Edwards Construction Group Inc; 2022-07-14; PWS22-1788FAC
CITY OF CARLSBAD San Diego County California CONTRACT DOCUMENTS, GENERAL PROVISIONS AND TECHNICAL SPECIFICATIONS FOR THE Leo Carrillo Ranch Roof Repair CONTRACT NO. 4748 PWS22-1788FAC -Bidding ,, •+;' Revised 6/15/17 TABLE OF CONTENTS Item Page Notice Inviting Bids . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6 Contractor's Proposal............................................................................................................... 13 Bid Security Form ............... ...................................... ............................................................... 19 Bidder's Bond to Accompany Proposal . ... . . . . . . .. . . . .. .. . .. . . . .. . . . .. . .. . . . . . . . . . ... .. . . . . . . .... .. ... .. . .. . . . . .. ... . . . . .. 20 Guide for Completing the "Designation of Subcontractors" Form ............................................. 21 Designation of Subcontractor and Amount of Subcontractor's Bid Items . . .. . . . . . . . .. . .. . . . . . . .. . ... . .. . . 22 Bidder's Statement of Technical Ability and Experience........................................................... 23 Bidder's Certificate of Insurance for General Liability, Employers' Liability, Automotive Liability and Workers' Compensation . . . . . . . . .... .. . . . . ... . . . . .. . . . . .. . . .. . . .. . ... .. . . . . . . . ... ... ... . . . ... .. . . . . .. . . . . . . . . . . 24 Bidder's Statement Re Debarment ...................................... :.................................................... 25 Bidder's Disclosure of Discipline Record . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . ... . . . . . . . . . .. . 26 Non-collusion Declaration to Be Executed by Bidder and Submitted with Bid . . . . . . . . . . . . . . . . . . . . . . . . . . 28 Contract Public Works.............................................................................................................. 29 Labor and Materials Bond . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35 Faithful Performance/Warranty Bond....................................................................................... 37 Optional Escrow Agreement for Surety Deposits in Lieu of Retention . . . .. . . . . . . .. . .. . . . . . . . . . . .. .. .. .. .. . . 39 ATTACHMENTS A Conditions Assessment, dated March 26, 2020 B. Old House Journal Article ,, • ., Revised 6/12/18 Contract No. 4748 Page 2 of 107 Pages Section 1 1-1 1-2 1-3 1-4 Section 2 2-1 2-2 2-3 2-4 2-5 2-6 2-7 2-8 2-9 2-10 2-11 Section 3 3-1 3-2 3-3 3-4 3-5 Section 4 4-1 4-2 Section 5 5-1 5-2 5-3 5-4 5-5 5-6 Section 6 6-1 6-2 6-3 6-4 6-5 6-6 6-7 6-8 6-9 6-10 GENERAL PROVISIONS Terms, Definitions Abbreviations and Symbols Terms .............................................................................................................. 42 Definitions .................................................... . . ... . ... . . ... . .......... ... . .. . . . .. . . . . . . . .. .. . . . . . 42 Abbreviations ............................................... . . . .. . .. . . . . . . . .. . . .. . .. . . .. . .. . . . .. . . . . . . . . . . . . . . . . 46 Units of Measure.......................................... .. . .. . .. . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . .. . . .. . .. . . . . 49 Scope and Control of The Work Award and Execution of Contract................. .. .. . . .. . . . . . . .. .. .. . . .. . . .. . . . . .. . . . . .. . .. .. . . . . .. . 50 Assignment.................................................. .................................................... 50 Subcontracts................................................ . . . . . . . .. . . .. . . . . . . .. . . . . . .. . . . . . . . . . . . . . . .. . . .. . . . . 50 Contract Bonds ............................................ .................................. .................. 51 Plans and Specifications.............................. . . . .. . .. . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52 Work to be Done.......................................... .. . .. . .. . . . . . . . . . . . . . . .. . .. . . .. . . . .. . . . . . . . .. . . . . . . . 55 Subsurface Data .......................................... . .. .. .... . .. . . . ... . .. ... . .. .. .. . . . .. . . . .. . ... . . . . . . . 55 Right-of-Way................................................ . . . ...... ... . . . . . . ... . .. . .... ... . . .. . . . . .. .. . . .. . . .. 55 Surveying..................................................... . . . . . . .. . . . . . . . . . .. . . . . . . . . . . . .. . . .. . . . . . . .. . . . . . . . . 55 Authority of Board and Engineer.................. . . . .. . ... . .. . . . .. . . ...... .. . . .. . . . .. . . . . . .. .. . . . . . . . 56 Inspection .................................................... .............................................. ...... 56 Changes in Work Changes Requested by the Contractor ........ . . . . . . . . . .. . . .. .. .. .. .. . .. .. .. .. .. .. . . .. . . .. .. .. . . .. 57 Changes Initiated by the Agency.................. . . . . . . . . . .. . . . . . . . . . . .. . . . . .. . . . . . . . . . . . .. . . . .. . . .. . 57 Extra Work................................................... . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . .. . . . . . . .. . . . . . . . .. . . . 58 Changed Conditions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . .. . .. . . .. . . . ... .. . . . . . .. ... .. . . . . . . . . . . .. . . . . 60 Disputed Work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . .. . . . .. . . . . 62 Control of Materials Materials and Workmanship............................................................................. 63 Materials Transportation, Handling and Storage............................................... 72 Utilities Location .. . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . .. . . . . 73 Protection . . . . . .. . . .. . . . . . . . . . . . . . . . . . . . . . . . . . .. . .. . . . .. . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . 73 Removal.......................................................................................................... 74 Relocation ................................................... ~ . . . . . . . . . . . . . . . . . . . . . . .. . . . . . .. . . . . . . . . . . . . . . . .. . . . . 7 4 Delays.............................................................................................................. 75 Cooperation . . . .. . ... . .. .... ... . .. . . . .. . . . . . .. .. . . . ... . . . .. . . . . .. . . . . . . . . . ... . ... . . ... . . . . . .. . . . .. . .. . . . . . . ... . . . 75 Prosecution, Progress and Acceptance of the Work Construction Schedule and Commencement of Work ....................................... 76 Prosecution of Work..................................... . . . . . .. . ... . . . .. ......... .. . . . . . . . . . . . ... . . . . . .. . . . . 79 Suspension of Work..................................... . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . .. . . . . . . . .. . . . 90 Default by Contractor................................... . . . . . .. .. .. . . . .. . .. . . .. . . .. . . . . . . . . . . . . . . . . . . . . . . .. . 90 Termination of Contract................................ ................................ .................... 91 Delays and Extensions of Time.................... .................................................... 91 Time of Completion...................................... .. . . .. .. . .. . . . . . . . .. . .. . . .. . .. . . . . . . . . . . . . .. . . . . . . .. 92 Completion, Acceptance, and Warranty ....... .... .................... ............................ 93 Liquidated Damages.................................... . .. . .. . . . . . . . .. . . . . . . . . . . .. . .. . . . .. . . . . . . ... . . . . . . .. 96 Use of Improvement During Construction .. . . ....... .. . . . . .. . .. . . .. . . . . . . .. . . .... . .. . . ... .. . . . ... 96 l'\ •ff Revised 6/12/18 Contract No. 4748 Page 3 of 107 Pages Section 7 7-1 7-2 7-3 7-4 7-5 7-6 7-7 7-8 7-9 7-10 7-11 7-12 7-13 7-14 Section 8 8-1 8-2 8-3 8-4 Responsibilities of the Contractor Contractor's Equipment and Facilities .......... ............. ....................................... 97 Labor ........................................................... .................................................... 97 Liability Insurance ........................................ .................................................... 97 Workers' Compensation Insurance.............. .................................................... 97 Permits ........................................................ .................................................... 98 The Contractor's Representative.................. .................................................... 98 Cooperation and Collateral Work .. .. . . . . .. . . . . . . . . .. .. . . . .. . . .. . . . . . . . .. . .. . . .. . .. .. . .. . . . . . . .. . . . . . . 98 Project Site Maintenance ............................. . ... ... . .. . . .. . . . . . . . . . . .. . . . . . . . . . . ... . . . . . . . . . . .. . 99 Protection and Restoration of Existing Improvements .. . . .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. . .. 100 Public Convenience and Safety .. .. .. .. .. .. .. .. .. . .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. . .. .. .. .. .. .. .. .. .. . 100 Patent Fees or Royalties .............................. . .. . . .. . . .. .. . . . . . . . . . . . . .. . . . . .. . . . .. .. . . . . . .. . .. . . 103 Advertising ................................................... . . . . . .. . .. . . .. . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . .. . . . . . 103 Laws to be Observed . . . . . . . .. .. . . . .. . . .. . . .. . . .. .. . . . . . . .. . . . . . . .. .. . . . . . . .. . . . . . . . . . . . . . . . .. . . . . . . . .. . . . . . 103 Antitrust Claims............................................ . .. .... . . .. .... .. . . . . . . . . . ... . . . .. . . ... .. . . . . . . . .. . . 103 Measurement and Payment Measurement of Quantities for Unit Price Work .. .. . . .. . . .. .. .. .. .. .. .. . . .. .. .. .. .. .. .. .. 104 Lump Sum Work....................................................................................... 104 Payment .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 04 Bid Items................................................................................................... 107 ,, •,r Revised 6/12/18 Contract No. 4748 Page 4 of 107 Pages TECHNICAL SPECIFICATIONS DIVISION 01 GENERAL REQUIREMENTS 01 35 91 Restoration of Historic Features DIVISION 02 EXISTING CONDITIONS 02 42 96 Historic Treatment Procedures DIVISION 03 CONCRETE 03 62 18 Non-Shrink Grout DIVISION 04 MASONRY 04 10 00 Adobe 04 20 00 Adobe Repair and Stabilization DIVISION 05 METALS 05 50 00 Metal Fabrications DIVISION 06 WOOD, PLASTICS, AND COMPOSITES 06 03 12 Historic Wood Repair 06 10 00 Rough Carpentry DIVISION 07 07 31 70 07 32 13 07 46 23 07 51 10 07 62 00 THERMAL AND MOISTURE PROTECTION Wood Shingles Historic Roof Tile Repair and Replication Wood Siding Built-Up Asphalt Roofing Sheet Metal Flashing and Trim DIVISION 09 FINISHES 09 21 00 Plaster Repair and Restoration 09 90 00 Painting APPENDIX BRIEF 5 BRIEF 30 PRESERVATION BRIEFS -NATIONAL PARK SERVICE PRESERVATION OF HISTORIC ADOBE BUILDINGS PRESERVATION AND REPAIR OF HISTORIC CLAY TILE ROOFS ,., •+' Revised 6/12/18 Contract No. 4748 Page 5 of 107 Pages CITY OF CARLSBAD, CALIFORNIA NOTICE INVITING BIDS Until 5 p.m. on May 10, 2022, the City shall accept bids via electronic format via the City of Carlsbad Electronic Bidding Site, PlanetBids, which may be accessed at Contracting & Purchasing I Carlsbad, CA (carlsbadca.gov) for performing the work as follows: LEO CARRILLO RANCH ROOF REPAIR PROJECT CONTRACT NO. 4748 BID NO. PWS22-1788FAC ELECTRONIC FORMAT RECEIPT AND OPENING OF BIDS: Bids will be received in electronic format (eBids) EXCLUSIVELY at the City of Carlsbad's electronic bidding (eBidding) site, at: Contracting & Purchasing I Carlsbad, CA (carlsbadca.gov) and are due by the date and time shown on the cover of this solicitation. BIDDERS MUST BE PRE-REGISTERED with the City's bidding system and possess a system- assigned Digital ID in order to submit an electronic bid. The City's electronic bidding (eBidding) system will automatically track information submitted to the site including IP addresses, browsers being used and the URLs from which information was submitted. In addition, the City's bidding system will keep a history of every login instance including the time of login, and other information about the user's computer configuration such as the operating system, browser type, version, and more. Because of these security features, Bidders who disable their browsers' cookies will not be able to log in and use the City's bidding system. The City's electronic bidding system is responsible for bid tabulations. Upon the bidder's or proposer's entry of their bid, the system will ensure that all required fields are entered. The system will not accept a bid for which any required information is missing. This includes all necessary pricing, subcontractor listing(s) and any other essential documentation and supporting materials and forms requested or contained in these solicitation documents. BIDS REMAIN SEALED UNTIL DUE DATE AND TIME. eBids are transmitted into the City's bidding system via hypertext transfer protocol secure (https) mechanism using SSL 128-256-bit security certificates issued from VerisignlThawte which encrypts data being transferred from client to server. Bids submitted prior to the Due Date and Time are not available for review by anyone other than the submitter, who will have until the Due Date and Time to change, rescind or retrieve its bid should they desire to do so. BIDS MUST BE SUBMITTED BY DUE DATE AND TIME. Once the deadline is reached, no further submissions are accepted into the system. Once the Due Date and Time has passed, bidders, proposers, the general public, and City staff are able to immediately see the results online. City staff may then begin reviewing the submissions for responsiveness, compliance and other issues. RECAPITULATION OF THE WORK. Bids shall not contain any recapitulation of the Work. Conditional Bids may be rejected as being non- responsive. Alternative proposals will not be considered unless called for. BIDS MAY BE WITHDRAWN by the Bidder prior to, but not after time set as Due Date and Time. f.'\ •+;' Revised 6/12/18 Contract No. 4748 Page 6 of 107 Pages Important Note: Submission of the electronic bid into the system may not be instantaneous. Due to the speed and capabilities of the user's internet service provider (ISP), bandwidth, computer hardware and other variables, it may take time for the bidder's submission to upload and be received by the City's eBidding system. It is the bidder's sole responsibility to ensure their bids are received on time by the City's eBidding system. The City of Carlsbad is not responsible for bids that do not arrive by the Due Date and Time. ELECTRONIC SUBMISSIONS CARRY FULL FORCE AND EFFECT The Bidder, by submitting their electronic proposal, agrees to and certifies under penalty of perjury under the laws of the State of California, that the certification, forms and affidavits submitted as part of this proposal are true and correct. The bidder, by submitting its electronic bid , acknowledges that doing so carries the same force and full legal effect as a paper submission with a longhand (wet) signature. By submitting an electronic bid, the bidder certifies that the bidder has thoroughly examined and understands the entire Contract Documents (which consist of the plans and specifications, drawings, forms, affidavits and the solicitation documents), and that by submitting the eBid as its bid proposal, the bidder acknowledges, agrees to and is bound by the entire Contract Documents, including any addenda issued thereto, and incorporated by reference in the Contract Documents. BIDS ARE PUBLIC RECORDS Upon receipt by the City, bids shall become public records subject to public disclosure. It is the responsibility of the Bidder to clearly identify any confidential, proprietary, trade secret or otherwise legally privileged information contained within the proposal's General references to sections of the California Public Records Act (PRA) will not suffice. If the Bidder does not provide applicable case law that clearly establishes that the requested information is exempt from the disclosure requirements of the PRA, the City shall be free to release the information when required in accordance with the PRA, pursuant to any other applicable law, or by order of any court or government agency, and the Bidder agrees to hold the City harmless for any such release of this information. This bid and the terms of the Contract Documents and Supplemental Provisions constitute an irrevo- cable offer that shall remain valid and in full force for a period of 90 days and such additional time as may be mutually agreed upon by the City of Carlsbad and the Bidder. INSTRUCTIONS TO BIDDERS AND BID REQUIREMENTS This bid and the terms of the Contract Documents and General Provisions constitute an irrevocable offer that shall remain valid and in full force for a period of 90 days and such additional time as may be mutually agreed upon by the City of Carlsbad and the Bidder. No bid will be received unless it is made on a proposal form furnished by the Purchasing Department. Each bid must be accompanied by security in a form and amount required by law. The bidder's security of the second and third next lowest responsive bidders may be withheld until the Contract has been fully executed. The security submitted by all other unsuccessful bidders shall be returned to them, or deemed void, within ten (10) days after the Contract is awarded. Pursuant to the provisions of law (Public Contract Code section 10263), appropriate securities may be substituted for any obligation required by this notice or for any monies withheld by the City to ensure performance under this Con- tract. Section 10263 of the Public Contract Code requires monies or securities to be deposited with the City or a state or federally chartered bank in California as the escrow agent. The escrow agent shall maintain insurance to cover negligent acts and omissions of the agent in connection with the handling of retentions under this section in an amount not less than $100,000 per contract. The City of Carlsbad may disqualify a contractor or subcontractor from participating in bidding when a contractor or subcontractor has been debarred by the City of Carlsbad or another jurisdiction in the State of California as an irresponsible bidder. {'\ •ff Revised 6/12/18 Contract No. 4748 Page 7 of 107 Pages GENERAL SCOPE OF WORK The Leo Carrillo Ranch is located at 6200 Flying Leo Carrillo Lane in Carlsbad CA 92009. The City desires to structurally reinforce replace/restore the roofs on eight historic properties on site per the plans and specifications for the work, as indicated in the Bid Documents. The work shall be performed sequentially by building as agreed to by the city, and in strict conformance with the plans, provisions and specifications as approved by the City Council of the City of Carlsbad on file with the City Clerk's Office. Reference is hereby made to these plans, provisions and specifi- cations for full particulars and description of the work. The General Provisions (Part 1) to the SSPWC do not apply. The City of Carlsbad encourages the participation of minority and women-owned businesses and en- courages all bidders, suppliers, manufacturers, fabricators and contractors to utilize recycled and re- cyclable materials when available, appropriate and approved by the Engineer. BID DOCUMENTS The bid documents comprise the following documents which must be completed and properly exe- cuted including notarization, where indicated. 1. Contractor's Proposal 2. Bidder's Bond (At Time of Bid Submit PDF Copy via PlanetBids / All Bidders). Bid Bond (Original) Due within Two Business Days After Bid Opening / 3 Apparent Low Bidders. 3. Non-collusions Declaration 4. Designation of Subcontractor and Amount of Subcontractor's 5. Bidder's Statement of Technical Ability and Experience 6. Acknowledgement of Addendum(a) 7. Certificate of Insurance. The riders covering the City, its officials, employees and volunteers may be omitted at the time of bid submittal but shall be provided by the Bidder prior to award of contract 8. Bidder's Statement Re Debarment 9. Bidder's Disclosure of Discipline Record 10. Escrow Agreement for Security Deposits -(optional, must be completed if the Bidder wishes to use the Escrow Agreement for Security) BIDDER'S GUARANTEE OF GOOD FAITH (BID SECURITY) At the time of bid submission, bidders must upload and submit an electronic PDF copy of the afore- mentioned bid security. Whether in the form of a cashier's check, a properly certified check or an approved corporate surety bond payable to the City of Carlsbad, the bid security must be uploaded to the City's eBidding system. Within two (2) business days after the bid opening date, the first three (3) apparent low bidders must provide the City with the original bid security. Failure to submit the electronic version of the bid security at time of bid submission shall cause the bid to be rejected and deemed non-responsive. Only the three (3) apparent low bidders are required to submit original bid security to the city within two (2) business days after bid opening date. Failure to provide the original within two (2) business days may deem the bidder non-responsive. ENGINEER'S ESTIMATE All bids will be compared on the basis of the Engineer's Estimate. The estimated quantities listed in the Contractor's Proposal are approximate and serve solely as a basis for the comparison of bids. The Engineer's Estimate is $1,013.018. TIME OF COMPLETION The contractor shall complete the Work within the time set in the contract as defined in the General Provisions Section 6-7. (' It' Revised 6/12/18 Contract No. 4748 Page 8 of 107 Pages SPECIALTY CONTRACTORS: ACCEPTABLE LICENSE TYPES Except as provided herein a bid submitted to the City by a Contractor who is not licensed as a contractor pursuant to the Business and Professions Code shall be considered nonresponsive and shall be re- jected by the City. In all contracts where federal funds are involved, no bid submitted shall be invalidated by the failure of the bidder to be licensed in accordance with California law. Where federal funds are involved the contractor shall be properly licensed at the time the contract is awarded. In all other cases the contractor shall state their license number, expiration date and classification in the proposal, under penalty of perjury. This invitation to bid does not include federal funds. The following classifications are acceptable for this contract: B -General Building. BIDDER'S STATEMENT OF TECHNICAL ABILITY AND EXPERIENCE Contractor and his designated subcontractor(s) shall demonstrate proof of their experience and technical ability for construction in the disciplines of construction required to complete this project. Proof of the Contractor's technical ability and experience (as outlined below) shall be attached to The Bidder's Statement of Technical Ability and Experience to be included with the Contractor's bid. The City will only consider Contractors that demonstrate they have the experience and ability to manage, construct, and staff the project. 1. Submit no more than three projects completed by the Contractor in the last 10 years that are comparable in size, scope, complexity, building, type, technically sound and aesthetically distinctive projects constructed for public owner or institutional clients. The City will not give additional consideration for submitting more than three projects. Projects presented for con- sideration must be attached to the Bidders Statement of Technical Ability and Experience form. 2. The lead personnel including superintendent, the foreman, and lead crew personnel for the Contractor and designated subcontractors must have a minimum of three (3) years of total experience and must have demonstrated competency and experience to perform the scope of work contained in this contract. Please provide the name and experience of each lead individ- ual performing work on this contract. Please attach responses to the Bidders Statement of Technical Ability and Experience. Personnel replaced by the Contractor, on this contract, shall have similar, verifiable experience as the personnel originally submitted for the project. ESCROW AGREEMENT If the Contractor intends to utilize the escrow agreement included in the contract documents in lieu of the usual 5% retention from each payment, these documents must be completed and submitted with the signed contract. The escrow agreement may not be substituted at a later date. OBTAINING PLANS AND SPECIFICATIONS Bid packages, various supplemental provisions and Contract Documents may be obtained on the City of Carlsbad website at www.carlsbadca.gov. Paper copies will not be provided or sold. INTENT OF PLANS AND SPECIFICATIONS Any prospective bidder who is in doubt as to the intended meaning of any part of the drawings, spec- ifications or other contract documents, or finds discrepancies in or omissions from the drawings and specifications may submit to the Engineer a written request for clarification or correction. Any response will be made only by a written addendum duly issued by the Engineer a copy of which will be mailed or delivered to each person receiving a set of the contract documents. No oral response will be made to such inquiry. Prior to the award of the contract, no addition to, modification of or interpreta- tion of any provision in the contract documents will be given by any agent, employee or con- tractor of the City of Carlsbad except as hereinbefore specified. No bidder may rely on direc- tions given by any agent, employee or contractor of the City except as hereinbefore specified. {"\ •+;' Revised 6/12/18 Contract No. 4748 Page 9 of 107 Pages REJECTION OF BIDS The City of Carlsbad reserves the right to reject any or all bids and to waive any minor irregularity or informality in such bids. PREVAILING WAGE TO BE PAID The general prevailing rate of wages for each craft or type of worker needed to execute the Contract shall be those as determined by the Director of Industrial Relations pursuant to the sections 1770, 1773, and 1773.1 of the Labor Code. Pursuant to section 1773.2 of the Labor Code, a current copy of applicable wage rates is on file in the Office of the City Engineer. The Contractor to whom the Contract is awarded shall not pay less than the said specified prevailing rates of wages to all workers employed by him or her in the execution of the Contract. The Prime Contractor shall be responsible for insuring compliance with provisions of section 1777.5 of the Labor Code and section 4100 et seq. of the Public Contracts Code, "Subletting and Subcon- tracting Fair Practices Act." The City Engineer is the City's "duly authorized officer" for the purposes of section 4107 and 4107.5. The provisions of Part 7, Chapter 1, of the Labor Code commencing with section 1720 shall apply to the Contract for work. A contractor or subcontractor shall not be qualified to bid on, be listed in a bid proposal, subject to the requirements of Section 4104 of the Public Contract Code, or engage in the performance of any con- tract for public work, unless currently registered and qualified to perform public work pursuant to Sec- tion 1725.5. This project is subject to compliance monitoring and enforcement by the Department of Industrial Relations. The Prime Contractor and all subcontractors shall comply with Section 1776 of the Labor Code, which generally requires keeping accurate payroll records, verifying and certifying payroll records, and making them available for inspection. Contractor shall require all subcontractors to comply with Section 1776. MANDATORY PRE-BID MEETING A mandatory pre-bid meeting and tour of the project site will be held at the Leo Carrillo Ranch, 6200 Flying Leo Carrillo Lane, Carlsbad, CA 92009 on April 7, 2022 at 10:00 a.m. UNIT PRICES AND COMPUTATION OF BIDS All bids are to be computed on the basis of the given categories and/or units of work, as indicated in the Contractor's Proposal, times the unit price (if applicable) as submitted by the bidder. In case of a discrepancy between words and figures, the words shall prevail. In case of an error in the extension of a unit price, the corrected extension shall be calculated, and the bids will be computed as indicated above and compared on the basis of the corrected totals. All bids are to be complete work including all fees, equipment, labor and materials associated with carrying out the work in accordance with plans and specifications. All prices must be in ink or typewritten. Changes or corrections may be crossed out and typed or written in with ink and must be initialed in ink by a person authorized to sign for the Contractor. BIDDER'S INQUIRIES Questions on the bid documents during the bid period shall be submitted via Online Q&A in PlanetBids. Questions shall be definite and certain and shall reference applicable drawing sheets, notes, details or specification sheets. {'\ • ., Revised 6/12/18 Contract No. 4748 Page 10 of 107 Pages Pre-bid substitution requests shall be submitted to Contract Administrator in accordance with the In- structions to Bidders and Technical Specifications Section with a minimum of 14 calendar days prior to bid opening (by April 26 , 2022 at 5 p.m.). The cutoff date and time to submit questions or substitution request regarding this project via Online Q&A in PlanetBids is April 26, 2022, at 5:00 p.m. No questions will be entertained after that date. The answers to questions submitted during the bidding period will be published in an addendum and provided to those bidding on the project by May 3, 2022. ADDENDA Bidders are advised to verify the issuance of all addenda and receipt thereof one day prior to bidding. Submission of bids without acknowledgment of addenda may be cause of rejection of bid. BOND AND INSURANCE REQUIREMENTS The Contractor shall provide bonds to secure faithful performance and warranty of the work in an amount equal to one hundred percent (100%) of the Contract price on this project. The Contractor shall provide bonds to secure payment of laborers and materials suppliers, in an amount equal to one hundred percent (100%) of the total amount payable by the terms of the contract. These bonds shall be kept in full force and effect during the course of this project and shall extend in full force and effect and be retained by the City until they are released as stated in the General Provisions section of this contract. All bonds are to be placed with a surety insurance carrier admitted and authorized to transact the business of insurance in California and whose assets exceed their liabilities in an amount equal to or in excess of the amount of the bond. The bonds are to be accompanied by the following documents: 1) An original, or a certified copy, of the unrevoked appointment, power of attorney, by laws, or an- other instrument entitling or authorizing the person who executed the bond to do so. 2) A certified copy of the certificate of authority of the insurer issued by the insurance commissioner. If the bid is accepted, the City may require copies of the insurer's most recent annual statement and quarterly statement filed with the Department of Insurance pursuant to Article 10 (commencing with section 900) of Chapter 1 of Part 2 of Division 1 of the Insurance Code, within 10 calendar days of the insurer's receipt of a request to submit the statements. Insurance is to be placed with insurers that: 1) Have a rating in the most recent Best's Key Rating Guide of at least A-:VII 2) Are admitted and authorized to transact the business of insurance in the State of California by the Insurance Commissioner. Auto policies offered to meet the specification of this contract must: 1) Meet the conditions stated above for all insurance companies. 2) Cover any vehicle used in the performance of the contract, used onsite or offsite, whether owned, non-owned or hired, and whether scheduled or non-scheduled. Workers' compensation insurance required under this contract must be offered by a company meeting the above standards with the exception that the Best's rating condition is waived. The City does accept policies issued by the State Compensation Fund meeting the requirement for workers' compensation insurance. The Contractor shall be required to maintain insurance as specified in the Contract. Any additional cost of said insurance shall be included in the bid price. ,., •+;' Revised 6/12/18 Contract No. 4748 Page 11 of 107 Pages The award of the contract by the City Council is contingent upon the Contractor submitting the required bonds and insurance, as described in the contract, within twenty days of bid opening. If the Contractor fails to comply with these requirements, the City may award the contract to the second or third lowest bidder and the bid security of the lowest bidder may be forfeited. BUSINESS LICENSE The prime contractor and all subcontractors are required to have and maintain a valid City of Carlsbad Business License for the duration of the contract. Approved by the City Council of the City of Carlsbad, California, by Resolution No. 2022-068, adopted on the 15th day of March, 2022. March 16, 2022 Date DeputyClrl< l' •ff Revised 6/12/18 Contract No. 4748 Page 12 of 107 Pages CITY OF CARLSBAD LEO CARRILLO RANCH ROOF REPAIR PROJECT CONTRACT NO. 4748 PWS22-1788FAC City Council City of Carlsbad CONTRACTOR'S PROPOSAL 1200 Carlsbad Village Drive Carlsbad, California 92008 The undersigned declares he/she has carefully examined the location of the work, read the Notice Inviting Bids, examined the Plans, Specifications, General Provisions, Contract Documents, and ad- denda thereto, and hereby proposes to furnish all labor, materials, equipment, transportation, and services required to do all the work to complete Contract No. 4748 in accordance with the Plans, Specifications, General Provisions, Contract Documents, and addenda thereto and that he/she will take in full payment for the work the total bid value stipulated below in the Schedule of Values com- prising the basis of award. The Schedule "A" Items listed below will be made a part of the basis of award and upon City approval of the Contractor's value distributions, will become the Schedule of Values for monthly progress payments. Items of contract work not specifically referenced in the Schedule "A" below but shown on the project drawings and/or customary in the construction industry for completing the scope of work described in the contract documents, shall be in- cluded in Schedule "A" below. Contractor to refer to all contract documents in the preparation of the values below. NOTE: Any line items that exceed $300,000 in value will be reviewed by the City's Construction Management Consultant on site and may require subdivision into lesser sub parts. SCHEDULE OF VALUES "A" per GENERAL AND TECHNICAL SPECIFICATIONS Item No. Description A-1 Mobilization and Preparatory Work Per General Provisions 8.3.4.1 Twenty thousand dollars (Price in Words) A-2 General Provisions seventeen thousand four hundred ninety-five and 0011 oo dollars (Price in Words) Approxi- mate Quantity and/or Unit LS LS A-3 Division 01 ; General Requirements LS one hundred eighty-two thousand seven hundred fifty six and 00/1 oo dollars (Price in Words) l'\ ._, Revised 6/12/18 Co ntract No. 4748 Unit Price Total Amount (Figures) (Figures) $ $20,000 $ $20,000 $ 17 495 00 $ 182 756.00 Page 13 of 107 Pages Item No. A-4 A-5 A-6 A-7 A-8 A-9 Approxi- mate Description Quantity and/or Unit Division 02; Existing Conditions twe□f:¥ □i □e tbo11sa □d fnll[ b11□dced □i□et¥-Se~e□ a□d OOl:l 00 dollacs (Price in Words) Division 03; Concrete o□e tbo11saad □i□e b11□dred fact¥ seven and QQ/1 QQ dQllars (Price in Words) Division 04; Masonry touctee□ tboLJsa□d fouc buodred sixt¥ six a□d OOL1 oo dollars (Price in Words) Division 05; Metals fQY[ tbQysand seven hundred si~y- Q□e a□d QQL1 QQ dQlla[S (Price in Words) Division 06; Wood, Plastics and Composites sixty-fiv!;l thQysand fQyr hyodred fi~- □i□e a□d OOL1 oo dollars (Price in Words) Division 07; Thermal and Moisture Protection follC bI mdced fift¥-eigbt tbo11sa□d three hyod[ed sixty-eight aod 00/1 OQ dQUars (Price in Words) LS LS LS LS LS LS A-10 Division 09; Finishes LS o□e huodred sixty-three tbousaod eight hundred ninety-nine and 00/100 dollars (Price in Words) ,., •;; Revised 6/12/1 8 Co ntract No. 4748 Unit Price Total Amount (Figures} (Figures} $ 29 497 00 $ 1 947.00 $ 14 466 00 $ 4 761 00 $ 65 459 00 $~58 368 QQ $ 163 899 00 Page 14 of 107 Pages Item No. Description A-11 Allowance for linear feet of roof rafters that require replacement, with all associated work to access and replace them with new materi- als appropriate for construction should any be encountered. seven thousand one hundred ten and 0011 oo doUars (Price in Words) A-12 Allowance for square footage of plywood sheathing that requires re- placement, with all associated work to access and replace it with new materials appropriate for construc- tion should any be encountered. six thousand five hundred tweotv tive aod 0011 aa dallacs (Price in Words) Approxi- mate Quantity and/or Unit 500 LF 500SF Unit Price (Figures) $ 14.22 $ 13 05 Total Amount (Figures) $ 7 110 00 $ 6 525 00 SCHEDULE OF VALUES "B" per BUILDING ON SITE (distribution of A-1 thru A-10 values) Item No. Building Name Valuation 1 Hacienda $ 517 671 00 2 Cabana $ 115 038 00 3 Wash House $ 57,519.00 4 Carriage House $ 47,932 00 5 Staff Offices $ 67 105 00 6 Staff Office Restroom $ 52.726,00 7 Deedee's House $ 76 692 00 8 Cantina $ 23 966 00 Schedule B above is required for the City to track project progress another way. The sum value for all eight (8) building structures should match the sum value of items A-1 thru A-10 in Schedule A above, not the sum of items A-1 thru A-12. Work in each building structure is required to be sequen- tial (building by building) in coordination with the City instead of simultaneously in multiple buildings, ,, •,,-Revised 6/1 2/1 8 Contract No. 4748 Page 15 of 107 Pages so public access can be coordinated and/or restricted during certain time periods as necessary. The work in the Hacienda building will have to be done between the months of December and February if specific hours for daily work and work area cleanup cannot be successfully coordinated. Total amount of bid in words for Schedule "A" Items No. 1-12: nine hundred seventy-two thousand two hundred eighty-three and 0011 oo dollars Total amount of bid in numbers for Schedule "A" Items No. 1-12:$ -'9""'7c..::2::.i;2::.;8=-:3::.:..0,:.;0=--------- Total amount of bid in words for Schedule "B" Items No. 1-8: nine hundred fifty-eight thousand six hundred forty-nine and 0011 oo dollars Total amount of bid in numbers for Schedule "B" Items No. 1-8:$ __,9,,_,,5,.,,8,..,.6-<.::4..,.9w0...,.0.__ ______ _ The City shall determine the low bid based on the calculated sum of the line Items in Schedule "A" above. items A-1 through A-12. Depending on the calculated sum. bid award may differ from the Schedule "A" total that has been written above on the form by the Contractor at time of bid. Contractors are encouraged to double-check the values submitted in the Contractors Proposal. Price(s) given above are firm for 90 days after date of bid opening. Addendum(a) No(s). 1 has/have been received and is/are included in this bid. The Undersigned has carefully checked all of the above figures and understands that the City will not be responsible for any error or omission on the part of the Undersigned in preparing this bid. The Undersigned agrees that in case of default in executing the required Contract with necessary bonds and insurance policies within twenty (20) days from the date of award of Contract by the City Council of the City of Carlsbad. the City may administratively authorize award of the contract to the second or third lowest bidder and the bid security of the lowest bidder may be forfeited. The Undersigned bidder declares. under penalty of perjury. that the undersigned is licensed to do business or act in the capacity of a contractor within the State of California. validly licensed under license number 1057451 . classification A & B which expires on 08/31/2023 , and Department of Industrial Relations PWC registration number 1000459456 which expires on 06/30/2023 , and that this statement is true and correct and has the legal effect of an affidavit. A bid submitted to the City by a Contractor who is not licensed as a contractor pursuant to the Business and Professions Code shall be considered nonresponsive and shall be rejected by the City § 7028.15(e). In all contracts where federal funds are involved, no bid submitted shall be invalidated by the failure of the bidder to be licensed in accordance with California law. However, at the time the contract is awarded, the contractor shall be properly licensed. The Undersigned bidder hereby represents as follows: 1. That no Council member, officer agent, or employee of the City of Carlsbad is personally inter- ested, directly or indirectly, in this Contract, or the compensation to be paid hereunder; that no repre- sentation, oral or in writing, of the City Council, its officers, agents, or employees has inducted him/her to enter into this Contract, excepting only those contained in this form of Contract and the papers made a part hereof by its terms; and 2. That this bid is made without connection with any person, firm, or corporation making a bid for the same work, and is in all respects fair and without collusion or fraud. ,, •;; Revised 6/12/18 Contract No. 4748 Page 16 of 107 Pages Accompanying this proposal is _B.;_;I_D....:B:....:O:....;N...;,,:D:;__ ________ (Cash, Certified Check, Bond or Cashier's Check) for ten percent (10%) of the amount bid. The Undersigned is aware of the provisions of section 3700 of the Labor Code which requires every employer to be insured against liability for workers' compensation or to undertake self-insurance in accordance with the provisions of that code, and agrees to comply with such provisions before com- mencing the performance of the work of this Contract and continue to comply until the contract is complete. The Undersigned is aware of the provisions of the Labor Code, Part 7, Chapter 1, Article 2, relative to the general prevailing rate of wages for each craft or type of worker needed to execute the Contract and agrees to comply with its provisions. IF A SOLE OWNER OR SOLE CONTRACTOR SIGN HERE: (1) Name under which business is conducted ---'-'Nc.;;./A....;.._ _____________ _ (2) Signature (given and surname) of proprietor --!N..!!/-'-'A,__ ____________ _ (3) Place of Business N/A (Street and Number) City and State _ __:_N.:.:,;IA:....:........ ______________________ _ (4) Zip Code __ N_/A ______ Telephone No. _N_/_A ___________ _ (5) E-Mail _ ___,_N=/A:....:.._ _________________ _ IF A PARTNERSHIP, SIGN HERE: (1) Name under which business is conducted_.....:N:...:.:..:..IA.:._.. ______________ _ (2) Signature (given and surname and character of partner) (Note: Signature must be made by a general partner) N/A (3) Place of Business _....;N....;.;/.;_A.;...._ ______________________ _ (Street and Number) City and State ___ N_/A ______________________ _ (4) Zip Code -"'"'N"-'-/A-'--------Telephone No. _..:..N.:.:.;/A'-'------------- (5) E-Mail _ __:_N.:.:.;/A'-'-------------------- ,, • ., Revised 6/12/18 Con tract No . .11.1J!. Page 17 of 107 Pages IF A CORPORATION, SIGN HERE: (1) Name under which business is conducted EDWARDS CONSTRUCTION GROUP, INC. (2)_4;---'-----=-~--~-----/4-rk __ ~ ___ _ (Signature) BRAD EDWARDS, PRESIDENT RYAN EDWARDS, VICE-PRESIDENT (Title) Impress Corporate Seal here (3) Incorporated under the laws of the State of _C_A_L_IF_O_R_N_IA _____ _ (4) Place of Business 2045 PREISKER LN., STE. A, City and State SANTA MARIA, CA (Street and Number) (5) Zip Code _9_34_54 _______ Telephone No. _B_05_-_33_5_-_11_6_1 _______ _ (6) E-Mail BE@EDWARDSCONGROUP.COM NOTARIAL ACKNOWLEDGMENT OF EXECUTION BY ALL SIGNATORIES MUST BE A TT ACHED List below names of president, vice president, secretary and assistant secretary, if a corporation; if a partnership, list names of all general partners, and managing partners: BRAD EDWARDS, PRESIDENT & TREASURER RYAN EDWARDS, VICE-PRESIDENT & SECRETARY 0 Revised 6/12/18 Contract No.~ Page 18 of 107 Pages JURAT A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document. State of California County of Santa Barbara Subscribed and sworn to (or affirmed) before me on this 2nd day of June 2022, by Brad Thomas Edwards proved to me on the basis of satisfactory evidence to be the person who appeared before me. (Seal) Signatur~ _ ____,,....,._Z:, _______ ~--=-~----_-_::::::-----,,.~--- JURAT A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document. State of California County of Santa Barbara Subscribed and sworn to (or affirmed) before me on this 2nd day of June 2022, by Ryan Edwards proved to me on the basis of satisfactory evidence to be the person who appeared before me. 1. • s~v:;. F~N;,;c:..; •t I COMM. #2329879 5 · NOTARY PUBLIC· CALIFORNIA ~ A. · SANTA BARBARA COUNTY ~ ~ . "' My comm. Expires June 23, 2024 .............. , .. (Seal) BID SECURITY FORM (Check to Accompany Bid) LEO CARRILLO RANCH ROOF REPAIR PROJECT CONTRACT NO. 4748 PWS22-1788FAC (NOTE: The following form shall be used if check accompanies bid.) Accompanying this proposal is a *Certified *Cashier's check payable to the order of CITY OF CARLSBAD, in the sum of _________________________ _ ________________________ dollars($ ______ ~, this amount being ten percent (10%) of the total amount of the bid. The proceeds of this check shall become the property of the City provided this proposal shall be accepted by the City through action of its legally constituted contracting authorities and the undersigned shall fail to execute a contract and furnish the required Performance, Warranty and Payment Bonds and proof of insurance coverage within the stipulated time; otherwise, the check shall be returned to the undersigned. The proceeds of this check shall also become the property of the City if the undersigned shall withdraw his or her bid within the period of fifteen (15) days after the date set for the opening thereof, unless otherwise re- quired by law, and notwithstanding the award of the contract to another bidder. BIDDER *Delete the inapplicable word. (NOTE: If the Bidder desires to use a bond instead of check, the Bid Bond form on the following pages shall be executed--the sum of this bond shall be not less than ten percent (10%) of the total amount of the bid.) ,, •;;' Revised 6/12/18 Contract No. 4748 Page 19 of 107 Pages BIDDER'S BOND TO ACCOMPANY PROPOSAL LEO CARRILLO RANCH ROOF REPAIR PROJECT CONTRACT NO. 4748 PWS22-1788FAC KNOW ALL PERSONS BY THESE PRESENTS: That we, EDWARDS CONSTRUCTION GROUP, INC. I as Principal, and NATIONWIDE MUTUAL INSURANCE COMPANY I as Surety are held and firmly bound unto the City of Carlsbad, California, in an amount as follows: (must be at least ten percent (10%) of the bid amount) 10% OF AMOUNT BID for which payment, well and truly made, we bind ourselves, our heirs, executors and administrators, successors or assigns, jointly and severally, firmly by these presents. THE CONDITION OF THE FOREGOING OBLIGATION IS SUCH that if the proposal of the above- bounden Principal for: LEO CARRILLO RANCH ROOF REPAIR PROJECT CONTRACT NO. 4748 PWS22-1788FAC in the City of Carlsbad, is accepted by the City Council, and if the Principal shall duly enter into and execute a Contract including required bonds and insurance policies within twenty (20) days from the date of award of Contract by the City Council of the City of Carlsbad, being duly notified of said award, then this obligation shall become null and void; otherwise, it shall be and remain in full force and effect, and the amount specified herein shall be forfeited to the said City. In the event Principal executed this bond as an individual, it is agreed that the death of Principal shall not exonerate the Surety from its obligations under this bond. SIGNcD AND SEALED, this _11_T_H ____ day of APRIL 2022 I -- EDWARDS CONSfRUCTION GROUP, INC. (SEAL) By:d ~A--- (Signature) Jj(tµ\ ~ c\'-'.)~,...ch, fc<2 ~i da.vrt KEVIN VEGA, ATTORNEY-in-FACT (Print Name/Title) (Print Name/Title) (SEAL AND NOTARIAL ACKNOWLEDGEMENT OF SURETY -ATTACH ATTORNEY-IN-FACT CERTIFICATE) APPROVED AS TO FORM: CELIA A. BREWER ~~r Attorney _1(\i (2 A (X Assistant ~/y" Attorr1ey ~ l' •+i' Revised 6/12/18 Contract No. 4748 Page 20 of 107 Pages Power of Attorney KNOW ALL MEN BY THESE PRESENTS THAT: Nationwide Mutual Insurance Company, an Ohio corporation hereinafter referred to severally as the 'Company" and collectively as "the Companies· does hereby make, constitute and appoint: PHILIP E VEGA, MYRNA F SMITH, KEVIN VEGA; BRITTON CHRISTIANSEN each In their individual capacity, its true and lawful attorney-in-fact, with full power and authority to sign, seal, and execute on its behalf any and all bonds and undertakings, and other obligatory instruments of similar nature, In penalties not exceeding the sum of UNLIMITED and to bind the Company thereby, as fully and to the same extent as if such Instruments were signed by the duly authorized officers of the Company; and all acts of said Attorney pursuant to the authority given are hereby ratified and confirmed. This power of attorney is made and executed pursuant to end by authority of the following resolution duly adopted by the board of directors or the Company: 'RESOLVED, that the president, or any vice president be, and each hereby Is, authorized and empowered to appoint attorneys-in-fact of the Company, and to authorize them to execute and deliver on behalf of the Company any and all bonds, forms, applications, memorandums, undertakings, recognizances, transfers, contracts of Indemnity, policies, contracts guaranteeing the fidelity of persons holding positions of public or private trust, and other writings obligatory In nature that the business of the Company may require; and to modify or revoke, with or without cause, any such appointment or 11ulhority; provided, however, that the authority granted hereby shall in no way limit the authority of other duly authorized agents to sign and countersign any of said documents on behalf of the Company." 'RESOLVED FURTHER, that such attorneys-In-fact shall have full power and authority to execute and deliver any and all such documents and to bind the Company subject to the terms and limitations of the power of attorney issued to them, and to affix the seal of the Company thereto; provided, however, that said seal shall not be necessary for the validity of any such documents." This power of attorney is signed and sealed under and by the following bylaws duly adopted by the board of directors of the Company. Execution of Instruments. Any vice president, any assistant secretary or any assistant treasurer shall have the power and authority to sign or attest all approved documents, instruments, contracts, or other papers in connection with the operation of the business of the company In addition lo the chairman of the board, the chief executive officer, president, treasurer or secretary; provided, however, the signature of any of them may be printed, engraved, or stamped on any approved document, contract, instrument, or other papers of the Company. IN WITNESS WHEREOF, the Company has caused this instrument to be sealed and duly attested by the signature of its officer the 20th day of August. 2021. Antonio C. Albanese, Vice President of Nationwide Mutual Insurance Company ACKNOWLEDGMENT STATE OF NEW YORK COUNTY OF NEW YORK: ss On this 20th day of August, 2021, before me came the above-named officer for the Company aforesaid, to me personally known to be the officer described In and who executed the preceding instrument, and he acknowledged the execution of the same, and being by me duly sworn, deposes and says, that he is the officer of the Company aforesaid, that the seal affixed hereto Is the corporate seal or said Company, and the said corporate seal and his signature were duly affixed and subscribed to said instrument by the authority and direction of said Company. Slophanle Rubino McArthur Notary Public, Slate of New Y0<1< No. 02MC6270t 17 Quallfie<I In New Yori< County Commlosion ExmrH October I 9 2024 CERTIFICATE ~~~~ No""Y""l>k My Comm:.tlon e..m OC1oberlt,202◄ I, Laura B. Guy, Assistant Secretary of the Company, do hereby certify that the foregoing is a full, true and correct copy of the original power of attorney Issued by the Company; that the resolution included therein is a true and correct transcript from the minutes of the meetings of the boards of directors and the same has not been revoked or amended in any manner; that said Antonio C. Albanese was on the date of the execution of the foregoing power of attorney the duly elected officer of the Company, and the corporate seal and his signature as officer were duly affixed and subscribed to the said Instrument by the authority of said board of directors; and the foregoing power of attorney is still In full force and effect. IN WITNESS WHEREOF, I have hereunto subscribed my name as Assistant Secretary. and affixed the corporate seal of said Company this 11th day of ~ ~ ~ -- . Cl\~ [3. C:,-v 'd-- Assistant Secretary BDJ 1 (08-21 )00 CALIFORNIA ALL-PURPOSE ACKNOWLEDGMENT CIVIL CODE§ 1189 A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document. State of California County of LOS ANGELES On 04/11/2022 before me, PHILIP VEGA, NOTARY PUBLIC Date Here Insert Name and Title of the Officer personally appeared KEVIN VEGA, ATTORNEY-in-FACT Name(s) of Signer(s) who proved to me on the basis of satisfactory evidence to be the person'tsl., whose nameW is/ar,e subscribed to the within instrument and acknowledged to me that he/~/fhe1/ executed the same in his/f"re.ltheir authorized capacity(tes). and that by his/hef:~ signature~ on the instrument the person(st or the entity upon behalf of which the person~ acted, executed the instrument. I certify under PENAL TY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct. ········1 PHILIP VEGA Notary Public • California : WITNESS my hand and o Los Anaeles County s Commission # 2327592 - y Comm. Expires May 31, 2024 Place Notary Seal Above ----------------OPTIONAL---------------- Though this section is optional, completing this information can deter alteration of the document or fraudulent reattachment of this form to an unintended document. Description of Attached Document Title or Type of Document: _____________ Document Date: _______ _ Number of Pages: ___ Signer(s) Other Than Named Above: ____________ _ Capacity(ies) Claimed by Signer(s) Signer's Name: ____________ _ Signer's Name: ____________ _ □ Corporate Officer -Title(s): ______ _ □ Corporate Officer -Title(s): ______ _ □ Partner -□ Limited □ General □ Partner -□ Limited □ General □ Individual □ Attorney in Fact □ Individual □ Attorney in Fact □ Trustee □ Guardian or Conservator □ Trustee D Guardian or Conservator □Other: _____________ _ □ Other: ______________ _ Signer Is Representing: _________ _ Signer Is Representing: _________ _ ~~~~~~~~~~ ©2014 National Notary Association· www.NationalNotary.org • 1-800-US NOTARY (1-800-876-6827) Item #5907 GUIDE FOR COMPLETING THE "DESIGNATION OF SUBCONTRACTORS" FORM REFERENCES Prior to preparation of the following "Subcontractor Disclosure Form" Bidders are urged to review the definitions in section 1-2 of the General Provisions to this Contract, especially, "Bid", "Bidder", "Contract", "Contractor", "Contract Price", "Contract Unit Price", "Engineer", "Own Or- ganization", "Subcontractor", and "Work". Bidders are further urged to review sections 2-3 SUBCONTRACTS of the General Provisions. CAUTIONS This form will be used by the Agency to determine the percentage of work that the Bidder proposes to perform. Bidders are cautioned that failure to provide complete and correct information may result in rejection of the bid as non-responsive. Any bid that proposes performance of more than 20 percent of the work by subcontractors or otherwise to be performed by forces other than the Bid- der's own organization will be rejected as non-responsive. Specialty items of work that may be so designated by the Engineer on the "Contractor's Proposal" are not included in computing the percent- age of work proposed to be performed by the Bidder. INSTRUCTIONS The Bidder shall set forth the name and location of business of each and every subcontractor whom the Bidder proposes to perform work or labor or render service in or about the work or improvement, and every subcontractor licensed as a contractor by the State of California whom the Bidder proposes to specially fabricate and install any portion of the work or improvement according to detailed drawings contained in the plans and specifications in excess of one-half of one percent (0.5%) of the Bidder's total bid or, in the case of bids or offers for the construction of streets and highways, including bridges, in excess of one-half of one percent (0.5%) or ten thousand dollars ($10,000) whichever is greater. Said name(s) and location(s) of business of subcontractor(s) shall be set forth and included as an integral part of the bid offer. The Designation of Subcontractors form must be submitted as a part of the Bidder's sealed bid. Failure to provide complete and correct information may result in rejection of the bid as non-responsive. Suppliers of materials from sources outside the limits of work are not subcontractors. The value of materials and transport of materials from sources outside the limits of work, as shown on the plans, shall be assigned to the Contractor or the Subcontractor as the case may be, that the Bidder proposes as installer of said materials. The value of material incorporated in any Subcontractor-installed bid item that is supplied by the Bidder shall be included as a part of the work that the Bidder proposes to be performed by the Subcontractor installing said item. When a Subcontractor has a Carlsbad business license, the number must be entered on the proper form. If the Subcontractor does not have a valid business license, enter "NONE". When the Bidder proposes using a Subcontractor to construct or install less than 100 percent of a bid item, the Bidder shall attach an explanation sheet to the Designation of Subcontractor form. The ex- planation sheet shall clearly apprise the City of the specific facts that show the Bidder proposes to perform no less than twenty percent (20%) of the work with its own forces. Determination of the sub- contract amounts for purposes of award of the contract shall be determined by the City Council in conformance with the provisions of the contract documents and the various supplemental provisions. The decision of the City Council shall be final. Contractor is prohibited from performing any work on this project with a subcontractor who is ineligible to perform work on a public works project pursuant to Labor Code Sections 1771 .1 or 1777.7. Bidders shall make any additional copies of the disclosure forms as may be necessary to provide the required information. The page number and total number of additional form pages shall be entered in the location provided on each type of form so duplicated. ft Q Revised 6/12/18 Contract No. ilil Page 21 of 107 Pages DESIGNATION OF SUBCONTRACTOR AND AMOUNT OF SUBCONTRACTOR'S BID ITEMS (To Accompany Proposal) LEO CARRILLO RANCH ROOF REPAIR PROJECT CONTRACT NO. 4748 PWS22-1788FAC The Bidder certifies that it has used the sub-bid of the following listed subcontractors in preparing this bid for the Work and that the listed subcontractors will be used to perform the portions of the Work as designated in this list in accordance with applicable provisions of the specifications and section 4100 et seq. of the Public Contract Code, "Subletting and Subcontracting Fair Practices Act." The Bidder further certifies that no additional subcontractor will be allowed to perform any portion of the Work in excess of one-half of one percent (0.5%) of the Bidder's total bid, or in the case of bids or offers for construction of streets and highways, including bridges, in excess of one-half of one percent (0.5%) or ten thousand dollars ($10,000), whichever is greater, and that no changes in the subcontractors listed work will be made except upon the prior approval of the Agency. SUBCONTRACTOR'S BID ITEMS Subcontractor Name Phone No. DIR Subcontractor's Amount of Portion of and and Email Registration License No. and Work by Work Location of Business Address No.