HomeMy WebLinkAboutHDP 96-13; Kelly Ranch Village E; Hillside Development Permit (HDP) (2)September 3, 1997
Pam Whitcomb
Kelly Ranch
201 1 Palomar Airport Road Suite 206
Carlsbad, CA. 92009
SUBJECT: CT 96-07 - KELLY RANCH VILLAGE “E”
Dear Pam:
Current California Environmental Quality Act (CEQA) regulations require that a project
Negative Declaration be completed and adopted or denied within 180 days of being
deemed complete. (October 20, 1997 in this case.) However, the project Mitigated
Negative Declaration will not be considered for approval by the City Council until project
issues have been fully resolved. Those issues are complex and will require additional
time for resolution.
I suggest that at a minimum we agree to a 90 day extension for processing. A 90 day
extension will require that the outstanding issues be completely resolved within a nine
week period. If you do not believe that we can close these issues within that period of
time, please suggest an alternate period.
Let’s discuss the time constraints of processing your application at your earliest
convenience.
Sincerely,
CHRISTER WESTMAN
Associate Planner
CW:kr