HomeMy WebLinkAboutLFMP 06A; LOCAL FACILITIES MANAGEMENT PLAN ZONE 06A; Local Facilities Management Plan (LFMP)APPLICATION COMPLETE DATE: January 10. 1989 STAFF REPORT DATE: FEBRUARY 1, 1989 TO: PLANNING COMMISSION FROM: PLANNING DEPARTMENT SUBJECT: SDP 86-11 fAVHDP 88-11/SUP 88-1/CUP/PCD/GPC 87-9/CUP 88-14/ CUP 88-15/ZC 88-1/LCPA 88-2/LFMP 6(A) VON PER AHE - Request approval of various related actions to develop an approximately 27 acre commercial/ governmental center at the northwest corner of El Camino Real and Alga Road within Local Facilities Management Zone 6. I. RECOMMENDATION That the Planning Commission ADOPT Resolution No.2811 recommending APPROVAL of the Mitigated Negative Declaration (SCH #88090722) issued by the Planning Director and ADOPT Resolution Nos. 2812, 2813, 2814, 2815, 2816, and 2817 APPROVING SDP 86-11(A), HDP 88-11, SUP 88-1, CUP/PCD/GPC 87-9, CUP 88-14, and CUP 88-15, and ADOPT Resolution Nos. 2818, 2819, 2820 recommending APPROVAL of ZC 88-1, LCPA 88-2, and LFMP 6(A). II. BACKGROUND AND PROJECT DESCRIPTION The proposed project is bounded by El Camino Real, Alga Road, a proposed residential subdivision, and the future westward extension of Dove Lane. As shown on Exhibit "L" the southern portion of the site was graded in the early 1980's to accommodate two previously approved projects. The project to the west (CT 82-23) was a 7.3 acre condominium development of 60 dwellings. This project has an approved final map which will be superceded by the approval of this project. The project to the east was an expired Site Development Plan (SDP 82- 4) for a 9.5 acre commercial center. The northern third of the site is covered with partially disturbed natural land. The site plan for the project proposes two interconnected levels. The lower level, at the southeastern end of the site, is largely retail. As shown and itemized on Exhibit "A", this level includes a 46,800 square foot major grocery store, a 10,000 square foot store, a 8,000 square foot building pad for a restaurant, and groups of smaller retail space totalling 26,950 square feet. This area also includes a recycling facility, an outdoor plaza and a pad for a 22,000 square foot South Carlsbad Post Office. The upper level at the northwestern end of the site is oriented to cultural, entertainment and service uses. This level's dominate features are the City's proposed 58,000 square foot South Carlsbad Library, a 4-5 screen/1,500 seat 22,800 square foot theater, and an outdoor plaza with seating and landscaping for informal cultural events. As listed on Exhibit "A", these uses will also include 13,950 square feet of restaurant/retail office use; and a 4,000 square foot maximum building pad for a potential drive-thru restaurant is provided at the northeasterly edge of the upper level. A tentative parcel map through the VON DER AHE FEBRUARY 1, 1989 PAGE 2 Engineering Department, would be processed for the site if the Site Development Plan is approved. The parcel map would create 4 parcels, 1 for the commercial center, 1 for the post office, 1 for the library and 1 for the detention/desiltation basin north of Dove Lane. As shown on Exhibits "A", "B", "C" and "D", the two levels are connected by a loop driveway which provides auto access between the project's entry points on Alga Road and Dove Lane. A system of plazas, arched arcades, pedestrian paths and landscaped arbors provides pedestrian circulation along and between all the site's buildings. This system is shown on Exhibits "B", "C", "J" and "K". The central plaza also connects the two levels with an elevator and a landscaped stairway. The architecture and landscape styles are classical Mediterranean as shown on Exhibits "B" and "D" - "K". III. ANALYSIS The proposed project involves several land use actions. Consequently, the following analysis and discussion is divided into groups of actions for clarity. A. - Site Development Plan - SDP 86-ll(A) - Hillside Development Permit - HDP 88-11 - Special Use Permit - SUP 88-1 B. - Conditional Use Permit/Planning Commission Determination/General Plan Consistency for the south Carlsbad Library - CUP/PCD/GPC 87-9 - Conditional Use Permit for the proposed recycling collection facilities - CUP 88-14. - Conditional Use Permit for the South Carlsbad Branch Post Office - CUP 88-15 C. - Zone Change ZC 88-1/Local Coastal Program Amendment LCPA 88-2 - Local Facilities Management Plan 6 Boundary Amendment - LFMP 6(A) - Local Facilities Management Plan compliance D. - Certification of the Mitigated Negative Declaration of the projects potential environmental impact. Issues; A. Site Development Plan SDP 86-11(A): 1. Is the site plan environmentally sensitive, orderly, and attractive, and compatible with existing and future surrounding land use? 2. Is the Site Plan consistent with Carlsbad's Local Coastal Program? VON DER AHE FEBRUARY 1, 1989 PAGE 3 Hillside Development Permit HDP 88-11: 1. 2. Have hillside conditions been adequately identified and incorporated into the site plan? Does the site plan implement the hillside development and design standards? B. Special Use Permit SUP 88-1: 1. Does the project enhance the scenic qualities of the El Camino Real corridor consistent with the corridor's development standards? 2. Does the project protect scenic views and traffic safety along El Camino Real? Conditional Use Permits CUP/PCD/GPC 87-9/CUP 88-14/CUP 88-15: 1. For each of the project's three conditional uses are the following true? (a) That the conditional use is necessary or desirable for the development of the community, is essentially in harmony with the various elements and objectives of the General Plan, and is not detrimental to existing or proposed uses in the site plan and zoning category; (b) That the site plan is adequate in size and shape to accommodate the use; (c) That all of the yards, setbacks, walls, fences, landscaping, and other features necessary to adjust the conditional use to the site plan and permitted feature uses in the neighborhood are provided and maintained; (d) That the street system serving the conditional use is adequate to properly handle all traffic generated by the conditional use. Zone Change ZC 88-1: 1. Does the Zone Change implement the General Plan and Local Coastal Program? VON DER AHE FEBRUARY 1, 1989 PAGE 4 Local Facilities Management Plan 6 Boundary Amendment LFMP 6(A): 1. Does the boundary amendment implement the City's Growth Management Program including Chapter 21.90 of Carlsbad's Municipal Code? 2. Is the amendment consistent with the adopted Local Facilities Management Plan for Zone 6? Local Coastal Program Amendment LCPA 88-2: 1. Is the amendment consistent with the California Coastal Act and the overall intent of Carlsbad's Local Coastal Program? D. Certification of Negative Declaration: 1. Have the potential environmental impacts of the proposed project been identified and mitigated to a level of insignificance? DISCUSSION A. Site Development Plan The site plan provides sensitivity to the natural environment through several means. First is the topographically sensitive westward alignment of Dove Lane. This alignment works with the surrounding topography to avoid extensive grading. Second, the project replaces pockets of natural vegetation on the northern portion of 'the site with up to a 60 foot wide slope of naturalized and fire retardant vegetation. This slope is the site's west boundary and provides a significant land use buffer for residential uses to the west. Lastly, the project also retains what is left of the site's general landform. This is done by terracing the site down from high points at the northwest portion of the site to low points at the southeast portion of the site. As described earlier, this is done by creating two levels on the site. The theater, buildings C, D, and E and the central plaza are at the boundary between the two levels. As shown on Exhibits "A", "E", "F", "K", and "P", Buildings C, D and E are two stories. The upper story is at the ground level of the upper site level and the lower story is at the ground level of the lower level. The central plaza provides stairs and an elevator which connects these two levels. Nearly all the buildings within the site are below the elevation of El Camino Real thus affording views across the site consistent with Carlsbad's Local Coastal Program. Extensive landscaping enhances this view. As shown on Exhibits "Q" - "W" the site's signage program is subdued. The dimensions and area of signage are well within the requirements of Carlsbad's sign ordinance and Local Coastal Program. VON DER AHE FEBRUARY 1, 1989 PAGE 5 As stated earlier, the project provides a significant buffer on the west. On the site's north, east, and south sides, streets, grade changes, landscaping and building setbacks buffer existing and future residential uses. In addition to these onsite buffers, off-site landscaping is being provided opposite the access points on both Alga Road and Dove Lane as shown on Exhibit "B". In addition, the amount and illumination of signage on the periphery of the site has been reduced to minimize glare. This is shown on Exhibits "Q" - "W" and made a condition of approval. The internal workings of the site plan have been reviewed. As shown on Exhibit "C", the site plan adequately provides for delivery and trash removal vehicles, passenger vehicles, public transit, bicycles and pedestrians. The three plazas located in front of the library and in the southeast central portions of the site along with the covered arcades, detailed on Exhibits "C", "J" and "K", provide an attractive pedestrian setting. Hillside Development Permit Hillside conditions exist on the northern 1/3 of the site. These conditions are identified on Exhibit "L". Much of the site's steep slopes consist of small isolated ravines. As stated earlier, the project generally retains what is left of the site's natural land form from previous grading. The project uses a significantly stepped foundation in buildings C, D, E and the theater to fit the development into the hillside. Except for the crib wall at the site's western edge all manufactured vertical grade changes in the form of crib or retaining walls are small scale and screened from public view. A detailed landscaping program is provided on Exhibits"B" and "0" to screen crib walls. The volume of grading on the site is 5,250 cubic yards per graded acre which is considered acceptable according to hillside standards. No cut or fill slope is greater than 30 feet in height. All structures are located and designed to fit into the site's hillside condition. Profiles of the site plan are provided on Exhibits "M" and "0". The only area that could fall into a gray area of interpretation with the Hillside Ordinance is the undulating 2:1 slope and crib wall structure at the site's western edge. This structure as shown on Exhibits "A", "B", "M", "0" and "P" reaches a maximum height of approximately 30 feet of which 15 feet is 2:1 slope and 15 feet is crib wall. The Hillside Ordinance allows greater than 30' slope structures for nonresidential development if written and graphic exhibits justify such modification to the decision making body. The Hillside Ordinance discourages steep grade changes. The crib wall is needed to provide the largest and flattest site for the proposed South Carlsbad Post Office and City Library. This allows maximum design flexibility for these civic buildings. The final site and building designs for the Post Office and City's Library could reduce or eliminate the crib wall. This could be done by using retaining walls as a part of these building walls, terraced building foundations and/or reconfiguration of the parking lots. The Site Development Plan, library and post office Conditional Use Permits have been conditioned to encourage this type of hillside design. However, until these designs are finalized the slope/crib wall structure VON DER AHE FEBRUARY 1, 1989 PAGE 6 provides maximum usability of the site. Again, Exhibits "B" and "0" detail how the crib wall would be landscaped to help reduce the hillside impact. Special Use Permit The project is within Area 5 of the El Camino Real Corridor. A Special Use Permit is needed to assure compliance with the corridor's development standards. The applicable standards refer to design theme, signage, grading, setbacks, street furniture and roof equipment. The standards call for a design theme of "Old California/Hispanic". As shown on Exhibits "D" - "K", the project provides this. Signage is limited to 7 foot by 12 foot stucco monument signs. Exhibits "Q" - "W", the sign program, shows all signage. The monument signs use a new fiberglass material which weathers better