& Exp Classification Subcontractor Date In Dollars* Pr"°''rv;itinn ;ind MARK SAUER 951-279-4245 PW-LR-1000650639 500572 B $210,000.00 repair work CONSTRUCTION, INC. contact@msauer.com EXP 06/30/2022 EXP 05/31/2024 Roof reoair SYLVESTER ROOFING 760-7 43-0048 1000006357 516696 $360,000.00 restoration & COMPANY, INC. kurt@sylvesterroofing.cc m EXP 06/30/2025 EXP 08/31/2023 replacement Page _1_ of _1 _ pages of this Subcontractor Designation form • Pursuant to section 4104 (a)(3)(A) California Public Contract Code, receipt of the information preceded by an asterisk may be submitted by the Bidder up to 24 hours after the deadline for submitting bids contained in the "Notice Inviting Bids.• ('\ •,r Revised 6/12/18 Contract No.11..4.! Page 22 of 107 Pages Edwards Construction Group, Inc. BIDDER'S STATEMENT OF TECHNICAL ABILITY AND EXPERIENCE (To Accompany Proposal) LEO CARRILLO RANCH ROOF REPAIR PROJECT CONTRACT NO. 4748 PWS22-1788FAC The Bidder is required to state what work of a similar character to that Included in the proposed Con- tract he/she has successfUly performed and give references, with telephone numbers, which will en- able the City to judge his/her responslblllty, experience and skill. An attachment can be used. Date Name and Address Name and Phone No. Amount Contract of the Employer of Person to Type of Work of Comoleted Contract Contract 02/07/2018* 5anta Maria Bonita School Disl Tony Cuellar, 805-249-0662 Re-roofing & HV AC $1,660,239.9' 7025.Miller,-SantaMaria, CA ln<>•~,1 08/10/2015· Cuadalupe Union School Dist. Ed Cora, 805-343-2114 Re-Roofin2 &-HVAC $510,930.00 4465 9th -Si. Guadalupe, CA laHO.A "The,e um le ro ect1 were com leted under arenl com an V emon &!wards Constructor, and are roofln on! roecla. p p ~ p p p y g yp j ECG and VEC are General Contractors. We do nol perform the roofing ouraclva but work with dedicated and hardworking professional roofing subcontractors to perform the work. ECG hu 3 re-roofing projecta underway right now, scheduled to be 0 completed within the year. We alao have multiple projects completed and underway with new building construction. Please let w know if you would IJlce more detailed information on any of thou projects. Revised 6/12/18 Contract No. ilil Page 23 of 107 Pages Mark Sauer Construction, Inc. 19712 Temescal Canyon Road Corona, CA 92881 California License # 500572 B MIC Excel/e11ce since I 986! Phone: Fax: (951) 279-4245 (95 1) 279-5917 Website: www.msauer.com Email: contact@msauer.com Small Business Cert. #0035176 Nevada License# 0068157 B Registered Historic Projects Completed by Mark Sauer Construction, Inc. State of California and/or National Register Casa De La Guerra -Santa Barbara, California Orena Adobe -Santa Barbara, California * Santa Barbara Bldg. Dept. Special Case Study Yorba-Slaughter Adobe -County of San Bernardino, California Pacific Electric Substation #14 -Santa Ana, Californ ia Woman's Improvement Club of Corona -Corona, California Rancho Santa Fe Irrigation Dist. Office -Rancho Santa Fe, California Serrano Adobe -Lake Forest, California Guajome Ranch -Vista, California Barbara Greenwood Kindergarten Bungalow -Pomona, California Rancho Los Cerritos -Long Beach, California Rancho Los Alamitos (Chimney Project) -Long Beach, California Strathearn Adobe -Simi Valley, California Reyes Adobe (House Repairs) -Agoura Hills, California San Gabriel Mission -San Gabriel, California * 1998 Calif. Preservation Foundation Design Award Virginia Robinson Gardens -Beverly Hills, California Friendship Baptist Church -Pasadena, California * 2000 Calif. Preservation Foundation Design Award * 2000 L.A. Conservancy Preservation Award Phillips Mansion -Pomona, California Hillcrest Park -Fullerton, California Leo Carrillo Ranch -Carlsbad, California Sikes Adobe Farmhouse -San Diego, California * 2005 Calif. Preservation Foundation Design Award * 2004 SOHO People in Preservation Award Reyes Adobe (Barn Project) -Agoura Hills, California Rancho Los Alamitos (Foundation Project) -Long Beach, California Breed Street Shul -Los Angeles, California * 2005 L.A. Conservancy Preservation Award Warner's Ranch -Warner Springs, California * 2009 Calif. Preservation Foundation Design Award Los Penasquitos Ranch -San Diego, California * 2011 San Diego Historic Resources Board Award Leo Carrillo Ranch BBQ -Carlsbad, California Rancho Los Cerritos (Water Tower) -Long Beach, California * 2010 Long Beach Heritage Award San Timoteo Schoolhouse -Riverside County, California * 2008 Calif. Preservation Foundation Design Award * 2009 Old Riverside Foundation Award Leo Carrillo Ranch Barn Stabilization -Carlsbad, California * 2012 California Govemor'l· Award Walker House -San Dimas, California * 2010 L.A. Conservancy Preservation Award * 2010 Califomia Preservation Foundation Award Sikes Adobe Farmhouse Reconstruction -San Diego, California 2011 San Diego Historic Resources Board Award 2011 SOHO People in Preservation Award * 2011 California Preservation Foundation Award * 2013 California Governor's Award Vallecito Stage Station Adobe -San Diego, California 1991 1992 1992 1993 1994 1994 1995 1996 1996 1996 1996 1996 1997 1997 1999 2000 2001 2002 2002 2003 2004 2004 2004 2005 2006 2006 2007 2007 2009 2009 2010 2010 Montanez Adobe -San Juan Capistrano, California * 2012 California Preservation Foundation Award * 2012 San Diego A/A Award (Devine Detail) Bailey Adobe Stabilization -Anza Borrego Desert, California San Diego Mission de Alcala Rafter Restoration -San Diego, California St. Josephs Cathedral -San Diego, California Diego Sepulveda Adobe -Costa Mesa, California Fenyes Mansion -Pasadena, California Leo Carrillo Ranch Barn-Theater -Carlsbad, California * 2012 Califomia Governor's Award Warner-Carrillo Ranch Restoration -Warner Springs, California -" 2012 SOHO People in Preservation Award * 2013 California Preservation Foundation Award * 2013 APWA San Diego Chapter Project of the Year * 2013 San Diego A/A Award (Devine Detail and Historic Preservation) 2013 California Governor's Award 2010 2010 2010 2010 2011 2011 2011 2011 Rancho Los Cerritos Visitor's Center -Long Beach, California 2011 Pilgrims Congregational Church Window Stabilization -Pomona, California 2012 Furnace Creek Inn & Resort -Death Valley, California Beginning 2012 and on-going Osuna Adobe -Rancho Santa Fe, Ca. 2012 Audrey Geisel University House UCSD-La Jolla, Ca. 2014 * 2014 California Preservation Foundation Award 2015 San Diego A/A Award * 2015 San Diego Historic Resources Board Award Jt 2015 California Govemor's Award San Diego Mission de Alcala Education CTR -San Diego, Ca. Guajome Adobe Ranch Wood Post Repair Project. Co. of San Diego Johnston Ward House. Escondido, Ca. Los Penasquitos Wing C, San Diego, Ca. Blas Aguilar Adobe Phase I San Juan Capistrano, Ca. Harada House Site Protection. Riverside Ca. Michael White Adobe, San Marino, Ca. Casa de Estudillo (adobe repair/ whitewash) Old Town San Diego Casa de Padre, (adobe repair/ whitewash) San Diego Mission Sepulveda Adobe, Malibu Creek State Park, Calabasas, Ca. Ole Hanson Beach House, Can Clemente, Ca. Blas Aguilar Adobe Phase II San Juan Capistrano, Ca. Hearst Neptune Pool "historic treatment specialist". San Simeon Ca. * 2019 California Preservation Foundation Award Moreno and Machado Adobe. Santa Rosa Plateau Reserve, Riv. Co. Harada House Structural Assessment and Stabilization. Riverside, Ca. Leo Carrillo Ranch Park Stable & Chicken Coop Restoration. Carlsbad, Ca. * 2019 California Preservation Foundation Award Leo Carrillo Ranch Park Maintenance Project, Carlsbad, Ca. Asistencia Mission Restoration Project, Co. of San Bernardino, Ca. John Rains House Dining Room Floor Replacement, Rancho Cucamonga Ca. Yucaipa Adobe Wall Repairs, Yucaipa, Ca. Co. of San Bernardino, Ca. Hunt Ranch Barn Stabilization, Yucaipa, Ca. Co. of San Bernardino, Ca. Parsonage House, bldg. Move & Re-assembly. Long Beach, Ca. Las Tunas Adobe Restoration. San Gabriel, Ca. AC Hotel, Historic Window Restoration. San Diego, Ca. North Sector Office, Adobe Wall Reconstruction. Calif. State Parks Vallecito Stage Station, Adobe Wall Reconstruction. Co. of San Diego Casa de Estudillo, interior restoration phase I Old Town San Diego Machado Y Silvas, exterior fa~ade restoration. Old Town San Diego Torey Pins Lodge, adobe wall reconstruction. State Parks, San Diego Leo Carrillo Ranch Park, Carriage House Roof, Carlsbad Ca. Casa de Estudillo, interior restoration phase 2 Old Town San Diego Diego Sepulveda Adobe, Earthen Floor project. Costa Mesa, Ca. Mission San Diego de Alcala, Museum Expansion Project. San Diego Mission San Luis Rey. Arch and Kiln Restoration. San Diego Ca. 2014 2015 2015 2015 2015 2016 2016 2016 2016 2016 2017 2017 2018 2017 2018 2018 2019 2018 2019 2019 2019 2020 2020 Current 2021 2021 2021 2021 2021 2021 2022 2022 2022 2022 Sylvester Roofing Co Inc. Historical Roofing Projects Date of Name and Address of The Employer Contract Person Type of Work Amount of Contract Contract PUB Construction Inc. 909-455-0187 Complete re-roof on $180,711.00 3/18/2017 23545 Palomino Drive, #104 Chris Yi-President historical building with wood shakes. 2/2/2019 California Custom Homes Jeff Jester Complete re-roof of Cliff $30,565.00 1835A So. Centre City Parkway #436 760-747-1207 May AIA historical home in Escondido, CA 92025 San Diego with 2-Pc Clay tile. 6/2/18 County of San Diego Ranger Mark Reed Re-roof San Diego County $41,559.00 Rancho Guajome Adobe Ranch 760-724-4082 Park of 2-pc tile and BUR 2210 N Santa Fe Ave, low slope sections Vist a, CA 92083 9/20/19 Spectra Company Tim Harris Re-roof with Asphalt $27,327.00 2510 Supply St. 909-599-0760 Shingle on the Graves Pomona, CA 91767 House (AKA Top Gun House) 7/18/18 Spectra Company Tim Harris Re-roof with Cedar Shingle $94,798.00 2510 Supply St. 909-599-0760 on the Hargitt Museum Pomona, CA 91767 BIDDER'S CERTIFICATE OF INSURANCE FOR GENERAL LIABILITY, EMPLOYERS' LIABILITY, AUTOMOTIVE LIABILITY AND WORKERS' COMPENSATION (To Accompany Proposal) LEO CARRILLO RANCH ROOF REPAIR PROJECT CONTRACT NO. 4748 PWS22-1788FAC As a required part of the Bidder's proposal the Bidder must attach either of the following to this page. 1) Certificates of insurance showing conformance with the requirements herein for each of: □ Comprehensive General Liability □ Automobile Liability D Workers Compensation □ Employer's Liability 2) Statement with an insurance carrier's notarized signature stating that the carrier can, and upon payment of fees and/or premiums by the Bidder, will issue to the Bidder Policies of insurance for Comprehensive General Liability, Automobile Liability, Workers Compensation and Employer's Liability in conformance with the requirements herein and Certificates of insurance to the Agency showing conformance with the requirements herein. All certificates of insurance and statements of willingness to issue insurance for auto policies offered to meet the specification of this contract must: 1) Meet the conditions stated in The Notice Inviting Bids and the General Provisions for this project for each insurance company that the Contractor proposes. 2) Cover any vehicle used in the performance of the contract, used onsite or offsite, whether owned, non-owned or hired, and whether scheduled or non-scheduled. ~ Q Revised 6/12/18 Co ntract No.~ Page 24 of 107 Pages ~ ACORD 9 CERTIFICATE OF LIABILITY INSURANCE I DATE (MM/00/YYYY) ~ 5/19/2022 cl THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S), AUTHORIZED REPRESENTATIVE OR PRODUCER, AND THE CERTIFICATE HOLDER. IMPORTANT: If the certificate holder is an ADDITIONAL INSURED, the policy(les) must be endorsed. If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may require an endorsement. A statement on this certificate does not confer rights to the certificate holder in lieu of such endorsement(s). PRODUCER 1,UNIAI, Frank Marino NAME: Leavitt Coastal Valley Insurance Services, Inc r .. ~£>NJ_ c..-\. (805)925-8607 l rf;fc_ Nol: (BOS) 028-7210 License #0598871 !tci"J~ss: frank-marino@leavitt.com 204 E . Enos Dr Suite B INSURER/SI AFFORDING COVERAGE NAIC # Santa Maria CA 93454 INSURER A: Travelers Indemni tv Conmanv of CT 25682 INSURED INSURER B : Travelers Pronertv Casual tv co~anv of 25674 Edwards Construction Group Inc INSURER C : Colonv Insurance Comnanv 39993 PO Box 350 INSURER D: INSURER E : Nipomo CA 93444 INSURER F: COVERAGES CERTIFICATE NUMBER· 22 Master REVISION NUMBER: THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS. INSR ADDL SUBR 1,~~)55~ ,~~To'%~ LTR TYPE OF INSURANCE '···~~ , ... -POLICY NUMBER LIMITS X COMMERCIAL GENERAL LIABILITY EACH OCCURRENCE $ 1 ,000,000 -D CLAIMS-MADE W OCCUR ~~~c ~iJ~:.E~~ncel A $ 300,000 X 'i CO-OT843250-TCT-22 2/1/2022 7/1/2022 MED EXP (Any one pe"'on) $ 10,000 -PERSONAL & MJV INJURY $ 1 ,000,000 -GEN'l AGGREGATE LIMIT APPLIES PER: GENERAL AGGREGATE $ 2 ,000,000 ~ POLICY □ j~ □ LOC PRODUCTS-COMP/OPAGG $ 2 ,000,000 OTHER: Electtonlc Data LlablNty $ 1 ,000,000 AUTOMOBILE LIABILITY ~~"!~d~~t;'INGLE LIMIT $ 1 ,000,000 -X ANY AUTO BODILY INJURY (Per pe"'°") $ B -ALL OWNED -SCHEDULED AUTOS AUTOS X y BA-0T84 8301-22-26-G 2/1/2022 7/1/2022 BODILY INJURY (Per accident) $ --NON-OWNED r:.?~=RAMAGE HIRED AUTOS AUTOS $ -..__ Medical paym<>nts $ 5 ,000 X UMBRELLA UAB H OCCUR EACH OCCURRENCE $ 10 000 000 - B EXCESS LIAB CLAIMS-MADE AGGREGATE $ 10 000 000 OED I X I RETENTION $ 10 000 CUP-OT84934 6-22-26 2/1/2022 7/1/2022 $ WORKERS COMPENSATION X I ~~fn m, I I ~~H- AND EMPLOYERS' LIABILITY Y /N ANY PROPRIETOR/PARTNER/EXECUTNE □ N/A E.L. EACH ACCIDENT $ 1 000 000 OFFICER/MEMBER EXCLUDED? B (Mandatory In NH) y UB-9N981098 7/1/2021 7/1/2022 E.L. DISEASE • EA EMPLOYEE $ 1 000 000 tt yes, deserlbe under DESCRIPTION OF OPERATIONS below E.L. DISEASE • POLICY LIMIT $ 1 000 000 B RENTED/LEASED EQUIPMENT QT 630 lT210340 TIL 22 2/1/2022 7/1/2022 LIMIT/OED $500,000/1 ,000 C POLLUTION LIABILITY CSP42582H 6/24/2021 6/24/2022 LIMIT OCCIAGG $1M/$2M DESCRIPTION OF OPERATIONS / LOCATIONS /VEHICLES (ACORD 101, Additional Remar1<s Schedule, may be attached ii more •pace Is required) The City of Carlsbad is named Additional Insured per attached endorsements . Waiver of subrogation applies. 30 day cancellation notice. CERTIFICATE HOLDER City of Carlsbad/CMWD c/o EXIGIS Insurance Compliance Services PO Box 947 Murrieta, CA 92564 I CANCELLATION SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EXPIRATION DATE Ti-U:REOF, NOTICE WILL BE DELIVERED IN ACCORDANCE WITH THE POLICY PROVISIONS. AUTHORIZED REPRESENTATIVE Dan Lillard/FRMARI © 1988-2014 ACORD CORPORATION. All rights reserved. ACORD 25 (2014/01) INS025 (201401) The ACORD name and logo are registered marks of ACORD ADDITIONAL COVERAGES Ref# I Description I Coverage Code Form No. I Edition Date Uninsured/Underinsured Motorist Bl UMUIM Limit 1 l Limit 2 l Limit 3 I Deductible Amount I Deductible Type Premium 1,000,000 Ref# I Description I Coverage Code Form No. I Edition Date Schedule rate adjustment SRA Limit 1 l Limit 2 l Limit 3 I Deductible Amount j Deductible Type Premium -$30,275.00 Ref# I Description I Coverage Code Form No. I Edition Date Premium discount POIS Limit 1 I Llmit2 I Limit 3 I Deductible Amount I Deductible Type Premium -$4,087.00 Ref# l Description I Coverage Code Form No. I Edition Date Expense constant EXCNT Limit 1 J Limit 2 l Limit 3 I Deductible Amount J Deductible Type Premium $160.00 Ref# I Description I Coverage Code Form No. I Edition Date Limit 1 J Limit 2 I Limit 3 l Deductible Amount I Deductible Type Premium Ref# I Description I Coverage Code Form No. I Edition Date 0 Limit 1 l Limit 2 I Limit 3 I Deductible Amount l Deductible Type Premium Ref# I Description I Coverage Code Form No. I Edition Date Limit 1 j Limit2 I Limit 3 I Deductible Amount l Deductible Type Premium Ref# I Description I Coverage Code Form No. I Edition Date Limit 1 I Limit 2 l Limit 3 I Deductible Amount l Deductible Type Premium Ref# I Description I Coverage Code Form No. I Edition Date Limit 1 l Limit 2 l Limit3 l Deductible Amount I Deductible Type Premium Ref # I Description I Coverage Code Form No. I Edition Date Limit 1 I Limit 2 I Limit3 I Deductible Amount I Deductible Type Premium Ref# I Description I Coverage Code Form No. I Edition Date Limit 1 J Limit 2 I Limit 3 I Deductible Amount I Deductible Type Premium OFADTLCV Copyright 2001, AMS Services, Inc. COMMERCIAL GENERAL LIABILITY C. Method Of Sharing If all of the other insurance pennits contribution by equal shares, we will follow this method also. Under this approach each insurer contributes equal amounts until it has paid its applicable limit of insurance or none of the loss remains, whichever comes first. If any of the other insurance does not permit contribution by equal shares, we will contribute by limits. Under this method, each insurer's share is based on the ratio of its applicable limit of insurance to the total applicable limits of insurance of all insurers. d. Primary And Non-Contributory Insurance If Required By Written Contract If you specifically agree in a written contract or agreement that the insurance afforded to an insured under this Coverage Part must apply on a primary basis, or a primary and non- contributory basis, this insurance is primary to other insurance that is available to such insured which covers such insured as a named insured, and we will not share with that other insurance, provided that: (1) The "bodily in pry'' or "property damage" for which coverage is sought occurs; and (2) The "personal and advertising injury'' for which coverage is sought is caused by an offense that is committed; subsequent to the signing of that contract or agreement by you. 5. Premium Audit a. We will compute all premiums for this Coverage Part in accordance with our rules and rates. b. Premium shown in this Coverage Part as advance premium is a deposit premium only. At the close of each audit period we will compute the earned premium for that period and send notice to the first Named Insured. The due date for audit and retrospective premiums is the date shown as the due date on the bill. If the sum of the advance and audit premiums paid for the policy period is greater than the earned premium, we will return the excess to the first Named Insured. c. The first Named Insured must keep records of the information we need for premium computation, and send us copies at such times as we may request. 6. Representations By accepting this policy, you agree: a. The statements in the Declarations are accurate and complete; b. Those statements are based upon representations you made to us; and c. We ha~ issued this policy in reliance upon your representations. The unintentional omission of, or unintentional error in, any information prmnded by you which we relied upon in issuing this policy will not prejudice your rights under this insurance. However, this provision does not affect our right to collect additional premium or to exercise our rights of cancellation or nonrenewal in accordance with applicable insurance laws or regulations. 7. Separation Of Insureds Except with respect to the Limits of Insurance, and any rights or duties specifically assigned in this Coverage Part to the first Named Insured, this insurance applies: a. As if each Named Insured were the only Named Insured; and b. Separately to each insured against whom claim is made or "suit" is brought. 8. Transfer Of Rights Of Recovery Against others To Us If the insured has rights to recover all or part of any payment we have made under this Coverage Part, those rights are transferred to us. The insured must do nothing after loss to impair them. At our request, the insured will bring "suit" or transfer those rights to us and help us enforce them. 9. When We Do Not Renew If we decide not to renew this Coverage Part, we will mail or deliver to the first Named Insured shown in the Declarations written notice of the nonrenewal not less than 30 days before the expiration date. If notice is mailed, proof of mailing will be sufficient proof of notice. SECTION V -DEFINITIONS 1. "Advertisement" means a notice that is broadcast or published to the general public or specific market segments about your goods, products or services for the purpose of attracting customers or supporters. For the purposes of this definition: a. Notices that are published include material placed on the Internet or on similar electronic means of communication; and b. Regarding websites, only that part of a website that is about your goods, products or services for the purposes of attracting customers or supporters is considered an advertisement. Page 16 of 21 © 2017 The Travelers Indemnity Company. All rights reserved. CG T1000219 Includes copyrighted material of Insurance Services Office, Inc. with its permission. a. We ha\e used up the applicable limit of insurance in the payment of judgments, settlements or medical expenses; or b. The concfrtions set forth ~ or the terms of the agreement described in Paragraph f. above, are no longer met SECTION II-WHO IS AN INSURED 1. If you ae designated in the Declarations as: a. An individual, you and your spouse c¥"e insureds, but only with respect to the conduct of a business of which you are the sde ONner. b. A partnership or joint wnture, you are an insured. Your members, your pcrtnera, aid their spouses c¥"e also insureds, but only with respect to the conduct of your business. c. A limited liability company, you are an insured. Yrur members are also insureds, but only with respect to the conduct of your business. Your ma,agers are insureds, but only with respect to their duties as your maiagers. d. An organi:za:ion other than a partnership, joint VEnture or limited liability cornpa,y, you a"e an insured. Your "eJECUtiw officers" and directa-s are insureds, but only with respect to their duties as your officers or directors. Your stockholders a"e also insureds, but only with respect to their liability as stockholders. e. A trust, you are c11 insured. Your trustees are also Insureds, but only with respect to their duties as trustees. 2. Each ct the follONing is also a, insured: a. YClJr "vdunteer workers" only while performing duties relcted to the conduct of your business, or your "empfC7y13E!S", other than either your "e>eeutive officers" (if you are an orgarii:za:ion other than a partnership, joint venture or limited liability compa,y) or your maiagers (if you are a limited liability company), but only for acts within the scope of their employment by you or while perfoo'ning duties related to the conduct of your business. Ho.vEM3r, none of these "emplC7y13E!S" or "vdunteer workers" are insureds for: (1) "Bodily injury" or "personal injury': (a) To you, to your partners or members (if you cW"e a partnership or joint venture), to your members (If you ae a limited liability company), to a co-"employee" while in the course of his or her employment or performing duties relcted to the conduct of your business, or to your other "vdunteer COMMERCIAL GENERAL LIABILITY workers" while performing duties related to the conduct of your business; (b) To the spouse, child, parent, brother or sister of that co-"empl0y'8e'' or "vdunteer worker'' as a consequence of PcV"agraph (1 )(a) above; (c) For which there is any obligction to share damages with or repay somea,e else who must pay damages because of the injury described in Paragraph (1)(a) or(b).aoote; or (d) Arising out of his or her providing or failing to provide professional health care services. Unless you are in the business or occupation of providing professional health care services, Paragraphs (1Xa), (b), (c) a1d (d) atx,,,,e do net apply to "bodily injury'' aising out of providing or failing to provide first aid or "Good Samaritan service;" by any ct your "emplc1jees" or "vdunteer workers", other than a, employed or \Olunteer doctor. Any such "emplo,ees" or ''\.dunteer workers" providing or failing to provide first aid or "Good Samari1an services" during their work hours for you will be deemed to be acting within the scope of their empk:¥nent by you or performing duties related to the conduct of your business. (2) "Property damage'' to property: (a) Owned, occupied or used by; (b) Rented to, in the care, custody or control of, or aver-which physical control is being exercised for any purpose by; you, any of your "emplc,yees", "vdunteer wor1<ers", any pcnner or member (if you are a partnership or joint venture), or any member (if you are a limited liability company). b. Any person (other than your "empl(¥!e'' or "vdunteer worker''), or any organizaia,, while acting as your real estate mariager. c. Any person or orga,izaion having proper temporary custody of your property if you die, but a,ty: (1) With respect to.liability arising out of the maintenance or use of that property; a,d (2) Until your lega representctiw ·has been appointed. CG T1 000219 © 2017 The Travelers Indemnity Company. All rights reserved. Page11 of21 Includes copyrighted material of Insurance Services Office, Inc. with its permission. COMMERCIAL GENERAL LIABILITY d. Yoor legal representati-.e if you die, but only with respect to duties as such. That representative will hcM:! all your rights and duties under this Coverage Part e. Any person or organizcilon that, with your e>q:>ress or i"l)lied consent, either uses or is responsible for the use of a watercraft that }'OU do not o.vn tha: is: (1) 50 feet long or less; aid (2) Not being used to carry afT'J person or property for a charge 3. Any organizaion }'OU newly acquire or form, other thai a partnership, joint \la'lture or limited liabifity company, aid of which you are the sole ONra or in which you maintain an ONnership interest m more tha, 50%, will qualify as a Named Insured if there is no other sinilar insurance a-.eilable to that organizatioo. Ho.ve-.ier: a. Coverage under this pro"1sion is affcrded only until the 180th day after you acquire or form the organizatioo or the end cl the policy period, whichever is earlier; b. Co\efaQe A does not apply to "bodily injury" or "property damage' that occurred before you acquired or formed the organization; aid c. Cowrage B does not apply to "personal and adwrtising injury" aising out of an offense committed before you acquired or formed the organization. For the purposes of Parcgraph 1. of Section II - Who Is An Insured, ea:h such organizatioo will be deemed to be designaed in the Declarations as: a. An organization, other than a partnership, joint \la'lture or limited liability company; or b. A trust; as indicated in its name or the documents that g0v'erl1 its structure. 4. Any person or organizatioo that is a premises ONner, manager or lessor and that you haw agreed in a written contract or agreement to include as an additional insured on this Coverage Part is an insured, but only with respect to liability for "bodily injury", "property damage" or "personal aid advertising injury" tha:: a. Is "bodily injury' or "property damage" tha occurs, or is "personal and advertising injury" caused by a, offense that is canmitted, subsequent to the signing of that contract or agreement; aid b. Arises out of the oivnership, maintenance or use <:I that part of any premises leased to you. The insurance pro"1ded to such premises ONner, manager or lessor is subject to the following provisions: a. The limits cl insurance provided to such premises o.vr,er, manager or lessor will be the minimum limits that you agreed to pro.iide in the written contract or agreement, or the limits shONn in the Decla--atioos, whichever are less. b. The insurance pro\1ded to such premises o.vr,er, n,a,ager or lessor does not cl>P1Y to: (1) Any "bodily injury" or "property damage" that occurs, or "persona and advertising injury" caused by an offense that is canmitted, afta-you cease to be a tenant in that premises; or (2) Structural alterations, new construction or dernditioo operations performed by or on behalf of such premises o.vner, ma,ager or lessor. 5. Any person or organizatioo that is an equipment lessor c11d that yru h8l.e ~reed in a written contract or agreement to include as an ackfrtional insured on this C0\€1'age Part is an insured, but only with respect to liability for "bodily injury'', "property damage'', or "personal and advertising injury'' tha: a. Is "bodily injury'' or "property damage'' tha: occurs, or is "persooal and adwrtising injury" caused by an offense that Is committed, subsequent to the signing cl that contract or agreement; aid b. Is caused, in whole or in part, by ~ acts or omissions in the maintenance, operation or use of equipment leased to yru by such eqt.ipment lessor. The insurance provided to such equipment lessor is subject to the follONing pro.iisions: a. The limits cl insurance provided to such equipment lessor will be the minimun limits tha you agreed to pro1Ade in the written contract or agreement, or the limits sho.vn in the Declarations, whiche\.er are less. b. The insurance provided to such equipment lessor does not apply to any "bodily injury'' or "property da--nage" that occurs, or "personal and adwrtising injury'' caused by an ctfense that is committed, after the equipment lease e>q:>ires. No person or organi:zaion Is an insured with respect to the cooduct of any current or past partnership, joint Page12 of21 © 2017 The Travelers Indemnity Company. All rights reserved. CG T1 000219 Includes copyrighted material of Insurance Services Office, Inc. with its permission. venture or limited liability compa,y that is not shown as a Named Insured in the Decla-ations. This paragraph does net apply to any such pa"tnership, joint venture or limited liabaity ccmpany that otherwise qualifies as an insured under Section II -Who Is An Insured. SECTION 111-LIMITS OF INSURANCE 1. The Limits of Insurance shcmn in the Declarations and the rules belo.v fix the most we will pay regardless of the number ct: a. Insureds; b. Claims ma::le or "suits" brought; or c. Perscns or orga,izaions ma<ing claims or bringing "suits''. 2. The General Aggregate Limit is the most we will pay for the sum ct: a. Medica ecpenses urder Co.,erageC; b. Damages under Coverage A, e,ccept damcges because of "bodily injuy' or "prq>erty dam;;ge" included in the "products-completed operaior,s hazad"; a,d c. Damages underCo.,erageB. 3. The Products-Completed Operations Aggregate Limit is the most we will pay urder Coverage A for dami:ges because of "bodily injury'' and "property dami:ge' included in the "products-completed operations haza'd''. 4. Subject to Paragraph 2. above, the Persor,al And Advertising lnjuy Limit is the most we will pay urder Cc:M:!rage 8 for the sum a all dami:ges because of an "personal injury'' and "adwrtising injury" sustained by any or,e persor, or organizalioo. 5. Subject to Paragraph 2. or 3. abcJJe, whichever applies, the Each Occurrence Limit is the most we will pay for the sum ct: a . Damages under Co.,erageA; md b. Medica ecpenses under Co.,erageC; because of all "bodily injury" and "property dcrnage'' arising out of any one "occurrence". For the purposes of determining the applicable Each Occurrence Limit, all related acts or omissions committed in pro\Ading or failing to provide first aid or "Good Sama-itcll services'' to any one person will be deemed to be one "occurrence'. 6. Subject to Paragraph 5. abcJJe, the Dami:ge To Premises Rented To You Limit is the most we win pay under Coverage A for dami:ges because of "premises dami:ge' to any one premises. The Damage To Premises Rented To You Limit will be: COMMERCIAL GENERAL LIABILITY a. The amount shown for the Damage To Premises Rented To Yru Limit in the DeclEl'atioos of this Co\eraQ8 Part; or b. $300,000 if no anount is shOM'I for the Damage To Premises Rented To Yoo Limit in the Declarations of this Coverage Part. 7. Subject to Paragraph 5. abo.e, the Medical Expense Limit is the most we will pay under CO\eraQ8 C for all medical expenses because of "bodily injury'' sustained by any one person. The Limits ct lnsura,ce of this Co\Erage Pat apply sepa-ately to ea::h consecuti-.e a,nual period and to a,y remaining period of less tha, 12 mooths, starting with the beginning of the policy period shOM'I in the Declcl'atioos, unless the policy period is extended after issu.n;e for an additiooal period of less than 12 months. In that case, the adcfrtiona period will be deemed part ct the last precedng period fa purposes ct determining the Limits ct Insurance. SECTION IV -COMMERCIAL GENERAL LIABILITY CONDITIONS 1. Bankruptcy Ba,kruptcy or insOM:ll'lcy of the insured or of the insured's estate will net relieve us of our obligations urder this CO\EraQ8 Pat. 2. Duties In The Event Of Occurrence, Offense, Claim Or Suit a. Yru must see to it that we are notified as soon as practicable of a, "occurrence!' or an offense which may result in a claim. To the extent possible, notice should include: (1) How, when and where the "occurrence" or offense took place; (2) The nanes and addresses of any injured persoos and witnesses; aid (3) The nature and locaion of any injury or dcmi:ge arising out of the "occurrence' or offense. b. If a claim is ma:fo or "suit'' is brought against any insured, you must: (1) Immediately record the specifics of the claim or "suit'' and the date recei\ed; a,d (2) Notify us as soon as practicable. You must see to it that we receive written notice of the claim or "suit'' as soon as practicable. c. You a,d a,y ether in\dved insured must: (1) Immediately send us copies of any dema,ds, notices. summonses or legal pc4)ElfS recei\ed in comectior, with ·the claim or "suit''; CG T1 000219 IC) 2017 The Travelers Indemnity Company. All rights reserved. Pi:ge13of21 Includes copyrighted material of Insurance Services Office, Inc. with its permission. COMMERCIAL GENERAL LIABILITY THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. XTEND ENDORSEMENT FOR CONTRACTORS This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE PART GENERAL DESCRIPTION OF COVERAGE -This endorsement broadens coverage. However, coverage for any injury, damage or medical expenses described in any of the provisions of this endorsement may be excluded or limited by another endorsement to this Coverage Part, and these coverage broadening provisions do not apply to the extent that coverage is excluded or limited by such an endorsement. The following listing is a general coverage description only. Read all the provisions of this endorsement and the rest of your policy carefully to determine rights, duties, and what is and is not covered. A. Who Is An Insured -Unnamed Subsidiaries B. Blanket Additional Insured -Governmental Entities -Permits Or Authorizations Relating To Operations PROVISIONS A. WHO IS AN INSURED UNNAMED SUBSIDIARIES The following is added to SECTION II -WHO IS AN INSURED: Any of your subsidiaries, other than a partnership, joint venture or limited liability company, that is not shown as a Named Insured in the Declarations is a Named Insured if: a. You are the sole owner of, or maintain an ownership interest of more than 50% in, such subsidiary on the first day of the policy period; and b. Such subsidiary is not an insured under similar other insurance. No such subsidiary is an insured for "bodily injury'' or "property damage" that occurred, or "personal and advertising injury" caused by an offense committed: a. Before you maintained an ownership interest of more than 50% in such subsidiary; or b. After the date. if any, during the policy period that you no longer maintain an ownership interest of more than 50% in such subsidiary. For purposes of Paragraph 1. of Section II -Who Is An Insured, each such subsidiary will be deemed to be designated in the Declarations as: C. Incidental Medical Malpractice D. Blanket Waiver Of Subrogation E. Contractual Liability -Railroads F. Damage To Premises Rented To You a. An organization other than a partnership, joint venture or limited liability company; or b. A trust; as indicated in its name or the documents that govern its structure. B. BLANKET ADDITIONAL INSURED GOVERNMENTAL ENTITIES -PERMITS OR AUTHORIZATIONS RELATING TO OPERATIONS The following is added to SECTION II -WHO IS AN INSURED: Any governmental entity that has issued a permit or authorization with respect to operations performed by you or on your behalf and that you are required by any ordinance, law, building code or written contract or agreement to include as an additional insured on this Coverage Part is an insured, but only with respect to liability for "bodily injury", "property damage" or "personal and advertising injury" arising out of such operations. The insurance provided to such governmental entity does not apply to: a. Any "bodily injury", "property damage" or "personal and advertising injury" arising out of operations performed for th e governmental entity; or b. Any "bodily injury" or "property damage" included in the "products-completed operations hazard". CG 0316 0219 © 201 7 The Travelers Indemnity Company. All rights reserved. Page 1 of 3 Includes copyrighted material of Insurance Services Office, Inc., with its permission. COMMERCIAL GENERAL LIABILITY C. INCIDENTAL MEDICAL MALPRACTICE 1. The following replaces Paragraph b. of the definition of "occurrence" In the DEFINITIONS Section: b. An act or omission committed in providing or failing to provide "incidental medical services", first aid or "Good Samaritan services" to a person, unless you are in the business or occupation of providing professional health care services. 2. The following replaces the last paragraph of Paragraph 2.a.(1) of SECTION 11 -WHO IS AN INSURED: Unless you are in the business or occupation of providing professional health care services, Paragraphs (1)(a), (b), (c) and (d) above do not apply to "bodily injury" arising out of providing or failing to provide: (a) "Incidental medical services" by any of your "employees" who is a nurse, nurse assistant, emergency medical technician or paramedic; or (b) First aid or "Good Samaritan services" by any of your "employees" or "volunteer workers", other than an employed or volunteer doctor. Any such "employees" or "volunteer workers" providing or failing to provide first aid or "Good Samaritan services" during their work hours for you will be deemed to be acting within the scope of their employment by you or performing duties related to the conduct of your business. 3. The following replaces the last sentence of Paragraph 5. of SECTION 111 -LIMITS OF INSURANCE: For the purposes of determining the applicable Each Occurrence Limit, all related acts or omissions committed in providing or failing to provide "incidental medical services", first aid or "Good Samaritan services" to any one person will be deemed to be one "occurrence". 4. The following exclusion is added to Paragraph 2., Exclusions, of SECTION I - COVERAGES -COVERAGE A -BODILY INJURY AND PROPERTY DAMAGE LIABILITY: Sale Of Pharmaceuticals "Bodily injury'' or "property damage" ansing out of the violation of a penal statute or ordinance relating to the sale of pharmaceuticals committed by, or with the knowledge or consent of, the insured. 5. The following is added to the DEFINITIONS Section: "Incidental medical services" means: a. Medical, surgical, dental, laboratory, x-ray or nursing service or treatment, advice or instruction, or the related furnishing of food or beverages; or b. The furnishing or dispensing of drugs or medical, dental, or surgical supplies or appliances. 6. The following is added to Paragraph 4.b., Excess Insurance, of SECTION IV - COMMERCIAL GENERAL LIABILITY CONDITIONS: This insurance is excess over any valid and collectible other Insurance, whether primary, excess, contingent or on any other basis, that is available to any of your "employees" for "bodily Injury" that arises out of providing or failing to provide "incidental medical services" to any person to the extent not subject to Paragraph 2.a.(1) of Section II -Who Is An Insured. D. BLANKET WAIVER OF SUBROGATION The following is added to Paragraph 8., Transfer Of Rights Of Recovery Against Others To Us, of SECTION IV -COMMERCIAL GENERAL LIABILITY CONDITIONS: If the insured has agreed in a contract or agreement to waive that insured's right of recovery against any person or organization, we waive our right of recovery against such person or organization, but only for payments we make because of: a. "Bodily injury" or "property damage" that occurs; or b. "Personal and advertising injury" caused by an offense that is committed; subsequent to the execution of the contract or agreement. E. CONTRACTUAL LIABILITY -RAILROADS 1. The following replaces Paragraph c. of the definition of "insured contract" in the DEFINITIONS Section: c. Any easement or license agreement; Page 2 of3 @ 2017 The Travelers Indemnity Company. All rights reserved. CG 03 16 02 19 Includes copyrighted material of Insurance Services Office, Inc., with its permission. 2. Paragraph f.(1) of the definition of "insured contract" in the DEFINITIONS Section is deleted. F. DAMAGE TO PREMISES RENTED TO YOU The following replaces the definition of "premises damage" in the DEFINITIONS Section: "Premises damage" means "property damage" to: COMMERCIAL GENERAL LIABILITY a. Any premises while rented to you or temporarily occupied by you with permission of the owner; or b. The contents of any premises while such premises is rented to you, if you rent such premises for a period of seven or fewer consecutive days. CG D316 0219 © 2017 The Travelers Indemnity Company. All rights reserved. Includes copyrighted material of Insurance Services Office, Inc., w~h tts permission. Page 3 of 3 COMMERCIAL GENERAL LIABILITY THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. BLANKET ADDITIONAL INSURED (Includes Products-Completed Operations If Required By Contract) This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE PART PROVISIONS The following is added to SECTION II -WHO IS AN INSURED: Any person or organization that you agree in a written contract or agreement to include as an additional insured on this Coverage Part is an insured, but only: a. With respect to liability for "bodily injury" or "property damage" that occurs, or for "personal injury" caused by an offense that is committed, subsequent to the signing of that contract or agreement and while that part of the contract or agreement is in effect; and b. If, and only to the extent that, such injury or damage is caused by acts or omissions of you or your subcontractor in the performance of "your work" to which the written contract or agreement applies. Such person or organization does not qualify as an additional insured with respect to the independent acts or omissions of such person or organization. The insurance provided to such additional insured is subject to the following provisions: a. If the Limits of Insurance of this Coverage Part shown in the Declarations exceed the minimum limits required by the written contract or agreement, the insurance provided to the additional insured will be limited to such minimum required limits. For the purposes of determining whether this limitation applies, the minimum limits required by the written contract or agreement will be considered to include the minimum limits of any Umbrella or Excess liability coverage required for the additional insured by that written contract or agreement. This provision will not increase the limits of insurance described in Section Ill -Limits Of Insurance. b. The insurance provided to such additional insured does not apply to: (1) Any "bodily injury", "property damage" or "personal injury" arising out of the providing, or failure to provide, any professional architectural, engineering or surveying services, including: (a) The preparing, approving, or failing to prepare or approve, maps, shop drawings, opinions, reports, surveys, field orders or change orders, or the preparing, approving, or failing to prepare or approve, drawings and specifications; and (b) Supervisory, inspection, architectural or engineering activities. (2) Any "bodily injury" or "property damage" caused by "your work" and included in the "products-completed operations hazard" unless the written contract or agreement specifically requires you to provide such coverage for that additional insured during the policy period. c. The additional insured must comply with the following duties: (1) Give us written notice as soon as practicable of an "occurrence" or an offense which may result in a claim. To the extent possible, such notice should include: (a) How, when and where the ''occurrence" or offense took place; (b) The names and addresses of any injured persons and witnesses; and (c) The nature and location of any injury or damage arising out of the "occurrence" or offense. (2) If a claim is made or "suit" is brought against the additional insured: CG D246 0419 @2018 The Travelers Indemnity Company. All rights reserved. Page 1 of 2 COMMERCIAL GENERAL LIABILITY (a) Immediately record the specifics of the claim or "suit'' and the date received; and (b) Notify us as soon as practicable and see to it that we receive written notice of the claim or "suit" as soon as practicable. (3) Immediately send us copies of all legal papers received in connection with the claim or "suit", cooperate with us in the investigation or settlement of the claim or defense against the "suit", and otherwise comply with all policy conditions. (4) Tender the defense and indemnity of any claim or "suit" to any provider of other insurance which would cover such additional insured for a loss we cover. However, this condition does not affect whether the insurance provided to such additional insured is primary to other insurance available to such additional insured which covers that person or organization as a named insured as described in Paragraph 4., Other Insurance, of Section IV -Commercial General Liability Conditions. Page 2 of 2 © 2018 The Travelers Indemnity Company. All rights reserved. CG D2 46 0419 COMMERCIAL AUTO THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. BLANKET ADDITIONAL INSURED -PRIMARY AND NON-CONTRIBUTORY WITH OTHER INSURANCE This endorsement modifies insurance provided under the following: BUSINESS AUTO COVERAGE FORM PROVISIONS 1. The following is added to Paragraph A.1.c., Who Is An Insured, of SECTION II -COVERED AUTOS LIABILITY COVERAGE: This includes any person or organization who you are required under a written contract or agreement between you and that person or organization, that is signed by you before the "bodily injury" or "property damage" occurs and that is in effect during the policy period, to name as an additional insured for Covered Autos Liability Coverage, but only for damages to which this insurance applies and only to the extent of that person's or organization's liability for the conduct of another "insured". 2. The following is added to Paragraph B.S., Other Insurance of SECTION IV -BUSINESS AUTO CONDITIONS: Regardless of the provisions of paragraph a. and paragraph d. of this part 5. Other Insurance, this insurance is primary to and non-contributory with applicable other insurance under which an additional insured person or organization is the first named insured when the written contract or agreement between you and that person or organization, that is signed by you before the "bodily injury" or "property damage" occurs and that is in effect during the policy period, requires this insurance to be primary and non-contributory. CA T4 74 0216 0 2016 The Travelers Indemnity Company. All rights reserved. Page 1 of 1 lndudes copyrighted material of Insurance Services Office, Inc. with its permission. COMMERCIAL AUTO THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. BUSINESS AUTO EXTENSION ENDORSEMENT This endorsement modifies insurance provided under the following: BUSINESS AUTO COVERAGE FORM GENERAL DESCRIPTION OF COVERAGE -This endorsement broadens coverage. However, coverage for any injury, damage or medical expenses described in any of the provisions of this endorsement may be excluded or limited by another endorsement to the Coverage Part, and these coverage broadening provisions do not apply to the extent that coverage is excluded or limited by such an endorsement. The following listing is a general cover- age description only. Limitations and exclusions may apply to these coverages. Read all the provisions of this en- dorsement and the rest of your policy carefully to determine rights, duties, and what is and is not covered. A. BROAD FORM NAMED INSURED H. HIRED AUTO PHYSICAL DAMAGE -LOSS OF B. BLANKET ADDITIONAL INSURED C. EMPLOYEE HIRED AUTO D. EMPLOYEES AS INSURED E. SUPPLEMENTARY PAYMENTS -INCREASED LIMITS F. HIRED AUTO -LIMITED WORLDWIDE COV- ERAGE -INDEMNITY BASIS G. WAIVER OF DEDUCTIBLE -GLASS PROVISIONS A. BROAD FORM NAMED INSURED The following is added to Paragraph A.1., Who Is An Insured, of SECTION II -COVERED AUTOS LIABILITY COVERAGE: Any organization you newly acquire or form dur- ing the policy period over which you maintain 50% or more ownership interest and that is not separately insured for Business Auto Coverage. Coverage under this provision is afforded only un- til the 180th day after you acquire or form the or- ganization or the end of the policy period, which- ever is earlier. B. BLANKET ADDITIONAL INSURED The following is added to Paragraph c. in A. 1 ., Who Is An Insured, of SECTION II -COVERED AUTOS LIABILITY COVERAGE: Any person or organization who is required under a written contract or agreement between you and that person or organization, that is signed and executed by you before the "bodily injury" or "property damage" occurs and that is in effect during the policy period, to be named as an addi- tional insured is an "insured" for Covered Autos Liability Coverage, but only for damages to which USE -INCREASED LIMIT I. PHYSICAL DAMAGE -TRANSPORTATION EXPENSES -INCREASED LIMIT J. PERSONALPROPERTY K. AIRBAGS L. NOTICE AND KNOWLEDGE OF ACCIDENT OR LOSS M. BLANKET WAIVER OF SUBROGATION N. UNINTENTIONAL ERRORS OR OMISSIONS this insurance applies and only to the extent that person or organization qualifies as an "ins~d" under the Who Is An Insured provision contained in Section II. C. EMPLOYEE HIRED AUTO 1. The following is added to Paragraph A.1., Who Is An Insured, of SECTION II -COV- ERED AUTOS LIABILITY COVERAGE: An "employee" of yours is an "insured" while operating an "auto" hired or rented under a contract or agreement in an "employee's" name, with your permission, while performing duties related to the conduct of your busi- ness. 2. The following replaces Paragraph b. in B.5., Other Insurance, of SECTION IV -BUSI• NESS AUTO CONDITIONS: b. For Hired Auto Physical Damage Cover- age, the following are deemed to be cov- ered "autos" you own: (1) Any covered "auto" you lease, hire, rent or borrow: and (2) Any covered "auto" hired or rented by your "employee" under a contract in an "employee's" name, with your CA Tl 53 0215 ~ 2015 The Travelers Indemnity Company. All rights reserved. Page 1 of 4 Includes copyrighted material of Insurance Services Office, Inc. with its permission. COMMERCIAL AUTO perm1ss1on, while performing duties related to the conduct of your busi- ness. However, any "auto" that is leased, hired, rented or borrowed with a driver is not a covered "auto". D. EMPLOYEES AS INSURED The following is added to Paragraph A.1., Who Is An Insured, of SECTION II -COVERED AUTOS LIABILITY COVERAGE: Any "employee" of yours is an "insured" while us- ing a covered "auto" you don't own. hire or borrow in your business or your personal affairs. E. SUPPLEMENTARY PAYMENTS -INCREASED LIMITS 1. The following replaces Paragraph A.2.a.(2), of SECTION II -COVERED AUTOS LIABIL- ITY COVERAGE: (2) Up to $3,000 for cost of bail bonds (in- cluding bonds for related traffic law viola- tions) required because of an "accident" we cover. We do not have to furnish these bonds. 2. The following replaces Paragraph A.2.a.(4), of SECTION II -COVERED AUTOS LIABIL- ITY COVERAGE: (4) All reasonable expenses incurred by the "insured" at our request. including actual loss of earnings up to $500 a day be- cause of time off from work. F. HIRED AUTO -LIMITED WORLDWIDE COV- ERAGE -INDEMNITY BASIS The following replaces Subparagraph (5) in Para- graph B.7 .. Policy Period, Coverage Territory, of SECTION IV -BUSINESS AUTO CONDI- TIONS: (5) Anywhere in the world, except any country or jurisdiction while any trade sanction, em- bargo, or similar regulation imposed by the United States of America applies to and pro- hibits the transaction of business with or within such country or jurisdiction, for Cov- ered Autos Liability Coverage for any covered "auto" that you lease, hire. rent or borrow without a driver for a period of 30 days or less and that is not an "auto" you lease, hire, rent or borrow from any of your "employees", partners (if you are a partnership), members (if you are a limited liability company) or members of their households. (a) With respect to any claim made or "suit" brought outside the United States of America, the territories and possessions of the United States of America, Puerto Rico and Canada: (i) You must arrange to defend the "in- sured" against, and investigate or set- tle any such claim or "suit" and keep us advised of all proceedings and ac- tions. (ii) Neither you nor any other involved "insured" will make any settlement without our consent. (iii) We may, at our discretion, participate in defending the "insured" against. or in the settlement of, any claim or "suit". (iv) We will reimburse the "insured" for sums that the "insured" legally must pay as damages because of "bodily injury" or "property damage" to which this insurance applies, that the "in- sured" pays with our consent. but only up to the limit described in Para- graph C., Limits Of Insurance, of SECTION II -COVERED AUTOS LIABILITY COVERAGE. (v) We will reimburse the "insured" for the reasonable expenses incurred with our consent for your investiga- tion of such claims and your defense of the "insured" against any such "suit", but only up to and included within the limit described in Para- graph C., Limits Of Insurance, of SECTION II -COVERED AUTOS LIABILITY COVERAGE, and not in addition to such limit. Our duty to make such payments ends when we have used up the applicable limit of insurance in payments for damages, settlements or defense expenses. (b) This insurance is excess over any valid and collectible other insurance available to the "insured" whether primary, excess, contingent or on any other basis. (c) This insurance is not a substitute for re- quired or compulsory insurance in any country outside the United States, its ter- ritories and possessions, Puerto Rico and Canada. Page 2 of 4 C 2015 The Travelers Indemnity Company. All rights reserved. CA Tl 53 02 15 lnpludes copyrighted material of Insurance Services Office, Inc. with its permission. You agree to maintain all required or compulsory insurance in any such coun- try up to the minimum limits required by local law. Your failure to comply with compulsory insurance requirements will not invalidate the coverage afforded by this policy, but we will only be liable to the same extent we would have been liable had you complied with the compulsory in- surance requirements. (d) It is understood that we are not an admit- ted or authorized insurer outside the United States of America. its territories and possessions, Puerto Rico and Can- ada. We assume no responsibility for the furnishing of certificates of insurance, or for compliance in any way with the laws of other countries relating to insurance. G. WAIVER OF DEDUCTIBLE -GLASS The following is added to Paragraph D., Deducti- ble, of SECTION Ill -PHYSICAL DAMAGE COVERAGE: No deductible for a covered "auto" will apply to glass damage if the glass is repaired rather than replaced. H. HIRED AUTO PHYSICAL DAMAGE -LOSS OF USE -INCREASED LIMIT The following replaces the last sentence of Para- graph A.4.b., Loss Of Use Expenses, of SEC- TION Ill -PHYSICAL DAMAGE COVERAGE: However, the most we will pay for any expenses for loss of use is $65 per day, to a maximum of $750 for any one "accident". I. PHYSICAL DAMAGE -TRANSPORTATION EXPENSES -INCREASED LIMIT The following replaces the first sentence in Para- graph A.4.a., Transportation Expenses, of SECTION 111 -PHYSICAL DAMAGE COVER- AGE: We will pay up to $50 per day to a maximum of $1 ,500 for temporary transportation expense in- curred by you because of the total theft of a cov- ered "auto" of the private passenger type. J. PERSONAL PROPERTY The following is added to Paragraph A.4., Cover- age Extensions, of SECTION Ill -PHYSICAL DAMAGE COVERAGE: Personal Property We will pay up to $400 for "loss" to wearing ap- parel and other personal property which is: (1) Owned by an "insured"; and COMMERCIAL AUTO (2) In or on your covered "auto". This coverage applies only in the event of a total theft of your covered "auto". No deductibles apply to this Personal Property coverage. K. AIRBAGS The following is added to Paragraph B.3., Exclu- sions, of SECTION Ill -PHYSICAL DAMAGE COVERAGE: Exclusion 3.a. does not apply to "loss" to one or more airbags in a covered "auto" you own that in- flate due to a cause other than a cause of "loss" set forth in Paragraphs A.1.b. and A.1.c., but only: a. If that "auto" is a covered "auto" for Compre- hensive Coverage under this policy; b. The airbags are not covered under any war- ranty; and c. The airbags were not intentionally inflated. We will pay up to a maximum of $1,000 for any one "loss". L NOTICE AND KNOWLEDGE OF ACCIDENT OR LOSS The following is added to Paragraph A.2.a., of SECTION IV -BUSINESS AUTO CONDITIONS: Your duty to give us or our authorized representa- tive prompt notice of the "accident" or "loss" ap- plies only when the "accident" or "loss" is known to: (a) You (if you are an individual); (b) A partner (if you are a partnership); (c) A member (if you are a limited liability com- pany); (d) An executive officer. director or insurance manager (if you are a corporation or other or- ganization); or (e) Any "employee" authorized by you to give no- tice of the "accident" or "loss•. M. BLANKET WAIVER OF SUBROGATION The following replaces Paragraph A.5., Transfer Of Rights Of Recovery Against Others To Us, of SECTION IV -BUSINESS AUTO CONDI- TIONS : 5. Transfer Of Rights Of Recovery Against Others To Us We waive any right of recovery we may have against any person or organization to the ex- tent required of you by a written contract signed and executed prior to any "accident" or "loss", provided that the "accident" or "loss" arises out of operations contemplated by CA T3 53 02 15 ~ 2015 The Travelers Indemnity Company. All rights reserved. Page 3 of4 Includes copyrighted material of Insurance Services Office, Inc. with its permission. COMMERCIAL AUTO such contract. The waiver applies only to the person or organization designated in such contract. N. UNINTENTIONAL ERRORS OR OMISSIONS The following is added to Paragraph B.2., Con- cealment, Misrepresentation, Or Fraud, of SECTION IV -BUSINESS AUTO CONDITIONS: The unintentional om1ss1on of, or unintentional error in, any information given by you shall not prejudice your rights under this insurance. How- ever this provision does not affect our right to col- lect additional premium or exercise our right of cancellation or non-renewal. Page 4 of 4 © 2015 The Travelers Indemnity Compa ny. All rights reserved . CA T353 0215 Includes copyrighted material of Insurance Servlc.es Offic.e, Inc. with its permission. ~ TRAVELERSJ ONE TOWER SQUARE HARTFORD CT 06183 WORKERS COMPENSATION AND EMPLOYERS LIABILITY POLICY ENDORSEMENT WC 99 03 76 ( A) -001 POLICY NUMBER: UB-9N981098 WAIVER OF OUR RIGHT TO RECOVER FROM OTHERS ENDORSEMENT -CALIFORNIA (BLANKET WAIVER) We have the right to recover our payments from anyone liable for an injury covered by this policy. We will not enforce our right against the person or organization named in the Schedule. The additional premium for this endorsement shall be 2 . oo % of the California workers' compensation pre- mium. Person or Organization ANY PERSON OR ORGANIZATION FOR WHICH THE INSURED HAS AGREED BY WRITTEN CONTRACT EXECUTED PRIOR TO LOSS TO FURNISH THIS WAIVER. Schedule Job Description This endorsement changes the policy to which it is attached and is effective on the date issued unless otherwise stated. (The information below is required only when this endorsement is issued subsequent to preparation of the policy.) Endorsement Effective 7-01-2021 Insured Insurance Company DATE OF ISSUE: 6-28-2021 Policy No. UB-9N981098 Endorsement No. Premium Countersigned by ~Q <.:: ST ASSIGN: Page 1 of 1 UMBRELLA d. That Extended Reporting Period endorsement is issued by us and made a part of this policy. 