HomeMy WebLinkAboutSDP 2019-0012; RAF PACIFICA GROUP FUSION; HYDROLOGY REPORT; 2020-05-01HYDROLOGY STUDY FOR GRADING PERMIT 1950 CAMINO VIDA ROBLE RAF PACIFICA GROUP FUSION -OUTDOOR AMENITY AREA GR 2020-0006 / DWG 523-3A (PRE 2019-0006 / DEV 2019-0138) CITY OF CARLSBAD, CA PREPARED FOR: RAF PACIFICA GROUP-REAL ESTATE FUND IV, LLC 111 C STREET, SUITE 200 ENCINITAS, CA 92024 PH: (858) 314-3116 PREPARED BY: PASCO LARET SUITER & AS SOCIA TES, INC. 535 N. HIGHWAY 101, SUITE A SOLANA BEACH, CA 92075 PH: (858) 259-8212 Prepared: February 2020 Revised: April 2020 Final: May 2020 -~-~ TYLER G. LAWSON, RCE 80356 DATE No. 80356 p. 12/31/ . .,-, "" "--, ••• ,.i....._..J Executive Summary Introduction Existing Conditions Proposed Project Conclusions References Methodology Introduction TABLE OF CONTENTS County of San Diego Criteria Runoff Coefficient Determination Hydrology & Hydraulic Model Output Pre-Developed Hydrologic Calculations ( 100-Year Event) Post-Developed Hydrologic Calculations (100-Year Event) Detention Analysis ( 100-Year Event) Hydromodification Analysis Storm Water Pollutant Control Appendix Hydrology Support Material SECTION 1.0 1.1 1.2 1.3 1.4 1.5 2.0 2.1 2.2 2.3 3.0 3.1 3.2 3.3 3.4 3.5 4.0 PLSA 3140-02 1.0 EXECUTIVE SUMMARY 1.1 Introduction This Hydrology Study / Drainage Report for the proposed development and outdoor amenity area improvements at 1950 Camino Vida Roble has been prepared to analyze the hydrologic and hydraulic characteristics of the existing and proposed project site. This report intends to present both the methodology and the calculations used for determining the runoff from the project site in both the pre-developed ( existing) conditions and the post-developed (proposed) conditions produced by the 100-year, 6-hour storm. 1.2 Existing Conditions The subject property is located in an industrial / business park at the intersections of Kellogg A venue and Owens A venue with Camino Vida Roble in the City of Carlsbad. Currently, the site consists of an existing commercial building used for office space, and also includes a private drive aisle with various onsite parking including an onsite parking lot on the eastern portion of the site. The site is bound to the north by another existing commercial development, McClellan-Palomar Airport to the northeast, Kellogg A venue to the west, Camino Vida Roble to the south, and Owens Avenue to the southeast. Overflow parking for the McClellan-Palomar Airport borders the site to the east as well near the terminus of Owens A venue. The project site is located in the Encinas Hydrologic Sub-Area within the Carlsbad Watershed (904.40). A study of the site's surrounding edge conditions by Pasco, Laret, Suiter & Associates determined that the existing commercial development to the north, as well as curb & gutter surface improvements along Kellogg A venue, Camino Vida Roble, and Owens Avenue, preclude any offsite drainage from entering the subject property. The McClellan-Palomar Airport overflow parking to the east collects runoff and drains to private storm drain before discharging offsite as well, and it can be assumed there is no cross-lot drainage entering the site across the eastern property line. After review of the boundary conditions adjacent to the McClellan-Palomar Airport as well as as-built record drawings for an existing private storm drain running through the site, the airport is discharging storm water through the subject property toward Owens A venue downstream. Based on published HGL information shown on DWG 241-6, it was calculated that approximately 30.2 cfs is being conveyed from the airport through the site by means of an existing 36" RCP private storm drain. For this analysis, the offsite flow was ignored to compare pre-and post-developed peak discharge generated onsite only. See additional discussion in Section 1.3 of the report regarding the relocation of the existing 36" RCP private storm drain. The existing onsite drainage can be categorized into four (4) major drainage basins, with four (4) discharge locations from the subject property. However, as public storm drain piping exists in the surrounding streets, all discharge from the site currently enters this system and eventually confluences just south of the site at the intersection of Camino Vida Roble and Owens A venue. From here, discharge is routed further south toward Page 1 of 13 PLSA 3140-02 Palomar Airport Road by means of the aforementioned public storm drain piping, and outlets on the surface to a detention basin located northeast of the intersection of Camino Vida Roble and Palomar Airport Road. The site itself primarily drains from north to south, with a local low point located at a curb inlet on the north side of Owens Avenue at the Camino Vida Roble intersection. The existing project site has a total area of 10.96 acres and is approximately 70% impervious. A small portion 0.03-acre portion of the site in the northeast comer of the property was excluded from the onsite hydrology calculations as it is upstream of an existing brow ditch running along the property line. Per the Web Soil Survey application available through the United States Department of Agriculture, the basin is generally categorized to have group D soils. Based on the hydrologic soil type and existing land use of Planned Industrial (P-M) per the City of Carlsbad zoning map, a pre-development runoff coefficient of 0.85 was determined using Table 3-1 "Runoff Coefficients for Urban Areas" of the San Diego County Hydrology Manual. This runoff coefficient was used to calculate peak runoff generated by the onsite drainage basins in the existing condition. Using the Rational Method Procedure outlined in the San Diego County Hydrology Manual, a peak flow rate and time of concentration were calculated for a 100-year, 6- hour storm event for each of the onsite drainage basins. Table 1 below summarizes the results of the Rational Method calculations. EXISTING DRAINAGE FLOWS DRAINAGE DRAINAGE Q100 lioo AREA AREA (CFS) (IN/HR) (ACRES) EX-1 3.71 16.54 6.2 EX-2 3.03 15.86 6.14 EX-3 2.64 11.09 5.48 EX-4 1.55 9.40 7.11 *OFF-1 -30.22 - Table 1. Existing Condition Peak Drainage Flow Rates Table 1 above lists the peak flow rates for the project site in the existing condition for the respective rainfall events. The offsite drainage basin was not considered in the analysis to compare only the effects of the proposed development to the onsite drainage. The four ( 4) streams were then confluenced using Advanced Engineering Software (AES) to determine total peak flow generated onsite in the existing condition. This was determined to be 49.69 cfs with a time of concentration of 6.29 minutes. Refer to pre- development hydrology calculations included in Section 3.1 of this report for a detailed Page 2 of 13 PLSA 3140-02 analysis of the existing drainage basins, as well as a pre-development hydrology node map included in the appendix of this report for pre-development drainage basin delineation and discharge locations. 1.3 Proposed Project The proposed project includes the construction of an outdoor amenity area for the existing commercial building. Separate from the amenities that include a basketball court bocce ball courts, a 20-foot-wide fire access road along with miscellaneous surface, utility, and retaining wall improvements are proposed. Onsite grading to construct the amenity area is also necessitated. The proposed building is to remain and be protected in place as shown on the project precise grading plan under separate cover (DWG 523-3A). Similar to the pre-project condition, the proposed onsite drainage can be categorized into four (4) major drainage basins, with four (4) discharge locations from the subject property. The entirety of the proposed drainage basin is approximately 10.93 acres as in the existing condition, as the 0.03-acre portion of the site upstream of a brow ditch routing off site runoff through the property was excluded from the hydrology calculations. Basin EX-1 covering the western portion of the property remains undisturbed and unchanged in the proposed condition. The remaining onsite major drainage basins have been altered slightly, but continue to convey runoff to the same points of discharge as in the pre-project state. The project proposes to reroute a portion of the existing private 36" RCP storm drain running north-to-south through the property out of the proposed amenity improvements. An additional hydraulic analysis is not required to confirm this private storm drain piping is adequately sized, as the pipe capacity of the system will not be altered, nor will additional flows be routed to this stretch of piping than those which exist in the pre- project state. Published HGL information on record drawing DWG 241-6 shows that the pipe should be flowing less than half-full while conveying peak runoff generated by the 100-year storm event, so sufficient capacity exists. Based on the hydrologic soil type and proposed land use of Planned Industrial (P-M) per the City of Carlsbad zoning map, a post-development runoff coefficient of 0.85 was determined using Table 3-1 "Runoff Coefficients for Urban Areas" of the San Diego County Hydrology Manual. This runoff coefficient was used to calculate peak runoff generated by the onsite drainage basins in the proposed condition (as well as the existing condition). Using the Rational Method Procedure outlined in the San Diego County Hydrology Manual, a peak flow rate and time of concentration were calculated for a 100- year, 6-hour storm event for each of the onsite drainage basins. Table 2 below summarizes the results of the Rational Method calculations. Page 3 of 13 PLSA 3140-02 PROPOSED DRAINAGE FLOWS DRAINAGE Q100 DRAINAGE 1100 AREA AREA (CFS) (IN/HR) (ACRES) EX-l 3.71 16.53 6.19 PR-l. l 1.65 8.60 6.01 PR-1.2 1.29 7.60 7.11 PR-2 2.75 11.14 5.42 PR-3 1.53 9.25 7.11 *OFF-l -30.22 - Table 2. Proposed Condition Peak Drainage Flow Rates The four ( 4) streams were then confluenced using Advanced Engineering Software (AES) to determine total peak flow generated onsite in the proposed condition, in order to compare to pre-developed conditions. This was determined to be 48.25 cfs with a time of concentration of 6.56 minutes, a decrease of 1.44 cfs compared to the existing condition. Refer to post-development hydrology calculations included in Section 3.2 of this report for a detailed analysis of the proposed drainage basin, as well as a post-development hydrology node map included in the appendix of this report for post-development drainage basin delineation and discharge locations. In an effort to comply with the City of Carlsbad storm water standards, the proposed site has also incorporated LID design techniques to optimize the site layout. Runoff from proposed hardscape areas will be directed to landscaped areas in an effort to disperse drainage to pervious surfaces. Landscaping will remove sediment and particulate-bound pollutants from storm water and will assist in decreasing peak runoff by slightly increasing the site's overall time of concentration. Additional site design and source control measures will be implemented as applicable. 