HomeMy WebLinkAboutMS 01-15; THOMPSON SUBDIVISION; PRELIMINARY GEOTECHNICAL EVALUTATION; 2001-06-29PRELIMINARY GEOTECHNICAL EVALUATION
3940 ALDER AVENUE
CITY OF CARLSBAD, SAN DIEGO COUNTY, CALIFORNIA
FOR
MR. DAVID THOMPSON
3940 ALDER AVENUE
CARLSBAD, CALIFORNIA 92054
W.O. 3104-A-SC JUNE 299 2001
0
Geotechnical *Geologic * Environmental
5741 Palmer Way • Carlsbad, California 92008 • (760) 438-3155 • FAX (760) 931-0915
June 29, 2001
W.O. 3104-A-SC
Mr. David Thompson
3940 Alder Avenue
Carlsbad, California 92008
Attention: Mr. David Thompson
Subject: Preliminary Geotechnical Evaluation, 3940 Alder Avenue, City of Carlsbad,
San Diego County, California
Dear Sir:
In accordance with your request and authorization, GeoSoils, Inc. (GSI) has performed a
geotechnical evaluation of the subject site. The purpose of the study was to evaluate the
onsite soils and geologic conditions and their effects on the proposed site development
from a geotechnical viewpoint.
EXECUTIVE SUMMARY
Based on our review of the available data (Appendix A), as well as field exploration,
laboratory testing, and geologic and engineering analysis, development of the property
appears to be feasible from a geotechnical viewpoint, provided the recommendations
presented in the text of this report are properly incorporated into design and construction
of the project. The most significant elements of this study are summarized below:
All existing topsoil/colluvium is generally loose and potentially compressible, and
is not suitable for the support of settlement sensitive improvements. These
materials will require removal and recompaction if settlement sensitive
improvements are proposed within their influence. Depth of removals are outlined
in the conclusions and recommendations section of this report. In general,
removals will be on the or f1to2etarossa"majority of the site
Laboratory testing indicates the expansion potential of the onsite soils is low. At the
present time, soluble sulfate and corrosion testing results were not available. An
addendum report presenting those results will be provided when lab testing is
complete.
Reviewed by:
Groundwater was not encountered onsite and is generally not anticipated to affect
site development, providing that the recommendations contained in this report are
incorporated into final design and construction and that prudent surface and
subsurface drainage practices are incorporated into the construction plans.
Perched groundwater conditions along zones of contrasting permeabilities should
not be precluded from occurring in the future due to site irrigation, poor drainage
conditions, or damaged utilities. Should perched groundwater conditions develop,
this office could assess the affected area(s) and provide the appropriate
recommendations to mitigate the observed groundwater conditions.
Conventional foundation systems utilizing slab-on-grade may be used onsite.
The seismic design parameters presented herein should be considered during
project planning and design.
The geotechnical design parameters presented herein should be incorporated into
project planning, design, and construction by the project structural engineer and
architect.
The opportunity to be of service is greatly appreciated. If you have any questions
concerning this report or if we may be of further assistance, please do not hesitate to
contact any of the undersigned. 0
Respectfully submitted
GeoSoils, Inc.
11Exp.•VI 1-I
eobe;rt G ~Cnsman
Engineering Geologist, CEG 1934
RGC/ARKTJh
Distribution: (4) Addressee
Mr. David Thompsom W.O. 31 04-A-SC
F1Ie:e:\wp7\3100\3104a.pge Page Two
GeoSoils, Inc.
TABLE OF CONTENTS
SCOPE OF SERVICES . 1
SITE CONDITIONS/PROPOSED DEVELOPMENT ..............................1
FIELD STUDIES ..........................................................3
REGIONAL GEOLOGY . ...................................................3
EARTH MATERIALS ......................................................3
Colluvium/Topsoil (Not mapped) ......................................3
Terrace Deposits (Map Symbol-Qt) ......................................5
GROUNDWATER ............................................. ............5
FAULTING AND REGIONAL SEISMICITY ......................................5
Faulting ................• ...................5
Seismicity ..........................................................6
Seismic Shaking Parameters ...........................................6
Seismic Hazards ....................................................7
LABORATORY TESTING ..................................................8
General ........................................................... 8 -
Moisture-Density Relations ..........................................8
Shear Testing ......................................................8
Expansion Potential .................................................8
Corrosion/Sulfate Testing ...............................................9
CONCLUSIONS ..........................................................9
EARTHWORK CONSTRUCTION RECOMMENDATIONS ........................9
General............................................................9
Site Preparation ...................................................9
Removals (Unsuitable Surficial Materials) ...............................9
Fill Placement ......................................................10
Overexcavation ....................................................10
FOUNDATION RECOMMENDATIONS ......................................10
General............................................................10.
Preliminary Foundation Design .......................................11
Bearing Value ................................................11
Lateral Pressure ...............................................11
Footing Setbacks -..................................................11
Construction .......................................................12
Low Expansive Soils (Expansion Index 21 to 50) ................... 12
GeoSoils, Inc.
CONVENTIONAL RETAINING WALLS .• 13
General..........................................................13
Restrained Walls....................
.....................
........... 13
Cantilevered Walls ..................................................13
Wall Backfill and Drainage ............................................14
Retaining Wall Footing Transitions ...................................14
Footing Excavation Observation .....................................15
DEVELOPMENT -CRITERIA ................................................15
Landscape Maintenance and Planting .................................15
Additional Site Improvements .........................................16
Trenching........................................................16
Drainage ...........................................................16
Utility Trench Backfill ................................................16
PLAN REVIEW ............................................................17
LIMITATIONS .............................................................17
FIGURES:
Figure .1 - Site Location Map ..........................................2
Figure 2 - Boring Location Map ........................................4
ATTACHMENTS:
Plate 1 -. Geotechnical Map .................................Rear of Text
Appendix A - References ...................................Rear of Text
Appendix B - Test Pit Logs ................................... Rear of Text
Appendix C- Laboratory Data ...............................Rear of Text
Appendix D - General Earthwork and Grading Guidelines ..........Rear of Text
Mr. Tom Robertson Table of Contents
File:e:/wp7/3000/3058a.pge S Page ii
GeoSoils, Inc.
PRELIMINARY GEOTECHNICAL EVALUATION
3940 ALDER AVENUE
CITY OF CARLSBAD, SAN DIEGO COUNTY, CALIFORNIA
SCOPE OF SERVICES
The scope of our services has included the following:
Review of readily available soils and geologic data (Appendix A), including the
previous geologic report for the site,
Subsurface exploration consisting of 5 hand auger boring excavations to determine
the soil/bedrock profiles, obtain relatively undisturbed .and bulk samples of
representative materials, and delineate earth material parameters for the proposed
development (Appendix B). -
Laboratory testing of representative soil samples collected during our subsurface
exploration program (Appendix C).
General areal seismicity evaluation.
Appropriate engineering and geologic analysis Of data collected and preparation
of this report.
SITE CONDITIONS/PROPOSED DEVELOPMENT
The site consists of a irregular shaped parcel located on the south side of Alder Avenue
in Carlsbad, California (Figure 1). The existing site is surrounded by existing housing
developments. Site drainage is generally to the southwest. According to a USGS 1968
(photorevised 1975) San Luis Rey Quadrangle map, the subject site is approximately 299
feet above Mean Sea Level (MSL). Vegetation onsite consists of grasses and scattered
trees.
It is also our understanding that the proposed site development will consist of preparing
the pad for the construction of a new residential structure. Cut and fill grading techniques
would be utilized to create design grades for the proposed single-family residential
structure. It is anticipated that the residential development will consist of a one- or two-
story structure with slab-on-grade floors and continuous footings, utilizing wood-frame
construction. Building loads are assumed to be typical for this type of relatively light
construction. The need for import soils is unknown. It is anticipated that sewage disposal
will be tied into the regional system.
GeoSoils, Inc.
3-D TopoQuads Copyright 1999 DeLorme \armouth, SIr, ,4)9b Source Data: USGS
L
-------
'
:Buer av4 'F -
'il F
'
7 -
11 N
''• II Wee
-v
/
WT 162 —
Ke
mt
y
We
'h HIgh
Seh
- Mgnoba SITE
/ "Ch t
Valky Jr HkhRch*
k>t / A G A
2AZ
/
I
Ii
/
6
/aJ
/
ç\
/ -
va Poi
/
•
. VA --
- Agua
357
sSubsta
essc
-
F
Wafer -. -77
F
Base Map: San Luis Rey Quadrangle, California--San Diego Co., 7.5 Minute Series (Topographic),
1968 (photorevised 1975) by USGS, 1":2000
W.0.