and cannot be distinguished from wood, masonary or ceramic tile. Staff believes the standards are maintained even though actual wood materials are not used. The standards of the El Camino Real Corridor limit grading to 10 feet above or below existing grades, unless the Planning Director and City Engineer both determine a deviation is warranted. Grading in excess of 10 feet from existing grade occurs at several locations on the site as shown on Exhibit "A". Both the Planning Director and City Engineer have found that the deviation from this standard is necessary because, 1) the existing grading and irregular topography make the standard infeasible; 2) both the scenic qualities of corridor and the intent of the scenic presentation overlay zone are maintained by the project design; and 3) traffic safety has been improved by providing efficient roadway and driveway grades. The corridor's applicable building setback requirements are 30 feet from the right-of-way of El Camino Real for buildings at grade and 45 feet for buildings downslope of El Camino Real. In addition, no 6 foot or higher walls, or parking areas are allowed within 25 feet of the right-of-way. The setback area is to be heavily landscaped. As shown on Exhibit "B", these setback standards are met. The last two applicable corridor standards concern street furniture and roof equipment screening. The street furniture standards call for wrought iron and wood materials. The project has been conditioned to provide these materials, masonry, or fiberglass replicas of wood and wrought iron; for all street furniture on the site. Locations and some examples of street furniture is shown on Exhibits "C" - "K". As shown on Exhibit "H" all rooftop equipment shall be screened from view, unless an onsite visual analysis indicates screening is not needed to hide rooftop equipment from all views. VON DER AHE FEBRUARY 1, 1989 PAGE 7 ; B. Conditional Uses The project includes three conditional uses - The South Carlsbad Post Office, City Library, and a recycling facility. Staff believes the justification for these facilities can be made. All three uses are necessary and desirable additions to the community. The post office will provide complete postal services for an area without such facilities. The library, which will be the City's main library, upgrades library facilities for South Carlsbad. The new South Carlsbad Library also implements the City's General Plan and Growth Management Program by providing public facilities concurrent or in advance of need to meet the City's performance standards. State law and Carlsbad's zoning ordinance requires a recycling facility at the center. The proposed facility will more than meet this requirement. The sites for all three facilities have been designed to accommodate their use. The library site was designed to have a dominate visual presence from Dove Lane and strong relationship with the cultural/entertainment uses of this center. The amount and location of available library parking exceeds City standards. The Post Office was designed to accommodate drop-off mail service and to effectively screen the vehicle service and mail truck parking areas. The recycling facility also provides drop-off service and aesthetically screens the storage bins. The project's site plan and all the conditional uses provide a sensitivity to surrounding residential land uses. The library, post office, and recycling facility are separated by elevation changes, landscaping, roadways and parking area. The recycling facility is also screened by building B. Traffic that would be generated from the conditional uses has been analyzed in the traffic report for the entire project. The project includes traffic mitigation which is consistent with the City's Circulation Element, Local Facilities Management Plan for Zone 6, and meets the City's circulation performance standards. C. Zone Change and Local Coastal Program Amendment The proposed zone change and Local Coastal Program Amendment is shown on Attachments 8 and 9. There are two components of this change. The first is a minor boundary adjustment between commercial and residential land uses. This adjustment reflects the project's separation between the commercial center and the post office and library sites. The net acreage change in commercial and residential zoning is negligible due to this adjustment. VON DER AHE FEBRUARY 1, 1989 PAGE 8 The second component is the zoning change for the western portion of the site. This is"the area of the City Library and Post Office. The change is from R-D- M, Residential Density-Multiple, to RP-Q, Residential/Professional with a Qualified overlay. This change is for the provision of a semi-residential land use buffer between the commercial center and the surrounding residential areas. This is of particular concern since the proposed RP-Q area has no significant topographic or circulation separation from the commercial center. This Zone Change is consistent with both Carlsbad's General Plan and Local Coastal Program Land Use Plan which designate the area RD-M (Medium Density Residential). RP- Q zoning is consistent with this RM land use designation. Local Facilities Management Plan 6 Boundary Amendment This very minor boundary amendment would add a small 3.03 acre area of RM Residential Medium designated land use to Zone 6. As shown in Attachment 10, this area is at the project's extreme northwest corner, and is a part of the City Library site. This boundary adjustment is consistent with the Growth Management Program by utilizing roadways, in this case Dove Lane, as general Local Facilities Management Zone delineators. The theoretical potential public facility demand of this minor boundary adjustment which is shown in attachment 10 will be addressed in the yearly monitoring report for Local Facilities Management Plan 6. The actual public facilities demand for this entire project is itemized on Attachment 14. Local Facilities Management Plan Compliance The project's public facility impacts are summarized on attachment 14. As proposed and conditioned, the project complies with the Local Facilities Management Plan for Zone 6. Exhibit "X" shows how the project will improve adjacent circulation facilities. D. Environmental The project as proposed and conditioned presents no unmitigated impacts. As shown on Exhibit "L", approximately 2/3 of the 27 acre site has been previously graded under prior City and Coastal Commission approvals. The remaining 1/3 of the site is a partially disturbed natural area. A biological, archeological and paleontological analysis was submitted for this area. The analysis indicated the potential for disturbance to archeological and paleontological resources. The analysis submitted mitigation measures to reduce this potential impact to a level of insignificance. These measures are incorporated into the Negative Declaration. VON DER AHE FEBRUARY 1, 1989 PAGE 9 The biological analysis indicated the presence of a disturbed inland sage scrub habitat. This habitat although contributing to the biotic diversity of the area has no unique or sensitive status. There are policies within the Mello II segment of Carlsbad's Local Coastal Program which seek to preserve Coastal Sage Scrub habitats on steep slopes of 25% or greater. Some of the inland sage scrub habitat is located on some intermittent segments of these steep slopes. These areas are shown on Exhibit "L". Preservation of these small relatively isolated steep slope segments would do little to effectively achieve the Local Coastal Program's goal of preserving quality steep slope habitats. As indicated in the biological analysis the site contains a dryer inland sage scrub habitat .not the more lush, moist, and biologically diverse coastal sage scrub habitat. As such, the environmental impacts to Carlsbad's Coastal Program appear negligible. This is supported by both Carlsbad's and the Coastal Commission's approval of development on the southern portion of the site which contained similar biology and topography. However, to provide a biologically enhanced site plan, the project is conditioned to provide a "naturalized" landscape palette along the contiguous slope at the site's western edge. This slope is to be landscaped with a "naturalized" vegetative palette. This landscaped slope will provide a contiguous habitat for wildlife and a mix of plant materials which will provide: 1) slope stabilization and erosion control, 2) a portion of the native landscape in an urban setting, and 3) an aesthetically pleasing and fire retardant buffer between the project and residential areas to the west. Additionally, a detention/ desiltation basin is provided north of Dove Lane to control erosion. A traffic study was also prepared for the project. That indicated mitigation to reduce project impacts to an insignificant level and assure Carlsbad's adopted performance standards are maintained. The project is conditioned to provide that mitigation. In addition to the above discussed mitigation; conditions have been placed on the project which reduce potential impacts to: 1) public facilities, 2) downstream water quality, and 3) views from surrounding residential areas to a level of insignificance. The applicant has agreed to implement this mitigation in the Negative Declaration. Since the project is located in the Coastal Zone and a Coastal Development Permit is needed, the Negative Declaration, project description and environmental studies, were submitted to the State Clearinghouse for a 30 day review and comment period (SCH #880907). Two comments where received. Comments were fully incorporated into the Site Development Plan's conditions of approval and mitigated Negative Declaration approval. In summary, staff recommends approval of the projects as conditioned. VON DER AHE FEBRUARY 1, PAGE 10 1989 Attachments 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. Planning Commission Commission Commission Commission Commission Commission Commission Commission Commission Map Data Sheet Form Planning Planning Planning Planning Planning Planning Planning Planning Location Background Disclosure Resolution Resolution Resolution Resolution Resolution Resolution Resolution Resolution Resolution Resolution No. No. No. No. No. No. No. No. No. No. 2811 2812 2813 2814 2815 2816 2817 2818 2819 2820 (Neg Dec) (SDP 86-11) (HDP 88-11) (SUP 88-1) (CUP/PCD/GPC (CUP 88-14) (CUP 88-15) (ZC 88-1) (LCPA 88-2) (LFMP 6(A)) 87-9) Local Facilities Impact Assessment Form Environmental Analysis (previously distributed) A. July 18, 1988 letter from RBR & Associates B. July 1988 addendum to RBR & Associates biological survey C. December 1, 1987 biological survey by RBR & Associates D. June 1988 cultural resource assessment by Sanchez Talarico Associates E. February 15, 1988 traffic impact and parking study by Linscott, Law & Greenspan Engineers 16. Exhibits "A" - "Y", dated February 1, 1989 November 3, LBS:af 1988 Exhibit "ND" 2075 LAS PALMAS DRIVE • >fJ¥ J» TELEPHONE CARLSBAD, CA 920094659 Wf^LfJi (6(9) 438-1 if 1 PLANNING DEPARTMENT NEGATIVE DECLARATION PROJECT ADDRESS/ LOCATION: 27 Acres located at the northwest corner of El Camino Real and Alga Road. PROJECT DESCRIPTION: A nixed use community shopping center which includes 123,400 sq. ft. of commercial/office land use, a 1,500 seat theater, a 58,000 sq. ft. public library and a 22,000 sq. ft. branch post office. The City of Carlsbad has conducted an environmental review of the above described project pursuant to the Guidelines for Implementation of the California Environmental Quality Act and the Environmental Protection Ordinance of the City of Carlsbad. As a result of said review, a Negative Declaration (declaration that the project will not have a significant impact on the environment) is hereby issued for the subject project. Justification for this action is on file in the Planning Department . A copy of the Negative Declaration with supportive documents is on file in the Planning Department, 2075 Las Palmas Drive, Carlsbad, California 92009. Comments from the public are invited. Please submit comments in writing to the Planning Department within ten (10) days of date of issuance. MICHAEL J. Planning Director DATED: September 9, 1988 CASE NO: SDP 86-ll(A)/SUP 88-1/ HDP 88-10/CUP 88-14/ CUP 88-15/ZC 88-1/ LFMP 6 (A), LCPA 88-2 APPLICANT: Carlsbad Retail Associates PUBLISH DATE: September 9, 1988 Exhibit "PIP 'Ml T*P*CT ASSBSSMENT PQP^ - PART II (TO BE COMPETED BY THE PLANNING DEPARTMENT) CASE N08.SDP 86-17fA). HDP 88-1Q. CUP as-H c ZC 88-1. LFMP DATE: _ September i. 1999 I. BACKGROUND 1. APPLICANT: Carlsbad Retail Associates _ ___ 2. ADDRESS AND PHONE NUMBER OF APPLICANT: 1601 Dove St. . J242 Newport Beach. CA 9266Q (7141 552-6623 _ ' 3. DATE CHECK LIST SUBMITTED: II. ENVIRONMENTAL IMPACTS (Explanations of all Affirmative Answers are to be written under Section III - Discussion of Environmental Evaluation) YES MAYBE 1. Earth - Will the proposal have significant results in: a. Unstable earth conditions or in changes in geologic substructures ? b. Disruptions, displacements, compaction or overcovering of the soil? c. Change in topography or ground surface relief features? d. The destruction, covering of modification of any unique geologic or physical features? e. Any increase in wind or water erosion of soils, either on or off the site? f. Changes in deposition or erosion of beach sands, or changes in siltation, deposition or erosion which may modify the channel or a river or stream or the bed of the ocean or any bay, inlet or lake? XES MAYBE 2. Air - Will the proposal have significant results in: a. Air emissions or deterioration of ambient air quality? b. The creation of objectionable odors? c. Alteration of air movement, moisture or temperature, or any change in climate, either locally or regionally? 