MEMORANDUM
June 15, 1998
TO: PRINCIPAL PLANNER - CHRIS DECERBO
FROM: Engineering Technician - Michele Masterson
GDP 98-45: CARLSBAD BY THE SEA - LOT 8
COMPLETENESS AND ISSUES REVIEW
Engineering Department staff has completed a review of the above-referenced project
for application completeness. The application and plans submitted for this proposed
project are currently incomplete and unsuitable for further review due to the
following incomplete items:
\Engin&ering Completeness Items
1. Please include a vicinity map that includes major cross streets.
2. Please show on the vicinity map a north arrow.
3. Please provide the name of the sewer, water and school districts providing
service to the project.
4. Please indicate aN easements and encumbrances if applicable.
5. Please show pad elevation and finished floor elevation.
6. Show street improvements, existing and proposed.
I Engineering Issues
CDP 98-48
Carlsbad by the Sea - Lot 8
Page 2
1. The line of the drainage swale must be 5' from the building and 2' from the property
line, i.e. the house must be 7' from the property line. (Refer to Standard GS -14). As
an alternative, a letter from a registered soils engineer recommending the swale be
less than 5' from the building may be accepted.
If you have any questions, please either see or call me at extension 4315.
MICHELE MASTERSON
Engineering Technician
c: Bob Wojcik