Recommended Action
Support staff’s recommendation to implement the improvement plans for Segment 2 of the
Avenida Encinas Coastal Rail Trail and Pedestrian Improvements, Capital Improvement Program
Project No. 6004.
Summary
In July 2017, Caltrans awarded the City of Carlsbad an Active Transportation Program, or ATP,
grant by Caltrans to construct a portion of the Coastal Rail Trail, or CRT, along Avenida Encinas
between Carlsbad Boulevard and Cannon Road. Construction of this portion of the CRT has
been identified as a high priority by the local and regional community. The CRT is a planned
regional bikeway that includes a 44-mile regional bikeway that connects six coastal cities
throughout San Diego County.
On Dec. 7, 2021, with a recommendation from staff, the City Council authorized executing an
agreement with NASLAND Engineering for engineering design and environmental services for
the project.
On April 4, 2022, the Traffic and Mobility Commission received a presentation and provided
input on the preliminary design of the project. At the same meeting, the commission voted
unanimously to support staff’s recommended bike lane classification, enhanced Class II bike
lane, along Avenida Encinas
Following the April 4, 2022, Traffic and Mobility Commission meeting, staff discovered
additional comments submitted by the public relating to the project. To provide those
additional comments to the Traffic and Mobility Commission, staff placed an item on the June
6, 2022, Regular Meeting Agenda for the Commission’s consideration.
At the June 6, 2022, meeting, the Commission discussed the additional comments that had
been received as well as comments received in person at the meeting. Following consideration
of all the comments received staff were directed to return to the Traffic and Mobility
Commission with the final improvement plans for Segment 2 of the Avenida Encinas Coastal
Rail Trail and Pedestrian Improvements.
Aug. 18, 2022 Item #1 1
Discussion
Staff have received input from Traffic and Mobility Commission and the public on the
preliminary design plans. Staff directed NASLAND Engineering to update the improvement
plans and environmental documents for Segment 2 of the project. Segment 2 is located
between Poinsettia Transit Station and Carlsbad Boulevard as shown in Exhibit 1.
Improvements along the project corridor include the following features as identified in the
improvement plans provided in Exhibit 2:
• Striping modifications
• Enhanced Class II bike lanes
• Enhanced intersection treatments including curb extensions, traffic calming measures,
and high visibility crosswalks at the following intersections on Avenida Encinas:
o Poinsettia Lane
o Portage Way
o Dory Lane
o Carlsbad Boulevard
• Traffic calming with a road lane realignment between Poinsettia Lane and Windrose
Circle that has been identified to reduce the level of service (LOS).
• Enhanced midblock pedestrian crossing at San Carlos Street and Avenida Encinas
As shown in the proposed improvements plans, provided in Exhibit 2, most of the roadway
improvements will be implemented through roadway restriping. The roadway segment from
Poinsettia Lane to Windrose Circle will be restriped from 5-vehicle lanes to 2-vehicle lanes.
While traffic studies show the road lane realignment for this segment will result in a drop in
Level of Service, from LOS C to LOS D, this segment will still operate at acceptable levels of
service under the City’s General Plan Mobility Element. Consistent with Mobility Element 3-
P.15, staff will therefore bring this item to the City Council with a recommendation to approve
the road lane re-alignment.
Next Steps
Following the Traffic and Mobility Commission’s review, staff will finalize the construction plans
for Segment 2 of the project and submit a construction allocation request to Caltrans for the
ATP grant funding by Aug. 31, 2022. Thereafter, staff will bring a staff report to the City Council
in late 2022 with a recommendation to approve the plans, specifications, and contract
documents and authorize the City Clerk to advertise for construction bids for the project.
After the bidding process is complete, the project will be brought back to the City Council with a
request to award a construction contract to the lowest responsive and responsible bidder. The
construction is targeted to begin in mid-2023.