3. Any Extended Reporting Period endorsement for this insurance will not reinstate or increase the Limits of Insurance or extend the policy period. 4. Except with respect to any provisions to the contrary contained in Paragraphs 1., 2. or 3. above, all provisions of any option to purchase an "extended reporting period" granted to you in the "underlying insurance" apply to this insurance. J. INSPECTIONS AND SURVEYS 1. We have the right but are not obligated to: a. Make inspections and surveys at any time; b. Give you reports on the conditions we find; and c. Recommend changes. 2. Any inspections, surveys, reports or recommendations relate only to insurability and the premiums to be charged. We do not make safety inspections. We do not undertake to perform the duty of any person or organization to provide for the health or safety of workers or the public. We do not warrant that conditions: a. Are safe or healthful; or b. Comply with laws, regulations, codes or standards. K. LEGAL ACTION AGAINST US 1. No person or organization has a right under this insurance: a. To join us as a party or otherwise bring us into a "suit" asking for damages from an insured; or b. To sue us on this insurance unless all of its terms have been fully complied with. 2. A person or organization may sue us to recover on an agreed settlement or on a final judgment against an insured. We will not be liable for damages that: a. Are not payable under the terms of this insurance; or b. Are in excess of the applicable limit of insurance. An agreed settlement means a settlement and release of liability signed by us, the insured and the claimant or the claimant's legal representative. L. MAINTENANCE OF UNDERLYING INSURANCE 1. The insurance afforded by each policy of "underlying insurance" will be maintained for the full policy period of this Excess Follow- Form And Umbrella Liability Insurance. This provision does not apply to the reduction or exhaustion of the aggregate limit or limits of such "underlying insurance" solely by payments as permitted in Paragraphs 4.a.(1), (2) and (3) of COVERAGE A -EXCESS FOLLOW-FORM LIABILITY of SECTION I - COVERAGES. As such policies expire, you will renew them at limits and with coverage at least equal to the expiring limits of insurance. If you fail to comply with the above requirements, Coverage A is not invalidated. However, in the event of a loss, we will pay only to the extent that we would have paid had you complied with the above requirements. 2. The first Named Insured shown in the Declarations must give us written notice of any change in the "underlying insurance" as respects: a. Coverage; b. Limits of insurance; c. Termination of any coverage; or d. Exhaustion of aggregate limits. 3. If you are unable to recover from any "underlying insurer" because you fail to comply with any term or condition of the "underlying insurance", Coverage A is not invalidated. However, we will pay for any loss only to the extent that we would have paid had you complied with that term or condition in that "underlying insurance". M. OTHERINSURANCE This insurance is excess over any valid and collectible "other insurance" whether such "other insurance" is stated to be primary, contributing, excess. contingent or otherwise. This provision does not apply to a policy bought specifically to apply as excess of this insurance. However, if you specifically agree in a written contract or agreement that the insurance provided to any person or organization that qualifies as an insured under this insurance must apply on a primary basis, or a primary and non-contributory basis, then insurance provided under Coverage A is subject to the following provisions: Page 14 of 22 © 2016 The Travelers Indemnity Company. All rights reserved. EU 00 010716 1. This insurance will apply before any "other insurance" that is available to such additional insured which covers that person or organization as a named insured, and we will not share with that "other insurance", provided that the injury or damage for which coverage is sought is caused by an "event" that takes place or is committed subsequent to the signing of that contract or agreement by you. 2. This insurance is still excess over any valid and collectible "other insurance", whether primary, excess, contingent or otherwise, which covers that person or organization as an additional insured or as any other insured that does not qualify as a named insured. N. PREMIUM 1. The first Named Insured shown in the Declarations is responsible for the payment of all premiums and will be the payee for any return premiums. 2. If the premium is a flat charge, it is not subject to adjustment except as provided in Paragraph 4. below. 3. If the premium is other than a flat charge, it is an advance premium only. The earned premium will be computed at the end of the policy period, or at the end of each year of the policy period if the policy period is two years or longer, at the rate shown in the Declarations, subject to the Minimum Premium. 4. Additional premium may become payable when coverage is provided for additional insureds under the provisions of SECTION II -WHO IS AN INSURED. 0 . PREMIUM AUDIT The premium for this policy is the amount stated in Item 5. of the Declarations. The premium is a flat charge unless it is specified in the Declarations as adjustable. P. PROHIBITED COVERAGE UNLICENSED INSURANCE 1. With respect to loss sustained by any insured in a country or jurisdiction in which we are not licensed to provide this insurance, this insurance does not apply to the extent that insuring such loss would violate the laws or regulations of such country or jurisdiction. 2. We do not assume responsibility for: a. The payment of any fine, fee, penalty or other charge that may be imposed on any person or organization in any country or jurisdiction because we are not licensed to UMBRELLA provide insurance in such country or jurisdiction; or b. The furnishing of certificates or other evidence of insurance in any country or jurisdiction in which we are not licensed to provide insurance. Q. PROHIBITED COVERAGE TRADE OR ECONOMIC SANCTIONS We will provide coverage for any loss, or otherwise will provide any benefit, only to the extent that providing such coverage or benefit does not expose us or any of our affiliated or parent companies to: 1. Any trade or economic sanction under any law or regulation of the United States of America; or 2. Any other applicable trade or economic sanction, prohibition or restriction. R. REPRESENTATIONS By accepting this insurance, you agree: 1. The statements in the Declarations and any subsequent notice relating to "underlying insurance" are accurate and complete; 2. Those statements are based upon representations you made to us; and 3. We have issued this insurance in reliance upon your representations. S. SEPARATION OF INSUREDS Except with respect to the Limits of Insurance, and any rights or duties specifically assigned in this policy to the first Named Insured shown in the Declarations, this insurance applies: 1. As if each Named Insured were the only Named Insured; and 2. Separately to each insured against whom claim is made or "suit" is brought. T. WAIVER OR TRANSFER OF RIGHTS OF RECOVERY AGAINST OTHERS TO US 1. If the insured has rights to recover all or part of any payment we have made under this insurance, those rights are transferred to us and the insured must do nothing after loss to impair them. At our request, the insured will bring suit or transfer those rights to us and help us, and with respect to Coverage A, the "underlying insurer", enforce them. If the insured has agreed in a contract or agreement to waive that insured's right of recovery against any person or organization, we waive our right of recovery against that person or organization, but only for payments we make because of an "event" that takes place or is committed subsequent to the EU 00 010716 © 2016 The Travelers Indemnity Company. All rights reserved. Page 15 of 22 POLICY NUMBER: DT22-CO-0T843250-TCT-22 COMMERCIAL GENERAL LIABILITY ISSUE DATE: 02-02-22 THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY DESIGNATED PROJECT(S) GENERAL AGGREGATE LIMIT This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE PART SCHEDULE Designated Project(s): Designated Project General Aggregate(s): EACH "PROJECT" FOR WHICH YOU HAVE AGREED IN A WRITTEN CONTRACT THAT IS IN EFFECT DURING THIS POLICY PERIOD, TO PROVIDE A SEPARATE GENERAL AGGREGATE LIMIT, PROVIDED THAT THE CONTRACT IS SIGNED BY YOU BEFORE THE "BODILY INJURY" OR "PROPERTY DAMAGE" OCCURS. GENERAL AGGREGATE LIMIT SHOWN ON THE DECLARATIONS. A. For all sums which the insured becomes legally obligated to pay as damages caused by "occur- rences" under COVERAGE A. (SECTION I), and for all medical expenses caused by accidents un- der COVERAGE C (SECTION I), which can be attributed only to operations at a single desig- nated "project" shown in the Schedule above: 1. A separate Designated Project General Ag- gregate Limit applies to each designated "pro- ject", and that limit is equal to the amount of the General Aggregate Limit shown in the Declarations, unless separate Designated Project General Aggregate(s) are sched- uled above. 2. The Designated Project General Aggregate Limit is the most we will pay for the sum of all damages under COVERAGE A., except damages because of "bodily injury" or "prop- erty damage" included in the "products- completed operations hazard", and for medi- cal expenses under COVERAGE C, regard- less of the number of: a. Insureds; b. Claims made or "suits" brought; or c. Persons or organizations making claims or bringing "suits". 3. Any payments made under COVERAGE A. for damages or under COVERAGE C. for medical expenses shall reduce the Desig- nated Project General Aggregate Limit for that designated "project". Such payments shall not reduce the General Aggregate Limit shown in the Declarations nor shall they re- duce any other Designated Project General Aggregate Limit for any other designated "project" shown in the Schedule above. 4. The limits shown in the Declarations for Each Occurrence, Damage To Premises Rented To You and Medical Expense continue to apply. However, instead of being subject to the General Aggregate Limit shown in the Declarations, such limits will be subject to the applicable Designated Project General Ag- gregate Limit. B. For all sums which the insured becomes legally obligated to pay as damages caused by "occur- rences" under COVERAGE A. (SECTION I), and for all medical expenses caused by accidents un- der COVERAGE C. (SECTION I), which cannot be attributed only to operations at a single desig- nated "project" shown in the Schedule above: CG 0211 01 04 Copyright. The Travelers Indemnity Company, 2004 Page 1 of 2 COMMERCIAL GENERAL LIABILITY 1. Any payments made under COVERAGE A. for damages or under COVERAGE C. for medical expenses shall reduce the amount available under the General Aggregate Limit or the Products-Completed Operations Ag- gregate Limit. whichever is applicable; and 2. Such payments shall not reduce any Desig- nated Project General Aggregate Limit. C. Part 2. of SECTION Ill -LIMITS OF INSURANCE is deleted and rep laced by the following: 2. The General Aggregate Limit is the most we will pay for the sum of: a. Damages under Coverage B; and b. Damages from "occurrences" under COVERAGE A (SECTION I) and for all medical expenses caused by accidents under COVERAGE C (SECTION I) which cannot be attributed only to operations at a single designated "project" shown in the SCHEDULE above. D. When coverage for liability arising out of the "products-completed operations hazard" is pro- vided, any payments for damages because of "bodily injury" or "property damage" included in the "products-completed operations hazard" will reduce the Products-Completed Operations Ag- gregate Limit, and not reduce the General Aggre- gate Limit nor the Designated Project General Aggregate Limit. E. For the purposes of this endorsement the Defini- tions Section is amended by the addition of the following definition: "Project" means an area away from premises owned by or rented to you at which you are per- forming operations pursuant to a contract or agreement. For the purposes of determining the applicable aggregate limit of insurance, each "project" that includes premises involving the same or connecting lots, or premises whose con- nection is interrupted only by a street, roadway, waterway or right-of-way of a railroad shall be considered a single "project". F. The provisions of SECTION Ill -LIMITS OF INSURANCE not otherwise modified by this en- dorsement shall continue to apply as stipulated. Page 2 of 2 Copyright, The Travelers Indemnity Company, 2004 CG D2 11 01 04 Table of Contents I. II. Ill. COVERAGE A -CONTRACTING SERVICES POLLUTION LIABILITY 1. Third-Party Claims 2. Emergency Expenses COVERAGE B -ENVIRONMENTAL CRISIS MANAGEMENT COSTS EXCLUSIONS a. Claims Brought by Waste Disposal Facility Owner or Operator b. Contractual Liability c. Covered by Project-Specific Insurance d. Criminal Fines, Penalties or Assessments e. Damage to Your Work f. Employer's Liability g. Expected or Intended Injury or Damage h. Failure to Comply i. Intentional Acts j. Internal Expenses k. Known Pollution Condition, Injury or Damage I. Nuclear Material m. Property Damage to a Conveyance n. Related Entities and/or Individuals o. War p. Waste Disposal q. Workers' Compensation and Similar Laws r. Your Product IV. DEFENSE V. WHO IS AN INSURED VI. LIMITS OF LIABILITY ANO DEDUCTIBLE 1. Policy Aggregate Limit 2. Contracting Services Pollution Liability -Each Pollution Condition Limit 3. Environmental Crisis Management Costs Limit 4. Multiple Policies or Policy Periods 5. Extension of Policy Period 6. Deductible VII. NOTICE, RIGHTS AND DUTIES 1. Your Duties in the Event of a Pollution Condition 2. Our Rights in the Event of a Pollution Condition 3. Your Duties in the Event of a Claim or Suit 4. Your Duties with Respect to Emergency Expenses 5. Knowledge of a Pollution Condition 6. Mistaken Notice CPL001-0615 Includes copyrighted material of Insurance Services Office, Inc., with its permission. 4 4 5 8 8 10 12 Page 11 (2) Property damage or environmental damage to your product, arising out of it or any part of it. However, subparagraph (1) does not apply to your products that are installed as part of your work at a job site. IV. DEFENSE We have the right and duty to defend the insured against a suit seeking damages to which this insurance applies. We have no duty to defend the insured against any claim or suit seeking damages to which this insurance does not apply. Our duty to defend ends when the applicable Limit of Liability has been exhausted by the payment of loss. We may, at our discretion, investigate any pollution condition or claim and settle any claim or suit. With respect to any pollution condition or claim we investigate or suit we defend, we will pay legal defense costs. Legal defense costs are in addition to, and do not reduce, the limits of liability. V . WHO IS AN INSURED Each of the following is an insured: 1. If you are designated in the Declarations as: a. An individual, you and your spouse are insureds, but only with respect to the conduct of a business of which you are the sole owner. b. A partnership or joint venture, you are an insured. Your members, your partners, and their spouses are also insureds, but only with respect to the conduct of your business. c. A limited liability company, you are an insured. Your members are also insureds, but only with respect to the conduct of your business. Your managers are insureds, but only with respect to their duties as your managers. d. An organization other than a partnership, joint venture or limited liability company, you are an insured. Your executive officers and directors are insureds, but only with respect to their duties as your officers or directors. Your stockholders are also insureds, but only with respect to their liability as stockholders. e. A trust, you are an insured. Your trustees are also insureds, but only with respect to their duties as trustees. 2. Each of the following is also an insured: a. Your volunteer workers, but only while performing duties related to the conduct of your business, or your employees, other than either your executive officers (if you are an organization other than a partnership, joint venture or limited liability company) or your managers (if you are a limited liability company), but only for acts within the scope of their employment by you or while performing duties related to the conduct of your business. However, none of these employees or volunteer workers is an insured for: CPL001-0615 (1) Bodily injury: Includes copyrighted material of Insurance Services Office, Inc., with its permission. Page J 8 (a) To you, to your partners or members (if you are a partnership or joint venture), or to your members (if you are a limited liability company); (b) For which there is any obligation to share damages with or repay someone else who must pay damages because of the injury described in subparagraph (1) (a) above; or (c) Arising out of the providing or failure to provide professional health care services except incidental health care services provided by any physician, dentist, nurse, emergency medical technician or paramedic who is employed by you to provide such services and provided you are not engaged in the business of providing such services. (2) Property damage or environmental damage to property: (a) Owned, occupied or used by; or (b) Rented to, in the care, custody or control of, or over which physical control is being exercised for any purpose by you, any of your employees, volunteer workers, any partner or member (if you are a partnership or joint venture), or any member (if you are a limited liabil ity company). b. Any person (other than your employee or volunteer worker), or any organization while acting as your real estate manager. c. Any person or organization having proper temporary custody of your property if you die, but only: (1) With respect to liability arising out of the maintenance or use of that property; and (2) Until your legal representative has been appointed. d. Your legal representative if you die, but only with respect to duties as such. That representative will have all your rights and duties under this Policy. 3. Any subsidiary, associated, affiliated or allied company or corporation, including subsidiaries thereof, of which you have more than 50% ownership interest as of the inception date is a Named Insured; however, such entities shall cease to be a Named Insured if you cease to maintain more than a 50% ownership interest. 4. Any organization you newly acquire or form, other than a partnership, joint venture or limited liability company, and over which you maintain ownership or majority interest, will qualify as a Named Insured if there is no other similar insurance available to that organization. However, coverage for such organization: a. Is afforded only until the 90th day after you acquire or form the organization or the end of the policy period, whichever is earlier; b. Applies only if you give us written notice within 90 days after you acquire or form the organization, or before the end of the policy period, whichever is earlier; c. Is conditioned upon your payment of any additional premium that we charge for such organization; CPL001 -0615 Includes copyrighted material of Insurance Services Office, Inc., with its permission. Page 19 d. Is subject to any changes in policy terms, conditions or exclusions that we impose; and e. Does not apply to any bodily injury, property damage, environmental damage or pollution condition that took place before you acquired or formed the organization . Unless there is compliance with each of subparagraphs b. through e. above, there shall be no coverage under this Policy for a newly acquired or formed organization. 5. Any person or organization with whom you agree to include as an insured pursuant to a written contract, written agreement or permit is an insured, but only with respect to bodily injury, property damage or environmental damage: (i) arising out of your work, including completed operations, (ii) caused, in whole or in part, by your acts or omissions or the acts or omissions of those acting on your behalf, and (iii) only for the lesser of the applicable limits of liability set forth in Section VI. LIMITS OF LIABILITY AND DEDUCTIBLE or the minimum limits of liability required by such written contract. The insurance afforded under this paragraph 5. only applies to the extent permitted by law and will not be broader than that which you are required by the contract or agreement to provide for such insured. Furthermore, a manager or lessor of premises, a lessor of leased equipment, or a mortgagee, assignee, or receiver is not an insured as respects bodily injury, property damage or environmental damage: a. Arising out of any pollution condition that takes place after the equipment lease expires or you cease to be a tenant; or b. Arising out of structural alterations, new construction or demolition operations performed by or on behalf of the manager or lesser of premises, or mortgagee, assignee, or receiver. No person or organization is an insured with respect to the conduct of any current or past partnership, joint venture or limited liability company that is not shown as a Named Insured in the Declarations. VI. LIMITS OF LIABILITY AND DEDUCTIBLE Regardless of the number of claims, suits, claimants or insureds, the following limits of liability apply: 1. Policy Aggregate Limit The Policy Aggregate Limit set forth in Item 3 of the Declarations is the most we will pay for all loss under this Policy. 2. Contracting Services Pollution Liability -Each Pollution Condition Limit Subject to Paragraph 1. above, the Contracting Services Pollution Liability -Each Pollution Condition Limit set forth in Item 3 of the Declarations is the most we will pay for all loss arising out of the same, related, continuous or repeated pollution condition(s). 3. Environmental Crisis Management Costs Limit Subject to Paragraph 1. above, the Environmental Crisis Management Costs Limit set forth in Item 3 of the Declarations is the most we will pay for all loss under Coverage B - Environmental Crisis Management Costs. CPL00 1-0615 Includes copyrighted material of Insurance Services Office, Inc., with its permission. Page 110 POLICY NUMBER: CUP-0T849346-22-26 UMBRELLA ISSUE DATE: 02/01/2022 THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. AGGREGATE LIMIT APPLIES ON A PER PROJECT BASIS SUBJECT TO THE TOTAL AGGREGATE LIMIT This endorsement modifies insurance provided under the following: EXCESS FOLLOW-FORM AND UMBRELLA LIABILITY INSURANCE SCHEDULE OF TOTAL AGGREGATE LIMIT Total Aggregate Limit S 10,000 PROVISIONS 1. The following is added to Paragraph B. of SECTION Ill -LIMITS OF INSURANCE: For damages because of "bodily injury" and "property damage", if any "underly ing insurance" applies a separate aggregate limit in the same policy for each "project ", other than a products- completed operations aggregate limit, then the General Aggregate Limit will apply in the same manner as such aggregate limit in such "underlying insurance". However, we won't pay more than the Total Aggregate Limit shown in the Schedule Of Total Aggregate Limit for the combined total of all damages covered by this policy because of all "bodily injury" or "property damage" arising out of "projects". For the purposes of determining the applicable General Aggregate Limit, each "project" that includes premises involving the same or connecting lots, or premises whose connection is interrupted only by a street, roadway or waterway, or by a right-of-way o f a railroad, will be considered a single "project". If no entry appears in the Schedule Of Total Aggregate Limit, the Total Aggregate Limit is deemed to be the General Aggregate Limit. 2. The following is added to Paragraph A. of SECTION VI -DEFINITIONS: "Project" means any area away from any premises, site or location that you rent or lease from others, or own, and at which you are performing operations pursuant to a contract or agreement. EU 01 14 07 16 © 2016 The Travelers Indemnity Company. All rights reserved. Page 1 of 1 COMMERCIAL INLAND MARINE THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. BLANKET LOSS PAYEES This endorsement modifies insurance provided under the IM PAK COVERAGE FORM. The following is added to Section E -ADDITIONAL COVERAGE CONDITIONS: Loss Payable Provision In the event of a Covered Cause of Loss to Covered Property in which both you and a Loss Payee share an insurable interest. we will: a. Adjust the loss or damage with you; and b. Pay any claim for loss or damage jointly to you and the Loss Payee as your interests may ap- pear. This endorsement applies to all Covered Property for which a Loss Payee is on file with us or your insur- ance agent or insurance broker. CM TS 60 0110 C 2009 The Travelers Indemnity Company Page 1 of 1 Includes copyrighted material of Insurance Services Office, Inc. with its permission. BIDDER'S STATEMENT RE DEBARMENT (To Accompany Proposal) LEO CARRILLO RANCH ROOF REPAIR PROJECT CONTRACT NO. 4748 PWS22-1788FAC 1) Have you or any of your subcontractors ever been debarred as an irresponsible bidder by another jurisdiction in the State of California? X yes no 2) If yes, what was/were the name(s) of the agency(ies) and what was/were the period(s) of debar- ment(s)? Attach additional copies of this page to accommodate more than two debarments. party debarred agency period of debarment BY CONTRACTOR: EDWARDS CONSTRUCTION GROUP, INC. (name of Contractor) By:A~~ (sign here) BRAD EDWARDS, PRESIDENT (print name/title) party debarred agency period of debarment Page _1_ of _1_ pages of this Re Debarment form 0 Revised 6/12/18 Contract No. ill.B. Page 25 of 107 Pages BIDDER'S DISCLOSURE OF DISCIPLINE RECORD (To Accompany Proposal) LEO CARRILLO RANCH ROOF REPAIR PROJECT CONTRACT NO. 4748 PWS22-1788FAC Contractors are required by law to be licensed and regulated by the Contractors' State License Board which has jurisdiction to investigate complaints against contractors if a complaint regarding a patent act or omission is filed within four years of the date of the alleged violation. A complaint regarding a latent act or omission pertaining to structural defects must be filed within 10 years of the date of the alleged violation. Any questions concerning a contractor may be referred to the Registrar, Contractors' State License board, P.O. Box 26000, Sacramento, California 95826. 1) Have you ever had your contractor's license suspended or revoked by the California Contractors' State license Board two or more times within an eight-year period? X yes no 2) Has the suspension or revocation of your contractor's license ever been stayed? X yes no 3) Have any subcontractors that you propose to perform any portion of the Work ever had their con- tractor's license suspended or revoked by the California Contractors' State license Board two or more times within an eight-year period? X yes no 4) Has the suspension or revocation of the license of any subcontractor's that you propose to perform any portion of the Work ever been stayed? X yes no 5) If the answer to either of 1. or 3. above is yes fully identify, in each and every case, the party disciplined, the date of and violation that the disciplinary action pertain to, describe the nature of the violation and the disciplinary action taken therefore. NIA (If needed attach additional sheets to provide full disclosure.) Page _1_ of __ 2_ pages of this Disclosure of Discipline form 0 Revised 6/12/18 Contract No. ili!!. Page 26 of 107 Pages BIDDER'S DISCLOSURE OF DISCIPLINE RECORD (CONTINUED) (To Accompany Proposal) LEO CARRILLO RANCH ROOF REPAIR PROJECT CONTRACT NO. 4748 PWS22-1788FAC 6) If the answer to either of 2. or 4. above is yes fully identify, in each and every case, the party who's discipline was stayed, the date of the violation that the disciplinary action pertains to, describe the nature of the violation and the condition (if any) upon which the disciplinary action was stayed. N/A (If needed attach additional sheets to provide full disclosure.) BY CONTRACTOR: EDWARDS CONSTRUCTION GROUP, INC. (name of Contractor) By:_d;~.,,___~ __ h--__ _ (sign here) BRAD EDWARDS, PRESIDENT (print name/title) Page _2_ of _2_ pages of this Disclosure of Discipline form ft Q Revised 6/12/18 Contract No. 4748 Page 27 of 107 Pages NONCOLLUSION DECLARATION TO BE EXECUTED BY BIDDER AND SUBMITTED WITH BID PUBLIC CONTRACT CODE SECTION 7106 LEO CARRILLO RANCH ROOF REPAIR PROJECT CONTRACT NO. 4748 PWS22-1788FAC The undersigned declares: EDWARDS CONSTRUCTION I am the PRESIDENT of GROUP, INC. , the party making the foregoing bid. The bid is not made in the interest of, or on behalf of, any undisclosed person, partnership, company, association, organization, or corporation. The bid is genuine and not collusive or sham. The bidder has not directly or indirectly induced or solicited any other bidder to put in a false or sham bid. The bidder has not directly or indirectly colluded, conspired, connived, or agreed with any bidder or anyone else to put in a sham bid, or to refrain from bidding. The bidder has not in any manner, directly or indirectly, sought by agreement, communication, or conference with anyone to fix the bid price of the bidder or any other bidder, or to fix any overhead, profit, or cost element of the bid price, or of that of any other bidder. All statements contained in the bid are true. The bidder has not, directly or indirectly, submitted his or her bid price or any breakdown thereof, or the contents thereof, or divulged infor- mation or data relative thereto, to any corporation, partnership, company, association, organization, bid depository, or to any member or agent thereof, to effectuate a collusive or sham bid, and has not paid, and will not pay, any person or entity for such purpose. Any person executing this declaration on behalf of a bidder that is a corporation, partnership, joint venture, limited liability company, limited liability partnership, or any other entity, hereby represents that he or she has full power to execute, and does execute, this declaration on behalf of the bidder. I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct and that this declaration is executed on MAY 9 , 20R_ at SANTA MARIA [city], CA [state]. Signature of Bidder 0 Revised 6/12/18 Contract No.~ Page 28 of 107 Pages CONTRACT PUBLIC WORKS This agreement is made this 11"~ day of _____ ~~:----J--------' 2022, by and between the City of Carlsbad, California, a municipal corporation, (he einafter called "City"), and Edwards Construction Group, Inc., a California corporation whose princip I place of business is 4350 Executive Drive, Suite #205, San Diego, CA 92121 (hereinafter called "Contractor''). City and Contractor agree as follows: 1. Description of Work. Contractor shall perform all work specified in the Contract documents for: LEO CARRILLO RANCH ROOF REPAIR PROJECT CONTRACT NO. 4748 PWS22-1788FAC (hereinafter called "project") 2. Provisions of Labor and Materials. Contractor shall provide all labor, materials, tools, equip- ment, and personnel to perform the work specified by the Contract Documents. 3. Contract Documents. The Contract Documents consist of this Contract, Notice Inviting Bids, Contractor's Proposal, Bidder's Bond, Non-collusion Declaration, Designation of Subcontractors, Technical Ability and Experience, Bidder's Statement Re Debarment, Escrow Agreement, Release Form, the Plans and Specifications, the General Provisions, addendum(s) to said Plans and Specifi- cations and General Provisions, and all proper amendments and changes made thereto in accordance with this Contract or the Plans and Specifications, and all bonds for the project; all of which are incor- porated herein by this reference. Contractor, her/his subcontractors, and materials suppliers shall provide and install the work as indi- cated, specified, and implied by the Contract Documents. Any items of work not indicated or specified, but which are essential to the completion of the work, shall be provided at the Contractor's expense to fulfill the intent of said documents. In all instances through the life of the Contract, the City will be the interpreter of the intent of the Contract Documents, and the City's decision relative to said intent will be final and binding. Failure of the Contractor to apprise subcontractors and materials suppliers of this condition of the Contract will not relieve responsibility of compliance. 4. Payment. For all compensation for Contractor's performance of work under this Contract, City shall make payment to the Contractor per section 9-3 PAYMENT of the General Provisions section of this contract. The Engineer will close the estimate of work completed for progress payments on the last working day of each month. The City shall withhold retention as required by Public Contract Code Section 9203. 5. Independent Investigation. Contractor has made an independent investigation of the jobsite, the soil conditions at the jobsite, and all other conditions that might affect the progress of the work and is aware of those conditions. The Contract price includes payment for all work that may be done by Contractor, whether anticipated or not, in order to overcome underground conditions. Any information that may have been furnished to Contractor by City about underground conditions or other job condi- tions is for Contractor's convenience only, and City does not warrant that the conditions are as thus indicated. Contractor is satisfied with all job conditions, including underground conditions and has not relied on information furnished by City. 6. Hazardous Waste or Other Unusual Conditions. If the contract involves digging trenches ~ Q Revised 6/12/18 Contract No.~ Page 29 of 107 Pages or other excavations that extend deeper than four feet below the surface Contractor shall promptly, and before the following conditions are disturbed, notify City, in writing, of any: A. Hazardous Waste. Material that Contractor believes may be material that is hazardous waste, as defined in section 25117 of the Health and Safety Code, that is required to be removed to a Class I, Class 11, or Class Ill disposal site in accordance with provisions of existing law. B. Differing Conditions. Subsurface or latent physical conditions at the site differing from those indicated. C. Unknown Physical Conditions. Unknown physical conditions at the site of any unusual nature, different materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in the contract. City shall promptly investigate the conditions, and if it finds that the conditions do materially so differ, or do involve hazardous waste, and cause a decrease or increase in contractor's costs of, or the time required for, performance of any part of the work shall issue a change order under the procedures described in this contract. In the event that a dispute arises between City and Contractor whether the conditions materially differ, or involve hazardous waste, or cause a decrease or increase in the contractor's cost of, or time re- quired for, performance of any part of the work, contractor shall not be excused from any scheduled completion date provided for by the contract, but shall proceed with all work to be performed under the contract. Contractor shall retain any and all rights provided either by contract or by law which pertain to the resolution of disputes and protests between the contracting parties. 7. Immigration Reform and Control Act. Contractor certifies it is aware of the requirements of the Immigration Reform and Control Act of 1986 (8 USC sections 1101 -1525) and has complied and will comply with these requirements, including, but not limited to, verifying the eligibility for employment of all agents, employees, subcontractors, and consultants that are included in this Contract. 8. Prevailing Wage. Pursuant to the California Labor Code, the director of the Department of Industrial Relations has determined the general prevailing rate of per diem wages in accordance with California Labor Code, section 1773 and a copy of a schedule of said general prevailing wage rates is on file in the office of the City Engineer, and is incorporated by reference herein. Pursuant to Cali- fornia Labor Code, section 1775, Contractor shall pay prevailing wages. Contractor shall post copies of all applicable prevailing wages on the job site. Contractor shall comply with California Labor Code, section 1776, which generally requires keeping accurate payroll records, verifying and certifying pay- roll records, and making them available for inspection. Contractor shall require all subcontractors to comply with Section 1776. 9. Indemnification. Contractor shall assume the defense of, pay all expenses of defense, and indemnify and hold harmless the City, and its officers and employees, from all claims, loss, damage, injury and liability of every kind, nature and description, directly or indirectly arising from or in connec- tion with the performance of the Contract or work; or from any failure or alleged failure of Contractor to comply with any applicable law, rules or regulations including those relating to safety and health; and from any and all claims, loss, damages, injury and liability, howsoever the same may be caused, resulting directly or indirectly from the nature of the work covered by the Contract, except for loss or damage caused by the sole or active negligence or willful misconduct of the City. The expenses of defense include all costs and expenses including attorneys' fees for litigation, arbitration, or other dispute resolution method. Contractor shall also defend and indemnify the City against any challenges to the award of the contract ~ Q Revised 6/12/1 8 Contract No. illa Page 30 of 107 Pages to Contractor, and Contractor will pay all costs, including defense costs for the City. Defense costs include the cost of separate counsel for City, if City requests separate counsel. Contractor shall also defend and indemnify the City against any challenges to the award of the contract to Contractor, arising in whole or in part from alleged inaccuracies or misrepresentation by the Con- tractor, whether intentional or otherwise, and Contractor will pay all costs, including defense costs for the City. Defense costs include the cost of separate counsel for City, if City requests separate counsel. 10. Insurance. Contractor shall procure and maintain for the duration of the contract insurance against claims for injuries to persons or damage to property which may arise from or in connection with the performance of the work hereunder by the Contractor, his or her agents, representatives, employees or subcontractors. Said insurance shall meet the City's policy for insurance as stated in City Council Policy # 70. (A) Coverages and Limits Contractor shall maintain the types of coverages and minimum limits indicted herein: a. Commercial General Liability (CGL) Insurance: Insurance written on an "occurrence" basis, including products-completed operations, personal & advertising injury, with limits no less than $2,000,000 per occurrence. If a general aggregate limit applies, either the general aggregate limit shall apply separately to this project/location or the general aggregate limit shall be twice the required oc- currence limit. b. Business Automobile Liability Insurance: $2,000,000 combined single limit per accident for bodily injury and property damage. In addition, the auto policy must cover any vehicle used in the performance of the contract, used onsite or offsite, whether owned, non-owned or hired, and whether scheduled or non-scheduled. c. Workers' Compensation and Employers' Liability Insurance: Workers' compensation limits as required by the Labor Code of the State of California and Employers' Liability limits of $1 ,000,000 per incident. Workers' compensation offered by the State Compensation Insurance Fund is acceptable to the City. (8) Additional Provisions: Contractor shall ensure that the policies of insurance required under this agreement with the exception of Workers' Compensation and Business Automobile Liability Insurance contain, or are endorsed to contain, the following provisions. a. The City, its officials, employees and volunteers are to be covered as additional insured as re- spects: liability arising out of activities performed by or on behalf of the Contractor; products and com- pleted operations of the contractor; premises owned, leased, hired or borrowed by the contractor. The coverage shall contain no special limitations on the scope of protection afforded to the City, its officials, employees or volunteers. All additional insured endorsements must be evidenced using separate doc- uments attached to the certificate of insurance; one for each company affording general liability, and employers' liability coverage. b. The Contractor's insurance coverage shall be primary insurance as respects the City, its officials, employees and volunteers. Any insurance or self-insurance maintained by the City, its officials, em- ployees or volunteers shall be in excess of the contractor's insurance and shall not contribute with it. c. Any failure to comply with reporting provisions of the policies shall not affect coverage provided to the City, its officials, employees or volunteers. d. Coverage shall state that the contractor's insurance shall apply separately to each insured against whom claim is made or suit is brought, except with respect to the limits of the insurer's liability. (C) Notice of Cancellation. Each insurance policy required by this agreement shall be endorsed to ft Q Revised 6/12/18 Contract No.~ Page 31 of 107 Pages state that coverage shall not be nonrenewed, suspended, voided, canceled, or reduced in coverage or limits except after ten (10) days' prior written notice has been sent to the City by certified mail, return receipt requested. (D) Deductibles and Self-Insured Retention (S.1.R.) Levels. Any deductibles or self-insured reten- tion levels must be declared to and approved by the City. At the option of the City, either: the insurer shall reduce or eliminate such deductibles or self-insured retention levels as respects the City, its officials and employees; or the contractor shall procure a bond guaranteeing payment of losses and related investigation, claim administration and defense expenses. (E) Waiver of Subrogation. All policies of insurance required under this agreement shall contain a waiver of all rights of subrogation the insurer may have or may acquire against the City or any of its officials or employees. (F) Subcontractors. Contractor shall include all subcontractors as insured under its policies or shall furnish separate certificates and endorsements for each subcontractor. Coverages for subcontractors shall be subject to all of the requirements stated herein. (G) Acceptability of Insurers. Insurance is to be placed with insurers that have a rating in Best's Key Rating Guide of at least A-:VII. Insurers must also be authorized to transact the business of in- surance by the State of California Insurance Commissioner as admitted carriers as evidenced by a listing in the official publication of the Department of Insurance of the State of California and/or under the standards specified by City Council Policy# 70. (H) Verification of Coverage. Contractor shall furnish the City with certificates of insurance and orig- inal endorsements affecting coverage required by this clause. The certificates and endorsements for each insurance policy are to be signed by a person authorized by that insurer to bind coverage on its behalf. The certificates and endorsements are to be in forms approved by the City and are to be received and approved by the City before the Contract is executed by the City. (I) Cost of Insurance. The Cost of all insurance required under this agreement shall be included in the Contractor's bid. 11. Claims and Lawsuits. All claims by Contractor shall be resolved in accordance with Public Contract Code section 9204, which is incorporated by reference. A copy of Section 9204 is included in Section 3 of the General Provisions. In addition, all claims by Contractor for $375,000 or less shall be resolved in accordance with the provisions in the Public Contract Code, Division 2, Part 3, Chapter 1, Article 1.5 (commencing with section 20104) which are incorporated by reference. A copy of Article 1.5 is included in Section 3 of the General Provisions. In the event of a conflict between Section 9204 and Article 1.5, Section 9204 shall apply. Notwithstanding the provisions of this section of the contract, all claims shall comply with the Government Tort Claim Act (section 900 et seq., of the California Government Code) for any claim or cause of action for money or damages prior to filing any lawsuit for breach of this agreement. (A) Assertion of Claims. Contractor hereby agrees that any contract claim submitted to the City must be asserted as part of the contract process as set forth in this agreement and not in anticipation of litigation or in conjunction with litigation. (B) False Claims. Contractor acknowledges that if a false claim is submitted to the City, it may be considered fraud and the Contractor may be subject to criminal prosecution. (C) Government Code. Contractor acknowledges that California Government Code sections 12650 et seq., the False Claims Act, provides for civil penalties where a person knowingly submits a false claim to a public entity. These provisions include false claims made with deliberate ignorance of the false information or in reckless disregard of the truth or falsity of the information. ~ Q Revised 6/12/18 Contract No . .4I4a Page 32 of 107 Pages (D) Penalty Recovery. If the City of Carlsbad seeks to recover penalties pursuant to the False Claims Act, it is entitled to recover its litigation costs, including attorney's fees. (E) Debarment for False Claims. Contractor hereby acknowledges that the filing of a false claim may subject the Contractor to an administrative debarment proceeding wherein the Contractor may be prevented from further bidding on public contracts for a period of up to five years. (F) Carlsbad Municipal Code. The provisions of Carlsbad Municipal Code sections 3.32.025, 3.32.026, 3.32.027 and 3.32.028 pertaining to false claims are incorporated herein by reference. (G) Debarment from Other Jurisdictions. Contractor hereby acknowledges that debarment by an- other jurisdiction is grounds for the City of Carlsbad to disqualify the Contractor or subcontractor from participating in future contract bidding. (H) Jurisdiction. Contractor agrees and hereby stipulates that the proper venue and jurisdiction for resolution of any disputes between the parties arising out of this agreement is San Diego County, California. I have read and understand all provisions of Section 11 above. 6£..init ~ ~ 12. Maintenance of Records. Contractor shall maintain and make available at no cost to the City, upon request, records in accordance with sections 1776 and 1812 of Part 7, Chapter 1, Article 2, of the Labor Code. If the Contractor does not maintain the records at Contractor's principal place of business as specified above, Contractor shall so inform the City by certified letter accompanying the return of this Contract. Contractor shall notify the City by certified mail of any change of address of such records. 13. Labor Code Provisions. The provisions of Part 7, Chapter 1, commencing with section 1720 of the Labor Code are incorporated herein by reference. 14. Security. Securities in the form of cash, cashier's check, or certified check may be substituted for any monies withheld by the City to secure performance of this contract for any obligation estab- lished by this contract. Any other security that is mutually agreed to by the Contractor and the City may be substituted for monies withheld to ensure performance under this Contract. 15. Unfair Business Practices. In entering into a public works contract or a subcontract to supply goods, services, or materials pursuant to a public works contract, the contractor or subcontractor offers and agrees to assign to the awarding body all rights, title, and interest in and to all causes of action it may have under Section 4 of the Clayton Act (15 U.S.C. Sec. 15) or under the Cartwright Act (Chapter 2 (commencing with Section 16700) of Part 2 of Division 7 of the Business and Professions Code), arising from purchases of goods, services, or materials pursuant to the public works contract or the subcontract. This assignment shall be made and become effective at the time the awarding body tenders final payment to the contractor, without further acknowledgment by the parties. 16. Provisions Required by Law Deemed Inserted. Each and every provision of law and clause required by law to be inserted in this Contract shall be deemed to be inserted herein and in- cluded herein, and if, through mistake or otherwise, any such provision is not inserted, or is not cor- rectly inserted, then upon application of either party, the Contract shall forthwith be physically amended to make such insertion or correction. 17. Additional Provisions. Any additional provisions of this agreement are set forth in the "Gen- eral Provisions" or "Supplemental Provisions" attached hereto and made a part hereof. NOTARIAL ACKNOWLEDGMENT OF EXECUTION BY ALL SIGNATORIES MUST BE A TT ACHED ft Q Revised 6/12/18 Contract No.~ Page 33 of 107 Pages (CORPORA TE SEAL) CONTRACTOR: EDWARDS CONSTRUCTION GROUP, INC. (name of Contractor) By:~~~ (sign here) BRAD EDWARDS, PRESIDENT Jtint name and title) '-·// l ~ By:----.,....,....---,--,------(sign here) RYAN EDWARDS, VICE PRESIDENT (print name and title) CITY OF CARL the Stat ATTEST: for Faviola Medina, City Clerk Services Manager President or vice-president and secretary or assistant secretary must sign for corporations. If only one officer signs, the corporation must attach a resolution certified by the secretary or assistant secretary under the corporate seal empowering that officer to bind the corporation. APPROVED AS TO FORM: CELIA A. BREWER City Attorney ~ By: i V ,0 AssistantcityPiomey ~ Q Revised 6/12/18 Contract No. ~ Page 34 of 107 Pages EXECUTED IN 2 ORIGINAL COUNTERPARTS BOND NUMBER: 7901099484 LABOR AND MATERIALS BOND WHEREAS, the City of Carlsbad, State of California, has awarded to EDWARDS CONSTRUCTION GROUP INC. (hereinafter designated as the "Principal"), a Contract for: LEO CARRILLO RANCH ROOF REPAIR PROJECT CONTRACT NO. 4748 PWS22-1788FAC in the City of Carlsbad, in strict conformity with the drawings and specifications, and other Contract Documents now on file in the Office of the City Clerk of the City of Carlsbad and all of which are incorporated herein by this reference. WHEREAS, Principal has executed or is about to execute said Contract and the terms thereof require the furnishing of a bond, providing that if Principal or any of their subcontractors shall fail to pay for any materials, provisions, provender or other supplies or teams used in, upon or about the performance of the work agreed to be done, or for any work or labor done thereon of any kind, the Surety on this bond will pay the same to the extent hereinafter set forth. NOW, ___________ THEREFORE WE, EDWARDS CONSTRUCTION GROUP, INC. ' as Principal, (hereinafter designated as the "Contractor"), and NATIONWIDE MUTUAL INSURANCE COMPANY as Surety, are held firmly bound unto the City of Carlsbad in the sum of NINE HUNDRED SEVENTY TWO THOUSAND TWO HUNDRED EIGHTY THREE & 00/100 Dollars ($ 972,283.00 ), said sum being an amount equal to: One hundred percent (100%) of the total amount payable under the terms of the contract by the City of Carlsbad, and for which payment well and truly to be made we bind ourselves, our heirs, executors and administrators, successors, or assigns, jointly and severally, firmly by these presents. THE CONDITION OF THIS OBLIGATION IS SUCH that if the Contractor or his/her subcontrac- tors fail to pay for any materials, provisions, provender, supplies, or teams used in, upon, for, or about the performance of the work contracted to be done, or for any other work or labor thereon of any kind, consistent with California Civil Code section 9100, or for amounts due under the Unemployment Insurance Code with respect to the work or labor performed under this Contract, or for any amounts required to be deducted, withheld, and paid over to the Employment Develop-ment Department from the wages of employees of the contractor and subcontractors pursuant to section 13020 of the Unemployment Insurance Code with respect to the work and labor, that the Surety will pay for the same, and, also, in case suit is brought upon the bond, reasonable attor-ney's fees, to be fixed by the court consistent with California Civil Code section 9554. This bond shall inure to the benefit of any of the persons named in California Civil Code section 9100, so as to give a right of action to those persons or their assigns in any suit brought upon the bond. Surety stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Contract, or to the work to be performed hereunder or the specifications accompanying the same shall affect its obligations on this bond, and it does hereby waive notice of any change, {'. •+r' Revised 6/12/18 Contrn ct No. 4748 Page 35 of 107 Pages extension of time, alterations or addition to the terms of the contract or to the work or to the specifications. In the event that Contractor is an individual, it is agreed that the death of any such Contractor shall not exonerate the Surety from its obligations under this bond. SIGNED AND SEALED, this _23_R_D ____ day of _M_A_Y _________ , 2022 EDWARDS CONSTRUCTION GROUP, INC. (SEAL) (Principal) By:~~ (Signature) ~ca..d Edwo.x:ds . f r'Q..