HomeMy WebLinkAbout2024-06-18; City Council; Resolution 2024-149RESOLUTION NO. 2024-149
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CARLSBAD,
CALIFORNIA, DETERMINING THAT THE FISCAL YEAR 2024-25 CAPITAL
IMPROVEMENT PROGRAM IS CONSISTENT WITH THE GENERAL PLAN
AND APPLICABLE CLIMATE ACTION PLAN MEASURES AND ACTIONS
WHEREAS, the City Council of the City of Carlsbad, California ha s reviewed the Capital
Improvement Program for FY 2024-25 and has held such public hearings as are necessary prior to
adoption of the Capital Improvement Program; and
WHEREAS, on June 18, 2024, the City Council reviewed for consistency with the General Plan
goals and policies all Capital projects receiving an allocation of funds for FY 2024-25 pursuant to
Carlsbad Municipal Code Section 2.24.040(8); and
WHEREAS, the City Council also reviewed the FY 2024-25 Capital Improvement Program
projects for consistency with applicable Climate Action Plan measures and actions; and
WHEREAS, upon hearing and considering all testimony and arguments, if any, of all persons
desiring to be hea rd, the City Council considered all factors relating to the City Council determination.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Carlsbad, California, as
follows:
1. That the above recitations are true and correct.
2. That based on the evidence presented at the hearing, the City Council
determines that the Capital Improvement Program for FY 2024-25 is consistent with the General Plan
based on the following findings:
a) The projects are consistent with the goals and policies of the city's
General Plan in that the projects are required to ensure the provision of adequate public facilities and
services concurrent with or prior to need.
b} The projects are consistent with applicable goals and policies of the Arts,
History, Culture, and Education; Land Use and Community Design; Mobility; Public Safety; and
Sustainability Elements, as described in Attachment A.
c} Specific projects are consistent with, and support Climate Action Plan
greenhouse gas reduction measures and actions, if applicable, as described in Attachment A.
d} As required by the General Plan, the proposed improvements are
consistent with the city's Growth Management Plan in that the projects ensure that the necessary
improvements are provided for facilities maintenance, park development, recycled water, sewer and
storm drain projects, and circulation systems, in accordance with the performance standards contained
in the city's Growth Management regulations.
3. This action is final as of the date this resolution is adopted by the City Council.
The Provisions of Chapter 1.16 of the Carlsbad Municipal Code, "Time Limits for Judicial Review" shall
apply:
"NOTICE"
The time within which judicial review of this decision must be sought is governed by Code of Civil
Procedure, Section 1094.6, which has been made applicable in the City of Carlsbad by Carlsbad
Municipal Code Chapter 1.16. Any petition or other action seeking review must be filed in the
appropriate court not later than the ninetieth day following the date on which this decision becomes
final; however, if within ten days after the decision becomes final a request for the record is filed with
a deposit in an amount sufficient to cover the estimated cost or preparation of such record, the time
within which such petition may be filed in court is extended to not later than the thirtieth day following
the date on which the record is either personally delivered or mailed to the party, or his attorney of
record, if he has one. A written request for the preparation of the record of the proceedings sha ll be
filed with the City Clerk, City of Carlsbad, 1200 Carlsbad Village Drive, Carlsbad, CA 92008.
PASSED, APPROVED AND ADOPTED at a Joint Special Meeting of the City Council of the City of
Carlsbad, the Board of Directors of the Carlsbad Municipal Water District, the Board of Directors of the
Carlsbad Public Financing Authority, the Community Development Commission, and the City Council as
Successor Agency to the Carlsbad Redevelopment Agency held on the 18th day of June, 2024, by the
following vote, to wit:
AYES :
NAYS:
ABSTAIN:
ABSENT:
BLACKBURN, BHAT-PATEL, ACOSTA, BURKHOLDER, LUNA.
NONE.
NONE.
NONE.
Attachment A
NEW CAPITAL IMPROVEMENT PROJECTS
Carlsbad Municipal Water District Building
and Site Improvements
Council District: 2
Managing Department:
Utilities
Budget Category:
Maintenance
Funding Source:
Water, Recycled Water and
Sewer Replacement Funds
Budget
FY25 $ 600,000
FY26 $ 200,000
TOTAL $ 800,000
About This Project
Interior and exterior building, warehouse and site improvements for storage, site security, charging
station for electric vehicle and forklift, paving for materials storage and electric forklift operation,
restroom, locker room, drinking fountain, and remodel of interior finishes.