3. Water - Will the proposal have significant results in: a. Changes in currents, or the course or direction of water movements, in either marine or fresh waters? b. Changes in absorption rates, drainage patters, or the rate and amount of surface water runoff? c. Alterations to the course or flow of flood waters? d. Change in the amount of surface water in any water body? e. Discharge into surface waters, or in any alteration of surface water quality, including but not limited to, temperature, dissolved oxygen or turbidity? f. Alteration of the direction or rate of flow of ground waters? g. Change in the quantity of ground waters, either through direct additions or withdrawals, or through interception of an aquifer by cuts or excavations? h. Reduction in the amount of water otherwise available for public water supplies? -2- XES 4. pJLftftfc Life - will the proposal have significant results in: a. Change in the diversity of species, or numbers of any species of plants (including trees, shrubs, grass, crops, microflora and aquatic plants)? b. Reduction of the numbers of any unique, rare or endangered species of plants? c. Introduction of new species of plants into an area, or in a barrier to the normal replenishment of existing species? d. Reduction in acreage of any agricultural crop? 5. Animal Li fa - Will the proposal have significant results in: a. Changes in the diversity of species, or numbers of any species of animals (birds, land animals including reptiles, fish and shellfish, benthic organisms, insects or microfauna) ? b. Reduction of the numbers of any unique, rare or endangered species of animals? c. Introduction of new species of animals into an area, or result in a barrier to the migration or movement of animals? _ _ _ X_ d. Deterioration to existing fish or wildlife habitat? 6. Noise - Will the proposal significantly increase existing noise levels? 7. Light and Glare - Will the proposal sig- nificantly produce new light or glare? 3- Land Use - will the proposal have significant results in the alteration of the present or planned land use of an area? . -3- XES 9- Natural Resource - Will the proposal hav« significant results in: a. Increase in the rate of use of any natural resources? b. Depletion of any nonrenewable natural resource? 10. Risk of Upset - Does the proposal involve a significant risk of an explosion or the release of hazardous substances (including, but not limited to, oil, pesticides, chemicals or radiation) in the event of an accident or upset conditions? 11. Population - Will the proposal signif- icantly alter the location, distribu- tion, density, or growth rate of the human population of an area? 12. Housing - Will the proposal signif- icantly affect existing housing, or create a demand for additional housing? 13. Transportation/Circulation - Will the proposal have significant results in: a. Generation of additional vehicular movement? b. Effects on existing parking facili- ties, or demand for new parking? c. Impact upon existing transportation systems? d. Alterations to present patterns of circulation or movement of people and/or goods? e. Alterations to waterborne, rail or air traffic? f. Increase in traffic hazards to motor vehicles, bicyclists or pedestrians? -4- MAYBE 14. public Servie«a - Will the proposal have a significant effect upon, or have signif- icant results in the need for new or altered governmental services in any of the following areas: a. Fire protection? b. Police protection? c. Schools? d. Parks or other recreational facilities? e. Maintenance of public facilities, including roads? f. Other governmental services? 15. Energy - Will the proposal have significant results in: a. Use of substantial amounts of fuel or energy? b. Demand upon existing sources of energy, or require the development of new sources of energy? 16. Utilities - Will the proposal have significant results in the need for new systems, or alterations to the following utilities: a. Power or natural gas? b. Communications systems? c. Water? d. Sewer or septic tanks? e. Storm water drainage? f. Solid waste and disposal? 17. Human Health - will the proposal have significant results in the creation of any health hazard or potential health hazard (excluding mental health)? -5- X££ MAYBfi 18. A«ath«ti*:» - Will the proposal have significant results in the obstruction of any scenic vista or view open to the public, or will the proposal result in creation of an aesthetically offensive public view? 19. Recreation - Will the proposal have significant results in the impact upon the quality or quantity of existing recreational opportunities? 20. Archeoloaical/Historical/PaleontQloo^eal - Will the proposal have significant results in the alteration of a significant archeological, paleontological or historical site, structure, object or building? 21. Analyze viable alternatives to the proposed project such as: a) Phased development of the project, b) alternate site designs, c) alternate scale of development, d) alternate uses for the site, e) development at some future time rather than now, f) alter- nate sites for the proposed, and g) no project alternative. a) The project is phased to a degree. The post office and library, along with pads A and B will most likely be developed in phases. b) The site design is an environmentally preferred variation of alternative site designs that were analyzed beginning in 1986. c) The scale of the project has been reduced from earlier designs. The scale of the project is less than anticipated by Carlsbad's General Plan and Growth Management Program. d) Alternative uses would be inconsistent with the General Plan and Local Coastal Program and less appropriate given adjacent roadway classifications and topographic situation. e) This would continue the environmentally detrimental erosion on the site. f) A more environmentally preferred site is not available in the vicinity. g) See (e) above. This would reduce library and post office service to unacceptable levels. -6- KQ 22. Mandatory findings of significance - a. Does th« project have the potential to degrade the quality of the environment, or curtail the diversity in the environment? b. Does the project have the potential to achieve short-term, to the dis- advantage of long-term, environmental goals? (A short-term impact on the environment is one which occurs in a relatively brief, definitive period of time while long-term impacts will endure well into the future.) c. Does the project have impacts which are individually limited, but cumulatively considerable? (A project may impact on two or more separate resources where the impact on each resource is relatively small, but where the effect of the total of those impacts on the environment is significant.) d. Does the project have environmental effects which will cause substantial adverse effects on human beings, either directly or indirectly? III. DISCUSSION OF ENVIRONMENTAL EVALUATION Ic. The project utilizes topography in site design. In addition, compliance with Carlsbad's Hillside Development Regulations will assure changes to topographic features will be insignificant. le. The project will remedy an existing soil erosion problem. Further, the project incorporates erosion controlling landscaping and detention/desilitation basins. If. The site has created siltation in a downstream detention/siltation basin which drains into Batiquitos Lagoon. The project as proposed and condition will correct this existing siltation problem. -7- DISCUSSION OP ENVIRONMENTAL EVALUATION (Continued) 2a. The project, by providing an appropriate mix of land uses encourage* "one-stop" shopping thus potentially reducing vehicle missions. The project also proposes public and private bus stop, and park and ride facilities to help reduce .vehicle emissions. 3b. The project provides significant perimeter landscaping and detention basins to moderate onsite runoff and absorption rates. Offsite runoff may need more mitigation. A mitigation condition is provided. 3e. The project will correct an existing erosion impact on surface waters of Batiquitos Lagoon. The project has the potential to add urban runoff pollutants to Batiquitos Lagoon surface waters. A parking lot sweeping/cleaning program would mitigate this potential impact. 4a i c. The project by creating a "naturalized1* landscaped corridor 5a & c. on the western edge of the site will reconfigure some insignificant disturbed biological habitats. A biological survey has been conducted for the project site. 6. The project provides significant grade separation along with orientation and design of noise producing uses to mitigate noise impacts. 7. The project topographic and site design reduces light and glare impacts to surrounding areas. In addition, the project proposes an extensive on and off site landscaping program to further reduce light and glare. Signage lighting is low intensity and generally of a low level. 8. The project will change the existing land use which is predominantly a barren graded area. Some disturbed natural vegetation is also on the site. The project is consistent with land uses planned for the site and area. 10. The project's only potential for risk of upset could occur with the post 'office's gas tanks. The gas tanks will be installed and operated pursuant to all applicable safety standards. In addition, the tanks are fenced-off from public contact. 13a. The project will generate additional vehicular movement. The movement has been planned for by the city of Carlsbad's Growth Management Program, specifically, Local Facilities Management Plan 6 (LFMP 6). The project incorporates LFMP 6 circulation improvements along with bus and park and ride facilities to mitigate this planned for impact. A detailed traffic and parking impact study has been prepared which outlines the potential impact and scope of mitigation incorporated into the project. -8- DISCUSSION OP gMvjRQNMENTAL EVALUATION (Continued) 13b. The project meets the City of Carlsbad's minimum requirements for off-street parking. No parking impacts are anticipated. 16d. Downstream sever facilities may be impacted by the project. A mitigation condition is provided. 16f. The project provides a recycling collection facility consistent with Agenda Bill 2020 and Carlsbad's Municipal Code 21.105. 18. The project's topographic, architectural and landscape site design results in a sensitive aesthetic treatment of public view sheds. Several view corridors are provided by the site design. 20. As outlined in a Cultural Resources Study, the project has the potential to impact archaeological and paleontological resources. A mitigation program is proposed that will reduce this potential to a level of insignificance. IV. DETERMINATION (To Be Completed By The Planning Department) On the basis of this initial evaluation: I find the proposed project COULD NOT have a significant effect on the environment, and a NEGATIVE DECLARATION will be prepared. .1 find that although the proposed project could have a significant "effect on the environment, there will not be a significant effect in this case because the mitigation measures described on an attached sheet have been added to the project. A Conditional Negative Declaration will be proposed. ,1 find the proposed project MAY have a significant effect on the "environment, and an ENVIRONMENTAL IMPACT REPORT is required. Date Planning DWector -9- v* MITIGATING MEASUR^g (If Applicable) 1. All submittals to the City of Carlsbad to fulfill the conditions of this mitigated Negative Declaration shall reference: a) the project file no. SDP ll(a); b) This Negative Declaration's State Clearinghouse No. and c) the specific mitigation number listed below. Conditions 2. Prior to occupancy of the first structure within the project, a parking lot sweeping and cleaning program that cleans the site's pavement of urban runoff pollutants shall be submitted to the Planning Director for review and approval. 