~·, a.Q,t'\'t' (Print Name & Title) NATIONWIDE MUTUAL INSURANCE COMPANY (SEAL) (Sur KEVIN VEGA, ATTORNEY-in-FACT (Print Name & Title) (SEAL AND NOTARIAL ACKNOWLEDGEMENT OF SURETY -ATTACH ATTORNEY-IN-FACT CERTlrlCATE) APPROVED AS TO FORM: CELIA A. BREWER City Attorney By: W.cit~y l' •~ Revised 6/12/18 Contract No. 4748 Page 36 of 107 Pages Power of Attorney KNOW ALL MEN BY THESE PRESENTS THAT: Nationwide Mutual Insurance Company, an Ohio corporation hereinafter referred to severally as the 'Company· and collectively as 'the Companies· does hereby make, constitute and appoint: PHILIP E VEGA, MYRNA F SMITH, KEVIN VEGA, BRITTON CHRISTIANSEN each in their individual capacity, its true and lawful attorney-in-fact, with full power and authority to sign, seal, and execute on its behalf any and all bonds and undertakings, and other obligatory instruments of similar nature, in penalties not exceeding the sum of UNLIMITED and to bind the Company thereby, as fully and to the same extent as if such Instruments were signed by the duly authorized officers of the Company; and all acts of said Attorney pursuant to the authority given are hereby ratified and confirmed, This power of attorney is made and executed pursuant to end by authority of the following resolution duly adopted by the board of directors of the Company: "RESOLVED, that the president, or any vice president be, and each hereby Is, authorized and empowered to appoint attorneys-in-fact of the Company, and to authorize them to execute and deliver on behalf of the Company any and all bonds, forms, applications, memorandums, undertakings, recognizances, transfers, contracts of Indemnity, policies, contracts guaranteeing the fidelity of persons holding positions of public or private trust, and other writings obligatory In nature that the business of the Company may require; and to modify or revoke, with or without cause, any such appointment or authority; provided, however, that the authority granted hereby shall in no way limit the authority of other duly authorized agents to sign and countersign any of said documents on behalf of the Company." "RESOLVED FURTHER, that such attorneys-In-fact shall have full power and authority to execute and deliver any and all such documents and to bind the Company subject to the terms and limitations of the power of attorney issued to them, and to affix the seal of the Company thereto; provided, however, that said seal shall not be necessary for the validity of any such documents." This power of attorney is signed and sealed under and by the following bylaws duly adopted by the board of directors of the Company. Execution of Instruments. Any vice president, any assistant secretary or any assistant treasurer shall have the power and authority to sign or attest all approved documents, instruments, contracts, or other papers in connection with the operation of the business of the company In addition to the chairman of the board, the chief executive officer, president, treasurer or secretary; provided, however, the signature of any of them may be printed, engraved, or stamped on any approved document, contract, instrument, or other papers of the Company. IN WITNESS WHEREOF, the Company has caused this instrument to be sealed and duly attested by the signature of its officer the 20th day of August, 2021. Antonio C. Albanese. Vice President of Nationwide Mutual Insurance Company ACKNOWLEDGMENT STATE OF NEW YORK COUNTY OF NEW YORK: ss On this 20th day of August, 2021, before me came the above-named officer for the Company aforesaid, to me personally known to be the officer described in and who executed the preceding instrument, and he acknowledged the execution of the same, and being by me duly sworn, deposes and says, that he is the officer of the Company aforesaid, that the seal affixed hereto is the corporate seal of said Company, and the said corporate seal and his signature were duly affixed and subscribed to said instrument by the authority and direction of said Company. Stephanlo Rubino McArthur Notary Public, Si.to of New YO<k No. 02MC6270117 aua1r,ec1 In New Yortc County Commbslon E:11oires October 19 2024 CERTIFICATE ~~~~ N--,Plilllo My Conimi»lon Eq,(re, OctONr II, 2024 I, Laura B. Guy, Assistant Secretary of the Company, do hereby certify that the foregoing is a full, true and correct copy of the original power of attorney issued by the Company; that the resolution included therein is a true and correct transcript from the minutes of the meetings of the boards of directors and the same has not been revoked or amended in any manner; that said Antonio C. Albanese was on the date of the execution of the foregoing power of attorney the duly elected officer of the Company, and the corporate seal and his signature as officer were duly affixed and subscribed to the said instrument by the authority of said board of directors; and the foregoing power of attorney is still in full force and effect. IN WITNESS WHEREOF, I have hereunto subscribed my name as Assistant Secretary, and affixed the corporate seal of said Compa:;y this 23rd day of May _2_02_2 __ Assistant Secretary BDJ 1(08-21 )00 CALIFORNIA ALL-PURPOSE ACKNOWLEDGMENT CIVIL CODE§ 1189 A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document. State of California County of LOS ANGELES On 05/23/2022 before me, PHILIP VEGA, NOTARY PUBLIC Date Here Insert Name and Title of the Officer personally appeared KEVIN VEGA, ATTORNEY-in-FACT Name(s) of Signer(s) who proved to me on the basis of satisfactory evidence to be the person-est whose nameW is/ar.e subscribed to the within instrument and acknowledged to me that he/9Re/fhe1/ executed the same in his/tre./their authorized capacity(tes). and that by his/hei:~ signature~ on the instrument the person(lsl, or the entity upon behalf of which the person~ acted, executed the instrument. 1V'> 0 0 0 ♦ ♦ e ~ PHILIP VEGA Notary Publlc • Callfornla I Los Anatlff County Commission# 2327592 ~ y Comm. Explr,s May 31, 2024 Place Notary Seal Above I certify under PENAL TY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct. WITNESS my hand and official seal. ----------------OPTIONAL---------------- Though this section is optional, completing this information can deter alteration of the document or fraudulent reattachment of this form to an unintended document. Description of Attached Document Title or Type of Document: _____________ Document Date: _______ _ Number of Pages: ___ Signer(s) Other Than Named Above: ____________ _ Capacity(ies) Claimed by Signer(s) Signer's Name: ____________ _ Signer's Name: ____________ _ D Corporate Officer -Title(s): ______ _ □ Corporate Officer -Title(s): ______ _ D Partner -D Limited D General D Partner -□ Limited D General D Individual D Attorney in Fact D Individual □ Attorney in Fact D Trustee D Guardian or Conservator □ Trustee □ Guardian or Conservator □Other: ______________ _ □ Other: _____________ _ Signer Is Representing: _________ _ Signer Is Representing: _________ _ ©2014 National Notary Association• www.NationalNotary.org • 1-800-US NOTARY (1-800-876-6827) Item #5907 EXECUTED IN 2 ORIGINAL COUNTERPARTS BOND NUMBER: 7901099484 FAITHFUL PERFORMANCE/WARRANTY BOND WHEREAS, the City Council of the City of Carlsbad, State of California, has awarded to EDWARDS CONSTRUCTION GROUP INC. (hereinafter designated as the "Principal"}, a Contract for: LEO CARRILLO RANCH ROOF REPAIR PROJECT CONTRACT NO. 4748 PWS22-1788FAC in the City of Carlsbad, in strict conformity with the contract, the drawings and specifications, and other Contract Documents now on file in the Office of the City Clerk of the City of Carlsbad, all of which are incorporated herein by this reference. WHEREAS, Principal has executed or is about to execute said Contract and the terms thereof require the furnishing of a bond for the faithful performance and warranty of said Contract; NOW, THEREFORE, WE, EDWARDS CONSTRUCTION GROUP, INC. ' as Principal, (hereinafter designated as the "Contractor"), and NATIONWIDE MUTUAL INSURANCE COMPANY as Surety, are held firmly bound unto the City of Carlsbad in the sum of ________ _ NINE HUNDRED SEVENTY TWO THOUSAND TWO HUNDRED EIGHTY THREE & 00/100 Dollars ($972,283.00 ), said sum being an amount equal to: One hundred percent (100%) of the total amount payable under the terms of the contract by the City of Carlsbad, and for which payment well and truly to be made we bind ourselves, our heirs, executors and administrators, successors, or assigns, jointly and severally, firmly by these presents. THE CONDITION OF THIS OBLIGATION IS SUCH that if the above bounden Contractor, their heirs, executors, administrators, successors or assigns, shall in all things stand to and abide by, and well and truly keep and perform the covenants, conditions, and agreements in the Contract and any alteration thereof made as therein provided on their part, to be kept and performed at the time and in the manner therein specified, and in all respects according to their true intent and meaning, and shall indemnify and save harmless the City of Carlsbad, its officers, employees and agents, as therein stipulated, then this obligation shall become null and void; otherwise it shall remain in full force and effect. As a part of the obligation secured hereby and in addition to the face amount specified therefore, there shall be included costs and reasonable expenses and fees, including reasonable attorney's fees, incurred by the City in successfully enforcing such obligation, all to be taxed as costs and included in any judgment rendered. Surety stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Contract, or to the work to be performed there under or the specifications accompanying the same shall affect its obligations on this bond, and it does hereby waive notice of any change, extension of time, alterations or addition to the terms of the contract or to the work or to the specifications. l' • .., Revised 6/12/18 Contract No. 4748 Page 37 of 107 Pages In the event that Contractor is an individual, it is agreed that the death of any such Contractor shall not exonerate the Surety from its obligations under this bond. SIGNED AND SEALED, this _2_3_R_D ____ day of_M_A_Y _________ , 2022 EDWARDS CONSTRUCTION GROUP, INC. (SEAL) (Principal) By:_~--~---/,__-· -- (Sig nature) ~:ro...c!. £a w,J"ds.1 ea~s,de,V\.t- (Print Name & Title) NATIONWIDE MUTUAL INSURANCE COMPANY (SEAL) (Sur KEVIN VEGA, ATTORNEY-in-FACT (Print Name & Title) (SEAL AND NOTARIAL ACKNOWLEDGEMENT OF SURETY-ATTACH ATTORNEY-IN-FACT CERTIFICATE) APPROVED AS TO FORM: CELIA A. BREWER City Attorney By: fill) a r) Assistant ~ey l' •+;' Revised 6/12/18 Contract No. 4748 Page 38 of 107 Pages Power of Attorney KNOW ALL MEN BY THESE PRESENTS THAT: Nationwide Mutual Insurance Company, an Ohio corporation hereinafter referred to severally as the ·company· and collectively as "the Companies· does hereby make, constitute and appoint: PHILIP E VEGA, MYRNA F SMITH, KEVIN VEGA, BRITTON CHRISTIANSEN each in their individual capacity, its true and lawful attorney-in-fact, with full power and authority to sign, seal, and execute on its behalf any and all bonds and undertakings, and other obligatory instruments of similar nature, in penalties not exceeding the sum of UNLIMITED and to bind the Company thereby, as fully and to the same extent as if such Instruments were signed by the duly authorized officers of the Company; and all acts of said Attorney pursuant to the authority given are hereby ratified and confirmed. This power of attorney is made and executed pursuant to end by authority of the following resolution duly adopted by the board of directors of the Company: "RESOLVED, that the president, or any vice president be, and each hereby Is, authorized and empowered to appoint attorneys-In-fact of the Company, and to authorize them to execute and deliver on behalf of the Company any and all bonds, forms, applications, memorandums, undertakings, recognizances, transfers, contracts of Indemnity, policies, contracts guaranteeing the fidelity of persons holding positions of public or private trust, and other writings obligatory In nature that the business of the Company may require; and to modify or revoke, with or without cause, any such appointment or authority; provided, however, that the authority granted hereby shall in no way limit the authority of other duly authorized agents to sign and countersign any of said documents on behalf of the Company." "RESOLVED FURTHER, that such attorneys-In-fact shall have full power and authority to execute and deliver any and all such documents and to bind the Company subject to the terms and limitations of the power of attorney issued to them, and to affix the seal of the Company thereto; provided, however, that said seal shall not be necessary for the validity of any such documents." This power of attorney is signed and sealed under and by the following bylaws duly adopted by the board of directors of the Company. Execution of Instruments. Any vice president, any assistant secretary or any assistant treasurer shall have the power and authority to sign or attest all approved documents, instruments, contracts, or other papers in connection with the operation of the business of the company In addition to the chairman of the board, the chief executive officer, president, treasurer or secretary; provided, however, the signature of any of them may be printed, engraved, or stamped on any approved document, contract, instrument, or other papers of the Company. IN WITNESS WHEREOF, the Company has caused this instrument to be sealed and duly attested by the signature of its officer the 20th day of August, 2021. Antonio C. Albanese, Vice President of Nationwide Mutual Insurance Company ACKNOWLEDGMENT STATE OF NEW YORK COUNTY OF NEW YORK: ss On this 20th day of August. 2021, before me came the above-named officer for the Company aforesaid, to me personally known to be the officer described In and who executed the preceding instrument, and he acknowledged the execution of the same, and being by me duly sworn, deposes and says, that he is the officer of the Company aforesaid, that the seal affixed hereto Is the corporate seal of said Company, and the said corporate seal and his signature were duly affixed and subscribed to said instrument by the authority and direction of said Company. Swphonlo Rubino McArthur Notary Public, State of New Yoril No. 02MC6270117 aua1rte<1 In New Yor1< County Commission Emros October 19 2024 CERTIFICATE ~~~~ N...,.,P,,olc: My Commi.a1on E.q,lres Oc1ob9r'H,2024 I, Laura 8, Guy, Assistant Secretary of the Company, do hereby certify that the foregoing is a full, true and correct copy of the original power of attorney Issued by the Company; that the resolution included therein Is a true and correct transcript from the minutes of the meetings of the boards of directors and the same has not been revoked or amended in any manner; that said Antonio C. Albanese was on the date of the execution of the foregoing power of attorney the duly elected officer of the Company, and the corporate seal and his signature as officer were duly affixed and subscribed to the said instrument by the authority of said board of directors; and the foregoing power of attorney is still in full force and effect. IN WITNESS WHEREOF, I have hereunto subscribed my name as Assistant Secretary, and affixed the corporate seal of said Company this ~ day of May .c:2.:..:02;:;2 __ Assistant Secretary BDJ 1 (08-21 )00 CALIFORNIA ALL-PURPOSE ACKNOWLEDGMENT CIVIL CODE§ 1189 A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document. State of California County of LOS ANGELES On 05/23/2022 before me, PHILIP VEGA, NOTARY PUBLIC Date Here Insert Name and Title of the Officer personally appeared _K_E_V_IN_V_E_G_A_,_A_T_T_O_R_N_E_Y_-_in_-F_A_C_T ________________ _ Name(s) of Signer(s) who proved to me on the basis of satisfactory evidence to be the person"('sl whose name~ is/ar.e subscribed to the within instrument and acknowledged to me that he/9R.lc/t'h81; executed the same in his/tre./their authorized capacity{f"es). and that by his/hei:Jtheu: signature~ on the instrument the personM, or the entity upon behalf of which the person~ acted, executed the instrument. I certify under PENAL TY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct. Place Notary Sea/ Above ----------------OPTIONAL---------------- Though this section is optional, completing this information can deter alteration of the document or fraudulent reattachment of this form to an unintended document. Description of Attached Document Title or Type of Document: _____________ Document Date: _______ _ Number of Pages: ___ Signer(s) Other Than Named Above: ____________ _ Capacity(ies) Claimed by Signer(s) Signer's Name: ____________ _ Signer's Name: ____________ _ D Corporate Officer -Title(s): ______ _ D Corporate Officer -Title(s): ______ _ D Partner -D Limited D General D Partner -D Limited D General D Individual D Attorney in Fact D Individual D Attorney in Fact D Trustee D Guardian or Conservator D Trustee D Guardian or Conservator D Other: _____________ _ D Other: _____________ _ Signer Is Representing: _________ _ Signer Is Representing: _________ _ ©2014 National Notary Association· www.NationalNotary.org · 1-800-US NOTARY {1-800-876-6827) Item #5907 April 21, 2022 ADDENDUM NO. 1 C cifyof Carlsbad RE: PWS22-1788FAC -Leo Carrillo Ranch Roof Repair Project Please include the attached addendum in the Notice to Bidder/Request for Bids you have for the above project. This addendum must be acknowledged via PlanetBids proposal. JAN£AN 1lAWN£Y Contract Administrator I ACKNOWLEDGE RECEIPT OF ADDENDUM NO. 1 Bidder's Signature Public Works Branch Contract Administration 1635 Faraday Avenue I Carlsbad, CA 92008 or submitted with your bid /} /V ,() l)W )-eJt:td fAJ4U' I • &s Vt?!~ CITY OF CARLSBAD LEO CARRILLO RANCH ROOF REP AIR From: No. of Pages: Date: Bid Due Date: CONTRACT NO. 4748 BID NO. PWS22-1788FAC Addendum No. 1 Steven Stewart, Municipal Projects Manager Phone: (442) 339-2938 steven.stewart@carlsbadca.gov 1635 Faraday Ave Carlsbad, CA 92008 4 (including this page) April 21 , 2022 May 10, 2022 -5:00 PM (no change) Notice: This Addendum forms a part of the Contract Documents for the above identified project and modifies portions of the original Contract Documents. Documents not specifically mentioned in this Addendum remain in full force. Contractor must acknowledge receipt of this Addendum by submitting issued Addendum with RFB response. Failure to do so may subject bidder to disqualification. I. Construction companies present at mandatory job walk, April 7, 2022: a) A Good Roofer, Inc. b) Burke Contractors c) Edwards Construction Group d) ERC Roofing e) Handy Industrial f) Klondike Construction g) Mark Sauer Construction h) Oakhollow Restoration i) Preman Roofing j) Superior Roofing k) Sylvester Roofing II. Comments and Clarifications from Job walk, April 7, 2022: 1. Working hours on the project are from 7:00am and 4:00pm, Monday through Thursday per section 6-7.2 of the Request for Bid. Work on Fridays must be completed by 2:00pm due Bid No. PWS22-1788FAC Addendum No. 1 to public use of the ranch on the weekends. Contractor will also be allowed to work from 7:00am to 5:30pm Monday through Thursday to achieve four (4) ten (10) hour workdays per week. All work areas must be left in a clean, safe, and orderly condition at the end of each workday. 2. Construction related work around the Hacienda is of critical importance due to heavy public use of this area from Fridays at 2:00pm through Sunday evenings. Accordingly, all work in this area of the ranch must be limited to Mondays through Thursdays and cleaned up and secured to satisfaction of city's construction management consultant each Thursday. If the integrity of this work area cannot be maintained per city requirements, this work may have to be completed between December and mid-March at contractor's expense. 3. Contractor is required to drive slowly and exercise caution when driving vehicles on site due to dust generation potential and public use of the ranch. 4. Contractors are encouraged to thoroughly review the Roof Conditions Assessment Report dated March 26, 2020, the project drawings prepared by Heritage Architecture & Planning dated November 8, 2021, and the Request for Bid (Contract 4748, PWS22-1788FAC) published for this project on PlanetBids on or about March 16, 2022, in the preparation of their bid proposal. 5. Per the Request for Bid , contractors qualified to present bids for this project shall be in possession of General Building -B license. 6. The cutoff date and time to submit questions or substitution requests regarding this project via Online Q&A in PlanetBids is April 26, 2022, at 5:00pm. No questions will be entertained after that date. Ill. Questions and Answers 1. Question: Can you provide a copy of the contractors/ vendors who attended the mandatory pre-bid walk on 4/7/22? Answer: Yes, see attached. 2. Question: Will the eity accept the General Contractor's subcontractors and vendors collective/ past experience on similar type projects in lieu of the GC's past experience? Answer: The city will accept a general contractor's project team that has relevant experience shared by a majority of its staff who are regularly engaged in the project work onsite. A vendor's experience will not be considered relevant unless that vendor is performing regular work on site as a subcontractor. 3. Question: Will the city accept a General Contractor with over 40 years of broad-based experience and its staff of over 80 years of collective experience in lieu of the specific project type based qualifications as described in the bid documents? Answer: No. The city requires the skills of contractors experienced in working with historic buildings for this project. 4. Question: Does the city have a list/ contact info of certified, approved and qualified specialty vendors it prefers to utilize for historical preservation work on its properties? Bid No. PWS22-1788FAC Addendum No. 1 Answer: No. The city only requires that specialty vendors/contractors demonstrate their experience working with historic buildings. 5. Question: Can you provide the name / contact for the city's Construction Manager for the project? Answer: Yes, the city will retain SchneiderCM to provide construction management services. SchneiderCM will be represented by Robert Polley, CCM. Bid No. PWS22-1788FAC Addendum No. 1 ~ 1 z.,:z..., GENERAL PROVISIONS FOR LEO CARRILLO RANCH ROOF REPAIR PROJECT CONTRACT NO. 4748 CITY OF CARLSBAD SECTION 1 --TERMS, DEFINITIONS, ABBREVIATIONS, AND SYMBOLS 1-1 TERMS -Unless otherwise stated, the words directed, required, permitted, ordered, in- structed, designated, considered necessary, prescribed, approved, acceptable, satisfactory, or words of like meaning, refer to actions, expressions, and prerogatives of the Engineer. 1-1.1 Reference to Drawings. Where words "shown", "indicated", "detailed", "noted", "scheduled", or words of similar import are used, it shall be understood that reference is made to the plans accom- panying these provisions, unless stated otherwise. 1-1 .2 Directions. Where words "directed", "designated", "selected", or words of similar import are used, it shall be understood that the direction, designation or selection of the Engineer is intended, unless stated otherwise. The word "required" and words of similar import shall be understood to mean "as required to properly complete the work as required and as approved by the Engineer," unless stated otherwise. 1-1.3 Equals and Approvals. Where the words "equal", "approved equal", "equivalent", and such words of similar import are used, it shall be understood such words are followed by the expression "in the opinion of the Engineer", unless otherwise stated. Where the words "approved", "approval", "ac- ceptance", or words of similar import are used, it shall be understood that the approval, acceptance, or similar import of the Engineer is intended. 1-1.4 Perform. The word "perform" shall be understood to mean that the Contractor, at its expense, shall perform all operations, labor, tools and equipment, and further, including the furnishing and in- stalling of materials that are indicated, specified or required to mean that the Contractor, at its expense, shall furnish and install the work, complete in place and ready to use, including furnishing of necessary labor, materials, tools, equipment, and transportation 1-2 Definitions. The following words, or groups of words, shall be exclusively defined by the defi- nitions assigned to them herein. Addendum -Written or graphic instrument issued prior to the opening of Bids which clarifies, corrects, or changes the bidding or Contract Documents. The term Addendum shall include bulletins and all other types of written notices issued to potential bidders prior to opening of Bids. ('\ •+;' Revised 6/15/17 Page 42 of 114 Pages Agency -The City of Carlsbad, California. Agreement -See Contract. Application for Payment -The term "Application for Payment" means the submittal from Contractor wherein payment for certain portions of the completed Work is requested in accordance with Article 9 of the General Provisions Assessment Act Contract -A Contract financed by special assessments authorized under a State Act or procedural ordinance of a City or County. Base -A layer of specified material of planned thickness placed immediately below the pavement or surfacing. Beneficial Occupancy -A The term "Beneficial Occupancy" means the City of Carlsbad's occu- pancy or use of any part of the Work in accordance with Article 9 of the General Provisions. Bid -The offer or proposal of the Bidder submitted on the prescribed form setting forth the prices for the Work. Bidder -Any individual, firm, partnership, corporation, or combination thereof, submitting a Bid for the Work, acting directly or through a duly authorized representative . Board -The officer or body constituting the awarding authority of the Agency, which is the City Council for the City of Carlsbad or the Board of Directors of Carlsbad Municipal Water City. Bond -Bid, performance, and payment bond or other instrument of security. City Council -the City Council of the City of Carlsbad. City Manager -the City Manager of the City of Carlsbad or his/her approved representative. Cash Contract -A Contract financed by means other than special assessments. Change Order-A written order to the Contractor signed by the Agency directing an addition, deletion, or revision in the Work, or an adjustment in the Contract Price or the Contract time issued after the effective date of the Contract. A Change Order may or may not also be signed by the Contractor. City's Construction Management Consultant-the city's agent on site and first level of appeal for informal dispute resolution. Code -The terms Government Code, Labor Code, etc., refer to codes of the State of California. Contract -The written agreement between the Agency and the Contractor covering the Work. Contract Documents -Including but not limited to; the Contract, any Addendum (which pertain to the contract documents), Notice Inviting Bids, Instructions to Bidders; Bid (including documentation accompanying the Bid and any post-bid documentation submitted prior to the Notice of Award) when attached as an exhibit to the Contract, the Bonds, the General Provisions, permits from other agencies, the Technical Specifications, the Supplemental Provisions, the Plans, Standard Plans, Standard Spec- ifications, Reference Specifications, and all Modifications issued after the execution of the Contract. (.'\ •+;' Revised 6/15/17 Contract No. 4715 Page 43 of 107 Pages Contractor-The individual, partnership, corporation, joint venture, or other legal entity having a Con- tract with the Agency to perform the Work. In the case of work being done under permit issued by the Agency, the permittee shall be constructed to be the Contractor. The term "prime contractor" shall mean Contractor. Contract Price -The total amount of money for which the Contract is awarded. Contract Unit Price -The amount stated in the Bid for a single unit of an item of work. County Sealer -The Sealer of Weights and Measures of the county in which the Contract is let. Days -Days shall mean consecutive workday's days unless otherwise specified. Dispute Board -Persons designated by the City Manager of the City of Carlsbad, to hear and advise the City Manager on claims submitted by the Contractor. The City Manager for the City of Carlsbad is the last appeal level for informal dispute resolution. Engineer -The City Engineer of the City of Carlsbad or his/her approved representative. The Engi- neer is the fourth level of appeal for informal dispute resolution. Minor Bid Item -A single contract item constituting less than 10 percent (10%) of the original Contract Price bid. Modification -Includes Change Orders and Supplemental Agreements. A Modification may only be used after the effective date of the Contract. Municipal Projects Manager -The City's Construction Management Consultant's immediate super- visor and second level of appeal for informal dispute resolution. Notice of Award -The written notice by the Agency to the successful Bidder stating that upon com- pliance by it with the required conditions, the Agency will execute the Contract. Notice to Proceed -A written notice given by the Agency to the Contractor fixing the date on which the Contract time will start. Own Organization -When used in Section 2-3.1 -Employees of the Contractor who are hired, di- rected, supervised and paid by the Contractor to accomplish the completion of the Work. Further, such employees have their employment taxes, State disability insurance payments, State and Federal income taxes paid and administered, as applicable, by the Contractor. When used in Section 2-3.1 "own organization" means construction equipment that the Contractor owns or leases and uses to accomplish the Work. Equipment that is owner operated or leased equipment with an operator is not part of the Contractor's Own Organization and will not be included for the purpose of compliance with Section 2-3.1 . Person -Any individual, firm, association, partnership, corporation, trust, joint venture, or other legal entity. Private Contract-Work subject to Agency inspection, control, and approval, involving private funds, not administered by the Agency. Project -The term "Project" means the Work of the Contract for all exercised Phases and all other work, labor, equipment, and materials necessary to accomplish the Project. The Project may include construction by City of Carlsbad or by Separate Contractors. Proposal -See Bid. {' •f' Revised 6/15/17 Contract No. 471 5 Page 44 of 107 Pages Public Works Manager, Fleet & Facilities -The Municipal Projects Manager's immediate supervisor and third level of appeal for informal dispute resolution. Reference Specifications -Those bulletins, standards, rules, methods of analysis or test, codes, and specifications of other agencies, engineering societies, or industrial associations referred to in the Contract Documents. These refer to the latest edition, including amendments in effect and published at the time of advertising the project or issuing the permit, unless specifically referred to by edition, volume, or date. Roadway -The portion of a street reserved for vehicular use. Service Connection -Service connections are all or any portion of the conduit, cable, or duct, in- cluding meter, between a utility distribution line and an individual consumer. Sewer -Any conduit intended for the reception and transfer of sewage and fluid industrial waste. Specifications -General Provisions, Standard Specifications, Technical Specifications, Reference Specifications, Supplemental Provisions, and specifications in Supplemental Agreements between the Contractor and the Board. Standard -The shaft or pole used to support street lighting luminaire, traffic signal heads, mast arms, etc. Standard Plans -Details of standard structures, devices, or instructions referred to on the Plans or in Specifications by title or number. State -State of California. Storm Drain -Any conduit and appurtenances intended for the reception and transfer of storm water. Street -Any road, highway, parkway, freeway, alley, walk, or way. Subbase -A layer of specified material of planned thickness between a base and the subgrade. Subcontractor -An individual, firm, or corporation having a direct contract with the Contractor or with any other Subcontractor for the performance of a part of the Work. Subgrade -For roadways, that portion of the roadbed on w~ich pavement, surfacing, base, subbase, or a layer of other material is placed. For structures, the soil prepared to support a structure. Substantial Completion -The term "Substantial Completion" is defined in Section 9.7 of the General Pro- visions. Superintendent -The term "Superintendent" means the person designated by Contractor to repre- sent Contractor at the Project site in accordance with Article 3 of the General Provisions. Supervision -Supervision, where used to indicate supervision by the Engineer, shall mean the per- formance of obligations, and the exercise of rights, specifically imposed upon and granted to the Agency in becoming a party to the Contract. Except as specifically stated herein, supervision by the Agency shall not mean active and direct superintendence of details of the Work. Supplemental Agreement -A written amendment of the Contract Documents signed by both parties. ,, • .-, Revised 6/15/17 Contract No. 4715 Page 45 of 107 Pages Supplemental Provisions -Additions and revisions to the Standard Specifications setting forth con- ditions and requirements peculiar to the work. Surety -Any individual, firm, or corporation, bound with and for the Contractor for the acceptable performance, execution, and completion of the Work, and for the satisfaction of all obligations incurred. Utility -Tracks, overhead or underground wires, pipeline, conduits, ducts, or structures, sewers, or storm drains owned, operated, or maintained in or across a public right of way or private easement. Work -The term "Work" means the Pre-Construction Services, all Construction Work, all Work di- rected by City of Carlsbad pursuant to the Additional Improvements Allowance, and other require- ments of the Contract Documents as modified by Change Order, whether completed or partially com- pleted, and includes all labor, materials, equipment, tools, and services provided, or to be provided by, Contractor to fulfill Contractor's obligations without limitation. The Work may constitute the whole or a part of the Project. 1-3 ABBREVIATIONS 1-3.1 General. The abbreviation herein, together with others in general use, are applicable to these Standard Specifications and to project Plans or other Contract Documents. All abbreviations and symbols used on Plans for structural steel construction shall conform to those given by the "Manual of Steel Construction" published by the American Institute of Steel Construction, Inc. 1-3.2 Common Usage Abbreviation Word or Words ABAN ............................................................. Abandon CCTV ............................................... Closed Circuit TV ABAND ....................................................... Abandoned CES .......................... Carlsbad Engineering Standards ABS ........................ Acrylonitrile -butadiene -styrene CF ................................................................ Curb face AC .................................................... Asphalt Concrete CF ................................................................ Cubic foot ACP ........................................... Asbestos cement pipe C&G .................................................... Curb and gutter ACWS ..................... Asphalt concrete wearing surface CFR ................................ Code of Federal Regulations ALT ................................................................ Alternate CFS ......................................... Cubic Feet per Second APTS ................................. Apartment and Apartments CIP ......................................................... Cast iron pipe AMER STD ................................... American Standard GIPP ................................................ Cast-in place pipe AWG ............... American Wire Gage (nonferrous wire) CL ............................................. Clearance. center line BC .................................................. Beginning of curve CLF .................................................... Chain link fence BCR ....................................... Beginning of curb return CMB ............................... Crushed miscellaneous base BORY ............................................................ Boundary CMC ......................................... Cement mortar-coated BF ..................................................... Bottom of footing CML ............................................ Cement mortar-lined BLDG ........................................ Building and Buildings CMWD ......................... Carlsbad Municipal Water City BM .............................................................. Benchmark CO .................................................... Cleanout (Sewer) BVC .................................... Beginning of vertical curve COL .................................................................. Column B/W ........................................................... Back of wall COMM ....................................................... Commercial CIC ..................................................... Center to center CONC ........................................................... Concrete CAB ...................................... Crushed aggregate base CONN ........................................................ Connection CAUOSHA ............ California Occupational Safety and CONST .................................. Construct, Construction Health Administration COORD ...................................................... Coordinate CalTrans ....... California Department of Transportation CSP ............................................ Corrugated steel pipe CAP .................................... Corrugated aluminum pipe CSD ............................... Carlsbad Standard Drawings CB ............................................................. Catch Basin CTB ............................................ Cement treated base Cb ........................................................................ Curb CV ............................................................ Check valve CBP ............................... Catch Basin Connection Pipe CY ............................................................... Cubic yard CBR ....................................... California Bearing Ratio D .............................................................. Load of pipe CCR ............................ California Code of Regulations dB ................................................................... Decibels (' ti Revised 6/15/17 Contract No. 4715 Page 46 of 107 Pages DBL .................................................................. Double HGL. ............................................. Hydraulic grade line OF ............................................................... Douglas fir HORIZ .......................................................... Horizontal DIA ................................................................ Diameter HP ............................................................. Horsepower DIP ..................................................... Ductile iron pipe HPG ................................................ High pressure gas DL ................................................................ Dead load HPS ................................ High pressure sodium (Light) DR ...................................................... Dimension Ratio HYDR ............................................................ Hydraulic OT ................................................................. Drain Tile IE ......................................................... Invert Elevation DWG ............................................................... Drawing ID ........................................................ Inside diameter DWY .............................................................. Driveway INCL ............................................................... lncluding DWY APPR ................................... Driveway approach INSP ............................................................. lnspection E ....................................................................... Electric INV ...................................................................... lnvert EA ........................................................................ Each IP .................................................................... Iron pipe EC ............................................................ End of curve ECR ................................................ End of curb return EF ................................................................ Each face EG ......................................................... Edge of gutter EGL.. ................................................ Energy grade line El ................................................................... Elevation ELC ..................................... Electrolier lighting conduit EL T ........................................................ Extra long ton ENGR. ...................................... Engineer, Engineering EP ................................................... Edge of pavement ESMT ........................................................... Easement JC ..................................................... Junction chamber JCT ................................................................. Junction JS ..................................................... Junction structure JT ......................................................................... Joint L ........................................................................ Length LAB ............................................................. Laboratory LAT ................................................................... Lateral LB ...................................................................... Pound LO ..................................................... Local depression LF ................................................................ Linear foot LH ............................................................... Lamp hole LL ................................................................... Live load ETB .......................................... Emulsion-treated base EVC ............................................... End of vertical curb EWA ............................... Encina Wastewater Authority LOL ............................................................. Layout line LONG ........................................................ Longitudinal LP ................................................................ Lamp post EXC ............................................................ Excavation LPS ................................. Low pressure sodium (Light) EXP JT ................................................. Expansion joint LS ................................................................ Lump sum EXST ............................................................... Existing F .................................................................. Fahrenheit L TS .................................................... Lime treated soil LWD ................................... Leucadia Wastewater City F&C ................................................... Frame and cover MAINT ..................................................... Maintenance F&I .................................................. Furnish and install FAB ............................................................... Fabricate FAS ............................................... Flashing arrow sign FD ............................................................... Floor drain FON ............................................................ Foundation FED SPEC ................................. Federal Specification FG ........................................................ Finished grade FH ............................................................. Fire hydrant FL. .................................................................. Flow line FS ...................................................... Finished surface FT-LB ......................................................... Foot-pound MAX ............................................................. Maximum MCR ............................................ Middle of curb return MEAS ............................................................. Measure MH ................................... Manhole, maintenance hole MIL SPEC .................................... Military specification MISC ..................................................... Miscellaneous MOD ................................................... Modified, modify MON ............................................................ Monument MSL.. Mean Sea Level (Reg. Standard Drawing M-12) MTBM ......................... Microtunneling Boring Machine MUL T ............................................................... Multiple MUTCD ..... Manual on Uniform Traffic Control Devices FTG .................................................................. Footing FW ............................................................ Face of wall G ........................................................................... Gas MVL. .............................................. Mercury vapor light NCTD ................................... North County Transit City NRCP .............................. Non reinforced concrete pipe GA ..................................................................... Gauge OBS ............................................................... Obsolete GAL.. ............................................. Gallon and Gallons OC ................................................................ On center GAL V ......................................................... Galvanized OD ..................................................... Outside diameter GAR ........................................... Garage and Garages GIP .............................................. Galvanized iron pipe GL ........................................ Ground line or grade line GM .............................................................. Gas meter GNV ............................................... Ground Not Visible GP .................................................................. Guy pole GPM ................................................ gallons per minute GR ...................................................................... Grade GRTG ............................................................... Grating GSP ........................................... Galvanized steel pipe H ............................................................ High or height HB .................................................................. Hose bib HC ................................................... House connection OE .............................................................. Outer edge OHE ................................................ Overhead Electric OMWD ...................... Olivenhain Municipal Water City OPP ............................................................... Opposite ORIG ................................................................ Original PB ................................................................... Pull box PC .................................................... Point of curvature PCC ....................... Portland cement concrete or point of compound curvature PCVC ....................... Point of compound vertical curve PE ........................................................... Polyethylene Pl. ................................................. Point of intersection PL. ............................................................ Property line PMB ............................ Processed miscellaneous base HOWL ........................................................... Headwall POC ...................................................... Point on curve ,, •;, Revised 6/15/17 Contract No. 471 5 Page 47 of 107 Pages POT .................................................... Point on tangent SPEC ..................................................... Specifications PP .............................................................. Power pole SPPWC .......................................... Standard Plans for PRC .......................................... Point of reverse curve Public Works Construction PRVC ............................ Point of reverse vertical curve SSPWC ............................. Standard Specifications for PSI ......................................... Pounds per square inch PT .................................................... Point of tangency PVC .................................................. Polyvinyl chloride PVMT ........................................................... Pavement Public Works Construction ST HWY ................................................ State highway ST A ................................................................... Station STD ............................................................... Standard PVT RMI ....................................... Private right-of-way STR .................................................................. Straight Q ........................ Rate of flow in cubic feet per second QUAD ....................................... Quadrangle, Quadrant STR GR ................................................ Straight grade STRUC .......................................... Structural/Structure R ....................................................................... Radius SW ................................................................. Sidewalk R&O ......................................................... Rock and oil SWD ...................................................... Sidewalk drain RNV .......................................................... Right-of-way SY ............................................................ Square yard RA ...................................................... Recycling agent RAC ................................... Recycled asphalt concrete RAP ................................ Reclaimed asphalt pavement T .................................................................. Telephone TAN ................................................................. Tangent TC .............................................................. Top of curb RBAC ............................. Rubberized asphalt concrete TEL ............................................................. Telephone RC ................................................ Reinforced concrete TF ........................................................... Top of footing RCS ...................................... Reinforced concrete box TOPO ........................................................ Topography RCE ...................................... Registered civil engineer RCP ..................................... Reinforced concrete pipe TR ........................................................................ Tract TRANS ......................................................... Transition RCV ........................................... Remote control valve TS ......................... Traffic signal or transition structure REF ............................................................. Reference TSC ............................................. Traffic signal conduit REINF .............................. Reinforced or reinforcement TSS ........................................... Traffic signal standard RES ............................................................... Reservoir TW .............................................................. Top of wall RGE ........................ Registered geotechnical engineer TYP .................................................................. Typical ROW ....................................................... Right-of-Way UE .............................................. Underground Electric RR ................................................................... Railroad USA .................................... Underground Service Alert RSE .............................. Registered structural engineer VAR ..................................................... Varies, Variable RTE .................................... Registered traffic engineer VB ................................................................ Valve box S .................................... Sewer or Slope, as applicable VC .......................................................... Vertical curve SCCP ............................... Steel cylinder concrete pipe VCP ................................................... Vitrified clay pipe SD ............................................................. Storm drain VERT ............................................................... Vertical SDNR .............................. San Diego Northern Railway VOL .................................................................. Volume SOR ....... Standard thermoplastic pipe dimension ratio VWD ............................................ Vallecitos Water City (ratio of pipe O.D. to minimum wall thickness) W. ....................... Water, Wider or Width, as applicable SDRSD ......... San Diego Regional Standard Drawings WATCH .............. Work Area Traffic Control Handbook SE ...................................................... Sand Equivalent WI ............................................................ Wrought iron SEC .................................................................. Section VI/M ........................................................... Water meter SF ............................................................. Square foot WPJ .......................................... Weakened plane joint SFM ................................................ Sewer Force Main XCONN ............................................ Cross connection SI. ...................... International System of Units (Metric) XSEC ..................................................... Cross section 1-3.3 Institutions Abbreviation Word or Words AASHTO American Association of State Highway and Transportation Officials AISC .................................................................... American Institute of Steel Construction ANSI ...................................................................... American National Standards Institute API ...................................................................................... American Petroleum Institute AREA ............................................................ American Railway Engineering Association ASTM ............................................................ American Society for Testing and Materials AWPA. ................................................................ American Wood Preservers Association AWS ........................................................................................ American Welding Society A WWA. ...................................................................... American Water Works Association FHWA. ............................................................................. Federal Highway Administration GRI ................................................................................. Geosynthetic Research Institute ,., •ff Revised 6/15/17 Contract No. ~ Page 48 of 107 Pages NEMA. ........................................................ National Electrical Manufacturers Association NOAA ................ National Oceanic and Atmospheric Administration (Dept. of Commerce) UL .................................................................................... Underwriters' Laboratories Inc. USGS ............................................................................. United States Geological Survey 1-4 UNITS OF MEASURE. 1-4.1 General. U.S. Standard Measures, also called U.S. Customary System, are the principal measurement system in these specifications. However, certain material specifications and test re- quirements contained herein use SI units specifically and conversions to U.S. Standard Measures may or may not have been included in these circumstances. When U.S. Standard Measures are not included in parenthesis, then the SI units shall control. S.I. units and U.S. Standard Measures in parenthesis may or may not be exactly equivalent. Reference is also made to ASTM E 380 for definitions of various units of the SI system and a more extensive set of conversion factors. 1-4.2 Units of Measure and Their Abbreviations. Not Used. (' +; Revised 6/15/17 Contract No. 4748 Page 49 of 107 Pages SECTION 2 -SCOPE AND CONTROL OF WORK 2-1 AWARD AND EXECUTION OF CONTRACT. Award and execution of Contract will be as pro- vided for in the Specifications, Instruction to Bidders, or Notice Inviting Bids. 2-2 ASSIGNMENT. No Contract or portion thereof may be assigned without consent of the Board, except that the Contractor may assign money due or which will accrue to it under the Contract. If given written notice, such assignment will be recognized by the Board to the extent permitted by law. Any assignment of money shall be subject to all proper withholdings in favor of the Agency and to all deductions provided for in the Contract. All money withheld, whether assigned or not, shall be subject to being used by the Agency for completion of the Work, should the Contractor be in default. 2-3 SUBCONTRACTS. 