HomeMy WebLinkAbout2024-01-09; Municipal Water District; ; Authorize additional contingency funds for the Pressure-Reducing Station Replacement Phase 2 ProjectCA Review GH
Meeting Date: Jan. 9, 2024
To: President and Board Members
From: Scott Chadwick, Executive Manager
Staff Contact: Emily Hasegawa, Engineering Manager
emily.hasegawa@carlsbadca.gov, 442-339-5763
Dave Padilla, District Engineer
dave.padilla@carlsbadca.gov, 442-339-2356
Subject Authorize additional contingency funds for the Pressure-Reducing Station
Replacement Phase 2 Project
Districts: 2 and 3
Recommended Action
Adopt a Carlsbad Municipal Water District Board of Directors resolution authorizing additional
contingency funds and increasing the Executive Manager’s authority for approval of change
orders by $345,300 to the revised amount of $870,000 for the Pressure-Reducing Station
Replacement Phase 2 Project.
Executive Summary
The Carlsbad Municipal Water District (CMWD) has been replacing pressure-reducing stations
to replace aging infrastructure and add needed redundancy to the potable water distribution
system. The project includes abandoning two water pressure-reducing stations and
constructing three new pressure-reducing stations and approximately 2,500 feet of potable
water pipeline on El Fuerte Street, Palomar Airport Road and Melrose Drive.
The project is currently under construction, and additional costs have been incurred for CMWD-
-initiated design changes, unanticipated field conditions, changes in materials and staff time.
Staff estimate the contingency budget set at the time of contract award will be exceeded.
The CMWD Board authorized the Executive Manager to execute change orders for the project
up to $524,700. Staff recommend that the CMWD Board authorize an increase in construction
contingency funds in the amount of $345,300 for the CMWD-initiated design change and
unforeseen conditions and increase the authority delegated to the Executive Manager to
approve change orders to an increased total of $870,000.
The CMWD-initiated design change included an increase in the size of 1,845 feet of pipe to 16
inches in diameter when a 12-inch diameter pipe was in the original scope of work. This change
was necessary to maintain adequate system capacity.
There is adequate funding in the project budget to cover this increase, so no additional
appropriation is required.
Jan. 9, 2024 Item #4 Page 1 of 6
MUNICIIPAL WATER D IISTRIC'f
Staff Report
Discussion
The CMWD Board of Directors approved the project on April 18, 2023, by adopting Resolution
No. 1703, which awarded a contract to CCL Contracting, Inc. for construction of the Pressure-
Reducing Station Replacement Project Phase 2, Capital Improvement Program, or CIP, Project
No. 5020-B. The construction contract amount was $3,497,740, and the construction
contingency established at the time of contract award was $524,700.
The project has incurred additional construction costs due to the following changes or field
conditions:
• The CMWD-initiated increase of the pipe diameter from 12 inches to 16 inches for 1,845
lineal feet
• Hard-rock conditions which increased the excavation effort
• Need for additional potholes to be dug to confirm the limits and materials for pipeline
connections
• Additional paving needed to accommodate a wider trench
• Increased material costs
The construction project is 41% complete and change orders to date total $390,111 with
$134,589 remaining for contingencies. Staff estimate an additional contingency amount of
$345,300 will be needed to complete the project, in addition to the remaining $134,589, for a
combined total of $480,000 or 12% of construction costs to date.
The total estimated amount of $870,000 for needed change orders through completion will
exceed the contingency amount set when the contract was awarded by $345,300. Carlsbad
Municipal Code Section 3.28.040(C)(5) provides that the City Manager’s authority to approve
project change orders is set when the underlying contract is awarded, and the proposed
increase exceeds the City Manager’s previously approved authority.
The CMWD Board is the awarding authority for change orders beyond the contingency amount
set when the contract was awarded, under Carlsbad Municipal Code Section 3.28.040(D)(3).