Project Need
The office building and warehouse need remodeling and new amenities for safety, security, storage, and
privacy and to accommodate electric vehicle charging.
General Plan Consistency
Goal 2-G.21 of the Land Use & Community Design Element: Ensure that adequate public facilities and
services are provided in a timely manner to preserve the quality of life of residents.
Climate Action Plan Consistency
This project is consistent with Measure L, Increase zero-emission vehicle travel.
Anticipated Environmental Review
The project is exempt from environmental review per CEQA Guidelines Section 15301(a) – Minor
alteration of existing facilities, including exterior alterations, that involve negligible or no expansion of
use.
June 18, 2024 Item #11 Page 473 of 625
Carlsbad Water Recycling Facility
Improvements
Council District: 3
Managing Department: Utilities
Budget Category: Maintenance
Funding Source: Recycled Water
Replacement, Recycled Water
Connection Funds
Budget
FY25 $ 350,000
TOTAL $ 350,000
About This Project
Feasibility study to evaluate best available technologies for future equipment upgrades and forecasted
recycled water demands in the event of reduced supply from alternative sources.
Project Need
The study will evaluate best available technologies and capacities for recycled water production at
CWRF and supplementation with alternative sources.
General Plan Consistency
Goal 9-G.4 of the Sustainability Element: Reduce the city’s reliance on imported water.
Climate Action Plan Consistency
This project is consistent with Measure N, Reduce the GHG intensity of water supply conveyance,
treatment and delivery.
Anticipated Environmental Review
The feasibility study itself would not be defined as a “project” under CEQA (CEQA Guidelines Section
15378 (b)(5)), but the proposed project that results from the study will need further environmental
analysis. It is likely environmental review could range from a CEQA exemption (project is exempt from
environmental review) to a Mitigated Negative Declaration (project has environmental impacts that can
be mitigated).
June 18, 2024 Item #11 Page 474 of 625
Downtown Tile Replacement
Council District: 1
Managing Department:
Transportation
Budget Category: Maintenance
Funding Source: Infrastructure
Replacement Fund
Budget
FY25 $ 250,000
TOTAL $ 250,000
About This Project
Sidewalk tiles are antiquated, damaged or broken and are detaching in multiple locations throughout
the Village area and along portions of Carlsbad Boulevard.
Project Need
Damaged tiles are a safety concern and may create potential tripping hazards.
General Plan Consistency
Policy 3-P.26 of the Mobility Element: Identify and implement necessary pedestrian improvements on
streets where pedestrians are to be accommodated per Table 3-1, with special emphasis on providing
safer access to schools, parks, community and recreation centers, shopping districts, and other
appropriate facilities.
Climate Action Plan Consistency
Not applicable.
Anticipated Environmental Review
The project is exempt from environmental review per CEQA Guidelines Section 15301(c) – Existing
Facilities. Exempted are existing highways and streets, sidewalks, gutters, bicycle and pedestrian trails,
and similar facilities (this includes road grading for the purpose of public safety), and other alterations
such as the addition of bicycle facilities, including but not limited to bicycle parking, bicycle-share
facilities and bicycle lanes, transit improvements such as bus lanes, pedestrian crossings, street trees,
and similar alterations that do not create additional automobile lanes.
June 18, 2024 Item #11 Page 475 of 625
Fire Station 5 Renovation
Council District: 2
Managing Department:
Facilities
Budget Category: Maintenance
Funding Source: Infrastructure
Replacement Fund
Budget
FY25 $ 150,000
FY25 $ 2,000,000
TOTAL $ 2,150,000
About This Project
Replace roof, renovate kitchen, exterior finishes, remodel bathrooms, replace apparatus bay door and
remove epoxy flooring, interior and exterior finishes.
Project Need
Many of the building systems have reached the end of their useful life cycle.
General Plan Consistency
Goal 2-G.21 of the Land Use & Community Design Element: Ensure that adequate public facilities and
services are provided in a timely manner to preserve the quality of life of residents.
