HomeMy WebLinkAboutEIR 93-02; Green Valley; Environmental Impact Report (EIR) (6).-
April 6, 1995
Steve Sasaki
WPA Traffic Engineering, Inc.
680 Langsdorf Drive, Suite 222
Fullerton, CA 9263 1
GREEN VALLEY REVISED TRAFFIC REPORT - NOTICE TO PROCEED
Please consider this correspondence as the Notice to Proceed, regarding the revision to the
Green Valley Traffic Report and Traffic Section of the Green Valley Environmental Impact
Report (EIR). Attached for your records is a copy of the executed "Agreement for Traffic
Engineering Consultant Services."
In accordance with the agreement, work on the project shall begin within ten (10) days of
receipt of this correspondence and shall be completed within fifty (50) days of that date.
Please contact staff once this correspondence is received to discuss the project schedule
and to determine if a project "kick off" meeting is warranted.
F ease contact me at telephone 438-1 161, extension 4388.
Associate Engineer - Land Use Review
Enclosure
cc. (memo only)
Community Development Director
City Engineer
Planning Director
Assistant City Engineer
Principal Civil Engineer - Land Use Review
Senior Planner - B. Hunter
Associate Planner - C. Westrnan
Gary Wood - P&D Technologies
@ 2075 Las Palmas Dr. - Carlsbad, CA 92009-1 576 0 (61 9) 438-11 61 FAX (61 9) 438-0894