HomeMy WebLinkAbout2024-06-18; City Council; ; Accepting Bids and Awarding Contract for the Traffic Calming Plans for Park Drive, Black Rail Road, Plum Tree Road and Carrillo Way to Quality Construction & Engineering,CA Review GH
Meeting Date: June 18, 2024
To: Mayor and City Council
From: Scott Chadwick, City Manager
Staff Contact: John Kim, City Traffic Engineer
john.kim@carlsbadca.gov, 442-339-2757
Subject: Accepting Bids and Awarding Contract for the Traffic Calming Plans for
Park Drive, Black Rail Road, Plum Tree Road and Carrillo Way to Quality
Construction & Engineering, Inc.
Districts: 1, 2, 3
Recommended Action
Adopt a resolution accepting bids and awarding a construction contract to Quality Construction
& Engineering, Inc. for the traffic calming plans for Park Drive, Black Rail Road, Plum Tree Road
and Carrillo Way, Capital Improvement Program Project No. 6070, in an amount not to exceed
$247,922.
Executive Summary
The City Council approved the project plans, specifications and contract documents for the
traffic calming plans for Park Drive, Black Rail Road, Plum Tree Road and Carrillo Way on March
26, 2024
The city has received eight bids for the project. The lowest responsive and responsible bid was
submitted by Quality Construction & Engineering, Inc. in an amount not to exceed $247,922.
Staff request that City Council accept the bids received and award the project’s construction
contract to Quality Construction & Engineering, Inc. in an amount not to exceed $247,922.
The contract requires the City Council’s approval under Carlsbad Municipal Code Sections
3.28.080(C) and 3.28.080(I)(6), which apply to purchasing for construction contracts when the
value exceeds $200,000, as this project does.
Explanation & Analysis
The Carlsbad Residential Traffic Management Program was adopted by the City Council in 2001
to address speeding concerns on residential streets. Staff have collaborated with residents on
Park Drive, Black Rail Road, Plum Tree Road and Carrillo Way to develop traffic calming plans
for each street as outlined in the program and shown in the location map in Exhibit 2. The
June 18, 2024 Item #7 Page 1 of 6
traffic calming plans for these streets have met the criteria for neighborhood support as
outlined in the program.
• The City Council approved the project’s plans, specifications, and contract documents
and authorized advertising the project for construction bids on March 26, 2024
(Resolution No. 2024-066).
• The project was then advertised using the city’s formal bidding procedures.
• Staff received eight bids for construction of the project on May 1, 2024.
• Staff reviewed the bid documents and determined the lowest responsive and
responsible bidder was Quality Construction & Engineering Inc., with a bid in an amount
not to exceed $247,922.
Staff recommend acceptance of bids and award of the construction contract to Quality
Construction & Engineering, Inc. for the project in an amount not to exceed $247,922.
Fiscal Analysis
Sufficient funding is available in the Traffic Calming Program, Capital Improvement Program
Project No. 6070, to complete the project. No additional appropriations are needed at this
time. The available funds and estimated construction costs are shown in the following table:
Traffic Calming Program
Capital Improvement Program Project No. 6070
Total appropriation to date $3,388,000
Total expenditures and encumbrances to date -$2,634,702
Total available balance $753,298
Traffic Calming for Park Drive, Black Rail Road, Plum Tree Road and Carrillo Way
Capital Improvement Program Project No. 6070
Construction contract (Quality Construction & Engineering, Inc.) -$247,922
Construction contingency -$37,200
Construction management, inspection and material testing (estimated) -$63,000
Total estimated construction costs -$348,122
Remaining balance $405,176
Additional appropriation needed $0
Carlsbad Municipal Code Sections 3.28.040(C)(5) and 3.28.090(B) authorize the City Manager or
designee to approve change orders in an amount equal to the contingency set at the time of
project award, which for this project is $37,200.
Next Steps
Once the City Council accepts bids and awards the construction contract to Quality
Construction & Engineering, Inc., staff will issue a purchase order, schedule a pre-construction
meeting with Quality Construction & Engineering, Inc. and issue a notice to proceed for
construction of the project, which is expected to commence in summer 2024.
The duration of the construction contract is 60 working days, not including rainy days and
delays from change orders that may extend the contract duration. Upon successful completion
June 18, 2024 Item #7 Page 2 of 6
of the project, which is expected to be in fall 2024, a notice of completion will be recorded to
release bonds issued for the project.
Environmental Evaluation
The City Planner, through the process outlined in Carlsbad Municipal Code Section 19.04.060,
has determined that this project is exempt from the California Environmental Quality Act
pursuant to California Code of Regulations Section15301(c), which covers the repair,
maintenance, or minor alteration of existing public structures or facilities involving negligible or
no expansion of use. The improvements to these streets involve negligible expansion of the
current use. A notice of exemption was filed with the San Diego County Clerk and the California
State Clearinghouse on May 9, 2024.