2-3.1 General. Each Bidder shall comply with the Chapter of the Public Contract Code including Sections 4100 through 4113. The following excerpts or summaries of some of the requirements of this Chapter are included below for information: The Bidder shall set forth in the Bid, as provided in 4104: "(a) The name and location of the place of business of each subcontractor who will perform work or labor or render service to the prime contractor in or about the construc- tion of the work or improvements, or a subcontractor licensed by the State of California who, under subcontract to the prime contractor, specially fabricates and installs a por- tion of the work or improvement according to detailed drawings contained in the plans and specifications, in an amount in excess of one-half of 1 percent of the prime contrac- tor's total bid, or, in the case of bids or offers for the construction of streets or highways, including bridges, in excess of one-half of 1 percent of the prime contractor's total bid or ten thousand dollars ($10,000), whichever is greater." "(b) The portion of the work which will be done by each such subcontractor under this act. The prime contractor shall list only one subcontractor for each such portion as is defined by the prime contractor in his bid." If the Contractor fails to specify a Subcontractor, or specifies more than one Subcontractor for the same portion of the work to be performed under the Contract (in excess of one-half of 1 percent of the Contractor's total Bid), the Contractor shall be qualified to perform that portion itself, and shall perform that portion itself, except as otherwise provided in the Code. As provided in Section 4107, no Contractor whose Bid is accepted shall substitute any person as Subcontractor in place of the Subcontractor listed in the original Bid, except for causes and by proce- dures established in Section 4107 .5. This section provides procedures to correct a clerical error in the listing of a Subcontractor. Section 4110 provides that a Contractor violating any of the provisions of the Chapter violates the Contract and the Board may exercise the option either to cancel the Contract or assess the Contractor a penalty in an amount of not more than 10 percent of the subcontract involved, after a public hearing. Should the Contractor fail to adhere to the provisions requiring the Contractor to complete 25 percent of the contract price with its own organization, the Agency may at its sole discretion elect to cancel the contract or deduct an amount equal to 10 percent of the value of the work performed in excess of 75 {'\ • ., Revised 6/15/17 Contract No. 4748 Page 50 of 107 Pages percent of the contract price by other than the Contractor's own organization. The Board shall be the sole body for determination of a violation of these provisions. In any proceedings under this section, the prime contractor shall be entitled to a public hearing before the Board and shall be notified ten (10) days in advance of the time and location of said hearing. The determination of the City Council shall be final. 2-3.2 Additional Responsibility. The Contractor shall give personal attention to the fulfillment of the Contract and shall keep the Work under its control. The Contractor shall perform, with its own organization, Contract work amounting to at least 25 per- cent of the Contract Price except that any designated "Specialty Items" may be performed by subcon- tract, and the amount of any such "Specialty Items" so performed may be deducted from the Contract Price before computing the amount required to be performed by the Contractor with its own organiza- tion. "Specialty Items" will be identified by the Agency in the Bid or Proposal. Where an entire item is subcontracted, the value of work subcontracted will be based on the Contract Unit Price. When a portion of an item is subcontracted, the value of work subcontracted will be based on the estimated percentage of the Contract Unit Price. This will be determined from information submitted by the Con- tractor, and subject to approval by the Engineer. Before the work of any Subcontractor is started, the Contractor shall submit to the Engineer for ap- proval a written statement showing the work to be subcontracted giving the name and business of each Subcontractor and description and value of each portion of the work to be so subcontracted. 2-3.3 Status of Subcontractors. Subcontractors shall be considered employees of the Contractor, and the Contractor shall be responsible for their work. 2-4 CONTRACT BONDS. Before execution of the Contract, the Bidder shall file surety bonds with the Agency to be approved by the Board in the amounts and for the purposes noted below. Bonds issued by a surety, who is authorized to issue bonds in California, and whose bonding limitation shown in said circular is sufficient to provide bonds in the amount required by the Contract shall be deemed to be approved unless specifically rejected by the Agency. Bonds from all other sureties shall be ac- companied by all of the documents enumerated in Code of Civil Procedure 995.660 (a). The Bidder shall pay all bond premiums, costs, and incidentals. Each bond shall incorporate, by reference, the Contract and be signed by both the Bidder and Surety and the signature of the authorized agent of the Surety shall be notarized. The Contractor shall provide a faithful performance/warranty bond and payment bond (labor and ma- terials bond) for this contract. The faithful performance/warranty bond shall be in a sum not less than one hundred percent of the total amount payable by the terms of this contract. The Contractor shall provide bonds to secure payment of laborers and materials suppliers in a sum not less than one hun- dred percent of the total amount payable by the terms of this contract. Both bonds shall extend in full force and effect and be retained by the Agency during this project until they are released according to the provisions of this section. The faithful performance/warranty bond will be reduced to 25 percent of the original amount 30 days after recordation of the Notice of Completion and will remain in full force and effect for the one-year warranty period and until all warranty repairs are completed to the satisfaction of the Engineer. The bonds to secure payment of laborers and materials suppliers shall be released six months plus 30 days after recordation of the Notice of Completion if all claims have been paid. All bonds are to be placed with a surety insurance carrier admitted and authorized to transact the business of insurance in California and whose assets exceed their liabilities in an amount equal to or l' •+;' Revised 6/15/17 Contract No. 4748 Page 51 of 107 Pages in excess of the amount of the bond. The bonds are to contain the following documents: 1. An original, or a certified copy, of the un-revoked appointment, power of attorney, by laws, or an- other instrument entitling or authorizing the person who executed the bond to do so. 2. A certified copy of the certificate of authority of the insurer issued by the insurance commissioner. If the bid is accepted, the Agency may require a financial statement of the assets and liabilities of the insurer at the end of the quarter calendar year prior to 30 days next preceding the date of the execution of the bond. The financial statement shall be made by an officer's certificate as defined in Section 173 of the Corporations Code. In the case of a foreign insurer, the financial statement may be verified by the oath of the principal officer or manager residing within the United States. Should any bond become insufficient, the Contractor shall renew the bond within 10 days after receiv- ing notice from the Agency. Should any Surety at any time be unsatisfactory to the Board, notice will be given the Contractor to that effect. No further payments shall be deemed due or will be made under the contract until a new Surety shall qualify and be accepted by the Board. Changes in the Work or extensions of time, made pursuant to the Contract, shall in no way release the Contractor or Surety from its obligations. Notice of such changes or extensions shall be waived by the Surety. 2-5 PLANS AND SPECIFICATIONS 2-5.1 General. The plans and specifications for this project include the (1) Project Drawings, dated November 8, 2021 and titled Leo Carrillo Ranch Roof Repair and (2), the Contract Documents, Gen- eral Provisions and Technical Specifications for this project. The Plans, Specifications, and other Contract Documents shall govern the Work. The Contract Documents are intended to be complementary and cooperative. Anything specified in the Specifications and not shown on the Plans, or shown on the Plans and not specified in the Specifications shall be as though shown on or specified in both. The Plans shall be supplemented by such working drawings and shop drawings as are necessary to adequately control the Work. The Contractor shall ascertain the existence of any conditions affecting the cost of the Work through a reasonable examination of the Work site prior to submitting the Bid. Existing improvements visible at the Work site, for which no specific disposition is made on the Plans, but which interfere with the completion of the Work, shall be removed and disposed of by the Contractor. The Contractor shall, upon discovering any error or omission in the Plans or Specifications, immediately call it to the attention of the Engineer. 2-5.2 Precedence of Contract Documents. If there is a conflict between Contract Documents, the document highest in precedence shall control. The precedence shall be the most recent edition of the following documents listed in order of highest to lowest precedence: a) Permits from other agencies as may be required by law. b) Change orders, whichever occurs last. c) Contract addenda, whichever occurs last. d) Contract ,, •+;' Revised 6/15/17 Contract No. 4748 Page 52 of 107 Pages e) Carlsbad General Provisions and Technical Specifications f) Plans/drawings for this project. g) Standards plans. 1) City of Carlsbad Standard Drawings. 2) Carlsbad Municipal Water City Standard Drawings. 3) City of Carlsbad modifications to the San Diego Area Regional Standard Drawings. 4) San Diego Area Regional Standard Drawings. h) Standard Specifications for Public Works Construction, as amended. i) Reference Specifications. j) Manufacturer's Installation Recommendations Detail drawings shall take precedence over general drawings. Change Orders, Supplemental Agreements and approved revisions to Plans and Specifications will take precedence over items b) through f) above. Detailed plans and plan views shall have precedence over general plans. Organization of the Specifications into various subdivisions and the arrangement of the Drawings shall not control Contractor in dividing the Construction Work among Subcontractors or in establish- ing the extent of work to be performed by any trade. Unless otherwise stated in the Contract Documents, technical words and abbreviations contained in the Contract Documents are used in accordance with commonly understood construction industry meanings, and non-technical words and abbreviations are used in accordance with their commonly understood meanings. The Contract Documents may omit modifying words such as "all" and "any," and articles such as "the" and "an," but the fact that a modifier or an article is absent from one statement and appears in another is not intended to affect the interpretation of either statement. The use of the word "including," when following any general statement, shall not be construed to limit such statement to specific items or matters set forth immediately following such word or to similar items or matters, whether or not non-limiting language (such as "without limitation," "but not limited to," or words of similar import) is used with reference thereto, but rather shall be deemed to refer to all other items or matters that could reasonably fall within the broadest possible scope of such general statement. Whenever the context so requires, the use of the singular number shall be deemed to include the plural and vice versa. Each gender shall be deemed to include any other gender, and each shall include corporation, partnership, trust, or other legal entity whenever the context so requires. The captions and headings of the various subdivisions of the Contract Documents are intended only for reference and convenience and in no way define, limit, or prescribe the scope or intent of the Contract Documents or any subdivision thereof. 2-5.3 Submittals 2-5.3.1 General. Submittals shall be provided, at the Contractor's expense, as required in 2-5.3.2, 2- 5.3.3 and 2-5.3.4, when required by the Plans or General Provisions, or requested by the Engineer. Materials shall neither be furnished nor fabricated, nor shall any work for which submittals are required be performed, before the required submittals have been reviewed and accepted by the Engineer. Neither review nor acceptance of submittals by the Engineer shall relieve the Contractor from responsibility for errors, omissions, or deviations from the Contract Documents, unless such deviations were specifically called to the attention of the Engineer in the letter of transmittal. The Contractor shall be responsible for the correctness of the submittals. ,, •+' Revised 6/15/17 Contract No. ~ Page 53 of 107 Pages The Contractor shall allow a minimum of 20 working days for review of submittals unless otherwise specified in the General Provisions. Each submittal shall be accompanied by a letter of transmittal. Each submittal shall be consecutively numbered. Resubmittals shall be labeled with the number of the original submittal followed by an ascending alphabetical designation (e.g. The label '4-C' would indi- cate the third instance that the fourth submittal had been given to the Engineer). Each sheet of each submittal shall be consecutively numbered. Each set of shop drawings and submittals shall be ac- companied by a letter of transmittal on the Contractor's letterhead. The Letter of Transmittal shall contain the following: a) Project title and Agency contract number. b) Number of complete sets. c) Contractor's certification statement. d) Specification section number(s) pertaining to material submitted for review. e) Submittal number (Submittal numbers shall be consecutive including subsequent submittals for the same materials.) f) Description of the contents of the submittal. g) Identification of deviations from the contract documents. When submitted for the Engineer's review, Shop Drawings shall bear the Contractor's certification that the Contractor has reviewed, checked, and approved the Shop Drawings and that they are in con- formance with the requirements of the Contract Documents. The Contractor shall subscribe to and shall place the following certification on all submittals: "I hereby certify that the (equipment, material) shown and marked in this submittal is that proposed to be incorporated into this Project, is in compliance with the Contract Documents, can be installed in the allocated spaces, and is submitted for approval." By: Title: ____________ _ Date: ___________ _ Company Name: _____________________________ _ 2-5.3.2 Working Drawings. Working drawings are drawings showing details not shown on the Plans which are required to be designed by the Contractor. Working drawings shall be of a size and scale to clearly show all necessary details. Six copies and one reproducible shall be submitted. If no revisions are required, three of the copies will be returned to the Contractor. If revisions are required, the Engineer will return one copy along with the reproducible for resubmission. Upon acceptance, the Engineer will return two of the copies to the Contractor and retain the remaining copies and the reproducible. 2-5.3.3 Shop Drawings. Shop drawings are drawings showing details of manufactured or assembled products proposed to be incorporated into the Work. See section 6.-2.11 . 2-5.3.4 Supporting Information. Supporting information is information required by the Specification for the purposes of administration of the Contract, analysis for verification of conformance with the Specifications, the operation and maintenance of a manufactured product or system to be con- structed as part of the Work, and other information as may be required by the Engineer. Six copies of the supporting information shall be submitted to the Engineer prior to the start of the Work unless (' • ., Revised 6/15/17 Contract No. 4748 Page 54 of 107 Pages otherwise specified in the General Provisions or directed by the Engineer. Supporting information for systems shall be bound together and include all manufactured items for the system. If resubmittal is not required, three copies will be returned to the Contractor. Supporting information shall consist of the following and is required unless otherwise specified in the General Provisions: a) List of Subcontractors per 2-3 b) List of Materials c) Certifications d) Construction Schedule per 6-1 . e) Confined Space Entry Program per 7-10.4.4. f) Concrete mix designs g) Asphalt concrete mix designs h) Data, including, but not limited to, catalog sheets, manufacturer's brochures, technical bulle- tins, specifications, diagrams, product samples, and other information necessary to describe a system, product or item. This information is required for irrigation systems, street lighting sys- tems, and traffic signals, and may also be required for any product, manufactured item, or system. 2-5.3.5 Electronic Submittal Procedure -Not used 2-5.4 RECORD DRAWINGS. The Contractor shall provide and keep up-to-date a complete "as-built" record set of blue-line prints, which shall be corrected in red daily and show every change from the original drawings and specifications and the exact "as-built" locations, sizes and kinds of equipment, underground piping, valves, and all other work not visible at surface grade. Prints for this purpose may be obtained from the Agency at cost. This set of drawings shall be kept on the job and shall be used only as a record set and shall be delivered to the Engineer within ten (10) days of completion of the work. Payment for performing the work required by Section 2-5.4 shall be included in the various bid items and no additional payment will be made therefore. 2-6 WORK TO BE DONE. The Contractor shall perform all work necessary to complete the Contract in a satisfactory manner. Unless otherwise provided, the Contractor shall furnish all materials, equip- ment, tools, labor, and incidentals necessary to complete the Work. 2-7 SUBSURFACE DATA. Not used. 2-8 RIGHT-OF-WAY. Rights-of-way, easements, or rights-of-entry for the Work will be provided by the Agency. Unless otherwise provided, the Contractor shall make arrangements, pay for, and assume all responsibility for acquiring, using, and disposing of additional work areas and facilities temporarily required. The Contractor shall indemnify and hold the Agency harmless from all claims for damages caused by such actions. 2-9 SURVEYING. 2-9.1 Permanent Survey Markers. Not used. 2-9.2 Survey Service. Not used. 2-9.2.1 Submittal of Surveying Data. Not used. 2-9.2.2 Survey Requirements. Not used. ,., •+' Revised 6/15/17 Contract No. 4748 Page 55 of 107 Pages 2-10 AUTHORITY OF BOARD AND ENGINEER. The Board has the final authority in all matters affecting the Work. Within the scope of the Contract, the Engineer has the authority to enforce com- pliance with the Plans and Specifications. The Contractor shall promptly comply with instructions from the Engineer or an authorized representative. The decision of the Engineer is final and binding on all questions relating to: quantities; acceptability of material, equipment, or work; execution, progress or sequence of work; and interpretation of the Plans, Specifications, or other drawings. This shall be precedent to any payment under the Contract, unless otherwise ordered by the Board. 2-10.1 Availability of Records, The Contractor shall, at no charge to the Agency, provide copies of all records in the Contractor's or subcontractor's possession pertaining to the work that the Engineer may request. 2-10.2 Audit and Inspection, Contractor agrees to maintain and/or make available, to the Engineer, within San Diego County, accurate books and accounting records relative to all its activities and to contractually require all subcontractors to this Contract to do the same. The Engineer shall have the right to monitor, assess, and evaluate Contractor's and its subcontractors performance pursuant to this Agreement, said monitoring, assessments, and evaluations to include, but not be limited to, audits, inspection of premises, reports, contracts, subcontracts and interviews of Contractor's staff and the staff of all subcontractors to this contract. At any time during normal business hours and as often as the Engineer may deem necessary, upon reasonable advance notice, Contractor shall make available to the Engineer for examination, all of its, and all subcontractors to this contract, records with respect to all matters covered by this Contract and will permit the Engineer to audit, examine, copy and make excerpts or transcripts from such data and records, and to make audits of all invoices, materials, pay- rolls, records of personnel, and other data relating to all matters covered by this Contract. However, any such activities shall be carried out in a manner so as to not unreasonably interfere with Contrac- tor's ongoing business operations. Contractor and all subcontractors to this contract shall maintain such data and records for as long as may be required by applicable laws and regulations. 2-11 INSPECTION. The Work is subject to inspection and approval by the Engineer. The Contractor shall notify the Engineer before noon of the working day before inspection is required. Work shall be done only in the presence of the Engineer, unless otherwise authorized. Any work done without proper inspection will be subject to rejection. The Engineer and any authorized representatives shall at all times have access to the Work during its construction at shops and yards as well as the project site. The Contractor shall provide every reasonable facility for ascertaining that the materials and work- manship are in accordance with these specifications. Inspection of the Work shall not relieve the Con- tractor of the obligation to fulfill all conditions of the Contract. {'\ •+;' Revised 6/15/17 Contract No. 4748 Page 56 of 107 Pages SECTION 3 -CHANGES IN WORK 3-1 CHANGES REQUESTED BY THE CONTRACTOR. 3-1.1 General. Changes in the Plans and Specifications, requested in writing by the Contractor, which do not materially affect the Work and which are not detrimental to the Work or to the interests of the Agency, may be granted by the Engineer. Nothing herein shall be construed as granting a right to the Contractor to demand acceptance of such changes. 3-1.2 Payment for Changes Requested by the Contractor. If such changes are granted, they shall be made at a reduction in cost or no additional cost to the Agency. 3-2 CHANGES INITIATED BY THE AGENCY. 3-2.1 General. The Agency may change the Plans, Specifications, character of the work, or quantity of work provided the total arithmetic dollar value of all such changes, both additive and deductive, does not exceed 25 percent of the Contract Price. Should it become necessary to exceed this limita- tion, the change shall be by written Supplemental Agreement between the Contractor and Agency, unless both parties agree to proceed with the change by Change Order. Change Orders shall be in writing and state the dollar value of the change or established method of payment, any adjustment in contract time of completion, and when negotiated prices are involved, shall provide for the Contractor's signature indicating acceptance. 3-2.2 Payment. 3-2.2.1 Contract Unit Prices. If a change is ordered in an item of work covered by a Contract Unit Price, and such change does not involve substantial change in character of the work from that shown on the Plans or specified in the Specifications, then an adjustment in payment will be made. This adjustment will be based upon the increase or decrease in quantity and the Contract Unit Price. If the actual quantity of an item of work covered by a Contract Unit Price and constructed in conform- ance with the Plans and Specifications varies from the Bid quantity by 50 percent or less, payment will be made at the Contract Unit Price. If the actual quantity of said item of work varies from the Bid quantity by more than 50 percent, payment will be made per Section 3-2.2.2 or 3-2.2.3 as appropriate. If a change is ordered in an item of work covered by a Contract Unit Price, and such change does involve a substantial change in the character of the work from that shown on the Plans or specified in the Specifications, an adjustment in payment will be made per Section 3-2.4. 3-2.2.2 Increases of More Than 50 Percent. Should the actual quantity of an item of work covered by a Contract Unit Price and constructed in conformance with the Plans and Specifications, exceed the Bid quantity by more than 50 percent, payment for the quantity in excess of 150 percent of the Bid quantity will be made on the basis of an adjustment in the Contract Unit Price mutually agreed to by the Contractor and the Agency, or at the option of the Engineer, on the basis of Extra Work per Section 3-3. The Extra Work per Section 3-3, basis of payment, shall not include fixed costs. Fixed costs shall be deemed to have been recovered by the Contractor through payment for 150 percent of the Bid quantity at the Contract Unit Price. 3-2.2.3 Decreases of More Than 50 Percent. Should the actual quantity of an item of work covered by a Contract Unit Price, and constructed in conformance with the Plans and Specifications, be less l' • ., Revised 6/15/17 Contract No. 4748 Page 57 of 107 Pages than 50 percent of the Bid quantity, an adjustment in payment will not be made unless so requested in writing by the Contractor. If the Contractor so requests, payment will be made on the basis of an adjustment in the Contract Unit Price mutually agreed to by the Contractor and the Agency, or at the option of the Engineer, on the basis of Extra Work per Section 3-3; however, in no case will payment be less than would be made for the actual quantity at the Contract Unit Price nor more than would be made for 50 percent of the Bid quantity at the Contract Unit Price. 3-2.3 Stipulated Unit Prices. Not Used. 3-2.4 Agreed Prices. Agreed Prices are prices for new or unforeseen work, or adjustments in Contract Unit Prices per Section 3-2.2, established by mutual agreement between the Contractor and the Agency. If mutual agreement cannot be reached, the Engineer may direct the Contractor to proceed on the basis of Extra Work in accordance per Section 3-3, except as otherwise specified in Sections 3-2.2.2 and 3-2.2.3. 3.2.4.1 Schedule of Values. Prior to construction, Contractor shall provide a schedule of values for all lump sum bid items in the Contractor's Proposal. The Contractor's Proposal shall be used for the purpose of progress payments, though some line items may require further breakdown if requested by City's Construction Management Consultant. The proposal prices shall be valid for the purpose of change orders to the project. 3.2.5 Eliminated Items. Should any Bid item be eliminated in its entirety, payment will be made to the Contractor for its actual costs incurred in connection with the eliminated item prior to notification in writing from the Engineer so stating its elimination. If material conforming to the Plans and Specifica- tions is ordered by the Contractor for use in the eliminated item prior to the date of notification of elimination by the Engineer, and if the order for that material cannot be canceled, payment will be made to the Contractor for the actual cost of the material. In this case, the material shall become the property of the Agency. Payment will be made to the Contractor for its actual costs for any further handling. If the material is returnable, the material shall be returned and payment will be made to the Contractor for the actual cost of charges made by the supplier for returning the material and for han- dling by the Contractor. Actual costs, as used herein, shall be computed on the basis of Extra Work per Section 3-3. 3-3 EXTRA WORK. 3-3.1 General. New or unforeseen work will be classified as "extra work" when the Engineer deter- mines that it is not covered by Contract Unit Prices or stipulated unit prices. 3-3.2 Payment. 3-3.2.1 General. When the price for the extra work cannot be agreed upon, the Agency will pay for the extra work based on the accumulation of costs as provided herein. 3-3.2.2 Basis for Establishing Costs. a.) Labor. The costs of labor will be the actual cost for wages of workers performing the extra work at the time the extra work is done, plus employer payments of payroll taxes, workers compensation insurance, liability insurance, health and welfare, pension, vacation, apprentice- ship funds, and other direct costs, resulting from Federal, State, or local laws, as well as as- sessments or benefits required by lawful collective bargaining agreements. ("\ •~ Revised 6/15/17 Contract No. 4748 Page 58 of 107 Pages The use of a labor classification which would increase the extra work cost will not be permitted unless the Contractor establishes the necessity for such additional costs. Labor costs for equipment operators and helpers shall be reported only when such costs are not included in the invoice for equipment rental. The labor cost for foremen shall be proportioned to all of their assigned work and only that applicable to extra work will be paid. Non-direct labor costs, including superintendence, shall be considered part of the markup of Section 3-3.2.3 (a). b.) Materials. The cost of materials reported shall be at invoice or lowest current price at which such materials are locally available and delivered to the job site in the quantities involved, plus sales tax, freight, and delivery. The Agency reserves the right to approve materials and sources of supply, or to supply mate- rials to the Contractor if necessary, for the progress of the Work. No markup shall be applied to any material provided by the Agency. c.) Tool and Equipment Rental. No payment will be made for the use of tools which have a replacement value of $200 or less. Regardless of ownership, the rates and right-of-way delay factors to be used in determining rental and delay costs shall be the edition of the, "Labor Surcharge and Equipment Rental Rates" published by CAL TRANS, current at the time of the actual use of the tool or equipment. The right-of-way delay factors therein shall be used as multipliers of the rental rates for deter- mining the value of costs for delay to the Contractor and subcontractors, if any. The labor surcharge rates published therein are not a part of this contract. The rental rates paid shall include the cost offuel, oil, lubrication, supplies, small tools, neces- sary attachments, repairs and maintenance of any kind, depreciation, storage, insurance, and all incidentals. Necessary loading and transportation costs for equipment used on the extra work shall be included. If during the project contract time the work is stopped by an unforeseen reason, then the Con- tractor may be due compensation for idled equipment. The Contractor shall use idle time rates (delay factors) in the Caltrans's latest Labor Surcharge and Equipment Rental Rate Manual for pricing equipment that was idled due to the changed condition that caused the work stoppage of that same equipment. The specified idle time rate in the manual is to be multiplied by the Caltrans's equipment rate for that same piece of equipment to determine the product, which will be considered the allowable idle time dollar amount acceptable to the City. (Example: delay factor = .10, equipment hourly rate = $50, allowable idle time dollar amount = $5/hr). If equipment is used intermittently and, when not in use, could be returned to its rental source at less expense to the Agency than holding it at the Work site, it shall be returned, unless the Contractor elects to keep it at the Work site, at no expense to the Agency. All equipment shall be acceptable to the Engineer, in good working condition, and suitable for the purpose for which it is to be used. Manufacturer's ratings and approved modifications shall be used to classify equipment and it shall be powered by a unit of at least the minimum rating recommended by the manufacturer. The reported rental time for equipment already at the Work site shall be the duration of its use on the extra work. This time begins when equipment is first put into actual operation on the ,, •,r Revised 6/1 5/17 Contract No. 4748 Page 59 of 107 Pages extra work, plus the time required to move it from its previous site and back, or to a closer site. d.) Other Items. The Agency may authorize other items which may be required on the extra work, including labor, services, material, and equipment. These items must be different in their nature from those required for the Work and be of a type not ordinarily available from the Contractor or Subcontractors. Invoices covering all such items in detail shall be submitted with the request for payment. Ven- dors' invoices for material, equipment rental and other expenditures shall be submitted with the request for payment. If the request for payment is not substantiated by invoices or other documentation, the Agency may establish the cost of the item involved at the lowest price which was current at the time of the report. e.) Sales Tax. No markup will be allowed on sales and/or other taxes. 3-3.2.3 Markup. a) Work by Contractor. The following percentages shall be added to the Contractor's costs and shall constitute the markup for all overhead and profits: 1) Labor ........................................ 15 2) Materials............................. 15 3) Tools and Equipment Rental . . . 15 4) Other Items . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15 5) Sales and other taxes ............... 0 To the sum of the costs and markups provided for in this section, 1 percent shall be added as compensation for bonding. (b) Work by Subcontractor. When all or any part of the extra work is performed by a Subcon- tractor, the markup established in Section 3-3.2.3(a) shall be applied to the Subcontractor's actual cost of such work. A markup of 5 percent of the subcontracted portion of the extra work may be added by the Contractor. Contractor markup shall fully compensate Contractor for all General Conditions expenses, direct and indirect Overhead, and Profit. No additional charges will be made for project management, estimating, or supervision. 3-3.3 Daily Reports by Contractor. When the price for the extra work cannot be agreed upon, the Contractor shall submit a daily report to the Engineer on forms approved by the Agency. Included are applicable delivery tickets, listing all labor, materials, and equipment involved for that day, and other services and expenditures when authorized. Payment for extra work will not be made until such time that the Contractor submits completed daily reports and all supporting documents to the Engineer. Failure to submit the daily report by the close of the next working day may waive any rights for that day. An attempt shall be made to reconcile the report daily, and it shall be signed by the Engineer and the Contractor. In the event of disagreement, pertinent notes shall be entered by each party to explain points which cannot be resolved immediately. Each party shall retain a signed copy of the report. Reports by Subcontractors or others shall be submitted through the Contractor. The report shall: 1. Show names of workers, classifications, and hours worked. 2. Describe and list quantities of materials used. l'\ •f' Revised 6/15/17 Contract No. 4748 Page 60 of 107 Pages 3. Show type of equipment, size, identification number, and hours of operation, including loading and transportation, if applicable. 4. Describe other services and expenditures in such detail as the Agency may require. 3-4 CHANGED CONDITIONS. The Contractor shall promptly notify the Engineer of the following Work site conditions (hereinafter called changed conditions), in writing, upon their discovery and be- fore they are disturbed: 1. Subsurface or latent physical conditions differing materially from those represented in the Con- tract; 2. Unknown physical conditions of an unusual nature differing materially from those ordinarily encountered and generally recognized as inherent in work of the character being performed; and 3. Material differing from that represented in the Contract which the Contractor believes may be hazardous waste, as defined in Section 25117 of the Health and Safety Code, that is required to be removed to a Class I, Class II, or Class Ill disposal site in accordance with provisions of existing law. Regarding suspect hazardous waste, see section 6.2.18 The Engineer will promptly investigate conditions which appear to be changed conditions. If the Engi- neer determines that conditions are changed conditions and they will materially affect performance time, the Contractor, upon submitting a written request, will be granted an extension of time subject to the provisions of 6-6. If the Engineer determines that the conditions do not justify an adjustment in compensation, the Con- tractor will be notified in writing. This notice will also advise the Contractor of its obligation to notify the Engineer in writing if the Contractor disagrees. · The Contractor's failure to give notice of changed conditions promptly upon their discovery and before they are disturbed shall constitute a waiver of all claims in connection therewith. The Contractor shall not be entitled to the payment of any additional compensation for any act, or failure to act, by the Engineer, including failure or refusal to issue a change order, or for the happening of any event, thing, occurrence, or other cause, unless the Contractor shall have first given the Engi- neer due written notice of potential claim as hereinafter specified. Compliance with this section shall not be required as a prerequisite to notice provisions in Section 6-7.3 Contract Time Accounting, nor to any claim that is based on differences in measurement or errors of computation as to contract quantities. The written notice of potential claim for changed conditions shall be submitted by the Con- tractor to the Engineer upon their discovery and prior to the time that the Contractor performs the work giving rise to the potential claim. The Contractor's failure to give written notice of potential claim for changed conditions to the agency upon their discovery and before they are disturbed shall constitute a waiver of all claims in connection therewith. The Contractor shall provide the City with a written document containing a description of the particular circumstances giving rise to the potential claim, the reasons for which the Contractor believes addi- tional compensation may be due and nature of any and all costs involved within 20 working days of the date of service of the written notice of potential claim for changed conditions. Verbal notifications are disallowed The potential claim shall include the following certification relative to the California False Claims Act, Government Code Sections 12650-12655. ,, • ., Revised 6/15/17 Contract No. 4748 Page 61 of 107 Pages "The undersigned certifies that the above statements are made in full cognizance of the California False Claims Act, Government Code Sections 12650-12655. The undersigned further understands and agrees that this potential claim, unless resolved, must be restated as a claim in response to the City's proposed final estimate in order for it to be further considered." By: -------------Title: -------------- Date: ____________________________ _ Company Name: _____________________________ _ The Contractor's estimate of costs may be updated when actual costs are known. The Contractor shall submit substantiation of its actual costs to the Engineer within 20 working days after the affected work is completed. Failure to do so shall be sufficient cause for denial of any claim subsequently filed on the basis of said notice of potential claim. It is the intention of this section that differences between the parties arising under and by virtue of the contract be brought to the attention of the Engineer at the earliest possible time in order that such matters be settled, if possible, or other appropriate action promptly taken. 3-5 DISPUTED WORK. The Contractor shall give the agency written notice of potential claim prior to commencing any disputed work. Failure to give said notice shall constitute a waiver of all claims in connection therewith. If the contractor and the agency are unable to reach agreement on disputed work, the Agency may direct the contractor to proceed with the work. Prior to proceeding with dispute resolution pursuant to Public Contract Code provisions specified here- inafter, the contractor shall attempt to resolve all disputes informally through the following dispute resolution chain of command: 1 . City's Construction Management Consultant 2. City Municipal Projects Manager 3. Public Works Manager, Fleet & Facilities 4. City Engineer 5. City Manager The Contractor shall submit a complete report within 20 working days after completion of the disputed work stating its position on the claim, the contractual basis for the claim, along with all documentation supporting the costs and all other evidentiary materials. At each level of claim or appeal of claim the City will, within 1 0 working days of receipt of said claim or appeal of claim, review the Contractor's report and respond with a position, request additional information or request that the Contractor meet and present its report. When additional information or a meeting is requested the City will provide its position within 10 working days of receipt of said additional information or Contractor's presentation of its report. The Contractor may appeal each level's position up to the City Manager after which the Contractor may proceed under the provisions of the Public Contract Code. The authority within the dispute resolution chain of command is limited to recommending a resolution to a claim to the City Manager. Actual approval of the claim is subject to the change order provisions in the contract. All claims by the Contractor shall be resolved in accordance with Public Contract Code section 9204, which is set forth below: ,, • .,-., Revised 6/15/17 Contract No. 4748 Page 62 of 107 Pages 9204. (a) The Legislature finds and declares that it is in the best interests of the state and its citizens to ensure that all construction business performed on a public works project in the state that is com- plete and not in dispute is paid in full and in a timely manner. (b) Notwithstanding any other law, including, but not limited to, Article 7.1 (commencing with Section 10240) of Chapter 1 of Part 2, Chapter 10 ( commencing with Section 19100) of Part 2, and Article 1.5 (commencing with Section 20104) of Chapter 1 of Part 3, this section shall apply to any claim by a contractor in connection with a public works project. (c) For purposes of this section: (1) "Claim" means a separate demand by a contractor sent by registered mail or certified mail with return receipt requested, for one or more of the following : (A) A time extension, including, without limitation, for relief from damages or penalties for delay as- sessed by a public entity under a contract for a public works project. (B) Payment by the public entity of money or damages arising from work done by, or on behalf of, the contractor pursuant to the contract for a public works project and payment for which is not otherwise expressly provided or to which the claimant is not otherwise entitled. (C) Payment of an amount that is disputed by the public entity. (2) "Contractor" means any type of contractor within the meaning of Chapter 9 (commencing with Section 7000) of Division 3 of the Business and Professions Code who has entered into a direct con- tract with a public entity for a public works project. (3) (A) "Public entity" means, without limitation, except as provided in subparagraph (B), a state agency, department, office, division, bureau, board, or commission, the California State University, the University of California, a city, including a charter city, county, including a charter county, city and county, including a charter city and county, City, special City, public authority, political subdivision, public corporation, or nonprofit transit corporation wholly owned by a public agency and formed to carry out the purposes of the public agency. (B) "Public entity" shall not include the following: (i) The Department of Water Resources as to any project under the jurisdiction of that department. (ii) The Department of Transportation as to any project under the jurisdiction of that department. (iii) The Department of Parks & Recreation as to any project under the jurisdiction of that department. (iv) The Department of Corrections and Rehabilitation with respect to any project under its jurisdiction pursuant to Chapter 11 (commencing with Section 7000) of Title 7 of Part 3 of the Penal Code. (v) The Military Department as to any project under the jurisdiction of that department. (vi) The Department of General Services as to all other projects. (vii) The High-Speed Rail Authority. (4) "Public works project" means the erection, construction, alteration, repair, or improvement of any public structure, building, road, or other public improvement of any kind . (5) "Subcontractor'' means any type of contractor within the meaning of Chapter 9 (commencing with Section 7000) of Division 3 of the Business and Professions Code who either is in direct contract with a contractor or is a lower tier subcontractor. (d) (1) (A) Upon receipt of a claim pursuant to this section, the public entity to which the claim applies shall conduct a reasonable review of the claim and, within a period not to exceed 45 days, shall provide the claimant a written statement identifying what portion of the claim is disputed and what portion is undisputed. Upon receipt of a claim, a public entity and a contractor may, by mutual agreement, extend the time period provided in this subdivision. (B) The claimant shall furnish reasonable documentation to support the claim. (C) If the public entity needs approval from its governing body to provide the claimant a written state- ment identifying the disputed portion and the undisputed portion of the claim, and the governing body does not meet within the 45 days or within the mutually agreed to extension of time following receipt of a claim sent by registered mail or certified mail, return receipt requested, the public entity shall have (' •+i' Revised 6/15/17 Contract No. 4748 Page 63 of 107 Pages up to three days following the next duly publicly noticed meeting of the governing body after the 45- day period, or extension, expires to provide the claimant a written statement identifying the disputed portion and the undisputed portion. (D) Any payment due on an undisputed portion of the claim shall be processed and made within 60 days after the public entity issues its written statement. If the public entity fails to issue a written state- ment, paragraph (3) shall apply. (2) (A) If the claimant disputes the public entity's written response, or if the public entity fails to respond to a claim issued pursuant to this section within the time prescribed, the claimant may demand in writing an informal conference to meet and confer for settlement of the issues in dispute. Upon receipt of a demand in writing sent by registered mail or certified mail, return receipt requested, the public entity shall schedule a meet and confer conference within 30 days for settlement of the dispute. (B) Within 1 0 business days following the conclusion of the meet and confer conference, if the claim or any portion of the claim remains in dispute, the public entity shall provide the claimant a written statement identifying the portion of the claim that remains in dispute and the portion that is undisputed. Any payment due on an undisputed portion of the claim shall be processed and made within 60 days after the public entity issues its written statement. Any disputed portion of the claim, as identified by the contractor in writing, shall be submitted to nonbinding mediation, with the public entity and the claimant sharing the associated costs equally. The public entity and claimant shall mutually agree to a mediator within 10 business days after the disputed portion of the claim has been identified in writing. If the parties cannot agree upon a mediator, each party shall select a mediator and those mediators shall select a qualified neutral third party to mediate with regard to the disputed portion of the claim . Each party shall bear the fees and costs charged by its respective mediator in connection with the selection of the neutral mediator. If mediation is unsuccessful, the parts of the claim remaining in dispute shall be subject to applicable procedures outside this section. (C) For purposes of this section, mediation includes any nonbinding process, including, but not limited to, neutral evaluation or a dispute review board, in which an independent third party or board assists the parties in dispute resolution through negotiation or by issuance of an evaluation. Any mediation utilized shall conform to the timeframes in this section. (D) Unless otherwise agreed to by the public entity and the contractor in writing, the mediation con- ducted pursuant to this section shall excuse any further obligation under Section 20104.4 to mediate after litigation has been commenced. (E) This section does not preclude a public entity from requiring arbitration of disputes under private arbitration or the Public Works Contract Arbitration Program, if mediation under this section does not resolve the parties' dispute. (3) Failure by the public entity to respond to a claim from a contractor within the time periods described in this subdivision or to otherwise meet the time requirements of this section shall result in the claim being deemed rejected in its entirety. A claim that is denied by reason of the public entity's failure to have responded to a claim, or its failure to otherwise meet the time requirements of this section, shall not constitute an adverse finding with regard to the merits of the claim or the responsibility or qualifi- cations of the claimant. (4) Amounts not paid in a timely manner as required by this section shall bear interest at 7 percent per annum. (5) If a subcontractor or a lower tier subcontractor lacks legal standing to assert a claim against a public entity because privity of contract does not exist, the contractor may present to the public entity a claim on behalf of a subcontractor or lower tier subcontractor. A subcontractor may request in writing, either on his or her own behalf or on behalf of a lower tier subcontractor, that the contractor present a claim for work which was performed by the subcontractor or by a lower tier subcontractor on behalf of the subcontractor. The subcontractor requesting that the claim be presented to the public entity shall furnish reasonable documentation to support the claim. Within 45 days of receipt of this written re- quest, the contractor shall notify the subcontractor in writing as to whether the contractor presented the claim to the public entity and, if the original contractor did not present the claim , provide the sub- contractor with a statement of the reasons for not having done so. ,, •+;' Revised 6/15/17 Contract No. 4748 Page 64 of 107 Pages (e) The text of this section or a summary of it shall be set forth in the plans or specifications for any public works project that may give rise to a claim under this section. (f) A waiver of the rights granted by this section is void and contrary to public policy, provided, however, that (1) upon receipt of a claim, the parties may mutually agree to waive, in writing, mediation and proceed directly to the commencement of a civil action or binding arbitration, as applicable; and (2) a public entity may prescribe reasonable change order, claim, and dispute resolution procedures and requirements in addition to the provisions of this section, so long as the contractual provisions do not conflict with or otherwise impair the timeframes and procedures set forth in this section. (g) This section applies to contracts entered into on or after January 1, 2017. (h) Nothing in this section shall impose liability upon a public entity that makes loans or grants avail able through a competitive application process, for the failure of an awardee to meet its contractual obligations. (i) This section shall remain in effect only until January 1, 2020, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2020, deletes or extends that date. In addition, all claims by Contractor for $375,000 or less shall be resolved in accordance with the procedures in the Public Contract Code, Division 2, Part 3, Chapter 1, Article 1.5 (commencing with Section 20104) which is set forth below ARTICLE 1.5 RESOLUTION OF CONSTRUCTION CLAIMS 20104. (a)(1) This article applies to all public works claims of three hundred seventy-five thousand dollars ($375,000) or less which arise between a contractor and a local agency. (2) This article shall not apply to any claims resulting from a contract between a contractor and a public agency when the public agency has elected to resolve any disputes pursuant to Article 7.1 (commenc- ing with Section 10240) of Chapter 1 of Part 2. (b)(1) "Public work" has the same meaning as in Sections 3100 and 3106 of the Civil Code, except that "public work" does not include any work or improvement contracted for by the state or the Regents of the University of California. (2) "Claim" means a separate demand by the contractor for (A) a time extension, (8) payment of money or damages arising from work done by, or on behalf of, the contractor pursuant to the contract for a public work and payment of which is not otherwise expressly provided for or the claimant is not otherwise entitled to, or (C) an amount the payment of which is disputed by the local agency. (c) The provisions of this article or a summary thereof shall be set forth in the plans or specifications for any work which may give rise to a claim under this article. (d) This article applies only to contracts entered into on or after January 1, 1991 . 20104.2. For any claim subject to this article, the following requirements apply: (a) The claim shall be in writing and include the documents necessary to substantiate the claim. Claims must be filed on or before the date of final payment. Nothing in this subdivision is intended to extend the time limit or supersede notice requirements otherwise provided by contract for the filing of claims. (b)(1) For claims of less than fifty thousand dollars ($50,000), the local agency shall respond in writing to any written claim within 45 days of receipt of the claim, or may request, in writing, within 30 days of receipt of the claim, any additional documentation supporting the claim or relating to defenses to the claim the local agency may have against the claimant. (2) If additional information is thereafter required, it shall be requested and provided pursuant to this subdivision, upon mutual agreement of the local agency and the claimant. (3) The local agency's written response to the claim, as further documented, shall be submitted to the l' • ., Revised 6/15/17 Contract No. 4748 Page 65 of 107 Pages claimant within 15 days after receipt of the further documentation or within a period of time no greater than that taken by the claimant in producing the additional information, whichever is greater. (c)(1) For claims of over fifty thousand dollars ($50,000) and less than or equal to three hundred seventy-five thousand dollars ($375,000), the local agency shall respond in writing to all written claims within 60 days of receipt of the claim, or may request, in writing, within 30 days of receipt of the claim, any additional documentation supporting the claim or relating to defenses to the claim the local agency may have against the claimant. (2) If additional information is thereafter required, it shall be requested and provided pursuant to this subdivision, upon mutual agreement of the local agency and the claimant. (3) The local agency's written response to the claim, as further documented, shall be submitted to the claimant within 30 days after receipt of the further documentation, or within a period of time no greater than that taken by the claimant in producing the additional information or requested documentation, whichever is greater. (d) If the claimant disputes the local agency's written response, or the local agency fails to respond within the time prescribed, the claimant may so notify the local agency, in writing, either within 15 days of receipt of the local agency's response or within 1 ~ days of the local agency's failure to respond within the time prescribed, respectively, and demand an informal conference to meet and confer for settlement of the issues in dispute. Upon a demand, the local agency shall schedule a meet and confer conference within 30 days for settlement of the dispute. (e) Following the meet and confer conference, if the claim or any portion remains in dispute, the claim- ant may file a claim as provided in Chapter 1 (commencing with Section 900) and Chapter 2 (com- mencing with Section 910) of Part 3 of Division 3.6 of Title 1 of the Government Code. For purposes of those provisions, the running of the period of time within which a claim must be filed shall be tolled from the time the claimant submits his or her written claim pursuant to subdivision (a) until the time that claim is denied as a result of the meet and confer process, including any period of time utilized by the meet and confer process. (f) This article does not apply to tort claims and nothing in this article is intended nor shall be construed to change the time periods for filing tort claims or actions specified by Chapter 1 (commencing with Section 900) and Chapter 2 (commencing with Section 910) of Part 3 of Division 3.6 of Title 1 of the Government Code. 20104.4. The following procedures are established for all civil actions filed to resolve claims subject to this article: (a) Within 60 days, but no earlier than 30 days, following the filing or responsive pleadings, the court shall submit the matter to non-binding mediation unless waived by mutual stipulation of both parties. The mediation process shall provide for the selection within 15 days by both parties of a disinterested third person as mediator, shall be commenced within 30 days of the submittal, and shall be concluded within 15 days from the commencement of the mediation unless a time requirement is extended upon a good cause showing to the court or by stipulation of both parties. If the parties fail to select a mediator within the 15-day period, any party may petition the court to appoint the mediator. (b)(1) If the matter remains in dispute, the case shall be submitted to judicial arbitration pursuant to Chapter 2.5 (commencing with Section 1141 .10) of Title 3 of Part 3 of the Code of Civil Procedure, notwithstanding Section 1141 .11 of that code. The Civil Discovery Act of 1986 (Article 3 (commencing with Section 2016) of Chapter 3 of Title 3 of Part 4 of the Code of Civil procedure) shall apply to any proceeding brought under the subdivision consistent with the rules pertaining to judicial arbitration. (2) Notwithstanding any other provision of law, upon stipulation of the parties, arbitrators appointed for purposes of this article shall be experienced in construction law, and, upon stipulation of the parties, mediators and arbitrators shall be paid necessary and reasonable hourly rates of pay not to exceed their customary rate, and such fees and expenses shall be paid equally by the parties, except in the case of arbitration where the arbitrator, for good cause, determines a different division. In no event shall these fees or expenses be paid by state or county funds. (3) In addition to Chapter 2.5 (commencing with Section 1141.10) Title 3 of Part 3 of the Code of Civil ('\ •+;' Revised 6/15/17 Contract No. 4748 Page 66 of 107 Pages Procedure, any party who after receiving an arbitration award requests a trial de novo but does not obtain a more favorable judgment shall, in addition to payment of costs and fees under that chapter, pay the attorney's fees of the other party arising out of the trial de novo. (c) The court may, upon request by any party, order any witnesses to participate in the mediation or arbitration process. 