HomeMy WebLinkAboutCT 93-07; Carrillo Ranch Villages F, G, & P; Tentative Map (CT) (3)Hofman Planning
Associates
July 8, 1993
_ . TTBrian Hunter
2015 Las Palmas Drive
Carlsbad, CA. 92009
SUBJECT: CT 93-07 - Meeting Notes From July 7, 1993
Dear Brian:
The following are the notes I took during our meeting held on Wednesday, July 7, 1993 with
you, Chris Chambers, Bob Wilkinson, Ray Martin and myself. If there is anything incorrect
in these notes, please call me or markup these notes and FAX them back to me.
PROJECT ENGINEER
Mike Shirey is the project engineer.
WEEKLY MEETINGS
The weekly meetings will be held each Wednesday at 1:00 P.M. We suggested that it may
be appropriate for Bob Wojcik to attend the next meeting as well as every third meeting.
You agreed with this suggestion(Pv&ed-k i[U> ^tscus6i*/o jal vA\c3e-2i \e> bis sVWw\ce}
ACTION NEEDED: Mike Howes to call and ask Bob Wojcik to attend our next
meeting.
INTRODUCTION TO TENTATIVE MAP
Ray Martin began the discussion on the Tentative Map by explaining the phasing. Bob
Wilkinson discussed the revision to Village G per the input obtained from Fish and Game.
According to Bob, the revisions to Village G reduced the sensitive plant impacts to 20%,
which is in compliance with State policy.
Both Village G and P are Planned Developments with Village G containing lots of 7,500
square feet or larger. There are a few lots less than 60' in width in Village G, however, this
Village will appear to be a standard R-l project. There are no lots less than 6,000 square
feet in Village P and most of the lots will have 20' rear yards. Chris Chambers mentioned
that these units will be for first time and first time move up home buyers.
The landscape plans for this Tentative Map will also show fences, monuments and signs.
Chris mentioned that we are preparing design guidelines with Terri Woods for Village O.
We are also having discussions with Terri regarding DG vs. asphalt roads for utilities and
maintenance. Ray mentioned the discussions that are on going with the Engineering
Department regarding lot drains.
ACTION NEEDED: We will provide an exhibit showing maintenance
responsibilities. We will also provide you with a copy of the design guidelines for
Village O.
AFFORDABLE HOUSING
Chris mentioned that there are two architects working on a site plan for the affordable
housing site. Ray said that the grading shown on the site is subject to change.
TRASH
It is our understanding that you will speak to Terri regarding this issue.
COMMUNITY FACILITY SITE
It is our understanding that you will work with Gary Wayne to revert back to the wording
approved by the Planning Commission.
As I mentioned earlier, please let me know if there are any errors or misunderstandings in
these notes. The purpose of providing you with these notes is to assure that after each
meeting, we have the same understanding of what we have agreed to and what has to be
done.
Sincerely,
Mike Howes
cc. Chris Chambers
Bob Wilkinson
Ray Martin