Exhibits
1. City Council resolution
2. Location map
June 18, 2024 Item #7 Page 3 of 6
RESOLUTION NO. 2024-137
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CARLSBAD,
CALIFORNIA, ACCEPTING BIDS AND AWARDING A CONSTRUCTION
CONTRACT TO QUALITY CONSTRUCTION & ENGINEERING, INC. FOR THE
TRAFFIC CALMING PLANS FOR PARK DRIVE, BLACK RAIL ROAD, PLUM TREE
ROAD AND CARRILLO WAY, CAPITAL IMPROVEMENT PROGRAM PROJECT
NO. 6070, IN AN AMOUNT NOT TO EXCEED $247,922
WHEREAS, the City Council of the City of Carlsbad, California, has determined it is necessary,
desirable and in the public interest to construct the Traffic Calming Plans for Park Drive, Black Rail Road,
Plum Tree Road and Carrillo Way, Capital Improvement Program, or CIP, Project No. 6070; and
WHEREAS, the city contracted with STC Traffic, Inc., a traffic engineering firm, to develop the
construction plans, cost estimate and specifications; and
WHEREAS, city engineering staff reviewed the plans, cost estimate and specification developed
by STC Traffic and determined that the work met the city's engineering codes, standards, and policies,
and that the proposed work to reduce roadway speed on Park Drive, Black Rail Road, Plum Tree Road
and Carrillo Way; and
WHEREAS, on March 26, 2024, the City Council adopted Resolution No. 2024-066, approving he
plans, specifications and contract documents and authorizing advertisement of the project for bids for
construction; and
WHEREAS, on May 1, 2024, staff received eight bids for construction of the project; and
WHEREAS, Quality Construction & Engineering, Inc. submitted the lowest responsive and
responsible bid to construct the project, in an amount not to exceed $247,922; and
WHEREAS, sufficient funding in the Traffic Calming Program account is available to complete
the project; and
WHEREAS, Carlsbad Municipal Code, or CMC, Sections 3.28.080(C) and 3.28.080(1)(6), which
cover purchasing in construction contracts, require that the City Council award all formally bid contracts
when the value exceeds $200,000; therefore, the project is subject to this requirement; and
WHEREAS, CMC Sections 3.28.040(C)(S) and 3.28.090(8) authorize the City Manager or
designee to approve change orders in an amount equal to the contingency set at the time of project
award, which is $37,200 for the project; and
WHEREAS, the City Planner, through the process outlined in CMC Section 19.04.060, has
determined that this project is exempt from the California Environmental Quality Act, or CEQA, pursuant
Exhibit 1
June 18, 2024 Item #7 Page 4 of 6
to California Code of Regulations Section15301(c), which covers the repair, maintenance, or minor
alteration of existing public structures or facilities involving negligible or no expansion of use. The
improvements to these streets involve negligible expansion of the current use. A Notice of Exemption
was filed with the San Diego County Clerk and State Clearinghouse on May 9, 2024.
follows:
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad, California, as
1.That the above recitations are true and correct.
2.That the lowest bid of $247,922 submitted by Quality Construction & Engineering, Inc.
for construction of the Traffic Calming Plans for Park Drive, Black Rail Road, Plum Tree
Road and Carrillo Way, CIP Project No. 6070, is accepted, and the Mayor is authorized
to execute the contract for the project.
3.That the City Manager or designee is authorized to approve construction change orders
up to $37,200 for the project.
4.That the award of this contract is contingent upon Quality Construction & Engineering,
Inc. executing the required contract and submitting the required bonds and insurance
policies, as described in the contract, within 20 calendar days after adoption of this
Resolution. The City Manager may grant reasonable extensions of time to execute the
contract and assemble the required bonds and insurance policies.
PASSED, APPROVED AND ADOPTED at a Regular Meeting of the City Council of the City of
Carlsbad on the 18th day of June, 2024, by the following vote, to wit:
AYES:
NAYS:
ABSENT:
ABSTAIN:
BLACKBURN, BHAT-PATEL, ACOSTA, LUNA.
NONE.
NONE.
BURKHOLDER.
June 18, 2024 Item #7 Page 5 of 6
1
2
LOCATION MAP
4
2
3
Exhibit 2
June 18, 2024 Item #7 Page 6 of 6
PROJECT LOCATION
1. Parle Dr
2. Black Rail Rd
3. Plum Tree Rd
4. Carrillo Way
@
NOT TO SCALE
TRAFFIC CALMING EXHIBIT
Parle Dr, Black Rail Rd, Plum Tree Rd and Carrillo Way