1.4 Conclusions Based upon the analysis included in this report, there is a decrease in peak runoff as a result of the proposed development. Similar to the existing condition, the post-developed site will discharge from the property at four (4) different locations and connect to the existing buried public storm drain network. Once in the storm drain, all runoff leaving the property will eventually confluence at the intersection of Camino Vida Roble and Owens A venue prior to traveling south to outlet to a detention basin just north of Palomar Airport Road. Water will not be diverted away from existing drainage patterns, and the proposed development and resulting peak runoff will not have an adverse effect on the downstream watershed. Page 4 of 13 PLSA 3140-02 1.5 References "San Diego County Hydrology Manual", revised June 2003, County of San Diego, Department of Public Works, Flood Control Section. "San Diego County Hydraulic Design Manual", revised October 2012, County of San Diego, Department of Public Works, Flood Control Section "City of Carlsbad Engineering Standards, Volume 5: Carlsbad BMP Design Manual (Post Construction Treatment BMPs) ", revised February 2016 "Low Impact Development Handbook-Stormwater Management Strategies", revised July 2014, County of San Diego, Department of Public Works Soil Survey Staff, Natural Resources Conservation Service, United States Department of Agriculture. Web Soil Survey. Available online at http://m:bsoilsun cv .nrcs.usda.go\. Accessed July 20, 2015 Page 5 of 13 PLSA 3140-02 2.0 METHODOLOGY 2.1 Introduction The hydrologic model used to perform the hydrologic analysis presented in this report utilizes the Rational Method (RM) equation, Q=CIA. The RM formula estimates the peak rate of runoff based on the variables of area, runoff coefficient, and rainfall intensity. The rainfall intensity (I) is equal to: I= 7.44 X P6 X D"0645 Where: I = Intensity (in/hr) P6 = 6-hour precipitation (inches) D = duration (minutes -use Tc) Using the Time of Concentration (Tc), which is the time required for a given element of water that originates at the most remote point of the basin being analyzed to reach the point at which the runoff from the basin is being analyzed. The RM equation determines the storm water runoff rate (Q) for a given basin in terms of flow (typically in cubic feet per second (cfs) but sometimes as gallons per minute (gpm)). The RM equation is as follows: Where: Q=CIA Q = flow (in cfs) C = runoff coefficient, ratio of rainfall that produces storm water runoff (runoff vs. infiltration/evaporation/absorption/etc) I= average rainfall intensity for a duration equal to the Tc for the area, in inches per hour. A = drainage area contributing to the basin in acres. The RM equation assumes that the storm event being analyzed delivers precipitation to the entire basin uniformly, and therefore the peak discharge rate will occur when a raindrop that falls at the most remote portion of the basin arrives at the point of analysis. The RM also assumes that the fraction of rainfall that becomes runoff or the runoff coefficient C is not affected by the storm intensity, I, or the precipitation zone number. Page 6 of 13 PLSA 3140-02 2.2 County of San Diego Criteria As defined by the County Hydrology Manual dated June 2003, the rational method is the preferred equation for determining the hydrologic characteristics of basins up to approximately one square mile in size. The County of San Diego has developed its own tables, nomographs, and methodologies for analyzing storm water runoff for areas within the county. The County has also developed precipitation isopluvial contour maps that show even lines of rainfall anticipated from a given storm event (i.e. 100-year, 6-hour storm). One of the variables of the RM equation is the runoff coefficient, C. The runoff coefficient is dependent only upon land use and soil type and the County of San Diego has developed a table of Runoff Coefficients for Urban Areas to be applied to basin located within the County of San Diego. The table categorizes the land use, the associated development density ( dwelling units per acre) and the percentage of impervious area. Each of the categories listed has an associated runoff coefficient, C, for each soil type class. The County has also illustrated in detail the methodology for determining the time of concentration, in particular the initial time of concentration. The County has adopted the Federal Aviation Agency's (FAA) overland time of flow equation. This equation essentially limits the flow path length for the initial time of concentration to lengths under 100 feet, and is dependent on land use and slope. The time of concentration minimum is 5 minutes per the County of San Diego requirements. 2.3 Runoff Coefficient Determination As stated in section 2.2, the runoff coefficient is dependent only upon land use and soil type and the County of San Diego has developed a table of Runoff Coefficients for Urban Areas to be applied to basin located within the County of San Diego. The table, included at the end of this section, categorizes the land use, the associated development density ( dwelling units per acre) and the percentage of impervious area. 2.4 AES Rational Method Computer Model The Rational Method computer program developed by Advanced Engineering Software (AES) satisfies the County of San Diego design criteria, therefore it is the computer model used for this study. The AES hydrologic model is capable of creating independent node-link models of each interior drainage basin and linking these sub-models together at confluence points to determine peak flow rates. The program utilizes base information input by the user to perform calculations for up to 15 hydrologic processes. The required base information includes drainage basin area, storm water facility locations and sizes, land uses, flow patterns, and topographic elevations. The hydrologic conditions were analyzed in accordance with the 2003 County of San Diego Hydrology Manual criteria as follows: Page 7 of 13 Design Storm 100-year, 6-hour 2.7 inches PLSA 3140-02 100-year, 6-hour Precipitation Rainfall Intensity Based on the 2003 County of San Diego Hydrology Manual criteria Runoff Coefficient Soil Type Runoff Coefficient for Urban Areas based on Land Use per Table 3-1 of SDHDM Hydrologic Soils Group D 2.4.1 AES Computer Model Code Information 0: Enter Comment 2: Initial Subarea Analysis 3: Pipe/Box/Culvert Travel Time 5: Open Channel Travel Time 7: User-Specified hydrology data at Node 8: Addition of sub-area runoff to Main Stream 10: Copy Main Stream data onto a Memory Bank 11: Confluence Memory Bank data with Main Stream 13: Clear the Main Stream Page 8 of 13 3.0 HYDROLOGY MODEL OUTPUT 3.1 Pre-Developed Hydrologic Model Output (100-Year Event) Pre-Development: *Rational Method Equation PLSA 3140-02 Q=CIA P100 = 2.7 * 100-Year, 6-Hour Rainfall Precipitation Total Project Site Total Area= 477,340 sf-+ 10.958 Acres Impervious Area= 332,500 sf-+ 7.633 Acres Pervious Area= 144,840 sf-+ 3.325 Acres C, Runoff Coefficient for Urban Areas based on Land Use, -0.85, C value per SDHDM Table 3-1 *Type D Soils, Office Professional / Commercial and Limited Industrial Land Use per City of Carlsbad zoning map (Planned Industrial P-M) -0.35, C value per SDHDM Table 3-1 *Type D Soils, Permanent Open Space for Initial Overland Flow Basin EX-1 (Discharge to public storm drain in Camino Vida Roble) Total Area= 161,570 sf-+ 3.709 Acres Total Area Basin EX-1.1 = 34,617 sf ➔ 0. 795 Acres C = 0.85 Total Area Basin EX-1.2 = 126,953 sf ➔ 2.914 Acres C = 0.85 Peak Discharge: Tc= 6.19 min (See attached A.E.S. analysis for details) Q100 = 16.54 cfs (See attached A.E.S. analysis for details) A= 3.7 Acres Basin EX-2 Total Area= 131,805 sf-+ 3.026 Acres C = 0.85 Peak Discharge: Tc= 6.29 min (See attached A.E.S. analysis for details) Q100 = 15.86 cfs (See attached A.E.S. analysis for details) A= 3.0 Acres Page 9 of 13 Basin EX-3 Total Area= 114,945 sf-+ 2.639 Acres C = 0.85 Peak Discharge: Tc= 7.55 min (See attached A.E.S. analysis for details) Q100 = 12.22 cfs (See attached A.E.S. analysis for details) A= 3.71 Acres Basin EX-4 Total Area= 67,720 sf-+ 1.555 Acres C = 0.85 Tc= 5.0 Min (minimum for small areas) P6= 2.7 I = 7.44 X p 6 X o-0 645 1 = 7.44 x 2.1 x 5.o-0645 :::::: 1.11 in/hr l100:::::: 7.11 in/hr Q100 = 0.85 x 7.11 in/hr x 1.555 Ac= 9.4 cfs **Total Pre-Development (Discharge Leaving Site): Basin EX-1 Q100 = 16.54 cfs Basin EX-2 Q100 = 15.86 cfs Basin EX-3 Qrno = 11.09 cfs Basin EX-4 Q100 = 9.4 cfs PLSA 3140-02 Total Q100 = 49.69 cfs (all 4 streams were confluenced using AES for total peak flow) Tc= 6.29 min **Note: Offsite 100-year storm discharge from McClellan-Palomar Airport through the site per City of Carlsbad DWG 241-6 was determined to be ~30.2 cfs (published HGL of 1.3' above invert for 36-inch RCP storm drain at 2.5% slope). This flow was not considered in the overall pre-vs post-development conditions in order to compare the peak discharge generated by the proposed onsite improvements only. Page 10 of 13 3140EX00.txt **************************************************************************** RATIONAL METHOD HYDROLOGY COMPUTER PROGRAM PACKAGE Reference: SAN DIEGO COUNTY FLOOD CONTROL DISTRICT 2003,1985,1981 HYDROLOGY MANUAL (c) Copyright 1982-2016 Advanced Engineering Software (aes) Ver. 23.0 Release Date: 07/01/2016 License ID 1452 Analysis prepared by: PASCO LARET SUITER & ASSOCIATES 535 NORTH HIGHWAY 101, STE A SOLANA BEACH, CA 92075 858-259-8212 ************************** DESCRIPTION OF STUDY************************** * 3140 RAF PACIFICA GROUP FUSION -OUTDOOR AMENITY AREA * * ONSITE EXISTING CONDITION * * 100-YR * ************************************************************************** FILE NAME: 3140EX00.DAT TIME/DATE OF STUDY: 10:50 04/21/2020 USER SPECIFIED HYDROLOGY AND HYDRAULIC MODEL INFORMATION: 2003 SAN DIEGO MANUAL CRITERIA USER SPECIFIED STORM EVENT(YEAR) = 100.00 6-HOUR DURATION PRECIPITATION (INCHES)= 2.700 SPECIFIED MINIMUM PIPE SIZE(INCH) = 4.00 SPECIFIED PERCENT OF GRADIENTS(DECIMAL) TO USE FOR FRICTION SLOPE= 0.90 SAN DIEGO HYDROLOGY MANUAL "("-VALUES USED FOR RATIONAL METHOD NOTE: USE MODIFIED RATIONAL METHOD PROCEDURES FOR CONFLUENCE ANALYSIS *USER-DEFINED STREET-SECTIONS FOR COUPLED PIPEFLOW AND STREETFLOW MODEL* HALF-CROWN TO STREET-CROSSFALL: CURB GUTTER-GEOMETRIES: MANNING WIDTH CROSSFALL IN-/ OUT-/PARK-HEIGHT WIDTH LIP HIKE FACTOR NO. (FT) (FT) SIDE/ SIDE/ WAY (FT) (FT) (FT) (FT) (n) ====== ====== ======= 1 30.0 20.0 0.018/0.018/0.020 0.67 2.00 0.0313 0.167 0.0150 GLOBAL STREET FLOW-DEPTH CONSTRAINTS: 1. Relative Flow-Depth= 0.00 FEET as (Maximum Allowable Street Flow Depth) -(Top-of-Curb) Page 1 3140EX00.txt 2. (Depth)*(Velocity) Constraint= 6.0 (FT*FT/S) *SIZE PIPE WITH A FLOW CAPACITY GREATER THAN OR EQUAL TO THE UPSTREAM TRIBUTARY PIPE.* **************************************************************************** FLOW PROCESS FROM NODE 100.00 TO NODE 101.00 IS CODE= 21 >>>>>RATIONAL METHOD INITIAL SUBAREA ANALYSIS<<<<< *USER SPECIFIED(SUBAREA): USER-SPECIFIED RUNOFF COEFFICIENT= .3500 S.C.S. CURVE NUMBER (AMC II)= 0 INITIAL SUBAREA FLOW-LENGTH(FEET) = 75.00 UPSTREAM ELEVATION(FEET) = 292.00 DOWNSTREAM ELEVATION(FEET) = 257.24 ELEVATION DIFFERENCE(FEET) = 34.76 SUBAREA OVERLAND TIME OF FLOW(MIN.) = 5.427 WARNING: THE MAXIMUM OVERLAND FLOW SLOPE, 10.%, IS USED IN Tc CALCULATION! 100 YEAR RAINFALL INTENSITY(INCH/HOUR) = 6.747 SUBAREA RUNOFF(CFS) = 0.32 TOTAL AREA(ACRES) = 0.14 TOTAL RUNOFF(CFS) = 0.32 **************************************************************************** FLOW PROCESS FROM NODE 101.00 TO NODE 102.00 IS CODE= 31 >>>>>COMPUTE PIPE-FLOW TRAVEL TIME THRU SUBAREA<<<<< >>>>>USING COMPUTER-ESTIMATED PIPESIZE (NON-PRESSURE FLOW)<<<<< ELEVATION DATA: UPSTREAM(FEET) = 257.24 DOWNSTREAM(FEET) = 255.00 FLOW LENGTH(FEET) = 198.00 MANNING'S N = 0.015 DEPTH OF FLOW IN 6.0 INCH PIPE IS 3.6 INCHES PIPE-FLOW VELOCITY(FEET/SEC.) = 2.64 ESTIMATED PIPE DIAMETER(INCH) = 6.00 NUMBER OF PIPES= 1 PIPE-FLOW(CFS) = 0.32 PIPE TRAVEL TIME(MIN.) = 1.25 Tc(MIN.) = 6.68 LONGEST FLOWPATH FROM NODE 100.00 TO NODE 102.00 = 273.00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 101.00 TO NODE 102.00 IS CODE= 81 >>>>>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW<<<<< 100 YEAR RAINFALL INTENSITY(INCH/HOUR) = 5.903 *USER SPECIFIED(SUBAREA): USER-SPECIFIED RUNOFF COEFFICIENT= .3500 S.C.S. CURVE NUMBER (AMC II)= 0 AREA-AVERAGE RUNOFF COEFFICIENT= 0.3500 SUBAREA AREA(ACRES) = 0.66 SUBAREA RUNOFF(CFS) = 1.36 Page 2 3140EX00.txt TOTAL AREA(ACRES) = 0.8 TOTAL RUNOFF(CFS) = 1.64 TC(MIN.) = 6.68 **************************************************************************** FLOW PROCESS FROM NODE 102.00 TO NODE 103.00 IS CODE= 31 >>>>>COMPUTE PIPE-FLOW TRAVEL TIME THRU SUBAREA<<<<< >>>>>USING COMPUTER-ESTIMATED PIPESIZE (NON-PRESSURE FLOW)<<<<< ELEVATION DATA: UPSTREAM(FEET) = 250.50 DOWNSTREAM(FEET) = 246.10 FLOW LENGTH(FEET) = 65.00 MANNING'S N = 0.013 DEPTH OF FLOW IN 9.0 INCH PIPE IS 4.0 INCHES PIPE-FLOW VELOCITY(FEET/SEC.) = 8.77 ESTIMATED PIPE DIAMETER(INCH) = 9.00 NUMBER OF PIPES= 1 PIPE-FLOW(CFS) = 1.64 PIPE TRAVEL TIME(MIN.) = 0.12 Tc(MIN.) = 6.80 LONGEST FLOWPATH FROM NODE 100.00 TO NODE 103.00 = 338.00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 103.00 TO NODE 104.00 IS CODE= 31 >>>>>COMPUTE PIPE-FLOW TRAVEL TIME THRU SUBAREA<<<<< >>>>>USING COMPUTER-ESTIMATED PIPESIZE (NON-PRESSURE FLOW)<<<<< ===============---=====-----====-------===---------------------------------- ELEVATION DATA: UPSTREAM(FEET) = 246.10 DOWNSTREAM(FEET) = 242.50 FLOW LENGTH(FEET) = 355.00 MANNING'S N = 0.013 DEPTH OF FLOW IN 12.0 INCH PIPE IS 5.9 INCHES PIPE-FLOW VELOCITY(FEET/SEC.) = 4.31 ESTIMATED PIPE DIAMETER(INCH) = 12.00 NUMBER OF PIPES= 1 PIPE-FLOW(CFS) = 1.64 PIPE TRAVEL TIME(MIN.) = 1.37 Tc(MIN.) = 8.17 LONGEST FLOWPATH FROM NODE 100.00 TO NODE 104.00 = 693.00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 104.00 TO NODE 105.00 IS CODE= 31 >>>>>COMPUTE PIPE-FLOW TRAVEL TIME THRU SUBAREA<<<<< >>>>>USING COMPUTER-ESTIMATED PIPESIZE (NON-PRESSURE FLOW)<<<<< ELEVATION DATA: UPSTREAM(FEET) = 242.50 DOWNSTREAM(FEET) = FLOW LENGTH(FEET) = 125.00 MANNING'S N = 0.013 DEPTH OF FLOW IN 12.0 INCH PIPE IS 5.9 INCHES PIPE-FLOW VELOCITY(FEET/SEC.) = 4.28 ESTIMATED PIPE DIAMETER(INCH) = 12.00 PIPE-FLOW(CFS) = 1.64 NUMBER OF PIPES= PIPE TRAVEL TIME(MIN.) = 0.49 Tc(MIN.) = 1 241.25 LONGEST FLOWPATH FROM NODE 100.00 TO NODE 8.66 105.00 = 818.00 FEET. Page 3 3140EX00.txt **************************************************************************** FLOW PROCESS FROM NODE 105.00 TO NODE 105.00 IS CODE= 1 >>>>>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE<<<<< TOTAL NUMBER OF STREAMS= 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: TIME OF CONCENTRATION(MIN.) = 8.66 RAINFALL INTENSITY(INCH/HR) = 4.99 TOTAL STREAM AREA(ACRES) = 0.79 PEAK FLOW RATE(CFS) AT CONFLUENCE= 1.64 **************************************************************************** FLOW PROCESS FROM NODE 120.00 TO NODE 121.00 IS CODE= 21 >>>>>RATIONAL METHOD INITIAL SUBAREA ANALYSIS<<<<< *USER SPECIFIED(SUBAREA): USER-SPECIFIED RUNOFF COEFFICIENT= .8500 S.C.S. CURVE NUMBER (AMC II)= 0 INITIAL SUBAREA FLOW-LENGTH(FEET) = 100.00 UPSTREAM ELEVATION(FEET) = 254.70 DOWNSTREAM ELEVATION(FEET) = 252.00 ELEVATION DIFFERENCE(FEET) = 2.70 SUBAREA OVERLAND TIME OF FLOW(MIN.) = 2.836 WARNING: INITIAL SUBAREA FLOW PATH LENGTH IS GREATER THAN THE MAXIMUM OVERLAND FLOW LENGTH= 77.00 (Reference: Table 3-18 of Hydrology Manual) THE MAXIMUM OVERLAND FLOW LENGTH IS USED IN Tc CALCULATION! 