3. Prior to issuance of a grading permit, the applicant shall submit a landscape plan to the Planning Director for review and approval. The landscape plan shall incorporate "coastal sage scrub** type plant materials in the landscape palette along the sites westerly slope. The intent of this planting is to design a corridor of "naturalized" biological habitat which is aesthetically pleasing, controls soil erosion, and is not a fire hazard. 4. Prior to issuance of building permits a detailed lighting and signage program shall be submitted to the Planning Director for review and approval. The program shall minimize site illumination to surrounding residential and adjacent roadways. 5. Prior to issuance of building permits for the commercial portion of the project compliance with all public facility improvements required by the adopted Local Facilities Management Plan for Zone 6 shall be shown to the satisfaction of the Planning Director. 6. Archaeology - a) The brushing and initial stages of grading shall be monitored by a SOPA certified archaeologist prepared to document and recover any significant archaeological material which might appear. -10- (Continued) b) A SOPA certified archaeologist shall be retained by the applicant and be present at the pregrade conference and during grading activities. Prior to issuance of grading permits, the certified archaeologist shall prepare for review and approval by the Planning Director a research program that establishes procedures for archaeological resource surveillance. The research program shall define, in cooperation with the project developer and Carlsbad Planning Department, procedures for temporarily halting or redirecting work to permit the sampling, identification, and evaluation of the artifacts as appropriate . c) The project archaeologist and project developer shall be responsible for all archaeological material recovered during the project. All archaeological material shall be described in a professional report which receives sufficient distribution to ensure its availability to future researchers. Prior to issuance of occupancy permits, a copy of this publication shall be submitted to the Carlsbad Planning Department for transmittal to the Carlsbad Historical Society. d) The project archaeologist and project developer shall be responsible for all archaeological material recovered during the project to be donated to a local institution which has proper facilities for curation, display, and use by interest scholars and the general public. 7. Paleontology - a) Prior to any grading at the project site, the project developer shall be responsible for a qualified paleontologist to be retained to perform a walkover survey of the ungraded portions of the site and to review the soil reports and City approved grading plans to determine of proposed grading and regrading of the site will impact undisturbed portions of the Santiago Formation. b) The qualified paleontologist shall be retained to perform periodic inspections of the site and to salvage exposed fossils. Due to the small nature of some of the fossils present in the Santiago Formation, it may be necessary to collect large samples of matrix for laboratory processing through fine screens. -11- MITTCATTQU MEASURES (Continued) c) The paleontologist shall be allowed to divert or direct grading in the area of an exposed fossil in order to facilitate evaluation and, if necessary, salvage artifacts. d) The project developer and paleontologist shall be responsible for all fossils collected to be donated to a public, non-profit institution with a research interest in the materials, such as the San Diego Natural History Museum. e) Any conflicts regarding the role of the paleontologist and the grading activities of the project shall be resolved by the Planning Director. 8. Prior to issuance of building permits for this project the downstream sewer trunk line shall be video inspected. Repair or reconstruction shall be completed prior to occupancy of any portion of this project. 9. The developer shall construct detention basins concurrent with development to maintain the capacity of downstream drainage facilities per current City standards. • f_ :*, • * VI. APPLICANT CONCURRENCE WITH MITIGATING MEASURES THIS IS TO CERTIFY THAT I HAVE REVIEWED THE ABOVE MITIGATING MEASURES AND CONCUR WITH THE ADDITION OF THESE MEASURES TO THE PROJECT. Date LBS:af -12- PLAZA PASEO REAL Revised Project Description Plaza Paseo Real is a 27 acre master-planned mixed use center including civic, retail and entertainment facilities. Located at the northwest corner of El Camino Real and Alga Road, the center will provide library, postal and retail services to the southern portion of the city. surrounding Land Uses The project site is bounded on the east by El Camino Real and Westbluff Plaza. Northeast of the site across El Camino Real and north of existing Dove Lane are three condominium complexes: Paseo de la Costa, Westbluff Hills and Westbluff North. South of the site, across Alga Road, between Manzanita and Mimosa are the Seaport Villas condominiums. South of Seaport Villas are the Seaport detached homes. Carlsbad Retail Associates (CRA) has met with residents from each of these communities. A summary of these meetings is attached as Appendix A. West of and above the project site is a proposed single family residential project by Westana Development. The northern boundary of the project is defined by a curvilinear future extension of Dove Lane east of El Camino Real which follows an existing swale off to the northwest to tie into another north-south collector in the Pacific Rim project near the elementary school site. The property north of Dove Lane is zoned for residential use. Previous Approvals/Existing Conditions The southern two-thirds of the site was graded in 1983-84 in anticipation of a previously approved retail and residential project. This previous approval included a 90,050 sq. ft. retail center on 9.5 acres fronting El Camino Real and 60 condominium units on 7.25 acres behind the retail center. In addition to grading both the retail and condo parcels, the previous owner installed an access road and utility services for the residential development. Storm drains and inlet structures were also installed to convey upstream drainage through the site. The northern third of the site has not been graded except for the f installation of the storm drainage structures discussed above. Extensive erosion is evident on this portion of the site from runoff from El Camino Real and surrounding areas. «MMK -2- Existing and Proposed Zpnina/Proiect Approvals The western portion of the site is designated RM (Medium Density Residential) on the General Plan and zoned RD-M (Residential Density-Multiple Zone). A condominium tract map (CT 82-23) is recorded on a portion of this area. The eastern portion of the site is designated C (Community Commercial) on the General Plan and zoned C-2 (Q) (General Commercial, a Q suffix denoting special site plan review). A site development plan (SDP 82-44) was previously approved for the neighborhood retail center discussed above. The planned project includes a future post office branch and a city library on the western portion of the site and a community shopping center on the eastern portion of the site. The post office and library uses are consistent with the General Plan designation of RM. A zone change is requested to R-P (Q) (Residential-Professional with Q suffix). Per Chapter 21.18 of Zoning Code, the intent and purpose of the R-P zone is to: (1) Provide areas for the development of certain low-intensity business and professional offices and related uses in locations in conjunction with or adjacent to residential areas; and (2) Provide transitional light traffic-generating commercial areas between established residential areas and near-by commercial or industrial development. (Ord. 9391 Section l(part), 1974). Libraries are specifically permitted in the zone (21.18.020(8). A post office branch appears to meet the intent of 21.18.020(12): "Public buildings other than schools." The Q suffix will insure that any other use subsequently proposed for this area would require discretionary approval by the Planning Commission. Conditional us* permits are also required for both the post office and the library pursuant to Section 21.42.010(1) of the Zoning Code. The General Plan and Zoning Code designations on the shopping center area are appropriate for the planned use. An adjustment to the zone boundary is requested to provide flexibility in site design for the market and the library. r -3- A revised «it« development plan approval pursuant to the Q suffix is requested for the entire site. Detailed design for the library and post office facilities nay require subsequent minor adjustments to the approved master site plan. The final approval requested is a tentative parcel map/minor resubdivision to reparcelize the site into lots for the purpose of sale of the two parcels for the library and the post office. This map would supercede the previous final map (CT 83-22) on the 7.26 acre site in the western portion of the project. A scenic overlay along El Camino Real Corridor requires that the project comply with the policies and standards established by the Scenic Corridor Development Guidelines (21.40). Exhibit B provides a consistency analysis of the project with these standards and policies. Design In response to the existing topography and preferred access points from surrounding roads, the center has evolved into a two-tiered design. This two-tiered site design allows the proposed project to respond to the site's natural topography and that topography's relationship to the previously graded pads. Buildings "C" and "D" take a full grade-break allowing direct access on two levels. These should be thought of as "Hillside" or at least site-sensitive architecture. The lower level (at elevations from 162 - 166 msl) is accessed from Alga Road at Manzanita street. This lower level will include a major grocery store anchor, a minor anchor (probably a 9 - 10,000 sq. ft. drug store), a family style restaurant of approximately 8,000 sq. ft. and in-line retail shops accommodating a variety of smaller tenants. An outdoor plaza at the corner of El Camino Real and Alga Road provides access to the bus shelter and a visual focal point for motorists on El Camino Real and Alga Road. The upper level (at elevations from 180-190 msl) is accessed primarily from an extension of Dove Lane west of El Camino Real. Dove Lane, as it heads west from El Camino Real, has been realigned froa previous design alignments to now turn and follow a small canyon to the north allowing it to swing up and over a ridge to the east without excessive hillside grading. The upper level of the shopping center will include a movie theatre (4-5 screens/1, 500 seats), a drive-through restaurant, a sit-down dinner house restaurant and in-line retail shops. The restaurant and the shops facing north which are accessed from the upper parking area are stacked above retail shops which are -4- accessed from the lower parking area. The focus of the upper-level of the center is an outdoor plaza with public seating, areas for displays and special events and an architectural theme tower. This theme tower will not provide any habitable space pursuant to Section 21.46.020. This plaza is connected to the lower level of the center by stairs and an elevator. On the western portion of the upper level on a raised pad (approximately 190 msl) , is the planned 58/000 sq. ft. southern library. This facility has a separate employee and service area which is accessed from Dove Lane. The visitor entry is located off of a plaza and drop-off area oriented toward the theater andEl Camino Real. The final component of the upper level is a future post office branch of up to 22,000 sq. ft. This facility will have access from the internal loop road for lobby patrons and automobile mail drop (snorkel lane) from Alga Road. Screened and secured delivery vehicle parking, employee parking and truck loading areas are located in the rear of the building. Architecture The architectural style of all structures is classical mediterranean in keeping with the themes established by the La Costa Resort and the recently approved Pacific