct the fiscal year, or FY, 2020-21 ADA Improvement
Program, Capital Improvement Program, or CIP, Project No. 6049-21 (Project); and
WHEREAS, on June 8, 2021, the City Council adopted Resolution No. 2021-128 approving the
plans and specifications and authorizing advertisement of the Project for construction bids; and
WHEREAS, on July 8, 2021, staff received eight sealed bids for the Project; and
WHEREAS, the lowest responsive and responsible bid for the Project was submitted by Portillo
Concrete, Inc., or Portillo Concrete, in an amount of $640,650; and
WHEREAS, the Project is financed with TransNet local funds, and sufficient funding in the
project account is available to complete the Project; and
WHEREAS, Carlsbad Municipal Code Sections 3.28.080(() and 3.28.080(1)(6) require the City
Council to award all formally bid contracts when the value exceeds $200,000; therefore, the Project is
subject to this requirement; and
WHEREAS, Carlsbad Municipal Code Sections 3.28.040(()(5) and 3.28.090(B) authorize the
City Mana15er or designee to approve change orders in an amount equal to the contingency set at the
time of project award, which is $65,000 for the Project; and
WHEREAS, the City Planner has determined that the Project is exempt from the California
Environmental Quality Act (CEQA) in accordance with the CEQA Guidelines Section 15301(c) -minor
alteration of existing facilities including streets, sidewalks, gutters, and similar facilities involving
negligible or no expansion: and that none of the exceptions to the exemptions as set forth in CEQA
Guidelines in Section 15300.2 applies.
II
II
II
II
Aug. 31, 2021 Item #4 Page 5 of 7
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad, California, as
follows:
1. That the above recitations are true and correct.
2. That the bid of $640,650 submitted by Portillo Concrete for construction of the FY 2020-
21 ADA Improvement Program, CIP Project No. 6049-21, is accepted and the Mayor is
hereby authorized to execute the contract for the Project.
3. That the City Manager or designee is hereby authorized to approve construction change
orders up to $65,000.
4. That the award of this contract is contingent upon Portillo Concrete executing the
required contract and submitting the required bonds and insurance policies, as
described in the contract, within 20 calendar days of adoption of this Resolution. The
City Manager may grant reasonable extensions of time to execute the contract and
assemble the required bonds and insurance policies.
PASSED, APPROVED AND ADOPTED at a Regular Meeting of the City Council of the City of
Carlsbad on the 31st day of August, 2021, by the following vote, to wit:
AYES:
NAYS:
ABSENT:
Hall, Blackburn, Bhat-Patel, Acosta, Norby.
None.
None.
MATT HALL, Mayor
~~r~fo(
FAVIOLA MEDINA, City Clerk Services Manager
(SEAL)
Aug. 31, 2021 Item #4 Page 6 of 7
VISTA
ENCINITAS
SANMARCOS
S.D.COUNTY
OCEANSIDE
BATIQUITOS LAGOON
BUENAVISTALAGOON
AGUAHEDIONDALAGOONTAMARACKAV
LA C O STA AV
MELROSE
D
R
OLIVENHAIN RDC
A
R
L
S
B
A
D
B
L
A V IARA PYCARLSBADVILLAGEDR
RANCHOSAN TA F E RDA L G A R D
C O L L E G E BLPA LO M AR AIRPO RT RD
F A R ADAY A V
P O IN S E TT IA LN
CANNONRD
C
ARLSBADBL
ELCAMINOREAL
Exhibit 2LOCATION MAP
EXHIBIT2FY 2020-21ADA IMPROVEMENT PROGRAM
ZNORTHNOT TOSCALE
Created By: Benjamin Arp 3/17/2021 S:\Benjamin_Arp\Location Map\ADA_Improve\ADA_Improve_fy120-21_1.mxd
HOPEELEMENTARYSCHOOL
NORTHWESTQUADRANTSITES
Aug. 31, 2021 Item #4 Page 7 of 7
Scott Lyle, Senior Engineer
Aug. 31, 2021
Acceptance of Bids and Award of
Contract to Portillo Concrete Inc. for
FY 2020-21 ADA Improvement Program
Recommendation
Adopt a resolution accepting bids and awarding a
contract to Portillo Concrete Inc. for construction of
FY 2020-21 ADA Improvement Program, Capital
Improvement Program (CIP) Project No. 6049-21 in
an amount not to exceed $640,650
2
Background
•In 2013, city adopted an ADA Transition Plan to
provide a program to address accessibility
along city’s public right of way
•June 8, 2021, City Council approved the
project plans and specifications and authorized
advertising the project for construction bids
3
Project Details
•Part of city’s ongoing ADA Improvement Program
•Program improves accessibility and walking
conditions for all users of the public right-of-way
•Project will replace 90 curb ramps and retrofit four
existing curb ramps in District 1
4
Project Locations
5
•District 1
•Hope elementary school
•N.W. quadrant
•Replace 90 curb ramps
•Retrofit 4 existing curb
ramps
N.W. QUADRANT
SITES
CITY or OCEANSIDE HOPE ELEMENTARY SCHOOL
7a
Selection Process for Proposed ADA Ramps
•Public feedback
•Review priorities in ADA Transition Plan
•Projects grouped into areas that are similar in
geographic location
6
Selection Process for Proposed Contractor
•July 8, 2021, staff reviewed eight bid documents
and determined Portillo Concrete Inc. is the
lowest responsible and responsive bidder
•Staff recommend award of construction contract
to Portillo Concrete Inc. in an amount not to
exceed $640,650
7
Next Steps
Staff will proceed with the following steps:
–Execute contract documents
–Schedule pre-construction meeting and issue a notice
to proceed for construction
–Provide public outreach services
–Construct the ADA improvements
•Duration of contract is 100 working days
•Estimated project completion: late 2021/early 2022
10
Recommendation
Adopt a resolution accepting bids and
awarding a contract to Portillo Concrete Inc.
for construction of the FY 2020-21 ADA
Improvement Program, CIP Project No. 6049-21
in an amount not to exceed $640,650
11
Thank you