100 YEAR RAINFALL INTENSITY(INCH/HOUR) = 7.114 NOTE: RAINFALL INTENSITY IS BASED ON Tc= 5-MINUTE. SUBAREA RUNOFF(CFS) = 0.79 TOTAL AREA(ACRES) = 0.13 TOTAL RUNOFF(CFS) = 0.79 **************************************************************************** FLOW PROCESS FROM NODE 121.00 TO NODE 122.00 IS CODE= 51 >>>>>COMPUTE TRAPEZOIDAL CHANNEL FLOW<<<<< >>>>>TRAVELTIME THRU SUBAREA (EXISTING ELEMENT)<<<<< ELEVATION DATA: UPSTREAM(FEET) = 252.00 DOWNSTREAM(FEET) = 246.00 CHANNEL LENGTH THRU SUBAREA(FEET) = 625.00 CHANNEL SLOPE= 0.0096 CHANNEL BASE(FEET) = 3.00 "Z" FACTOR= 20.000 MANNING'S FACTOR= 0.015 MAXIMUM DEPTH(FEET) = 1.00 100 YEAR RAINFALL INTENSITY(INCH/HOUR) = 6.200 *USER SPECIFIED(SUBAREA): USER-SPECIFIED RUNOFF COEFFICIENT= .8500 S.C.S. CURVE NUMBER (AMC II)= 0 Page 4 3140EX00.txt TRAVEL TIME COMPUTED USING ESTIMATED FLOW(CFS) = 8.14 TRAVEL TIME THRU SUBAREA BASED ON VELOCITY(FEET/SEC.) = 3.11 AVERAGE FLOW DEPTH(FEET) = 0.29 TRAVEL TIME(MIN.) = 3.35 Tc(MIN.) = 6.19 SUBAREA AREA(ACRES) = 2.79 SUBAREA RUNOFF(CFS) = 14.68 AREA-AVERAGE RUNOFF COEFFICIENT= 0.850 TOTAL AREA(ACRES) = 2.9 PEAK FLOW RATE(CFS) = 15.36 END OF SUBAREA CHANNEL FLOW HYDRAULICS: DEPTH(FEET) = 0.39 FLOW VELOCITY(FEET/SEC.) = 3.62 LONGEST FLOWPATH FROM NODE 120.00 TO NODE 122.00 = 725. 00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 122.00 TO NODE 105.00 IS CODE= 1 >>>>>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE<<<<< >>>>>AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES<<<<< TOTAL NUMBER OF STREAMS= 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 6.19 RAINFALL INTENSITY(INCH/HR) = 6.20 TOTAL STREAM AREA(ACRES) = 2.91 PEAK FLOW RATE(CFS) AT CONFLUENCE= 15.36 ** CONFLUENCE DATA ** STREAM RUNOFF Tc INTENSITY AREA NUMBER (CFS) (MIN.) (INCH/HOUR) (ACRE) 1 1.64 8.66 4.991 0.79 2 15.36 6.19 6.200 2.91 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 2 STREAMS. ** PEAK FLOW RATE TABLE ** STREAM RUNOFF Tc INTENSITY NUMBER (CFS) (MIN.) (INCH/HOUR) 1 16.54 6.19 6.200 2 14.01 8.66 4.991 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 16.54 Tc(MIN.) = 6.19 TOTAL AREA(ACRES) = 3.7 LONGEST FLOWPATH FROM NODE 100.00 TO NODE 105.00 = 818.00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 105.00 TO NODE 106.00 IS CODE= 31 Page 5 3140EX00.txt >>>>>COMPUTE PIPE-FLOW TRAVEL TIME THRU SUBAREA<<<<< >>>>>USING COMPUTER-ESTIMATED PIPESIZE (NON-PRESSURE FLOW)<<<<< ELEVATION DATA: UPSTREAM(FEET) = 241.25 DOWNSTREAM(FEET) = 239.90 FLOW LENGTH(FEET) = 30.00 MANNING'S N = 0.013 DEPTH OF FLOW IN 18.0 INCH PIPE IS 12.0 INCHES PIPE-FLOW VELOCITY(FEET/SEC.) = 13.26 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES= 1 PIPE-FLOW(CFS) = 16.54 PIPE TRAVEL TIME(MIN.) = 0.04 Tc(MIN.) = 6.23 LONGEST FLOWPATH FROM NODE 100.00 TO NODE 106.00 = 848.00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 106.00 TO NODE 106.00 IS CODE= 10 >>>>>MAIN-STREAM MEMORY COPIED ONTO MEMORY BANK# 1 <<<<< **************************************************************************** FLOW PROCESS FROM NODE 250.00 TO NODE 251.00 IS CODE= 21 >>>>>RATIONAL METHOD INITIAL SUBAREA ANALYSIS<<<<< *USER SPECIFIED(SUBAREA): USER-SPECIFIED RUNOFF COEFFICIENT= .8500 S.C.S. CURVE NUMBER (AMC II)= 0 INITIAL SUBAREA FLOW-LENGTH(FEET) = 100.00 UPSTREAM ELEVATION(FEET) = 253.70 DOWNSTREAM ELEVATION(FEET) = 248.10 ELEVATION DIFFERENCE(FEET) = 5.60 SUBAREA OVERLAND TIME OF FLOW(MIN.) = 2.420 WARNING: INITIAL SUBAREA FLOW PATH LENGTH IS GREATER THAN THE MAXIMUM OVERLAND FLOW LENGTH= 91.20 (Reference: Table 3-lB of Hydrology Manual) THE MAXIMUM OVERLAND FLOW LENGTH IS USED IN Tc CALCULATION! 100 YEAR RAINFALL INTENSITY(INCH/HOUR) = 7.114 NOTE: RAINFALL INTENSITY IS BASED ON Tc= 5-MINUTE. SUBAREA RUNOFF(CFS) = 1.71 TOTAL AREA(ACRES) = 0.28 TOTAL RUNOFF(CFS) = 1.71 **************************************************************************** FLOW PROCESS FROM NODE 250.00 TO NODE 251.00 IS CODE= 22 >>>>>RATIONAL METHOD INITIAL SUBAREA ANALYSIS<<<<< *USER SPECIFIED(SUBAREA): USER-SPECIFIED RUNOFF COEFFICIENT= .8500 S.C.S. CURVE NUMBER (AMC II)= 0 Page 6 3140EX00.txt USER SPECIFIED Tc(MIN.) = 5.000 100 YEAR RAINFALL INTENSITY(INCH/HOUR) = 7.114 SUBAREA RUNOFF(CFS) = 1.71 TOTAL AREA(ACRES) = 0.28 TOTAL RUNOFF(CFS) = 1.71 **************************************************************************** FLOW PROCESS FROM NODE 251.00 TO NODE 252.00 IS CODE= 31 >>>>>COMPUTE PIPE-FLOW TRAVEL TIME THRU SUBAREA<<<<< >>>>>USING COMPUTER-ESTIMATED PIPESIZE (NON-PRESSURE FLOW)<<<<< ELEVATION DATA: UPSTREAM(FEET) = 246.40 DOWNSTREAM(FEET) = FLOW LENGTH(FEET) = 240.00 MANNING'S N = 0.013 DEPTH OF FLOW IN 9.0 INCH PIPE IS 6.8 INCHES PIPE-FLOW VELOCITY(FEET/SEC.) = 4.74 ESTIMATED PIPE DIAMETER(INCH) = 9.00 PIPE-FLOW(CFS) = 1.71 NUMBER OF PIPES= PIPE TRAVEL TIME(MIN.) = 0.84 Tc(MIN.) = 1 243.10 LONGEST FLOWPATH FROM NODE 250.00 TO NODE 5.84 252.00 = 240.00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 251.00 TO NODE 252.00 IS CODE= 81 >>>>>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW<<<<< 100 YEAR RAINFALL INTENSITY(INCH/HOUR) = 6.433 *USER SPECIFIED(SUBAREA): USER-SPECIFIED RUNOFF COEFFICIENT= .8500 S.C.S. CURVE NUMBER (AMC II)= 0 AREA-AVERAGE RUNOFF COEFFICIENT= 0.8500 SUBAREA AREA(ACRES) = 1.46 SUBAREA RUNOFF(CFS) = TOTAL AREA(ACRES) = 1.7 TOTAL RUNOFF(CFS) = TC(MIN.) = 5.84 8.00 9.54 **************************************************************************** FLOW PROCESS FROM NODE 252.00 TO NODE 253.00 IS CODE= 31 >>>>>COMPUTE PIPE-FLOW TRAVEL TIME THRU SUBAREA<<<<< >>>>>USING COMPUTER-ESTIMATED PIPESIZE (NON-PRESSURE FLOW)<<<<< ELEVATION DATA: UPSTREAM(FEET) = 243.10 DOWNSTREAM(FEET) = FLOW LENGTH(FEET) = 125.00 MANNING'S N = 0.013 DEPTH OF FLOW IN 15.0 INCH PIPE IS 10.7 INCHES PIPE-FLOW VELOCITY(FEET/SEC.) = 10.19 ESTIMATED PIPE DIAMETER(INCH) = 15.00 PIPE-FLOW(CFS) = 9.54 NUMBER OF PIPES= PIPE TRAVEL TIME(MIN.) = 0.20 Tc(MIN.) = 1 239.00 LONGEST FLOWPATH FROM NODE 250.00 TO NODE 6.05 253.00 = 365.00 FEET. Page 7 3140EX00.txt **************************************************************************** FLOW PROCESS FROM NODE 253.00 TO NODE 254.00 IS CODE= 31 >>>>>COMPUTE PIPE-FLOW TRAVEL TIME THRU SUBAREA<<<<< >>>>>USING COMPUTER-ESTIMATED PIPESIZE (NON-PRESSURE FLOW)<<<<< -=-------------------------------------------------------------------------- ELEVATION DATA: UPSTREAM(FEET) = 239.00 DOWNSTREAM(FEET) = 236.20 FLOW LENGTH(FEET) = 105.00 MANNING'S N = 0.013 DEPTH OF FLOW IN 15.0 INCH PIPE IS 11.7 INCHES PIPE-FLOW VELOCITY(FEET/SEC.) = 9.30 ESTIMATED PIPE DIAMETER(INCH) = 15.00 NUMBER OF PIPES= 1 PIPE-FLOW(CFS) = 9.54 PIPE TRAVEL TIME(MIN.) = 0.19 Tc(MIN.) = 6.24 LONGEST FLOWPATH FROM NODE 250.00 TO NODE 254.00 = 470.00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 252.00 TO NODE 254.00 IS CODE= 81 >>>>>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW<<<<< 100 YEAR RAINFALL INTENSITY(INCH/HOUR) = 6.169 *USER SPECIFIED(SUBAREA): USER-SPECIFIED RUNOFF COEFFICIENT= .8500 S.C.S. CURVE NUMBER (AMC II)= 0 AREA-AVERAGE RUNOFF COEFFICIENT= 0.8500 SUBAREA AREA(ACRES) = 1.28 SUBAREA RUNOFF(CFS) = TOTAL AREA(ACRES) = 3.0 TOTAL RUNOFF(CFS) = TC(MIN.) = 6.24 6.71 15.86 **************************************************************************** FLOW PROCESS FROM NODE 254.00 TO NODE 255.00 IS CODE= 31 >>>>>COMPUTE PIPE-FLOW TRAVEL TIME THRU SUBAREA<<<<< >>>>>USING COMPUTER-ESTIMATED PIPESIZE (NON-PRESSURE FLOW)<<<<< ELEVATION DATA: UPSTREAM(FEET) = 236.20 DOWNSTREAM(FEET) 216.70 FLOW LENGTH(FEET) = 75.00 MANNING'S N = 0.013 DEPTH OF FLOW IN 12.0 INCH PIPE IS 9.1 INCHES PIPE-FLOW VELOCITY(FEET/SEC.) = 24.95 ESTIMATED PIPE DIAMETER(INCH) = 12.00 NUMBER OF PIPES= 1 PIPE-FLOW(CFS) = 15.86 PIPE TRAVEL TIME(MIN.) = 0.05 Tc(MIN.) = 6.29 LONGEST FLOWPATH FROM NODE 250.00 TO NODE 255.00 = 545.00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 106.00 TO NODE 255.00 IS CODE= 11 Page 8 3140EX00.txt >>>>>CONFLUENCE MEMORY BANK# 1 WITH THE MAIN-STREAM MEMORY<<<<< =--------------------------------------------------------------------------- ** MAIN STREAM CONFLUENCE DATA** STREAM RUNOFF Tc INTENSITY AREA NUMBER (CFS) (MIN.) (INCH/HOUR) (ACRE) 1 15.86 6.29 6.137 3.03 LONGEST FLOWPATH FROM NODE 250.00 TO NODE 255.00 = 545.00 FEET. ** MEMORY BANK# 1 CONFLUENCE DATA** STREAM RUNOFF Tc INTENSITY AREA NUMBER (CFS) (MIN.) (INCH/HOUR) (ACRE) 1 16.54 6.23 6.176 3.71 LONGEST FLOWPATH FROM NODE 100.00 TO NODE 255.00 = 848.00 FEET. ** PEAK FLOW RATE TABLE** STREAM RUNOFF Tc INTENSITY NUMBER (CFS) (MIN.) (INCH/HOUR) 1 32.25 6.23 6.176 2 32.30 6.29 6.137 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 32.30 Tc(MIN.) = 6.29 TOTAL AREA(ACRES) = 6.7 **************************************************************************** FLOW PROCESS FROM NODE 106.00 TO NODE 255.00 IS CODE= 12 >>>>>CLEAR MEMORY BANK# 1 <<<<< =-------=------------------------------------------------------------------- **************************************************************************** FLOW PROCESS FROM NODE 255.00 TO NODE 255.00 IS CODE= 10 >>>>>MAIN-STREAM MEMORY COPIED ONTO MEMORY BANK# 1 <<<<< **************************************************************************** FLOW PROCESS FROM NODE 300.00 TO NODE 301.00 IS CODE= 21 >>>>>RATIONAL METHOD INITIAL SUBAREA ANALYSIS<<<<< ===-----===-------==-------------------------------------------------------- *USER SPECIFIED(SUBAREA): USER-SPECIFIED RUNOFF COEFFICIENT= .3500 S.C.S. CURVE NUMBER (AMC II)= 0 INITIAL SUBAREA FLOW-LENGTH(FEET) = 100.00 UPSTREAM ELEVATION(FEET) = 298.00 DOWNSTREAM ELEVATION(FEET) = 267.50 Page 9 3140EX00.txt ELEVATION DIFFERENCE(FEET) = 30.50 SUBAREA OVERLAND TIME OF FLOW(MIN.) = 6.267 WARNING: THE MAXIMUM OVERLAND FLOW SLOPE, 10.%, IS USED IN Tc CALCULATION! 