Rim project. The pedestrian arcade will be defined by true arches accented with metal canopies at key entries. Variegated terra-cotta and creme tile mansards interspersed with stucco parapets will create screens for roof equipment. All rooftop equipment wells visible from El Camino Real will be screened by louvers or trellises matching the color scheme of the adjoining parapet or mansard. i The elevations for the library and post office are conceptual. It is anticipated that the City and U.S. Postal Service will each retain their own architects who will generally follow the architectural style depicted in the conceptual elevations. The two pad buildings will also be required to substantially conform to the architecture of the other retail buildings and will not exceed the maximum building heights shown for Building A. Trash enclosures will be finished in stucco to match the buildings and covered by wood framed trellises. Landscape Architecture landscape plan responds to both the City streetscape standards and the architectural design of the project. London plane trees are the dominant street tree along El Camino Real. Eucalyptus is also included to mirror the existing stands on the east side of the street. The Alga Road streetscape is dominated -5- by various types of pines with Chir pines in the median. The pines in the median will be densely planted to screen headlights from the right in/right out Alga Road entry. In order to provide increased landscaped screening and security for the Seaport Villas units facing Alga Road, CRA has offered to implement a landscape screening plan on the south side of Alga Road. The conceptual plan to be approved by the Seaport Villas Homeowners Association includes dense screening shrubs in the common area between the rear fences and the stucco wall. Selected shrubs include sweet hakea, natal plum, silver berry and bougainvillea. In addition, clusters of street trees including Canary Island pines will be planted in the dirt strip between the sidewalk and the curb. Seaport, villas HOA has agreed to maintain these plantings including the street trees. Entries to the project are denoted by clusters of queen palms and mexican fan palms. The interior loop road is accented by colorful jacaradas. Plaza areas and key architectural corners are softened by special accent trees. Parking areas will include a variety of trees in raised planter strips or boxes. The perimeter slopes on the western edge of the site will be planted with drought tolerant trees and ground cover to resisterosion. Sianaae and Lighting A comprehensive sign program with specific criteria regulating the number, size, type and location of monument, tenant, directional and code required signs is included. The sign program criteria balance the need for tenant visibility with the desire to maintain architectural integrity and respond to the objectives of the scenic corridor policies of the LCP and ordinance. Lighting for parking areas and security will be controlled to preclude spillage or glare from reaching sensitive receptors (Seaport Villas, proposed single family detached homes above and west of the site, and condominiums north and east across El Camino Real). Circulation/Service Vehicular circulation within the center is facilitated by a loop drive which circles the entire project. Ample vehicular stacking distance is provided at all entry points to public streets. A reciprocal easement/ access agreement providing all uses/owners use of the loop drive will be entered into between the owners of the three parcels. -6- Offsite circulation improvements will include: completing the frontage along El Camino Real; upgrading the intersection of Dove Lane/El Camino Real to include full four way movements including a northbound left turn pocket on El Camino Real; removing the existing curb on the north side of Alga Road and dedicating and, constructing a third westbound lane and completing all frontage improvements; planting and irrigating the existing median in Alga Road; signalizing or bonding for a signal at Alga Road/Manzanita and the project entry; dedicating and constructing Dove Lane from El Camino Real to the project entry and from the project entry to the western edge of the library parcel dedicating the southern half right of way and building the southern half section plus ten feet of paving on the northern half section with a temporary asphalt curb; upgrading the intersection of Alga Road/El Camino Real to provide additional peak hour capacity as recommended in the Linscott, Law & Greenspan traffic study. Parking is provided in excess of code requirements and arranged for convenient access to the various uses. A reciprocal parking agreement will be entered into between the owners of the three parcels to provide for shared use between the various project components as discussed in Project Operations below. Pedestrian circulation is enhanced by covered acrades throughout most of the project. Both upper and lower levels of the central core of the center can be accessed on foot without crossing a parking area. Pedestrian connections between the central core and the other buildings, including the library and post office, are well defined by enriched paving and other features such as a trellis leading to the library entry. A bus shelter is located adjacent to the restaurant pad (Pad A) on El Camino Real per direction from North County Transit District staff. Truck service is provided to all uses on site. The major grocery includes a screened truck well which can accommodate three trailers at the dock' as well as screened, off-street, waiting areas for at least two additional trucks. Both the library and the post office have self contained service and loading areas which will be screened from surrounding uses/streets. Most retail shops are front loaded due to grade changes and locations along public streets. Loading zones are provided proximate to each group of line shops. Pad buildings have their own loading zones. The internal circulation system is designed to accommodate the appropriate sizes of trucks. -7- Delivery frequencies will vary widely with the particular use. The major grocery will have the most frequent service intervals with up to fifty trucks per week including all sizes ranging from snail bread trucks to tractor-trailers. The post office will be serviced from the downtown station. Two delivery trucks will bring in presorted mail each day. Library service will include an occasional tractor-trailer with primarily smaller trucks and vans. It is anticipated that inter-library service will occur on a daily basis. Among the remainder of the uses, the restaurants will have several deliveries each day. Service to other retail uses will be substantially less frequent. Trash pick-up from the major grocery and the restaurants will be on a daily basis. All other uses will have weekly pick-up. Development Phasing Initial construction activity will include removal of roads and utilities installed on the 7.26 acres in the western portion of the property and grading (or regrading) the entire 28 acres including the alignment of Dove Lane to the western edge of the library site. Upon completion of grading, utilities and drainage and siltation control improvements will be installed. Base and rough paving for the loop road will also be completed. Landscaping will be installed along all perimeter slopes/ setbacks, at project entries and along the interior loop road. The landscape screening for Seaport Villas will also be installed at this time. Completion of this "master" site development phase is expected to take three to four months. CRA will deliver finished pads, including any crib or retaining walls, to both the City and the U.S. Postal Service. Each pad will be graded and unpaved with curb breaks at designated points from the interior loop road and Dove Lane. Utilities will be stubbed out at a mutually agreed upon location. The timing of construction of the library building, post office branch and related onsite improvements is at the discretion of the City and U.S. Postal Services, respectively. Construction of all buildings in the shopping center will commence at or near the end of the "master" site development phase with the possible exception of Pad A and Pad B. These buildings may be built at a later time depending on leasing negotiations with specific users. All offsite improvements will be completed prior to occupancy of the shopping center. -8- Completion of the shopping center structures and onsite shopping center improvements and offsite circulation improvements is expected to take nine to twelve months. Project operetions Moat retail shops will be open from 9 a.m. to 6 p.m. except for the major grocery and the restaurants which may be open earlier (if breakfast is served) and which will likely be open later in the evening. No discos or nightclubs will be permitted. Light live entertainment (piano, jazz, or chamber music) may be allowed as an ancillary part of a dinner house restaurant. The theater will be open for typical show times including weekend matinees. The library is expected to operate from 9 a.m. to 9 p.m. Monday through Thursday and from 9 a.m. to 5 p.m. Friday and Saturday. Peak hours for the theater are Friday and Saturday evenings while peak hours for the library are Monday through Thursday between 11 a.m. and 7 p.m. and Saturday between noon and 3 p.m. This off peak relationship will ensure that ample parking is available for both uses. The post office counter is expected to operate from 9:30 a.m. to 5 p.m., Monday through Friday. Limited operation on Saturday morning may also occur. No mail sorting is expected occur at this facility. Pre-sorted mail will be delivered from the main station downtown and transferred to the carriers who will leave the site mid-morning and return by late afternoon. The lobby and curb-side mail drop facilities are open at all hours. The project will be managed by a professional property manager who will be responsible for maintenance, security and operations. CARLSBAD/V 2 IMCMEEHMCflMIIMl t*M LOCATION MAP La Plaza De paseo Real CARLSBAD BETA*. ASSOCIATES STATE Q, CAUM«NU-OffKa Of TH€ GO OFFICE OF PLANNING AND RESEARCH 1400 TENTH STREET SAOUMCNTO, CA 9MU EXmdlT "SCH" - GtO*G( DSUKMtllAN, Gowmor- Lance Schulte City of Carlsbad 2975 Las Palmas Drive Carlsbad, CA 92009 October 11, 1988 Subject: Carlsbad Retail Associates - SCH# 88090714 Dear Mr. Schulte: The State Clearinghouse has submitted the above named proposed Negative Declaration to selected state agencies for review. The review period is now closed and the cements from the responding agency(ies) is(are) enclosed. On the enclosed Notice of Completion form you will note that the Clearinghouse has checked the agencies that have consented. Please review the Notice of Completion to ensure that your comment package is complete. If the comment package is not in order, please notify the State Clearinghouse immediately. Remember to refer to the project's eight-digit State Clearinghouse number so that we may respond promptly. Please note that Section 21104 of the California Public Resources Coda requires that: "a responsible agency or other public agency shall only make substantive comments regarding those activities involved in a project which are within an area of expertise of the agency or which are required to be carried out or approved by the agency." Commenting agencies are also required by this section to support their comments with specific documentation. Th-sse cc~:ents are forwarded for your use in adopting your Negative D^claracion. if you need more information or clarification, we recommend that you contact the commenting agency at your earliest convenience. This letter acknowledges that you have complied with the State Clearinghouse review requirements for draft environmental documents, pursuant to the California Environmental Quality Act. Please contact Keith Lee at 916/445-0612 if you have any questions regarding the environmental review process. Sincerely/ David C. tfunenkamp Chief Office of Permit Assistance Enclosures cc: Resources StaN •* California ft. A'-// Th« R«MWTCM Agency moron d u m To ' From 1. Project* Coordinator Resources Agency 2. City of Carlsbad Planning Department 2075 Las Palmas Drive Carlsbad, CA 92009 D«partiii«nr •* fiih and Oam* Oat*October 4, 1988 ! Negative Declaration: Carlsbad Retail Associates, San Diego County - SCH 88090714 The Department biologist familiar with the project area has reviewed the Negative Declaration for Carlsbad Retail Associates, a proposed community shopping center at the northwest corner of El Camino Real and Alga Road in the City of Carlsbad. We recommend that the following mitigation measure be included to avoid short-term and long-term adverse impacts to Batiquitos Lagoon: "Detention/siltation basins created by the project shall be maintained as long as needed during construction and thereafter to prevent sediment transport into Batiquitos Lagoon. Detention/siltation basins shall contain 'grease catching' devices to prevent urban pollutants from entering the Lagoon." Given inclusion of this additional mitigation measure, we find that a Negative Declaration of project impact would be appropriate. If the project proponent is unwilling to include this mitigation measure as an enforceable condition of certification of the Negative Declaration, then we find that the project has potential 'to result in significant adverse environmental impacts and we would recommend the preparation of an EZR for the project in lieu of the Negative Declaration presently under consideration. Thank you for the opportunity to review and comment on this project. If you have any questions, please contact Fred Worthley, Regional Manager of Region 5, at 330 Golden Shore, Suite 50, Long Beach, CA 90802 or by telephone at (213) 590-5113. Pete Bontadelli Director STATE Of CALIFORNIA NATIVE AMERICAN HERITAGE COMMISSION 913 CAPITOL MAIL, ROOM 2M SACRAMENTO, CALIFORNIA 9»14 (916) 322-7791 September 29, 1988 Mr. Lance Schulte City of Carlsbad 2075 Las Palmas Drive Carlsbad, California. 