The CMWD Board may delegate other duties or powers to the Executive Manager by resolution
under Carlsbad Municipal Code Section 2.12.035(L).
Staff recommend that the CMWD Board authorize an additional $345,300 for contingency
funds and increase the delegated authority to the Executive Manager to approve change orders
up to a total of $870,000.
Jan. 9, 2024 Item #4 Page 2 of 6
Fiscal Analysis
Additional funds are available in the project budget to support the requested action. The table
below summarizes the appropriations and expenditures to date and the estimated remaining
expenditures.
Pressure-Reducing Station Replacement Phase 2
CIP Project No. 5020-B
Total appropriation to date $6,431,040
Total expenditures and encumbrances to date -$5,554,261
Total available funds $876,779
Estimated future change orders -$480,000
Additional engineering services during construction (estimated) -$30,000
Additional staff time (estimated) -$40,000
Estimated additional project costs -$550,000
Remaining balance $326,779
Additional appropriation needed $0
Next Steps
Upon CMWD Board approval of additional contingency funds and authorization of an increase
to the Executive Manager’s delegated authority to approve change orders in the amount of
$345,300 to the revised amount of $870,000 for the project, staff will continue to manage the
project through completion, which is estimated to be in summer 2024.
Environmental Evaluation
The City Planner has determined that this project classifies as a maintenance project and is
exempt from environmental review according to California Environmental Quality Act
Guidelines sections 15302 – Replacement or reconstruction of existing facilities. None of the
exceptions described in Section 15300.2 apply to this project. A notice of exemption was filed
on Jan. 26, 2023, with the San Diego County Clerk (File # 2023-000055) in compliance with
Section 21152(b) of the California Public Resources Code.
Exhibits
1. Carlsbad Municipal Water District Board resolution
2. Location map
Jan. 9, 2024 Item #4 Page 3 of 6
RESOLUTION NO. 1724
A RESOLUTION OF THE BOARD OF DIRECTORS OF THE CARLSBAD
MUNICIPAL WATER DISTRICT OF THE CITY OF CARLSBAD, CALIFORNIA,
AUTHORIZING ADDITIONAL CONTINGENCY FUNDS AND INCREASING THE
EXECUTIVE MANAGER'S AUTHORITY FOR APPROVAL OF CHANGE ORDERS
BY $345,300 TO THE REVISED AMOUNT OF $870,000 FOR THE PRESSURE
REDUCING STATION REPLACEMENT PHASE 2 PROJECT
WHEREAS, on April 18, 2023, the Carlsbad Municipal Water District, or CMWD, Board of
Directors adopted Resolution No. 1703, awarding a contract to CCL Contracting, Inc., or Contractor, for
construction of the Pressure-Reducing Station Replacement Phase 2, Capital Improvement Program, or
CIP, Project No. 5020-B; and
WHEREAS, the construction contingency amount of $524,700 was set at the time of contract
award consistent with the requirements of Carlsbad Municipal Code, or CMC, Section 3.28.040(C)(5);
and
WHEREAS, the project has incurred additional construction costs due to design changes and
unanticipated field conditions; and
WHEREAS, staff estimate that additional contingency funds in the estimated amount of
$345,300 may be needed to complete the project; and
WHEREAS, the total increased contingency of $870,000 will exceed the contingency amount set
when the contract was awarded; and
WHEREAS, CMC Section 3.28.040(D){3) requires the CMWD Board of Directors to award change
orders which exceed the contingency amount set when the contract was awarded; and
WHEREAS, CMC Section 2.12.035{L) authorizes the Executive Manager to perform such other
duties and exercise such other powers as may be delegated by resolution; and
WHEREAS, the City Planner has determined that the project is exempt from the California
Environmental Quality Act, or CEQA, per State CEQA Guidelines Sections 15302 (replacement or
reconstruction of existing facilities). None of the exceptions described in CEQA Section 15300.2 are
applicable to this project. A notice of exemption was filed in the office of the San Diego County Clerk
(File# 2023-000055) in compliance with Section 21152 (b) of the Public Resources Code.