100 YEAR RAINFALL INTENSITY(INCH/HOUR) = 6.150 SUBAREA RUNOFF(CFS) = 1.08 TOTAL AREA(ACRES) = 0.50 TOTAL RUNOFF(CFS) = 1.08 **************************************************************************** FLOW PROCESS FROM NODE 301.00 TO NODE 302.00 IS CODE= 51 >>>>>COMPUTE TRAPEZOIDAL CHANNEL FLOW<<<<< >>>>>TRAVELTIME THRU SUBAREA (EXISTING ELEMENT)<<<<< ELEVATION DATA: UPSTREAM(FEET) = 267.50 DOWNSTREAM(FEET) = 249.80 CHANNEL LENGTH THRU SUBAREA(FEET) = 340.00 CHANNEL SLOPE= 0.0521 CHANNEL BASE(FEET) = 3.00 "Z" FACTOR= 20.000 MANNING'S FACTOR= 0.015 MAXIMUM DEPTH(FEET) = 1.00 100 YEAR RAINFALL INTENSITY(INCH/HOUR) = 5.568 *USER SPECIFIED(SUBAREA): USER-SPECIFIED RUNOFF COEFFICIENT= .8500 S.C.S. CURVE NUMBER (AMC II)= 0 TRAVEL TIME COMPUTED USING ESTIMATED FLOW(CFS) = 6.05 TRAVEL TIME THRU SUBAREA BASED ON VELOCITY(FEET/SEC.) = 5.43 AVERAGE FLOW DEPTH(FEET) = 0.17 TRAVEL TIME(MIN.) = 1.04 Tc(MIN.) = 7.31 SUBAREA AREA(ACRES) = 2.14 SUBAREA RUNOFF(CFS) = 10.12 AREA-AVERAGE RUNOFF COEFFICIENT= 0.755 TOTAL AREA(ACRES) = 2.6 PEAK FLOW RATE(CFS) = 11.09 END OF SUBAREA CHANNEL FLOW HYDRAULICS: DEPTH(FEET) = 0.23 FLOW VELOCITY(FEET/SEC.) = 6.19 LONGEST FLOWPATH FROM NODE 300.00 TO NODE 302.00 = 440.00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 302.00 TO NODE 303.00 IS CODE= 31 >>>>>COMPUTE PIPE-FLOW TRAVEL TIME THRU SUBAREA<<<<< >>>>>USING COMPUTER-ESTIMATED PIPESIZE (NON-PRESSURE FLOW)<<<<< ELEVATION DATA: UPSTREAM(FEET) = 244.10 DOWNSTREAM(FEET) = 241.70 FLOW LENGTH(FEET) = 87.00 MANNING'S N = 0.013 DEPTH OF FLOW IN 18.0 INCH PIPE IS 10.8 INCHES PIPE-FLOW VELOCITY(FEET/SEC.) = 10.06 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES= 1 PIPE-FLOW(CFS) = 11.09 PIPE TRAVEL TIME(MIN.) = 0.14 Tc(MIN.) = 7.45 LONGEST FLOWPATH FROM NODE 300.00 TO NODE 303.00 = 527.00 FEET. Page 10 3140EX00.txt **************************************************************************** FLOW PROCESS FROM NODE 303.00 TO NODE 304.00 IS CODE= 31 >>>>>COMPUTE PIPE-FLOW TRAVEL TIME THRU SUBAREA<<<<< >>>>>USING COMPUTER-ESTIMATED PIPESIZE (NON-PRESSURE FLOW)<<<<< ELEVATION DATA: UPSTREAM(FEET) = 241.70 DOWNSTREAM(FEET) = 222.00 FLOW LENGTH(FEET) = 75.00 MANNING'S N = 0.013 DEPTH OF FLOW IN 12.0 INCH PIPE IS 7.0 INCHES PIPE-FLOW VELOCITY(FEET/SEC.) = 23.45 ESTIMATED PIPE DIAMETER(INCH) = 12.00 NUMBER OF PIPES= 1 PIPE-FLOW(CFS) = 11.09 PIPE TRAVEL TIME(MIN.) = 0.05 Tc(MIN.) = 7.51 LONGEST FLOWPATH FROM NODE 300.00 TO NODE 304.00 = 602.00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 255.00 TO NODE 304.00 IS CODE= 11 >>>>>CONFLUENCE MEMORY BANK# 1 WITH THE MAIN-STREAM MEMORY<<<<< ** MAIN STREAM CONFLUENCE DATA** STREAM RUNOFF Tc INTENSITY NUMBER (CFS) (MIN.) (INCH/HOUR) 1 11.09 7.51 5.473 LONGEST FLOWPATH FROM NODE 300.00 TO NODE ** MEMORY BANK# 1 CONFLUENCE DATA** STREAM NUMBER 1 LONGEST ** PEAK STREAM NUMBER 1 2 RUNOFF Tc (CFS) (MIN.) 32.30 6.29 FLOWPATH FROM NODE FLOW RATE TABLE** RUNOFF Tc (CFS) (MIN.) 41.58 6.29 39.89 7.51 INTENSITY (INCH/HOUR) 6.137 100.00 TO NODE INTENSITY (INCH/HOUR) 6.137 5.473 AREA (ACRE) 2.64 304.00 AREA (ACRE) 6.74 304.00 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 41.58 Tc(MIN.) = 6.29 TOTAL AREA(ACRES) = 9.4 = 602.00 FEET. = 848.00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 304.00 TO NODE 304.00 IS CODE= 1 >>>>>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE<<<<< Page 11 3140EX00.txt TOTAL NUMBER OF STREAMS= 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: TIME OF CONCENTRATION(MIN.) = 6.29 RAINFALL INTENSITY(INCH/HR) = 6.14 TOTAL STREAM AREA(ACRES) = 9.37 PEAK FLOW RATE(CFS) AT CONFLUENCE= 41.58 **************************************************************************** FLOW PROCESS FROM NODE 4.00 TO NODE 4.00 IS CODE= 7 >>>>>USER SPECIFIED HYDROLOGY INFORMATION AT NODE<<<<< USER-SPECIFIED VALUES ARE AS FOLLOWS: TC(MIN) = 5.00 RAIN INTENSITY(INCH/HOUR) = 7.11 TOTAL AREA(ACRES) = 1.55 TOTAL RUNOFF(CFS) = 9.40 **************************************************************************** FLOW PROCESS FROM NODE 4.00 TO NODE 304.00 IS CODE= 1 >>>>>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE<<<<< >>>>>AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES<<<<< TOTAL NUMBER OF STREAMS= 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 5.00 RAINFALL INTENSITY(INCH/HR) = 7.11 TOTAL STREAM AREA(ACRES) = 1.55 PEAK FLOW RATE(CFS) AT CONFLUENCE= 9.40 ** CONFLUENCE DATA ** STREAM RUNOFF Tc INTENSITY AREA NUMBER (CFS) (MIN.) (INCH/HOUR) (ACRE) 1 41.58 6.29 6.137 9.37 2 9.40 5.00 7.114 1. 55 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 2 STREAMS. ** PEAK FLOW RATE TABLE ** STREAM RUNOFF Tc INTENSITY NUMBER (CFS) (MIN.) (INCH/HOUR) 1 42.48 5.00 7.114 2 49.69 6.29 6.137 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 49.69 Tc(MIN.) = 6.29 TOTAL AREA(ACRES) = 10.9 LONGEST FLOWPATH FROM NODE 100.00 TO NODE 304.00 = Page 12 848.00 FEET. END OF STUDY SUMMARY: TOTAL AREA(ACRES) = PEAK FLOW RATE(CFS) = 3140EX00.txt 10.9 TC(MIN.) = 49.69 END OF RATIONAL METHOD ANALYSIS Page 13 6.29 3.2 Post-Developed Hydrologic Model Output (100-Year Event) Post-Development (without considering HMP/BMP treatment): *Rational Method Equation PLSA 3140-02 Q=CIA P100= 2.7 * 100-Year, 6-Hour Rainfall Precipitation Total Proiect Site Total Area= 477,340 sf-+ 10.958 Acres Impervious Area= 329,460 sf-+ 7.563 Acres Pervious Area= 147,880 sf-+ 3.395 Acres C, Runoff Coefficient for Urban Areas based on Land Use, -0.85, C value per SDHDM Table 3-1 *Type D Soils, Office Professional / Commercial and Limited Industrial Land Use per City of Carlsbad zoning map (Planned Industrial P-M) -0.35, C value per SDHDM Table 3-1 *Type D Soils, Permanent Open Space for Initial Overland Flow Basin EX-1 Total Area= 161,570 sf-+ 3.71 Acres Total Area Basin EX-1. 1 = 34,617 sf ➔ 0.795 Acres C = 0.85 Total Area Basin EX-1.2 = 126,953 sf ➔ 2.914 Acres C = 0.85 Peak Discharge: Tc= 6.24 min (See attached A.E.S. analysis for details) Qrno = 16.53 cfs (See attached A.E.S. analysis for details) A= 3.7 Acres Basin PR-1 Total Area= 127,865 sf-+ 2.94 Acres Total Area Basin PR-1.1 = 1.65 Acres C = 0.85 Total Area Basin PR-1.2 = 1.19 Acres C = 0.85 Total Area Basin PR-1.3 = 0.10 Acres C = 0.85 Peak Discharge: Tc-PR-1.1 = 6.50 min, Tc-PR-1.2 = 4.53 min (See attached A.E.S. analysis for details) Qrno-PR-1.1 = 8.60 cfs, Q100-PR-1.2 = 7.60 cfs (See attached A.E.S. analysis for details) AToT = 2.9 Acres Page 11 of 13 Basin PR-2 Total Area= 119,560 sf-+ 2.75 Acres C = 0.85 Peak Discharge: Tc= 7.71 min (See attached A.E.S. analysis for details) Q100 = 11.14 cfs (See attached A.E.S. analysis for details) A= 2.75 Acres Basin PR-3 Total Area= 66,690 sf-+ 1.530 Acres C = 0.85 Tc= 5.0 Min (minimum for small areas) P6= 2.7 1 = 7.44 x P6 x D-0645 1 = 7.44 x 2.1 x 5.o-0645 ~ 1.11 in/hr l100~ 7.11 in/hr Q100 = 0.85 x 7.11 in/hr x 1.530 Ac= 9.25 cfs **Total Post-Development (Discharge Leaving Site): Basin EX-1 Q100 = 16.53 cfs Basin PR-1.1 Q100 = 8.60 cfs Basin PR-1.2 0100 = 7.60 cfs Basin PR-1 Q100 (PR-1.1 + PR-1.2 + PR-1.3) = Basin PR-2 Qrno = 11.14 cfs Basin PR-3 Q100 = 9.25 cfs PLSA 3140-02 Total Q100 = 48.25 cfs (all 4 streams were confluenced using AES for total peak flow) Tc= 6.56 min **Note: Offsite 100-year storm discharge from McClellan-Palomar Airport through the site per City of Carlsbad DWG 241-6 was determined to be ~30.2 cfs (published HGL of 1.3' above invert for 36-inch RCP storm drain at 2.5% slope). This flow was not considered in the overall pre-vs post-development conditions in order to compare the peak discharge generated by the proposed onsite improvements only. Pre-Development vs. Post-Development (Discharge Leaving Site): Pre-Development Q100 = 49.69 cfs Post-Development Q100 = 48.25 cfs Delta -1.44 cfs Page 12 of 13 PLSA 3140-02 3.3 Detention Analysis (100-Y ear Event) The onsite biofiltation basin BMP provides pollutant control, hydromodification management to satisfy requirements of the MS4 Permit (See brief discussion in Section 3.4 below and Storm Water Quality Management Plan under separate cover for HMP analysis), as well as mitigation of the 100-year, 6-hour storm event peak flow rate. HydroCAD-10 has the ability to route the 100-year, 6-hour storm event inflow hydrograph (generated and modeled using RatHydro, which is a Rational Method Design Storm Hydrograph software that creates a hydrograph using the results of the Rational Method calculations) through the biofiltration BMP facility. Based on the BMP cross- section geometry, incremental stage-storage volume, and outlet structure data, HydroCAD-10 has the ability to calculate the detained peak flow rate and detained time to peak. However, it was determined from the results of the Rational Method analysis comparing post-developed peak flows to the existing site conditions that runoff is reduced in the proposed condition, and thus an additional 100-year, 6-hour storm detention analysis was not performed. It can be assumed that the proposed biofiltration basin further assists to mitigate peak runoff generated by the proposed outdoor amenity area to values well beneath pre-project conditions. 3.4 Hydromodification Analysis Refer to the project Storm Water Quality Management Plan prepared by Pasco, Laret, Suiter & Associates under separate cover for discussion of hydromodification management strategy and compliance to satisfy the requirements of the MS4 Permit. 3.5 Storm Water Pollutant Control To meet the requirements of the MS4 Permit, the HMP biofiltration facility is designed to treat onsite storm water pollutants contained in the volume of runoff from a 24-hour, 85th percentile storm event by filtering runoff through an engineered soil layer and gravel layer. Refer to the project Storm Water Quality Management Plan prepared by Pasco, Laret, Suiter & Associates under separate cover for discussion of pollutant control. Page 13 of 13 3140EXPR.TXT **************************************************************************** RATIONAL METHOD HYDROLOGY COMPUTER PROGRAM PACKAGE Reference: SAN DIEGO COUNTY FLOOD CONTROL DISTRICT 2003,1985,1981 HYDROLOGY MANUAL (c) Copyright 1982-2016 Advanced Engineering Software (aes) Ver. 23.0 Release Date: 07/01/2016 License ID 1452 Analysis prepared by: PASCO LARET SUITER & ASSOCIATES 535 NORTH HIGHWAY 101, STE A SOLANA BEACH, CA 92075 858-259-8212 ************************** DESCRIPTION OF STUDY************************** * 3140 RAF PACIFICA GROUP FUSION -OUTDOOR AMENITY AREA * * ONSITE PROPOSED CONDITION * * 100-YR * ************************************************************************** FILE NAME: 3140EXPR.DAT TIME/DATE OF STUDY: 14:10 04/22/2020 USER SPECIFIED HYDROLOGY AND HYDRAULIC MODEL INFORMATION: 2003 SAN DIEGO MANUAL CRITERIA USER SPECIFIED STORM EVENT(YEAR) = 100.00 6-HOUR DURATION PRECIPITATION (INCHES)= 2.700 SPECIFIED MINIMUM PIPE SIZE(INCH) = 4.00 SPECIFIED PERCENT OF GRADIENTS(DECIMAL) TO USE FOR FRICTION SLOPE= 0.90 SAN DIEGO HYDROLOGY MANUAL "("-VALUES USED FOR RATIONAL METHOD NOTE: USE MODIFIED RATIONAL METHOD PROCEDURES FOR CONFLUENCE ANALYSIS *USER-DEFINED STREET-SECTIONS FOR COUPLED PIPEFLOW AND STREETFLOW MODEL* HALF-CROWN TO STREET-CROSSFALL: CURB GUTTER-GEOMETRIES: MANNING WIDTH CROSSFALL IN-/ OUT-/PARK-HEIGHT WIDTH LIP HIKE FACTOR NO. (FT) (FT) SIDE/ SIDE/ WAY (FT) (FT) (FT) (FT) (n) ====== 1 30.0 20.0 0.018/0.018/0.020 0.67 GLOBAL STREET FLOW-DEPTH CONSTRAINTS: 1. Relative Flow-Depth= 0.00 FEET Page 1 ====== ======= 2.00 0.0313 0.167 0.0150 3140EXPR.TXT as (Maximum Allowable Street Flow Depth) -(Top-of-Curb) 2. (Depth)*(Velocity) Constraint= 6.0 (FT*FT/S) *SIZE PIPE WITH A FLOW CAPACITY GREATER THAN OR EQUAL TO THE UPSTREAM TRIBUTARY PIPE.* **************************************************************************** FLOW PROCESS FROM NODE 100.00 TO NODE 101.00 IS CODE= 21 >>>>>RATIONAL METHOD INITIAL SUBAREA ANALYSIS<<<<< ----------------------------------------------------------------=-===------- *USER SPECIFIED(SUBAREA): USER-SPECIFIED RUNOFF COEFFICIENT= .3500 S.C.S. CURVE NUMBER (AMC II)= 0 INITIAL SUBAREA FLOW-LENGTH(FEET) = 75.00 UPSTREAM ELEVATION(FEET) = 292.00 DOWNSTREAM ELEVATION(FEET) = 257.24 ELEVATION DIFFERENCE(FEET) = 34.76 SUBAREA OVERLAND TIME OF FLOW(MIN.) = 5.427 WARNING: THE MAXIMUM OVERLAND FLOW SLOPE, 10.%, IS USED IN Tc CALCULATION! 