HomeMy WebLinkAbout2021-12-16; El Camino Real Capital Improvement Program Projects Status Updates (District 2); Gomez, PazTo the members of the:
ITY COUNCIL
Oat CA ~CC ..JL
CM L A DCM (3).L
Council Memorandum
Dec. 16, 2021
To: Honorable Mayor Hall and Members of the City Council
From: Paz Gomez, Deputy City Manager, Public Works
{city of
Carlsbad
Memo ID #2021229
Via: Geoff Patnoe, Assistant City Manager ~
Re: El Camino Real Capital Improvement Program Projects Status Updates (District 2)
This memorandum provides status updates on existing Capital Improvement Program, or CIP,
projects along El Camino Real that are currently in either design or construction phases.
Background
Staff are currently working on seven transportation-related CIP projects along El Camino Real
that are in either design or construction phases, as shown on location maps provided as -
Attachments A and B. Staff provided updates on some of these projects through a Council
nquiry earlier this month (Council Inquiry of Nov. 15, 2021, Reference# C001500-111521). This
memorandum provides further detail on these projects.
Staff also provided a Council Memorandum dated May 13, 2021 (Attachment C), on the El
Camino Real and Cannon Road Intersection Improvements, CIP Project Nos. 6042 and 6056.
Discussion
The El Camino Real corridor generally runs north and south through the city. Seven
transportation projects are currently in design or construction along this corridor. The summary
below provides a brief description and status update for each of these projects:
CIP Proiect Nos. 6042 and 6056, Phase I -El Camino Real Bridge Improvements at Cannon Road
On Feb. 16, 2021, the City Council adopted Resolution No. 2021-044, awarding a contract to
Hazard Construction Company for construction of Phase I of the project. Phase I is currently
under construction and provides improvements to enhance pedestrian mobility on El Camino
Real at Cannon Road in both directions.
Phase I includes construction of a new separate pedestrian bridge on northbound El Camino
Real over the Agua Hedionda Creek to provide new access for pedestrians. It also includes
construction of a new sidewalk, curb and gutter on both northbound and southbound sides of
the road, and a barrier wall on northbound El Camino Real. The contractor anticipates installing
the new pre-manufactured pedestrian bridge on northbound El Camino Real (east side of the
road) by the end of January 2022.
Public Works Branch
Transportation Department
1635 Faraday Avenue I Carlsbad, CA 92008 I 760-602-2730 t
Council Memo -El Camino Real CIP Projects Status Updates (District 2)
Dec. 16,2021
Page 2
The work on northbound El Camino Real included installation of micropiles1 to depths
exceeding 100 feet to support the new pedestrian bridge. That portion of the work took longer
than expected due to challenges related to installation of micropiles. The contractor has since
recovered from those delays and is back on schedule.
New railings have already been installed on both sides of the existing bridge over the Agua
Hedionda Creek. A wider sidewalk has also been installed on southbound El Camino Real (west
side of the existing bridge). The contractor anticipates completing the remaining work,
including utility connections, landscape, irrigation and hardscape by March 2022.
CIP Project No. 6042, Phase II -El Camino Real and Cannon Road Intersection Improvements
On Aug. 31, 2021, the City Council adopted Resolution No. 2021-198, approving the plans and
specifications and authorizing advertisement for bids for Phase II of the El Camino Real and
Cannon Road Improvements project. Phase II will realign the median and re-stripe northbound
El Camino Real near the Cannon Road intersection. This re -striping will provide an additional
northbound vehicle through lane and an enhanced northbound dedicated bike lane. In
addition, the project will maintain the existing left-and right-turn only lanes onto Cannon Road .
Staff have reviewed the bids received and will return to the City Council in January 2022 with a
recommendation to award a construction contract to the lowest responsible and responsive
bidder. To reduce potential construction conflicts due to overlapping construction activities,
construction of Phase II will begin upon completion of Phase I, which is expected to be in
March 2022.
CIP Project No. 6094 -El Camino Real Widening from Sunny Creek Road to Jackspar Drive
This widening project is in the design and land acquisition phase. The project will provide
complete street improvements matching adjacent, multi-modal roadway segments along
northbound El Camino Real from just south of Sunny Creek Road to Jackspar Drive. It includes
creating a complete street with buffered bike lanes, sidewalks and a consistent six-lane arterial
roadway facility for this segment.
Additional project improvements include installation of additional streetlights, storm drain
improvements, retaining walls, striping modifications and utility relocations. Staff have been
coordinating closely with adjacent property owners, including those involved in right-of-way
acquisition, and keeping them apprised of the project's progress.
Staff plan to present this project to the City Council for approval of plans and specifications and
authorization to bid in summer 2022.
1 Micropiles are part of the bridge foundation that extend deep into the ground for stability.
Council Memo -El Camino Real CIP Projects Status Updates (District 2)
Dec. 16,2021
Page 3
CIP Proiect No. 6071 -El Camino Real and College Boulevard Intersection Improvements
On Oct. 13, 2020, the City Council adopted Resolution No. 2020-201, awarding a contract to
Blue Pacific Engineering for construction of the project. Construction for this project has
recently been completed.