Exhibit 1
Jan. 9, 2024 Item #4 Page 4 of 6
NOW, THEREFORE, BE IT RESOLVED by the Carlsbad Municipal Water District Board of Directors
of the City of Carlsbad, California, as follows:
1.That the above recitations are true and correct.
2.That the contingency amount for the Pressure-Reducing Station Replacement Phase 2,
CIP Project No. 5020-B, is increased by $345,300 for an increased total contingency
amount of $870,000.
3.That the Executive Manager's delegated authority to award construction change orders
is increased to a total of $870,000.
PASSED, APPROVED AND ADOPTED at a Special Meeting of the Board of Directors of the
Carlsbad Municipal Water District of the City of Carlsbad on the 9th day of January, 2024, by the
following vote, to wit:
AYES:
NAYS:
ABSTAIN:
ABSENT:
Blackburn, Bhat-Patel, Acosta, Burkholder, Luna.
None.
None.
None.
KEITH BLACKBURN, President
SHERRY FREISINGER, Secretary
(SEAL)
Jan. 9, 2024 Item #4 Page 5 of 6
LOCATION MAP
PROJECT NAME PROJECT EXHIBIT
NUMBER
Exhibit 2
-BJan. 9, 2024 Item #4 Page 6 of 6
LOWER EL
¼FUERTE SITE
NOT TO SCALE
MELROSE
SITE
CORINTIA
SITE
VICINITY MAP
PHASE 2 PRESSURE REDUCING
STATION REPLACEMENTS
LOWER EL FUERTE PRS SITE
5020 2
Tammy Cloud-McMinn
From:
Sent:
To:
Subject:
Item #4
Get Outlook for iOS
Sheila Cobian
Tuesday, January 9, 2024 9:30 AM
Tammy Cloud-McMinn; Ana Alarcon
FW: Question
From: Rick Green <rgreen74@sbcglobal.net>
Sent: Saturday, January 6, 2024 12:00:25 AM
To: Emily Hasegawa <Emily.Hasegawa@carlsbadca.gov>
All Receive -Agenda Item # .!L..
For the Information of the:
Jb/JjOUNCIL Date CA .,.--cc ~
CM ....::ACM _vOCM (3) _::::-
Cc: Brandon Miles <Brandon.Miles@carlsbadca.gov>; Nick De Letto <Nick.DeLetto@carlsbadca.gov>; Traffic
<traffic@CarlsbadCA.gov>; Dave Pad ii la <Dave. Pad i lla@ca rlsbadca .gov>
Subject: Re: Question
Emily,
2024 is not starting off so great on El Fuerte in La Costa. Here I am again voicing my concerns and complaints.
The city engineers and traffic and public works are not the most liked departments right now by local
residents(various city projects) and that can easily be seen and 'heard' on various local neighborhood message
boards.
1. Let's rehash the El Fuerte Pressure Reducing Project that now is set to most likely receive more funding from
a huge costly change order.See below.
AUTHORIZE ADDITIONAL CONTINGENCY FUNDS FOR THE PRESSURE-REDUCING STATION
REPLACEMENT PHASE 2 PROJECT -Adoption of a Carlsbad Municipal Water District Board of Directors
resolution authorizing additional contingency funds and increasing the Executive Manager's authority
for approval of change orders by $345,300 to the revised amount of $870,000 for the Pressure-
Reducing Station Replacement Phase 2 Project. (Staff contact: Emily Hasegawa and.Dave Padilla, Public
Works Department)
I appreciate your transparency in the previous email dated 11/15/2023 but since then a few things have
happened, or not happened per say.