100 YEAR RAINFALL INTENSITY(INCH/HOUR) = 6.747 SUBAREA RUNOFF(CFS) = 0.62 TOTAL AREA(ACRES) = 0.26 TOTAL RUNOFF(CFS) = 0.62 **************************************************************************** FLOW PROCESS FROM NODE 101.00 TO NODE 102.00 IS CODE= 31 >>>>>COMPUTE PIPE-FLOW TRAVEL TIME THRU SUBAREA<<<<< >>>>>USING COMPUTER-ESTIMATED PIPESIZE (NON-PRESSURE FLOW)<<<<< -------------------------------------------------------------========--===== ELEVATION DATA: UPSTREAM(FEET) = 257.24 DOWNSTREAM(FEET) = 255.00 FLOW LENGTH(FEET) = 198.00 MANNING'S N = 0.015 DEPTH OF FLOW IN 9.0 INCH PIPE IS 4.1 INCHES PIPE-FLOW VELOCITY(FEET/SEC.) = 3.13 ESTIMATED PIPE DIAMETER(INCH) = 9.00 NUMBER OF PIPES= 1 PIPE-FLOW(CFS) = 0.62 PIPE TRAVEL TIME(MIN.) = 1.06 Tc(MIN.) = 6.48 LONGEST FLOWPATH FROM NODE 100.00 TO NODE 102.00 = 273.00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 101.00 TO NODE 102.00 IS CODE= 81 >>>>>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW<<<<< 100 YEAR RAINFALL INTENSITY(INCH/HOUR) = 6.017 *USER SPECIFIED(SUBAREA): USER-SPECIFIED RUNOFF COEFFICIENT= .3500 S.C.S. CURVE NUMBER (AMC II)= 0 AREA-AVERAGE RUNOFF COEFFICIENT= 0.3500 Page 2 SUBAREA AREA(ACRES) = TOTAL AREA(ACRES) = TC(MIN.) = 6.48 0.53 0.8 3140EXPR.TXT SUBAREA RUNOFF(CFS) = TOTAL RUNOFF(CFS) = 1.12 1.67 **************************************************************************** FLOW PROCESS FROM NODE 102.00 TO NODE 103.00 IS CODE= 31 >>>>>COMPUTE PIPE-FLOW TRAVEL TIME THRU SUBAREA<<<<< >>>>>USING COMPUTER-ESTIMATED PIPESIZE (NON-PRESSURE FLOW)<<<<< ELEVATION DATA: UPSTREAM(FEET) = 250.50 DOWNSTREAM(FEET) = FLOW LENGTH(FEET) = 65.00 MANNING'S N = 0.013 DEPTH OF FLOW IN 9.0 INCH PIPE IS 4.0 INCHES PIPE-FLOW VELOCITY(FEET/SEC.) = 8.81 ESTIMATED PIPE DIAMETER(INCH) = 9.00 PIPE-FLOW(CFS) = 1.67 NUMBER OF PIPES= PIPE TRAVEL TIME(MIN.) = 0.12 Tc(MIN.) = 1 246.10 LONGEST FLOWPATH FROM NODE 100.00 TO NODE 6.61 103.00 = 338.00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 103.00 TO NODE 104.00 IS CODE= 31 >>>>>COMPUTE PIPE-FLOW TRAVEL TIME THRU SUBAREA<<<<< >>>>>USING COMPUTER-ESTIMATED PIPESIZE (NON-PRESSURE FLOW)<<<<< ELEVATION DATA: UPSTREAM(FEET) = 246.10 DOWNSTREAM(FEET) = FLOW LENGTH(FEET) = 355.00 MANNING'S N = 0.013 DEPTH OF FLOW IN 12.0 INCH PIPE IS 5.9 INCHES PIPE-FLOW VELOCITY(FEET/SEC.) = 4.32 ESTIMATED PIPE DIAMETER(INCH) = 12.00 PIPE-FLOW(CFS) = 1.67 NUMBER OF PIPES= PIPE TRAVEL TIME(MIN.) = 1.37 Tc(MIN.) = 1 242.50 LONGEST FLOWPATH FROM NODE 100.00 TO NODE 7.97 104.00 = 693.00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 104.00 TO NODE 105.00 IS CODE= 31 >>>>>COMPUTE PIPE-FLOW TRAVEL TIME THRU SUBAREA<<<<< >>>>>USING COMPUTER-ESTIMATED PIPESIZE (NON-PRESSURE FLOW)<<<<< ELEVATION DATA: UPSTREAM(FEET) = 242.50 DOWNSTREAM(FEET) = 241.25 FLOW LENGTH(FEET) = 125.00 MANNING'S N = 0.013 DEPTH OF FLOW IN 12.0 INCH PIPE IS 6.0 INCHES PIPE-FLOW VELOCITY(FEET/SEC.) = 4.30 ESTIMATED PIPE DIAMETER(INCH) = 12.00 NUMBER OF PIPES= 1 PIPE-FLOW(CFS) = 1.67 PIPE TRAVEL TIME(MIN.) = 0.48 Tc(MIN.) = 8.46 LONGEST FLOWPATH FROM NODE 100.00 TO NODE 105.00 = 818.00 FEET. Page 3 3140EXPR.TXT **************************************************************************** FLOW PROCESS FROM NODE 105.00 TO NODE 105.00 IS CODE= 1 >>>>>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE<<<<< ----------------------------------------------------------------=====------= TOTAL NUMBER OF STREAMS= 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: TIME OF CONCENTRATION(MIN.) = 8.46 RAINFALL INTENSITY(INCH/HR) = 5.07 TOTAL STREAM AREA(ACRES) = 0.79 PEAK FLOW RATE(CFS) AT CONFLUENCE= 1.67 **************************************************************************** FLOW PROCESS FROM NODE 120.00 TO NODE 121.00 IS CODE= 21 >>>>>RATIONAL METHOD INITIAL SUBAREA ANALYSIS<<<<< *USER SPECIFIED(SUBAREA): USER-SPECIFIED RUNOFF COEFFICIENT= .8500 S.C.S. CURVE NUMBER (AMC II)= 0 INITIAL SUBAREA FLOW-LENGTH(FEET) = 100.00 UPSTREAM ELEVATION(FEET) = 254.70 DOWNSTREAM ELEVATION(FEET) = 252.00 ELEVATION DIFFERENCE(FEET) = 2.70 SUBAREA OVERLAND TIME OF FLOW(MIN.) = 2.836 WARNING: INITIAL SUBAREA FLOW PATH LENGTH IS GREATER THAN THE MAXIMUM OVERLAND FLOW LENGTH= 77.00 (Reference: Table 3-18 of Hydrology Manual) THE MAXIMUM OVERLAND FLOW LENGTH IS USED IN Tc CALCULATION! 100 YEAR RAINFALL INTENSITY(INCH/HOUR) = 7.114 NOTE: RAINFALL INTENSITY IS BASED ON Tc= 5-MINUTE. SUBAREA RUNOFF(CFS) = 0.79 TOTAL AREA(ACRES) = 0.13 TOTAL RUNOFF(CFS) = 0.79 **************************************************************************** FLOW PROCESS FROM NODE 121.00 TO NODE 122.00 IS CODE= 51 >>>>>COMPUTE TRAPEZOIDAL CHANNEL FLOW<<<<< >>>>>TRAVELTIME THRU SUBAREA (EXISTING ELEMENT)<<<<< ELEVATION DATA: UPSTREAM(FEET) = 252.00 DOWNSTREAM(FEET) = 246.00 CHANNEL LENGTH THRU SUBAREA(FEET) = 625.00 CHANNEL SLOPE= 0.0096 CHANNEL BASE(FEET) = 3.00 "Z'' FACTOR= 20.000 MANNING'S FACTOR= 0.015 MAXIMUM DEPTH(FEET) = 1.00 100 YEAR RAINFALL INTENSITY(INCH/HOUR) = 6.193 *USER SPECIFIED(SUBAREA): USER-SPECIFIED RUNOFF COEFFICIENT= .8500 Page 4 3140EXPR.TXT S.C.S. CURVE NUMBER (AMC II)= 0 TRAVEL TIME COMPUTED USING ESTIMATED FLOW(CFS) = 8.12 TRAVEL TIME THRU SUBAREA BASED ON VELOCITY(FEET/SEC.) = 3.10 AVERAGE FLOW DEPTH(FEET) = 0.29 TRAVEL TIME(MIN.) = 3.36 Tc(MIN.) = 6.20 SUBAREA AREA(ACRES) = 2.78 SUBAREA RUNOFF(CFS) = 14.62 AREA-AVERAGE RUNOFF COEFFICIENT= 0.850 TOTAL AREA(ACRES) = 2.9 PEAK FLOW RATE(CFS) = 15.30 END OF SUBAREA CHANNEL FLOW HYDRAULICS: DEPTH(FEET) = 0.39 FLOW VELOCITY(FEET/SEC.) = 3.60 LONGEST FLOWPATH FROM NODE 120.00 TO NODE 122.00 = 725.00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 122.00 TO NODE 105.00 IS CODE= 1 >>>>>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE<<<<< >>>>>AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES<<<<< TOTAL NUMBER OF STREAMS= 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 6.20 RAINFALL INTENSITY(INCH/HR) = 6.19 TOTAL STREAM AREA(ACRES) = 2.91 PEAK FLOW RATE(CFS) AT CONFLUENCE= 15.30 ** CONFLUENCE DATA ** STREAM RUNOFF Tc INTENSITY AREA NUMBER (CFS) (MIN.) (INCH/HOUR) (ACRE) 1 1.67 8.46 5.068 0.79 2 15.30 6.20 6.193 2.91 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 2 STREAMS. ** PEAK FLOW RATE TABLE ** STREAM RUNOFF Tc INTENSITY NUMBER (CFS) (MIN.) (INCH/HOUR) 1 16.53 6.20 6.193 2 14.19 8.46 5.068 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 16.53 Tc(MIN.) = 6.20 TOTAL AREA(ACRES) = 3.7 LONGEST FLOWPATH FROM NODE 100.00 TO NODE 105.00 = 818. 00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 105.00 TO NODE Page 5 106.00 IS CODE= 31 3140EXPR.TXT >>>>>COMPUTE PIPE-FLOW TRAVEL TIME THRU SUBAREA<<<<< >>>>>USING COMPUTER-ESTIMATED PIPESIZE (NON-PRESSURE FLOW)<<<<< ELEVATION DATA: UPSTREAM(FEET) = 241.25 DOWNSTREAM(FEET) = 239.90 FLOW LENGTH(FEET) = 30.00 MANNING'S N = 0.013 DEPTH OF FLOW IN 18.0 INCH PIPE IS 12.0 INCHES PIPE-FLOW VELOCITY(FEET/SEC.) = 13.26 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES= 1 PIPE-FLOW(CFS) = 16.53 PIPE TRAVEL TIME(MIN.) = 0.04 Tc(MIN.) = 6.24 LONGEST FLOWPATH FROM NODE 100.00 TO NODE 106.00 = 848.00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 106.00 TO NODE 106.00 IS CODE= 10 >>>>>MAIN-STREAM MEMORY COPIED ONTO MEMORY BANK# 1 <<<<< **************************************************************************** FLOW PROCESS FROM NODE 250.00 TO NODE 251.00 IS CODE= 21 >>>>>RATIONAL METHOD INITIAL SUBAREA ANALYSIS<<<<< *USER SPECIFIED(SUBAREA): USER-SPECIFIED RUNOFF COEFFICIENT= .8500 S.C.S. CURVE NUMBER (AMC II)= 0 INITIAL SUBAREA FLOW-LENGTH(FEET) = 100.00 UPSTREAM ELEVATION(FEET) = 253.70 DOWNSTREAM ELEVATION(FEET) = 248.10 ELEVATION DIFFERENCE(FEET) = 5.60 SUBAREA OVERLAND TIME OF FLOW(MIN.) = 2.420 WARNING: INITIAL SUBAREA FLOW PATH LENGTH IS GREATER THAN THE MAXIMUM OVERLAND FLOW LENGTH= 91.20 (Reference: Table 3-lB of Hydrology Manual) THE MAXIMUM OVERLAND FLOW LENGTH IS USED IN Tc CALCULATION! 100 YEAR RAINFALL INTENSITY(INCH/HOUR) 7.114 NOTE: RAINFALL INTENSITY IS BASED ON Tc= 5-MINUTE. SUBAREA RUNOFF(CFS) = 1.72 TOTAL AREA(ACRES) = 0.28 TOTAL RUNOFF(CFS) = 1.72 **************************************************************************** FLOW PROCESS FROM NODE 250.00 TO NODE 251.00 IS CODE= 22 >>>>>RATIONAL METHOD INITIAL SUBAREA ANALYSIS<<<<< *USER SPECIFIED(SUBAREA): USER-SPECIFIED RUNOFF COEFFICIENT= .8500 Page 6 3140EXPR.TXT S.C.S. CURVE NUMBER (AMC II)= 0 USER SPECIFIED Tc(MIN.) = 5.000 100 YEAR RAINFALL INTENSITY(INCH/HOUR) = 7.114 SUBAREA RUNOFF(CFS) = 1.72 TOTAL AREA(ACRES) = 0.28 TOTAL RUNOFF(CFS) = 1.72 **************************************************************************** FLOW PROCESS FROM NODE 251.00 TO NODE 252.00 IS CODE= 31 >>>>>COMPUTE PIPE-FLOW TRAVEL TIME THRU SUBAREA<<<<< >>>>>USING COMPUTER-ESTIMATED PIPESIZE (NON-PRESSURE FLOW)<<<<< ELEVATION DATA: UPSTREAM(FEET) = 246.40 DOWNSTREAM(FEET) = 243.90 FLOW LENGTH(FEET) = 210.00 MANNING'S N = 0.013 DEPTH OF FLOW IN 12.0 INCH PIPE IS 5.8 INCHES PIPE-FLOW VELOCITY(FEET/SEC.) = 4.61 ESTIMATED PIPE DIAMETER(INCH) = 12.00 NUMBER OF PIPES= 1 PIPE-FLOW(CFS) = 1.72 PIPE TRAVEL TIME(MIN.) = 0.76 Tc(MIN.) = 5.76 LONGEST FLOWPATH FROM NODE 250.00 TO NODE 252.00 = 285.00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 252.00 TO NODE 253.00 IS CODE= 31 >>>>>COMPUTE PIPE-FLOW TRAVEL TIME THRU SUBAREA<<<<< >>>>>USING COMPUTER-ESTIMATED PIPESIZE (NON-PRESSURE FLOW)<<<<< ELEVATION DATA: UPSTREAM(FEET) = 243.90 DOWNSTREAM(FEET) = 239.00 FLOW LENGTH(FEET) = 160.00 MANNING'S N = 0.013 DEPTH OF FLOW IN 9.0 INCH PIPE IS 5.2 INCHES PIPE-FLOW VELOCITY(FEET/SEC.) = 6.57 ESTIMATED PIPE DIAMETER(INCH) = 9.00 NUMBER OF PIPES= 1 PIPE-FLOW(CFS) = 1.72 PIPE TRAVEL TIME(MIN.) = 0.41 Tc(MIN.) = 6.17 LONGEST FLOWPATH FROM NODE 250.00 TO NODE 253.00 = 445.00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 252.00 TO NODE 253.00 IS CODE= 81 >>>>>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW<<<<< 100 YEAR RAINFALL INTENSITY(INCH/HOUR) = 6.215 *USER SPECIFIED(SUBAREA): USER-SPECIFIED RUNOFF COEFFICIENT= .8500 S.C.S. CURVE NUMBER (AMC II)= 0 AREA-AVERAGE RUNOFF COEFFICIENT= 0.8500 SUBAREA AREA(ACRES) = 1.17 SUBAREA RUNOFF(CFS) = TOTAL AREA(ACRES) = 1.5 TOTAL RUNOFF(CFS) = Page 7 6.17 7.67 3140EXPR.TXT TC(MIN.) = 6.17 **************************************************************************** FLOW PROCESS FROM NODE 253.00 TO NODE 254.00 IS CODE= 31 >>>>>COMPUTE PIPE-FLOW TRAVEL TIME THRU SUBAREA<<<<< >>>>>USING COMPUTER-ESTIMATED PIPESIZE (NON-PRESSURE FLOW)<<<<< ELEVATION DATA: UPSTREAM(FEET) = 239.00 DOWNSTREAM(FEET) = 234.00 FLOW LENGTH(FEET) = 95.00 MANNING'S N = 0.013 DEPTH OF FLOW IN 12.0 INCH PIPE IS 9.7 INCHES PIPE-FLOW VELOCITY(FEET/SEC.) = 11.29 ESTIMATED PIPE DIAMETER(INCH) = 12.00 NUMBER OF PIPES= 1 PIPE-FLOW(CFS) = 7.67 PIPE TRAVEL TIME(MIN.) = 0.14 Tc(MIN.) = 6.31 LONGEST FLOWPATH FROM NODE 250.00 TO NODE 254.00 = 540.00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 253.00 TO NODE 254.00 IS CODE= 81 >>>>>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW<<<<< 100 YEAR RAINFALL INTENSITY(INCH/HOUR) = 6.125 *USER SPECIFIED(SUBAREA): USER-SPECIFIED RUNOFF COEFFICIENT= .8500 S.C.S. CURVE NUMBER (AMC II)= 0 AREA-AVERAGE RUNOFF COEFFICIENT= 0.8500 SUBAREA AREA(ACRES) = 0.20 SUBAREA RUNOFF(CFS) = TOTAL AREA(ACRES) = 1.7 TOTAL RUNOFF(CFS) = TC(MIN.) = 6.31 1.04 8.60 **************************************************************************** FLOW PROCESS FROM NODE 254.00 TO NODE 255.00 IS CODE= 31 >>>>>COMPUTE PIPE-FLOW TRAVEL TIME THRU SUBAREA<<<<< >>>>>USING COMPUTER-ESTIMATED PIPESIZE (NON-PRESSURE FLOW)<<<<< ELEVATION DATA: UPSTREAM(FEET) = 233.80 DOWNSTREAM(FEET) = 233.00 FLOW LENGTH(FEET) = 75.00 MANNING'S N = 0.013 DEPTH OF FLOW IN 18.0 INCH PIPE IS 12.6 INCHES PIPE-FLOW VELOCITY(FEET/SEC.) = 6.53 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES= 1 PIPE-FLOW(CFS) = 8.60 PIPE TRAVEL TIME(MIN.) = 0.19 Tc(MIN.) = 6.50 LONGEST FLOWPATH FROM NODE 250.00 TO NODE 255.00 = 615.00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 255.00 TO NODE Page 8 255.00 IS CODE= 1 3140EXPR.TXT >>>>>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE<<<<< TOTAL NUMBER OF STREAMS= 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: TIME OF CONCENTRATION(MIN.) = 6.50 RAINFALL INTENSITY(INCH/HR) = 6.01 TOTAL STREAM AREA(ACRES) = 1.65 PEAK FLOW RATE(CFS) AT CONFLUENCE= 8.60 **************************************************************************** FLOW PROCESS FROM NODE 500.00 TO NODE 501.00 IS CODE= 21 >>>>>RATIONAL METHOD INITIAL SUBAREA ANALYSIS<<<<< *USER SPECIFIED(SUBAREA): USER-SPECIFIED RUNOFF COEFFICIENT= .8500 S.C.S. CURVE NUMBER (AMC II)= 0 INITIAL SUBAREA FLOW-LENGTH(FEET) = 90.00 UPSTREAM ELEVATION(FEET) = 253.40 DOWNSTREAM ELEVATION(FEET) = 251.80 ELEVATION DIFFERENCE(FEET) = 1.60 SUBAREA OVERLAND TIME OF FLOW(MIN.) = 3.145 WARNING: INITIAL SUBAREA FLOW PATH LENGTH IS GREATER THAN THE MAXIMUM OVERLAND FLOW LENGTH= 71.67 (Reference: Table 3-18 of Hydrology Manual) THE MAXIMUM OVERLAND FLOW LENGTH IS USED IN Tc CALCULATION! 