HomeMy WebLinkAbout2024-05-14; City Council; Resolution 2024-099RESOLUTION NO. 2024-099
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CARLSBAD,
CALIFORNIA, ACCEPTING BIDS AND AWARDING A CONTRACT TO AMTEK
CONSTRUCTION FOR CONSTRUCTION OF THE POINSETTIA LIFT STATION
GENERATOR REPLACEMENT PROJECT IN AN AMOUNT NOT TO EXCEED
$370,340
WHEREAS, the City Council of the City of Carlsbad, California has determined it necessary,
desirable and in the public interest to complete the Poinsettia Lift Station Generator Replacement
Project, Capital Improvement Program, or CIP, Project No. 3840-23, or Project; and
WHEREAS, on Feb. 6, 2024, the City Council adopted Resolution No. 2024-019, approving plans,
specifications, and contract documents and authorizing the City Clerk to advertise to receive bids for
construction of the Project; and
WHEREAS, on March 27, 2024, staff received eight bids in response to the bid advertisement;
and
WHEREAS, AMTEK Construction, a California corporation, submitted the lowest responsive and
responsible bid in an amount not to exceed $370,340; and
WHEREAS, Carlsbad Municipal Code Sections 3.28.040(C)(S) and 3.28.090(8) authorize the
City Manager or designee to approve change orders in an amount equal to the contingency set at the
time of project award, which is $74,000; and
WHEREAS, the City Planner has determined that the project is exempt from the California
Environmental Quality Act, or CEQA, per CEQA Guidelines Section 15302(c) -replacement or
reconstruction of existing structures and/or facilities involving negligible or no expansion of capacity.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad, California, as
follows:
1. That the above recitations are true and correct.
2. Th at the bid in the amount of $370,340 submitted by AMTEK Construction for
construction of the Poinsettia Lift Station Generator Replacement Project, CIP Project
No. 3840-23, is accepted, and the Mayor is hereby authorized to execute a contract with
AMTEK Construction.
3. That the City Manager or designee is hereby authorized to approve construction change
orders for the Poinsettia Lift Station Generator Replacement Project up to $74,000.
4. That the award of this contract is contingent upon AMTEK Construction executing the
required contract and submitting the required bonds and insurance policies, as
described in the contract, within 20 calendar days after adoption of this Resolution. The
City Manager may grant reasonable extensions of time to execute the contract and
assemble the required bonds and insurance policies.
PASSED, APPROVED AND ADOPTED at a Regular Meeting of the City Council of the City of
Carlsbad on the 14th day of May, 2024, by the following vote, to wit:
AYES:
NAYS:
ABSTAIN:
ABSENT:
BLACKBURN, BHAT-PATEL, ACOSTA, BURKHOLDER, LUNA.
NONE.
NONE.
NONE.
KEITH BLACKBURN, Mayor
SHERRY FREISINGER, City Clerk