Exhibits
1. Project Location Map
2. Improvement Plans
Aug. 18, 2022 Item #1 2
ââ
ââ
ââ
ââ
ââââ
ââ
ââ
ââ
ââ
ââââââââââRD
AVENIDA
ENC
INAS
POINSETT
I
A
PALOMAR AIRPORT
CARLSBAD BL
§¨¦5
§¨¦5
LNRD
CANNON
PRTS
PLOTTED BY: Andy Chang PLOT DATE: 10/25/2021 PATH: Z:\Brandon_Miles\LocationMaps\6004_Avenida_Encinas_Coastal_Rail_Trail\6004_LocationMap_WithVicinityMap.mxd
PROJECT NAME EXHIBITPROJECT
NUMBER6004 1Avenida Encinas Coastal Rail Trail and
Pedestrain Improvements
LOCATION MAP
CARLSBAD
VISTA
ENCINITAS
OCEANSIDE
SAN MARCOSPROJECTLIMITS
è
è
PROJECTLIMITS
è
èPRTS - Poinsettia Regional Transit Station
Legend
ââ ââ ââ ââ Segment 1 - Completed
Segment 2 - To be Completed by ATP and City Funds
Segment 3 - To be Completed by City-Only Funds
Exhibit 1
Aug. 18, 2022 Item #1 3
”
CITY OF CARLSBAD
AVENIDA ENCINAS COASTAL RAIL TRAIL PROJECT
AND PEDESTRIAN IMPROVEMENTS
SEGMENT 2
VICINITY MAP
CITY OF CARLSBAD
CARLSBAD, CA
CITY COUNCIL
MATT HALL - MAYOR
TERESA ACOSTA - COUNCIL MEMBER
PRIYA BHAT-PATEL - COUNCIL MEMBER
KEITH BLACKBURN - COUNCIL MEMBER
PEDER NORBY - COUNCIL MEMBER
SCOTT CHADWICK - CITY MANAGER
Exhibit 2
Aug. 18, 2022 Item #1 4
Aug. 18, 2022Item #1 5
Aug. 18, 2022Item #1 6
Aug. 18, 2022 Item #1 7
Aug. 18, 2022 Item #1 8
Aug. 18, 2022 Item #1 9
Aug. 18, 2022 Item #1 10
Aug. 18, 2022 Item #1 11
Δ
Aug. 18, 2022 Item #1 12
Aug. 18, 2022 Item #1 13
Aug. 18, 2022 Item #1 14
Aug. 18, 2022 Item #1 15
Aug. 18, 2022 Item #1 16
Δ
Aug. 18, 2022 Item #1 17
Δ
Aug. 18, 2022 Item #1 18
Δ
Aug. 18, 2022 Item #1 19
Δ
Aug. 18, 2022 Item #1 20
Δ
Aug. 18, 2022 Item #1 21
Δ
Aug. 18, 2022 Item #1 22
TRAFFICNOT FORCONSTRUCTIONAVENIDA ENCINAS CRT IMPROVEMENTSDETAIL SHEETAug. 18, 2022Item #1 23
DORY LNMARLIN LNPORTAGEWAYMERIDIANWAY 7800P57.94AVENIDA ENCINASAVENIDA ENCINASCARLSBADBLVD (NB)TRAFFICNOT FORCONSTRUCTIONAVENIDA ENCINAS CRT IMPROVEMENTSPONTO DRSEE BELOW LEFTMATCHLINE 21+50SEE ABOVE RIGHTMATCHLINE 21+50
MATCHLINE 34+75
SEE SHEET 22 CARLSBADBLVD (SB)SIGNING AND STRIPING PLANTrail35...........................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................Aug. 18, 2022Item #1 24
AVENIDA ENCINASDWYA
V
E
N
ID
A
E
N
C
I
N
A
SWINDROSE CIRTRAFFICNOT FORCONSTRUCTIONAVENIDA ENCINAS CRT IMPROVEMENTSSEE SHEET 23MATCHLINE 53+50MATCHLINE CSEE ABOVE RIGHT SEE SHEET 21MATCHLINE 34+75
SEE BELOW LEFTMATCHLINE 42+50SIGNING AND STRIPING PLAN35TrailTrailAug. 18, 2022Item #1 25
5558ICV/WV58.95SAN CARLOS ST
AVENIDA ENCINAS
6585AD1 B
64.036586AD164.076587AD164.026588AD1 CLO
63.98
SAN LUCAS
S
T
SHOPPIN
G
CENTER
D
W
YAVENIDA EN
CINAS
TRAFFICNOT FORCONSTRUCTIONAVENIDA ENCINAS CRT IMPROVEMENTSMA
T
C
H
L
I
N
E
5
3
+
5
0
S
E
E
S
H
E
E
T
2
2 MATCHLINE 64+70SEE BELOW LEFTSEE ABOVE RIGHTMATCHLINE 64+70MATCHLINE 75+75SEE SHEET 24POINSETTIA
L
N
SIGNING AND STRIPING PLAN
35
SHOPPI
N
G
CENTE
R
D
WY
Aug. 18, 2022 Item #1 26
EMBARCADERO LN (S)AVENIDA ENCINASRAINTREE DRMACADAMIA DRAVENIDA ENCINASTRAFFICNOT FORCONSTRUCTIONAVENIDA ENCINAS CRT IMPROVEMENTSSEE SHEET 23MATCHLINE 75+75
MATCHLINE 87+10
SEE BELOW LEFT
SEE ABOVE RIGHTMATCHLINE 87+10
SEE SHEET 25MATCHLINE 99+003025SIGNING AND STRIPING PLAN25Aug. 18, 2022Item #1 27
DWY136CSLB-13
6
54.