Climate Action Plan Consistency
Not applicable.
Anticipated Environmental Review
The project is exempt from environmental review per CEQA Guidelines Section 15301(a) – Minor
alteration of existing facilities, including exterior alterations, that involve negligible or no expansion of
use.
June 18, 2024 Item #11 Page 476 of 625
Flower Fields Overlook Sidewalk Replacement
Council District: 2
Managing Department:
Transportation
Budget Category: Maintenance
Funding Source: Infrastructure
Replacement Fund
Budget
FY25 $ 250,000
TOTAL $ 250,000
About This Project
Sidewalk replacement with root and base modification.
Project Need
Aging trees are lifting the sidewalk in multiple areas causing tripping hazards and safety concerns
throughout the entire walkway. The area is a high foot traffic walkway and is a high tourism location.
General Plan Consistency
Policy 3-P.26 of the Mobility Element: Identify and implement necessary pedestrian improvements on
streets where pedestrians are to be accommodated per Table 3-1, with special emphasis on providing
safer access to schools, parks, community and recreation centers, shopping districts, and other
appropriate facilities.
Climate Action Plan Consistency
Not applicable.
Anticipated Environmental Review
The project is exempt from environmental review per CEQA Guidelines Section 15301(c) – Existing
Facilities. Exempted are existing highways and streets, sidewalks, gutters, bicycle and pedestrian trails,
and similar facilities (this includes road grading for the purpose of public safety), and other alterations
such as the addition of bicycle facilities, including but not limited to bicycle parking, bicycle-share
facilities and bicycle lanes, transit improvements such as bus lanes, pedestrian crossings, street trees,
and similar alterations that do not create additional automobile lanes.
June 18, 2024 Item #11 Page 477 of 625
Green Paint Maintenance
Council District: Citywide
Managing Department: Transportation
Budget Category: Maintenance
Funding Source: General Capital Construction
Budget
FY25 $ 250,000
TOTAL $ 250,000
About This Project
As part of the Safer Streets Together program, the city installed painted green bike lanes in various
locations throughout the city. Green paint maintenance is expected to range from annual to bi-annual
service per location, depending on the paint lifespan. Green paint locations are projected to grow
exponentially as the city strives to promote safe routes to school and continue implementing paint
upgrades to our roadways.
Project Need
Green paint lifespan is dramatically lower than other intersection paint due to the frequency of turning
and slowing vehicles, degrading the paint. Our in-house efforts are projected not to be able to perform
the required maintenance, i.e., refreshing the paint. Staff project nearly ¾ to all green paint refreshing
services will have to be contracted out.
General Plan Consistency
Policy 3-P.25 of the Mobility Element: Implement the projects recommended in the pedestrian, trails
and bicycle master plans through the city’s capital improvement program, private development
conditions and other appropriate mechanisms.
Climate Action Plan Consistency
This project is consistent with Measure K, Promote Transportation Demand Management.
Anticipated Environmental Review
The project is exempt from environmental review per CEQA Guidelines Section 15301(c) – Existing
Facilities. Exempted are existing highways and streets, sidewalks, gutters, bicycle and pedestrian trails,
and similar facilities (this includes road grading for the purpose of public safety), and other alterations
such as the addition of bicycle facilities, including but not limited to bicycle parking, bicycle-share
facilities and bicycle lanes, transit improvements such as bus lanes, pedestrian crossings, street trees,
and similar alterations that do not create additional automobile lanes.
June 18, 2024 Item #11 Page 478 of 625
La Costa Avenue Box Culvert Cleaning
Council District: 4
Managing Department:
Transportation
Budget Category: Maintenance
Funding Source: General
Capital Construction
Budget
FY25 $ 275,000
TOTAL $ 275,000
About This Project
Feasibility study to evaluate and assess the scope of necessary debris removal and other culvert clearing
activities in order to develop the project design and determine permitting requirements.
Project Need
The project is needed to clean an impacted storm drain asset.
General Plan Consistency
Goal 6-G.1 of the Public Safety Element: Minimize injury, loss of life, and damage to property resulting
from fire, flood, sea-level rise, hazardous material release, or seismic disasters.
Climate Action Plan Consistency
Not applicable.