GeoQ Us, 3104-A-SC
SITE LOCATION MAP
0 2000 4000
Scale Feet Figure 1
FIELD STUDIES
Field work conducted during our evaluation of the property consisted of excavating five
hand auger borings within the lot to evaluate near surface soil and geologic conditions.
The borings were logged by a geologist from our firm. Representative bulk and in-place
samples were taken for appropriate laboratory testing. Logs of the borings are presented
in Appendix B. The approximate locations of the borings are shown on Plate 1.
REGIONAL GEOLOGY
The subject property is located within a prominent natural geomorphic province in
southwestern California known as the Peninsular Ranges. It is characterized by steep,
elongated mountain ranges and valleys that trend northwesterly. The mountain ranges are
underlain by basement rocks consisting of pre-Cretaceous metasedimentary rocks,
Jurassic metavolcanic rocks, and Cretaceous plutonic rocks of the southern California
batholith.
In the San Diego region, deposition occurred during the Cretaceous period and Cenozoic
era in the continental margin of a forearc basin. Sediments, derived from Cretaceous-age
plutonic rocks and Jurassic-age volcanic rocks, were deposited into the narrow, steep,
coastal plain and continental margin of the basin. These rocks have been uplifted, eroded
and deeply incised. During early Pleistocene time, a broad coastal plain was developed
from the deposition of marine terrace deposits. During mid to late Pleistocene time, this
plain was uplifted, eroded and incised. Alluvial deposits have since filled the lower valleys,
and young marine sediments are currently being deposited/eroded within coastal and
beach areas.
EARTH MATERIALS
Earth materials encountered on the site are Shown on Figure 2. The materials consist of
colluvium and terrace deposits.
Topsoll/Colluvlum (Not Mapped)
Topsoil/colluvium onsite was found to generally consist of a brown, dry, loose, silty sand.
Thickness of the material is approximately 1 to 2 feet. Topsoil/colluvium at the subject site
is considered potentially compressible in its present state. Accordingly, these soils are
considered unsuitable for support of additional fill and/or settlement sensitive
improvements in their existing state.
Mr. David Thompson W.O. 31 04-A-SC
3940 Alder Avenue, Carlsbad June 29, 2001
F1Ie:e:\wp7\3100\3104a.pge Page 3
GeoSoils, Inc.
Terrace Deposits (Map Symbol - Qt)
The Quaternary-age terrace deposits underlie the entire site at depth. As encountered, the
terrace deposits generally consist of reddish brown, damp, silty sandy to clayey silty sand,
and is medium dense to dense with depth. Due to the relatively soft and weathered
condition of the upper ±1 foot, these materials should be removed, moisture conditioned,
and recompacted and/or processed in place, should settlement-sensitive improvements
be proposed. This unit typically has a low to medium expansion potential.
GROUNDWATER
Groundwater was not encountered onsite and is generally not anticipated to significantly
affect site development, providing that recommendations contained in this report are
incorporated into final design and construction, and that prudent surface and subsurface
drainage practices are incorporated into the construction plans.
Perched groundwater conditions along zones of contrasting permebilities should not be
precluded from occurring in the future (i.e. post grading) due to site irrigation, rainfall, poor
drainage conditions, or damaged utilities. Should perched groundwater conditions
develop, this office could assess the affected area(s) and provide the appropriate
recommendations to mitigate the observed groundwater conditions.
FAULTING AND REGIONAL SEISMICITY
Faulting
The site is situated in aregion of active as well as potentially-active faults. Our review
indicates that there are no known active faults crossing the Site within the areas proposed
for development (Jennings, 1994), and the site is not within an Earthquake Fault Zone
(Hart and Bryant, 1997).
There are a number of faults in the southern California area that are considered active and
would have an effect on the site in the form of ground shaking, should they be the source
of an earthquake (Figure 2). These faults include—but are not limited to—the San Andrëas
fault, the San Jacinto fault, the Elsinore fault, the Coronado Bank fault zone, and the
Newport-Inglewood - Rose Canyon fault zone. The possibility of ground acceleration or
shaking at the site may be considered as approximately similar to the southern California
region as a whole.
The following table lists the major faults andfault zones in southern California that could
have a significant effect on the site should they experience significant activity.
Mr. David Thompson - W.O. 3104-A-SC
3940 Alder Avenue, Carlsbad June 29, 2001
File:e:\wp73100\3104a.pge Page 5
GeoSoils, Inc.
ABBREVIATED FAULT NAME APPROXIMATE DISTANCE
MILES (KM)
Coronado Bank-Agua Blanca 22 (35)
Elsinore 23 (38)
La Naàión 24 (39)
Newport-Inglewood-Offshore 9 (14)
Rose Canyon 5 (9)
San Diego Trough-Bahia Sol. 31(50)
Seismicity
The acceleration-attenuation relations of Joyner and Boore (1982), Campbell and
Bozorgnia (1994), and Sadigh and others (1987) have been incorpprated into EQFAULT
(Blake, 1997). For this study, peak horizontal ground accelerations anticipated at the site
were determined based on the random mean and mean plus 1 sigma attenuation curves
developed by Joyner and Boore (1982), Campbell and Bozorgnia (1994), and Sadigh and
others (1989). These acceleration-attenuation relations have been incorporated in
EQFAULT, a computer program by Thomas F. Blake (1997), which performs deterministic
seismic hazard analyses using up to 150 digitized California faults as earthquake sources.
The program estimates the closest distance between each fault and a user-specified file.
If a fault is found to be within a user-selected radius, the program estimates peak horizontal
ground acceleration that may occur at the site from the upper bound 'maximum credible'
and "maximum probable" earthquakes on that fault.
Site acceleration, as a percentage of the acceleration of gravity (g), is computed by any of
the 14 user-selected acceleration-attenuation relations that are contained in EQFAULT.
Based on the above, peak horizontal ground accelerations from an upper bound
(maximum credible) earthquake may be on the order of 0.48 g to 0.69 g, and maximum
probable event may be on the order of 0.32 g to 0.39 g, assuming upper bound (maximum
credible) and maximum probable event of a magnitude about 6.9, on the Rose Canyon
fault zone, located approximately 6 miles from the subject site.
Seismic Shaking Parameters.
Based on the site conditions, Chapter 16 of the Uniform Building Code (International
Conference of Building Officials, 1997), the following seismic parameters are provided.
Mr. David Thompson W.O. 3104-A-SC
3940 Alder Avenue, Carlsbad June 29, 2001
F1Ie:e:\wp731OO'.31O4a.pge Page 6
GeoSoi is, Inc.
Seismic zone (per Figure 16.2*) . 4
Seismic Zone Factor (per Table 16.1*) . 0.40
Soil Profile Type (per Table 16-J*) SD
Seismic Coefficient C. (per Table 16-Q*) 0.44 Na
Seismic Coefficient C (per Table 16-R*) 0.64 N'
Near Source Factor N1 (per Table 16.S*) .1.0
Near Source Factor N (per Table 16.1*) 1.05
Seismic Source Type (per Table 16-U*) . B
Distance to Seismic Source 5.3 mi. (8.5 km)
Upper Bound Earthquake . MW 6.9
* Figure and table references from Chapter 16 of the Uniform Building Code (1997).
Seismic Hazards
The following list includes other seismic related hazards that have been considered during
our evaluation of the site. The hazards listed are considered negligible and/or completely
mitigated as a result of site location, soil characteristics and typical site development
procedures:
Liquefaction
Tsunami
Dynamic Settlement
Surface Fault Rupture
Ground Lurching or Shallow Ground Rupture
It is important to keep in perspective that in the event of a maximum probable or credible
earthquake occurring on any of the nearby major faults, strong ground shaking would
occur in the subject site's general area. Potential damage to any structure(s) would likely
be greatest from the vibrations and impelling force caused by the inertia of a structure's
mass, than from those induced by the hazards considered above. This potential would be
no greater than that for other existing structures and improvements in the immediate
vicinity. .