0
6AVENIDA ENCINASTRAFFICNOT FORCONSTRUCTIONAVENIDA ENCINAS CRT IMPROVEMENTSSEE SHEET 24MATCHLINE 99+00
3035EMBARCADERO LN
(N
)SIGNING AND STRIPING PLANAug. 18, 2022Item #1 28
GGEECATVCATVTTGGGGGGGGGGGGGGGGGGGGGGGGGGGGGGEEEEEEEEEEEEEEE EEE E
EEEEEEEEEEEEE E E
EEEEEEEEEEEEWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWW W W W W W
T
T
T
T
E E E E E
EEEEEESSSCATVCATVW W W
FOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOCATVCATVCATVCATVCATVCATVCATVCATVCATVCATVCATVCATVCATVCATVCATVCATVCATVCATVCATVTTTTTTEEEEETTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTSSSSSSSSSSSSSSSSSSSSSSSSSSSSSRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWTTTTTTTTTTTTTTTTTTTTTTTTTRAFFICNOT FORCONSTRUCTIONAVENIDA ENCINAS CRT IMPROVEMENTSAVENIDA ENCINAS AND SAN CARLOS STREETPEDESTRIAN SIGNAL PLANAVENIDA ENCINASSAN CARLOS STREETSHOPPING CENTER DWYAug. 18, 2022Item #1 29
5558ICV/WV58.95TRAFFIC
AVENIDA ENCINAS CRT IMPROVEMENTSNOT FORCONSTRUCTIONAVENIDA ENCINAS AND POINSETTIA LANETRAFFIC SIGNAL MODIFICATION PLANAVENIDA ENCINASPOINSETTIA LANEAug. 18, 2022Item #1 30
AVENIDA ENCINASCARLSBAD BLVD (SB)CARLSBAD BLVD (NB)AVENIDA ENCINASSHOPPING CENTER DWYSAN LUCAS ST658
5AD1
B64.03
6586AD164.0
7
6587AD164.02
658
8AD1
C
L
O
63.98TRAFFICNOT FORCONSTRUCTIONAVENIDA ENCINAS CRT IMPROVEMENTSDETECTOR LOOP REPLACEMENT PLANAug. 18, 2022Item #1 31
EEEE E E E
GGGGGGGEEEEEEEEFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOCATVCATVCATVCATVCATVTTTTTTTTGGGGFOFOFOFOEEEEETTTTFOFOFOFOFOCATVCATVCATVG G G GGGGGGGGGGGGGGGGGG
GGGGGGGGGGGGGGGGGGGGGGEEEEEEEEEEEEEEE EEE
E
EEEEEEEEEE E
E
EEEEEEEEEWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWW W W W W W
T T T T
E E E E E
EEEEEESSSCATVCATVCATVCATVW W W
FOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOCATVCATVCATVCATVCATVCATVCATVCATVCATVCATVCATVCATVCATVCATVCATVCATVTEEEEEEEEEEEEEETTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTFOFOFOFOFOFOFOFOFOFOFOFOFOTTTTTTTTTTTTTTTTTTTTTTTTTCATVCATVCATVCATVCATVCATVCATV CATV CATV
SSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSRW RW RWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWW W W WTTT TTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTTRW RW RW SAN LUCAS ST6585AD1 B64.036586AD164.076587AD164.026588AD1 CLO63.98 AVENIDA ENCINASSAN CARLOS STREETSHOPPINGCENTER DWYGGGGGGGGGGGGGGGGGGGGGGGGGGGGGGGEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWEW
W
W
W
W
W
W
W
W
W
W
W
W
G
G
G
GGG
G
G
G
G
G
G
G
G FOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOFOT
T
T T TTTTTT T
T
T
T
T
TCATVCATVCATVCATVCATVCATVCATVCATVCATVCATVCATVCATVCATVCATVCATVCATV
CATVCATVCATVCATVCATVEEEEEEETTTTTTTTTTEEEEEEEEEEEEEEEEEEEEEE
E
E
E
E
E
E WWWWSDSDSDSDSDSDSDSDSDSD
SD
SD
SD
RW
RW
RW
RW
RW
RW
RW
RW
RW
