HomeMy WebLinkAboutCUP 99-30; Cannon Court; Conditional Use Permit (CUP) (12)I
I
I
I
I
I • I
I
I
I
I
I • I
I
I • I
Hydrology and Hydraulic Calclations
Cannon Court #210-010-38
MS xxxxxx
Date: December 8,1999
Prepared for:
West Development, Inc.
Prepared by:
O'Day Consultants, Inc.
5900 Pasteur Court Suit 100
Carlsbad, Califomia 92008
Prepared By: TG
Checked By: MC
N. Carroll
I
I TABLE OF CONTENTS
Introduction/Methodology 1
Run-off Coefficients 2
Time of Concentration Nomograph 3
Intensity-Duration Chart/Isopluviab 5-7
Rational Method Calculations & Exhibits App.
I
I
I
INTRODUCTION
The foUowing Hydrology study was prepared to support the Tentative Parcel Map/Site
Development plan for Cannon Court APN# 210-010-38.
EXISTING CONDITION
Presently, the site is vacant and slopes gently from east to west. The site currently
receives diainage fiom the parcel to the north, and a 24" RCP drainage outlet pipe @ the
CalTrans right-of-way. The flow from the CalTrans pipe is conveyed across the property
via a drainage swale and a shallow steel pipe. The entire site (and off-site contributing)
drains to a 5'x 5' railroad tie culvert at the AT&SF raifroad.
PROPOSED CONDITION
The development plan proposes commercial/tourist site \^ch will cover most of the lot
with buildings and A/C paving. The drainage will be connected to the existing outlet via
a series of pipes/inlets as shown on the site plan (attached).
HYDROLOGY
Tlie run-off was calcualted using the rational method as outlined in the San Diego County
Hydrology Manual.
The following criteria was used:
• lOO-year storm event
• Time of concentration (Tc) calculated using appendix X-C (see page 3).
• "C" values of .45 for existing, and .9 for proposed (see page 2).
• Intensity "I" was calculated using the Intensity-duration Charts (see pages 5-7).
RUiNGFF COEFFICIENTS (RATIONAL METHOD)
LAND USE
80% Impervious
Industrial (2)
90% Impervious
Coefficient. C
Soil Group (!)
A B C D
Undeveloped .30 .35 .40 EE Residential: 1 ii
Sural .50 .33 .40 .45
Single Faaily .40 .45 .50
Multi-Units .45 .30 .60 . 70
Mobile Homes (2) .45 .50 •55 -.65
Counercial (2) .70 .75 .80 .35
.80 .85 90
JO
.93
NOTES:
(1) Obtain soil group from maps on file with the Oeparment of Sanitation
and Flood. Control.
(2) Where actual conditions deviate significantly fron the tabulated
imperviousness values of 80% or 90%, the values given for coefficient
C, may be revised by multiplying 80% or 90% by the ratio of actual
imperviousness to the tabulated imperviousness. However, in no case
shall the final coefficient be less than 0.50. For example: Consider
ccmmercial property on D soil group.
'^T:t\ml~iBqfier9io'us^^^ '~5Q%
Tabulated imperviousness » 80%
Revised C « |2. X 0.8S ' 0.S5 80
APPENDIX IX
mmm
..£jc.ompJ4t-!- —
^eacf • Oi^tUnt//Tonr/Zne '/^ Aff/fe//es
SAN DIEGO COUNTY
DEPARTMENT OF SPECIAL OISTRICT SERVICES
OESIGN MANUAL
APPROVED ?'/ - xr-gi
URBAN AREAS OVERLAND TIMI
OF FLOW CURVES
OATE '^/f/6f T
APPENDIX
^FBUTSKO
•l^ UTILITY DESIGN, INC.
May 31, 2000
Planning Systems
Dennis Cunningham
1530 Faraciay Ave #100
Carlsbad.Ca. 92009
Re: Cannon Court
Dear Mr. Cunningham:
Butsko Utility Design, Inc. has reviewed the above-mentioned site to determine if there is a potential to
relocate the transmission corridor and substation. Based upon this preliminary analysis and
information gathering, please find below a listing of existing utility constraints and what we believe to be
the critical constraints, and summary.
I. EXISTING UTILITY CONSTRAINTS
1. Encina Power Plant
The Encina Power Plant provides the feed to the Cannon substation and the
transmission corridor that extends east across Interstate 5. If the Encina Power Plant
were to be relocated to the proposed site to the north, it is unlikely that the substation
and transmission lines would be relocated from their present location. With the Agua
Hedionda Lagoon on both sides of the proposed site, there is not an acceptable
location for a new transmission corridor. The transmission lines would need to extend
south from the proposed power plant location to the existing transmission corridor to
maintain the alignment across Interstate 5. The Cannon substation would need to be
within the alignment of the transmission corridor and accessible to the new power
plant location.
The relocation of the power plant would be contingent upon SDG&E being able to
acquire the necessary private property, easements, permits, and satisfying state and
local requirements for the realignment of the transmission corridor.
2. Cannon Substation
Cannon substation currently occupies 160 feet by 275 feet (approximately). In order
to relocate a substation, SDGE would require an acceptable alternative site location.
The new site location would need to be accessible from the Encina Power Plant or the
proposed location in order to maintain the feed to the Cannon substation.
The relocation of the substation would have a significant impact on the existing 12KV
distribution lines that leave the substation. There is an existing overhead and
underground distribution line. These lines would need to be extended to maintain the
circuits. State Highway and Railroad Permits would be required for any new highway
and railroad crossing locations.
The cost to relocate a substation is estimated at $10-15 million. This estimate is
based upon historical data, but varies due to site-specific issues.