92009 re: SCH #88090714-Carlsbad Retail Associates Dear Mr. Schulte: Although a search of the sacred lands file maintained at this office failed to disclose the presence of cultural resources, due to the high number of culturally sensitive areas within San Diego County, the Native American Heritage Commission submits this letter of response. The sacred lands file is comprised of site information supplied by local Indians, tribal groups and elders and is separate and apart from other collections and repositories of cultural resource information or data. The information in the file is classified and is employed in the review of environmental documents.. The concern of the Native American Heritage Commission is in those places where the prehistoric sites underlie areas which have been previously developed and thought to be free of cultural resources. Sites have been covered by natural causes, flooding would be one example, over a period of centuries. The alluvial buildup has provided a buffer zone between the present surface and the prehistoric site. Structures have been placed on some, the soil covering others has been cultivated over many years. When an older structure is replaced with a modern building, or an old underground water or sewer line is upgraded to meet present needs is when the problem of impacting such a location takes place. When a foundation is dug to comply with the building codes and requirements of today, or utility lines are buried to meet health and safety standards, previously undisturbed soil becomes impacted. In a situation, such as the proposed Carlsbad Retail Associates Project, where certain portions of the property are undisturbed and covered with heavy vegetation, a cursory archaeological study is often not enough. There are roughly eleven thousand, (11,000), known and recorded archaeological sites within San Diego County. It has been estimated, based on recovered artifacts, that some of these sites were occupied as far back as twenty thousand, (20,000), years. Previously undiscovered Native American sites are encountered within that general region with a greater frequency than most other parts of the state. The likelihood of discovering previously undetected cultural resources is a possibility which should be fully investigated and fully addressed in any environmental review or study originating in that area. The California Environmental Quality Act, Appendix K, deals with the discovery of archaeological sites and the procedures to follow. It also contains the instructions to follow when human remains are found during any phase of development. The Native American Heritage Commission has prepared a pamphlet for use by lead agencies, planners, developers and property owners. It provides an easy-to-read breakdown of the California Codes pertaining to Native American human remains and their disposition. I have included a copy of this brochure for your use. If you have any questions or if you need additional information, please contact this office. Sincerely, William Amo7frJohron Staff Analyst. enclosure WHAT TO DO A RESOURCE GUIDE FOR: CORONERS NATIVE AMERICAN MOST LIKELY DESCENDENTS CITY AND COUNTV PLANNERS PROPERTY OWNERS DEVELOPERS The following actions must be taken immediately upon I he discovery of remains at a construction site: a) Stop work immediately and contact the County Coroner. b) The Coroner has two working days to examine remains after being notified by the person responsible Tor the excavation. If the remains are Native American, the Coroner has 24 hours to notify the Native American Heritage Commission. c) The Native American Heritage Commission will immediately notify (he person it believes to be the most likely dependent of the deceased Native American. d) The most likely descendent has 24 hours to make recommenda- tions to the owner, or represen- tative, for the treatment or disposition, with proper dignity, of the remains and grave goods. e) If the descendent doesn't make recommendations within 24 hours the owner may reinter the remains in an area of the properly secure from further disturbance, or: If the owner doesn't accept the dependent's recommenda- tions, the owner or the descendent may request mediation by the Native American Heritage Commission. A PROFESSIONAL GUIDE FOR THE PRESERVATION AND PROTECTION OF NATIVE AMERICAN REMAINS AND ASSOCIATED GRAVE GOODS FOR ADDITIONAL INFORMATION: call the NATIVE AMERICAN HERITAGE COMMISSION at (91*) 322-7791 or write to: NATIVE AMERICAN HERITAGE COMMISSION 915 Capitol Mall, Room 288 Sacramento, CA 95814 Published by the California Naiive American Heritage Commission 2/88 GEORGE DEUKMFJIAN. Governor •sjininq ueaoauiy 3Ant'N qiiM powixisss siuaH /Cue put suieum ueumq aqi jo 'XtiuAp awudoidde qii* 'Suisodsip jo Zuittw joj tdnod mpuamy •puqaqi'uonafoid * 10 acn pauund 9qi tpu& luaisisiioo tpoa8 anuui punxxCT put •ROTUUI (tlapv *H*!"MI uiauwiv »Ai>»N jo "oqitatap pw umiman MOBUM »J sp!*o«l P« uofiaump wauaApwi put wn RMM jtp ui i ofijns MM are sunmioi iiqi icqi '3(ioj luJtuaiDAOi) aqi jo £ afiij. jo z untsiAig jo c WJ jo (IWWJ uonaas qii* Aiiauaiuuioi) Q\ tavieio 4l'» aauepjo^ae ui 'pauiuiiaiap scq patMoxip ait surauiai ununq aqi qonj* in Xninoi aqi jo tMoxo aqi (nun tuieiuai n»w»fpt SIJOAO 01 panadcnc Atqwosm KM A^j«au Xut jo aws aqi jo aawRu^sip » iMMWARixa jaqunj ou aq |fiqt amp -X Xut jo uoniu&xsu jo Ajauunop jo «cMa aqi tq (q) uoGudamc aqt M wauiuonriuii Aq aiqeqsnind n U.»UM Auop) • i XWn8 a sonniWM jo aainjui qu* jo waswp jo gai HiaHB MI qiut unw JO aAuS unuauiy aAiwN • ("OiJ sumuai wunq JO snqiui URMauiy aAiXN <«• '*•« jo Aiuoiant moqii* •saAoiuad oq« uouad Xuy (a) •uosud amc aqi IB maunocudun Xq anvunund n im* Xuoiajijo/tiiwJa'geifiOtuonaaSoilutnsjndjo iM|iinj O) i.xrfqns i aip uo Atniftp ateudujJdc I|>IM i]Bunq unitauiv a*fl>N I|)IM painxKsv suiw pus sureuiai wnunq auMnpu»| aqi 'JjuMOpuBi ap m 3|i|Bxl. apiAOJd ot qnj j« i60S uoo»S P (1) uomAipqns w JDJ paptAOUt uoiinpau aqi pin wapoaaop aqi jo umj SWUM |na|av put sfnini) ununq unuauiy 9AinN n uoipaiajd apiAOjd u«|s nuaiiMai8t aqj. •qvunq uouauiy MIWN qii« papiaotsc tumi put tumuaj imp* •sjiunq ununq wnuauiy a*0»N jo uowsodnp put Homnaq aqi c* iwiqaJ auapuncap UMOU^ put stWMOpuq itWMiaq ftusui samdnp put •manual pur wauoxui M sucnuoa Jiaqi iMuxq JDJ paau aqi auipjcgai mtapitajgap ucaauiy (j) tuautaad* M q»* Muqucno* w jo AMI Xq papuoid idaoica -gut 'I (q) 86 /.60S uonaas at mntwf jo M'tiK u»w»s <° (0 ""^^W" tn Mnuri poqaoi wawMd* w OtJ* JO 09 Up3 JO SAU* UOUaUIV *M»»N • "WJ uagp a» «pi«/» n»»ui wujnq JO naqiui urauauiy :spoo« JAtlg pannoni JD SMMiaj UKXjauiy aAlBN SWKSOd jo UfVKlp oi Xuoro * >! Suninu 'apo »^mi»3H I »jja owl '8861 ' 1 <«"ui!f UQ IIS JM| JO M| jo fMMOpuq M(| jo 'u t apui 01 «p»J paijnuspi iuapu»sap aqj jo •t « X|iiuapi 01 3|qtun si UQISSIUIUJO^ aqi jaAauaq^ (q) •tfRmq utaoauiy »AIWN HV* painaocai suoii put MMUIM unumj jo sKXpnie aAimnsapuou put ICAOUUI aypuaiac aqi apn|3Ui ABUI uoqapuaujuiocKu aiU. -11011X101(1100 98nu3H unijauiv MINN a>P ^1 uopmjixiu Jiai|i jo unoq w UIIOIM uoqipiiauiiuom BMQ 3ftui put uoqMdsui jisqi aofduim lieqs nuapmxap am spooS aAed pami3Otai Xut pill tureutai ucumq aqi 'Ximftp JisuiloidJe IQIM •guisodsip jo tonmn JQJ SUBSUI v0* uoqcAiaita aip joj atqisuociKU uouad aip jo tauMO aqi 01 puaunuoaai AIUI put sumuiaj unuauiy SAWN 3*0 J° AJMOocip alp jo aiis aqi taadsui 'MneiuKaidai pazuoqini jai| jo s«| JO 'puB) aqi jo JMWO aqi JO uowsiuuad aip qiiM "Xeui siuapua^ap aqj. 'urwauiy aAiKN paccaaap aqi tuoij papuaKgp X|%|i) isoui aq li 'apoj Xiaj«s PUB mi»l( *0 J» S OSOi u»n»S jo (3) uCHSiAipqns 01 luuiisjn J LKXIJUD Xiunoa n uiOJj nuBiuai ueiunq UEJUJUIV SAIIEN )c> Xj3AO%ip • jo (e) *MI put uaMOd >in«o||oj aqi 3Mq n«qc UOWIUMIOJ aqj. *« jo M'IMS •UOBSIIUUI03 a>nuaH unuauiy MOIN aqi 'unoq Xq •iMwoa ||H|i aqt jo aq • asoqi am Aaqi Mqi a*atpq « mem t*q JO 'unuaurv 9AIHN • jo amp *t <• HIJIIUM ununq aqi tazndoaaj a aqi ji pw Xjuoqint oq jo nq 01 ixrfqm UKUJ twnuai mw put Sfjunq ununq unuaiuy 3An«N oi uotiaaiojd aptAQtd DX (|) :si 13* cnp jo atodjnd auj. (q) •spnmq uouauiy SAIKN M»» paniMsst sutaii put •timnuai tVfU^np 'sinjnq unuwiy »An»K| jo uooisodsip put tuaunjan aqi ftqucSai siuaaKM jtaip IUUMOI afnu mo nuapuajMp wnuauiy *umn qaiq« <q autp nip w sucaui jqniaj ou n aoqj. (£) WMUIM wunq aqi jo uoaniftmi jo ija*oasip aqi jo jauojoa aqi saijnou •aAimuacudaj panioqim jaq JQ aq to •uoquoira aqi ouad aqi 3UJO aqi UKUJ sXip tuqjOM ntuaiap jaq JQ sn| ayni |(iqc jauojoo pw uaifipuEA UKUJ sumuiaj pw t|Miq ataqi jo uonaatojd aquoj apiAatd KM op s«q ants (z) •am auBKuan w v uoammp wauMpmii put UKIR^UU 01 loafcjnt an sunmcu rnatKrn pw S|Bunq unumi unuamy aAO^i (|) :s«o||oj H spuy ajnjt|siSai auj. (•) aqj, ui papiAOid aqi in 'ii paauoqm* jaq jo siq duo •uonunna aqi JDJ atqreutidsaj uoBiad aqi at apnu uaaq a*iq sunwu ununq aqi jo uontwdsip put tuaunKui aqi SUIUIXMOI woiwpuaiuuMxxu aqi pw 'qinp Am jo asno pw rauueui 'saDueisumaua aqi jo uonidrvaAui IUIUJMUOJ »«| jo suoisiAajd panpi jaqto kot jo apo.-) wauiuoAOO 3qi jo \WLl uoi»as aqi 01 66 t60S PW 86Z60«, suwiaos pgpp* put 3003 s»M"oK>a »N"d «P jo t« UfK uonaas papuaiw •apoo AWJBS pw qqvaH aqi « S'osot 11011305 PW* jji jo Minims tj sumituj iM M«| JMOt JOJ I«{«JU<iiu Vuuu>||Oj MU. Mail to: State Clearinghouse, 1400 .enth Street, «m. 121, Sacramento, CA 95fci4 -- 916/445-0613 1. Project Titl« NOTICE OF COMPLETION AW ENVIRONMENTAL DOCUMENT FOM t>aoe<.tes See NOTE MlOM: SCN f 2. Lead Agency: Cttv of Carlsbad. 3a. Street Addrees: 2075 La« Palmes Drive 3c. County: San Diego _ 3. Contact Person; Lance Sehulte _ 5». City; Cj_l_b__| 3d. Zip: 92009 3e. Phone: 619-438-1161 PROJECT LOCATION 4. County: Sen Diego 4b.(optional) Attestor1* Percel Mo. 4e. City/Community: Carlsbad 4c. Section: ______ Tup. For Rural, Range 5a. Crott Streett: El Camino Reel t Ala* Rd. 56. Nearest Community!. 6. Within 2 mi let of: e. State Hwy No. b. Airports Palomar 7. DOCUMENT TYPE 8. LOCAL ACTION TYPE c. Waterways 10. DEVELOPMENT TYPE CEQA 01 _ NOP 02 ___ Early Cons 03 X Meg Dec 04 _ Draft Eli 05 _ Supplement/ Subsequent E1R (if so, prior SCM *_ ) HEPA 06 _ Notice of Intent 07 _ Envir. Assessment/ FONSI 08 _ Draft E1S OTHER 09 _ Information Only 10 _ Final Document 11 ' Other: _ 01 _ General Plan Update 02 _ NCM Element 03 _ General Plan Amendment 04 _ Matter Plan 05 _ Annexation 06 _ Specific Plan 01 02 03 Residential: Unitt Office: Sq. Ft. Acres Acres Employees X Shopping/C Acres 04 Industrial: rcial: Sq.Ft. 123.400 Employees N/A Sq. Ft. 07 Redevelopment 08 X Reione 05 09 X Land Division 06 (Subdivision, Parcel Map. Tract Map, etc.) 07 10 X Use Permit 08 Acres Sewer: MGO Water: MGO Employees Transportation: Type Mineral Extraction: Mineral 11 Cencel Ag Preserve 09 Power Generation: Wattage 12 X Other Site Plan Type: 10 X Other: Gov. - Post Offices 4 Library 9 TOTAL ACRES;27 11. PROJECT ISSUES DISCUSSED IX DOCUMENT 01 x Aesthetic/Visual 08 02 Agricultural Land 09 03 X Air Quality 10 04 X Archeeological/NUtoMeel/ 11 Paleontological 12 05 X Coastal 13 06 Fire Hazard 14 07 X Flooding/Drainage Geologic/Seismic 15 __ Sewer Capacity 22 Jobs/Housing Balance 16 Soil Erosion 23 17 Solid Waste 24 18 Toxic/Hazardous 25 Minerals Noise Public Services Schools Septic Systems 19 X Traffic/Circulation 26 20 Vegetation 27 21 X Water Quality 28 Water Supply Wetland/Riparian Wildlife Growth Inducing Incompatible landuse Cumulative Effects Other 12 fUMDIMS (approx.)Federal $State S.Total * 13 PRESENT LAND USE AND ZONING; Present land uses - vecant disturbed and undisturbed land. Present zoning is commercial and multiple density residential. 