100 YEAR RAINFALL INTENSITY(INCH/HOUR) = 7.114 NOTE: RAINFALL INTENSITY IS BASED ON Tc= 5-MINUTE. SUBAREA RUNOFF(CFS) = 1.08 TOTAL AREA(ACRES) = 0.18 TOTAL RUNOFF(CFS) = 1.08 **************************************************************************** FLOW PROCESS FROM NODE 501.00 TO NODE 502.00 IS CODE= 31 >>>>>COMPUTE PIPE-FLOW TRAVEL TIME THRU SUBAREA<<<<< >>>>>USING COMPUTER-ESTIMATED PIPESIZE (NON-PRESSURE FLOW)<<<<< ELEVATION DATA: UPSTREAM(FEET) = 244.80 DOWNSTREAM(FEET) = 243.20 FLOW LENGTH(FEET) = 105.00 MANNING'S N = 0.013 DEPTH OF FLOW IN 9.0 INCH PIPE IS 4.8 INCHES PIPE-FLOW VELOCITY(FEET/SEC.) = 4.52 ESTIMATED PIPE DIAMETER(INCH) = 9.00 NUMBER OF PIPES= 1 PIPE-FLOW(CFS) = 1.08 PIPE TRAVEL TIME(MIN.) = 0.39 Tc(MIN.) = 3.53 LONGEST FLOWPATH FROM NODE 500.00 TO NODE 502.00 = 195.00 FEET. **************************************************************************** Page 9 3140EXPR.TXT FLOW PROCESS FROM NODE 501.00 TO NODE 502.00 IS CODE= 81 >>>>>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW<<<<< ------------------------------------------------------------------===---==== 100 YEAR RAINFALL INTENSITY(INCH/HOUR) = 7.114 NOTE: RAINFALL INTENSITY IS BASED ON Tc= 5-MINUTE. *USER SPECIFIED(SUBAREA): USER-SPECIFIED RUNOFF COEFFICIENT= .8500 S.C.S. CURVE NUMBER (AMC II)= 0 AREA-AVERAGE RUNOFF COEFFICIENT= 0.8500 SUBAREA AREA(ACRES) = 0.31 SUBAREA RUNOFF(CFS) = TOTAL AREA(ACRES) = 0.5 TOTAL RUNOFF(CFS) = TC(MIN.) = 3.53 1.87 2.95 **************************************************************************** FLOW PROCESS FROM NODE 502.00 TO NODE 503.00 IS CODE= 31 >>>>>COMPUTE PIPE-FLOW TRAVEL TIME THRU SUBAREA<<<<< >>>>>USING COMPUTER-ESTIMATED PIPESIZE (NON-PRESSURE FLOW)<<<<< ELEVATION DATA: UPSTREAM(FEET) = 243.20 DOWNSTREAM(FEET) = 241.90 FLOW LENGTH(FEET) = 85.00 MANNING'S N = 0.013 DEPTH OF FLOW IN 12.0 INCH PIPE IS 7.4 INCHES PIPE-FLOW VELOCITY(FEET/SEC.) = 5.78 ESTIMATED PIPE DIAMETER(INCH) = 12.00 NUMBER OF PIPES= 1 PIPE-FLOW(CFS) = 2.95 PIPE TRAVEL TIME(MIN.) = 0.25 Tc(MIN.) = 3.78 LONGEST FLOWPATH FROM NODE 500.00 TO NODE 503.00 = 280.00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 502.00 TO NODE 503.00 IS CODE= 81 >>>>>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW<<<<< 100 YEAR RAINFALL INTENSITY(INCH/HOUR) = 7.114 NOTE: RAINFALL INTENSITY IS BASED ON Tc= 5-MINUTE. *USER SPECIFIED(SUBAREA): USER-SPECIFIED RUNOFF COEFFICIENT= .8500 S.C.S. CURVE NUMBER (AMC II)= 0 AREA-AVERAGE RUNOFF COEFFICIENT= 0.8500 SUBAREA AREA(ACRES) = 0.18 SUBAREA RUNOFF(CFS) = TOTAL AREA(ACRES) = 0.7 TOTAL RUNOFF(CFS) = TC(MIN.) = 3.78 1.08 4.03 **************************************************************************** FLOW PROCESS FROM NODE 503.00 TO NODE 504.00 IS CODE= 31 >>>>>COMPUTE PIPE-FLOW TRAVEL TIME THRU SUBAREA<<<<< Page 10 3140EXPR.TXT >>>>>USING COMPUTER-ESTIMATED PIPESIZE (NON-PRESSURE FLOW)<<<<< ELEVATION DATA: UPSTREAM(FEET) = 241.90 DOWNSTREAM(FEET) = 239.00 FLOW LENGTH(FEET) = 195.00 MANNING'S N = 0.013 DEPTH OF FLOW IN 12.0 INCH PIPE IS 9.6 INCHES PIPE-FLOW VELOCITY(FEET/SEC.) = 6.00 ESTIMATED PIPE DIAMETER(INCH) = 12.00 NUMBER OF PIPES= 1 PIPE-FLOW(CFS) = 4.03 PIPE TRAVEL TIME(MIN.) = 0.54 Tc(MIN.) = 4.32 LONGEST FLOWPATH FROM NODE 500.00 TO NODE 504.00 = 475.00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 503.00 TO NODE 504.00 IS CODE= 81 >>>>>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW<<<<< 100 YEAR RAINFALL INTENSITY(INCH/HOUR) = 7.114 NOTE: RAINFALL INTENSITY IS BASED ON Tc= 5-MINUTE. *USER SPECIFIED(SUBAREA): USER-SPECIFIED RUNOFF COEFFICIENT= .8500 S.C.S. CURVE NUMBER (AMC II)= 0 AREA-AVERAGE RUNOFF COEFFICIENT= 0.8500 SUBAREA AREA(ACRES) = 0.52 SUBAREA RUNOFF(CFS) = TOTAL AREA(ACRES) = 1.2 TOTAL RUNOFF(CFS) = TC(MIN.) = 4.32 3.15 7.18 **************************************************************************** FLOW PROCESS FROM NODE 504.00 TO NODE 505.00 IS CODE= 31 >>>>>COMPUTE PIPE-FLOW TRAVEL TIME THRU SUBAREA<<<<< >>>>>USING COMPUTER-ESTIMATED PIPESIZE (NON-PRESSURE FLOW)<<<<< ELEVATION DATA: UPSTREAM(FEET) = 239.00 DOWNSTREAM(FEET) = 226.00 FLOW LENGTH(FEET) = 170.00 MANNING'S N = 0.013 DEPTH OF FLOW IN 12.0 INCH PIPE IS 7.9 INCHES PIPE-FLOW VELOCITY(FEET/SEC.) = 13.14 ESTIMATED PIPE DIAMETER(INCH) = 12.00 NUMBER OF PIPES= 1 PIPE-FLOW(CFS) = 7.18 PIPE TRAVEL TIME(MIN.) = 0.22 Tc(MIN.) = 4.53 LONGEST FLOWPATH FROM NODE 500.00 TO NODE 505.00 = 645.00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 505.00 TO NODE 505.00 IS CODE= 81 >>>>>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW<<<<< 100 YEAR RAINFALL INTENSITY(INCH/HOUR) = 7.114 NOTE: RAINFALL INTENSITY IS BASED ON Tc= 5-MINUTE. Page 11 3140EXPR.TXT *USER SPECIFIED(SUBAREA): USER-SPECIFIED RUNOFF COEFFICIENT= .3500 S.C.S. CURVE NUMBER (AMC II)= 0 AREA-AVERAGE RUNOFF COEFFICIENT= 0.7870 SUBAREA AREA(ACRES) = 0.17 SUBAREA RUNOFF(CFS) = TOTAL AREA(ACRES) = 1.4 TOTAL RUNOFF(CFS) = TC(MIN.) = 4.53 0.43 7.60 **************************************************************************** FLOW PROCESS FROM NODE 505.00 TO NODE 255.00 rs CODE= 1 >>>>>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE<<<<< >>>>>AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES<<<<< TOTAL NUMBER OF STREAMS= 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 4.53 RAINFALL INTENSITY(INCH/HR) = 7.11 TOTAL STREAM AREA(ACRES) = 1.36 PEAK FLOW RATE(CFS) AT CONFLUENCE= 7.60 ** CONFLUENCE DATA ** STREAM RUNOFF Tc INTENSITY AREA NUMBER (CFS) (MIN.) (INCH/HOUR) (ACRE) 1 8.60 6.50 6.008 1.65 2 7.60 4.53 7.114 1. 36 RAINFALL INTENSITY AND TIME OF CONCENTRATION RATIO CONFLUENCE FORMULA USED FOR 2 STREAMS. ** PEAK FLOW RATE TABLE ** STREAM RUNOFF Tc INTENSITY NUMBER (CFS) (MIN.) (INCH/HOUR) 1 13.60 4.53 7.114 2 15.02 6.50 6.008 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 15.02 Tc(MIN.) = 6.50 TOTAL AREA(ACRES) = 3.0 LONGEST FLOWPATH FROM NODE 500.00 TO NODE 255.00 = 645.00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 255.00 TO NODE 256.00 rs CODE= 31 >>>>>COMPUTE PIPE-FLOW TRAVEL TIME THRU SUBAREA<<<<< >>>>>USING COMPUTER-ESTIMATED PIPESIZE (NON-PRESSURE FLOW)<<<<< ELEVATION DATA: UPSTREAM(FEET) = 231.00 DOWNSTREAM(FEET) = 230.00 Page 12 3140EXPR.TXT FLOW LENGTH(FEET) = 22.00 MANNING'S N = 0.013 DEPTH OF FLOW IN 18.0 INCH PIPE IS 11.2 INCHES PIPE-FLOW VELOCITY(FEET/SEC.) = 13.06 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES= 1 PIPE-FLOW(CFS) = 15.02 PIPE TRAVEL TIME(MIN.) = 0.03 Tc(MIN.) = 6.52 LONGEST FLOWPATH FROM NODE 500.00 TO NODE 256.00 = 667.00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 256.00 TO NODE 257.00 IS CODE= 31 >>>>>COMPUTE PIPE-FLOW TRAVEL TIME THRU SUBAREA<<<<< >>>>>USING COMPUTER-ESTIMATED PIPESIZE (NON-PRESSURE FLOW)<<<<< ELEVATION DATA: UPSTREAM(FEET) = 230.00 DOWNSTREAM(FEET) = 226.20 FLOW LENGTH(FEET) = 40.00 MANNING'S N = 0.013 DEPTH OF FLOW IN 15.0 INCH PIPE IS 10.1 INCHES PIPE-FLOW VELOCITY(FEET/SEC.) = 17.11 ESTIMATED PIPE DIAMETER(INCH) = 15.00 NUMBER OF PIPES= 1 PIPE-FLOW(CFS) = 15.02 PIPE TRAVEL TIME(MIN.) = 0.04 Tc(MIN.) = 6.56 LONGEST FLOWPATH FROM NODE 500.00 TO NODE 257.00 = 707.00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 106.00 TO NODE 257.00 IS CODE= 11 >>>>>CONFLUENCE MEMORY BANK# 1 WITH THE MAIN-STREAM MEMORY<<<<< ---------------------------------------------------------------------------~ ** MAIN STREAM CONFLUENCE DATA** STREAM RUNOFF Tc INTENSITY AREA NUMBER (CFS) (MIN.) (INCH/HOUR) (ACRE) 1 15.02 6.56 5.969 3.01 LONGEST FLOWPATH FROM NODE 500.00 TO NODE 257.00 = 707. 00 FEET. ** MEMORY BANK# 1 CONFLUENCE DATA** STREAM RUNOFF Tc INTENSITY AREA NUMBER (CFS) (MIN.) (INCH/HOUR) (ACRE) 1 16.53 6.24 6.168 3.70 LONGEST FLOWPATH FROM NODE 100.00 TO NODE 257.00 = 848.00 FEET. ** PEAK FLOW RATE TABLE** STREAM RUNOFF Tc INTENSITY Confluence of streams leaving NUMBER (CFS) (MIN.) (INCH/HOUR) the subject property to 1 30.80 6.24 6.168 determine total peak runoff 2 31.01 6.56 5.969 leaving the site. COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: Page 13 PEAK FLOW RATE(CFS) = TOTAL AREA(ACRES) = 3140EXPR.TXT 31.01 Tc(MIN.) = 6.7 6.56 **************************************************************************** FLOW PROCESS FROM NODE 257.00 TO NODE 257.00 IS CODE= 10 >>>>>MAIN-STREAM MEMORY COPIED ONTO MEMORY BANK# 2 <<<<< **************************************************************************** FLOW PROCESS FROM NODE 304.00 TO NODE 304.00 IS CODE= ----> SEE AES PRINTOUT NODES 304-304 <---- >>>>>USER SPECIFIED HYDROLOGY INFORMATION AT NODE<<<<< 7 -------------------------------------------·-------------------------------- USER-SPECIFIED VALUES ARE AS FOLLOWS: TC(MIN) = 7.71 RAIN INTENSITY(INCH/HOUR) = 5.38 TOTAL AREA(ACRES) = 2.70 TOTAL RUNOFF(CFS) = 11.14 See AES printout 3 I 40PR02 attached below for backup of user specified information **************************************************************************** FLOW PROCESS FROM NODE 257.00 TO NODE 304.00 IS CODE= 11 >>>>>CONFLUENCE MEMORY BANK# 2 WITH THE MAIN-STREAM MEMORY<<<<< ** MAIN STREAM NUMBER 1 STREAM CONFLUENCE DATA** RUNOFF Tc INTENSITY (CFS) (MIN.) (INCH/HOUR) 11.14 7.71 5.380 LONGEST FLOWPATH FROM NODE 100.00 TO NODE ** MEMORY BANK# 2 CONFLUENCE DATA** STREAM RUNOFF Tc INTENSITY NUMBER (CFS) (MIN.) (INCH/HOUR) 1 31.01 6.56 5.969 LONGEST FLOWPATH FROM NODE 100.00 TO NODE ** PEAK FLOW RATE TABLE** STREAM RUNOFF Tc INTENSITY NUMBER (CFS) (MIN.) (INCH/HOUR) 1 40.49 6.56 5.969 2 39.09 7.71 5.380 AREA (ACRE) 2.70 304.00 = AREA (ACRE) 6.71 304.00 = COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 40.49 Tc(MIN.) = 6.56 TOTAL AREA(ACRES) = 9.4 848.00 FEET. 848.00 FEET. Confluence of streams leaving the subject property to determine total peak runoff leaving the site. **************************************************************************** Page 14 3140EXPR.TXT FLOW PROCESS FROM NODE 304.00 TO NODE 304.00 IS CODE= 10 >>>>>MAIN-STREAM MEMORY COPIED ONTO MEMORY BANK# 3 <<<<< **************************************************************************** FLOW PROCESS FROM NODE 3.00 TO NODE 3.00 IS CODE= 7 >>>>>USER SPECIFIED HYDROLOGY INFORMATION AT NODE<<<<< USER-SPECIFIED VALUES ARE AS FOLLOWS: TC(MIN) = 5.00 RAIN INTENSITY(INCH/HOUR) = 7.11 TOTAL AREA(ACRES) = 1.53 TOTAL RUNOFF(CFS) = 9.25 **************************************************************************** FLOW PROCESS FROM NODE 3.00 TO NODE 304.00 IS CODE= 11 >>>>>CONFLUENCE MEMORY BANK# 3 WITH THE MAIN-STREAM MEMORY<<<<< ** MAIN STREAM CONFLUENCE DATA** STREAM RUNOFF Tc INTENSITY AREA NUMBER (CFS) (MIN.) (INCH/HOUR) (ACRE) 1 9.25 5.00 7.114 1. 53 LONGEST FLOWPATH FROM NODE 100.00 TO NODE 304.00 = ** MEMORY BANK# 3 CONFLUENCE DATA** STREAM RUNOFF Tc INTENSITY AREA NUMBER (CFS) (MIN.) (INCH/HOUR) (ACRE) 1 40.49 6.56 5.969 9.41 LONGEST FLOWPATH FROM NODE 100.00 TO NODE 304.00 = ** PEAK FLOW RATE TABLE** STREAM RUNOFF Tc INTENSITY NUMBER (CFS) (MIN.) (INCH/HOUR) 1 40.10 5.00 7.114 2 48.25 6.56 5.969 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 48.25 Tc(MIN.) = 6.56 TOTAL AREA(ACRES) = 10.9 END OF STUDY SUMMARY: TOTAL AREA(ACRES) = PEAK FLOW RATE(CFS) = 10.9 TC(MIN.) = 48.25 6.56 END OF RATIONAL METHOD ANALYSIS Page 15 848.00 FEET. 848.00 FEET. 3140EXPR.TXT Page 16 3140PR02.TXT **************************************************************************** RATIONAL METHOD HYDROLOGY COMPUTER PROGRAM PACKAGE Reference: SAN DIEGO COUNTY FLOOD CONTROL DISTRICT 2003,1985,1981 HYDROLOGY MANUAL (c) Copyright 1982-2016 Advanced Engineering Software (aes) Ver. 23.0 Release Date: 07/01/2016 License ID 1452 Analysis prepared by: PASCO LARET SUITER & ASSOCIATES 535 NORTH HIGHWAY 101, STE A SOLANA BEACH, CA 92075 858-259-8212 ************************** DESCRIPTION OF STUDY************************** * 3140 RAP PACIFICA GROUP FUSION -NODES 304-304 * * ONSITE PROPOSED CONDITION * * 100-YR * ************************************************************************** FILE NAME: 3140PR02.DAT TIME/DATE OF STUDY: 14:00 04/22/2020 USER SPECIFIED HYDROLOGY AND HYDRAULIC MODEL INFORMATION: 2003 SAN DIEGO MANUAL CRITERIA USER SPECIFIED STORM EVENT(YEAR) = 100.00 6-HOUR DURATION PRECIPITATION (INCHES)= 2.700 SPECIFIED MINIMUM PIPE SIZE(INCH) = 4.00 SPECIFIED PERCENT OF GRADIENTS(DECIMAL) TO USE FOR FRICTION SLOPE= 0.90 SAN DIEGO HYDROLOGY MANUAL "("-VALUES USED FOR RATIONAL METHOD NOTE: USE MODIFIED RATIONAL METHOD PROCEDURES FOR CONFLUENCE ANALYSIS *USER-DEFINED STREET-SECTIONS FOR COUPLED PIPEFLOW AND STREETFLOW HALF-CROWN TO STREET-CROSSFALL: CURB GUTTER-GEOMETRIES: WIDTH CROSSFALL IN-/ OUT-/PARK-HEIGHT WIDTH LIP HIKE NO. (FT) (FT) SIDE/ SIDE/ WAY (FT) (FT) (FT) (FT) ====== ====== MODEL* MANNING FACTOR (n) ======= 1 30.0 20.0 0.018/0.018/0.020 0.67 2.00 0.0313 0.167 0.0150 GLOBAL STREET FLOW-DEPTH CONSTRAINTS: Page 1 3140PR02.TXT 1. Relative Flow-Depth= 0.00 FEET as (Maximum Allowable Street Flow Depth) -(Top-of-Curb) 2. (Depth)*(Velocity) Constraint= 6.0 (FT*FT/S) *SIZE PIPE WITH A FLOW CAPACITY GREATER THAN OR EQUAL TO THE UPSTREAM TRIBUTARY PIPE.* **************************************************************************** FLOW PROCESS FROM NODE 300.00 TO NODE 301.00 IS CODE= 21 >>>>>RATIONAL METHOD INITIAL SUBAREA ANALYSIS<<<<< *USER SPECIFIED(SUBAREA): USER-SPECIFIED RUNOFF COEFFICIENT= .3500 S.C.S. CURVE NUMBER (AMC II)= 0 INITIAL SUBAREA FLOW-LENGTH(FEET) = 100.00 UPSTREAM ELEVATION(FEET) = 298.00 DOWNSTREAM ELEVATION(FEET) = 267.50 ELEVATION DIFFERENCE(FEET) = 30.50 SUBAREA OVERLAND TIME OF FLOW(MIN.) = 6.267 WARNING: THE MAXIMUM OVERLAND FLOW SLOPE, 10.%, IS USED IN Tc CALCULATION! 