Mr. David Thompson W.O. 3104-A-SC
3940 Alder Avenue, Carlsbad June 29, 2001
F1Ie:e:\wp7\3100\3104a.pge Page 7
GeoSoils, Inc.
LABORATORY TESTING
General
Laboratory tests were performed on representative samples of the onsite earth materials
in order to evaluate their physical characteristics. The test procedures used and results
obtained are presented below.
Moisture-Density Relations
The laboratory maximum dry density and optimum moisture content for representative site
soils was determined according to test method ASTM D-1 557. A modified proctor-of 120.0
pounds per cubic foot (pcf), with an optimum moisture content of .11.5 percent was
determined for a composite sample of terrace and existing fill materials.
Shear Teèting
Shear testing was performed on a representative, undisturbed and remolded sample of site
soil in general accordance with ASTM test method D-3080 in a Direct Shear Machine of the
strain control type. Shear test results are presented in the following table:
Sample ,
los I 1P
(rAmnideth 232 33 215 .33
Expansion Potential
Expansion testing was performed on a representative samples of site soil in accordance
with UBC Standard 18-2. The results of expansion testing are presented in the following
table.
LOCATIONV EXPANSION INDEX Fyzf EXPANSION
POTENTIALW
I B-i, Silty Sand 0 Very Low
Mr. David Thompson W.O. 3104-A-SC
3940 Alder Avenue, Carlsbad . June 29, 2001
FiIe:e:\wp7\310031 04a.pge . Page 8
GeoSoils, Inc.
Corrosion/Sulfate Testing
A typical sample of the site material was analyzed for corrosion/soluble sulfate potential.
The testing included determination of pH, soluble sulfates, and saturated resistivity. Test
results are presented in Appendix C as Plate C-i.
CONCLUSIONS
Based upon our site reconnaissance, test results, and review of the previous report, it is
our opinion that the subject site appears suitable for the proposed residential development.
The following recommendations should be incorporated into the construction details.
EARTHWORK CONSTRUCTION RECOMMENDATIONS
General
All grading should conform to the guidelines presented in Appendix Chapter A33 of the
Uniform Building Code, the requirements of the City of Carlsbad, and the Grading
Guidelines presented in Appendix D, except where specifically superseded in the text of
this report. Prior to grading, a GSI representative should be present at the preconstruction
meeting to provide additional grading guidelines, if needed, and review the earthwork
schedule.
During earthwork construction all site preparation and the general grading procedures of
the contractor should be observed and the fill selectively tested by a representative(s) of
GSI. If unusual or unexpected conditions are exposed in the field, they should be reviewed
by this office and if warranted, modified and/or additional recommendations will be offered.
All applicable requirements of local and national construction and general industry safety
orders, the Occupational Safety and Health Act, and the Construction Safety Act should
be met.
Site Preparation
Debris, vegetation and other deleterious material should be removed from the building
area prior to the start of grading. Sloping areas to receive fill should be properly benched
in accordance with current industry standards of practice and guidelines specified in the
Uniform Building Code.
Removals (Unsuitable Surficlal Materials)
Due to the relatively loose/soft condition of topsoil/colluvium and weathered terrace
deposits, these materials should be removed and recompacted in areas proposed for
Mr. David Thompson W.O. 3104-A-SC
3940 Alder Avenue, Carlsbad
S
June 29, 2001
F11e:e:\wp7'31003104a.pge Page 9
GeoSoils, Inc.
settlement sensitive structures, or areas to receive compacted fill. At this time, removal
depths on the order of ±1 to ±2 feet should be anticipated; however, locally deeper
removals may. be necessary. Removals should be completed below a 1:1 projection down
and away from the edge of any settlement sensitive structure and/or limit of proposed fill.
Once removals are completed, the exposed bottom should be reprocessed and
compacted.
Fill Placement
Subsequent to ground preparation, onsite soils may be placed in thin (6±inch) lifts,
cleaned of vegetation and debris, brought to a least optimum moisture content, and
compacted to achieve a minimum relative compaction of 90 percent. If soil importation is
planned, a sample of the soil import should be evaluated by this office prior to importing,
in order to assure compatibility with the onsite site soils and the recommendations
presented in this report. Import soils (if any) for a fill cap should be low expansive (E.l. less
than 50). The use of subdrains at the bottom of the fill cap may be necessary, and
subsequently recommended based on compatibility with onsite soils.
Overexcavatlon
In order to provide for the uniform support of the planned structure, a minimum 3-foot thick
fill blanket is recommended for the graded pad. Any cut portion of the pad for the
residence should be overexcavated a minimum 3 feet below finish pad grade. Areas with
planned fills less than 3 feet should be overexcavated in order to provide the minimum fill
thickness.
FOUNDATION RECOMMENDATIONS
General
In the event that the information concerning the proposed development plan is not correct,
or any changes in the design; location or loading conditions of the proposed structure are
made, the, conclusions and recommendations contained in this report shall not be
considered valid unless the changes are reviewed and conclusions of this report are
modified or approved in writing by this office. It is our understanding that slab-on-grade
construction is desired for the proposed development.
The information and recommendations presented in this section are not meant to
supersede design by the project structural engineer. Upon request, GSI could provide
additional input/consultation regarding soil parameters, as related to foundation design.
Mr. David Thompson W.O. 3104-A-SC
3940 Alder Avenue, Carlsbad June 29, 2001
Fde:e:\wp7\31 OO1 04ap9e Page 10
GeoSoils, Inc.
Preliminary Foundation Design
Our review, field work, and laboratory testing indicates that onsite soils have a very low
expansion potential. Preliminary recommendations for foundation design and construction
are presented below. Final foundation recommendations should be provided at the
conclusion of grading, and based on laboratory testing of fill materials exposed at finish
grade.
Bearing Value
The foundation systems should be designed and constructed in accordance with
guidelines presented in the latest edition of the Uniform Building Code.
An allowable bearing value of 1500 pounds per square foot may be used for the
design of continuous footings at least 12 inches wide and 12 inches deep, and
column footings at least 24 inches square and 18 inches deep, connected by a
grade beam in at least one direction. This value may be increased by 20 percent
for each additional 12 inches in depth to a maximum of 2500 pounds per square
foot. No increase.in bearing value is recommended for increased footing width.
Lateral Pressure
For lateral sliding resistance, a 0.35 coefficient of friction may be utilized for a
concrete to soil contact when multiplied by the dead load.
Passive earth pressure may be computed as an equivalent fluid having a density of
250 pounds per cubic foot with a maximum earth pressure of 2500 pounds per
square foot.
When combining passive pressure and frictional resistance, the passive pressure
component should be reduced by one-third.
Footing Setbacks
All footings should maintain a minimum 7-foot horizontal setback from the base of the
footing to any descending slope. This distance is measured from the footing face at the
bearing elevation. Footings should maintain a minimum horizontal setback of H/3
(H=siope height) from the base of the footing to the descending slope face and no less
than 7 feet, nor need to be greater than 40 feet. Footings adjacent to unlined drainage
swaies should be deepened to a minimum of 6 inches below the invert of the adjacent
unlined swale. Footings for structures adjacent to retaining walls should be deepened so
as to extend below a 1:1 projection from the heel of the wall. Alternatively, wails may be
designed to accommodate structural loads from buildings or appurtenances as described
in the retaining wail section of this report.
Mr. David Thompson W.O. 3104-A-SC
3940 Alder Avenue, Carlsbad June 29, 2001
FIIe:e:\wp7\3100\3104a.pge Page 11
GeoSoils, Inc.
Construction
The following foundation construction recommendations are presented as a minimum
criteria from a soils engineering standpoint.
generally-inthe -very- low - (expans]ñdio to 20). irijading of the site, we
recommend-that any, expanshiiiterial encountered should not be placed within 3 feet
of finish grade, if feasible. Therefore, it is anticipated that the finish grade materials will
have a very low expansion potential.
Recommendations by the project's design-structural engineer or architect, which may
exceed the soils engineers recommendations, should take precedence over the following
minimum requirements. Final foundation design will be provided based on the expansion
potential of the near surface soils encountered during grading.