The project was designed and constructed to improve mobility for pedestrians and bicyclists
and upgrade existing curb ramps and crosswalks to meet current Americans with Disabilities Act
(ADA) standards. The improvements included enhanced bike lanes and pedestrian access, high-
visibility crosswalks for all legs of the intersection and traffic signal timing modifications to
improve traffic flow. These improvements upgraded the existing bike lanes and pedestrian
ramps to current design standards.
The improvements also included modification to the El Camino Real median to accommodate a
left-turn only lane on southbound El Camino Real onto eastbound College Boulevard, three
southbound vehicle through lanes on El Camino Real, a southbound dedicated bike lane on El
Camino Real with green paint approaching the intersection and a southbound right turn-only
lane on El Camino Real onto westbound College Boulevard.
CIP Proiect No. 6072 -El Camino Real Widening from Poinsettia Lane to Camino Vida Roble
This project is in the final design and right-of-way acquisition phase. The project is partially
funded by a federal earmarked repurposed fund program. The project will provide an additional
northbound vehicle through lane from Poinsettia Lane to Camino Vida Roble.
In addition, the project will construct a sidewalk along northbound El Camino Real to address a
sidewalk gap north of Cinnabar Way. Additional project improvements will include installation
of streetlights, storm drain improvements, retaining walls, striping modifications, median
landscaping and utility relocations. The final design and right-of-way acquisition are expected to
be completed in summer 2022.
CIP Proiect No. 6051-El Camino Real Widening from Arena/ Road to La Costa Avenue
This project is in the design and environmental phase and addresses operational segments
along El Camino Real from Arenal Road to La Costa Avenue. This project includes widening
southbound El Camino Real to a six-lane arterial with buffered bike lanes and separated
pedestrian bridges over San Marcos Creek. The project also involves utility relocations and
right-of-way acquisition. Staff have also been coordinating closely with the Batiquitos Lagoon
Foundation to include two new observation desks on the west side of El Camino Real.
Staff anticipate completing final design and environmental documents in fall 2023.
CIP Proiect No. 6001-20OL -2020-21 Pavement Overlay
On Aug. 31, 2021, the City Council adopted Resolution No. 2021-191, authorizing award of this
construction project to All American Asphalt. This project includes resurfacing the following
Council Memo -El Camino Real CIP Projects Status Updates (District 2)
Dec. 16,2021
Page 4
streets: El Camino Real between Cannon Road and College Boulevard, El Camino Real between
Arenal Road and Levante Street, and Batiquitos Drive between Poinsettia Lane and Camino De
Las Ondas.
Challenges have arisen regarding the resurfacing methodology, so staff intend to revisit this
project in early 2022 and will subsequently provide an update to the City Council.
Next Steps
Staff plan to continue making progress on the projects as listed below:
CIP Proiect Nos. 6042 and 6056, Phase I -El Camino Real Bridge Improvements at Cannon Road
The contractor anticipates completing the remaining work, including utility connections,
landscape, irrigation and hardscape in March 2022.
CIP Proiect No. 6042, Phase II -El Camino Real and Cannon Road Intersection Improvements
Staff are scheduled to present this project to the City Council for award of a construction
contract to the lowest responsible and responsive bidder in January 2022. Construction of
Phase II will begin upon completion of Phase I, which is expected to be in March 2022.
CIP Proiect No. 6094 -El Camino Real Widening from Sunny Creek Road to Jackspar Drive
Staff are currently working on acquiring additional right-of-way and coordinating utility
relocation. Staff plan to present this project to the City Council for approval of plans and
specifications and authorization to bid in summer 2022.
CIP Proiect No. 6071 -El Camino Real and College Boulevard Intersection Improvements
This project has been completed.
CIP Proiect No. 6072 -El Camino Real Widening from Poinsettia Lane to Camino Vida Roble
Staff are currently working on acquiring additional right-of-way and coordinating utility
relocation. Pending federal a·pproval, staff plan to present this project to the City Council for
approval of plans and specifications and authorization to bid in summer 2022.
CIP Proiect No. 6051-El Camino Real Widening from Arena/ Road to La Costa Avenue
Staff expect completion of the final design and environmental documents for this project in fall
2023.
CIP Proiect No. 6001-20OL-2020-21 Pavement Overlay
Staff plan to revisit this project in early 2022 and subsequently will provide an update to the
City Council.
