HomeMy WebLinkAbout2021-11-16; City Council; Resolution 2021-254RESOLUTION NO. 2021-254
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CARLSBAD,
CALIFORNIA, APPROVING THE PLANS AND SPECIFICATIONS AND
AUTHORIZING THE CITY CLERK TO ADVERTISE FOR BIDS FOR THE MAGNOLIA
AVENUE STORM DRAIN IMPROVEMENTS PROJECT -PHASE I AS PART OF
THE CITYWIDE DRAINAGE IMPROVEMENT PROGRAM
Exhibit 1
WHEREAS, the City Council of the City of Carlsbad, California has determined it necessary,
desirable and in the public interest to construct the Phase I portion of the Magnolia Avenue Storm
Drain Improvements Project as part of the Citywide Drainage Improvement Program, Capital
Improvement Program, or CIP, Project No. 6608 (Project); and
WHEREAS, the plans, specifications and contract documents for Phase I of the Project, have
been prepared and are on file at the City Clerk's office and are incorporated herein by reference; and
WHEREAS, Carlsbad Municipal Code Section 3.28.080{E) requires the City Council to approve
plans and specifications for all construction projects that are to be formally bid upon when the value
exceeds the $200,000 limit established by the Public Contract Code, including the alternative provisions
of the Uniform Public Construction Cost Accounting Act; and Phase I of the Project is estimated to cost
$712,252, not including construction contingency and construction management costs, so the Project
is subject to the requirement; and
WHEREAS, the Project is funded with Gas Tax and Infrastructure Replacement Funds, and
sufficient funds are available to complete Phase I of the Project; and
WHEREAS, the Project was previously evaluated in the Final Environmental Impact Report (FEIR
04-02, SCH No. 2006041066}, dated December 2007, for the City of Carlsbad Drainage Master Plan
Update and no further California Environmental Quality Act (CEQA) documentation is required per
CEQA Guidelines Section 15162.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad, California, as
follows:
1. That the above recitations are true and correct.
2. That the plans, specifications and contract documents for the Magnolia Avenue Storm
Drain Improvements Project -Phase I as part of the Citywide Drainage Improvement
Program, CIP Project No. 6608, are hereby approved.
Nov. 16, 2021 Item #5 Page 5 of 20
3. That the City Clerk is hereby authorized and directed to publish, in accordance with state
law, a notice to contractors inviting bids for construction of Phase I of the Project, in
accordance with the plans, specifications and contract documents referred to herein.
PASSED, APPROVED AND ADOPTED at a Regular Meeting of the City Council of the City of Carlsbad on
the 16!!!. day of November 2021, by the following vote, to wit:
AYES:
NAYS:
ABSENT:
Hall, Blackburn, Bhat-Patel, Acosta, Norby.
None.
None.
MATT HALL, Mayor