A REPORT TO THE PLANNING COMMISSION
Item No.
P.C. AGENDA OF: January 5, 2000
Application complete date: August 1, 1999
Project Planner: Don Rideout
Project Engineer: Bob Wojcik
SUBJECT: CDP 99-30 - POINSETTIA LANE BRIDGE WIDENING - Request for
approval of a Mitigated Negative Declaration, Mitigation Monitoring and
Reporting Program, and Coastal Development Permit to allow the widening of the
Poinsettia Lane bridge crossing the San Diego Northern Railroad tracks to full
Major Arterial Standards between Carlsbad Boulevard and Avenida Encinas.
I. RECOMMENDATION
That the Planning Commission ADOPT Planning Commission Resolution No. 4715
APPROVING the Mitigated Negative Declaration issued by the Planning Director, and ADOPT
Planning Commission Resolution No. 4716 APPROVING Coastal Development Permit CDP
99-30, based on the findings and subject to the conditions contained therein.
II. INTRODUCTION
The City of Carlsbad Public Works Department has applied for approvals to widen the existing
bridge on Poinsettia Lane between Carlsbad Boulevard and Avenida Encinas, as shown in
Attachment 3. The bridge spans the San Diego Northern railroad tracks. The existing bridge
was constructed in 1984. Approvals needed for the project include a Coastal Development
Permit and certification of a Mitigated Negative Declaration. The project site is within the Mello
II Segment of the City's Local Coastal Program. To the east of the site are existing
Travel/Recreation Commercial uses along Avenida Encinas. West of the site is Carlsbad
Boulevard and South Carlsbad State Beach Campground. To the north is the Poinsettia
Properties Specific Plan which is approved and graded. South of the site are Lakeshore Gardens
Mobile Home Park, Poinsettia Plaza Shopping Center, and a smaller portion of the Poinsettia
Properties Specific Plan.
III. PROJECT DESCRIPTION AND BACKGROUND
Poinsettia Lane is designated as a Major Arterial in the Circulation Element of the General Plan.
The road is currently improved to four lanes at the approaches to the bridge, narrowing to two
lanes across the bridge itself. The current roadway section varies from 36 feet to 94 feet. On
eastbound Poinsettia lane at Avenida Encinas there is a dedicated left turn lane, two through-
lanes, and a shared right turn lane. On Poinsettia Lane at Carlsbad Boulevard, there is a
dedicated right turn lane and a dedicated left turn lane. Although the existing bridge was
constructed with only two lanes, the embankments were constructed to accommodate the
ultimate right-of-way necessary for a four lane roadway. The existing bridge was constructed on
the southerly half of the embankments, leaving the northern half vacant and available for future
o
CDP 99-30 - POINSETTIATANE BRIDGE WIDENING
January 5, 2000
Page 2
expansion. A total right-of-way of 130 feet is provided on the top of the embankments. The
existing bridge is a three-span structure, approximately 142 feet in length and 45 feet wide. It
provides 23 feet of vertical clearance above the railroad tracks.
The proposed project would widen the bridge to 76 feet, including four 12-foot traffic lanes, two
bicycle lanes varying in width from 5 to 8 feet, two five-foot sidewalks, and a raised center
median. All widening will occur on the northern half of the right-of-way. The existing bridge
will become the eastbound lanes and the new bridge will carry the westbound lanes. The
approaches to the bridge would be widened and restriped accordingly. Landscaping will be
provided in the median-and on the embankments. The sidewalks will be separated from the
traffic lanes by concrete safety barriers from 2 to 3 feet in height. A 12 inch water line and 8 inch
recycled water line will be undergrounded beneath the new roadway. Drainage improvements
will be installed. The project will involve minimal earth moving. Pile driving will be necessary
to install the structural supports for the new bridge.
The project is subject to the following regulations and requirements:
A. Carlsbad General Plan - Circulation Element, including Scenic Corridor Guidelines
B. Mello II Segment of the Local Coastal Program and the Coastal Resource Protection
Overlay Zone - Carlsbad Municipal Code Section 21.203
C. California Environmental Quality Act and Title 19 of the Carlsbad Municipal Code.
IV. ANALYSIS
The recommendation for approval of this project was developed by analyzing the project's
consistency with the applicable policies and regulations listed above. This section will describe
the project's compliance with each regulation.
A. General Plan
The proposed project is consistent with the applicable goals, objectives and policies of the
Circulation Element of the General Plan. The Circulation Element calls for Poinsettia Lane to be
improved to Major Arterial standards, and the proposed project will accomplish that. The
proposed project will bring this reach of Poinsettia Lane to ultimate width and improvements.
Poinsettia Lane is designated as a Community Scenic Corridor addressed in the Scenic Corridor
Guidelines. The Guidelines state that the goal for Community Scenic Corridors is to:
• Create identifiable and visually pleasing intersections at points where scenic corridors
cross.
• Create a unique identity for individual corridors by selecting a predominant theme
tree to be used throughout the length of each corridor.
• Encourage consistency with any "theme" areas which may be designated in the
Architectural Standards through appropriate landscaping and street furniture.