Very Low Expansive Soils (Expansion index 0 to 20)
Exterior and interior footings should be founded at minimum depths of 12 and 18
inches for one or two-story floor loads, respectively, below the lowest adjacent
surface. Isolated column and panel pads or wall footings, should be founded at a
minimum depth of 18 inches and connected in one direction by a grade beam. All
footings should be reinforced with a minimum of two No. 4 reinforcing bars, one
placed near the top and one placed near the bottom of the footing, and in
accordance with the recommendations width per UBC.
A grade beam, reinforced as above, and at least 12 inches wide should beprovided
across large (e.g., garage or parking area) entrances. The base of the grade beam
should be at the same elevation as the bottom of adjoining footings.
Concrete slabs should be underlain by a minimum of 2 inches of washed sand.
Where moisture condensation is undesirable, conàrete slabs should be underlain
with a vapor barrier consisting of a minimum 6 mu, polyvinyl-chloride or equivalent
membrane, with all laps sealed. This membrane should be placed on acceptable
pad grade materials with a minimum 2-inch thickness of sand should be placed
over the visqueen to aid in uniform concrete curing. if proven by testing (i.e., sand
equivalent greater than 30 and less than ¼ inch in any size dimension), some of the
native sands could be utilized.
Concrete slabs, including garage areas, should be minimally reinforced with No. 3
reinforcement bars placed on 18-1
*
nch centers, each way. All slab reinforcement
should be supported and positined near the vertical midpoint of the slab.
"Hooking" of reinforcement is not an acceptable method of positioning the
reinforcement.
Mr. David Thompson W.O. 3104-A-SC
3940 Alder Avenue, Carlsbad June 29, 2001
FiIe:e:\wp7\3100\3104a.pge Page 12
GeoSoils, Inc.
Garage slabs should be poured separately from adjacent footings and be quartered
with expansion joints or saw cuts. A positive separation from the footings should
be maintained with expansion joint material to permit relative movement.
A minimum slab thickness of 4 inches is recommended. The design engineer
should determine the actual thickness of the slabs based on anticipated loadings
and use.
Premoistening is recommended for these soils conditions, with the moisture content
of the subgrade soils equal to or greater than the optimum moisture content to a
depth of 12 inches prior to poyring slabs and prior to placing visqueen or
reinforcement.
In design of any additional concrete, flatwork, pools or walls, the potential for
differential settlement of the soils should be considered.
CONVENTIONAL RETAINING WALLS
General
The design parameters provided below assume that either native soil or non-expansive
select material (such as gravel) is used to backfill any retaining walls. If high to very highly
expansive soils are used to backfill the proposed walls, increased active and at-rest earth
pressures will need to be utilized for retaining wall design, and may be provided upon
request. Building walls, below grade, should be water-proofed or damp-proofed,
depending on the degree of moisture protection desired. The foundation system for the
proposed retaining walls should be designed in accordance with the recommendations
presented in the preceding sections of this report; as appropriate. Footings should be
embedded a minimum of 18 inches below adjacent grade (excluding landscape layer, 6
inches). There should be no increase in bearing for footing width.
Restrained Walls
Any retaining walls that will be restrained prior to placing and compacting backfill material
or that have re-entrant or male corners, should be designed for an at-rest equivalent fluid
pressure (EFP) of 65 pounds per cubic foot (pcf), plus any applicable surcharge loading.
For areas of male or re-entrant corners, the restrained wall design should extend a
minimum distance of twice the height of the wall laterally from the corner.
Cantilevered Walls
The recommendations presented below are for cantilevered retaining walls up to 15 feet
high. Active earth pressure may be used for retaining wall design, provided the top of the
Mr. David Thompson W.O. 31 04-A-SC
3940 Alder Avenue, Carlsbad June 29, 2001
FiIe:e:\wp7'3100\31 04a.pge Page 13
GeoSoils, Inc.
wall is not restrained from minor deflections. An equivalent fluid pressure approach may
be used to compute the horizontal pressure against the wall. Appropriate fluid unit weights
are given below for specific slope gradients of the retained material. These do not include
other superimposed loading conditions such as traffic, structures, hydrostatic pressures,
seismic events or adverse geologic conditions. When wall configurations are finalized, the
appropriate loading conditions for superimposed loads can be provided upon request.
SURFACE SLOPE OF. ' ' EQUIVALENT .' '•" SELECT'
RETAINED MATERIAL . FLUID WEIGHT : . MATERIAL
HORIZONTAL TO VERTICAL P.C.F. (Native soil)' P.C.F. (Gravel)
Level 40 '
1
35
2tol 55 45
The equivalent fluid density should be increased to 65 pounds per cubic foot for level
backfill at the angle point of the wall (corner or male re-entrant) and extended a minimum
lateral distance of 2H (two times the wall height) on either side of the corner.
Wall Backfill and Drainage
The above criteria assumes that very low expansive soils are used as backfill, and that
hydrostatic pressures are not allowed to build up behind the wall. Positive drainage must
be provided behind all retaining walls in the form of perforated pipe placed within gravel
wrapped in geofabric and outlets. A backdrain system is considered necessary for
retaining walls that are 2 feet or greater in height. Backdrains should consist of a 4-inch
diameter perforated PVC or ABS pipe encased in either Class 2 permeable filter material
or 1/2 to 3/4-inch gravel wrapped in approved filter fabric (Mirafi 140 or equivalent). The filter
material should extend a minimum of one horizontal foot behind the base of the walls and
upward at least one foot. Outlets should consist of a 4-inch diameter solid PVC or ABS
pipe spaced no more greater than 100± feet apart. The use of weep holes in walls higher
than 2 feet should not be considered. The surface of the backfill should be sealed by
pavement or the top 18 inches compacted with relatively impermeable soil. Proper surface
drainage should also be provided. Consideration should be given to applying a water-
proof membrane to all retaining structures. The use of a waterstop should be considered
for all concrete and masonry joints.
Retaining Wall Footing Transitions
Site walls are anticipated to be founded on footings designed in accordance with the
recommendations in this report. Wall footings may transition from competent terrace
deposits to fill. If this condition is present the civil designer may specify either:
Mr. David Thompson W.O. 3104-A-SC
3940 Alder Avenue, Carlsbad June 29, 2001
F11e:e:\wp7'3100\3104a.pge Page 14
GeoSoils, Inc.
a) If transitions from terrace to fill transect the wall footing alignment at an angle of less
than 45 degrees (plan view), then the designer should perform a minimum 2-foot
overexcavation for a distance of two times the height of the wall and increase
overexcavation until such transition is between 45 and 90 degrees to the wall
alignment.
Increase of The amount of reinforcing steel and wall detailing (Le., expansion joints
or crack control joints) such that an angular distortion of 1/360 for a distance of 2H
(where H=wall height in feet) on either side of the transition may be
accommodated. Expansion joints should be sealed with a flexible, non-shrink
grout.
Embed the footings entirely into a homogeneous fill.
Footing Excavation Observation
All footing excavations for walls and appurtenant structures should be observed by the
geotechnical consultant to evaluate the anticipated near surface conditions prior to the
placement of steel or concrete. Based on the conditions encountered during the
observations of the footing excavation, supplemental recommendations may be offered,
as appropriate.
DEVELOPMENT CRITERIA
Landscape Maintenance and Planting
Water has been shown to weaken the inherent strength of soil and slope stability is
significantly reduced by overly wet conditions. Positive surface drainage away from graded
slopes should be maintained and only the amount of irrigation necessary to sustain plant
life should be provided for planted slopes. Overwatering should be avoided.
Graded slopes constructed within and utilizing onsite materials would be erosive. Eroded
debris may be minimized and surficial slope stability enhanced by establishing and
maintaining a suitable vegetation cover soon after construction. Plants selected for
landscaping should be light weight, deep rooted types which require little water and are
capable of surviving the prevailing climate. Compaction to the face of fill slopes would
tend to minimize short term erosion until vegetation is established. In order to minimize
erosion on a slope face, an erosion control fabric (i.e. jute matting) may be considered.
From a geotechnical standpoint leaching is not recommended for establishing
landscaping. If the surface soils area processed for the purpose of adding amendments
they should be recompacted to 90 percent relative compaction.
Mr. David Thompson W.O. 3104-A-SC
3940 Alder Avenue, Carlsbad
• June 29, 2001
FiIe:e:\wp731003104a.pge Page 15
GeoSoils, Inc.
