HomeMy WebLinkAboutCT 14-09; UPTOWN BRESSI RANCH; HYDRAULIC ANALYSIS REPORT; 2018-08-15Project Name: Uptown Bressic
Job Number: 17169A
Date: August 15, 2018
Prepared By: AP Hydraulic Analysis Report
Project Data
Project Title: 17169A Uptown Bressi
In support of DWG No. 502-8 CC Rev 1 -Minor
Relocation of Modular Wetland System on El Fuerte
Curb Opening Analysis
Designer:
Project Date: Wednesday, August 15, 2018
Project Units: U.S. Customary Units
Notes:
Curb and Gutter Analysis: El Fuerte Reverse D-25 Sizing 2in Dep
Notes:
Gutter Input Parameters
Longitudinal Slope of Road: 0.0780 ft/ft
Cross-Slope of Pavement: 0.0200 ft/ft
Depressed Gutter Geometry
Cross-Slope of Gutter: 0.0830 ft/ft
Manning's n: 0.0150
Gutter Width: 1.5000 ft
Width of Spread: 1.0756 ft
Gutter Result Parameters
Design Flow: 0.2000 cfs
Gutter Depression: 1.1340 in
Area of Flow: 0.0824 ftA2
Eo (Gutter Flow to Total Flow): 1.0000
Gutter Depth at Curb: 1.3921 in
Inlet Input Parameters
Inlet Location: Inlet on Grade
Inlet Type: Curb Opening
Length of Inlet: 5.0000 ft }
Local Depression: 2.0000 in
Inlet Result Parameters
Intercepted Flow: 0.2000 cfs
Bypass Flow: 0.0000 cfs
Efficiency: 1.0000
q
Hydraulic Analysis Report
Project Data
Project Title: 17169A Uptown Bressi
Designer:
Project Date: Wednesday, July 11, 2018
Project Units: U.S. Customary Units
Notes:
Curb and Gutter Analysis: El Fuerte Reverse D-25 Sizing 2in Dep
Notes:
Gutter Input Parameters
Longitudinal Slope of Road: 0.0780 ft/ft
Cross-Slope of Pavement: 0.0200 ft/ft
Depressed Gutter Geometry
Cross-Slope of Gutter: 0.0830 ft/ft
Manning's n: 0.0150
Gutter Width: 1.5000 ft
Design Flow: 0.2000 cfs
Gutter Result Parameters
Width of Spread: 1.0756 ft
Gutter Depression: 1.1340 in
Area of Flow: 0.0824 ft"2
Eo (Gutter Flow to Total Flow): 1.0000
Gutter Depth at Curb: 1.3921 in
Inlet Input Parameters
Inlet Location: Inlet on Grade
Inlet Type: Curb Opening
Length of Inlet: 5.0000 ft
Local Depression: 2.0000 in
Inlet Result Parameters
Intercepted Flow: 0.2000 cfs
Bypass Flow: 0.0000 cfs
Efficiency: 1.0000
RErrr,,Eo
1-iuG O 1 2018
LAND Ot:\Lc~_;PMENT
ENGINEERING