14 PROJECT DESCRIPTION; A mixed use commercial shopping center which includes 123,400 sq. ft. of commercial/offices land use, s 1,500 sq. ft. theater, a 50,000 sq. ft .^public library and a 22,000 sq. ft. brsnch post office. See detailed project description and site plan attach! 1 V IA/1J1 «s15. SIGNATURE OF LEAD AGENCY REPRESENTATIVE:Date: NOTE; Clearinghouse will assign identification/numbers for all new projects If e SCH Number alreedy exists for * U.Vll.WTMr; Agency _Air nmuuivM Board .Conservation _Fiah and Game .Ooastal Ccranission _caltrans District _Galtrans - Planning _Caltrans - Aeronautics .California Highway patrol .Boating and Waterways .Forestry .State Water Resoruoes Control Board - Headquarters .Regional Water Quality Control Board, Region .Division of water Rights (SWRCB) .Division of Water Quality (SWRCB) .Department of Water Resources .Reclamation Board .Solid Waste Management Board Colorado River Board CTRPA (CalTOPA) TRPA (Tahoe RPA) Bay Conservation & Dev't Conn Parks and Recreation Office of Historic Preservation Native American Heritage Conn State Lands Ccnm Public Utilities Conn Energy Conn Food and Agriculture Health Services Statewide Health Planning (hospitals) Housing and Ccnoaunity Dev't Corrections General Services Office of Local Assistance Public Works Board Office of Appropriate Tech. (OPR) local Government Unit (OPR) Santa Monica Mountains Conservancy Other Date Received at SCH_ Date Review Starts__ Date to Agencies Date to SCH FOR SCH USE ONLK Catalog Nunfcer Proponent Clearance Date Notes: Consultant. Contact Address Phone • •-». Area added to LFMP-6 3.03 acres of RM- Residential Medium Designated JOS -^* Land Use GENERAL PLAN \\ m 09 ZONE 6 JANUARY 1BB7 LOCAL FACILITIES MANAGEMENT PLAN CITY OF CARLSBAD EXHIBIT "B" February 1, 1989 GROWTH MANAGEMENT PROGRAM LOCAL FACILITIES IMPACTS ASSESSMENT FORM (To be Submitted with Development Application) PROJECT IDENTITY AND IMPACT ASSESSMENT: FILE NAME AND NO.: Local Facilities Management Plan 6(A) LOCAL FACILITY MANAGEMENT ZONE: _fi GENERAL PLAN: RM ZONING: RP-Q (Proposed) DEVELOPER'S NAME: Von Per Ahe ADDRESS: PHONE NO.: N/A ASSESSOR'S PARCEL NO.: 215^050-60 QUANTITY OF LAND USE/DEVELOPMENT (AC., SQ. FT., DU): 3.03 ac/18 du ESTIMATED COMPLETION DATE: 1989 A. City Administrative Facilities; Demand in Square Footage * 66.7 sq. ft. B. Library; Demand in Square Footage = 35.6 sq. ft. C. Wastewater Treatment Capacity (Calculate with J. Sewer) D. Parks; Demand in Acreage = .13 ac E. Drainage; Demand in CFS = Identify Drainage Basin = Batiquitos (Identify master plan facilities on site plan) Lagoon F. Circulation; Demand in ADTs = 144 ' (Identify Trip Distribution on site plan) G. Fire; Served by Fire Station No. = 2 H. Open Space; Acreage Provided - N/A E = 4.86 I. Schools; - JH « 1.30 (Demands to be determined by staff) H = 2.79 J. Sewer; Demand in EDUs - 18 Identify Sub Basin - (Identify trunk line(s) impacted on site plan) K. Water; Demand in GPD - 3.960 LOCATION MAP t City of Carisbad VON DER AHE SOP 86-1KA) SUP 88-1 CUP/PCD/QPC 87-9 CUP 88-14 CUP 88-16 HDP 88-1 1 ZC 88-1 LFMP 8(A) LCPA BACKGROUND DATA SHEET CASE NO I SDP 86-TH f*i) APPLICANT: Carlsbad Retail Associates REQUEST AND LOCATION: A commercial/government center which includes 123.400 square feet of commercial/office uses, a 1.500 square foot movie theater, a 58.000 square foot Citv Library, and a 22.000 square foot Branch Post Office. LEGAL DESCRIPTION: Lot 1 of Carlsbad tract no. 82-23 in the citv of Carlsbad County of San Diego. Citv of California according to the map thereof number 11002 filed in the office of the County Recorder of said County and a parcel of land being a portion of record of survey n"P^r 99QQ. County of San Diecro. Citv of California filed in the office of the County Recorder of said County together with those portions of the half of the northeast corridor of seciton 26. township 12 south, 4 west. San Bernadino Meridian in the County of San Diego, city of California according to the official platt thereof. APNs 215-050-61. 63-64 Acr«s_2J Proposed No. of Lots/Units 4 lots GENERAL PLAN AND ZONING Land Use Designation C - Community/Commercial & RM Residential Medium Density Allowed N/A Density Proposed N/A Existing Zone C-2-Q, RD-M. L-C Proposed Zone C-2-Q & RP-0, RD-M Surrounding Zoning and Land Use: Zoning Land Use Site C-2-Q. RD-M & L-C Graded & undisturbed vacant land North L-C Undisturbed vacant land South RD-H Residential & Graded vacant land East C-l-Q Neigh, commercial center West L-C Undisturbed vacant land PUBLIC FACILITIES School District Carlsbad Water Carlsbad Sewer Carlsbad EDU's Public Facilities Fee Agreement, Date June 20. 1988 ENVIRONMENTAL IMPACT ASSESSMENT X Negative declaration, issued September 9. 1988 - SCH #88090722 E.I.R. Certified, dated Other, ' 1 DISCLOSURE FORM ' i APPLICANT: Carlsbad Retail Associates (Partnership) Name (individual, partnership, joint venture, corporation, syndication) • 1601 Dove Street, Suite 242, Newport Beach, CA 92660 Business Address " ~~ (714)752-6628 Telephone Number Name Business Address Telephone Number MEMBERS: Johnson Wax Development Corporation n/a Name (individual, partner, joint Home Address venture, corporation, syndication) 3150 Bristol street, Ste. 250, Costa Mesa, CA 92626 Business Address (714)556-7300 n/a Telephone Number Telephone Number 727 Promontory Drive West Fred T. Von der Ahe Newport Beach, CA 9266Q Name Home Address 1601 Dove Street, Ste. 242, Newport Beach, CA 92660 Business Address (714)752-6628 (714)673-6598 Telephone Number Telephone Number (Attach more sheets if necessary) The applicant: is required to apply for Coastal Commission Approval if located in the Coastal Zone. I/Vfe declare under penalty of perjury that the information contained in this disclosure is true and correct and that it will remain true and correct and may be relied upon as being true and correct until amended. See Attached APPLICANT BY Agent, Owner, Partner CARLSBAD RETAIL ASSOCIATES, a California Joint Venture By: JDCR Limited Partnership, a Wisconsin Limited Partnership By: Johnson Wax Development Corporation of California, its sole General Partnerx .x // /r •f^ftCf^iJ^ LX ' /tJC^jt/l By: //Eugene A< Spindler, Vice President By: F. T. Von der Ahe Company, a Sole Proprietorship CARLSBAD [CRASigPg] 08/13/87 cure or CARLSBAD MtKAGEMEKr PBOG8AM LDCftL MCHHIES IMEMZES ASSESSMENT FORM (To be Submitted with Development Application) PROJECT IDENTITY AMD IMPACT ASSESSMENT: FILE NAME AND NO.: LOCAL FACILITY MANAGEMENT ZCNE: 6 GENERAL PLAN: C.RM ZCNDC: C2-Q, RP-Q DEVELOPER'S MAKE: Carlsbad Retail Associates | __ c/o Johnson Wax Development Corporation ADDRESS: 3150 Bristol Street. Suite 250. Costa Mesa. California 92660 PHONE NO.: (714) 556-7300 ASSESSORS PARCEL NO. 215-050-60.61.63.64 &.65 QUANTITY OF IAND USE/DEVELOPMENT (AC., SQ. FT., DU)! 28.57 acres ESTIMATED CCHPLBTICN DATE: Retail - 1990; Library/Post Office - 1991 A. City Administrative Facilities; Denand in Square Footage - N/A B. Library; Demand in Square Footage - .N/A C. Wastewater Treatment Capacity (Calculate with J. Sewer) D. Parks; Denand in Acreage » .N/A . . E. Drainage; Demand in CFS » 119* Identify Drainage Basin » DG (Identify iv>stf>r plan facilities on site plan) F. Circulation; Denand in ADTs » 16.370** (Identify Trip Distrihution on site plan) G. Fire; Served by Fire Station No. - __2 H. Open Space; Acreage Provided - 4.9 ac. I. Schools; (Demands to be determined by staff) J. Sewer; Denand in EDUs - 130 Identify Sub Basin - 6A. 21B (Identify trunk line(s) impacted on site plan) K. Hater; Danand in GPD - 84.000 * - See Attached Sheet ** - See Attached Sheet * - See drainage study by Rick Engineering dated October 7, 1988; net zero increase in storm discharge due to construction of on-site detention basin. ** - See traffic study by Linscott, Law & Greenspan dated February 15, 1988; ADT does not account for overlap trips/mixed use. Project increase over currently approved land use is 3,000 ADT. Mitigation included to achieve GMP LOS standards. STATE OF CALIFORNIA—THE RESOURCES AGENCY GEORGE DEUKMEJIAN, Governor CALIFORNIA COASTAL COMMISSION SAN DIEGO COAST DISTRICT 1333 CAMINO DEI RIO SOUTH, SUITE 125 SAN DIEGO. CA 92108-3520 (619) 297-9740 AMENDMENT TO PERMIT Carlsbad Retail Assoc. c/o Johnson Wax Development Company 3150 Bristol Street, Suite 250 Costa Mesa, CA 92626-3038 Date: September 26. 1989 Permit Number 6-89-110 issued to Carlsbad Retail Associates has been amended to include the following change: Allow grading and site stabilization to occur from October 1. 1989 to November 15. 1989^. This amendment was determined by the Executive Director to be immaterial, was duly noticed, and no objections were received. This amendment will become effective upon return of a signed copy of this form 'to the District office. Please note that the remaining conditions are still in effect. Sincerely, Peter Douglas Executive Director I have read and understand the above amendment and agree to be bound by its conditions and the remaining conditions of permit number ^-ST Date Signature // (1863N) STATE OF CALIFORNIA—THE RESOURCES AGE> GFORGE DEUKMFJIAN. Governor CALIFORNIA COASTAL COMMISSION SAN DIEGO COAST DISTRICT COASIAl. DEVtl OPMIN1 PERM1! NO. 6-89-110 1333 CAWINO DEI RIO SOUTH. SUITE 125 PadC 1 Of fc " SAN DIEGO, CA 92108-3520 y (619) 297-9740 Phase I.- Grading and Commercial Development On July 11. 1989 , the California Coastal Commission granted to Carslbad Retail Associates. Johnson Wax Dev. Corp. this permit for the development described below, subject to the attached Standard and Special Conditions. Description: Construction of a 212,500 sq.ft. retail shopping center with 146,200 sq.ft. of retail space, a 58,000 sq.ft. library and a 22,000 sq.ft. post office on a vacant 28.5 acre site. Project requires 150,000 cubic yards of balanced cut and fill. Lot Area 28.5 acres Building Coverage 212,500 sq. ft. (17%) Pavement Coverage 730,500 sq. ft. (59%) Landscape Coverage 298,000 sq. ft. (24%) Parking Spaces 1,222 Zoning - C-2-Q, RP-Q, RO-M Plan Designation Commercial/Residential (6 dua) Ht abv fin grade 45 feet Site: Northwest corner of El Camino Real and Alga Road, Carlsbad, San Diego County. APN 215-050-65, 64, 63, 61 and a portion of 60 Issued on behalf of the California Coastal Commission by PETER DOUGLAS Executive Director and IMPORTANT: THIS PERMIT IS NOT VALID UNLESS AND UNTIL A COPY OF THE PERMIT WITH THE SIGNED ACKNOWLEDGEMENT HAS BEEN RETURNED TO THE COMMISSION OFFICE. ACKNOWLEDGEMENT The undersigned permittee acknowledges receipt of this permit and agrees to abide by all terms and conditions thereof. Date bignatu/e of Permittee COASIAL DLVELOPMKN1 p-~MU NO. 6-89-110 Page 2 of b STANDARD CONDITIONS: 1. Notice of Receipt and Acknowledgement. The permit is not valid and development shall not commence until a copy of the permit, signed by the permittee or authorized agent, acknowledging receipt of the permit and acceptance of the terms and conditions, is returned to the Commission office. 2. Expiration. If development has not commenced, the permit will expire two years from the date on which the Commission voted on the application. Development shall be pursued in a diligent manner and completed in a reasonable period of time. Application for extension of the permit must be made prior to the expiration date. 3. Compliance. All development must occur in strict compliance with the proposal as set forth below. Any deviation from the approved plans must be reviewed and approved by the staff and may require Commission approval. 4. Interpretation. Any questions of intent or interpretation of any condition will be resolved by the Executive Director or the Commission. 5. Inspections. The Commission staff shall be allowed to inspect the site and the development during construction, subject to 24-hour advance notice. 6. Assignment. The permit may be assigned to any qualified person, provided assignee files with the Commission an affidavit accepting all terms and conditions of the permit. 