Additional Site Improvements
Recommendations for additional grading, exterior concrete flatwork design and
construction, including driveways, can be provided upon request. If in the future, any
additional improvements are planned for the site, recommendations concerning the
geological or geotechnical aspects of design and construction of said improvements could
be provided upon request.
Trenching
All footing trench excavations for structures and walls should be observed and approved
by a representative of this office prior to placing reinforcement. Footing trench spoil and
any excess soils generated from utility trench excavations should be compacted to a
minimum relative compaction of 90 percent if not removed from the site. All excavations
should be observed by one of our representatives and conform to CAL-OSHA and local
safety codes. GSI does not consult in the area of safety engineers.
In addition, the potential for encountering hard spots during footing and utility trench
excavations should be anticipated. If these concretions are encountered within the
proposed footing trench, they should be removed, which could produce larger excavated
areas within the footing or utilit/ trenches.
Drainage
Positive site drainage should be maintained at all times. Drainage should not flow
uncontrolled down any descending slope. Water should be directed away from
foundations and not allowed to pond and/or seep into the ground. Pad drainage should
be directed toward the street or other approved area. Roof gutters and down spouts
should be considered to control roof drainage. Down spouts should outlet a minimum of
5 feet from the proposed structure or into a subsurface drainage system. We would
recommend that any proposed open bottom planters adjacent to proposed structures be
eliminated for a minimum distance of 10 feet. As an alternative, closed bottom type
planters could be utilized. An outlet placed in the bottom of the planter, could be installed
to direct drainage away from structures or any exterior concrete flatwork.
Utility Trench Backfill
1.* All utility trench backfill in structural areas, slopes, and beneath hardscape features
should be brought to near optimum moisture content and then compacted to obtain
a minimum relative compaction of 90 percent of the laboratory standard.
Flooding/jetting is not recommended for the site soil materials. As an alternative,
imported sandy material with an S.E. of 30 or greater, may be flooded/jetted in
shallow (12±inch or less) under-slab interior trenches, only.
Mr. David Thompson W.O. 3104-A-SC
3940 Alder Avenue, Carlsbad June 29, 2001
FiIe:e:\wp7'3100104a.pge Page 16
GeoSoils, Inc.
Sand backfill, unless trench excavation material, should not be allowed in exterior
trenches adjacent to and within an area extending below a 1:1 plane projected from
the outside bottom edge of the footing.
All trench excavations should minimally conform to CAL-OSHA and local safety
codes.
Soils .generated from utility trench excavations to be used onsite should be
compacted to 90 percent minimum relative compaction. This material must not alter
positive drainage patterns that direct drainage away from the structural area and
towards the street.
PLAN REVIEW
Final site development and foundation plans should be submitted to this office for review
and comment, as the plans become available, for the purpose of minimizing any
misunderstandings between the plans and recommendations presented herein. In
addition, foundation excavations and any additional earthwork construction performed on
the site should be observed and tested by this office. If conditions are found to differ
substantially from those stated, appropriate recommendations would be offered at that
time.
LIMITATIONS
The materials encountered. on the project site and utilized in our study are believed•
representative of the area; however, soil and bedrock materials vary in character between
excavations and natural outcrops or conditions exposed during mass grading. Site
conditions may vary due to seasonal changes or other factors. GSI assumes no
responsibility or liability for work, testing or recommendations performed or provided by
others. The scope of work was performed within the limits of a budget. Inasmuch as our
study is based upon the site materials observed, selective laboratory testing and
engineering analysis, the conclusion and recommendations are professional .opinions.
These opinions have been derived in accordance with current standards of practice, and
no warranty is expressed or implied. Standards of practice are subject to change with
time.
Mr. David Thompson W.O. 3104-A-SC
3940 Alder Avenue, Carlébad June 29, 2001
File:e:\wp7\3100\3104a.pge Page 17
GeoSoils, Inc.
LEGEND
0 t Quaternary terrace d6p081t8
C B-5 Approximate location of test boring
Driveway
Alder
Avenue \ I roes and shrubs
Existing house
Iceplant
Stairway
Trees and shrubs at
CB-2
CB-4
Retaining wall
4)B-1
4)- Iceplant
ot. I
at
at
• •• • LOS ANGELES CO. g RIVERSIDE CO.
ORANGE CO.
'--.' '--' SAN DIEGO CO.
GEOTECHNICAL MAP
Plate 1
NOT A SURVEYED MAP 1w.o. 3104-A-SC DATE 6/01 SCALE flOfl
APPENDIX A
REFERENCES
APPENDIX A
REFERENCES
Benton Engineering, Inc., 1970, Final Compaction Report, La Costa South Unit 7, August
10, 1970, Project # 69-12-81).
Blake, Thomas F., 1997, EQFAULT computer program for the deterministic prediction
of horizontal accelerations from digitized California faults.
Campbell, K.W. and Bozorgnia, V., 1994, Near-source attenuation of peak horizontal
acceleration from worldwide accelrograms recorded from 1957 to 1993;
Proceedings, Fifth U.S. National Conference on Earthquake Engineering, volume
Ill, Earthquake Engineering Research Institute, pp 292-293.
Hart, E.W. and Bryant, W.A. 1997, Fault-rupture Hazard Zones in California, Alquist-Priolo
Earthquake Fault Zoning act with Index to Earthquake Fault Maps; California
Division of Mines and Geology Special Publication 42.
International Conference of Building Officials, 1997, Uniform building code: Whittier,
California, vol. 1, 2, and 3.
Jennings, C.W., 1994, Fault activity map of California and adjacent areas: California
Division of Mines and Geology,*Map Sheet No. 6, scale 1:750,000.
Joyner, W.B., and Boore, D.M., 1982, Estimation of response-spectral values as functions
of magnitude, distance and site conditions, in eds., Johnson, J.A., Campbell, K.W.,
and Blake, T.F., AEG short course, seismic hazard analysis, dated June 18, 1994.
Petersen, Mark D., Bryant, W.A., and Cramer, C.H., 1996, Interim table of fault parameters
used by the California Division of Mines and Geology to compile the probabilistic
seismic hazard maps of California.
Sadigh,K., Egan, J., and Youngs, R., 1987, Predictive ground motion equations reported
in Joyner, W.B., and Boore, D.M., 1988, "Measurement, characterization, and
prediction of strong ground motion', in Earthquake Engineering and Soil Dynamics
II, Recent Advances in Ground Motion Evaluation, Von Thun, J.L., ed.: American
Society of Civil Engineers Geotechnical Special Publication No. 20, pp. 43-102.
Tan, S.S., and Kennedy, Michael P., 1996, Geologic maps of the northwestern part of San
Diego County, California: California Division of Mines and Geology, Open File
Report 96-02.
GeoSoils, Inc.
APPENDIX B
BORING LOGS
BORING LOG
GeoSoils, Inc.
W.O. 3104-A-SC
PROJECT: David Thompson BORING B-i SHEET 10F
David Thompson
DATE EXCAVATED [5-29-011
'S Sample x SAMPLE METHOD: HAND ANGER
Sd
'S 9- C Standard Penetration Test 4- 0 9-•
'S L. 4- Water Seepage into hole u — C 3 Undisturbed, Ring Sample Z ow 5 0 4- L 4- Ad —.D 3 C#LJ3 IL 0 3 5. —L 0 05 31 4. F S C 3 — 3 L o 4- Description of Material &4 0 E (I)
- -
- 0-1' TOPSOIL/COLLUVIUM; SILTY SAND, brown, moist,
•
.
\loose; roots and rootlets.SM -
1-1 .5'TERRACE DEPOSITS; SILTY SAND, reddish brown, •
damp, medium dense.
• 1.5-2' -
'Clayey silty sandy reddish brown, damp, medium dense
- Practical Refusal @2' .)
5. - No groundwater encountered
Backfilled 5/29/01
10-
15-
20
25
- , GeoSoils Inc. David Thompson PLA TE B-i
BORING LOG
GeoSoils, Inc.
