P.C. AGENDA OF: May 6,1998 Project Planner: Eric Munoz
Project Engineer: Doug Helming
SUBJECT: CDP 97-5OcA) - BEACH ACCESS RECONSTRUCTION - Request by the
City’s Public Works Division for approval of a Coastal Development Permit
Amendment to modify one existing condition of approval to extend the required
completion date fi-om May 31 to July 3, 1998, for the reconstruction of two
existing beach access locations within the City’s Coastal Zone, within the Coastal
Commission Appeal area, located at the northern terminus of Ocean Street and at
Cherry Avenue within Local Facilities Management Zone 1.
I. RECOMMENDATION
That the Planning Commission ADOPT Planning Commission Resolution No. 4245
APPROVING Coastal Development Permit Amendment CDP 97-50(A) based upon the findings
and subject to the conditions contained therein.
11. BACKGROUND
This project was originally approved on December 17, 1997 with a condition to complete the
stairway reconstruction work by May 31, 1998. Subsequent to the December 1997 approval, the
Public Works Department informed the Planning Department that additional time was needed
and an extension until July 3, 1998 was requested.
The request to extend the project’s completion date until July 3 was considered by the Planning
Commission at the March 4, 1998 regularly scheduled Commission meeting. The Commission
voted unanimously to approve the permit amendment and related change in completion date.
However, subsequent to the March 4 hearing, it was realized that the Planning Department’s
noticing of the project areas (600’ radius required noticing for property owners and 100’ required
radius noticing for occupants) was not properly done.
Therefore, the same project staff report and resolution (attached) are presented again for
consideration by the Planning Commission.
Staff recommendation is to approve CDP 97-50(A) so that stairway reconstruction project may
be completed by early July so that beach users will be able to use stairs that were upgraded and
rehabilitated to meet current public safety standards.
P
CDP 97-50(A) - BEACH ACCESS RECONSTRUCTION
May 6,1998
ATTACHMENTS:
1.
2.
Planning Commission Resolution No. 4245
Staff Report dated March 4, 1998, with attachments.
e
@ The City of CARLSBAD Planning Department
A REPORT TO THE PLANNING COMMISSION
P.C. AGENDA OF: March 4,1998
Application complete date: February 1 1, 1998
Project Planner: Eric Munoz
Project Engineer: Doug Helming
SUBJECT: CDP 97-50(A) - BEACH ACCESS RECONSTRUCTION - Request by the
City’s Public Works Division for approval of a Coastal Development Permit
Amendment to modify one existing condition of approval to extend the required
completion date from May 31 to July 3, 1998 for the reconstruction of two
existing beach access locations within the City’s Coastal Zone, within the Coastal
Commission Appeal area, located at the northern terminus of Ocean Street and at
Cherry Avenue within Local Facilities Management Zone 1.
I. RECOMMENDATION
That the Planning Commission ADOPT Planning Commission Resolution No. 4245
APPROVING Coastal Development Permit Amendment CDP 97-50(A) based upon the findings
and subject to the conditions contained therein.
11. INTRODUCTION
Pursuant to Section 21.201.070(A)(l)(d) of the Carlsbad Municipal Code, the City’s Public
Works Division applied for and received approval of a Coastal Development Permit (CDP). That
CDP was conditioned to require completion of construction prior to May 31, 1998. Due to
unforseen circumstances described below, construction has been delayed. Public Works is
requesting to extend the completion date to July 3, 1998. The CDP amendment application was
reviewed for consistency with LCP policies and implementation. There are no unresolved issues.
The staff is recommending approval with conditions which are supported by the analysis as
follows.
111. PROJECT DESCRIPTION AND BACKGROUND
On December 17, 1997 the Planning Commission approved CDP 97-50 which allowed for the
reconstruction of two beach access stairways in the City. Condition No. 3 of approving Planning
Commission Resolution No. 42 1 1, requires that the reconstruction work be completed by
May 31, 1998. Awarding the contract took longer than anticipated. Therefore, the Public
Works Division has filed a request to extend the completion date until July 3, 1998. This will
allow the stairways to be fully rehabilitated to current safety standards for the summer season of
1998.
CDP 97-50(A) - BEACH ALCESS RECONSTRUCTION
MARCH 4,1998
IV. ANALYSIS
This project is a maintenance and repair effort for the long term upkeep of the two stairways
involved. Extending the required completion date from May 31 to July 3 will impact the beach
users who utilize these stairways. However, the short timeframe involved, combined with the
long term maintenance benefits of this project, override any short term beach access impacts. In
addition, alternate beach access locations are located near each of the two project sites which can
be used by beach users during the construction period.
A new condition of approval for this project will be the posting of signs, to the satisfaction of the
Planning Director, indicating to the public where alternate beach access can be found.
Attached is an Engineering Department Memo dated February 10, 1998 which outlines the
revised milestone dates for initiating the reconstruction work. The revised schedule anticipates a
start date for construction in early May which will accommodate job completion by July 3, 1998.
V. ENVIRONMENTAL REVIEW
The project was found to be exempt from CEQA per the exemption listed below:
(1) Section 1530 1 of CEQA exemptions (Class 1 (d)) exempts the restorationhehabilitation of
deteriorated or damaged structures to meet current standards of health, safety and welfare.
The Planning Director has determined that the proposed amendment is within the scope of the
CEQA exemption as conditioned.
ATTACHMENTS:
I.
2. Location Map
3.
Planning Commission Resolution No. 4245
Engineering Memo dated February 10, 1998
ENM:nm:mh
SITE
BEACH ACCESS- RECONSTRUCTION
CDP 97-50(A)
Date: February IO, 1998
To: ERIC MUNOZ, PLANNING
From:
Subject:
DOUG HELMING, CONSULTANT PROJECT MANAGER
BEACH ACCESS STAIR RECONSTRUCTION, PROJ. NO. 351 1
We are requesting an extension of time for the Coastal Development Permit to complete the
project. The Coastal Development Permit had a condition that the project be completed by
the Memorial Day weekend. The current schedule to complete the Beach Access Stair
Reconstruction project puts the end of construction beyond that date.
The project is currently scheduled to go to City Council on March 3, 1998 for authorization to
advertise for bid. Bids are scheduled to be opened on April 9, 1998. After review of the bids
received we then need to take the recommended bid to City Council for approval. This is
anticipated to take place on May 5, 1998. Upon approval of the contract by City Council
there is a week for the contractor to mobilize and a six week construction schedule. Allowing
a week for unforeseen delays and we are looking at completion prior to the July 4th
weekend.
We propose to place signs at the Ocean Street stairs and the Cherry Avenue stairs directing
the public to the nearest open beach access stair locations.
This is the best schedule of events I can provide at this time. Should you need additional
information, please call me at 431-5999.
c: Principal Civil Engineer, Planning & Design