2. Transmission Lines
There are multiple transmission lines that run east from the Encina Power Plant on the
west side of the railroad tracks to the Cannon substation. The transmission corridor
17065 Via Del Campi) • Suirc 200 • SanDiego • CA • 92127 • S58.676.0700 • TAX 858.676.9771
XX'itll OKict.s m S.m Dle,^o ' Orani^e County • IIIIIUKI Hiiipire • Ccntr.il Coasi
e Page 2 May 31, 2000
continues east from the Encina Power Plant, crosses the railroad tracks and the
freeway. The width of the transmission easement is 400 feet.
The location of the transmission corridor is dictated by the location of the Encina
Power Plant, the ocean and the freeway. The relocation would be contingent upon
SDGE being able to acquire the necessary easements and satisfying state and local
requirements for the proposed route. According to SDG&E, relocation of the
transmission lines would be virtually impossible unless the Encina Power Plant were
to be relocated.
Relocation of transmission poles is estimated at $200,000 per pole.
3. Overhead and Underground12l(v Distribution Lines
There is an existing overhead distribution line that extends out of the Cannon
substation on the north and continues east and west. There is an existing
underground distribution line that extends south to Cannon Rd and continues east
and west on Cannon Rd. Relocation of the substation would require the relocation of
all distribution lines. The acquisition of new easements would be required for the new
alignment as well as highway permits and railroad permits.
The estimated cost for relocation of the distribution poles is $12,000 per pole. The
estimated cost for relocation of the underground distribution system is $200.00 per
foot.
5. Gas
As a note, there is an existing 12" gas transmission line that runs north and south
along the westerly property line.
II. ADDITIONAL CONSTRAINTS
1. An Environmental impact report wiii be required per State of California, General Order
131D. The review and approval process historically takes 2-3 years.
2. Impact on the power grid, which is controlled by the power exchange. Any
modifications would be subject to state approval and schedule.
3. Successful acquisition of private property for new corndor site.
4. Successful acquisition of all necessary easements.
4. Project Scheduie as it relates to the process schedule.
5. Costs
6. Subject to Coastal Commission review and approval
In addition to our review, we contacted John Hernandez, Sempra Transmission Property Manager to
discuss the project. John acknowledged that our assumptions were consistent with Sempra/SDG&E's
position.
In summary, we have found that the relocation of the Encina Power Plant, transmission corridor and the
Cannon substation to be highly improbable based on the elements above.
Should you have any questions, please do not hesitate to call Gregg Butsko or me at (858) 676-9700
^IBUTSKO
mm UTILITY DESIGN, INC.
e Page 3 May 31, 2000
Or you may call to schedule a follow-up meeting to discuss these issues in more detail. Thank you for
providing Butsko Utility Design with the opportunity to be of service.
Sincerely,
Martha Smith
Project Manager
Cc: John Hernandez
Cc: John Buza
I^IBUTSKO
UTILITY DESIGN, INC.
j-j- TTi^iTftTiniinJ-iiHi-oniuiaii.iiHiHiiHfg.-j . 1' I'l.ia.i if t-ma;fhri I Directions for Application:
1) From precipitation naps detennine 6 hr. and
24 hr. amounts for the selected freouency.
These maps are printed In the County Hydrol
Manual (10, SO and 100 yr. maps Included In
Design and Procedure Manual).
i) Adjust 6 hr. precipitation (If necessary) sol
that It Is within the range of 45% to 65!li of]
the 24 hr. precipitation. (Not applicable
to Desert)
3) Plot 6 hr. precipitation on the rIgH side
of the chart.
4) Draw a line through the point parallel to the
plotted lines.
5) This line Is the Intensity-duration curve for
the location being analyzed.
Application Form:
0) Selected Frequency /^O yr.
1) Pg . I ia tn.. Pg^- 4.7> . \ • io±%*
?.
2) Adjusted *Pg- ^'^
3) tg- win.
4) I • ,1n/hr.
'24
In.
*Not Applicable to Desert Region
«nnD\inTV VT
r
A
a.
30 t/1
2S -a
o
COUNTY OF SAM DIEGO
OEPARTHENT OF SANITAjTION 6-
FLOOU CONTROL
33'
30'
15
Prt|w
U.S. DEPARTMEN I
NATIONAL OCIiAMC AND
SPECIAI. STUOieS BKANCII, OKFICii OF II
30*
lOO-YEAR 24-H0l|R PRECIPITATION
'-20^ISOPLUVIAL& OF 100 -VEAR 24-HOUn
PRECIPITATION IN ENTHS OF AN INCH
in* Jl*: • in I in • i Xf,"
V
<
n
a.
oo
t/1
TJ m •z o
X
X
COUfJTY OF SAN DIEGO j
OEPARTMENT OF SANITATION S
FLOOD CONTROL !
33'
100-YEAR 8-HOUk PRECIPITATIOri
^lU ISOPLUVIALS OF 100-VEAR 6-HOUR
PRECIPITATIOn ItJ TEimiS OF Ati IIJCII
U.S. DEPARTMEN T OF COMMERCE
NATIONAI. OCEANIC ANO ATujospilERIC AOMINISTIIATION
SPECIAL STUDIES BRANCH, OmCC OF II
30
111* ICI we.*
RATIONAL METHOD CALCULATIONS
AND
EXHIBITS
I
li
I
ICQ
*
'^K '^^V AieA *7.1 AO ^ t^l^ c^^o.iS'
4o t oveK/^vit? si^Tr u^>o-n> 'Af l='\']o'
0.45 (^^^^ C^^."^) * tc? ij^->:>
0Pf9T^ 1^ V-iiU.
ll
in
- t -
-1 .J
3
/
32
HYDROLOGY UAP
BosmcoHomoM
nYDROLOOiY MAP