WO. 3104-A-SC
PROJECT: David Thompson BORING B-2 SHEET 1 O
David Thompson
DATE EXCAVATED 15-29-01.J
Sample SAMPLE METHOD: HANDANGER
C 4- Standard Penetration Test 0
I.. 4 •f-_ a•
L 4- I - C ' Undisturbed, Ring Sample Water Seepage into hole
a o 4- 9 •-•o 3 V) J0 • a 0. - VL 0 QE - I- C - In L 0 Description of Material 4- DC 0 E In
- - 0-1' TOPSOIL/COLLUVIUM; SILTY SAND, brown, moist,
\loose;rootsandrootlets. SM -
1-3' TERRACE DEPOSITS; Clayey silty sand, reddish brown, -
(damp,,medium dense to dense with depth
- Practical Refusal @3' )
- • No groundwater encountered
Backfilled 5/29/01 5.
10
15
20
25-
GeoSoils, Inc. David Thompson PLATE B-2
BORING LOG
GeoSoils, Inc.
PROJECT: David Thompson
David Thompson
Sample
I 4-
I.. 4 4-. a
ID
I.- \ - Cl'.
L
we a o D 4- 4- .-.0 3. a IL -L 0 U :a" - a - u 0 o D9- V) 0 E
5
w.o. 3104-A-SC
BORING B-3 SHEET.J_OF .j...
DATE EXCAVATED , _5-29-01)
SAMPLE METHOD: HAND ANGER
Standard Penetration Test
4- . Water Seepage into hole Undisturbed, Ring Sample
Description of Material
- 0-1' TOPSOIL/COLLUVIUM;SILTY SAND, brown, dry to
- - damp, loose; roots and roolets.
1-2.5' TERRACE DEPOSITS; Clayey silty sand, reddish
brown, damp, medium dense to dense with depth.
Practical Refusal @2.51
No groundwater encountered,
Backfilled 5/29/01
David Thompson . Geo Soils, Inc.
PLATE_B-3
BORING LOG
GeoSoils, Inc.
w.o. 3104-A-SC
PROJECT: David Thompson BORING B-4 SHEET 1 OF
David Thompson
DATE EXCA VA TED .5-29-01
Sample
4-
4- II.
I.. 4- 4- I V
4- a -.uI 3 tn•.a CL IL —ILI 0 (JE 3" a lcI - 03 o P4-1 D(p 0
SAMPLE METHOD: HAND ANGER 9'
.a 9%
% C o Standard Penetration Test
S L - 4- Water Seepage into hole
4- L Undisturbed, Ring Sample
a
- o E
4-
Description of Material
ij- i . Jr ,ILIJLLuyIuIvI; OIL i i EIAND, orown, ary, loose;
- - rpts and rootlets.
1-3' TERRACE DEPOSITS: Clayey silty sand reddish brown,
brown,
damp, medium dense to dense with depth.
Practical (Refusal @3')
No groundwater encountered'
Backfilled 5/29/01
I 10-
I 15-1
I 25-I
David Thompson GeoSoils, Inc. PITE B-4
BORING LOG
GeoSoils, Inc.
W.O. 3104-A-SC
PROJECT: David Thompson BORING B5 SHEET 1 O
David Thompson.
DA TE EXCA VA TED 5-29-01)
- Sample - SAMPLE METHOD: HAND ANGER
• - - Standard Penetration Test
• Water Seepage into hole ; Undisturbed, Ring Sample
IL 13 L 0
IL
Description of Material
- - 0-1' TOPSOIL/COLLUVIUM; SILTY SAND, brown, dry, loose;
roots and rootlets. SM -
12.5' TERRACE DEPOSITS; Clayey silty sand, reddish
brawn, 'damp, medium dense to dense withdepth.
•
-
Practical Refusal @2.5'0
. No groundwater encountered •
' Backfilled 5/29/01
I 5-1
I 10-1
I 15-i
I 20-I
I 25-1
I I I I I I I I
David Thompson GeoSoils, Inc.
• PLATE B-5
APPENDIX C
LABORATORY DATA
M. J. Schiff & Associates, Inc.
Consulting Corrosion Engineers - Since 1959 1308 Monte Vista Avenue, Suite 6
Upland, CA 91786-8224
S 0 Phone: 909/931-1360
Table 1- Laboratory Tests on Soil Samples
3104-A-SC
Your #3104-A-SC, MJS&A #01-0465LAB
5-Jun-01
Sample ID
B-i
@ 0-2.5' SEW
Resistivity Units
as-received ohm-cm 320,000
saturated ohm-cm 6,000
pH 6.5
Electrical
Conductivity mS/cm 0.08
Chemical Analyses •
Cations
calcium Ca2' mg/kg 44
magnesium .Mg2 mg/kg 12
sodium Na1+ mg/kg ND
Anions
carbonate C032 . mg/kg ND
bicarbonate HCO3 mg/kg 43
chloride Cl'-.mg/kg 18
sulfate SO42 mg/kg ND
Other Tests
ammonium NH4'+ mg/kg na
nitrate NO3'_ Mg/kg na
II1[
qual iF.
Redox III' IF:
Electrical conductivity in millisiemens/cm and chemical analysis were made on a 1:5 soil-to-water extract.
mg/kg = milligrams per kilogram (parts per million) of dry soil.
Redox = oxidation-reduction potential in millivolts
ND = not detected • 0 •
0
na = not analyzed •
S
• •
Page lofi
• Plate C-I
GeoSoils, Inc.
APPENDIX D
GENERAL EARTHWORK AND GRADING GUIDELINES
GENERAL EARTHWORK AND GRADING GUIDELINES
General
These guidelines present general procedures and requirements for earthwork and grading
as shown on the approved grading plans, including preparation of areas to filled,
placement of fill, installation of subdrains and excavations. The recommendations
contained in the geotechnical report are part of the earthwork and grading guidelines and
would supersede the provisions contained hereafter in the case of conflict. Evaluations
performed by the consultant during the course of grading may result in new
recommendations which could supersede these guidelines or the recommendations
contained in the geotechnical report..
The contractor is responsible for the satisfactory completion of all earthwork in accordance
with provisions of the project plans and specifications. The project soil engineer and
engineering geologist (geotechnical consultant) or their representatives should provide
observation and testing services, and geotechnical consultation dunng the duration of the
project.
EARTHWORK OBSERVATIONS AND TESTING
Geotechnical Consultant
Prior to the commencement of grading, a qualified geotechnical consultant (soil engineer
and engineering geologist) should be employed for the purpose of observing earthwork
procedures and testing the fills for conformance with the recommendations of the
geotechnical report, the approved grading plans, and applicable grading codes and
ordinances.
The geotechnical consultant should provide testing and observation so that determination
may be made that the work is being accomplished as specified. It is the responsibility of
the contractor to assist the consultants and keep them apprised of anticipated work
schedules and changes, so that they may schedule their personnel accordingly.
All clean-outs, prepared ground to receive fill, key excavations, and subdrains should be
observed and documented by the project engineering geologist and/or soil engineer prior
to placing and fill. It is the contractors's responsibility to notify the engineering geologist
and soil engineer when such areas are ready for observation.
Laboratory and Field Tests
Maximum dry density tests to determine the degree of compaction should be performed
in accordance with American Standard Testing Materials test method ASTM designation
D-1 557-78. Random field compaction tests should be performed in accordance with test
method ASTM designation 0-1556-82, D-2937 or D-2922 and D-3017,* at intervals of
approximately 2 feet of fill height or every 100 cubic yards of fill placed. These criteria
GeoSoils, Inc.
would vary depending on the soil conditions and the size of the project. The location and
frequency of testing would be at the discretion of the geotechnical consultant.
Contractor's Responsibility
All clearing, site preparation, and earthwork performed on the project should be conducted
by the contractor, with observation by geotechnical consultants and staged approval by
the governing agencies, as applicable. It is the contractor's responsibility to prepare the
ground surface to receive the fill, to the satisfaction of the soil engineer, and to place,
spread, moisture condition, mix and compact the fill in accordance with the
recommendations of the soil engineer. The contractor should also remove all major non-
earth material considered unsatisfactory by the soil engineer.
It is the sole responsibility of the contractor to provide adequate equipment and methods
to accomplish the earthwork in accordance with applicable grading guidelines, codes or
agency ordinances, and approved grading plans. Sufficient watering apparatus and
compaction equipment should be provided by the contractor with due consideration for
the fill material, rate of placement, and climatic conditions. If, in the opinion of the
geotechnical consultant, unsatisfactory conditions such as questionable weather,
excessive oversized rock, or deleterious material, insufficient support equipment, etc., are
resulting in a quality of work that is not acceptable, the consultant will inform the
contractor, and the contractor is expected to rectify the conditions, and if necessary, stop
work until conditions are satisfactory.