7. Terms and Conditions Run with the Land. These terms and conditions shall be perpetual, and it is the intention of the Commission and the permittee to bind all future owners and possessors of the subject property to the terms and conditions. SPECIAL CONDITIONS: The permit is subject to the following conditions: 1. Phasing. The coastal development permit may be transmitted in three phases permitting portions of the development to occur prior to City and Executive Director review of building plans for the post office and library. A. Phase 1 - Grading and Commercial Development. Prior to issuance of the coastal development permit for all proposed improvements except for the construction of the post office and library, the applicant shall comply with all of the Special Condition Nos. 2 through 9 below. COAS'IAL OEVhLOPMtNl ? Mil NO. b-89-110 Page 3 of 6 SPECIAL CONDITIONS, continued: B. Phase 2 - Library Construction. Prior to issuance of the permit for the Library, the applicant shall submit to the Executive Director for review and written approval, the City-approved final buildings for the library. These plans shall be in substantial conformance with the conceptual plans provided with this application. C. Phase 3 - Post Office. Prior to issuance of the permit for the construction of the post office, the applicant shall submit to the Executive Director for review and written approval, the City-approved final building plans for the post office. These plans shall be in substantial conformance with the conceptual plans provided with this application. 2. Open Space/Steep Slope Preservation. Prior to the issuance of a coastal development permit, the applicant shall identify an open space area to be secured as permanent open space on the Westana Viewpoint subdivision (Carlsbad Tract No. 85-34) adjacent to the west. The secured open space shall be subject to the Executive Director's review and approval in consultation with the Department of Fish and Game and shall meet the following criteria: A) Preservation of a minimum 21,780 sq.ft. of steep slopes naturally vegetated with coastal sage scrub and chaparral on or contiguous with the open space area approved pursuant to Coastal Development Permit Nos. 6-89-146 and 6-89-171. This requirement is to provide for retention of an equivalent amount of steep slope habitat in open space as that which is permitted to be disturbed, pursuant to the submitted site plan attached as Exhibit 2 and dated December 7, 1988. B) Preservation of an additional 1.5 acres of open space on or contiguous with the open space approved pursuant to Coastal Development Permit No. 6-89-146 and 6-89-171. The open space may include non-steep areas containing oak woodland, coastal sage scrub and chaparral vegetation or steep areas with vegetation which is disturbed or of limited quality to be enhanced pursuant to Special Condition No. 4 of this coastal development permit. C) The secured open space shall be shown on scaled topographic maps and subject to the review and written approval of the Executive Director in consultation with the Department of Fish and Game. D) The approved open space area shall be permanently.protected through an offer to dedicate an open space easement, pursuant to Special Condition No. 3 below. COASTAL UtVfcl.OPMLNI P 111 NO. b-89-110 Page 4 of 6 SPECIAL CQNDTIONS. continued: 3. Offer to Dedicate Open Space Easement. Prior to the issuance of a coastal development permit, the applicant shall submit evidence that an irrevocable offer to dedicate to a public agency, or to a private association acceptable to the Executive Director, an open space easement over the area shown on the attached Exhibit "3" and generally described as the open space area proposed under Coastal Development Permit Application No. 6-89-171, has been recorded. The recorded document shall include legal descriptions of both Westana Viewpoint's entire parcel(s) and the easement area. The offer shall be irrevocable for a period of 21 years, shall run in favor of the People of the State of California, binding successors and assigns of the applicant and/or landowners, and shall be recorded prior to all other liens and encumbrances, except tax liens. The offer to dedicate shall be in a form and content acceptable to the Executive Director. 4. Steep Slope Restoration. Pursuant to Special Condition No. 2.B) above, prior to the issuance of the coastal development permit, the applicant shall submit a restoration plan for the review and approval of the Executive Director in consultation with the Department of Fish and Game, to restore any habitat areas with vegetation that is currently disturbed or of limited quality coastal sage scrub and chaparral habitat. The restoration plan shall indicate the type and size of plants to be used, method of planting, irrigation necessary, and a continuing maintenance program to assure success of the restoration plan. Restoration of the steep slopes shall be completed prior to October 15 or within 30 days of the completion of grading for the project site, whichever occurs first. The applicant shall conduct a post project visit and submit an assessment of the conditions of the enhanced habitat area on or before October 15 of the second year following the installation of planting. At that time, the Commission staff in consultation with the Department of Fish and Game, shall concur that 90% coverage has been achieved, or if 90% coverage has not been achieved within the specified time frame, the applicant shall plant additional vegetation to achieve 90% coverage on or before March 1 of the subsequent year. The applicant shall conduct a post-project assessment of the mitigation project in the month of October on an annual basis for five years following the achievement of 90% coverage. If at any time 90% coverage is not provided, the applicant shall revegatate the area to achieve 90% coverage within 90 days of the site visit. 5. Erosion. Sedimentation and Drainage Control. Prior to the issuance of the coastal development permit, the applicant shall submit for the review and written approval of the Executive Director an erosion, sedimentation and drainage control plan for the project, approved by the City of Carlsbad, including associated roads and utilities. The plan shall be prepared and reviewed in accordance with the 1980 Master Drainage Plan for the City of Carlsbad, including the Model Erosion Control Ordinance contained in the plan. The erosion, sedimentation and drainage plans shall include: COASIAL DLVLLOPMKN1 ' 'Mil NO. 6-89-110 Page b of 6 SPECIAL CONDITIONS, continued: A) A runoff control plan designed by a licensed engineer qualified in hydrology and hydraulics, which would assure no increase in peak runoff rate from the developed site over the greatest discharge expected from the existing undeveloped site as a result of a 10-year, 6-hour frequency storm. Runoff control shall be accomplished by a variety of measures, including but not limited to: on-site catchment basins, detention basins, siltation traps and energy dissipators. B) Detailed maintenance arrangements and various alternatives for providing the on-going repair and maintenance of any approved drainage and erosion control facilities. If the off-site or on-site improvements are not to be accepted or maintained by a public agency, detailed maintenance agreements binding the applicants and their successors in interest shall be secured prior to the transmittal of the permit. Such agreements shall be subject to the review and written approval of the Executive Director. 6. Grading Activities. Prior to the issuance of a coastal development permit, the applicant shall submit final grading plans which incorporate the following: A.) All permanent runoff and erosion control devices shall be developed and installed prior to or concurrent with any on-site grading activities. B.) All grading activities, including that required for streets and utilities, shall be prohibited within the period from October 1st to March 31st of each year. C.) All areas disturbed by grading, by not completed during the construction period, shall be planted and stabilized prior to October 1st with temporary or permanent (in the case of finished slopes) erosion control measures and landscaping. The use of temporary erosion control measures, such as berms, interceptor ditches, sandbagging, filtered inlets, debris basins and silt traps, shall be utilized in conjunction with plantings to minimize soil loss from the construction site. 7. Landscaping. Prior to the issuance of the coastal development permit, the applicant shall submit a detailed landscaping plan indicating the type, size, extent and location of plants and hydroseeding material, irrigation systems and other landscape features for the proposed project. The plans shall be subject to the review and written approval of the Executive Director. Drought tolerant plant materials and native vegetation shall be utilized to the maximum extent feasible. The plant species list and landscape plan shall be reviewed by the Executive Director, in consultation with the State Department of Fish and Game, to guard against introduction of any species which are inherently noxious to, or incompatible with, the adjacent native vegetation. COASIAL OhVhl.OPMfcNl "~'Wll NO. b-89 -110 Page b of _6_ SPECIAL CONDITIONS, continued: Landscaping shall include the use of specimen-sized trees to provide a landscape screen to buffer development from views from El Camino Real. The landscape plan shall also include the use of a native vegetation to the maximum extent feasible along the western limits of grading and the provision of riparian and wetland species within and around the detention basin in the north east corner of the project site in order to provide a naturalized habitat ,in these areas. 8. Archaeology/Paleontology. A limited testing program followed by a program of implemental preservation and/or impact mitigation for sites identified in the Negative Declaration for the the project shall be completed as recommended in the Negative Declaration and required by the City of Carlsbad. Any change in this requirement shall be reported to and subject to the written approval of the the Executive Director. 9. Signage. Prior to the issuance of the coastal development permit, the applicant shall submit a comprehensive sign program for Phase 1 of the project. The sign program shall prohibit the erection or placement of tall freestanding (other than eight-foot-high monument) or roof signs and shall prohibit any off site signs. The sign program shall be subject to the review and written approval of the Executive Director. Any additional signage for the library or post office shall be submitted prior to issuance of the permits for Phase 2 and 3 of the project. (9110P) ST\TE OF CALIFORNIA—THE RESOURCES AGEK GEORGE OEUKMEJIAN. Governor CALIFORNIA COASTAL COMMISSION SAN DIEGO COAST DISTRICT 1333 CAMINO DEI RIO SOUTH, SUITE 125 SAN DI^GO. CA 92108-3520 (619) 297-9740 NOTICE OF COMMENCEMENT OF CONSTRUCTION I/We hereby notify the CALIFORNIA COASTAL COMMISSION that I/We began the development authorized by Permit Number o •"?> - ''*-' on «£y/- '7 /7ffi and that the development will be Date Construction Began completed in accordance with any conditions imposed in the permit. C/, Signature of Applicant or Representative Date 2075 LAS PALMAS DRIVE CARLSBAD, CALIFORNIA 92009-4859 PLANNING DEPARTMENT WWWJrM (619)438-1161 City of CarlSiab NOTICE OF DETERMINATION County Clerk Date: November 13, 1987 County of San Diego Attn: Mail Drop C-ll 220 West Broadway San Diego, CA 92101 This is to advise that the City of Carlsbad on November 10. 1987. approved the following project: Project Title: Local Facilities Management Plan for Zone 6 Project Address/Location: The developed portions of the La Costa area. Generally described as; 1. The developed areas east and west of El Camino Real from Camino Vida Roble to Olivenhain Road; and 2. The developed areas north of Alga Road between El Camino Real and Melrose Avenue; and 3. The undeveloped area east of Melrose and north of Rancho Santa Fe Road; and 4. The area south of Alga Road betwen El Camino Real and Rancho Santa Fe Road to Levante; and 5. The developed area south of Levante. Project Description: The project provides for a detailed plan for the provision of public facilities to meet adopted perform- ance standards, based on the City of Carlsbad's General Plan. This is to advise that the City of Carlsbad has approved the above described project and has made the following determinations regarding the above described project: 1. The project will not have a significant effect on the environment. 1987 Notice of Determination Page Two 2. Mitigation measures were not made a condition of the approval of this project. 3. A statement of Overriding Considerations was not adopted for this project. MICHAEL J. HOLZMIDEER Planning Director MJH:LBS/af •| FILED IIT THE OFFICE OF THE COUNTY CLERK, NOVKA¥ 2ISGO CGUMTY OS"^ un\i 4 n ind s li.ffi^OB,BED TO DEPUTY