City of Carlsbad
February 24,2003
Kentoo, LLC
Ken Satterlee
4510 Executive Drive, Plaza 5
San Diego CA 92121
SUBJECT: PIP 02-05 - CANYON RIDGE BUSINESS PARK
Thank you for applying for Land Use Permits in the City of Carlsbad. The Planning Department
has reviewed your, application no. 02-05, as to its completeness for processing.
The items requested from you earlier to make your Planned Industrial Permit, application no.
02-05 complete have been received and reviewed by the Planning Department. It has been
determined that the application is now complete for processing. Although the initial processing
of your application may have already begun, the technical acceptance date is acknowledged by
the date of this communication.
Please note that although the application is now considered complete, there may be issues that
could be discovered during project review and/or environmental review. Please find attached a
list of issues that must be addressed. Any issues should be resolved prior to scheduling the
project for public hearing. In addition, the City may request, in the course of processing the
application, that you clarify, amplify, correct, or otherwise, supplement the basic information
required for the application.
Please contact your staff planner, Van Lynch, at (760) 602-4613, or David Rick, staff engineer
at (760) 602-2781if you have any questions or wish to set up a meeting to discuss the
application.
Sincerely,
MICHAEL J. HOBMILLER
Planning Director
MJH:VL:mh
C: Chris DeCerbo
David Rick
File Copy
Data Entry
Planning Aide
1635 Faraday Avenue Carlsbad, CA 92008-7314 (760) 602-4600 FAX (760) 602-8559 www.ci.carlsbad.ca.us @
NO. PIP 02-05
ISSUES OF CONCERN
Planning:
1. Please provide the wall heights (TW/BW) of the screen walls proposed adjacent to
Buildings A and D.
2. Please revise the extent of the stripping for the service aisles where the driveway width
(24 feet) interferes with the service aisle. (At the north and south ends of Bldg B and the
north end of Bldg C) The project will be conditioned to strip the shared service area
(loading) and the extents should be shown correctly on the plan.
Engineering:
1. The letter from Geocon Incorporated addressing the required distance between the
building foundation and drainage swale indicates that there must be a horizontal distance
of 7 feet yet only 3 feet is provided. Please revise plans accordingly. In addition, the letter
should specify whether the drainage swale is an earth drainage swale or a concrete brow
ditch.
2. On the grading plan, add a note next to the notes to the Type ‘F’ .Catch Basin Inlets stating
that Flo-Guard or equivalent filters will be installed. In addition, provide a detail showing
the filter’s configuration inside the catch basin. It appears that the filters will interfere with
the first step on the inlet. The depth of the existing drain is approximately 12 feet and this
catch basin must be equipped with steps since the catch basin is deeper than 4 feet. In
addition, the depth of the pipe according to the improvement plans on file at the City is
approximately 12 feet, not 9 feet as shown. Please correct.
3. Locate the concrete brow ditches within the parking lot at the end of the stalls against the
curb. In addition, the ditch located near the west property line appears to terminate at the
curb and there is no mentioning of an opening at the curb. How will water drain at this
location?