During construction, the contractor shall properly grade all surfaces to maintain good
drainage and prevent ponding of water. The contractor shall take remedial measures to
control surface water and to prevent erosion of graded areas until such time as permanent
drainage and erosion control measures have been installed.
SITE PREPARATION
All major vegetation, including brush, trees, thiôk grasses, organic debris, and other
deleterious material should be removed and disposed of off-site. These removals must be
concluded prior to placing fill. Existing fill, soil, alluvium, colluvium, or rock materials
determined by the soil engineer or engineering geologist as being unsuitable in-place
should be removed prior to fill placement. Depending upon the soil conditions, these
materials may be reused as compacted fills. Any materials incorporated as part of the
compacted fills should be approved by the soil engineer.
Any underground structures such as cesspools, cisterns, mining shafts, tunnels, septic
tanks, wells, pipelines, or other structures not located prior to grading are to be removed
or treated in a manner recommended by the soil engineer. Soft, dry, spongy, highly
fractured, or otherwise-unsuitable ground extending to such a depth that surface
processing cannot adequately improve the condition should be overexcavated down to
Mr. David Thompson S Appendix
RI9:e:\wp7\31003104a.pge Page 2
GeoSoils, Inc.
firm ground and approved by the soil engineer before compaction and filling operations
continue. Overexcavated and processed soils which have been properly mixed and
moisture conditioned should be re-compacted to the minimum relative compaction as
specified in these guidelines.
Existing ground which is determined to be satisfactory for support of the fills should be
scarified to a minimum depth of 6 inches or as directed by the soil engineer. After the
scarified ground is brought to optimum moisture content or greater and mixed, the
materials should be compacted as specified herein. If the scarified zone is grater that 6
inches in depth, it may be necessary to remove the excess and place the material in lifts
restricted to about 6 inches in compacted thickness.
Existing ground which is not satisfactory to support compacted fill should be
overexcavated as required in the geotechnical report or by the on-site soils engineer
and/or engineering geologist. Scarification, disc harrowing, or other acceptable form of
mixing should continue until the soils are broken down and free of large lumps or clods,
until the working surface is reasonably uniform and free from ruts, hollow, hummocks, or
other uneven features which would inhibit compaction as described previously.
Where fills are to be placed on ground with slopes steeper than 5:1 (horizontal to vertical),
the ground should be stepped or benched. The lowest bench, which will act as a key,
should be a minimum of 15 feet wide and should be at least 2 feet deep into firm material,
and approved by the soil engineer and/or engineering geologist. In fill over cut slope
conditions, the recommended minimum width of the lowest bench or, key is also 15 feet
with the key founded on firm material, as designated by the Geotechnical Consultant. As
a general rule, unless specifically recommended otherwise by the Soil Engineer, the
minimum width of fill keys should be approximately equal to 1/2 the height of the slope.
Standard benching is generally 4 feet (minimum) vertically, exposing firm, acceptable
material. Benching may be used to remove unsuitable materials, although it is understood
that the vertical height of the bench may exceed 4 feet. Pre-stripping may be considered
for unsuitable materials in excess of 4 feet in thickness.
All areas to receive fill, including processed areas, removal areas, and the toe of fill
benches should be observed and approved by the soil engineer and/or engineering
geologist prior to placement of fill. Fills may then be properly placed and compacted until
design grades (elevations) are attained..
COMPACTED FILLS
Any earth materials imported or excavated on the property may be utilized in the fill
provided that each material has been determined to be suitable by the soil engineer.
These materials should .be free of roots, tree branches, other organic matter or other
deleterious materials. All unsuitable materials should be removed from the fill as directed
Mr. David Thompson Appendix
FiIe:e:\wp7\31 00\31 04a.pge Page 3
GeoSoils, Inc.
by the soil engineer. Soils of poor gradation, undesirable expansion potential,' or
substandard strength characteristics may be designated by the consultant as unsuitable
and may require blending with other soils to serve as a satisfactory fill material.
Fill materials derived from benching operations 'should be dispersed throughout the fill
area and blended with other bedrock derived material. Benching operations should not
result in the benched material being placed only within a single equipment width away
from the fill/bedrock contact.
Oversized materials defined as rock or other irreducible materials with a maximum
dimension greater than 12 inches should not be buried or placed in fills unless the location
of materials and disposal methods are specifically approved by the soil engineer.
Oversized material should be taken off-site or placed in accordance with recommendations
of the soil engineer in areas designated as suitable for rock disposal. Oversized material
should not be placed within 10 feet vertically of finish grade (elevation) or within 20 feet
horizontally of slope faces.
To facilitate future trenching, rock should not be placed within the -range of foundation
excavations, future utilities, or underground construction unless specifically approved by
the soil engineer and/or the developers representative.
If import material is required 'for grading, representative samples of the materials to be
utilized as compacted fill should be analyzed in the laboratory by the soil engineer to
determine its physical properties: If any material other than that previously tested is
encountered during grading, an appropriate analysis of this material should be conducted
by the soil engineer as soon as possible.
Approved fill material should be placed in areas prepared to receive fill in near horizontal
layers that when compacted should not exceed 6 inches in thickness. The soil engineer
may approve thick lifts if testing indicates the grading procedures are such that adequate
compaction is being achieved with lifts of greater thickness. Each layer should be spread
evenly and blended to attain uniformity of material and moisture suitable for compaction.
Fill layers at a moisture content less than optimum should be watered and mixed, and wet
fill layers should, be aerated by scarification or should be blended with drier material.
Moisture condition, blending, and mixing of the fill layer should continue until the fill
materials have a'uniform moisture content at or above optimum moisture.
After each layer has been evenly spread, moisture conditioned and mixed, it should be
uniformly compacted to a minimum of 90 percent of maximum density as determined by
ASTM test designation, D-1 557-78, or as otherwise recommended by the soil engineer.
Compaction equipment should be adequately sized and should be specifically designed
for soil compaction or of proven reliability to efficiently achieve the specified degree of
compaction.
Mr. David Thompson Appendix
F11e:e:\wp7't31 00\31 04a.pge Page 4
GeoSoils, 'Inc.
Where tests indicate that the density of any layer of fill, or portion thereof, is below the
required relative compaction, or improper moisture is in evidence, the particular layer or
portion shall be re-worked until the required density and/or moisture content has been
attained. No additional fill shall be placed in an area until the last placed lift of fill has been
tested and found to meet the density and moisture requirements, and is approved by the
soil engineer.
Compaction of slopes should be accomplished by over-building a minimum of 3 feet
horizontally, and subsequently trimming back to the design slope configuration; Testing
shall be performed as the fill is elevated to evaluate compaction as the fill core is being
developed. Special efforts may be necessary to attain the specified compaction in the fill
slope zone. Final slope shaping should be performed by trimming and removing loose
materials with appropriate equipment. A final determination of fill slope compaction should
be based on observation and/or testing of the finished slope face. Where compacted fill
slopes are designed steeper than 2:1 (horizontal to vertical), specific material types, a
higher minimum relative compaction, and special grading procedures, may be
recommended.
If an alternative to over-building and cutting back the compacted fill slopes is selected,
then special effort should be made to achieve the required compaction in the outer 10 feet
of each lift of fill by undertaking the following:
An extra piece of equipment consisting of a heavy short shanked sheepsfoot should'.
be used to roll (horizontal) parallel to the slopes continuously as fill is placed. The
sheepsfoot roller should also be used to roll perpendicular to the slopes, and
extend out over the slope to provide adequate compaction to the face of the slope.
2: Loose fill should not be spilled out, over the face of the slope as each lift is
compacted. Any loose fill spilled over a previously completed slope face should be
trimmed off or be subject to re-rolling.
Field compaction tests will be made in the outer (horizontal) 2 to 8 feet of the slope
at appropriate vertical intervals, subsequent to compaction operations.
After completion of the slope, the slope face should be shaped with a small tractor
and then re-rolled with a sheepsfoot to achieve compaction to near the slope face.
Subsequent to testing to verify compaction, the slopes should be grid-rolled to
achieve compaction to the slope face. Final testing should be used to confirm
compaction after grid rolling.