100 YEAR RAINFALL INTENSITY(INCH/HOUR) = 6.150 SUBAREA RUNOFF(CFS) = 0.40 TOTAL AREA(ACRES) = 0.19 TOTAL RUNOFF(CFS) = 0.40 **************************************************************************** FLOW PROCESS FROM NODE 301.00 TO NODE 302.00 IS CODE= 51 >>>>>COMPUTE TRAPEZOIDAL CHANNEL FLOW<<<<< >>>>>TRAVELTIME THRU SUBAREA (EXISTING ELEMENT)<<<<< ELEVATION DATA: UPSTREAM(FEET) = 267.50 DOWNSTREAM(FEET) = 254.00 CHANNEL LENGTH THRU SUBAREA(FEET) = 325.00 CHANNEL SLOPE= 0.0415 CHANNEL BASE(FEET) = 3.00 "Z" FACTOR= 20.000 MANNING'S FACTOR= 0.015 MAXIMUM DEPTH(FEET) = 1.00 100 YEAR RAINFALL INTENSITY(INCH/HOUR) = 5.492 *USER SPECIFIED(SUBAREA): USER-SPECIFIED RUNOFF COEFFICIENT= .8500 S.C.S. CURVE NUMBER (AMC II)= 0 TRAVEL TIME COMPUTED USING ESTIMATED FLOW(CFS) = 4.94 TRAVEL TIME THRU SUBAREA BASED ON VELOCITY(FEET/SEC.) = 4.51 AVERAGE FLOW DEPTH(FEET) = 0.17 TRAVEL TIME(MIN.) = 1.20 Tc(MIN.) = 7.47 SUBAREA AREA(ACRES) = 1.98 SUBAREA RUNOFF(CFS) = 9.22 AREA-AVERAGE RUNOFF COEFFICIENT= 0.807 TOTAL AREA(ACRES) = 2.2 PEAK FLOW RATE(CFS) = 9.58 END OF SUBAREA CHANNEL FLOW HYDRAULICS: DEPTH(FEET) = 0.23 FLOW VELOCITY(FEET/SEC.) = 5.41 Page 2 3140PR02.TXT LONGEST FLOWPATH FROM NODE 300.00 TO NODE 302.00 = 425.00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 302.00 TO NODE 302.00 IS CODE= 10 >>>>>MAIN-STREAM MEMORY COPIED ONTO MEMORY BANK# 1 <<<<< **************************************************************************** FLOW PROCESS FROM NODE 600.00 TO NODE 601.00 IS CODE= 21 >>>>>RATIONAL METHOD INITIAL SUBAREA ANALYSIS<<<<< *USER SPECIFIED(SUBAREA): USER-SPECIFIED RUNOFF COEFFICIENT= .3500 S.C.S. CURVE NUMBER (AMC II)= 0 INITIAL SUBAREA FLOW-LENGTH(FEET) = 100.00 UPSTREAM ELEVATION(FEET) = 294.50 DOWNSTREAM ELEVATION(FEET) = 265.00 ELEVATION DIFFERENCE(FEET) = 29.50 SUBAREA OVERLAND TIME OF FLOW(MIN.) = 6.267 WARNING: THE MAXIMUM OVERLAND FLOW SLOPE, 10.%, IS USED IN Tc CALCULATION! 100 YEAR RAINFALL INTENSITY(INCH/HOUR) = 6.150 SUBAREA RUNOFF(CFS) = 0.46 TOTAL AREA(ACRES) = 0.22 TOTAL RUNOFF(CFS) = 0.46 **************************************************************************** FLOW PROCESS FROM NODE 601.00 TO NODE 402.00 IS CODE= 31 >>>>>COMPUTE PIPE-FLOW TRAVEL TIME THRU SUBAREA<<<<< >>>>>USING COMPUTER-ESTIMATED PIPESIZE (NON-PRESSURE FLOW)<<<<< ELEVATION DATA: UPSTREAM(FEET) = 261.00 DOWNSTREAM(FEET) = 251.10 FLOW LENGTH(FEET) = 106.00 MANNING'S N = 0.013 DEPTH OF FLOW IN 6.0 INCH PIPE IS 2.2 INCHES PIPE-FLOW VELOCITY(FEET/SEC.) = 7.13 ESTIMATED PIPE DIAMETER(INCH) = 6.00 NUMBER OF PIPES 1 PIPE-FLOW(CFS) = 0.46 PIPE TRAVEL TIME(MIN.) = 0.25 Tc(MIN.) = 6.51 LONGEST FLOWPATH FROM NODE 600.00 TO NODE 402.00 = 206.00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 402.00 TO NODE 402.00 IS CODE= >>>>>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE<<<<< TOTAL NUMBER OF STREAMS= 2 CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 1 ARE: Page 3 1 3140PR02.TXT TIME OF CONCENTRATION(MIN.) = 6.51 RAINFALL INTENSITY(INCH/HR) = 6.00 TOTAL STREAM AREA(ACRES) = 0.22 PEAK FLOW RATE(CFS) AT CONFLUENCE= 0.46 **************************************************************************** FLOW PROCESS FROM NODE 650.00 TO NODE 651.00 IS CODE= 21 >>>>>RATIONAL METHOD INITIAL SUBAREA ANALYSIS<<<<< *USER SPECIFIED(SUBAREA): USER-SPECIFIED RUNOFF COEFFICIENT= .3500 S.C.S. CURVE NUMBER (AMC II)= 0 INITIAL SUBAREA FLOW-LENGTH(FEET) = 140.00 UPSTREAM ELEVATION(FEET) = 293.50 DOWNSTREAM ELEVATION(FEET) = 264.10 ELEVATION DIFFERENCE(FEET) = 29.40 SUBAREA OVERLAND TIME OF FLOW(MIN.) = 6.267 WARNING: INITIAL SUBAREA FLOW PATH LENGTH IS GREATER THAN THE MAXIMUM OVERLAND FLOW LENGTH= 100.00 (Reference: Table 3-1B of Hydrology Manual) THE MAXIMUM OVERLAND FLOW LENGTH IS USED IN Tc CALCULATION! 100 YEAR RAINFALL INTENSITY(INCH/HOUR) = 6.150 SUBAREA RUNOFF(CFS) = 0.30 TOTAL AREA(ACRES) = 0.14 TOTAL RUNOFF(CFS) = 0.30 **************************************************************************** FLOW PROCESS FROM NODE 651.00 TO NODE 402.00 IS CODE= 31 >>>>>COMPUTE PIPE-FLOW TRAVEL TIME THRU SUBAREA<<<<< >>>>>USING COMPUTER-ESTIMATED PIPESIZE (NON-PRESSURE FLOW)<<<<< ELEVATION DATA: UPSTREAM(FEET) = 252.30 DOWNSTREAM(FEET) = 251.10 FLOW LENGTH(FEET) = 60.00 MANNING'S N = 0.013 DEPTH OF FLOW IN 6.0 INCH PIPE IS 2.6 INCHES PIPE-FLOW VELOCITY(FEET/SEC.) = 3.62 ESTIMATED PIPE DIAMETER(INCH) = 6.00 NUMBER OF PIPES= 1 PIPE-FLOW(CFS) = 0.30 PIPE TRAVEL TIME(MIN.) = 0.28 Tc(MIN.) = 6.54 LONGEST FLOWPATH FROM NODE 650.00 TO NODE 402.00 = 200.00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 402.00 TO NODE 402.00 IS CODE= 1 >>>>>DESIGNATE INDEPENDENT STREAM FOR CONFLUENCE<<<<< >>>>>AND COMPUTE VARIOUS CONFLUENCED STREAM VALUES<<<<< -------------------------------------------------------==-----====---======- TOTAL NUMBER OF STREAMS= 2 Page 4 3140PR02.TXT CONFLUENCE VALUES USED FOR INDEPENDENT STREAM 2 ARE: TIME OF CONCENTRATION(MIN.) = 6.54 RAINFALL INTENSITY(INCH/HR) = 5.98 TOTAL STREAM AREA(ACRES) = 0.14 PEAK FLOW RATE(CFS) AT CONFLUENCE= 0.30 ** CONFLUENCE DATA ** STREAM RUNOFF Tc INTENSITY NUMBER (CFS) (MIN.) (INCH/HOUR) 1 0.46 6.51 5.998 2 0.30 6.54 5.981 RAINFALL INTENSITY AND TIME OF CONCENTRATION CONFLUENCE FORMULA USED FOR 2 STREAMS. ** PEAK FLOW RATE TABLE ** STREAM RUNOFF Tc INTENSITY NUMBER (CFS) (MIN.) (INCH/HOUR) 1 0.76 6.51 5.998 2 0.76 6.54 5.981 COMPUTED CONFLUENCE PEAK FLOW RATE(CFS) ESTIMATES ARE AS FOLLOWS: = 0.76 Tc(MIN.) = 0.4 TOTAL AREA(ACRES) = LONGEST FLOWPATH FROM NODE 600.00 TO NODE AREA (ACRE) 0.22 0.14 RATIO 6.54 402.00 = 206.00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 402.00 TO NODE 302.00 IS CODE= 31 >>>>>COMPUTE PIPE-FLOW TRAVEL TIME THRU SUBAREA<<<<< >>>>>USING COMPUTER-ESTIMATED PIPESIZE (NON-PRESSURE FLOW)<<<<< ELEVATION DATA: UPSTREAM(FEET) = 250.90 DOWNSTREAM(FEET) = 244.30 FLOW LENGTH(FEET) = 265.00 MANNING'S N = 0.013 DEPTH OF FLOW IN 6.0 INCH PIPE IS 4.5 INCHES PIPE-FLOW VELOCITY(FEET/SEC.) = 4.86 ESTIMATED PIPE DIAMETER(INCH) = 6.00 NUMBER OF PIPES 1 PIPE-FLOW(CFS) = 0.76 PIPE TRAVEL TIME(MIN.) = 0.91 Tc(MIN.) = 7.45 LONGEST FLOWPATH FROM NODE 600.00 TO NODE 302.00 = 471.00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 302.00 TO NODE 302.00 IS CODE= 11 >>>>>CONFLUENCE MEMORY BANK# 1 WITH THE MAIN-STREAM MEMORY<<<<< **MAINSTREAM CONFLUENCE DATA** Page 5 3140PR02.TXT STREAM RUNOFF Tc INTENSITY AREA NUMBER (CFS) (MIN.) (INCH/HOUR) (ACRE) 1 0.76 7.45 5.500 0.36 LONGEST FLOWPATH FROM NODE 600.00 TO NODE 302.00 = 471. 00 FEET. ** MEMORY BANK# 1 CONFLUENCE DATA** STREAM RUNOFF Tc INTENSITY AREA NUMBER (CFS) (MIN.) (INCH/HOUR) (ACRE) 1 9.58 7.47 5.492 2.16 LONGEST FLOWPATH FROM NODE 300.00 TO NODE 302.00 = 425.00 FEET. ** PEAK FLOW RATE TABLE** STREAM RUNOFF Tc INTENSITY NUMBER (CFS) (MIN.) (INCH/HOUR) 1 10.32 7.45 5.500 2 10.34 7.47 5.492 COMPUTED CONFLUENCE ESTIMATES ARE AS FOLLOWS: PEAK FLOW RATE(CFS) = 10.34 Tc(MIN.) = 7.47 TOTAL AREA(ACRES) = 2.5 **************************************************************************** FLOW PROCESS FROM NODE 302.00 TO NODE 303.00 IS CODE= 31 >>>>>COMPUTE PIPE-FLOW TRAVEL TIME THRU SUBAREA<<<<< >>>>>USING COMPUTER-ESTIMATED PIPESIZE (NON-PRESSURE FLOW)<<<<< ELEVATION DATA: UPSTREAM(FEET) = 244.10 DOWNSTREAM(FEET) = 241.70 FLOW LENGTH(FEET) = 105.00 MANNING'S N = 0.013 DEPTH OF FLOW IN 18.0 INCH PIPE IS 10.9 INCHES PIPE-FLOW VELOCITY(FEET/SEC.) = 9.20 ESTIMATED PIPE DIAMETER(INCH) = 18.00 NUMBER OF PIPES= 1 PIPE-FLOW(CFS) = 10.34 PIPE TRAVEL TIME(MIN.) = 0.19 Tc(MIN.) = 7.66 LONGEST FLOWPATH FROM NODE 600.00 TO NODE 303.00 = 576.00 FEET. **************************************************************************** FLOW PROCESS FROM NODE 302.00 TO NODE 303.00 IS CODE= 81 >>>>>ADDITION OF SUBAREA TO MAINLINE PEAK FLOW<<<<< 100 YEAR RAINFALL INTENSITY(INCH/HOUR) = 5.404 *USER SPECIFIED(SUBAREA): USER-SPECIFIED RUNOFF COEFFICIENT= .8500 S.C.S. CURVE NUMBER (AMC II)= 0 AREA-AVERAGE RUNOFF COEFFICIENT= 0.7512 SUBAREA AREA(ACRES) = 0.23 SUBAREA RUNOFF(CFS) = TOTAL AREA(ACRES) = 2.7 TOTAL RUNOFF(CFS) = Page 6 1.04 11.14 3140PR02.TXT TC(MIN.) = 7.66 **************************************************************************** FLOW PROCESS FROM NODE 303.00 TO NODE 304.00 IS CODE= 31 >>>>>COMPUTE PIPE-FLOW TRAVEL TIME THRU SUBAREA<<<<< >>>>>USING COMPUTER-ESTIMATED PIPESIZE (NON-PRESSURE FLOW)<<<<< ELEVATION DATA: UPSTREAM(FEET) = 241.70 DOWNSTREAM(FEET) = 222.00 FLOW LENGTH(FEET) = 75.00 MANNING'S N = 0.013 DEPTH OF FLOW IN 12.0 INCH PIPE IS 7.0 INCHES PIPE-FLOW VELOCITY(FEET/SEC.) = 23.47 ESTIMATED PIPE DIAMETER(INCH) = 12.00 NUMBER OF PIPES= 1 PIPE-FLOW(CFS) = 11.14 PIPE TRAVEL TIME(MIN.) = 0.05 Tc(MIN.) = 7.71 LONGEST FLOWPATH FROM NODE 600.00 TO NODE 304.00 = 651.00 FEET. END OF STUDY SUMMARY: TOTAL AREA(ACRES) = PEAK FLOW RATE(CFS) = 2.7 TC(MIN.) = 11.14 END OF RATIONAL METHOD ANALYSIS Page 7 7.71 APPENDIX A Hydrology Support Material 0 C') 0 ,-... .,.... .,.... io .,.... 0 ,-... ..... ..- 0 0 0 ,-... .,.... ..- io "<t 0 c.o ..- 0 C') 0 c.o ..-..- io ..- 0 c.o ..-.,.... ~3030' ~:..--::~~-~ 11 .... :llif? l I I I I I # • ....... • ..... . . . ' .· ~ / . \t-. : ' ... ·· ,.: ... ;-.. ·· • .. :, ......... ..·· ,• .... • v.-s. ..· ·' ,• G.· ............ .· ,. ~•:-' . "'· . . _ .. ., . .. • n•. /'I ...... ...·v .... . . . ,....... ,,.... ., ... _ ... !l.o• ..-.. ~ v . : , . . . . . ...... .. -.... ..... '-.. .. ······:.-.-_-:::::::·= ... :· ····..... ··· ... :~::··... · .. . ,····. ··. ··. ... .. ... • • • • • • .•."I .,_ • •.t-, • • • IJ' r. .. v-, • . ·~ •• ·o ·~ .. . (}-. --·. ~ .. .. . . ..... -...... " . ·. . . . . ........ -.... . . •· . . ··•. .. ...... ·. .. .. .. .. . .... . .. I f I •' I I (•••b ~~---..,__ : r .. o ·. \ 33°15 \ ,.-···: :.,_ ·, ', -~ : .. \,. ! ..... - . . . . . . . . . . . . . . . 33°30' : ·. ..· .. .. . . . .· ~ : .·· .... •' . . . . . . . . . . .· . . . . ) .. • ·. .. . ' ' . ..... 2-.5·' 33°15' •••••••••••••••• I ·-.. _ .... .. , -~ •. ·• ~-! .... _.... ~ . -.. -· ........ . . .... .. -.. -... . ·. . . . . . . • ... '\ CJ) j,,. :.. ·;.T\ ··"""-·-•• '"i, ·-~·-· ·, . ... .···•-.... -• . . ' ·•. ·· .. ..... --"' ... ··. ::,.-·· ...... .: ,--~ ... -I) ! : ' . "' ; .. ~ . . 0 ! -· .---r---, . .A' ···· .... ,.... 33°00' 0 0 0 ~ ~ -:, .... -----.. , . . . t._~4 / ·;.r • .. . ..---;' :s.O. COUNiV 7 . , . ... ... . . . .... . . . . I I I • I I : •, ~ : tl' ... ·. ~ ·Q , 1 I I t I • \, I • I ' ... ·. '•.. .. ........... .. . . . . . . . . . . . . . . ..•-, ~ .. • \ " ... . .... _ .... ·&·. -...... ! • • ·····•, ,t"I 1.. •• • ..... • •••• '->-Jfr . -•• · 1,. ,.· 33°00' 3 '"C CD ~-0) \ ..................... . ... ~ ....... , '·A"\ ··• ... ·· .. ··.. \ '""'.' ·-..... ·-.... ',, .... \ ........... ---- 32°45' 32°30' r T t • ,-0 t C') t t t ,-0 ,-... ..-..-~ ~ l . • ,-io ..-0 ,-... + ,. .,.... ..- 0 0 0 ,-... ..-..- ,.---..... I ,' • _:T .·· .!..·· I LO t "<t <D ..-.,.... . ' . . --...... , Q . ---...... ~ .. ........ -..... " . ·•' s .... · ,:••.'",~-: ... . ~ M e X ' C g 0 c.o .,.... ..- ..... ··. \ ... . •• •• \t, •• \ . . " " I I I "-0 •• I I I 'I • ' ♦• l • • • I I I •• I I I •, ··---· : : \ . _, # • . . . _ ...... , ",,, . c.> ~6 io ..- 0 c.o ..-..- . \ . . . a2°45' 32°30' County of San Diego Hydrology Manual .•&i ~ .. '>-• ' , .. :::.~~~- . . ~~ .,~~. Rainfall lsopluvials 100 Year Rainfall Event -6 Hours lsopluvial (inches) DPW ~GIS s1iiG1s ~-:1Pwlic!K,Gt1t'S ~lrfo'Tf.~~n-\Xie H.iv..: San D1t:go C:cm:rcJ! N + s 3 0 3 ~ THIS MAP IS PROVIDED WITHOUT WARRANTY OF ANY KIND, El'THER EXPRESS OR IMPLIED, INQ.UDING, BUT NOT LIMITED TO. THE IMPLIED WARRANTIES OF MERCHANTABILITY AND FITNESS FOR A PARTICULAR PURPOSE. Cowight SanGIS. Al RijJllls Rese<ved. This pn,duds nv,y ~ '""""-"on from tt,e SANDAG Rog;onal lnfonnatlon s---be reproduced without tt,e Mitlen-ofSANOAG. This -nv,ycx,nta;n --.... been reproduced ---by-BmttwsMaps. Miles 10.0 9.0 8.0 7.0 6.0 5.0 4.0 3.0 2.0 ~ 0 1 -5 c 1,0 ~0.9 ~0.8 ~0.7 0.6 0.5 0.4 0.3 0.2 0.1 .,...,. "'I",,. ......... ..... ... .... r,,.. ,.._ ... I",,. .., I""" I' .... r,,.. .. N. • i"o,,, .... , .... I",. .... , I'._ i-...._"' ..... .... .., i"o.i-,.. "i-,.. "'i-.. i"' .... r-..;,_ I",,. ..... .. ""' .... , .... '" .... " ,. .. ~ .. , .. "" i...., ...... ~~ "'' ..... .. ,..... ... "'!",. ... .. I"' .. .. .. i ..... ' ..... 'i-.. '"' ....... ~~ ... ~ .... , I= 3.2 in/hr ..... .. .. ~~ -r-,., I' .. I .... ... " .. .. ~ ! ...... .. ..... " .... '" .... ~ ' .... "r,,.. ..... "' ! .... , '" ~ ..... i,,. .. i-,.. .... .. .. .... I'-. ~~ "'i-.. ~ ..... .... i ' ..... ~ I .. I i ! ----+------------· -+---- I I \;-20 min I I Ill I I 111 5 6 7 8 9 10 15 20 30 Minutes I I I ! I I ' I .. ...... ~ .... .... .. .. ~ .. ~ J ' .... i ~ .... i .. "' .... i .. ~ .... I .. .. I .... I r i .... ""' I .... i I I ! I I I I 40 50 Duration ! I I i ! I EQUATION I = 7.44 P5 D-0.645 I = Intensity (in/hr) P5 = 6-Hour Precipitation (in) D = Duration (min) I ' I ! : I i r-,.. ! i ' I ,...i I I 11 ~ r-,.. ~~ I i' ... "" I ~ ..... ,I I• ... "' ~~ .... .... "' .... .. , .. 11 ► I• .... ....... .. , .. i r-,.. ...... .. "i-,.. ' " .... ~ -'I~ ,. "' .... ~ "'I",. ..... ....... .. ... r,,.. ;' .. .. .. 1 r-,.. , ... "'i..... ~~ ,,,. I ,. 'i-,.. I .. "' 11"1,~ I~ ,, •'! I r-. , .. 'r, ' ..... •11 I",. 1 .. I•" '~ Ii r-,.. .. ~, .. !" ,, 11 ! I",. 