• Preserve distant views of the ocean, lagoons, and back country
• Encourage special landscaped setbacks.
CDP 99-30 - POINSETTlSANE BRIDGE WIDENING
January 5, 2000
Page 3
For Poinsettia Lane the Guidelines specify Southern Magnolia as the theme tree, with Flame
Tree as a supporting tree. However, in this reach of Poinsettia Lane, from 1-5 to Carlsbad
Boulevard, the median size is limited and will not support such large trees. In addition, there are
other strong landscape elements present in the vicinity, such as the palm trees at Lakeshore
Gardens, Poinsettia Plaza, and the Campgrounds. Finally, there are some views of the ocean
from this reach of Poinsettia Lane that could be obscured by large trees with dense foliage. For
these reasons, it is recommended that the landscaping for the bridge emphasize small palm trees,
shrubs and groundcovers. This landscape treatment will provide visual continuity with adjacent
landscaping and will preserve existing views from the road. There is currently minimal
landscaping of the existing bridge, and the added landscaping that will occur with the project will
create a significant visual improvement for this reach of Poinsettia Lane.
Regarding other aspects of the Scenic Corridor Guidelines, the bridge is a point at which two
scenic corridors cross (Poinsettia Lane and the San Diego Northern railroad tracks). A third
scenic corridor, Carlsbad Boulevard, is immediately adjacent. Views from the train and Carlsbad
Boulevard will not be negatively affected and will, in fact, be enhanced by the addition of
landscaping. There is no architectural theme for this area that is applicable to the bridge
structure. The appearance of the new bridge will duplicate the existing bridge, so that no overall
change in appearance will result. In addition to the landscaping provided on the bridge itself,
special landscaped setbacks will be provided along Poinsettia Lane (20 feet) and Carlsbad
Boulevard (40 feet) by the Poinsettia Properties Specific Plan.
B. Mello II Segment of the Local Coastal Program and the Coastal Resource Protection Overlay
Zone
Policy 5-5 of the Mello II Segment specifically address Poinsettia Lane within the Coastal Zone.
It states "Poinsettia Lane should be completed as a major arterial as indicated on the Local
Coastal Program map by 1995. It should also provide direct coastal access to Carlsbad
Boulevard. No assessment of agricultural lands shall be made to support this road extension."
Therefore, implementation of the project will satisfy this policy of the Mello II Segment. No
active agricultural land remains in the vicinity of the bridge.
A small amount of coastal sage scrub has grown on the bridge embankments since their
construction in 1984. Impacts to this vegetation have been analyzed with respect to the policies
in the Coastal Resource Protection Overlay Zone. None of the vegetation to be impacted is on
slopes greater than 25%, and therefore the standard for "dual criteria" slopes does not apply.
There are no gnatcatchers or other listed or sensitive species in the impact area. The vegetation
is of poor quality and not meriting onsite preservation. The wildlife agencies have visited the
site and concur that the impact qualifies as a "de minimus" impact. The impacts to 0.34 acres of
coastal sage scrub will be mitigated at a 1:1 ratio at the City's proposed mitigation bank at Lake
Calavera.
Documented vernal pools exist nearby on the railroad right-of-way. The location of the vernal
pools has been carefully mapped. They will be fenced during construction to prevent any
construction-related impacts. Erosion control measures will be implemented during construction
to prevent any runoff from the construction area entering the pools. After construction, the
hydrologic regime of the pools will not be altered because the existing bridge embankments will
remain virtually unchanged. Runoff from the new roadway will be directed into new drainage
iff,/CDP 99-30 - POINSETTIA"LANE BRIDGE WIDENING
January 5, 2000
Page 4
structures, so there will be no pollutant impact to the pools. In conclusion, all aspects of the
Coastal Resource Protection Overlay Zone are being complied with.
V. ENVIRONMENTAL REVIEW
The initial study (ElA Part II) submitted for the project indicated that potentially significant
impacts could occur with respect to biological resources and noise. The California
Environmental Quality Act indicates that a Mitigated Negative Declaration be prepared in such a
case if revisions in the project plans or proposals made by, or agreed to by, the applicant before
the proposed negative declaration is released for public review would avoid the effects or
mitigate the effects to a point where clearly no significant effect on the environment would
occur. The applicant in this case has revised the plans to reduce impacts to biological resources
and to reduce construction noise impacts. The revisions were incorporated into the project prior
to the documents being circulated to the public for review. The revisions and proposed
mitigation measure reduce the potential impacts to a less than significant level. In consideration
of the foregoing, a Mitigated Negative Declaration was issued by the Planning Director on
November 23, 1999. A notice was placed in the newspaper and mailed to the County Clerk,
responsible and trustee agencies, and interested individuals. No comments were received during
the 30 day comment period.
ATTACHMENTS:
1. Planning Commission Resolution No. 4715 (Mitigated Neg. Dec.)
2. Planning Commission Resolution No. 4716 (CDP)
3. Location Map
4. Mitigated Negative Declaration and PII (previously distributed)
5. Reduced Exhibit
6. Exhibit "A"
DR:mh