Anticipated Environmental Review
The feasibility study itself would not be defined as a “project” under CEQA (CEQA Guidelines Section
15378 (b)(5)), but the proposed project that results from the study will need further environmental
analysis. It is likely environmental review could range from a CEQA exemption (project is exempt from
environmental review) to a Mitigated Negative Declaration (project has environmental impacts that can
be mitigated).
June 18, 2024 Item #11 Page 479 of 625
Magee Park Building Restoration
Council District: 1
Managing Department:
Facilities
Budget Category: Maintenance
Funding Source: Infrastructure
Replacement Fund
Budget
FY25 $ 200,000
TOTAL $ 200,000
About This Project
Perform select restoration work to several of the buildings in the park. The work consists mostly of
repairing termite damage and minor refurbishing of existing systems. Work will be within the footprint
of existing facilities and is characterized as in-kind replacement.
Project Need
Restoration work is needed per the condition assessment.
General Plan Consistency
Policy 7-P.5 of the Arts, History, Culture, and Education Element: Encourage the rehabilitation of
qualified historic structures through application of the California Historical Building Code.
Climate Action Plan Consistency
Not applicable.
Anticipated Environmental Review
The project is exempt from environmental review per CEQA Guidelines Section 15301(a) – Minor
alteration of existing facilities, including exterior alterations, that involve negligible or no expansion of
use.
June 18, 2024 Item #11 Page 480 of 625
Parks Maintenance Program
Council District: Citywide
Managing Department: Parks
Budget Category: Maintenance
Funding Source: Infrastructure Replacement
Fund
Budget
FY25 $ 644,000 design
$1,503,000 construction
TOTAL $ 2,147,000
About This Project
This program will address ongoing maintenance and infrastructure needs for parks and recreation. The
types of work that will be done under this project include design and construction of sidewalk
replacements within the park footprint, tennis court lighting, existing playground re-surfacing and
replacement in kind of playground equipment, fencing replacements, and lighting controller
replacements.
Project Need
Various parks and recreation facilities are in need of ongoing maintenance updates throughout the city.
General Plan Consistency
Policy 4-G.6 of the Open Space, Conservation, and Recreation Element: Offer a wide variety of
recreational activities and park facilities designed to encourage educational benefits and active or
passive participation by users of all ages and interests.
Climate Action Plan Consistency
Not applicable.
Anticipated Environmental Review
The project is exempt from environmental review per CEQA Guidelines Section 15301(a) – Minor
alteration of existing facilities, including exterior alterations, that involve negligible or no expansion of
use.
June 18, 2024 Item #11 Page 481 of 625
District
□• o, o,
□•
Paseo Del Norte Pedestrian and Bike
Improvements
Council District: 3
Managing Department:
Transportation
Budget Category: Capital
Project
Funding Source: Gas Tax, State
Grant
Budget FY25 $ 180,000
TOTAL $ 180,000
About This Project
This project will enhance pedestrian and bike safety on Paseo Del Norte between Palomar Airport Road
and Sea Gate Road by reducing the number of travel lanes from four to two, adding bike buffers,
widening bike lanes and adding an uncontrolled crosswalk in the vicinity of Tip-Top Meat and Motel 6.
Project Need
This project was identified in the city’s Local Roadway Safety Plan as one of the priority safety
improvement projects. The project has been selected by Caltrans for the Highway Safety Improvement
Program (HSIP) fund in the amount of $593,900 for design and construction of the project with a
requirement of 10% local matching funds.
General Plan Consistency
Policy 3-P.17 of the Mobility Element: Consider innovative design and program solutions to improve the
mobility, efficiency, connectivity, and safety of the transportation system. Innovative design solutions
include, but are not limited to, traffic calming devices, roundabouts, traffic circles, curb extensions,
separated bicycle infrastructure, pedestrian scramble intersections, high visibility pedestrian treatments
and infrastructure, and traffic signal coordination...
Climate Action Plan Consistency
This project is consistent with Measure K, Promote Transportation Demand Management.