'i ,. -' ,. ,: ~ -f--~ ,. + I : I -~ -i : 2 3 4 Hours I I I 5 6 0) ± 0 !:; '1) ~ 6.0 i 5.5,:,: 5.0 g 4.5 '§' 0 4.0 i6 3.5 ~ 2.5 2.0 1.5 1.0 Intensity-Duration Design Chart -Example Directions for Application: (1) From precipitation maps determine 6 hr and 24 hr amounts for the selected frequency. These maps are included in the County Hydrology Manual (10, 50, and 100yrmaps included in the Design and Procedure Manual). (2) Adjust 6 hr precipitation (if necessary) so that it Is within the range of 45% to 65% of the 24 hr precipitation (not applicaple to Desert). (3) Plot 6 hr precipitation on the right side of the chart . (4) Draw a line through the point parallel to the plotted lines. (5) This line is the intensity-duration curve for the location being analyzed. Appllcatlon Form: (a) Selected frequency~ year p (b) P6 = _3_ in., p24 = ~ .~ = ~ %(2l 24 (c) Adjusted p6<2) = _3 __ in. (d) tx = _±Q_, min . (e) I = ~ in./hr. Note: This chart replaces the Intensity-Duration-Frequency curves used since 1965. P6 1 1.5 2 2.5 3 3.5 4 4.5 5 5.5 6 Duration I I I I I I I I I I I 5 2.63 3.95 5.27 6.59 7 90 9.22 10.54 11.86 1317 14.49 15.81 7 2.12 3.18 4.24 5.30 . 6.36 7 42 8.48 9.54 10.60 11.66 12.72 10 1.68 2.53 3.37 4.21 505 590 6 74 758 8.42 9.27 10 11 15 130 1 95· 2.59 3.24: 3.89 4.54 519 5.84 6.49 7.13 778 20 1 08 1 62. 2.15 2.69 3.23° 3.77 4.31 4.85 5.39 5.93 6.46 25 0 93 1.40 1.87 2.33 2.80 327 3.73 4.20 4.67 5.13 5.60 30 0.83 1.24 1.66 207 2.49 2 90 3.32 3.73 4.15 456 4.98 40 0.69 1 03 138 1.72 2.07 241 276 310 3.45 3 79 413 50 0.60 0.90 1.19 1 49 1.79 2.09 2.39 2.69 2.98 3.28 3.58 60 0.53 080 106 1.33 1 59 1.86 2 12 2.39 2.65 292 3.18 90 041 061 082 1.02 1 23 1.43 1 63 1 84 2.04 2.25 2.45 120 0.34 051·0.68 0.85 1 02 119 1 36 1 53 1.70 187 204 150 029 0.44. 059 0 73 088 1.03 118 1.32 1.47 1.62 1 76 180 0 26 0.39 0 52 0 65 o 15· o 91 1 04 1 18 1.31 1.44 1.57 240 022 0 33 0 43 054 065 0.76 0.87 0.98 108 1 19 1.30 300 019 0.28 0.38 0.47 0.56 0.66 0.75 0.85 0.94 1.03 113 360 0.17 025·0.33 042 0.50 0.58 067 0.75 0.84 0.92 1.00 FIGURE ~ San Diego County Hydrology Manual Date: June 2003 Table 3-1 Section: Page: RUNOFF COEFFICIENTS FOR URBAN AREAS Land Use Runoff Coefficient ''C" Soil T e NRCS Elements Count Elements % IMPER. A 8 Undisturbed Natural Terrain (Natural) Permanent Open Space 0* 0.20 0.25 Low Density Residential (LOR) Residential, 1.0 DU/ A or less 10 0.27 0.32 Low Density Residential (LOR) Residential, 2.0 DU/ A or less 20 0.34 0.38 Low Density Residential (LOR) Residential, 2.9 DU/A or less 25 0.38 0.41 Medium Density Residential (MOR) Residential, 4.3 DU/A or less 30 0.41 0.45 Medium Density Residential (MOR) Residential, 7.3 DU/A or less 40 0.48 0.51 Medium Density Residential (MOR) Residential, 10.9 DU/A or less 45 0.52 0.54 Medium Density Residential (MOR) Residential, 14.5 DU/A or less 50 0.55 0.58 High Density Residential (HOR) Residential, 24.0 DU/ A or less 65 0.66 0.67 High Density Residential (HOR) Residential, 43.0 DU/A or less 80 0.76 0.77 Commercial/Industrial (N. Com) Neighborhood Commercial 80 0.76 0.77 Commercial/Industrial (G. Com) General Commercial 85 0.80 0.80 Commercial/Industrial (O.P. Com) Office Professional/Commercial 90 0.83 0.84 Commercial/Industrial (Limited I.) Limited Industrial 90 0.83 0.84 Commercial/Industrial (General I.) General Industrial 95 0.87 0.87 C 0.30 0.36 0.42 0.45 0.48 0.54 0.57 0.60 0.69 0.78 0.78 0.81 0.84 0.84 0.87 3 6 of26 D [III] 0.41 0.46 0.49 0.52 0.57 0.60 0.63 0.71 0.79 0.79 0.82 ~ 5 0.87 *The values associated with 0% impervious may be used for direct calculation of the runoff coefficient as described in Section 3.1.2 (representing the pervious runoff coefficient, Cp, for the soil type), or for areas that will remain undisturbed in perpetuity. Justification must be given that the area will remain natural forever (e.g., the area is located in Cleveland National Forest). DU/ A = dwelling units per acre NRCS = National Resources Conservation Service 3-6 San Diego County Hydrology Manual Date: June 2003 Section: Page: 3 12 of 26 Note that the Initial Time of Concentration should be reflective of the general land-use at the upstream end of a drainage basin. A single lot with an area of two or less acres does not have a significant effect where the drainage basin area is 20 to 600 acres. Table 3-2 provides limits of the length (Maximum Length (LM)) of sheet flow to be used in hydrology studies. Initial Ti values based on average C values for the Land Use Element are also included. These values can be used in planning and design applications as described below. Exceptions may be approved by the "Regulating Agency" when submitted with a detailed study. Table 3-2 MAXIMUM OVERLAND FLOW LENGTH (LM) & INITIAL TIME OF CONCENTRATION (Ti) Element* DU/ .5% 1% 2% 3% 5% 10% Acre LM Ti LM Ti LM Ti LM Ti LM Ti LM Ti Natural 50 13.2 70 12.5 85 10.9 100 10.3 100 8.7 100 6.9 LOR 1 50 12.2 70 11.5 85 10.0 100 9.5 100 8.0 100 6.4 LOR 2 50 11.3 70 10.5 85 9.2 100 8.8 100 7.4 100 5.8 LOR 2.9 50 10.7 70 10.0 85 8.8 95 8.1 100 7.0 100 5.6 MOR 4.3 50 10.2 70 9.6 80 8.1 95 7.8 100 6.7 100 5.3 MOR 7.3 50 9.2 65 8.4 80 7.4 95 7.0 100 6.0 100 4.8 MOR 10.9 50 8.7 65 7.9 80 6.9 90 6.4 100 5.7 100 4.5 MOR 14.5 50 8.2 65 7.4 80 6.5 90 6.0 100 5.4 100 4.3 HOR 24 50 6.7 65 6.1 75 5.1 90 4.9 95 4.3 100 3.5 HOR 43 50 5.3 65 4.7 75 4.0 85 3.8 95 3.4 100 2.7 N.Com 50 5.3 60 4.5 75 4.0 85 3.8 95 3.4 100 2.7 G.Com 50 4.7 60 4.1 75 3.6 85 3.4 90 2.9 100 2.4 O.P./Com 50 4.2 60 3.7 70 3.1 80 2.9 90 2.6 100 2.2 Limited I. 50 4.2 60 3.7 70 3.1 80 2.9 90 2.6 100 2.2 General I. 50 3.7 60 3.2 70 2.7 80 2.6 90 2.3 100 1.9 *See Table 3-1 for more detailed description 3-12 lo !:: Hydrologic Soil Group-San _,ego County Area, California Map Scale: 1: 2,260 if pmed on A landscape (11" X 8.5") sheet ----====-------========Meters 0 8J 120 18J ----====-------=======feet 0 100 200 400 Map projection: Web Mercator Comero:xirtinates: WGS84 ElXl Edge ocs: lJTM Zale 11N WGS84 USDA Natural Resources Web Soil Survey National Cooperative Soil Survey :iiiiiii Conservation Service 8/27/2019 Page 1 of 4 33" 7 27' N 33" 7 17 N Hydrologic Soil Group-San ~.c:go County Area, California MAP LEGEND MAP INFORMATION Area of Interest (AOI) Area of Interest (AOI) Soils Soil Rating Polygons D A D AID D B D BID D C D CID D D D Not rated or not available Soil Rating Lines -A -AID -B -B/D C -CID -D --Not rated or not available Soil Rating Points ■ A ■ AID ■ B ■ B/D USDA Natural Resources •-Conservation Service □ ■ C CID ■ D □ Not rated or not available Water Features Streams and Canals Transportation +++ Rails -Interstate Highways -US Routes Major Roads Local Roads Background • Aerial Photography Web Soil Survey National Cooperative Soil Survey The soil surveys that comprise your AOI were mapped at 1 :24,000. Warning: Soil Map may not be valid at this scale. Enlargement of maps beyond the scale of mapping can cause misunderstanding of the detail of mapping and accuracy of soil line placement. The maps do not show the small areas of contrasting soils that could have been shown at a more detailed scale. Please rely on the bar scale on each map sheet for map measurements. Source of Map: Natural Resources Conservation Service Web Soil Survey URL: Coordinate System: Web Mercator (EPSG:3857) Maps from the Web Soil Survey are based on the Web Mercator projection, which preserves direction and shape but distorts distance and area. A projection that preserves area, such as the Albers equal-area conic projection, should be used if more accurate calculations of distance or area are required. This product is generated from the USDA-NRCS certified data as of the version date(s) listed below. Soil Survey Area: San Diego County Area, California Survey Area Data: Version 13, Sep 12, 2018 Soil map units are labeled (as space allows) for map scales 1 :50,000 or larger. Date(s) aerial images were photographed: Nov 3, 2014-Nov 22,2014 The orthophoto or other base map on which the soil lines were compiled and digitized probably differs from the background imagery displayed on these maps. As a result, some minor shifting of map unit boundaries may be evident. 8/27/2019 Page 2 of 4 Hydrologic Soil Group-San Diego County Area, California Hydrologic Soil Group Map unit symbol Map unit name Rating Acres in AOI Percent of AOI HrD2 t HrE2 Huerhuero loam, 9 to 15 D percent slopes, eroded Huerhuero loam, 15 to D 30 percent slopes, eroded 8.0 4.8 Totals for Area of Interest t I 12.8 Description Hydrologic soil groups are based on estimates of runoff potential. Soils are assigned to one of four groups according to the rate of water infiltration when the soils are not protected by vegetation, are thoroughly wet, and receive precipitation from long-duration storms. The soils in the United States are assigned to four groups (A, B, C, and D) and three dual classes (AID, 8/D, and C/D). The groups are defined as follows: Group A. Soils having a high infiltration rate (low runoff potential) when thoroughly wet. These consist mainly of deep, well drained to excessively drained sands or gravelly sands. These soils have a high rate of water transmission. Group B. Soils having a moderate infiltration rate when thoroughly wet. These consist chiefly of moderately deep or deep, moderately well drained or well drained soils that have moderately fine texture to moderately coarse texture. These soils have a moderate rate of water transmission. Group C. Soils having a slow infiltration rate when thoroughly wet. These consist chiefly of soils having a layer that impedes the downward movement of water or soils of moderately fine texture or fine texture. These soils have a slow rate of water transmission. Group D. Soils having a very slow infiltration rate (high runoff potential) when thoroughly wet. These consist chiefly of clays that have a high shrink-swell potential, soils that have a high water table, soils that have a claypan or clay layer at or near the surface, and soils that are shallow over nearly impervious material. These soils have a very slow rate of water transmission. If a soil is assigned to a dual hydrologic group (AID, 8/D, or C/D), the first letter is for drained areas and the second is for undrained areas. Only the soils that in their natural condition are in group Dare assigned to dual classes. USDA Natural Resources --.a Conservation Service Web Soil Survey National Cooperative Soil Survey 62.2% 37.8% 100.0% 8/27/2019 Page 3 of 4 Hydrologic Soil Group-San Diego County Area, California Rating Options Aggregation Method: Dominant Condition Component Percent Cutoff: None Specified Tie-break Rule: Higher USDA Natural Resources --,,_ Conservation Service Web Soil Survey National Cooperative Soil Survey 8/27/2019 Page 4 of 4 PER MAP 11288 BASIN EX-3 ' AREA = 114,945 SF --- 2.639AC ' 1; _11 ' \ \ \ \ \-1 l_ -l \ \ 'I , -,-__,._ ---\'--v" I ASINEX--3.2 \ --l 40 0 LEGEND PROPeR1YBOUNDARY CEIVTERLINE OF ROAD ADJACENT PROPERTY LINE I R/GHT-OF-WI\Y EXISTING CONTOUR LINE EXISTING PATH OF 1RAVEL EXISTING MAJOR DRAINAGE BASIN BOUNDARY EXISTING MAJOR DRAINAGE BASIN BOUNDARY DRAINING OFFS/TE (ONLY CONSIDERED FOR TOTAL PEAK DISCHARGE LEAVING SITE) EXISTING MINOR DRAINAGE BASIN BOUNDARY -------- ___ ,, __ _ ------------ BASIN EX-1-AREA CALCULATIONS TOTAL DRAINAGE BASIN AREA MINOR DRAINAGE BASIN AREA (EX-1. 1) MINOR DRAINAGE BAS/NAREA(EX-1.1) 161,570 SF /3.709AC) 34,617 SF (0.795AC) 126,953 SF (2.914AC) Cn Q100 0.85 16.SCFS BASIN EX-2 -AREA CALCULATIONS TOTAL BASIN AREA Cn Q100 131,805 SF (3.026AC) 0.85 15.9CFS BASIN EX-3-AREA CALCULATIONS TOTAL BASIN AREA Cn Q100 114,945 SF (2.639AC) 0.35 (INITIAL OVERLAND FLOI-\? 0.85 (OFFICE PROFESSIONAL I COMM) 11.1 CFS BASIN EX-4 -AREA CALCULATIONS TOTAL BASIN AREA Cn Q100 67,720SF (1.555AC) 0.85 9.4 CFS EXISTING HYDROLOGY EXHIBIT RAF FUSION --1950 CAMINO VIDA ROBLE CITY OF CARL SBAD PASCO LARET SUITER GRAPHIC SCALE: 1" = 40' & ASSOCIATES 40 80 120 CIVIL ENGINEERING + LAND PLANNING + LAND SURVEYING 555 Nonla Blpway 101, Ste A. Sowl& Beada. CA 92075 ph 858.259.8212 I fie 858.259.4812 I plleenlJlneerlng CGJD PLSA 3140-01 LEGEND PROPERTY BOUNDARY CENTERLINE OF ROAD ADJACENT PROPERTY LINE I RIGHT-OF-WAY EXISTING CONTOUR LINE PROPOSED CONTOUR LINE PROPOSED PA TH OF TRAVEL PROPOSED MAJOR DRAINAGE BASIN BOIJNDARY PROPOSED MAJOR DRAINAGE BASIN BOIJNOARY DRAINING OFFS/TE (NOT CONSIDERED IN ANALYSIS} PROPOSED MINOR DRAINAGE BASIN BOIJNDARY GRAPHIC SCALE: 1" = 40' 80 120 -------- --···-------------- PROPOSED HYDROLOGY EXHIBIT RAF FUSION-1950 CAMINO VIDA ROBLE CITY OF CARLSBAD PASCO LARET SUITER & ASSOCIATES CIVIL ENGINEERING + LAND PLANNING + LAND SURVEYING 595 North H1pway 101, Ste A, Solua Beach, CA 92075 ph 151.25!1.1212 ( & 151.25!1.4812 ( p~COID Pl.SA 3140-01