20104.6. (a) No local agency shall fail to pay money as to any portion of a claim which is undisputed except as otherwise provided in the contract. (b) In any suit filed under Section 20104.4, the local agency shall pay interest at the legal rate on any arbitration award or judgment. The interest shall begin to accrue on the date the suit is filed in a court of law. Although not to be construed as proceeding under extra work provisions, the Contractor shall keep and furnish records of disputed work in accordance with Section 3-3. {"\ •+r Revised 6/15/17 Contract No. 4748 Page 67 of 107 Pages SECTION 4 -CONTROL OF MATERIALS 4-1 MATERIALS AND WORKMANSHIP 4-1.1 . General. All materials, parts, and equipment furnished by the Contractor in the Work shall be new, high grade, and free from defects. Quality of work shall be in accordance with the generally accepted standards. Material and work quality shall be subject to the Engineer's approval. Materials and work quality not conforming to the requirements of the Specifications shall be consid- ered defective and will be subject to rejection. Defective work or material, whether in place or not, shall be removed immediately from the site by the Contractor, at its expense, when so directed by the Engineer. If the Contractor fails to replace any defective or damaged work or material after reasonable notice, the Engineer may cause such work or materials to be replaced. The replacement expense will be deducted from the amount to be paid to the Contractor. Used or secondhand materials, parts, and equipment may be used only if permitted by the Specifications. 4-1.2 Protection of Work and Materials. The Contractor shall provide and maintain storage facili- ties and employ such measures as will preserve the specified quality and fitness of materials to be used in the Work. Stored materials shall be reasonably accessible for inspection. The Contractor shall also adequately protect new and existing work and all items of equipment for duration of Contract. The Contractor shall not, without the Agency's consent, assign, sell, mortgage, hypothecate, or re- move equipment or materials which have been installed or delivered and which may be necessary for the completion of the Contract. 4-1.3 Inspection Requirements 4-1.3.1 General. Unless otherwise specified, inspection is required at the source for such typical ma- terials and fabricated items as bituminous paving mixtures, structural concrete, metal fabrication, metal casting, welding, concrete pipe manufacture, protective coating application, and similar shop or plant operations. Steel pipe in sizes less than 18 inches and vitrified clay and cast-iron pipe in all sizes are acceptable upon certification as to compliance with the Specifications, subject to sampling and testing by the Agency. Standard items of equipment such as electric motors, conveyors, elevators, plumbing fixtures, etc., are subject to inspection at the job site only. Special items of equipment such as designed elec- trical panel boards, large pumps, sewage plant equipment, etc., are subject to inspection at the source, normally only for performance testing. The Specifications may require inspection at the source for other items not typical of those listed in this section. The Contractor shall provide the Engineer free and safe access to any and all parts of work at any time. Such free and safe access shall include means of safe access and egress, ventilation, lighting, shoring, dewatering and all elements pertaining to the safety of persons as contained in the State of California, California Code of Regulations, Title 8, Industrial Relations, Chapter 4, Division of Industrial Safety, Subchapter 4, Construction Safety Orders and such other safety regulations as may apply. Contractor shall furnish Engineer with such information as may be necessary to keep the Engineer fully informed regarding progress and manner of work and character of materials. Inspection or testing of the whole or any portion of the work or materials incorporated in the work shall not relieve Contractor from any obligation to fulfill this Contract. ,, •+i' Revised 6/15/17 Contract No. 4748 Page 68 of 107 Pages 4-1.3.2 Inspection of Materials Not Locally Produced. When the Contractor intends to purchase materials, fabricated products, or equipment from sources located more than 50 miles outside the geographical limits of the Agency, an inspector or accredited testing laboratory (approved by the En- gineer), shall be engaged by the Contractor at its expense, to inspect the materials, equipment or process. This approval shall be obtained before producing any material or equipment. The inspector or representative of the testing laboratory shall judge the materials by the requirements of the Plans and Specifications. The Contractor shall forward reports required by the Engineer. No material or equipment shall be shipped nor shall any processing, fabrication or treatment of such materials be done without proper inspection by the approved agent. Approval by said agent shall not relieve the Contractor of responsibility for complying with the Contract requirements. 4-1 .3.3 Inspection by the Agency. The Agency will provide all inspection and testing laboratory ser- vices within 50 miles of the geographical limits of the Agency. For private contracts, all costs of in- spection at the source, including salaries and mileage costs, shall be paid by the permittee. 4-1.4 Test of Material. Before incorporation in the Work, the Contractor shall submit samples of materials, as the Engineer may require, at no cost to the Agency. The Contractor, at its expense, shall deliver the materials for testing to the place and at the time designated by the Engineer. Unless oth- erwise provided, all initial testing will be performed under the direction of the Engineer, and at no expense to the Contractor. If the Contractor is to provide and pay for testing, it will be stated in the Specifications. For private contracts, the testing expense shall be borne by the permittee. The Contractor shall notify the Engineer in writing, at least 15 days in advance, of its intention to use materials for which tests are specified, to allow sufficient time to perform the tests. The notice shall name the proposed supplier and source of material. If the notice of intent to use is sent before the materials are available for testing or inspection, or is sent so far in advance that the materials on hand at the time will not last but will be replaced by a new lot prior to use on the Work, it will be the Contractor's responsibility to renotify the Engineer when samples which are representative may be obtained. Except as specified in these Provisions, the Agency will bear the cost of testing of locally produced materials and/or on-site workmanship where the results of such tests meet or exceed the requirements indicated in the Standard Specifications, Technical Specification, and any Supplemental Provisions. The cost of all other tests shall be borne by the Contractor. At the option of the Engineer, the source of supply of each of the materials shall be approved by the Engineer before the delivery is started. All materials proposed for use may be inspected or tested at any time during their preparation and use. If, after incorporating such materials into the Work, it is found that sources of supply that have been approved do not furnish a uniform product, or if the prod- uct from any source proves unacceptable at any time, the Contractor shall furnish approved material from other approved sources. If any product proves unacceptable after improper storage, handling or for any other reason it shall be rejected, not incorporated into the work and shall be removed from the project site all at the Contractor's expense. Compaction tests may be made by the Engineer and all costs for tests that meet or exceed the requirements of the specifications shall be borne by the Agency. Said tests may be made at any place along the work as deemed necessary by the Engineer. The costs of any retests made necessary by noncompliance with the specifications shall be borne by the Contractor. 4-1.5 Certification. The Engineer may waive materials testing requirements of the Specifications and accept the manufacturer's written certification that the materials to be supplied meet those ,, • ., Revised 6/15/17 Contract No. 4748 Page 69 of 107 Pages requirements. Material test data may be required as part of the certification. 4-1.6 Trade Names or Equals. The Contractor may supply any of the materials specified or offer an equivalent. The Engineer shall determine whether the material offered is equivalent to that speci- fied. Adequate time shall be allowed for the Engineer to make this determination. Whenever any particular material, process, or equipment is indicated by patent, proprietary or brand name, or by name of manufacturer, such wording is used for the purpose of facilitating its description and shall be deemed to be followed by the words or equal . A listing of materials is not intended to be comprehensive, or in order of preference. The Contractor may offer any material, process, or equip- ment considered to be equivalent to that indicated. The substantiation of offers shall be submitted as provided in the contract documents. The Contractor shall, at its expense, furnish data concerning items offered by it as equivalent to those specified. The Contractor shall have the material tested as required by the Engineer to determine that the quality, strength, physical, chemical, or other characteristics, including durability, finish, efficiency, dimensions, service, and suitability are such that the item will fulfill its intended function. Test methods shall be subject to the approval of the Engineer. Test results shall be reported promptly to the Engineer, who will evaluate the results and determine if the substitute item is equivalent. The Engineer's findings shall be final. Installation and use of a substitute item shall not be made until approved by the Engineer. If a substitute offered by the Contractor is not found to be equal to the specified material, the Contractor shall furnish and install the specified material. The specified Contract completion time shall not be affected by any circumstance developing from the provisions of this section. The Contractor is responsible for the satisfactory performance of substituted items. If, in the sole opin- ion of the Engineer, the substitution is determined to be unsatisfactory in performance, appearance, durability, compatibility with associated items, availability of repair parts and suitability of application the Contractor shall remove the substituted item and replace it with the originally specified item at no cost to the Agency. 4-1.7 Weighing and Metering Equipment. All scales and metering equipment used for proportioning materials shall be inspected for accuracy and certified within the past 12 months by the State of California Bureau of Weights and Measures, by the County Director or Sealer of Weights and Measures, or by a scale mechanic registered with or licensed by the County. The accuracy of the work of a scale service agency, except as stated herein, shall meet the standards of the California Business and Professions Code and the California Code of Regulations pertaining to weighing devices. A certificate of compliance shall be presented, prior to operation, to the Engineer for approval and shall be renewed whenever required by the Engineer at no cost to the Agency. All scales shall be arranged so they may be read easily from the operator's platform or area. They shall indicate the true net weight without the application of any factor. The figures of the scales shall be clearly legible. Scales shall be accurate to within 1 percent when tested with the plant shut down. Weighing equipment shall be so insulated against vibration or moving of other operating equipment in the plant area that the error in weighing with the entire plant running will not exceed 2 percent for any setting nor 1.5 percent for any batch. ,, • ., Revised 6/15/17 Contract No. 4748 Page 70 of 107 Pages 4-1.8 Calibration of Testing Equipment. Testing equipment, such as, but not limited to pressure gages, metering devices, hydraulic systems, force (load) measuring instruments, and strain-measur- ing devices shall be calibrated by a testing agency acceptable to the Engineer at intervals not to ex- ceed 12 months and following repairs, modification, or relocation of the equipment. Calibration certifi- cates shall be provided when requested by the Engineer. 4-1 .9 Construction Materials Dispute Resolution (Soils, Rock Materials, Concrete, Mortar and Related Materials, Masonry Materials, Bituminous Materials, Rock Products, and Modified As- phalts). In the interest of safety and public value, whenever credible evidence arises to contradict the test values of materials, the Agency and the Contractor will initiate an immediate and cooperative investigation. Test values of materials are results of the materials' tests, as defined by these Specifi- cations or by the General provisions, required to accept the Work. Credible evidence is process ob- servations or test values gathered using industry accepted practices. A contradiction exists whenever test values or process observations of the same or similar materials are diverse enough such that the work acceptance or performance becomes suspect. The investigation shall allow access to all test results, procedures, and facilities relevant to the disputed work and consider all available information and, when necessary, gather new and additional information in an attempt to determine the validity, the cause, and if necessary, the remedy to the contradiction. If the cooperative investigation reaches any resolution mechanism acceptable to both the Agency and the Contractor, the contradiction shall be considered resolved and the cooperative investigation concluded. Whenever the cooperative in- vestigation is unable to reach resolution, the investigation may then either conclude without resolution or continue by written notification of one party to the other requesting the implementation of a resolu- tion process by committee. The continuance of the investigation shall be contingent upon recipient's agreement and acknowledged in writing within 3 calendar days after receiving a request. Without acknowledgement, the investigation shall conclude without resolution. The committee shall consist of three State of California Registered Civil Engineers. Within 7 calendar days after the written request notification, the Agency and the Contractor will each select one engineer. Within 14 calendar days of the written request notification, the two selected engineers will select a third engineer. The goal in selection of the third member is to complement the professional experience of the first two engineers. Should the two engineers fail to select the third engineer, the Agency and the Contractor shall each propose 2 engineers to be the third member within 21 calendar days after the written request notification. The first two engineers previously selected shall then select one of the four proposed engineers in a blind draw. The committee shall be a continuance of the cooperative investigation and will re-consider all available information and if necessary, gather new and additional information to determine the validity, the cause, and if necessary, the remedy to the contradiction. The committee will focus upon the performance adequacy of the material(s) using standard engineering principles and practices and to ensure public value, the committee may provide engineering recommendations as necessary. Unless otherwise agreed, the committee will have 30 calendar days from its formation to complete their review and submit their findings. The final resolution of the committee shall be by majority opinion, in writing, stamped and signed. Should the final resolution not be unanimous, the dissenter may attach a written, stamped, and signed minority opinion . Once started, the resolution process by committee shall continue to full conclusion unless: 1. Within 7 days of the formation of the committee, the Agency and the Contractor reach an acceptable resolution mechanism; or 2. Within 14 days of the formation of the committee, the initiating party withdraws its written notification and agrees to bear all investigative related costs thus far incurred; or 3. At any point by the mutual agreement of the Agency and the Contractor. Unless otherwise agreed, the Contractor shall bear and maintain a record for all the investigative costs until resolution. ('\ •+' Revised 6/15/17 Contract No. 4748 Page 71 of 107 Pages Should the investigation discover assignable causes for the contradiction, the assignable party, the Agency or the Contractor, shall bear all costs associated with the investigation. Should assignable causes for the contradiction extended to both parties, the investigation will assign costs cooperatively with each party or when necessary, equally. Should the investigation substantiate a contradiction without assignable cause, the investigation will assign costs cooperatively with each party or when necessary, equally. Should the investigation be unable to substantiate a contradiction, the initiator of the investigation shall bear all investigative costs. All claim notification requirements of the contract pertaining to the contradiction shall be suspended until the investigation is concluded. 4-2 MATERIAL TRANSPORTATION, HANDLING AND STORAGE. The Contractor shall order, pur- chase, transport, coordinate delivery, accept delivery, confirm the quantity and quality received, pre- pare storage area(s), store, handle, protect, move, relocate, remove and dispose excess of all mate- rials used to accomplish the Work. Materials shall be delivered to the site of the work only during working hours, as defined in Section 6-7.2, and shall be accompanied by bills of lading that shall clearly state for each delivery: the name of the Contractor as consignee, the project name and number, address of delivery and name of consignor and a description of the material(s) shipped. Prior to storage of any materials which have been shipped to or by the Contractor to any location within the Agency's boundaries the Contractor shall provide the Engineer a copy of lease agreements for each property where such materials are stored. The lease agreement shall clearly state the term of the lease, the description of materials allowed to be stored and shall provide for the removal of the mate- rials and restoration of the storage site within the time allowed for the Work. All such storage shall conform to all laws and ordinances that may pertain to the materials stored and to preparation of the storage site and the location of the site on which the materials are stored. Loss, damage or deterioration of all stored materials shall be the Contractor's responsibility. Conformance to the requirements of this section, both within and outside the limits of work are a part of the Work. The Engineer shall have the right to verify the suitability of materials and their proper storage at any time during the Work. ('\ •+;' Revised 6/15/17 Contract No. 4748 Page 72 of 107 Pages SECTION 5 -UTILITIES 5-1 LOCATION. The Agency and affected utility companies have, by a search of known records, endeavored to locate and indicate on the Plans, all utilities which exist within the limits of the work. However, the accuracy and/or completeness of the nature, size and/or location of utilities indicated on the Plans is not guaranteed. Where underground main distribution conduits such as water, gas, sewer, electric power, telephone, or cable television are shown on the Plans, the Contractor shall assume that every property parcel will be served by a service connection for each type of utility. As provided in Section 4216 of the California Government Code, at least 2 working days prior to com- mencing any excavation, the Contractor shall contact the regional notification center (Underground Service Alert of Southern California) and obtain an inquiry identification number. The California Department of Transportation is not required by Section 4216 to become a member of the regional notification center. The Contractor shall contact it for location of its subsurface installa- tions. The Contractor shall determine the location and depth of all utilities, including service connections, which have been marked by the respective owners and which may affect or be affected by its opera- tions. If no pay item is provided in the Contract for this work, full compensation for such work shall be considered as included in the prices bid for other items of work. 5-2 PROTECTION. The Contractor shall not interrupt the service function or disturb the support of any utility without authority from the owner or order from the Agency. All valves, switches, vaults, and meters shall be maintained readily accessible for emergency shutoff. Where protection is required to ensure support of utilities located as shown on the Plans or in accord- ance with Section 5-1 , the Contractor shall, unless otherwise provided, furnish and place the neces- sary protection at its expense. Upon learning of the existence and location of any utility omitted from or shown incorrectly on the Plans, the Contractor shall immediately notify the Engineer in writing. When authorized by the Engi- neer, support or protection of the utility will be paid for as provided in Section 3-2.2.3 or 3-3. The Contractor shall immediately notify the Engineer and the utility owner if any utility is disturbed or damaged. The Contractor shall bear the costs of repair or replacement of any utility damaged if located as noted in Section 5-1. When placing concrete around or contiguous to any non-metallic utility installation, the Contractor shall at its expense: 1. Furnish and install a 2-inch cushion of expansion joint material or other similar resilient material; or 2. Provide a sleeve or other opening which will result in a 2-inch minimum-clear annular space be- tween the concrete and the utility; or 3. Provide other acceptable means to prevent embedment in or bonding to the concrete. ,, •+; Revised 6/15/17 Contract No. 4748 Page 73 of 107 Pages Where concrete is used for backfill or for structures which would result in embedment, or partial em- bedment, of a metallic utility installation; or where the coating, bedding or other cathodic protection system is exposed or damaged by the Contractor's operations, the Contractor shall notify the Engineer and arrange to secure the advice of the affected utility owner regarding the procedures required to maintain or restore the integrity of the system. 5-3 REMOVAL. Unless otherwise specified, the Contractor shall remove all interfering portions of utilities shown on the Plans or indicated in the Bid documents as "abandoned" or "to be abandoned in place". Before starting removal operations, the Contractor shall ascertain from the Agency whether the abandonment is complete, and the costs involved in the removal and disposal shall be included in the Bid for the items of work necessitating such removals. 5-4 RELOCATION. When feasible, the owners responsible for utilities within the area affected by the Work will complete their necessary installations, relocations, repairs, or replacements before com- mencement of work by the Contractor. When the Plans or Specifications indicate that a utility installa- tion is to be relocated, altered, or constructed by others, the Agency will conduct all negotiations with the owners and work will be done at no cost to the Contractor, except for manhole frame and cover sets to be brought to grade. Utilities which are relocated in order to avoid interference shall be protected in their position and the cost of such protection shall be included in the Bid for the items of work necessitating such relocation. After award of the Contract, portions of utilities which are found to interfere with the Work will be relocated, altered or reconstructed by the owners, or the Engineer may order changes in the Work to avoid interference. Such changes will be paid for in accordance with Section 3-2. When the Plans or Specifications provide for the Contractor to alter, relocate, or reconstruct a utility, all costs for such work shall be included in the Bid for the items of work necessitating such work. Temporary or permanent relocation or alteration of utilities requested by the Contractor for its conven- ience shall be its responsibility and it shall make all arrangements and bear all costs. The utility owner will relocate service connections as necessary within the limits of the Work or within temporary construction or slope easements. When directed by the Engineer, the Contractor shall ar- range for the relocation of service connections as necessary between the meter and property line, or between a meter and the limits of temporary construction or slope easements. The relocation of such service connections will be paid for in accordance with provisions of Section 3-3. Payment will include the restoration of all existing improvements which may be affected thereby. The Contractor may agree with the owner of any utility to disconnect and reconnect interfering service connections. The Agency will not be involved in any such agreement. In conformance with Section 5-6 the Contractor shall coordinate the work with utility agencies and companies. Prior to the installation of any and all utility structures within the limits of work by any utility agency or company, or its contractor, the Contractor shall place all curb or curb and gutter that is a part of the work and adjacent to the location where such utility structures are shown on the plans and are noted as being located, relocated or are otherwise shown as installed by others. In order to mini- mize delays to the Contractor caused by the failure of other parties to relocate utilities that interfere with the construction, the Contractor, upon the Engineer's approval, may be permitted to temporarily omit the portion of work affected by the utility. If such temporary omission is approved by the Engineer the Contractor shall place survey or other physical control markers sufficient to locate the curb or curb and gutter to the satisfaction of the utility agency or company. Such temporary omission shall be for the Contractor's convenience and no additional compensation will be allowed therefore or for addi- tional work, materials or delay associated with the temporary omission. The portion thus omitted shall ,, • .., Revised 6/15/17 Contract No. 4748 Page 74 of 107 Pages be constructed by the Contractor immediately following the relocation of the utility involved unless otherwise directed by the Engineer. 5-5 DELAYS. The Contractor shall notify the Engineer of its construction schedule insofar as it affects the protection, removal, or relocation of utilities. Said notification shall be included as a part of the construction schedule required in Section 6-1. The Contractor shall notify the Engineer in writing of any subsequent changes in the construction schedule which will affect the time available for pro- tection, removal, or relocation of utilities. The Contractor will not be entitled to damages or additional payment for delays attributable to utility relocations or alterations if correctly located, noted, and completed in accordance with Section 5-1 . The Contractor may be given an extension of time for unforeseen delays attributable to unreasonably protracted interference by utilities in performing work correctly shown on the Plans. The Agency will assume responsibility for the timely removal, relocation, or protection of existing main or trunk line utility facilities within the area affected by the Work if such utilities are not identified in the Contract Documents. The Contractor will not be assessed liquidated damages for any delay caused by failure of Agency to provide for the timely removal, relocation, or protection of such existing facilities. If the Contractor sustains loss due to delays attributable to interferences, relocations, or alterations not covered by Section 5-1, which could not have been avoided by the judicious handling of forces, equipment, or plant, there shall be paid to the Contractor such amount as the Engineer may find to be fair and reasonable compensation for such part of the Contractor's actual loss as was unavoidable and the Contractor may be granted an extension of time. 5-6 COOPERATION. It is the Contractor's responsibility to be aware of all existing field conditions prior to bidding. Contractor shall cooperate and coordinate all construction activities with utility companies, special agencies, city departments, homeowner's associations, or other entities of any kind as may be required to facilitate the work herein. No additional compensation shall be requested by the Contractor, nor shall any be approved by the City related to this clause. When necessary, the Contractor shall so conduct its operations as to permit access to the Work site and provide time for utility work to be accomplished during the progress of the Work. l' • ., Revised 6/15/17 Contract No. 4748 Page 75 of 107 Pages SECTION 6 -PROSECUTION, PROGRESS, AND ACCEPTANCE OF THE WORK 6-1 CONSTRUCTION SCHEDULE AND COMMENCEMENT OF WORK. Except as otherwise provided herein and unless otherwise prohibited by permits from other agencies as may be required by law the Contractor shall begin work within _§_calendar days after receipt of the "Notice to Proceed". 6-1.1 Pre-Construction Meeting. After, or upon, notification of contract award, the Engineer will set the time and location for the Preconstruction Meeting. Attendance of the Contractor's management personnel responsible for the management, administration, and execution of the project is mandatory for the meeting to be convened. Failure of the Contractor to have the Contractor's responsible project personnel attend the Preconstruction Meeting will be grounds for default by Contractor per Section 6- 4. No separate payment will be made for the Contractor's attendance at the meeting. The notice to proceed will only be issued on or after the completion of the preconstruction meeting. 6-1.1.1 Baseline Construction Schedule Submittal. The Contractor shall submit the Baseline Construction Schedule per the submittal requirements of Section 2-5.3. The submittal of the Base- line Construction Schedule shall be on hard (paper) copy and electronic media conforming to Sec- tion 6-1.3.3 Electronic Media. 6-1.2 Preparation and Review of the Baseline Construction Schedule. The Contractor shall prepare the Baseline Construction Schedule as a Critical Path Method (CPM) Schedule in the prece- dence diagram method (activity-on-node) format. The Baseline Construction Schedule shall depict a workable plan showing the sequence, duration, and interdependence of all activities required to rep- resent the complete performance of all project work as well as periods where work is precluded. The Baseline Construction Schedule shall begin with the projected date of issuance of the notice to pro- ceed and conclude with the date of final completion per the contract duration. The Baseline Con- struction Schedule shall include detail of all project phasing, staging, and sequencing, including all milestones necessary to define beginning and ending of each phase or stage. 6-1.2.1 Time-Scaled Network Diagram. As a part of the Baseline Construction Schedule the Contractor shall prepare and submit to the Engineer a complete time-scaled network diagram showing all of the activities, logic relationships, and milestones comprising the schedule. 6-1.2.2 Tabular Listing. As a part of the Baseline Construction Schedule the Contractor shall prepare and submit to the Engineer a tabular listing of all of the activities, showing for each activity the identification number, the description, the duration, the early start, the early finish, the late start, the late finish, the total float, and all predecessor and successor activities for the activity described. 6-1.2.3 Bar Chart. As a part of the Baseline Construction Schedule the Contractor shall prepare and submit to the Engineer a chart showing individual tasks and their durations arranged with the tasks on the vertical axis and duration on the horizontal axis. The bar chart shall use differing texture patterns or distinctive line types to show the critical path. 6-1.2.4 Schedule Software. The Contractor shall use commercially available software equal to the Windows compatible Primavera "P6" or Microsoft "Project" to prepare the Baseline Construction Schedule and all updates thereto. The Contractor shall submit to the Agency all schedule and data files, in a format readable by Windows 10 software programs and/or Microsoft Project. ,, •,r Revised 6/15/17 Contract No. 4748 Page 76 of 107 Pages 6-1.2.5 Schedule Activities. Except for submittal activities, activity durations shall not be shorter than 1 working day nor longer than 15 working days, unless specifically and individually allowed by the Engineer. The Baseline Construction Schedule shall include between 100 and 300 activities, in- cluding submittals, interfaces between utility companies and other agencies, project milestones and equipment and material deliveries. The number of activities will be sufficient, in the judgment of the City's Construction Management Consultant, to communicate the Contractor's plan for project execu- tion, to accurately describe the project work, and to allow monitoring and evaluation of progress and of time impacts. Each activity's description shall accurately define the work planned for the activity and each activity shall have recognizable beginning and end points. 6-1.2.6 Float. Float or slack time within the schedule is available without charge or compensation to whatever party or contingency first exhausts it. 6-1.2. 7 Restraints to Activities. Any submittals, utility interfaces, or any furnishing of Agency supplied materials, equipment, or services, which may impact any activity's construction shall be shown as a restraint to those activities. Time periods to accommodate the review and correction of submittals shall be included in the schedule. 6-1.2.8 Late Completion. The Baseline Construction Schedule shall not show a project duration longer than the specified contract duration. 6-1.2.9 Early Completion. The Baseline Construction Schedule will show the Contractor's plan to support and maintain the project for the entire contractual time span of the project. Should the Con- tractor propose a project duration shorter than contract duration, a complete Baseline Construction Schedule must be submitted, reflecting the shorter duration, in complete accordance with all schedule requirements of Section 6-1. The Engineer may choose to accept the Contractor's proposal of a project duration shorter than the duration specified; provided the Agency is satisfied the shortened Baseline Construction Schedule is reasonable and the Agency and all other entities, public and pri- vate, which interface with the project are able to support the provisions of the shortened Baseline Construction Schedule. The Agency's acceptance of a shortened duration project will be confirmed through the execution of a contract change order revising the project duration and implementing all contractual requirements including liquidated damages in accordance with the revised duration. 6-1.2.10 Engineer's Review. The Construction Schedule is subject to the review of the Engineer. The Engineer's determination that the Baseline Construction Schedule proposed by the Contractor com- plies with the requirements of these supplemental provisions shall be a condition precedent to issu- ance of the Notice to Proceed by the Engineer. If the Engineer determines that the Construction Schedule does not meet the requirements of these specifications the Contractor shall correct the Con- struction Schedule to meet these specifications and resubmit it to the Engineer. Failure of the Con- tractor to obtain the Engineer's determination that the initial Construction Schedule proposed by the Contractor complies with the requirements of these supplemental provisions within thirty (30) working days after the date of the preconstruction meeting shall be grounds for termination of the contract per Section 6-4. Days used by the Engineer to review the initial Construction Schedule will not be included in the 30 working days. The Engineer will review and return to the Contractor, with any comments, the Baseline Construction Schedule within 15 working days of submittal. The Baseline Construction Schedule will be returned marked as per Sections 6-1.2.1 0.1 through 6-1.2.10.3. 6-1.2.10.1 "Accepted." The Contractor may proceed with the project work upon issuance of the Notice to Proceed and will receive payment for the schedule in accordance with Section 6-1.8.1. {'\ • ., Revised 6/15/17 Contract No. 4748 Page 77 of 107 Pages 6-1.2.10.2 "Accepted with Comments." The Contractor may proceed with the project work upon issuance of the Notice to Proceed. The Contractor must resubmit the schedule incorporating the comments prior to receipt of payment per Section 6-1 .8.1. 6-1.2.10.3 "Not Accepted." The Contractor must resubmit the schedule incorporating the corrections and changes of the comments prior to receipt of payment per Section 6-1.8.1. The Notice to Proceed will not be issued by the Engineer if the changes of the comments are not submitted as required hereinbefore and marked "Accepted" or "Accepted with Comments" by the Engineer. The Contractor, at the sole option of the Engineer, may be considered as having defaulted the contract under the provisions of Section 6-4 DEFAULT BY CONTRACTOR if the changes of the comments are not sub- mitted as required herein before and marked "Accepted" by the Engineer. 6-1.3 Preparation of Schedule Updates and Revisions. The Contractor shall meet with the Engineer during the last week of each month to agree upon each activity's schedule status and shall submit monthly updates of the Baseline Construction Schedule confirming the agreements no later than the fifth working day of the following month. The monthly update will be submitted on hard (paper) copy and electronic media conforming to Section 6-1.3.3 Electronic Media per the submittal require- ments of Section 2-5.3 and will include each item and element of Sections 6-1 .2 through 6-1.2.9 and 6-1.3.1 through 6-1 .3.7. 6-1.3.1 Actual Activity Dates. The actual dates each activity was started and/or completed during the month. After first reporting an actual date, the Contractor shall not change that actual date in later updates without specific notification to the Engineer with the update. 6-1.3.2 Activity Percent Complete. For each activity underway at the end of the month, the Con- tractor shall report the percentage determined by the Engineer as complete for the activity. 6-1.3.3 Electronic Media. The schedule data shall be submitted on a thumb-drive, labeled with the project name and number, the Contractor's name and the date of preparation of the schedule data disk. The schedule data disk shall be readable by the software specified in Section 6-1.2.4 "Schedule Software" and shall be free of file locking, encryption or any other protocol that would impede full access of all data stored on it. 6-1 .3.4 List of Changes. A list of all changes made to the activities or to the interconnecting logic, with an explanation for each change. 6-1.3.5 Change Orders. Each monthly update will include the addition of the network revisions re- flecting the change orders approved in the previous month. The network revisions will be as agreed upon during the review and acceptance of the Contractor's change orders. 6-1.3.6 Bar Chart. Each monthly update will include a chart showing individual tasks and their durations arranged with the tasks on the vertical axis and duration on the horizontal axis. The bar chart shall use differing texture patterns or distinctive line types to show the critical path. 6-1.4 Engineer's Review of Updated Construction Schedule. The Engineer will review and return the Updated Construction Schedule to the Contractor, with any comments, within 5 working days of submittal. The Updated Construction Schedule will be returned marked as per Sections 6-1.4.1 through 6-1.4.3. Any Updated Construction Schedule marked "Accepted with Comments" or "Not Ac- cepted" by the Engineer will be returned to the Contractor for correction. Upon resubmittal the Engi- neer will review and return the resubmitted Updated Construction Schedule to the Contractor, with any comments, within 5 working days. Failure of the Contractor to submit a monthly updated construction l' •+;' Revised 6/15/17 Contract No. 4748 Page 78 of 107 Pages schedule will invoke the same consequences as the Engineer returning a monthly updated construc- tion schedule marked "Not Accepted". 6-1.4.1 "Accepted." The Contractor may proceed with the project work and will receive payment for the schedule in accordance with Section 6-1.8.2. 6-1.4.2 "Accepted with Comments." The Contractor may proceed with the project work. The Con- tractor must resubmit the Updated Construction Schedule to the Engineer incorporating the correc- tions and changes noted in the Engineer's comments prior to receipt of payment per Section 6-1.8.2. 6-1.4.3 "Not Accepted." The Contractor must resubmit the Updated Construction Schedule to the Engineer incorporating the corrections and changes noted in the Engineer's comments prior to receipt of payment per Section 6-1 .8.2. The Contractor, at the sole option of the Engineer, may be considered as having defaulted the contract under the provisions of Section 6-4 DEFAULT BY CONTRACTOR if the changes of the comments are not submitted and marked "Accepted" by the Engineer before the last day of the month in which the Updated Construction Schedule is due. If the Contractor fails to submit the corrected Updated Construction Schedule as required herein the Contractor may elect to proceed with the project at its own risk. Should the Contractor elect not to proceed with the project, any resulting delay, impact, or disruption to the project will be the Contractor's responsibility. 6-1.5 Late Completion or Milestone Dates. Should the Schedule Update indicate a completion or contractually required milestone date later than the properly adjusted contract or milestone duration, the Agency may withhold Liquidated Damages for the number of days late. Should a subsequent "Accepted" Schedule Update remove all or a portion of the delay, all or the allocated portion of the previously held Liquidated Damages shall be released in the monthly payment to the Contractor im- mediately following the "Accepted" schedule. 6-1.6 Interim Revisions. Should the actual or projected progress of the work become substantially different from that depicted in the Project Schedule, independently of and prior to the next monthly update, the Contractor will submit a revised Baseline Construction Schedule, with a list and explana- tion of each change made to the schedule. The Revised Construction Schedule will be submitted per the submittal requirements of Section 2-5.3 and per the schedule review and acceptance requirements of Section 6-1, including but not limited to the acceptance and payment provisions. As used in this section "substantially different" means a time variance greater than 5 percent of the number of days of duration for the project. 6-1. 7 Final Schedule Update. The Contractor shall prepare and submit a final schedule update when one hundred percent of the construction work is completed. The Contractor's Final Schedule Update must accurately represent the actual dates for all activities. The final schedule update shall be prepared and reviewed per Sections 6-1 .3 Preparation of Schedule Updates and Revisions and 6-1.4 Engineer's Review of Updated Construction Schedule. Acceptance of the final schedule update is required for completion of the project and release of any and all funds retained per Section 9-3.2. 6-1.8 Measurement and Payment of Construction Schedule. The Contractor's preparation, revi- sion and maintenance of the Construction Schedule is incidental to the work and no separate payment will be made therefore. 6-2 PROSECUTION OF WORK. To minimize public inconvenience and possible hazard and to restore work areas to their original state of usefulness as soon as practicable, the Contractor shall diligently prosecute the Work to completion. If the Engineer determines that the Contractor is failing to prosecute the Work to the proper extent, the Contractor shall, upon orders from the Engineer, im- mediately take steps to remedy the situation. All costs of prosecuting the Work as described herein ,, • ., Revised 6/15/17 Contract No. 4748 Page 79 of 107 Pages shall be included in the Contractor's Bid. Should the Contractor fail to take the necessary steps to fully accomplish said purposes, after orders of the Engineer, the Engineer may suspend the work in whole or part, until the Contractor takes said steps. As stated in Contractor's Proposal, all work within each building structure is required to be sequential (building by building) in coordination with the City, instead of simultaneously in all buildings, so public access can be coordinated and/or restricted during certain time periods as necessary. The ranch serves the community as a wedding venue and is very busy coordi- nating space in certain buildings and around the ranch during the spring, summer and fall. For this reason, construction activity of any sort must be limited to Mondays -Thursdays, with complete clean up of all work areas by close of business on Thursdays. Work in the Hacienda building may occur on Fridays, but only during the months of December to February. If Work is suspended through no fault of the City, all expenses and losses incurred by the Contractor during such suspensions shall be borne by the Contractor. If the Contractor fails to properly provide for public safety, traffic, and protection of the Work during periods of suspension, the City may elect to do so and deduct the cost thereof from monies due the Contractor. Such actions will not relieve the Contractor from liability. 6-2.1 Review of Contract Documents and Field Conditions by Contractor 1. Contractor and its Subcontractors shall carefully study and compare each of the Contract Docu- ments with the others and with information furnished or made available by City of Carlsbad and shall promptly report in writing to City's Construction Management Consultant any errors, incon- sistencies, or omissions in the Contract Documents or inconsistencies with Legal Requirements observed by Contractor or its Subcontractors. 2. Contractor and its Subcontractors shall take field measurements, verify field conditions, and care- fully compare with the Contract Documents such field measurements, conditions, and other infor- mation known to Contractor before commencing any item of Construction Work. Errors, inconsist- encies, or omissions discovered at any time shall be promptly reported in writing to City's Con- struction Management Consultant. 3. If Contractor and its Subcontractors performs any construction activity involving an error, incon- sistency, or omission referred to in the General Provisions, without giving the notice required to the City's Construction Management Consultant and obtaining the written consent of the City's Construction Management Consultant, Contractor shall be responsible for the resultant losses, including, without limitation, the costs of correcting Defective Work. 4. Contractor shall be responsible for all Losses attributable to the errors or omissions of the Con- tractor in the performance of Pre-Construction Services. Prior to the issuance of a notice to pro- ceed for Phase 1, Phase 2 and Phase 3, Contractor shall certify and warrant that the plans for that Phase are constructible and constructible within the applicable Phase Time. 6-2.2 Supervision and Construction Procedures 1. Contractor shall supervise, coordinate, and direct the Construction Work using Contractor's best skill and attention. Contractor shall be solely responsible for and have control over construction means, methods, techniques, sequences, procedures, and the coordination of all portions of the Construction Work. Contractor shall manage and administer all phases of construction activities ,., •+;' Revised 6/15/17 Contract No. 4748 Page 80 of 107 Pages to achieve the completion of the Construction Work within the requirements of the Contract Docu- ments. The Contractor shall coordinate the work of its Subcontractors to optimize efficiency and minimize conflict and interference between the various Subcontractors on-site. 2. Contractor shall be responsible to City of Carlsbad for acts and omissions of Contractor's agents, employees, and Subcontractors, and their respective agents and employees. 3. Contractor shall not be relieved of its obligation to perform the Construction Work in accordance with the Contract Documents either by acts or omissions of City of Carlsbad or City's Construction Management Consultant in the administration of the Contract, or by tests, inspections, or approvals required or performed by persons or firms other than Contractor. 4. Contractor shall be responsible for inspection of all portions of the Construction Work, including those portions already performed under this Contract, to determine that such portions conform to the requirements of the Contract Documents and are ready to receive subsequent Construction Work. 5. Contractor shall at all times maintain good discipline and order among its employees and Subcon- tractors. Contractor shall provide competent, fully qualified personnel to perform the Work. 6. Contractor's responsibility shall include assuring that its Subcontractors are meeting all the terms of the Contract Documents. Contractor shall provide on-site quality control and inspection to en- sure compliance with documents, drawings and contract specifications, schedule coordination and information coordination for all construction activities on the construction site including all General Provisions Work. Contractor shall schedule and coordinate testing and inspection services. This will include coordination with the Subcontractors and the City's Construction Management Con- sultant, and scheduling of all Inspections. Prior to close-up of concealed areas, the Contractor shall coordinate all applicable inspections with the City's Construction Management Consultant and create a punch list and distribute to all affected Subcontractors. 7. Contractor shall coordinate all required utility shutdowns, road closures, traffic closures, and the like. This coordination shall follow procedures at the Facility, and or direction as provided by the City's Construction Management Consultant. 6-2.3 Labor and Materials. Unless otherwise provided in the Contract Documents, Contractor shall provide and pay for all labor, services, materials, equipment, tools, construction equipment and ma- chinery, water, heat, utilities, transportation, and other facilities and services necessary for proper execution and Final Completion of the Construction Work, whether temporary or permanent and whether or not incorporated or to be incorporated in the Construction Work. 6-2.4 Contractor's Warranty 1. Contractor warrants to City of Carlsbad that all materials and equipment used in or incorporated into the Construction Work will be of good quality, new, and free of liens, claims, and security interests of third parties; that the Construction Work will be of good quality and free from defects; and that the Construction Work will conform with the requirements of the Contract Documents. If required by City's Construction Management Consultant, Contractor shall furnish satisfactory ev- idence as to the kind and quality of materials and equipment. 2. The Contractor shall assure that there is no damage of existing utilities; and protect trees and root systems both during demolition and construction. ,, •+;' Revised 6/15/17 Contract No. 4748 Page 81 of 107 Pages 6-2.5 Taxes. Contractor shall pay all sales, consumer, use, and similar taxes for the Work or por- tions thereof provided by Contractor. 6-2.6 Permits, Fees and Notices. Except for the permits and approvals which are to be obtained by City of Carlsbad or the requirements with respect to which City of Carlsbad is not subject, Con- tractor shall secure and pay for all permits, approvals, government fees, licenses, and inspections necessary for the proper execution and performance of the Construction Work. Contractor shall de- liver to City of Carlsbad all original licenses, permits, and approvals obtained by Contractor in con- nection with the Construction Work prior to the final payment or upon termination of the Contract, whichever is earlier. 6-2.7 Compliance with Laws 1. Contractor shall keep fully informed of and shall comply with all statutes, laws, ordinances, codes, rules, regulations and orders of any properly constituted authority affecting the Work and persons connected with Work, and shall protect and indemnify the City of Carlsbad and its elected officials, officers, employees, consultants and agents against any claim or liability, including attorney's fees, arising from or based on violation of any statutes, laws, ordinances, codes, rules, regula- tions or orders, whether by Contractor or by Subcontractors, employees or agents. Authorized persons may at any time enter upon any part of the Work to ascertain compliance of all applicable statutes, laws, ordinances, codes, rules, regulations and orders. 2. Contractor's Permits and License. Contractor certifies that it possesses and shall continue to maintain or shall cause to be obtained and maintained, at no cost to the City of Carlsbad, all approvals, permissions, permits, licenses, and other forms of documentation required for it and its employees to comply with all applicable statutes, ordinances, and regulations, or other laws, that may apply to performance of work hereunder. City of Carlsbad may reasonably request and review all such applications, permits, and licenses. 3. Equal Opportunity. Contractor shall comply with the provisions of Title VII of the Civil Rights Act of 1964 in that Contractor shall not discriminate against any individual with respect to his or her compensation, terms, conditions, or privileges of employment nor shall Contractor discriminate in any way that would deprive or intend to deprive any individual of employment opportunities or otherwise adversely affect his or her status as an employee because of such individual's race, color, religion, sex, national origin, age, handicap, medical condition, sexual orientation or marital status. 4. Drug and Alcohol-Free Workplace. In Board of Supervisors' Policy C-25, City of Carlsbad Drug and Alcohol Use Policy, the Board of Supervisors recognized that those who perform services or work for City of Carlsbad under contract should perform the services or work as safely, effectively and efficiently as possible. a) Contractor and Contractor's employees, while performing work for the City, or while using City equipment: 1) Shall not be in any way impaired because of being under the influence of alcohol or a drug. 2) Shall not possess, consume or be under the influence of alcohol and/or an illegal drug. 3) Shall not sell, offer, or provide alcohol or an illegal drug to another person. b) Section 1. 7.5 is a material condition of this Contract. If the City's Construction Management Consultant determines that Contractor and/or Contractor's employee(s) has not complied with Section 1. 7 .5, City may terminate this Contract for default and may also terminate any other contract Contractor has with City. ,, • ., Revised 6/15/17 Contract No. 4748 Page 82 of 107 Pages 5. Cartwright Act. Following receipt of final payment under the Contract, Contractor assigns to City of Carlsbad all rights, title and interest in and to all causes of action it may have under Section 4 of the Clayton Act (15 U.S.C. Sec. 15) or under the Cartwright Act (Chapter 1 of Part 2 of Division 7 of the Business and Professions Code, commencing with section 16700), arising from pur- chases of goods, materials, or work by the Contractor for sale to City under this Contract. 