Anticipated Environmental Review
The project is exempt from environmental review per CEQA Guidelines Section 15301(c) – Existing
Facilities. Exempted are existing highways and streets, sidewalks, gutters, bicycle and pedestrian trails,
and similar facilities (this includes road grading for the purpose of public safety), and other alterations
such as the addition of bicycle facilities, including but not limited to bicycle parking, bicycle-share
facilities and bicycle lanes, transit improvements such as bus lanes, pedestrian crossings, street trees,
and similar alterations that do not create additional automobile lanes.
June 18, 2024 Item #11 Page 482 of 625
Police and Fire Headquarters Parking Lot and
Exterior Improvements
Council District: 2
Managing Department:
Facilities
Budget Category: Maintenance
Funding Source: Infrastructure
Replacement Fund
Budget
FY25 $ 120,000
TOTAL $ 120,000
About This Project
Secure the northeasterly 24 parking spots of the parking lot between the Police and Fire Headquarters
and Skate Park and create access improvements to the southeasterly access point of the Police and Fire
Headquarters building. Install fencing, improved lighting, secured access and hardscape improvements.
Project Need
Project will increase security and improve access in the parking lot.
General Plan Consistency
Goal 2-G.3 of the Public Safety Element: Maintain safety services that are responsive to citizens’ needs
to ensure a safe and secure environment for people and property in the community.
Climate Action Plan Consistency
Not applicable.
Anticipated Environmental Review
The project is exempt from environmental review per CEQA Guidelines Section 15301(a) – Minor
alteration of existing facilities, including exterior alterations, that involve negligible or no expansion of
use.
June 18, 2024 Item #11 Page 483 of 625
Schools Traffic Safety Program
Council District: Citywide
Managing Department: Transportation
Budget Category: Capital Project
Funding Source: Gas Tax, Federal Grant
Budget
FY25 $ 1,100,000
TOTAL $ 1,100,000
About This Project
Install high-visibility crosswalks and speed cushions near schools with support from federal grant
funding.
Project Need
Address speed concerns on all streets designed as “School Streets” in the General Plan’s Mobility
Element.
General Plan Consistency
Policy 3-P.17 of the Mobility Element: Consider innovative design and program solutions to improve the
mobility, efficiency, connectivity, and safety of the transportation system. Innovative design solutions
include, but are not limited to, traffic calming devices, roundabouts, traffic circles, curb extensions,
separated bicycle infrastructure, pedestrian scramble intersections, high visibility pedestrian treatments
and infrastructure, and traffic signal coordination...
Climate Action Plan Consistency
This project is consistent with Measure K, Promote Transportation Demand Management.
Anticipated Environmental Review
The project is exempt from environmental review per CEQA Guidelines Section 15301(c) – Existing
Facilities. Exempted are existing highways and streets, sidewalks, gutters, bicycle and pedestrian trails,
and similar facilities (this includes road grading for the purpose of public safety), and other alterations
such as the addition of bicycle facilities, including but not limited to bicycle parking, bicycle-share
facilities and bicycle lanes, transit improvements such as bus lanes, pedestrian crossings, street trees,
and similar alterations that do not create additional automobile lanes.
June 18, 2024 Item #11 Page 484 of 625
District
□' □, o,
□•
Synthetic Turf Replacement
Council District: 1, 2, 3
Managing Department: Parks
Budget Category: Maintenance
Funding Source: Infrastructure Replacement
Fund
Budget
FY25 $ 1,800,000
FY26 $ 4,258,000
FY27 $ 1,955,000
TOTAL $ 8,013,000
About This Project
Replace synthetic turf fields at the following parks: Alga Norte, Aviara, Poinsettia, and Pine.
Project Need
Synthetic turf fields have an expected useful life of 10 years. The fields at these locations will have
reached the end of useful life and will need to be replaced.
General Plan Consistency
Goal 4-G.6 of the Open Space, Conservation, and Recreation Element: Offer a wide variety of
recreational activities and park facilities designed to encourage educational benefits and active or
passive participation by users of all ages and interests.
Climate Action Plan Consistency
Not applicable.
Anticipated Environmental Review
The project is exempt from environmental review per CEQA Guidelines Section 15301(d) – Repair,
maintenance, and minor alteration of existing facilities, including restoration of deteriorated or
damaged facilities, involving negligible or no expansion of use.
June 18, 2024 Item #11 Page 485 of 625
District
0 1 o , o ,
□•