HomeMy WebLinkAboutCUP 154D; Pacific Bell; Conditional Use Permit (CUP) (10)TO: Van Lynch, Associate Planner
FROM: David Rick, Assistant Engineer
DATE: June 2,2000
CUP 154D: PACIFIC BELL- CAMINO VlDA ROBLE
COMPLETENESS & ISSUES REVIEW
Engineering Department staff has completed a review of the above-referenced project for
application completeness. The application and plans submitted for this proposed project are
currently incomplete and unsuitable for further review due to the following incomplete
items:
1. A Preliminary Title Report dated within the last 6 months.
The following issues need to be resolved prior to next submittal:
1.
2.
3.
4.
A grading permit will be required. The processing time for a grading permit is
approximately 3 months. The grading permit will need to be issued &the grading will
need to be completed before a building permit can be issued. In addition, the Conditional
Use Permit Amendment will need to be approved before the grading plan check process
can begin.
This site will need to be upgraded to comply with the National Pollutant Discharge
Elimination System. Show how the surface runoff within the parking lot will be filtered for
pollutants (oil, rubber, brake dust, etc.) before exiting the property. One possible method
would be to replace the concrete swale located at the west side of the property with a
grass-vegetated swale. Such a design would filter surface pollutants from the rear portion
of the parking lot. Filtration of the front portion of the parking lot needs to be addressed as
well. The existing design of cobblestone rock and ivy is insufficient for filtration. Also, the
storm drain note on the plan would only apply to inlets of which there are none.
A 5 foot wide sidewalk will need to be installed. Please show the proposed 5 foot wide
sidewalk on the grading plan. At least 48 inches of sidewalk clearance must be maintained
so the fire hydrant will probably need to be relocated. Please note that that the sidewalk
installation and the 5 foot street dedication shown on the grading plan will need to be
completed before the building permit can be issued. The processing time for the easement
dedication will take approximately 3 months. Processing of this easement dedication may
begin prior to processing of a Conditional Use Permit Amendment.
Unless the entrance gate is to be removed, show the gate and keypad on the plan.
Provide a turn around for vehicles waiting at the gate. Vehicles entering the site should not
be required to back onto Camino Vida Roble in the event that the gate does not open.
5. A water easement must be recorded over the new location for the fire hydrant and water
main. Show the existing and proposed location of the water easement and water main. A
construction change will also be required to alter the water improvement plans (DWG 348-
9). The project will be conditioned accordingly.
6. Add the Average Daily Trips generate by the proposed use on the site plan.
7. Provide additional TW and FL elevations along the wall located along the west end of the
property.
8. Is a trash receptacle located on site? If so, where is it located? Circulation for the trash
truck must be provided such the truck can exit the site in a forward position.
If you or the applicant has any questions, please either see or contact me at extension (760)
602-2781.
DAVID RICK
Development Services Division