RWTTTTTTTTTT SSSSSSSSSSSSSSSSSSSSSSSSSSSSSRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRWRW5558ICV/WV58.95 AVENIDA ENCINASTRAFFICNOT FORCONSTRUCTIONAVENIDA ENCINAS CRT IMPROVEMENTSFIBER OPTIC COMMUNICATION PLANSEE ABOVE RIGHTMATCHLINE 67+50
MATCHLINE 67+
5
0
SEE BELOW LE
F
TPOINSETTIA LANERTPROPOSEDETHERNET SWITCHTRRTTRRTTRPROPOSEDETHERNET SWITCHPROPOSEDETHERNET SWITCHPROPOSED SPLICE DIAGRAMSHOPPING CENTER DWYAug. 18, 2022Item #1 32
Avenida Encinas Coastal Rail Trail and
Pedestrian Improvements
Project No. 6004
Hossein Ajideh, Engineering Manager
Brandon Miles, Associate Engineer
Aug. 18, 2022
Recommended Action
Support staff’s recommendations to approve the plans
and specifications for Avenida Encinas Coastal Rail Trail
and Pedestrian Improvements, Capital Improvement
Program (CIP) Project No. 6004
2
Background
•Coastal Rail Trail (CRT) is a regional bikeway that includes a 44-mile
regional bikeway that connects six coastal cities throughout San
Diego County
•Project constructs 2.5 miles of enhanced bicycle and pedestrian
facilities, enhanced intersection treatments for improved safety, and
traffic calming with road lane realignment
3
Timeline
•Nov. 15, 2021 -SANDAG, as Metropolitan Planning Organization, approved both
requests for State-Only and scope change
•Dec. 7, 2021 –City Council authorized executing an agreement with consultant
•Dec. 24, 2021 –Caltrans approved State-Only Finding request
•April 4 and June 6, 2022 –Staff presented project to T&MC
•Aug. 1, 2022 –Requested funding allocation
•Request for Scope Change supported by Caltrans and now is under review by
California Transportation Commission (CTC) staff
–Tentatively scheduled to be presented at Oct 2022 CTC meeting
4
Project
•To expedite project schedule and realistically manage
environmental review and ROW acquisition phases to meet
ATP grant requirements, this project has been broken into:
1.Segment 1 -from Cannon Rd to Palomar Airport Rd –Completed
2.Segment 2 -from Poinsettia Coaster Station to Carlsbad Blvd –final draft
3.Segment 3 -from Palomar Airport Rd to Poinsettia Coaster Station –in design phase
5
6
Avenida Encinas Coastal Rail Trail and Pedestrian Improvements
Proposed Improvement
Segment 2
7
8
Avenida Encinas
Carlsbad Blvd to
Ponto Dr.
9
Avenida Encinas
Dory Ln to
Portage Way
10
Avenida Encinas
Windrose Cir
11
Avenida Encinas
Shopping Center to San
Lucas St.
12
Avenida Encinas
San Carlos St to
Poinsettia Ln
13
Avenida Encinas
Poinsettia Ln to
Raintree Dr
14
Avenida Encinas
Macadamia Dr
15
Avenida Encinas
Embarcadero Ln
To Poinsettia
Coaster Station
Next Steps
•Staff will
–Finalize project plans, specifications and cost estimate
•Request City Council to
–approve plans and specifications and authorize for
bids
–request City Council to award a construction contract
16
Recommended Action
Support staff’s recommendations to approve the plans
and specifications for Avenida Encinas Coastal Rail Trail
and Pedestrian Improvements
17