Where testing indicates less than adequate compaction, the contractor will be
responsible to rip, water, mix and re-compact the slope material as necessary to
achieve compaction. Additional testing should be performed to verify compaction.
Mr. David Thompson Appendix
File:e:\wp710031 04a.pge Page 5
GeoSoils, Inc.
6. Erosion control and drainage devices should be designed by the project civil
engineer in compliance with ordinances of the controlling governmental agencies,
and/or in accordance with the recommendation of the soil engineer or engineering
geologist.
SUBDRAIN INSTALLATION
Subdrains should be installed in approved ground in accordance with the approximate
alignment and details indicated by the geotechnical consultant. Subdrain locations or
materials should not be changed or modified without approval of the geotechnical
consultant. The soil engineer and/or engineering geologist may recommend and direct
changes in subdrain line, grade and drain material in the field, pending exposed
conditions. The location of constructed subdrains should be recorded by the project civil
engineer..
EXCAVATIONS
Excavations and cut slopes should be examined during grading by the engineering
geologist. If directed by the engineering geologist, further excavations or overexcavation
and re-filling of cut areas should be performed and/or remedial grading of cut slopes
should be performed. When fill over cut slopes are to be graded, unless otherwise
approved, the cut portion of the slope should be observed by the engineering geologist
prior to placement of materials for construction of the fill portion of the slope.
The engineering geologist should observe all cut slopes and should be notified by the
contractor when cut slopes are started.
-' If, during the course of grading, unforeseen adverse or potential adverse geologic
conditions are encountered, the engineering geologist and soil engineer should
investigate, evaluate and make recommendations to treat these problems. The need for
cut slope buttressing or stabilizing should be based on in-grading evaluation by-the
engineering geologist, whether anticipated or not.
Unless otherwise specified in soil and geological reports, no cut slopes should be
excavated higher or steeper than that allowed by the ordinances of controlling
governmental agencies. Additionally, short-term stability of temporary cut slopes is the
contractors responsibility. .
Erosion control and drainage devices should be designed by the project civil engineer and
should be constructed in compliance with the ordinances of the controlling governmental
agencies, and/or in accordance with the recommendations of the soil engineer or
engineering geologist..
Mr. David Thompson S Appendix
RIe:e:\wp7'3100\31 04a.pge S Page 6
GeoSoils, Inc.
COMPLETION
Observation, testing and consultation by the geotechnical consultant should be conducted
during the grading operations in order to state an opinion that all cut and filled areas are
graded in accordance with the approved project specifications.
After completion of grading and after the soil engineer and engineering geologist have
finished their observations of the work, final reports should be submitted Subject to review•
by the controlling governmental agencies. No further excavation or filling should be
undertaken without prior notification of the soil engineer and/or engineering geologist.
All finished cut and fill slopes should be protected from erosion and/or be planted in
accordance with the project specifications and/or as recommended by a landscape
architect. Such protection and/or planning should be undertaken as soon as practical after
completion of grading.
JOB SAFETY
General
At GeoSoils, Inc. (GSI) getting the job done safely is of primary concern. The following is
the company's safety considerations for use by all employees on multi-employer
construction sites. On ground personnel are at highest risk of injury and possible fatality
on grading and construction projects. GSI recognizes that construction activities will vary
on each site and that site safety is the prime responsibility of the contractor; however,
everyone must be safety conscious and responsible at all times. To achieve our goal of
avoiding accidents, cooperation between the client, the contractor and GSI personnel must
be maintained.
In an effort to minimize risks associated with geotechnical testing and observation, the
following precautions are to be implemented for the safety of field personnel on grading
and construction projects:
Safety Meetings: GSI field personnel are directed to attend contractors regularly
scheduled and documented safety meetings.
Safety Vests: Safety vests are provided for and are to be worn by GSI personnel at
all times When they are working in the field.
Safety Flags: Two safety flags are provided to GSI field technicians; one is to be
affixed to the vehicle when on site, the other is to be placed atop the
spoil pile on all test pits.
Mr. David Thompson Appendix
F1Ie:e:\wpl\3100\3104a.pge Page 7
GeoSoils, Inc.
Flashing Lights: All vehicles stationary in the grading area shall use rotating or flashing
amber beacon, or strobe lights, on the vehicle during all field testing.
While operating a vehicle in the grading area, the emergency flasher
on the vehicle shall be activated.
In the event that the contractor's representative observes any of our personnel not
following the above, we request that it be brought to the attention of our office.
Test Pits Location, Orientation and Clearance
The technician is responsible for selecting test pit locations. A primary concern should be
the technicians's safety. Efforts will be made to coordinate locations with the grading
contractors authorized representative, and to select locations following or behind the
established traffic pattern, preferably outside of current traffic. The contractors authorized
representative (dump man, operator, supervisor, grade checker, etc.) should direct
excavation of the pit and safety during the test period. Of paramount concern should be
the soil technicians safety and obtaining enough tests to represent. the fill.
Test pits should be excavated so that the spoil pile is placed away. form oncoming traffic,
whenever possible. The technician's vehicle is to be placed next to the test pit, opposite
the spoil pile. This necessitates the fill be maintained in a driveable condition.
Alternatively, the contractor may wish to park a piece of equipment in front of the test
holes, particularly in small fill areas or those with limited access..
A zone of non-encroachment should be established for all test pits. No grading equipment
should enter this zone during the testing procedure. The zone should extend
approximately 50 feet outward from the center of the test pit. This zone is established for
safety and to avoid excessive ground vibration which typically decreased test results.
When taking slope tests the technician should park the vehicle directly above or below the
test location If this is not possible, a prominent flag should be placed at the top of the
slope. The contractor's representative should effectively keep all equipment at a safe
operation distance (e.g. 50 feet) away from the slope during this testing.
The technician is directed to withdraw from the active portion of the fill as soon as possible
following testing. The technician's vehicle should be parked at the perimeter of the fill in
a highly visible location, well away from the equipment traffic pattern.
The contractor should inform our personnel of all changes to haul roads, cut and fill areas
or other factors that may affect site access and site safety.
In the event that the technicians safety is jeopardized or compromised as a result of the
contractors failure to comply with any of the above, the technician is required, by company
policy, to immediately withdraw and notify his/her supervisor. The grading contractors
representative will eventually be contacted in an effort to effect a solution. However, in the
Mr. David Thompson Appendix
FiIe:e:wp7\3100\3104a.pge Page 8
GeoSoils, Inc.
interim, no further testing will be performed until the situation is rectified. Any fill place can
be considered unacceptable and subject to reprocessing, recompaction or removal.
In the event that the soil technician does not comply with the above or other established
safety guidelines, we request that the contractor brings this to his/her attention and notify
this office. Effective communication and coordination between the contractors
representative and the soils technician is strongly encouraged in order to implement the
above safety plan.
Trench and Vertical Excavation
It is the contractors responsibility to provide safe access into trenches where compaction
testing is needed.
Our personnel are directed not to enter any excavation or vertical cut which 1) is 5 feet or
deeper unless shored or laid back, 2) displays any evidence of instability, has any loose
rock or other debris which could fall into the trench, or 3) displays any other evidence of
any unsafe conditions regardless of depth.
All trench excavations or vertical cuts in excess of 5 feet deep, which any person enters,
should be shored or laid back.
Trench access should be provided in accordance with CAL-OSHA and/or state and local
standards. Our personnel are directed not to enter any trench by being lowered or "riding
down" on the equipment.
If the contractor fails to provide safe access to trenches for compaction testing, our
company policy requires that the soil techniàian withdraw and notify his/her supervisor.
The contractors representative will eventually be contacted in an effort to effect a solution.
All backfill not tested due to safety concerns or other reasons could be subject to
reprocessing and/or removal.
If GSI personnel become aware of anyone working beneath an unsafe trench wall or
vertical excavation, we have a legal obligation to put the contractor and owner/developer
on notice to immediately correct the situation. If corrective steps are not taken, GSI then
has an obligation to notify CAL-OSHA and/or the proper authorities.
Mr. David Thompson Appendix
FBe:e:wp7\3100\3104a.pge Page 9
GeoSoils, Inc.
RECEIVED
NOV - 1 ZUlu
ENGINEERING
DEPARTMENT