HomeMy WebLinkAboutCT 99-13; Steiner Property; Tentative Map (CT) (15)Memorandum
TO: Associate Planner, Van Lynch
FROM: Engineering Technician, David Rick
DATE: July 26, 1999
CT 99-13: Steiner Property
COMPLETENESS REVIEW
Engineering Department staff has completed a review of the above-referenced project for
application completeness. The application and plans submitted for this proposed project are
considered complete. I will conduct a review of the project for engineering issues of concern
and inform you of any outstanding issues via a separate memo.
If you or the applicant have any questions, please either see or contact me at extension 4324.
DAVID RICK
Engineering Technician
Land Development Division
PLANNING DEPARTMENT
APPLICATION SUBMITTAL CHECKLIST
(for staff use only)
The following checklist includes items required on application forms and is intended to be an easy
checkoff for application submittal. All site plans, landscape plan, elevations, floor plans and constraint
maps should be submitted on 24" x 36" sheet(s) folded to 8 V*n x 11". Plans MUST be assembled into
10 complete packets by the applicant prior to acceptance by the City. Each packet must include 1
sheet of each exhibit and all sheets must be stapled into 1 complete set.
1. tg. Complete Land Use Review Application
2. T^ Site Plan - 10 copies
3. ^ Landscape Plan - 10 copies, 4 copies for projects with four or fewer units
4. ~f3 Building Elevations and Floor Plans - 10 copies
5. ^gsj Constraints map -1 copy
6. M EIA (Fee is not required when project is obviously exempt from CEQA, i.e., for single
family homes, less than 4 units, commercial with an occupancy load of less than 30)
7. pd PFF agreement - 1 notarized original and 1 reproduced copy
8. W\ Disclosure Statement
9. JN[ Preliminary Title Report - 3 copies dated within last 6 months
10. ('[jjProof of sewer availability if located in Leucadia or Vallecitos Water Districts.
11. \f£ School letter
12. nj When parcel map submitted
^ -O Agreement to waive tentative parcel map time limits
13. Q For projects with an ADT greater than 500 vehicles per day or 200 or more peak-hour
vehicle trips
Q Circulation Impact Analysis - 2 copies
14. K^ Environmental studies which may be necessary to allow adequate environmental review
by City
Q Biology Q] Noise
•rt. Archeology Q) Soils contamination
n Traffic fj Other
15. KTJ For all projects with cut or fill depths exceeding 5 feet
Q Preliminary soils/geologic report - 2 copies
16. Lfim^or condo conversions:
[3 Statement that Map Act will be complied with
n Letter from SDG &E - plans to convert are OK
[J Copy of compliance inspection by Building Department
17. /|^L For lots exceeding 1 acre
. » Q Preliminary hydrology map and calculations
18. -(yn&rchitectural Small Lot Guidelines Compliance Summary, if applicable
19. ^ Photographs of property
20. >[7^£or planned developments on properties designated or zoned for single family
( ' development
fj Prelminary tentative map showing how property could be subdivided under
standard zoning
21. V] Notice of Time Limits on Discretionary Applications
22. §K Project Description/Explanation
Planner Date
* See specific application form for additional items
H:\Word\Deve1opment Services\Current Planning\Application Chklst 06/03/99