A. STEEL PLATE-The steel plate is gone and the contractor filled the hole. Well it must have been filled
by Lumpy Paving Company. How hard is it to make the asphalt smooth? Like really? My 9 year old could have
done a better job. Should I speak to Ricardo Cervantes about this? Ultimately the City of Carlsbad inspectors
should have reviewed the repair. Speaking of City of Carlsbad inspectors ... I have yet to see one city vehicle in
and around the El Fuerte Project since inception. Now I understand that I don't sit outside La Costa Meadows
Elementary and watch the project take place but I am up and down El Fuerte between Corintia and Alga Roads
multiple times per day. City inspectors should be out there overseeing its selected "low bid"contractors. Am I
right?
B. TRENCH LINE-Like we previously discussed the long temporary lumpy asphalt line extending along
the center of El Fuerte between Santa Isabel Street and Corintia is to be paved at the end of the project during
La Costa Meadows elementary winter break. Winter break is just about over and nothing have been done. Is this
because of the 'rock in the waterline' issue?
1
C. Massive Construction@ Corintia and El Fuerte. This construction zone(sorry but don't know what's
going on here because local immediate vicinity residents were never told)literally in my back yard(I live on the
top of the greenbelt a few houses in) has really caused a huge mess of sorts right outside the gate of La Costa
• Ridge. What's the plan when school is back in session since the construction mess is literally at a major crossing
guard crosswalk with hundreds of parents and young kids and hundreds of vehicles too. Is the city going to
provide police to control traffic safety?
The city and your department has an obligation to inform residents AND commuters that live within an 1/8-1/4
mile from the construction zone since it affects them on various levels. Posting a message on the city website is
useless. Where are the digital signs explaining the approaching construction and timeline? I mean it shouldn't by
any means take a resident like myself to suggest these things.
Ricky Green
La Costa Ridge HOA
On Wednesday, November 15, 2023 at 09: 15:56. AM PST, Emily Hasegawa <emily.hasegawa@carlsbadca.gov> wrote:
Mr. Green,
Thank you for your email and caring about the city. As I mentioned previously, the work along El Fuerte in front of the
school is not complete and paving will be the last task. We have not allowed our Contractor to work in front of the school
during school time. The Contractor encountered rock in the waterline alignment and the noisy work of breaking
underground rock would not be great for the students' learning process. Since the Contractor has run into issues with
procurement, they plan to do that section of work during the holiday break in December.
As for the new steel plate on El Fuerte, those plates are from Vallecitos Water District. If you have any questions, please
reach out to them Ricardo Cervantes <rcervantes@vwd.org>
I am a resident too and I understand your frustration. Construction unfortunately can be inconvenient, but staff is trying to
work within our constraints to maintain our beautiful city.
Emily Hasegawa, PE, QSD
Engineering Manager
Construction Management & Inspection
Public Works Branch
City of Carlsbad
1635 Faraday Ave.
Carlsbad, CA 92008-7314
www.carlsbadca.gov
2
760-271-4193 mobile emily.hasegawa@carlsbadca.gov
-----Original Message-----
From: Ricky Green <rgreen74@sbcglobal.net>
Sent: Tuesday, November 14, 2023 11 :50 PM
To: Emily Hasegawa <Emily.Hasegawa@carlsbadca.gov>
Cc: Brandon Miles <Brandon.Miles@carlsbadca.gov>
Subject: Question
Emily,
Just following up. What's the status of El Fuerte water pressure reducing project?
Is it being overlayed during Thanksgiving break or is it going to be delayed?
Can you explain the new steel plate on El Fuerte too? I was happy to see a sign that says steel plate ahead but that's all I
was happy about.
FYI:
Residents are fed up with the way your department and city engineers are handling road projects in and around the city. If
you need to see the feedback first hand let me know and I'll provide it straight from Nextdoor.
Ricky Green
CAUTION: Do not open attachments or click o~ links unless you recognize the sender and know the content is safe.
CAUTION: Do not open attachments or click on links unless ou recognize the sender and know the content i
3