Attachments: A. El Camino Real CIP Improvements location map
B. CIP Project No. 6001-20OL, 2020-21 Pavement Overlay, location map
C. Council Memorandum dated May 13, 2021
Council Memo -El Camino Real CIP Projects Status Updates (District 2)
Dec. 16,2021
Page 5
cc: Scott Chadwick, City Manager
Celia Brewer, City Attorney
Gary Barberio, Deputy City Manager, Community Services
Laura Rocha, Deputy City Manager, Administrative Services
Robby Contreras, Assistant City Attorney
Tom Frank, Transportation Director/City Engineer
Jeff Murphy, Community Development Director
Kristina Ray, Community & Engagement Director
Hossein Ajideh, Engineering Manager
John Kim, City Traffic Engineer
Nathan Schmidt, Transportation Planning and Mobility Manager
Babaq Taj, Engineering Manager
Scott Lyle, Senior Engineer
Brandon Miles, Associate Engineer
)
z < w u 0
~
LI. ~
c..o\lege Blvd
Encinitas
ATTACHMENT A
Poinsettia Ln
Alga Rd
{city of ,
Carlsbad
BA TIQUITOS DRIVE
POINSETTIA LANE TO
CAMINO DE LAS ONDAS
LOCATION
EL CAMINO REAL
ARENAL ROAD TO LEVANTE STREET
PROJECT NAME
MAP
ATTACHMENT B
EL CAMINO REAL
CANNON ROAD TO COLLEGE BOULEVARD
VICINITY MAP
NOT TO SCALE
EXHIBIT
2020-21 PAVEMENT OVERLAY
PROJECT
NUMBER
6001-20OL 2
PLOTTED BY: BENJAMIN ARP PLOT DATE: 08/04/2020 PATH: S:\Benjamin_Arp\Location Map\C/P_6001\20200L_LocationMap.dwg
To the members of the:
,.J ITY COUNCIL
Date ?/J~f-i \ CA _y_ CC _L
CM ✓ ACM ✓ DCM(3) ✓ ---~
May 13, 2021
ATTACHMENTC
Council Memorandum
To: Honorable Mayor Hall and Members of the City Council
From: Paz Gomez, Deputy City Manager, Public Works
Via: Geoff Patnoe, Assistant City Manager {ff
{city of
Carlsbad
Memo ID #2021101
Re: El Camino Real and Cannon Road Intersection Improvements Project Update
(District 2)
This memorandum provides an update on the El Camino Real and Cannon Road Intersection
Improvements, Capital Improvement Program (CIP) Project Nos. 6042 and 6056 (Project).
Background
The El Camino Real and Cannon Road Intersection Improvements Project (Project) involves two
phases. Phase I of the Project, which is currently under construction, will provide improvements
to enhance pedestrian mobility at the intersection of El Camino Real and Cannon Road. Phase I
will construct a separate pedestrian bridge over the Agua Hedionda Creek to provide new
access for pedestrians and bring sidewalks up to the current design standards. On
Feb. 16, 2021, the City Council adopted Resolution No. 2021-044 awarding a contract to Hazard
Construction Company for construction of Phase I.
Phase II of the Project will realign the median and re-stripe northbound El Camino Real near the
Cannon Road intersection to provide an additional through lane to meet the standard
requirement for this arterial roadway. In addition, it will provide an enhanced dedicated bike
lane in the northbound direction and maintain the existing left and right turn lanes onto
Cannon Road.
Phases I and II of the Project were presented to the Traffic and Mobility Commission on
April 6, 2020 and Sept. 8, 2020, respectively.
Discussion
Two CIP projects are currently under construction along El Camino Real between College
Boulevard and Cannon Road. One project is the El Camino Real and College Boulevard
Intersection Improvements (CIP Project No. 6071), and the other one is Phase I of the El Camino
Real and Cannon Road Intersection Improvements (CIP Project Nos. 6042 and 6056). These
projects are expected to be completed in August 2021 and December 2021, respectively.
Public Works Branch
Transportation Department
1635 Faraday Avenue I Carlsbad, CA 92008 I 760-602-2730
Council Memo -El Camino Real and Cannon Road Intersection Improvements Project Update
May 13, 2021
Page 2
To reduce potential construction conflicts due to overlapping construction activities,
construction of Phase II of the Project will be postponed until late 2021, and after construction
of Phase I is substantially completed.
Next Steps
Staff have prepared the final plans, specifications and cost estimate for Phase II of the Project.
Upon substantial completion of the projects currently under construction, staff anticipate
scheduling the following City Council agenda items:
• August 2021-Approval of Phase II plans and specifications and authorization to bid
• October 2021-Award of a Phase II construction contract
Construction of Phase II of the Project is anticipated to begin in late 2021 and is expected to be
completed in summer 2022.
cc: Scott Chadwick, City Manager
Celia Brewer, City Attorney
Gary Barberio, Deputy City Manager, Community Services
Laura Rocha, Deputy City Manager, Administrative Services
Neil Gallucci, Police Chief
Michael Calderwood, Fire Chief
Robby Contreras, Assistant City Attorney
Tom Frank, Transportation Director
Jeff Murphy, Community Development Director
Kristina Ray, Community & Engagement Director
Babaq Taj, Engineering Manager
Hossein Ajideh, Engineering Manager
John Kim, City Traffic Engineer
Nathan Schmidt, Transportation Planning and Mobility Manager
Jonathan Schauble, Senior Engineer
Brandon Miles, Associate Engineer