6. Hazardous Materials. Contractor shall comply with all Environmental Laws and all other laws, rules, regulations, and requirements regarding Hazardous Materials, health and safety, notices, and training. Contractor shall not store any Hazardous Materials on any City property for more than 90 days or in violation of the applicable site storage limitations imposed by Environmental Law. At its sole expense, Contractor shall take all actions necessary to protect third parties, including, without limitation, employees and agents of City, from any exposure to Hazardous Ma- terials generated or utilized in Contractor's performance under this Contract. Contractor shall report to the appropriate governmental agencies all discharges, releases, and spills of Hazardous Materials that are required to be reported by any Environmental Law and to immediately notify the City of it. Contractor shall not be liable to the City for City's failure to comply with, or for City's violation of, any Environmental Law. As used in this section, the term "Environmental Laws" means any and all federal, State and local laws, ordinances, rules, decrees, orders, regulations or court decisions (including the "common law"), relating to hazardous substances, hazardous materials, hazardous waste, toxic substances, environmental conditions or other similar sub- stances or conditions. One such law is the Resource Conservation and Recovery Act. As used in this section, the term "Hazardous Materials" means any chemical, compound, material, sub- stance or other matter that: (a) is a flammable, explosive, asbestos, radioactive nuclear medicine, vaccine, bacteria, virus, hazardous waste, toxic, overtly injurious or potentially injurious material, whether injurious or potentially injurious by itself or in combination with other materials; (b) is controlled, referred to, designated in or governed by any Environmental Laws; (c) gives rise to any reporting, notice or publication requirements under any Environmental Laws; or (d) is any other material or substance for which there may be any liability, responsibility or duty on City or Contractor with respect to any third person under any Environmental Laws. 7. Debarment and Suspension. Contractor certifies that it, its principals, its employees and its Sub- contractors: a) Are not presently debarred, suspended, proposed for debarment, declared ineligible, or vol- untarily excluded from covered transactions by any State or federal department or agency. b) Have not within a 3-year period preceding this Contract been convicted of, or had a civil judg- ment rendered against them for, the commission of fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public (federal, State, or local) transac- tion; violation of federal or State anti-trust statutes or commission of embezzlement, theft, forgery, bribery, falsification or destruction of records, making false statements, or receiving stolen property; c) Are not presently indicted or otherwise criminally or civilly charged by a government entity (federal, State, or local) with commission of any of the offenses enumerated in the paragraph above;and d) Have not within a 3-year period preceding this Contract had one or more public transactions (federal, State, or local) terminated for cause or default. 8. To the extent applicable, whenever the Drawings and Specifications require larger sizes or higher standards than are required by any applicable law, ordinance, regulation or order, the Drawings and Specifications shall govern. Whenever the Drawings and Specifications require something, which would violate such laws, ordinances, regulations or orders, then such laws, ordinances, regulations or orders shall govern. ,, •ff Revised 6/15/17 Contract No. 4748 Page 83 of 107 Pages 9. During excavation or at any other time that evidence of any archaeological artifacts, human burial remains, or unique paleontology is found, the Contractor shall immediately cease work and notify the City of Carlsbad orally and in writing. a) The Contractor shall grant the City forty-eight (48) hours to evaluate the archaeological evi- dence. The Contractor will be granted an extension of time and will not be assessed with liquidated damages or any penalties for the forty-eight (48) hour period of this provision. The Contractor shall have no claim for any additional damage or compensation due to this delay. 10. For additional time, beyond the forty-eight (48) hours, required by the City to pursue any action relative to the archaeological aspects of the site, the Contractor will be granted an appropriate time extension as provided in this Contract. 6-2.8 Superintendent and Key Personnel 1. Contractor shall employ a competent Superintendent satisfactory to City who shall be at the Pro- ject site at all times during the performance of the Construction Work. Superintendent shall rep- resent Contractor, and communications given to and received from Superintendent shall be bind- ing on Contractor. Failure to maintain a Superintendent on the Project site at all times Construc- tion Work is in progress shall be considered a material breach of this Contract, entitling City of Carlsbad to terminate the Contract or alternatively, issue a Stop Work Order until the Superinten- dent is on the Project site. If, by virtue of issuance of said Stop Work Order, Contractor fails to complete the Contract on time, Contractor will be assessed Liquidated Damages in accordance with the Agreement. 2. The Superintendent approved for the Project must be able to read, write and orally communicate in English. The Superintendent may not perform the Construction Work of any trade, pick-up materials, or perform any Construction Work not directly related to the supervision and coordina- tion of the Construction Work at the Project site when Construction Work is in progress. 3. Contractor shall provide the Key Personnel, in addition to the Superintendent. Substitution or re- placement of any named individual requires the written approval of the City's Construction Man- agement Consultant, which approval will be at the sole discretion of City of Carlsbad. Failure to provide the listed individuals at all times Work is in progress shall be considered a material breach of this Contract unless the named individuals are no longer employed or retained by Contractor, a company Contractor has a financial interest in, or a parent company of Contractor; such material breach shall entitle City of Carlsbad to terminate the Contract or alternatively, issue a Stop Work Order until the individual or an acceptable replacement is provided. If, by virtue of issuance of said Stop Work Order, Contractor fails to complete the Contract on time, Contractor will be subject to Liquidated Damages in accordance with the Contract. 6-2.9 As-Built Documents. Contractor shall maintain one set of as-built drawings and specifica- tions on site, which shall be kept up to date during the Construction Work of the Contract. All changes incorporated into the Construction Work that differ from the documents as drawn and written shall be noted on the as-built set. Notations shall reflect the actual materials, equipment and installation meth- ods used for the Construction Work and each revision shall be initialed and dated by Superintendent. Prior to filing of the Notice of Completion, each drawing and the specification cover shall be signed by Contractor and dated attesting to the completeness of the information noted therein. As-built Docu- ments shall be turned over to the City's Construction Management Consultant and shall become part of the Record Documents. {\ • ., Revised 6/1 5/17 Contract No. 4748 Page 84 of 107 Pages 6-2.10 Documents and Samples at Project Site 1. Contractor shall maintain the following at the Project site a) One as-built copy of the Contract Documents, in good order and marked to record current changes and selections made during construction b) The current accepted Contract Schedule c) Shop Drawings, Product Data, and Samples d) All other required submittals 2. These documents shall be available to City's Construction Management Consultant and shall be delivered to City's Construction Management Consultant for submittal to City of Carlsbad upon the earlier of Final Completion or termination of the Contract. 6-2.11 Shop Drawings, Product Data and Samples 1. Definitions: a) Shop Drawings are drawings, diagrams, schedules, and other data specially prepared for the Construction Work by Contractor or a Subcontractor to illustrate some portion of the Con- struction Work. b) Product Data are illustrations, standard schedules, performance charts, instructions, bro- chures, diagrams, and other information furnished by Contractor to illustrate or describe ma- terials or equipment for some portion of the Construction Work. c) Samples are physical examples which illustrate materials, equipment, or workmanship and establish standards by which the Construction Work will be judged. 2. Shop Drawings, Product Data, Samples, and similar submittals are not Contract Documents. Their purpose is to demonstrate, for those portions of the Construction Work for which submittals are required, how Contractor proposes to conform to the information given and the design con- cept expressed in the Contract Documents. 3. Contractor shall review, approve, and submit to City's Construction Management Consultant Shop Drawings, Product Data, Samples, and similar submittals required by the Contract Documents with reasonable promptness and in such sequence as to cause no delay in the Construction Work or in the activities of City of Carlsbad or of Separate Contractors. Submittals made by Contractor that are not required by the Contract Documents may be returned without action by City's Construction Management Consultant. 4. Contractor shall perform no portion of the Construction Work requiring submittal and review of Shop Drawings, Product Data, Samples, or similar submittals until the respective submittal has been reviewed by City's Construction Management Consultant and no exceptions have been taken by City's Construction Management Consultant. Such Construction Work shall be in accordance with approved submittals and the Contract Documents. 5. By approving and submitting Shop Drawings, Product Data, Samples, and similar submittals, Con- tractor represents that it has determined or verified materials and field measurements and condi- tions related thereto, and that it has checked and coordinated the information contained within such submittals with the requirements of the Contract Documents and Shop Drawings for related Construction Work. 6. If Contractor discovers any conflicts, omissions, or errors in Shop Drawings or other submittals, Contractor shall notify City's Construction Management Consultant and receive instruction before proceeding with the affected Work. ,, •ff Revised 6/15/17 Contract No. 4748 Page 85 of 107 Pages 7. Contractor shall not be relieved of responsibility for deviations from requirements of the Contract Documents by City's Construction Management Consultant's review of Shop Drawings, Product Data, Samples, or similar submittals, unless Contractor has specifically informed City's Construc- tion Management Consultant in writing of such deviation at the time of submittal and City's Con- struction Management Consultant has given written approval of the specific deviation. Contractor shall not be relieved of responsibility for errors or omissions in Shop Drawings, Product Data, Samples, or similar submittals by City's Construction Management Consultant's review, ac- ceptance, comment, or approval thereof. 8. Contractor shall direct specific attention, in writing or on resubmitted Shop Drawings, Product Data, Samples, or similar submittals, to revisions other than those requested by City's Construc- tion Management Consultant on previous submittals. 6-2.12 Use of Site and Clean Up 1 . Contractor shall confine operations at the Project site to areas affected by the applicable Work exercised and to those areas permitted by law, ordinances, permits, and the Contract Documents. Contractor shall not unreasonably encumber the Project site with materials or equipment. 2. Contractor shall, during performance of the Construction Work, keep the Project site and sur- rounding area free from the accumulation of excess dirt, waste materials, and rubbish caused by Contractor. Contractor shall remove all dirt, waste material, and rubbish caused by the Contrac- tor; tools; equipment; machinery; and surplus materials from the Project site and surrounding area at the completion of the Construction Work. 3. Personnel of Contractor and Subcontractors shall not occupy, live upon, or otherwise make use of any portion of the Project site during any time that Work is not being performed at that portion the Project site, except as otherwise provided in the Contract Documents. 6-2.13 Cutting, Fitting and Patching 1. Contractor shall do all cutting, fitting, or patching of the Construction Work required to make all parts of the Construction Work come together properly and to allow the Construction Work to receive or be received by work of Separate Contractors shown upon, or reasonably implied by, the Contract Documents. 2. Contractor shall not endanger the Construction Work, the Project, or adjacent property by cutting, digging, or otherwise. Contractor shall not cut or alter the work of any Separate Contractor without the prior consent of City's Construction Management Consultant. 6-2.14 Access to Construction Work. City representative, their consultants, and other persons au- thorized by City shall at all times have access to the Construction Work wherever it is in preparation or progress. Contractor shall provide safe and proper facilities for such access and for inspection. 6-2.15 Royalties and Patents. Contractor shall pay all royalties and license fees required for the performance of the Work, which are included in the Contract Sum. Contractor shall defend suits or claims resulting from Contractor's or any Subcontractor's infringement of patent rights, and Contrac- tor's indemnification obligations per the General Provisions of the contract shall specifically apply to any losses on account thereof. ,., •~ Revised 6/15/17 Contract No. 4748 Page 86 of 107 Pages 6-2.16 Differing Site Conditions 1. If Contractor encounters any of the following conditions at the site, Contractor shall immediately notify the City's Construction Management Consultant in writing of the specific differing conditions before they are disturbed and before any affected Work is performed, and permit investigation of the conditions: a) Subsurface or latent physical conditions at the site (including Hazardous Materials) that differ materially from those indicated in this Contract, or if not indicated in this Contract, in the In- formation Available to Bidders; or b) Unknown physical conditions at the site, of an unusual nature, that differ materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in the Contract. 2. Contractor shall be entitled to an adjustment to the Contract Sum and/or Contract Time as the result of extra costs and/or delays resulting from a materially differing site condition, if and only if Contractor fulfills the following conditions: a) Contractor fully complies with the contact documents (including the timely filing of a Change Order Request and all other requirements for Change Orders Requests and Claims). 3. Adjustments to the Contract Sum and/or Contract Time shall be subject to the procedures and limitations set forth in the contact documents. 6-2.17 Concealed, Unforeseen or Unknown Conditions or Events 1. Except as and only to the extent provided otherwise in the contact documents, by signing the contract agreement, Contractor agrees: a) To bear the risk of concealed, unforeseen or unknown conditions and events, if any, which may be encountered in performing the Contract; and b) That Contractor's bid for the Contract was made with full knowledge of this risk. 2. In agreeing to bear the risk of concealed, unforeseen or unknown conditions and events, Con- tractor understands that concealed, unforeseen or unknown conditions or events shall not excuse Contractor from its obligation to achieve Final Completion of the Work within the Contract Time, and shall not entitle the Contractor to an adjustment of the Contract Sum. 3. If Contractor encounters concealed, unforeseen or unknown conditions or events that may re- quire a change to the design shown in the Contract Documents, Contractor shall immediately notify City's Construction Management Consultant in writing such that City's Construction Man- agement Consultant can determine if a change to the design is required. Contractor shall be liable to City of Carlsbad for any extra costs incurred as the result of Contractor's failure to immediately give such notice. 4. If, as the result of concealed, unforeseen or unknown conditions or events, the City of Carlsbad issues a Change Order or Field Change that changes the design from the design depicted in the Contract Documents, Contractor shall be entitled, subject to compliance with all the provisions of the Contract, to an adjustment of the Contract Sum and/or Contract Time, for the cost and delay resulting from implementing the changes to the design. 5. Contractor shall, as a condition precedent to any adjustment in Contract Sum or Contract Time above, fully comply with the General Provisions (including the timely filing of a Change Order Request and all other requirements for Change Orders Requests and Claims). l'\ • ., Revised 6/15/17 Contract No. 4748 Page 87 of 107 Pages 6-2.18 Notice of Hazardous Waste or Materials Conditions 1. Written notice of hazardous materials condition by Contractor shall be given to the City of Carls- bad promptly, before any of the following conditions are disturbed (except in an emergency as required by Section 10.3 of these General Provisions}, and in no event later than twenty-four (24) hours after first observance, of any (a) material that Contractor believes may be material that is hazardous waste or hazardous material, as defined in Section 25117 of the Health and Safety Code (including, without limitation, asbestos, lead, PCBs, petroleum and related hydrocarbons, and radioactive material) that is required to be removed to a Class I, Class II , or Class Ill disposal site in accordance with provisions of existing law ("hazardous materials"); (b) other material which may present a substantial danger to persons or property exposed thereto in connection with Work at the Site ("other materials"). 2. Except as otherwise provided in the Contract or as required by applicable law, Contractor shall not be required to give any notice for the disturbance or observation of any such hazardous ma- terials or other materials where such matter is disturbed or observed as part of the scope of Work under the Contract (such as hazardous waste or hazardous material investigation, reme- diation or disposal activities which are identified as the subject of Work under the Contract), where Contractor complies with all requirements in the Contract and applicable law respecting such materials. 3. Contractor's written notice of hazardous materials conditions under Section 3.19.1 above shall indicate whether the hazardous materials or other materials were shown or indicated in the Con- tract to be within the scope of Work, and whether the hazardous materials or other materials were brought to the Site by Contractor, its Subcontractors, suppliers, or anyone else for whom Con- tractor is responsible. 4. Contractor shall not be entitled to any adjustment in the Contract Sum or Contract Time regarding claimed hazardous waste or materials if (1) Contractor knew of the existence of such hazardous materials or other materials at the time Contractor submitted its proposal; or (2) Contractor should have known of the existence of such hazardous materials or other materials pursuant to Contrac- tor's due diligence required under Article 10 of the Agreement or Section 3.1 of these General Provisions; or (3) Contractor failed to give the written Notice of Hazardous Materials Conditions within the time required by Section 3.19.1 of these General Provisions. Notwithstanding (1) and (2) above, Contractor may (subject to (3) above) be entitled to adjustment in the Contract Sum or Time regarding claimed hazardous waste or materials if not reasonably discernible from the reports and information provided by City of Carlsbad, other information reasonably available to Contractor, visual observation or reasonable investigation. If the City of Carlsbad determines that conditions do involve hazardous materials or other materials or that change in Contract terms is justified, then the City of Carlsbad will either issue a Request for Proposal or an appropriate Change Order under the procedures described in the Contract. 5. If the City of Carlsbad determines that conditions do not involve hazardous materials or other materials or that no change in Contract terms is justified, the City of Carlsbad shall notify Con- tractor in writing, stating the reasons for its determination. If the City of Carlsbad and Contractor cannot agree on any claimed adjustment in Contract Sum or Contract Time, Contractor shall proceed with the Work and as directed by the City of Carlsbad and may file a claim as provided for in these General Provisions. 6. If the Contractor does not agree to resume work based on a reasonable belief that it is unsafe, or does not agree to resume work under special conditions, the City of Carlsbad may order the disputed portion of work deleted from the Work, or performed by others, or the City of Carlsbad ('\ •+' Revised 6/15/17 Contract No. 4748 Page 88 of 107 Pages may invoke its right to terminate Contractor's right to proceed under the Contract in whole or in part for convenience or for cause as the facts may warrant. If Contractor does not agree with the City of Carlsbad's determination of any adjustment in the Contract Sum or Times as a result, Contractor may make a claim as provided in Section 4.3 of these General Provisions. 6-2.19 Subcontractor Procurement Contractor is responsible to competitively procure all Subcontracted Work in accordance with the applicable provisions of the California Public Contract Code, including, without limitation, Section 20146 and the protections afforded subcontractors by Section 4100, et seq. 6-2.20 Project Meetings. The City's Construction Management Consultant will establish the time and location of Project Meetings. The Contractor's Representative shall attend each Project Meeting. The Project Representative shall be the individual determined under Section 7-6, "The Contractor's Rep- resentative". No separate payment for attendance of the Contractor, the Contractor's Representative or any other employee or subcontractor or subcontractor's employee at these meetings will be made. 6-2.21 Daily Reporting During Prosecution of Work. 1. Prepare a daily construction report recording the following information concerning events at Pro- ject site: a) List of subcontractors at Project site. b) List of separate contractors at Project site. c) Approximate count of personnel at Project site. d) Equipment at Project site. e) Material deliveries. f) High and low temperatures and general weather conditions, including presence of rain or Snow g) Accidents. h) Meetings and significant decisions. i) Unusual events (see special reports). j) Stoppages, delays, shortages, and losses. k) Meter readings and similar recordings. I) Emergency procedures. m) Orders and requests of authorities having jurisdiction. n) Change Orders received and implemented. o) Construction Change Directives received and implemented. p) Services connected and disconnected. q) Equipment or system tests and startups. r) Partial completions and occupancies. s) Substantial Completions authorized. 2. Daily labor sign in sheet logs and construction progress report shall be submitted to the Construction Manager on a daily basis. Copies of the previous day's reports must be submitted by 9 am of the following Workday. In the event the Contractor fails to provide a daily sign in log and/or construction progress report, the City may impose damages against the Contractor in the amount of fifty dollars ($50.00) for each log/report and deduct from the Contractor's payment re- quest, for each Day the Contractor does not provide the documentation. 3. Material Location Reports: At weekly intervals, prepare and submit a comprehensive list of materials delivered to and stored at Project site. List shall be cumulative, showing materials pre- viously reported plus items recently delivered. Include with list a statement of progress on and ,, •+f Revised 6/15/17 Contract No. 4748 Page 89 of 107 Pages delivery dates for materials or items of equipment fabricated or stored away from Project site. Indicate the following categories for stored materials: a) Material stored prior to previous report and remaining in storage. b) Material stored prior to previous report and since removed from storage and installed. c) Material stored following previous report and remaining in storage. 4. Site Condition Reports: Immediately on discovery of a difference between site conditions and the Contract Documents, prepare and submit a detailed report. Submit with a Request for Information. Include a detailed description of the differing conditions, together with recommendations for chang- ing the Contract Documents. 6-2.22 Special Reports 1. General: Submit special reports directly to Owner within one day(s) of an occurrence. Distribute copies of report to parties affected by the occurrence. 2. Reporting Unusual Events: When an event of an unusual and significant nature occurs at Pro- ject site, whether or not related directly to the Work, prepare and submit a special report. List chain of events, persons participating, response by Contractor's personnel, evaluation of results or effects, and similar pertinent information. Advise Owner in advance when these events are known or predictable. 6-3 SUSPENSION OF WORK. 6-3.1 General. The Work may be suspended in whole or in part when determined by the Engineer that the suspension is necessary in the interest of the Agency. The Contractor shall comply immedi- ately with any written order of the Engineer. Such suspension shall be without liability to the Contractor on the part of the Agency except as otherwise specified in Section 6-6.3. 6-3.2 Archaeological and Paleontological Discoveries. If discovery is made of items of archaeo- logical or paleontological interest, the Contractor shall immediately cease excavation in the area of discovery and shall not continue until ordered by the Engineer. When resumed, excavation operations within the area of discovery shall be as directed by the Engineer. Discoveries which may be encountered may include, but are not limited to, dwelling sites, stone im- plements or other artifacts, animal bones, human bones, and fossils. If such an evert occurs, the Contractor shall be entitled to an extension of time and may also be entitled to compensation in ac- cordance with the provisions of Section 6-6. 6-4 DEFAULT BY CONTRACTOR. If the Contractor fails to begin delivery of material and equip- ment, to commence the Work within the time specified, to maintain the rate of delivery of material, to execute the Work in the manner and at such locations as specified, or fails to maintain the Work schedule which will insure the Agency's interest, or, if the Contractor is not carrying out the intent of the Contract, the Agency may serve written notice upon the Contractor and the Surety on its Faithful Performance Bond demanding satisfactory compliance with the Contract. The Contract may be canceled by the Board without liability for damage, when in the Board's opinion the Contractor is not complying in good faith, has become insolvent, or has assigned or subcontracted any part of the Work without the Board's consent. In the event of such cancellation, the Contractor will be paid the actual amount due based on Contract Unit Prices or lump sums bid and the quantity of the Work completed at the time of cancellation, less damages caused to the Agency by acts of the Con- tractor. The Contractor, in having tendered a Bid, shall be deemed to have waived any and all claims (.'\ •+;' Revised 6/15/17 Contract No. 4748 Page 90 of 107 Pages for damages because of cancellation of Contract for any such reason . If the Agency declares the Contract canceled for any of the above reasons, written notice to that effect shall be served upon the Surety. The Surety shall, within five (5) days, assume control and perform the Work as successor to the Contractor. If the Surety assumes any part of the Work, it shall take the Contractor's place in all respects for that part and shall be paid by the Agency for all work performed by it in accordance with the Contract. If the Surety assumes the entire Contract, all money due the Contractor at the time of its default shall be payable to the Surety as the Work progresses, subject to the terms of the Contract. If the Surety does not assume control and perform the Work within 5 days after receiving notice of cancellation, or fails to continue to comply, the Agency may exclude the Surety from the premises. The Agency may then take possession of all material and equipment and complete the Work by Agency forces, by letting the unfinished Work to another Contractor, or by a combination of such methods. In any event, the cost of completing the Work shall be charged against the Contractor and its Surety and may be deducted from any money due or becoming due from the Agency. If the sums due under the Contract are insufficient for completion, the Contractor or Surety shall pay to the Agency within 5 days after the completion, all costs in excess of the sums due. The provisions of this section shall be in addition to all other rights and remedies available to the Agency under law. 6-5 TERMINATION OF CONTRACT. The Board may terminate the Contract at its own discretion or when conditions encountered during the Work make it impossible or impracticable to proceed, or when the Agency is prevented from proceeding with the Contract by act of God, by law, or by official action of a public authority. 6-6 DELAYS AND EXTENSIONS OF TIME. 6-6.1 General. If delays are caused by unforeseen events beyond the control of the Contractor, such delays will entitle the Contractor to an extension of time as provided herein, but the Contractor will not be entitled to damages or additional payment due to such delays, except as provided in 6-6.3. Such unforeseen events may include war, government regulations, labor disputes, strikes, fires, floods, ad- verse weather or elements necessitating cessation of work, inability to obtain materials, labor or equip- ment, required extra work, or other specific events as may be further described in the Specifications. No extension of time will be granted for a delay caused by the Contractor's inability to obtain materials unless the Contractor furnishes to the Engineer documentary proof. the proof must be provided in a timely manner in accordance with the sequence of the Contractor's operations and the approved con- struction schedule. If delays beyond the Contractor's control are caused by events other than those mentioned above, the Engineer may deem an extension of time to be in the best interests of the Agency. The Contractor will not be entitled to damages or additional payment due to such delays, except as provided in Section 6-6.3. If delays beyond the Contractor's control are caused solely by action or inaction by the Agency, such delays will entitle the Contractor to an extension of time as provided in Section 6-6.2. 6-6.2 Extensions of Time. Extensions of time, when granted, will be based upon the effect of delays to the Work. They will not be granted for noncontrolling delays to minor portions of the Work unless it can be shown that such delays did or will delay the progress of the Work. ,, •+; Revised 6/15/17 Contract No. 4748 Page 91 of 107 Pages 6-6.3 Payment for Delays to Contractor. The Contractor will be compensated for damages in- curred due to delays for which the Agency is responsible. Such actual costs will be determined by the Engineer. The Agency will not be liable for damages which the Contractor could have avoided by any reasonable means, such as judicious handling of forces, equipment, or plant. The determination of what damages the Contractor could have avoided will be made by the Engineer. 6-6.4 Written Notice and Report. The Contractor shall provide written notice to the Engineer within two hours of the beginning of any period that the Contractor has placed any workers or equipment on standby for any reason that the Contractor has determined to be caused by the Agency or by any organization that the Agency may otherwise be obligated by. The Contractor shall provide continuing daily written notice to the Engineer, each working day, throughout the duration of such period of delay. The initial and continuing written notices shall include the classification of each workman and super- visor and the make and model of each piece of equipment placed on standby, the cumulative duration of the standby, the Contractor's opinion of the cause of the delay and a cogent explanation of why the Contractor could not avoid the delay by reasonable means. Should the Contractor fail to provide the notice(s) required by this section the Contractor agrees that no delay has occurred and that it will not submit any claim(s) therefore. 6-7 TIME OF COMPLETION. 6-7.1 General. The Contractor shall complete the Work within the time set forth in the Contract. The Contractor shall diligently prosecute the work to completion within 4 months (85 working days) after the starting date specified in the Notice to Proceed. 6-7.2 Working Day. A working day is any day within the period between the start of the Contract time as defined in Section 6-1 and the date provided for completion, or upon field acceptance by the Engineer for all work provided for in the Contract, whichever occurs first, other than: 1. Saturday, 2. Sunday, 3. any day designated as a holiday by the Agency, 4. any other day designated as a holiday in a Master Labor Agreement entered into by the Contractor or on behalf of the Contractor as an eligible member of a contractor association, 5. any day the Contractor is prevented from working at the beginning of the workday for cause as defined in Section 6-6.1 , 6. any day the Contractor is prevented from working during the first 5 hours with at least 60 percent of the normal work force for cause as defined in Section 6-6.1. Unless otherwise approved in writing by the Engineer, the hours of work shall be between the hours of 7:00 a.m. and 4:00 p.m. on Mondays through Thursdays, excluding Agency holidays. The Contrac- tor shall obtain the written approval of the Engineer if the Contractor desires to work outside said hours or at any time during weekends and/or holidays. This written permission must be obtained at least 48 hours prior to such work. The Engineer may approve work outside the hours and/or days stated herein when, in his/her sole opinion, such work conducted by the Contractor is beneficial to the best interests of the Agency. The Contractor shall pay the inspection costs of such work. The Contractor shall incorporate the dates, areas and types of work prohibited in this section in the l' • .., Revised 6/15/17 Contract No. 4748 Page 92 of 107 Pages Construction Schedule required by Section 6.1 . No additional payment, adjustment of bid prices or adjustment of contract time of completion will be allowed as a consequence of the prohibition of work being performed within the dates, areas and/or types of work prohibited in this section. 6-7.3 Contract Time Accounting. The Engineer will make a daily determination of each working day to be charged against the Contract time. These determinations will be discussed and the Con- tractor will be furnished a periodic statement showing allowable number of working days of Contract time, as adjusted, at the beginning of the reporting period. The statement will also indicate the number of working days charged during the reporting period and the number of working days of Contract time remaining. If the Contractor does not agree with the statement, it shall file a written protest within 15 days after receipt, setting forth the facts of the protest. Otherwise, the statement will be deemed to have been accepted. 6-8 COMPLETION, ACCEPTANCE, AND WARRANTY. The Work will be inspected by the City for acceptance upon receipt of the Contractor's written assertion that the Work has been completed. The City will not accept the Work or any portion of the Work before all of the Work is completed and all outstanding deficiencies that may exist are corrected by the Contractor and the City is satisfied that all the materials and workmanship, and all other features of the Work, meet the requirements of all of the specifications for the Work. The only exception to this requirement is some unfinished work may be provisionally accepted if it still allows a temporary certificate of occupancy to be issued for Phase 1, 2 or 3. 6-8.1 Beneficial Occupancy The City reserves the right, at its option and convenience, to occupy or otherwise make use of any part of the Construction Work at any time prior to Substantial Completion or Final Completion upon ten (10) days' notice to Contractor. Such occupancy or use is herein referred to as "Beneficial Occu- pancy." Beneficial Occupancy or Temporary Occupancy, shall be subject to the following conditions: 1. City's Construction Management Consultant will inspect the portion of the Project to be benefi- cially occupied and prepare a list of items to be completed or corrected. Contractor shall obtain approval from City Building Inspector for Beneficial Occupancy. 2. Beneficial Occupancy by City of Carlsbad shall not be construed by Contractor as an acceptance by City of Carlsbad of that portion of the Construction Work which is to be occupied. 3. Beneficial Occupancy by City of Carlsbad shall not constitute a waiver of existing claims of City of Carlsbad or Contractor against each other. 4. Contractor shall provide, in the areas beneficially occupied and on a twenty-four (24) hour and seven (7) day a week basis as required, utility services, heating, and cooling for systems which are in operable condition at the time of Beneficial Occupancy. All responsibility for the operation and maintenance of equipment shall remain with Contractor while the equipment is so operated. Contractor shall submit to City of Carlsbad an itemized list of each piece of equipment so oper- ated with the date operation commences. 5. The Contractor's guarantee to repair will commence upon the date approved by the City for Ben- eficial Occupancy except that the guarantee to repair periods for that part of equipment or sys- tems that serve portions of the Work for which City has not taken Beneficial Occupancy shall not commence until the City has taken Beneficial Occupancy for that portion of the Work or has issued a Certificate of Substantial Completion with respect to the entire Project. The City will pay ,, •+' Revised 6/15/17 Contract No. 4748 Page 93 of 107 Pages all normal operating and maintenance costs resulting from its use of equipment in areas benefi- cially occupied. 6. The City will pay all utility costs that arise out of the Beneficial Occupancy. 7. Contractor shall not be responsible for providing security in areas beneficially occupied. 8. The City will use its best efforts to prevent its Beneficial Occupancy from interfering with the conduct of Contractor's remaining Construction Work. 9. Contractor shall not be required to repair damage caused by the City in its Beneficial Occupancy. 10. There shall be no added cost to the City due to Beneficial Occupancy. 11. Contractor shall continue to maintain all insurance required by the Contract in full force and effect. 6-8.2 Substantial Completion 1. "Substantial Completion" means the stage in the progress of the Construction Work, as deter- mined by City's Construction Management Consultant, when the Construction Work is complete and in accordance with the Contract Documents except only for completion of minor items that do not impair City's ability to occupy and fully utilize the Construction Work for its intended pur- pose and a Certificate of Occupancy for the Work has been issued by the City's Building Official. 2. When Contractor gives notice to City's Construction Management Consultant that the Construc- tion Work is substantially complete, unless City's Construction Management Consultant deter- mines that the Construction Work is not sufficiently complete to warrant an inspection to deter- mine Substantial Completion, City's Construction Management Consultant will inspect the Con- struction Work. If the City's Construction Management Consultant determines that the Work is not substantially complete the City's Construction Management Consultant will prepare and give to Contractor a comprehensive list of items to be completed or corrected before establishing Substantial Completion. Contractor shall proceed promptly to complete and correct items on the list. Failure to include an item on such list does not alter the responsibility of Contractor to com- plete all Construction Work in accordance with the Contract Documents. City's Construction Management Consultant will inspect to determine whether the Construction Work is substantially complete. Costs for additional inspection by City's Construction Management Consultant shall be deducted from any monies due and payable to Contractor. 3. When City's Construction Management Consultant determines that the Construction Work is sub- stantially complete, City's Construction Management Consultant will arrange for inspection by the City's Building Official and other officials, as appropriate, for the purpose of issuing a Certificate of Occupancy. After a Certificate of Occupancy has been issued by the City's Building Official, the City's Construction Management Consultant will prepare a Certificate of Substantial Completion, which, when signed by the City, shall establish the date of Substantial Completion and the respon- sibilities of City and Contractor for security, maintenance, utilities, insurance, and damage to the Construction Work. The City's Construction Management Consultant will prepare and furnish to the Contractor a comprehensive "punch list" of items to be completed or corrected prior to Final Completion. 4. Unless otherwise provided in the Certificate of Substantial Completion, the guarantee to repair period for the Construction Work covered by the Certificate of Substantial Completion, shall com ,, •+;' Revised 6/15/17 Contract No. 4748 Page 94 of 107 Pages mence on the date of Substantial Completion of the Construction Work except that Substantial Completion shall not commence the guarantee to repair period for any equipment or systems that: a) Are not operational (equipment or systems shall not be considered operational if they cannot be used to provide the intended service); b) Are not accepted by the City; or c) Are part of the Construction Work that is not yet Substantially Complete. The guarantee to repair period for equipment or systems operational and accepted subsequent to Substantial Completion will begin on the date of their written acceptance by the City. 5. The daily rate included in the Agreement and specifically identified as the rate to be paid to Con- tractor for Compensable Delays shall not apply to any delays occurring after the Construction Work is substantially completed. 6-8.3 Final Completion, Final Payment and Release of Retention 1. Upon receipt of notice from Contractor that the Work is ready for final inspection, City's Construc- tion Management Consultant will make such inspection. Final Completion shall be when City's Construction Management Consultant determines that the Work is fully completed and in accord- ance with the Contract Documents, including without limitation, satisfaction of all "punch list" items, and determines that a Certificate of Occupancy has been issued by the City's Building Official. The City will file a Notice of Completion within fifteen (15) days after Final Completion. After receipt of the final Application for Payment, if City's Construction Management Consultant determines that Final Completion has occurred, City's Construction Management Consultant will issue the final Certificate for Payment. 2. Final payment and retention shall be released to Contractor, as set forth above, after: a) Contractor submits the final Application for Payment and all submittals required above; b) Contractor submits all guarantees and warranties procured by Contractor from Subcontrac- tors, all operating manuals for equipment installed in the Project, as-built documents, and all other submittals required by the Contract Documents; and c) City's Construction Management Consultant issues the final Certificate for Payment. 3. Final payment shall be paid not more than ten (10) days after City's Construction Management Consultant issues the final Certificate for Payment. Retention shall be released to Contractor thirty-five (35) days after the Notice of Completion is filed by the county. 4. Acceptance of final payment by Contractor shall constitute a waiver of all claims related to the Work, except claims for retention and claims previously made in writing and identified by Con- tractor as unsettled at the time of the final Application for Payment. 5. Upon project completion and notice by the Engineer, the City may accept the completed project Work. Upon the City's acceptance of the Work the Engineer will cause a "Notice of Completion" to be filed in the office of the San Diego County Recorder. The date of recordation shall be the date of completion of the Work. 6. The completed project work shall be warranted for two (2) years after official notice from City's Construction Management Consultant that project work has been fully completed in accordance with the Contract Documents, including without limitation, satisfaction of all "punch list" items, and the City's Building Official has signed off the permit card. Any faulty work or materials dis- covered during the warranty periods shall be repaired or replaced by the Contractor, at its ex- pense. Twenty-five percent of the faithful performance bond shall be retained as a warranty bond l' •+;' Revised 6/15/17 Contract No. 4748 Page 95 of 107 Pages for the warranty periods. The Contractor shall replace or repair any such defective work in a manner satisfactory to the Engineer, after notice to do so from the Engineer, and within the time specified in the notice. If the Contractor fails to make such replacement or repairs within the time specified in the notice, the Agency may perform this work and the Contractor's sureties shall be liable for the cost thereof. 6-9 LIQUIDATED DAMAGES. Failure of the Contractor to complete the Work within the time al- lowed will result in damages being sustained by the Agency. For each consecutive calendar day in excess of the time specified for completion of Work, as adjusted in accordance with Section 6-6, the Contractor shall pay the Agency, or have withheld monies due it, the sum of one thousand dollars ($1 ,000.00) Such sum is liquidated damages and shall not be construed as a penalty, and may be deducted from payments due the Contractor if such delay occurs. Execution of the Contract shall constitute agreement by the Agency and Contractor that $1 ,000 per day is the minimum value of costs and actual damages caused by the Contractor to complete the Work within the allotted time. Any progress payments made after the specified completion date shall not constitute a waiver of this paragraph or of any damages. 6-10 USE OF IMPROVEMENT DURING CONSTRUCTION. The Agency reserves the right to take over and utilize all or part of any completed facility or appurtenance. The Contractor will be notified in writing in advance of such action. Such action by the Agency will relieve the Contractor of responsibility for injury or damage to said completed portions of the improvement resulting from use by public traffic or from the action of the elements or from any other cause, except Contractor operations or negli- gence. The Contractor will not be required to reclean such portions of the improvement before field acceptance, except for cleanup made necessary by its operations. Nothing in this section shall be construed as relieving the Contractor from full responsibility for correcting defective work or materials. In the event the Agency exercises its right to place into service and utilize all or part of any completed facility or appurtenance, the Agency will assume the responsibility and liability for injury to persons or property resulting from the utilization of the facility or appurtenance so placed into service, except for any such injury to persons or property caused by any willful or negligent act or omission by the Con- tractor, Subcontractor, their officers, employees, or agents. {'\ •+;' Revised 6/15/17 Contract No. 4748 Page 96 of 107 Pages SECTION 7 -RESPONSIBILITIES OF THE CONTRACTOR 7-1 CONTRACTOR'S EQUIPMENT AND FACILITIES. The Contractor shall furnish and maintain in good condition all equipment and facilities as required for the proper execution and inspection of the Work. Such equipment and facilities shall meet all requirements of applicable ordinances and laws. 7-2 LABOR. 7-2.1 General. Only competent workers shall be employed on the Work. Any person employed who is found to be incompetent, intemperate, troublesome, disorderly, or otherwise objectionable, or who fails or refuses to perform work properly and acceptably, shall be immediately removed from the Work by the Contractor and not be reemployed on the Work. 7-2.2 Laws. The Contractor, its agents, and employees shall be bound by and comply with applica- ble provisions of the Labor Code and Federal, State, and local laws related to labor. The Contractor shall strictly adhere to the provisions of the Labor Code regarding minimum wages; the 8-hour day and 40-hour week; overtime; Saturday, Sunday, and holiday work; and nondiscrimina- tion because of race, color, national origin, sex, or religion. The Contractor shall forfeit to the Agency the penalties prescribed in the Labor Code for violations. In accordance with the Labor Code, the Board has on file and will publish a schedule of prevailing wage rates for the types of work to be done under the Contract. The Contractor shall not pay less than these rates. Each worker shall be paid subsistence and travel as required by the collective bargaining agreement on file with the State of California Department of Industrial Relations. The Contractor's attention is directed to Section 1776 of the Labor Code which imposes responsibility upon the Contractor for the maintenance, certification, and availability for inspection of such records for all persons employed by the Contractor or Subcontractor in connection with the project. The Con- tractor shall agree through the Contract to comply with this Section and the remaining provisions of the Labor Code. 7-3 LIABILITY INSURANCE. Insurance shall be required as specified in section 10 of the Public Works Contract. The cost of this insurance shall be included in the Contractor's Bid. 7-4 WORKERS' COMPENSATION INSURANCE. Before execution of the Contract by the Board, the Contractor shall file with the Engineer the following signed certification: "I am aware of the provisions of Section 3700 of the Labor Code which re- quire every employer to be insured against liability for workers' compensa- tion or to undertake self-insurance in accordance with the provisions of that code, and I will comply with such provisions before commencing the perfor- mance of the work of this contract." The Contractor shall also comply with Section 3800 of the Labor Code by securing, paying for, and maintaining in full force and effect for the duration of the contract, complete Workers' Compensation Insurance, and shall furnish a Certificate of Insurance to the Engineer before execution of the Contract. ,, •ti' Revised 6/15/17 Contract No. 4748 Page 97 of 107 Pages The Agency, its officers, or employees, will not be responsible for any claims in law or equity occa- sioned by failure of the Contractor to comply with this paragraph. All compensation insurance policies shall bear an endorsement or shall have attached a rider whereby it is provided that, in the event of expiration or proposed cancellation of such policies for any reason whatsoever, the Agency shall be notified by registered mail not less than 30 days before expiration or cancellation is effective. All insurance is to be placed with insurers that are admitted and authorized to conduct business in the state of California and are listed in the official publication of the Department of Insurance of the State of California. Policies issued by the State Compensation Fund meet the requirement for workers' com- pensation insurance. 7-5 PERMITS. Except as specified herein the Contractor will obtain, at no cost to the Contractor all City of Carlsbad building permits necessary to perform work for this contract on Agency property, streets, or other rights-of-way. Contractor shall not begin work until all permits incidental to the work are obtained. The Contractor shall obtain and pay for all permits for the disposal of all materials re- moved from the project. The cost of said permit(s) shall be included in the price bid for the appropriate bid item and no additional compensation will be allowed therefore. The Contractor shall obtain and pay for all costs incurred for permits necessitated by its operations such as, but not limited to, those permits required for night work, overload, blasting, and demolition. For private contracts, the Contrac- tor shall obtain all permits incidental to the Work or made necessary by its operations, and pay all costs incurred by the permit requirements. The Contractor shall pay all business taxes or license fees that are required for the work. 7-5.1 Resource Agency Permits. Not used. 7-6 THE CONTRACTOR'S REPRESENTATIVE. Before starting work, the Contractor shall desig- nate in writing a representative who shall have complete authority to act for it. An alternative repre- sentative may be designated as well. The representative or alternate shall be present at the Work site whenever work is in progress or whenever actions of the elements necessitate its presence to take measures necessary to protect the Work, persons, or property. Any order or communication given to this representative shall be deemed delivered to the Contractor. A joint venture shall designate only one representative and alternate. In the absence of the Contractor or its representative, instructions or directions may be given by the Engineer to the superintendent or person ln charge of the specific work to which the order applies. Such order shall be complied with promptly and referred to the Con- tractor or its representative. In order to communicate with the Agency, the Contractor's representative, superintendent, or person in charge of specific work shall be able to speak, read, and write the English language. 7-7 COOPERATION AND COLLATERAL WORK. The Contractor shall be responsible for ascer- taining the nature and extent of any simultaneous, collateral, and essential work by others. The Agency, its workers and contractors and others, shall have the right to operate within or adjacent to the Work site during the performance of such work. The Agency, the Contractor, and each of such workers, contractors and others, shall coordinate their operations and cooperate to minimize interference. The Contractor shall include in its Bid all costs involved as a result of coordinating its work with others. the Contractor will not be entitled to additional compensation from the Agency for damages resulting ,, • ., Revised 6/15/17 Contract No. 4748 Page 98 of 107 Pages from such simultaneous, collateral, and essential work. If necessary to avoid or minimize such damage or delay, the Contractor shall redeploy its work force to other parts of the Work. Should the Contractor be delayed by the Agency, and such delay could not have been reasonably foreseen or prevented by the Contractor, the Engineer will determine the extent of the delay, the effect on the project, and any extension of time. 7-7.1 Coordination. The Contractor shall coordinate and cooperate with all the utility companies dur- ing the relocation or construction of their lines. The Contractor may be granted a time extension if, in the opinion of the Engineer, a delay is caused by the utility company. No additional compensation will be made to the Contractor for any such delay. 7-8 PROJECT SITE MAINTENANCE. 7-8.1 Cleanup and Dust Control. Throughout all phases of construction, including suspension of work, and until the final acceptance, the Contractor shall keep the site clean and free from rubbish and debris. The Contractor shall also abate dust nuisance by cleaning, sweeping and sprinkling with water, or other means as necessary. Materials and equipment shall be removed from the site as soon as they are no longer necessary. Before the final inspection, the site shall be cleared of equipment, unused materials, and rubbish so as to present a satisfactory clean and neat appearance. All cleanup costs shall be included in the Contractor's Bid. Care shall be taken to prevent spillage on haul routes. Any such spillage shall be removed immediately and the area cleaned. Failure of the Contractor to comply with the Engineer's cleanup orders may result in an order to sus- pend work until the condition is corrected. No additional compensation will be allowed as a result of such suspension. The Contractor shall conduct effective cleanup and dust control throughout the duration of the Con- tract. The Engineer may require increased levels of cleanup and dust control that, in his/her sole discretion, are necessary to preserve the health, safety and welfare of the public. Cleanup and dust control shall be considered incidental to the items of work that they are associated with and no addi- tional payment will be made therefore. 7-8.2 Air Pollution Control. The Contractor shall not discharge smoke, dust, or any other air con- taminants into the atmosphere in such quantity as will violate the regulations of any legally constituted authority. 7-8.3 Vermin Control. At the time of acceptance, structures entirely constructed under the Contract shall be free of rodents, insects, vermin, and pests. Necessary extermination work shall be arranged and paid for by the Contractor as part of the Work within the Contract time and shall be performed by a licensed exterminator in accordance with requirements of governing authorities. The Contractor shall be liable for injury to persons or property and responsible for the elimination of offensive odors result- ing from extermination operations. 7-8.4 Sanitation. The Contractor shall provide and maintain enclosed toilets for the use of employ- ees engaged in the Work. These accommodations shall be maintained in a neat and sanitary condi- tion. They shall also comply with all applicable laws, ordinances, and regulations pertaining to public health and sanitation of dwellings and camps. {'\ • ., Revised 6/15/17 Contract No. ~ Page 99 of 107 Pages Wastewater shall not be interrupted. Should the Contractor disrupt existing sewer facilities, sewage shall be conveyed in closed conduits and disposed of in a sanitary sewer system. Sewage shall not be permitted to flow in trenches or be covered by backfill. 7-8.5 Temporary Light, Power, and Water. The Contractor shall furnish, install, maintain, and re- move all temporary light, power, and water at its own expense. These include piping, wiring, lamps, and other equipment necessary for the Work. The Contractor shall not draw water from any fire hydrant (except to extinguish a fire), without obtaining permission from the water agency concerned. The Contractor shall obtain a construction meter for water used for the construction, plant establishment, maintenance, cleanup, testing and all other work requiring water related to this contract. The Con- tractor shall contact the appropriate water agency for requirements. The Contractor shall pay all costs of temporary light, power and water including hookup, service, meter and any, and all, other charges, deposits and/or fees therefore. Said costs shall be considered incidental to the items of work that they are associated with and no additional payment will be made therefore. 7-8.6 Water Pollution Control. Not used 7-8.7 Drainage Control. Not used 7-8.8 Noise Control. All internal combustion engines used in the construction shall be equipped with mufflers in good repair when in use on the project with special attention to the City Noise Control Ordinance, Carlsbad Municipal Code Chapter 8.48. 7-9 PROTECTION AND RESTORATION OF EXISTING IMPROVEMENTS. The Contractor shall be responsible for the protection of public and private property adjacent to the Work and shall exercise due caution to avoid damage to such property. The Contractor shall repair or replace any site amenities and/or building finishes which are damaged or removed as a result of its operations. Repairs and replacements shall be at least equal to existing improvements and shall match them in finish and dimension. All costs to the Contractor for protecting, removing, and restoring existing site amenities and/or build- ing finishes shall be included in the Bid. 7-10 PUBLIC CONVENIENCE AND SAFETY. 7-10.1 Traffic and Access. The Contractor's operations shall cause no unnecessary inconvenience. The access rights of the public shall be considered at all times. Unless otherwise authorized, traffic shall be permitted to pass through the Work, or an approved detour shall be provided. Safe and adequate pedestrian and vehicular access shall be provided and maintained to fire hydrants; commercial and industrial establishments; churches, schools and parking lots; service stations and motels; hospitals; police and fire stations; and establishments of similar nature. Access to these facil- ities shall be continuous and unobstructed unless otherwise approved by the Engineer. Safe and adequate pedestrian zones and public transportation stops, as well as pedestrian crossings of the Work at intervals not exceeding 90 m (300 feet), shall be maintained unless otherwise approved by the Engineer. The Contractor shall cooperate with the various parties involved in the delivery of mail and the collec- tion and removal of trash and garbage to maintain existing schedules for these services. r. •ff Revised 6/15/17 Contract No. 4748 Page 100 of 107 Pages The Contractor shall schedule the work so as to prevent damage by all traffic, including but not limited to mail delivery. The Contractor shall not schedule work so as to conflict with trash pickup. The trash hauling schedule can be obtained by calling the City's contracted waste disposal company, Coast Waste Management at 929-9417. The Contractor shall include in its Bid all costs for the above requirements. 7-10.2 Storage of Equipment and Materials in Public Streets. Construction materials shall not be stored in roadways after unloading. All materials or equipment not installed or used in construction after unloading shall be stored elsewhere by the Contractor at its expense unless authorized additional storage time. Construction equipment shall not be stored at the Work site before its actual use on the Work nor for more than 5 days after it is no longer needed. Time necessary for repair or assembly of equipment may be authorized by the Engineer. 7-10.3 Street Closures, Detours, Barricades. Not used 7-10.3.1 Construction Area Signs and Control Devices. All construction signs and control devices shall be maintained throughout the duration of work in good order. The City's Construction Manage- ment Consultant may require additional signage if deemed necessary. 7-10.3.2 Maintaining Traffic. Not used. 7-10.3.3 Traffic Control System for Lane Closure. Not used. 7-10.3.4 Traffic Control for Permanent and Temporary Traffic Striping. Not used. 7-10.3.5 Temporary Pavement Delineation. Not used 7-10.3.6 Preparation of New, or Modifications and Additions to Existing, Traffic Control Plan Sheets. Not used. 7-10.3.7 Payment. The Contractor shall prepare and install construction signs and control devices and shall furnish all labor and materials to maintain, replace and remove them as incidental expenses to the work with which they are associated and no other compensation will be allowed therefore. 7-10.4 Safety. 7-10.4.1 Safety Orders. The Contractor shall have at the Work site, copies or suitable extracts of: Construction Safety Orders and General Industry Safety Orders issued by the State Division of Indus- trial Safety. The Contractor shall comply with provisions of these and all other applicable laws, ordi- nances, and regulations. Payment for performing all work necessary to provide safety measures shall be included in the prices bid for each category of work. 7-10.4.2 Use of Explosives. Not used. 7-10.4.3 Special Hazardous Substances and Processes. Materials that contain hazardous sub- stances or mixtures may be required on the Work. A Material Safety Data Sheet as described in ('\ •+;' Revised 6/15/17 Contract No. 4748 Page 101 of 107 Pages Section 5194 of the California Code of Regulations shall be requested by the Contractor from the manufacturer of any hazardous products used. Material usage shall be accomplished with strict adherence to California Division of Industrial Safety requirements and all manufacturer warnings and application instructions listed on the Material Safety Data Sheet and on the product container label. The Contractor shall notify the Engineer if a specified product cannot be used under safe conditions. 7-10.4.4 Confined Spaces. 1. Confined Space Entry Program. The Contractor shall be responsible for implementing, adminis- tering and maintaining a confined space entry program (CSEP) in accordance with Sections 5156, 5157 and 5158, Title 8, CCR. Prior to starting the Work, the Contractor shall prepare and submit its comprehensive CSEP to the Engineer. The CSEP shall address all potential physical and environmental hazards and contain procedures for safe entry into confined spaces, including, but not limited to the following: a) Training of personnel b) Purging and cleaning the space of materials and residue c) Potential isolation and control of energy and material inflow d} Controlled access to the space e) Atmospheric testing of the space f) Ventilation of the space g) Special hazards consideration h} Personal protective equipment i) Rescue plan provisions The Contractor's submittal shall include the names of its personnel, including subcontractor per- sonnel, assigned to the project who will have CSEP responsibilities, their CSEP training, and their specific assignment and responsibility in carrying out the CSEP. 2. Permit-Required Confined Spaces. Entry into permit-required confined spaces as defined in Sec- tion 5157, Title 8, CCR may be required as a part of the Work. All manholes, tanks, vaults, pipe- lines, excavations, or other enclosed or partially enclosed spaces shall be considered permit-re- quired confined spaces until the pre-entry procedures demonstrate otherwise. The Contractor shall implement a permit space program prior to performing any work in a permit-required confined space. A copy of the permit shall be available at all times for review by Contractor and Agency personnel at the Work site. 3. Payment. Payment for implementing, administering, and providing all equipment and personnel to perform the CSEP shall be included in the bid items for which the CSEP is required. 7-10.4.5 Safety and Protection of Workers and Public. The Contractor shall take all necessary precautions for the safety of employees on the work and shall comply with all applicable provisions of Federal, State and Municipal safety laws and building codes to prevent accidents or injury to persons on, about, or adjacent to the premises where the work is being performed. The Contractor shall erect and properly maintain at all times, as required by the conditions and progress of the work, all neces- sary safeguards for the protection of workers and public, and shall use danger signs warning against hazards created by such features of construction as protruding nails, hoists, well holes, and falling materials. ,., •+;' Revised 6/15/17 Contract No. 4748 Page 102 of 107 Pages 7-11 PATENT FEES OR ROYALTIES. The Contractor shall absorb in its Bid the patent fees or royalties on any patented article or process furnished or used in the Work. The Contractor shall in- demnify and hold the Agency harmless from any legal acti on that may be brought for infringement of patents. 7-12 ADVERTISING. The names, addresses and specialties of Contractors, Subcontractors, archi- tects, or engineers may be displayed on removable signs. The size and location shall be subject to the Engineer's approval. Commercial advertising matter shall not be attached to or painted on the surfaces of build ings, fences, canopies, or barricades. 7-13 LAWS TO BE OBSERVED. The Contractor shall keep fully informed of State and National laws and County and Municipal ordinances and regulations which in any manner affect those em- ployed in the Work or the materials used in the Work or in any way affect the conduct of the Work. The Contractor shall at all times observe and comply with such laws, ordinances, and regulations. 7-14 ANTITRUST CLAIMS. Section 7103.5 of the Public Contract Code provides: "In entering into a public works contract or a subcontract to supply goods, services, or materials pur- suant to a public works contract, the contractor or subcontractor offers and agrees to assign to the awarding body all rights, title, and interest in and to all causes of action it may have under Section 4 of the Clayton Act (15 U.S.C. Sec 15) or Cartwright Act (Chapter 2 [commencing with Section 16700) of Part 2 of Division 7 of the Business and Professions Code), arising from purchases of goods, ser- vices, or materials pursuant to the public works contract or subcontract. The assignment shall be made and become effective at the time the awarding body tenders final payment to the contractor, without further acknowledgment of the parties." ,, •+; Revised 6/15/17 Contract No. 4748 Page 103 of 107 Pages SECTION 8 -MEASUREMENT AND PAYMENT 8-1 MEASUREMENT OF QUANTITIES FOR UNIT PRICE WORK. 8-1.1 General. Unless otherwise provided in Specifications, volumetric quantities shall be the prod- uct of the mean area of vertical or horizontal sections and the intervening horizontal or vertical dimen- sion. 8-1.2 Methods of Measurement. Materials and items of work which are to be paid for on basis of measurement shall be measured in accordance with methods stipulated in the particular sections in- volved. 8-1.3 Certified Weights. Not used 8-1.4 Units of Measurement. The system of measure for this contract shall be the U.S. Standard Measures. 8-2 LUMP SUM WORK. Items for which quantities are indicated "Lump Sum", "L.S.", or "Job", shall be paid for at the price indicated in the Bid. Such payment shall be full compensation for the items of work and all work appurtenant thereto. When required by the Specifications or requested by the City's Construction Management Consultant, the Contractor shall submit to the City's Construction Management Consultant within 15 days after award of Contract, a detailed schedule, to be used only as a basis for determining progress payments on a lump sum contract or designated lump sum bid item. This schedule shall equal the lump sum bid and shall be in such form and sufficiently detailed as to satisfy the City's Construction Management Consultant that it correctly represents a reasonable apportionment of the lump sum. 8-3 PAYMENT 8-3.1 General. Lump sum prices to be paid shall be full compensation for the items of work and all appurtenant work, including furnishing all materials, labor, equipment, tools, and incidentals. Payment will not be made for materials wasted or disposed of in a manner not called for under the Contract. This includes rejected material not unloaded from vehicles, material rejected after it has been placed, and material placed outside of the Plan lines. No compensation will be allowed for dis- posing of rejected or excess material. Payment for work performed or materials furnished under an Assessment Act Contract will be made as provided in particular proceedings or legislative act under which such contract was awarded. Whenever any portion of the Work is performed by the Agency at the Contractor's request, the cost thereof shall be charged against the Contractor, and may be deducted from any amount due or be- coming due from the Agency. Whenever immediate action is required to prevent injury, death, or property damage, and precautions which are the Contractor's responsibility have not been taken and are not reasonably expected to be taken, the Agency may, after reasonable attempt to notify the Contractor, cause such precautions to be taken and shall charge the cost thereof against the Contractor, or may deduct such cost from any {"\ •+' Revised 6/15/17 Contract No. 4748 Page 104 of 107 Pages amount due or becoming due from the Agency. Agency action or inaction under such circumstances shall not be construed as relieving the Contractor or its Surety from liability. Payment shall not relieve the Contractor from its obligations under the Contract; nor shall such pay- ment be construed to be acceptance of any of the Work. Payment shall not be construed as the trans- fer of ownership of any equipment or materials to the Agency. Responsibility of ownership shall remain with the Contractor who shall be obligated to store any fully or partially completed work or structure for which payment has been made; or replace any materials or equipment required to be provided under the Contract which may be damaged, lost, stolen or otherwise degraded in any way prior to acceptance of the Work, except as provided in Section 6-10. Guarantee periods shall not be affected by any payment but shall commence on the date of re- cordation of the "Notice of Completion." If, within the time fixed by law, a properly executed notice to stop payment is filed with the Agency, due to the Contractor's failure to pay for labor or materials used in the Work, all money due for such labor or materials will be withheld from payment to the Contractor in accordance with applicable laws. At the expiration of 35 days from the date of acceptance of the Work by the Board, or as prescribed by law, the amount deducted from the final estimate and retained by the Agency will be paid to the Contractor except such amounts as are required by law to be withheld by properly executed and filed notices to stop payment, or as may be authorized by the Contract to be further retained. 8-3.2 Partial and Final Payment. The Engineer will, after award of Contract, establish a closure date for the purpose of making monthly progress payments. The Contractor may request in writing that such monthly closure date be changed. The Engineer may approve such request when it is com- patible with the Agency's payment procedure. Each month, the Engineer will make an approximate measurement of the work performed to the clo- sure date as basis for making monthly progress payments. The estimated value will be based on contract unit prices, completed change order work and as provided for in Section 9-2 of these General Provisions. Progress payments shall be made no later than thirty (30) calendar days after the closure date. Five (5) working days following the closure date, the Engineer shall complete the detailed pro- gress pay estimate and submit it to the Contractor for the Contractor's information. Should the Con- tractor assert that additional payment is due, the Contractor shall within ten (10) days of receipt of the progress estimate, submit a supplemental payment request to the Engineer with adequate justification supporting the amount of supplemental payment request. Upon receipt of the supplemental payment request, the Engineer shall, as soon as practicable after receipt, determine whether the supplemental payment request is a proper payment request. If the Engineer determines that the supplemental pay- ment request is not proper, then the request shall be returned to the Contractor as soon as practicable, but not later than seven (7) days after receipt. The returned request shall be accompanied by a doc- ument setting forth in writing the reasons why the supplemental payment request was not proper. In conformance with Public Contract Code Section 20104.50, the City shall make payments within thirty (30) days after receipt of an undisputed and properly submitted supplemental payment request from the Contractor. If payment of the undisputed supplemental payment request is not made within thirty (30) days after receipt by the Engineer, then the City shall pay interest to the Contractor equivalent to the legal rate set forth in subdivision (a) of Section 685.010 of the Code of Civil Procedure. From each progress estimate, 5 percent will be deducted and retained by the Agency, and the remain- der less the amount of all previous payments will be paid. ,, •ti' Revised 6/15/17 Contract No. 4748 Page 105 of 107 Pages No progress payment made to the Contractor or its sureties will constitute a waiver of the liquidated damages under 6-9. As provided in Section 22300 of the California Public Contract Code, the Contractor may substitute securities for any monies withheld by the Agency to ensure performance under the Contract. After final inspection, the Engineer will make a Final Payment Estimate and process a corresponding payment. This estimate will be in writing and shall be for the total amount owed the Contractor as determined by the Engineer and shall be itemized by the contract bid item and change order item with quantities and payment amounts and shall show all deductions made or to be made for prior payments and amounts to be deducted under provisions of the contract. All prior estimates and progress pay- ments shall be subject to correction in the Final Payment Estimate. The Contractor shall have 30 calendar days from receipt of the Final Payment Estimate to make written statement disputing any bid item or change order item quantity or payment amount. The Contractor shall provide all documentation at the time of submitting the statement supporting its position. Should the Contractor fail to submit the statement and supporting documentation within the time specified, the Contractor acknowledges that full and final payment has been made for all contract bid items and change order items. If the Contractor submits a written statement with documentation in the aforementioned time, the En- gineer will review the disputed item within 30 calendar days and make any appropriate adjustments on the Final Payment. Remaining disputed quantities or amounts not approved by the Engineer will be subject to resolution as specified in Section 3-5, Disputed Work. The written statement filed by the Contractor shall be in sufficient detail to enable the Engineer to ascertain the basis and amount of said disputed items. The Engineer will consider the merits of the Contractor's claims. It will be the responsibility of the Contractor to furnish within a reasonable time such further information and details as may be required by the Engineer to determine the facts or contentions involved in its claims. Failure to submit such information and details will be sufficient cause for denying payment for the disputed items. 8-3.2.1 Payment for Claims. Except for those final payment items disputed in the written statement required in Section 9-3.2 all claims of any dollar amount shall be submitted in a written statement by the Contractor no later than the date of receipt of the final payment estimate. Those final payment items disputed in the written statement required in Section 9-3.2 shall be submitted no later than 30 days after receipt of the Final Payment estimate. No claim will be considered that was not included in this written statement, nor will any claim be allowed for which written notice or protest is required under any provision of this contract including Sections 3-4 Changed Conditions, 3-5 Disputed Work, 6-6.3 Payment for Delays to Contractor, 6-6.4 Written Notice and Report, or 6-7.3 Contract Time Accounting, unless the Contractor has complied with notice or protest requirements. The claims filed by the Contractor shall be in sufficient detail to enable the Engineer to ascertain the basis and amount of said claims. The Engineer will consider and determine the Contractor's claims and it will be the responsibility of the Contractor to furnish within a reasonable time such further infor- mation and details as may be required by the Engineer to determine the facts or contentions involved in its claims. Failure to submit such information and details will be sufficient cause for denying the claims. Payment for claims shall be processed within 30 calendar days of their resolution for those claims approved by the Engineer. The Contractor shall proceed with informal dispute resolution under Sec- tion 3-5, Disputed Work, for those claims remaining in dispute. {'\ •,r Revised 6/15/17 Contract No. 4748 Page 106 of 107 Pages 8-3.3 Delivered Materials. When provided for in the Specifications, and subject to the limitation and conditions therein, the cost of materials and equipment delivered but not incorporated into the Work will be included in the progress estimate. 8-3.4 Mobilization. When a bid item is included in the Proposal form for mobilization and subject to the conditions and limitations in the Specifications, the costs of work in advance of construction oper- ations and not directly attributable to any specific bid item will be included in the progress estimate. When no such bid item is provided, payment for such costs will be considered to be included in the other items of work. 8-3.4.1 Mobilization and Preparatory Work. The Contract lump-sum price paid for mobilization and preparatory work shall not exceed twenty thousand dollars ($20,000.00) and includes full compensa- tion for furnishing all insurance, bonds, licenses, labor, materials, utilities, tools, equipment and inci- dentals, and for doing all the work involved in mobilization and preparatory work and operations, in- cluding, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidental to preparing to conduct work on and off the project site and other offsite facilities necessary for work on the project; for all other facilities, sureties, work and operations which must be performed or costs incurred prior to beginning work on various contract items on or off the project site, excepting those specifically paid for under separate sections of these specifications. The Contractor hereby agrees that the stipulated lump sum amount is sufficient for Mobilization and Preparatory Work, as described in this section, and that the Contractor shall have no right to additional compensation for Mobilization and Preparatory Work. Progress payments for Mobilization and Preparatory Work will be made as follows: For the first progress payment (after the issuance of the Notice to Proceed), up to forty percent (40%) of the amount bid for Mobilization and Preparatory Work will be allowed. For the second progress payment, an additional amount up to sixty percent (60%) of the amount bid for mobilization and pre- paratory work will be allowed therefore. 8-4 BID ITEMS. Payment for each Bid Item shall be made at the quantity and type as listed in the Contractor's Proposal. All work shown or mentioned on the plans, in the Contract Documents, General Provisions, or Technical Provisions/Specifications shall be considered as included in the Bid Items. Contractor must protect existing utilities, improvements, landscaping, irrigation systems, and vegeta- tion in place. If damaged during the work, Contractor is responsible to repair or replace any utilities, improvements, landscaping, irrigation systems, and vegetation at his expense. ,, •+;' Revised 6/15/17 Contract No. 424!! Page 107 of 107 Pages CITY OF CARLSBAD San Diego County California CONTRACT DOCUMENTS, GENERAL PROVISIONS AND TECHNICAL SPECIFICATIONS FOR THE Leo Carrillo Ranch Roof Repair {"\ •+;' Revised 6/15/17 CONTRACT NO. 4748 PWS22-1788FAC -Bidding TABLE OF CONTENTS Item Page Notice Inviting Bids . ... .......................... .......................... .................................................. ........ 6 Contractor's Proposal............................................................................................................... 13 Bid Security Form . . . ... .. . . . . .. ... . . . .. . . . .... . . . . . .. . . . . . . . .. . . . . . . . . . . . . . . . . . . .. . .. . . .. . .. . . . .. . ... . . . . . .. . .. . . . .. . .. . . . . .. . .. . . . .. 19 Bidder's Bond to Accompany Proposal . . . .. . . . . . . .. . . .. . . . . . . ... . ... ... . . . . . ... . . . . . . . . ... . . . . . .. . . . . . . .. . .. . . . . .. . .. . . . .. 20 Guide for Completing the "Designation of Subcontractors" Form ............................................. 21 Designation of Subcontractor and Amount of Subcontractor's Bid Items .. .. .... ..... .. .... .. .. .. . .. .. .. . 22 Bidder's Statement of Technical Ability and Experience........................................................... 23 Bidder's Certificate of Insurance for General Liability, Employers' Liability, Automotive Liability and Workers' Compensation .. .. .. . .. .. .. . .. .. .. .. .. .. . .. .. .. .. .. .. .. .. .. . .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. . 24 Bidder's Statement Re Debarment........................................................................................... 25 Bidder's Disclosure of Discipline Record .. . .. . .. . . .. .. . .. . .. . .. . .. . .. . .. . . .. .. . .. . .. . .. . .. . ..... .. .......... .... 26 Non-collusion Declaration to Be Executed by Bidder and Submitted with Bid .. .... .. .. .. .. .. .. .. .. .. .. 28 Contract Public Works.............................................................................................................. 29 Labor and Materials Bond ........................................................................................................ 35 Faithful Performance/Warranty Bond....................................................................................... 37 Optional Escrow Agreement for Surety Deposits in Lieu of Retention .. .. .. .. .. .. .. .. .. .. .. .. .. . .. .. .. .. . .. 39 ATTACHMENTS A Conditions Assessment, dated March 26, 2020 B. Old House Journal Article (."\ •+f Revised 6/12/18 Contract No. 4748 Page 2 of 107 Pages Section 1 1-1 1-2 1-3 1-4 Section 2 2-1 2-2 2-3 2-4 2-5 2-6 2-7 2-8 2-9 2-10 2-11 Section 3 3-1 3-2 3-3 3-4 3-5 Section 4 4-1 4-2 Section 5 5-1 5-2 5-3 5-4 5-5 5-6 Section 6 6-1 6-2 6-3 6-4 6-5 6-6 6-7 6-8 6-9 6-10 GENERAL PROVISIONS Terms, Definitions Abbreviations and Symbols Terms.............................................................................................................. 42 Definitions.................................................... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . 42 Abbreviations . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . .. . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . 46 Units of Measure.......................................... .................................................... 49 Scope and Control of The Work Award and Execution of Contract................. . . . . . . . . . . . . . . . . . . . . . . .. . .. . . . . . . . .. . . . . . . . . . . . . . . . . 50 Assignment.................................................. . . .. . .. . . . . .. ... . . . . .. ... . . . . ... . . . .. ... . . . . . ... . . . . 50 Subcontracts................................................ . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 50 Contract Bonds . . . . . . . . . . .. . . . . . . . . . . . . . . . .. . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51 Plans and Specifications.............................. . . .. . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52 Work to be Done.......................................... . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . 55 Subsurface Data .......................................... . ... ............ ............ .. . . ... . . . . . . .. . . . .. . ... 55 Right-of-Way................................................ . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55 Surveying ..................................................... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55 Authority of Board and Engineer.................. .. . .. . ... .. .. . .. .. ... .............. .. .. .. .. .. .. .. ... 56 Inspection .................................................... ................................ .................... 56 Changes in Work Changes Requested by the Contractor ........ .... .. . .. . .. .. .. .... .. .. . .. .. .. ... .. .... ..... .. .. ... 57 Changes Initiated by the Agency.................. .................................................... 57 Extra Work................................................... .. . . . .. . . . . . . . . . . . . . . . . . . .. .. . . . . . . . . . . . . . . . . . . . . . . . 58 Changed Conditions . . . . . . . . . . . . . . . . . . . . .. . . . .. . . . . .. . . . .. . . . .. . . . . . . . . . . .. . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . 60 Disputed Work . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. .. . .. . . . . . . . . . . .. . . . . . . . . . . 62 Control of Materials Materials and Workmanship......................... .................................................... 63 Materials Transportation, Handling and Storage ... .. .. .. ... .... .. .. .. ... ... .... . ..... . .. .. . .. . 72 Utilities Location ....................................................... .................................................... 73 Protection . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . .. . . .. . . . . . . . . . . .. . . . . . .. . . . . . . . . . . .. . . . . .. . . . . . . . . . . . . .. . . . . . . . . . . . 73 Removal .......................................................................................................... 74 Relocation.................................................... . . . . . . . . . . .. . . . . . . . .. . . . . . . . . . . . .. . . . . . .. . . . . . . . .. . . 7 4 Delays.............................................................................................................. 75 Cooperation................................................. ................ .......................... .......... 75 Prosecution, Progress and Acceptance of the Work Construction Schedule and Commencement of Work....................................... 76 Prosecution of Work..................................... . . . . . . . . . .. . . . . . . . . . . . .. . .. . . . . . . .. . . . .. . . . . . . . . . . .. 79 Suspension of Work..................................... . . . . . . . . . . .. . . . . . . . .... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 90 Default by Contractor................................... . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . .. . . . 90 Termination of Contract................................ ................................ .................... 91 Delays and Extensions of Time.................... .................................................... 91 Time of Completion...................................... . . . . . . . . . . . . . . . .. . . . . . . . . .. . . . . . . .. . . . . . . . . . . . . . . . . . 92 Completion, Acceptance, and Warranty ....... .. ... .. . .. .. ............ ... .. .. ... .. .. . ... .. .. .... .. 93 Liquidated Damages.................................... . .. ... ... . . . . . . . . . . . . . . . .. . . . . . . . . . .. . . . . . . . .. . . . .. . 96 Use of Improvement During Construction .... .................................................... 96 ,, .,., Revised 6/12/18 Contract No. 4748 Page 3 of 107 Pages Section 7 7-1 7-2 7-3 7-4 7-5 7-6 7-7 7-8 7-9 7-10 7-11 7-12 7-13 7-14 Section 8 8-1 8-2 8-3 8-4 Responsibilities of the Contractor Contractor's Equipment and Facilities.......... .................................................... 97 Labor ............................................................................................................... 97 Liability Insurance........................................ ....... ........ ................... .................. 97 Workers' Compensation Insurance .............. ....... ............................................. 97 Permits............................................................................................................ 98 The Contractor's Representative.................. .................................................... 98 Cooperation and Collateral Work................. . . . . . . . . .. . .. . . . . .. ... . .. .. .. ... .. ... . . . . . . . ... .. .. . 98 Project Site Maintenance ............................. . . . . . . . . ... .. . . . ... ... . .. .. .. . .. .. ... . . . . . .. ... .. . . . 99 Protection and Restoration of Existing Improvements ....................................... 100 Public Convenience and Safety . ... . . . . .. . . . . . . . .. . .. . . . . . .. . .. . . . . . . .... .. .. .. . .. .. . .. . . . . . . ......... 100 Patent Fees or Royalties.............................. .......... ............. ........... ............. ..... 103 Advertising ................................................... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 103 Laws to be Observed . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 103 Antitrust Claims................................................................................................ 103 Measurement and Payment Measurement of Quantities for Unit Price Work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 104 Lump Sum Work.......................................... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 104 Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 104 Bid Items................................................................................................... 107 l' •+' Revised 6/12/18 Contract No. 4748 Page 4 of 107 Pages TECHNICAL SPECIFICATIONS DIVISION 01 GENERAL REQUIREMENTS 01 35 91 Restoration of Historic Features DIVISION 02 EXISTING CONDITIONS 02 42 96 Historic Treatment Procedures DIVISION 03 CONCRETE 03 62 18 Non-Shrink Grout DIVISION 04 MASONRY 04 10 00 Adobe 04 20 00 Adobe Repair and Stabilization DIVISION 05 METALS 05 50 00 Metal Fabrications DIVISION 06 WOOD, PLASTICS, AND COMPOSITES 06 03 12 Historic Wood Repair 06 10 00 Rough Carpentry DIVISION 07 07 31 70 07 32 13 07 46 23 07 51 10 07 62 00 THERMAL AND MOISTURE PROTECTION Wood Shingles Historic Roof Tile Repair and Replication Wood Siding Built-Up Asphalt Roofing Sheet Metal Flashing and Trim DIVISION 09 FINISHES 09 21 00 Plaster Repair and Restoration 09 90 00 Painting APPENDIX BRIEF 5 BRIEF 30 PRESERVATION BRIEFS -NATIONAL PARK SERVICE PRESERVATION OF HISTORIC ADOBE BUILDINGS PRESERVATION AND REPAIR OF HISTORIC CLAY TILE ROOFS ,, •,;' Revised 6/12/18 Contract No. 4748 Page 5 of 107 Pages CITY OF CARLSBAD, CALIFORNIA NOTICE INVITING BIDS Until 5 p.m. on May 10, 2022, the City shall accept bids via electronic format via the City of Carlsbad Electronic Bidding Site, PlanetBids, which may be accessed at Contracting & Purchasing I Carlsbad, CA {carlsbadca.gov) for performing the work as follows: LEO CARRILLO RANCH ROOF REPAIR PROJECT CONTRACT NO. 4748 BID NO. PWS22-1788FAC ELECTRONIC FORMAT RECEIPT AND OPENING OF BIDS: Bids will be received in electronic format (eBids) EXCLUSIVELY at the City of Carlsbad's electronic bidding (eBidding) site, at: Contracting & Purchasing I Carlsbad, CA (carlsbadca.gov) and are due by the date and time shown on the cover of this solicitation. BIDDERS MUST BE PRE-REGISTERED with the City's bidding system and possess a system- assigned Digital ID in order to submit an electronic bid. The City's electronic bidding (eBidding) system will automatically track information submitted to the site including IP addresses, browsers being used and the URLs from which information was submitted. In addition, the City's bidding system will keep a history of every login instance including the time of login, and other information about the user's computer configuration such as the operating system, browser type, version, and more. Because of these security features, Bidders who disable their browsers' cookies will not be able to log in and use the City's bidding system. The City's electronic bidding system is responsible for bid tabulations. Upon the bidder's or proposer's entry of their bid, the system will ensure that all required fields are entered. The system will not accept a bid for which any required information is missing. This includes all necessary pricing, subcontractor listing(s) and any other essential documentation and supporting materials and forms requested or contained in these solicitation documents. BIDS REMAIN SEALED UNTIL DUE DATE AND TIME. eBids are transmitted into the City's bidding system via hypertext transfer protocol secure (https) mechanism using SSL 128-256-bit security certificates issued from Verisign/Thawte which encrypts data being transferred from client to server. Bids submitted prior to the Due Date and Time are not available for review by anyone other than the submitter, who will have until the Due Date and Time to change, rescind or retrieve its bid should they desire to do so. BIDS MUST BE SUBMITTED BY DUE DATE AND TIME. Once the deadline is reached, no further submissions are accepted into the system. Once the Due Date and Time has passed, bidders, proposers, the general public, and City staff are able to immediately see the results online. City staff may then begin reviewing the submissions for responsiveness, compliance and other issues. RECAPITULATION OF THE WORK. Bids shall not contain any recapitulation of the Work. Conditional Bids may be rejected as being non- responsive. Alternative proposals will not be considered unless called for. BIDS MAY BE WITHDRAWN by the Bidder prior to, but not after time set as Due Date and Time. ,., •+;' Revised 6/12/18 Contract No. 4748 Page 6 of 107 Pages Important Note: Submission of the electronic bid into the system may not be instantaneous. Due to the speed and capabilities of the user's internet service provider (ISP), bandwidth, computer hardware and other variables, it may take time for the bidder's submission to upload and be received by the City's eBidding system. It is the bidder's sole responsibility to ensure their bids are received on time by the City's eBidding system. The City of Carlsbad is not responsible for bids that do not arrive by the Due Date and Time. ELECTRONIC SUBMISSIONS CARRY FULL FORCE AND EFFECT The Bidder, by submitting their electronic proposal, agrees to and certifies under penalty of perjury under the laws of the State of California, that the certification, forms and affidavits submitted as part of this proposal are true and correct. The bidder, by submitting its electronic bid , acknowledges that doing so carries the same force and full legal effect as a paper submission with a longhand (wet) signature. By submitting an electronic bid, the bidder certifies that the bidder has thoroughly examined and understands the entire Contract Documents (which consist of the plans and specifications, drawings, forms, affidavits and the solicitation documents), and that by submitting the eBid as its bid proposal, the bidder acknowledges, agrees to and is bound by the entire Contract Documents, including any addenda issued thereto, and incorporated by reference in the Contract Documents. BIDS ARE PUBLIC RECORDS Upon receipt by the City, bids shall become public records subject to public disclosure. It is the responsibility of the Bidder to clearly identify any confidential, proprietary, trade secret or otherwise legally privileged information contained within the proposal's General references to sections of the California Public Records Act (PRA) will not suffice. If the Bidder does not provide applicable case law that clearly establishes that the requested information is exempt from the disclosure requirements of the PRA, the City shall be free to release the information when required in accordance with the PRA, pursuant to any other applicable law, or by order of any court or government agency, and the Bidder agrees to hold the City harmless for any such release of this information. This bid and the terms of the Contract Documents and Supplemental Provisions constitute an irrevo- cable offer that shall remain valid and in full force for a period of 90 days and such additional time as may be mutually agreed upon by the City of Carlsbad and the Bidder. INSTRUCTIONS TO BIDDERS AND BID REQUIREMENTS This bid and the terms of the Contract Documents and General Provisions constitute an irrevocable offer that shall remain valid and in full force for a period of 90 days and such additional time as may be mutually agreed upon by the City of Carlsbad and the Bidder. No bid will be received unless it is made on a proposal form furnished by the Purchasing Department. Each bid must be accompanied by security in a form and amount required by law. The bidder's security of the second and third next lowest responsive bidders may be withheld until the Contract has been fully executed. The security submitted by all other unsuccessful bidders shall be returned to them, or deemed void, within ten (10) days after the Contract is awarded. Pursuant to the provisions of law (Public Contract Code section 10263), appropriate securities may be substituted for any obligation required by this notice or for any monies withheld by the City to ensure performance under this Con- tract. Section 10263 of the Public Contract Code requires monies or securities to be deposited with the City or a state or federally chartered bank in California as the escrow agent. The escrow agent shall maintain insurance to cover negligent acts and omissions of the agent in connection with the handling of retentions under this section in an amount not less than $100,000 per contract. The City of Carlsbad may disqualify a contractor or subcontractor from participating in bidding when a contractor or subcontractor has been debarred by the City of Carlsbad or another jurisdiction in the State of California as an irresponsible bidder. ,., •+;' Revised 6/12/18 Contract No. 4748 Page 7 of 107 Pages GENERAL SCOPE OF WORK The Leo Carrillo Ranch is located at 6200 Flying Leo Carrillo Lane in Carlsbad CA 92009. The City desires to structurally reinforce replace/restore the roofs on eight historic properties on site per the plans and specifications for the work, as indicated in the Bid Documents. The work shall be performed sequentially by building as agreed to by the city, and in strict conformance with the plans, provisions and specifications as approved by the City Council of the City of Carlsbad on file with the City Clerk's Office. Reference is hereby made to these plans, provisions and specifi- cations for full particulars and description of the work. The General Provisions (Part 1) to the SSPWC do not apply. The City of Carlsbad encourages the participation of minority and women-owned businesses and en- courages all bidders, suppliers, manufacturers, fabricators and contractors to utilize recycled and re- cyclable materials when available, appropriate and approved by the Engineer. BID DOCUMENTS The bid documents comprise the following documents which must be completed and properly exe- cuted including notarization, where indicated. 1 . Contractor's Proposal 2. Bidder's Bond (At Time of Bid Submit PDF Copy via PlanetBids / All Bidders). Bid Bond (Original) Due within Two Business Days After Bid Opening / 3 Apparent Low Bidders. 3. Non-collusions Declaration 4. Designation of Subcontractor and Amount of Subcontractor's 5. Bidder's Statement of Technical Ability and Experience 6. Acknowledgement of Addendum(a) 7. Certificate of Insurance. The riders covering the City, its officials, employees and volunteers may be omitted at the time of bid submittal but shall be provided by the Bidder prior to award of contract 8. Bidder's Statement Re Debarment 9. Bidder's Disclosure of Discipline Record 10. Escrow Agreement for Security Deposits -(optional, must be completed if the Bidder wishes to use the Escrow Agreement for Security) BIDDER'S GUARANTEE OF GOOD FAITH (BID SECURITY) At the time of bid submission, bidders must upload and submit an electronic PDF copy of the afore- mentioned bid security. Whether in the form of a cashier's check, a properly certified check or an approved corporate surety bond payable to the City of Carlsbad, the bid security must be uploaded to the City's eBidding system. Within two (2) business days after the bid opening date, the first three (3) apparent low bidders must provide the City with the original bid security. Failure to submit the electronic version of the bid security at time of bid submission shall cause the bid to be rejected and deemed non-responsive. Only the three (3) apparent low bidders are required to submit original bid security to the city within two (2) business days after bid opening date. Failure to provide the original within two (2) business days may deem the bidder non-responsive. ENGINEER'S ESTIMATE All bids will be compared on the basis of the Engineer's Estimate. The estimated quantities listed in the Contractor's Proposal are approximate and serve solely as a basis for the comparison of bids. The Engineer's Estimate is $1,013,018. TIME OF COMPLETION The contractor shall complete the Work within the time set in the contract as defined in the General Provisions Section 6-7. ~, \.+' Revised 6/12/18 Contract No. 4748 Page 8 of 107 Pages SPECIALTY CONTRACTORS: ACCEPTABLE LICENSE TYPES Except as provided herein a bid submitted to the City by a Contractor who is not licensed as a contractor pursuant to the Business and Professions Code shall be considered nonresponsive and shall be re- jected by the City. In all contracts where federal funds are involved, no bid submitted shall be invalidated by the failure of the bidder to be licensed in accordance with California law. Where federal funds are involved the contractor shall be properly licensed at the time the contract is awarded. In all other cases the contractor shall state their license number, expiration date and classification in the proposal, under penalty of perjury. This invitation to bid does not include federal funds. The following classifications are acceptable for this contract: B -General Building. BIDDER'S STATEMENT OF TECHNICAL ABILITY AND EXPERIENCE Contractor and his designated subcontractor(s) shall demonstrate proof of their experience and technical ability for construction in the disciplines of construction required to complete this project. Proof of the Contractor's technical ability and experience (as outlined below) shall be attached to The Bidder's Statement of Technical Ability and Experience to be included with the Contractor's bid. The City will only consider Contractors that demonstrate they have the experience and ability to manage, construct, and staff the project. 1. Submit no more than three projects completed by the Contractor in the last 10 years that are comparable in size, scope, complexity, building, type, technically sound and aesthetically distinctive projects constructed for public owner or institutional clients. The City will not give additional consideration for submitting more than three projects. Projects presented for con- sideration must be attached to the Bidders Statement of Technical Ability and Experience form. 2. The lead personnel including superintendent, the foreman, and lead crew personnel for the Contractor and designated subcontractors must have a minimum of three (3) years of total experience and must have demonstrated competency and experience to perform the scope of work contained in this contract. Please provide the name and experience of each lead individ- ual performing work on this contract. Please attach responses to the Bidders Statement of Technical Ability and Experience. Personnel replaced by the Contractor, on this contract, shall have similar, verifiable experience as the personnel originally submitted for the project. ESCROW AGREEMENT If the Contractor intends to utilize the escrow agreement included in the contract documents in lieu of the usual 5% retention from each payment, these documents must be completed and submitted with the signed contract. The escrow agreement may not be substituted at a later date. OBTAINING PLANS AND SPECIFICATIONS Bid packages, various supplemental provisions and Contract Documents may be obtained on the City of Carlsbad website at www.carlsbadca.gov. Paper copies will not be provided or sold. INTENT OF PLANS AND SPECIFICATIONS Any prospective bidder who is in doubt as to the intended meaning of any part of the drawings, spec- ifications or other contract documents, or finds discrepancies in or omissions from the drawings and specifications may submit to the Engineer a written request for clarification or correction. Any response will be made only by a written addendum duly issued by the Engineer a copy of which will be mailed or delivered to each person receiving a set of the contract documents. No oral response will be made to such inquiry. Prior to the award of the contract, no addition to, modification of or interpreta- tion of any provision in the contract documents will be given by any agent, employee or con- tractor of the City of Carlsbad except as herein before specified. No bidder may rely on direc- tions given by any agent, employee or contractor of the City except as herein before specified. l' • ., Revised 6/12/18 Contract No. 4748 Page 9 of 107 Pages REJECTION OF BIDS The City of Carlsbad reserves the right to reject any or all bids and to waive any minor irregularity or informality in such bids. PREVAILING WAGE TO BE PAID The general prevailing rate of wages for each craft or type of worker needed to execute the Contract shall be those as determined by the Director of Industrial Relations pursuant to the sections 1770, 1773, and 1773.1 of the Labor Code. Pursuant to section 1773.2 of the Labor Code, a current copy of applicable wage rates is on file in the Office of the City Engineer. The Contractor to whom the Contract is awarded shall not pay less than the said specified prevailing rates of wages to all workers employed by him or her in the execution of the Contract. The Prime Contractor shall be responsible for insuring compliance with provisions of section 1777.5 of the Labor Code and section 4100 et seq. of the Public Contracts Code, "Subletting and Subcon- tracting Fair Practices Act." The City Engineer is the City's "duly authorized officer" for the purposes of section 4107 and 4107.5. The provisions of Part 7, Chapter 1, of the Labor Code commencing with section 1720 shall apply to the Contract for work. A contractor or subcontractor shall not be qualified to bid on, be listed in a bid proposal, subject to the requirements of Section 4104 of the Public Contract Code, or engage in the performance of any con- tract for public work, unless currently registered and qualified to perform public work pursuant to Sec- tion 1725.5. This project is subject to compliance monitoring and enforcement by the Department of Industrial Relations. The Prime Contractor and all subcontractors shall comply with Section 1776 of the Labor Code, which generally requires keeping accurate payroll records, verifying and certifying payroll records, and making them available for inspection. Contractor shall require all subcontractors to comply with Section 1776. MANDATORY PRE-BID MEETING A mandatory pre-bid meeting and tour of the project site will be held at the Leo Carrillo Ranch, 6200 Flying Leo Carrillo Lane, Carlsbad, CA 92009 on April 7, 2022 at 10:00 a.m. UNIT PRICES AND COMPUTATION OF BIDS All bids are to be computed on the basis of the given categories and/or units of work, as indicated in the Contractor's Proposal, times the unit price (if applicable) as submitted by the bidder. In case of a discrepancy between words and figures, the words shall prevail. In case of an error in the extension of a unit price, the corrected extension shall be calculated, and the bids will be computed as indicated above and compared on the basis of the corrected totals. All bids are to be complete work including all fees, equipment, labor and materials associated with carrying out the work in accordance with plans and specifications. All prices must be in ink or typewritten. Changes or corrections may be crossed out and typed or written in with ink and must be initialed in ink by a person authorized to sign for the Contractor. BIDDER'S INQUIRIES Questions on the bid documents during the bid period shall be submitted via Online Q&A in PlanetBids. Questions shall be definite and certain and shall reference applicable drawing sheets, notes, details or specification sheets. ("\ ., Revised 6/12/18 Contract No. 4748 Page 10 of 107 Pages Pre-bid substitution requests shall be submitted to Contract Administrator in accordance with the In- structions to Bidders and Technical Specifications Section with a minimum of 14 calendar days prior to bid opening (by April 26, 2022 at 5 p.m.). The cutoff date and time to submit questions or substitution request regarding this project via Online Q&A in PlanetBids is April 26, 2022, at 5:00 p.m. No questions will be entertained after that date. The answers to questions submitted during the bidding period will be published in an addendum and provided to those bidding on the project by May 3, 2022. ADDENDA Bidders are advised to verify the issuance of all addenda and receipt thereof one day prior to bidding. Submission of bids without acknowledgment of addenda may be cause of rejection of bid. BOND AND INSURANCE REQUIREMENTS The Contractor shall provide bonds to secure faithful performance and warranty of the work in an amount equal to one hundred percent (100%) of the Contract price on this project. The Contractor shall provide bonds to secure payment of laborers and materials suppliers, in an amount equal to one hundred percent (100%) of the total amount payable by the terms of the contract. These bonds shall be kept in full force and effect during the course of this project and shall extend in full force and effect and be retained by the City until they are released as stated in the General Provisions section of this contract. All bonds are to be placed with a surety insurance carrier admitted and authorized to transact the business of insurance in California and whose assets exceed their liabilities in an amount equal to or in excess of the amount of the bond. The bonds are to be accompanied by the following documents: 1) An original, or a certified copy, of the unrevoked appointment, power of attorney, by laws, or an- other instrument entitling or authorizing the person who executed the bond to do so. 2) A certified copy of the certificate of authority of the insurer issued by the insurance commissioner. If the bid is accepted, the City may require copies of the insurer's most recent annual statement and quarterly statement filed with the Department of Insurance pursuant to Article 10 (commencing with section 900) of Chapter 1 of Part 2 of Division 1 of the Insurance Code, within 10 calendar days of the insurer's receipt of a request to submit the statements. Insurance is to be placed with insurers that: 1) Have a rating in the most recent Best's Key Rating Guide of at least A-:VII 2) Are admitted and authorized to transact the business of insurance in the State of California by the Insurance Commissioner. Auto policies offered to meet the specification of this contract must: 1) Meet the conditions stated above for all insurance companies. 2) Cover any vehicle used in the performance of the contract, used onsite or offsite, whether owned, non-owned or hired, and whether scheduled or non-scheduled. Workers' compensation insurance required under this contract must be offered by a company meeting the above standards with the exception that the Best's rating condition is waived. The City does accept policies issued by the State Compensation Fund meeting the requirement for workers' compensation insurance. The Contractor shall be required to maintain insurance as specified in the Contract. Any additional cost of said insurance shall be included in the bid price. ,, • ., Revised 6/12/18 Contract No. 4748 Page 11 of 107 Pages The award of the contract by the City Council is contingent upon the Contractor submitting the required bonds and insurance, as described in the contract, within twenty days of bid opening. If the Contractor fails to comply with these requirements, the City may award the contract to the second or third lowest bidder and the bid security of the lowest bidder may be forfeited. BUSINESS LICENSE The prime contractor and all subcontractors are required to have and maintain a valid City of Carlsbad Business License for the duration of the contract. Approved by the City Council of the City of Carlsbad, California, by Resolution No. 2022-068, adopted on the 15th day of March, 2022. March 16, 2022 Date Deputy Clerk {' • ., Revised 6/12/18 Contract No. 4748 Page 12 of 107 Pages